 TALL STRUCTURE
– Definition
– Needs of tall structure
– Types of tall structure
– Factor affecting tall structure
– Design consideration of tall structure
– Structural frame system
 URBAN SPATIAL STRUCTURE
– How do we measure USS?
 PRESTRESSED STRUCTURE
– Prestressing effect on beam
– Accessories require for pre-stressing
– Advantages & disadvantages
Definition :
A structure or a building having
height more than 80 m is known
as tall structure.
Tall structure are also known as a
skyscraper.
From structural Engineer’s point
of view, a tall building may be
defined as one that, because of
its height it is affected by lateral
forces such as wind force,
earthquake forces.
BURJ KHALIFA SKYSCRAPER
The rapid growth of the urban population and the pressure on
limited space have influenced the development of tall
structures.
Tall structure makes distinctive land marks and tall commercial
buildings are developing in city centers as prestige symbols for
corporate organizations.
The business and tourist community with its increasing
mobility has considered the preferable need for more high rise
and city Centre hotel accommodation.
Tall commercial structures are mainly a response to the
demand by business activity to be as close to each other,
especially to the city center areas as possible.
Multistorey
residential building
Multistorey commercial
building
Multistorey mix purpose
building
Cooling tower
High rise elevated
service reservoirTall chimney
1) Availability of construction materials, equipment (mobile cranes,
pumps for concrete)
2) Advancement in new construction technologies
3) Research and development of light weight concrete and light
weight framework
4) Development of skeleton structure
5) Advancement in analysis and design of tall structure
6) Availability of advance design software
7) Development of earthquake resistant structural design
8) Energy dissipation base isolation techniques
9) Increased speed of erection
10) Slip form technique and flying formwork
11) Light partitions, glass curtain walls etc.
1) Loading
2) Floor system
3) Strength and stiffness
4) Storey drift
5) Creep, shrinkage and temperature effects
6) Foundation settlement and soil-structure interation
7) Other important services like ventilation, electric
power supply, air conditioning, heating, water supply
system, waste disposal, vertical transportation (lifts)
etc.
1) Loading :
 The principal loads considered in the design of tall structures are :
• Gravity loads
• Dead loads
• Wind loads
• Earthquake loads
 These forces depends on :
• Size and shape of the building
• Geographical location of building
Dead load Earthquake load
Gravity load Wind load
2) Floor system :
 (a) For R.C.C. structures :
• One way slab on beams & joints
• Two way slab on beams & joints
• Two way flat slab
• Waffle flat slab
 (b) For steel structures :
• One way beam system
• Two way beam system
• Composite steel concrete floor system
3) Storey drift :
The drift in a storey is computed as a difference of deflections of
the floors at the top and bottom of the storey.
When building is subjected to earthquake forces, the floor are
deflected laterally.
The total drift in storey is the sum of shear deformations of that
storey, axial deformation of floor, axial deformation of column and
foundation rotation.
Total drift = S.D + A.D of floor + A.D of column + F.R
Due to the minimum specified design lateral force, the storey drift
in any storey with a partial load factor of 1.0, should not exceed
0.004 times the storey height.
Partial load factor < 0.004 (storey height)
LIMITATION DURING EARTHQUAKE :
To provide human comfort
To limit damage to non-structural elements
To preserve vertical stability of a structural system
To limit the effect of eccentric gravity load
To minimize damage due to pounding
4) Strength and stiffness :
The structure should have proper strength in lateral as well as in
vertical direction. The structure should not collapse even under a
worst combination of loads.
Stiffness is the property of a structure to resist deformation.
Lateral stiffness is the major consideration in the design of tall
structures.
The stiffness of joints particularly in the design of precast or
prefabricated structure, should be given special attention to
develop lateral stiffness of the structure and to avoid progressive
failure.
A brittle structure having more stiffness, proves to be less durable
during earthquake, while a ductile structure performs well in
earthquake.
5) Creep, Shrinkage and temperature effect :
The vertical deformation due to creep and shrinkage may cause
distress in non-structural elements like flooring, cladding,
partition etc.
Temperature difference between the exterior and interior
columns, induces stresses in the structural elements.
6) Foundation settlement and soil-structure interation :
In tall structures gravity forces and lateral forces (earthquake
force, wind force) are very large . So, the foundation should be
capable of transmitting these loads to the under ground strata
without exceeding permissible settlement.
For tall structure deep foundation ( pile foundation, deep caisson
) are provided.
Earthquake causes shaking of ground in all three
direction along the two horizontal directions ( X
and Y ) and vertical direction (Z).
There are main four structural systems to resist
lateral loads :
(a)Load bearing wall system
(b)Moment resisting frame system
(c)Dual system ( frame + shear wall/bracing )
(d)Tube systems
(a) Load bearing wall system :
• Suitable for low rise building
• Very weak in resisting lateral loads
• Seldom recommended for multi storey building
(b) Moment resisting frame system :
• The ability of multistorey building to resist the lateral
forces depends on the rigidity of joints between the
beams and columns.
• When this joints are fully rigid, the structure is capable
of resisting the lateral loads. The frame is called
moment resisting frame.
• Strength and stiffness are not sufficient
• M.R.F. may be strengthened by incorporating the following
structural components such type of system is known as dual
system.
1. Load bearing shear wall
2. Shear wall with column
3. Infilled shear walls
4. Bracing
5. Diaphragms
1. Load bearing shear wall :
• Useful in preventing the failure of non structural component
• May be of RCC, steel, composite and masonry
• Thickness :150 mm , height :400 mm
(c) Dual system :
2. Shear wall with column :
• Provided along both length and width of building
• Vertically oriented wide beams that can carry earthquake loads
from diaphragms and transmit them to the ground
3. Bracing :
• It may be offer lower resistance depending on their design and
construction
• Section may be steel rolled, circular bar or tube
• Vibration may cause the bracing to elongated or compress
• Ductility is very important in designing the bracing
4. Diaphrams :
• Horizontal resisting elements like floors, roofs
• Transfer the lateral forces between vertical resisting elements
• Acts as the web of beam and edges as flanges
Pure frame Load bearing shear
walls
Shear wall with
column
Infilled shear wall Braced frame Whole building
braced
• Building taller than about 40 storey the lateral
force becomes very intense. In this case tube
system is more economical.
• Classification of tube system
1. Framed tube
2. Trussed tube
3. Tube in tube
4. Bundled tube
(d) Tube system :
1. Framed tube system
• closely spaced columns
• tied at each floor level by deep spandrel beams
2. Trussed tube system
• The diagonal members along with grinder and columns, form a
truss system that imparts a great deal of stiffness to the building.
3. Tube in tube
• Consist of an exterior tube that resist the bending moment due to
lateral forces and an interior slender tube, which resist the shear
produced by the lateral forces.
4. Bundled tube
• Made up of a number of tubes separated by shear walls
• The tubes rise to various heights
• Each tube is designed independently
FRAME TUBE TRUSSED TUBE BUNDLED TUBE
Interior tube
Exterior tube
TUBE IN TUBE
 Construction:21 Sept 2004-4 Jan2010
 Design: Adrian Smith and his team
 Place: Chicago office of SOM
(skidmore,owings and Merrill)
 Height: 828 m
 NOS of floors: 160+
 Area of tower: 280,000 sq m
 Total Cost: 4.2 Billion Dollars
 22 million man hours to construct
 Concrete used: 250000 cu.m
 Steel rebars: 39,000 tonnes
 Curtain walls: 83,600 sq.m glass
27900 sq.m of metal
 Status: on hold
 Type: Hotel, residential retail
 Location: Marin line,
Mumbai
 Coordinates: 18.950159˚N
72.821348˚E
 Construction: started 2010
 Estimated completion: 2010
 Height: 700 m
 NOS of floors: 126
 Design and construction:
Architect Foster and Partners
 Opened : 2010
 Height: 210 m
 Floor: 60
 Address: Mumbai
 Architect: Hafeez
construction
IMPERICAL TOWER
PLANET GODREJ
City: Mumbai
Year: 2010
Height: 181 m
Floor: 51
RNA MirajMVRDCOrchid Enclave
NO. NAME CITY HEIGHT (m) FLOORS YEAR
1. Imperial tower Mumbai 249 60 2010
2. Lodha Bellissimo Mumbai 197 48 Under const.
3. Planet Godrej Mumbai 181 51 2009
4. Ashok Tower I Mumbai 193 49 2009
5. RNA Mirage Mumbai 180 40 2009
6. Oberoi woods tower Mumbai 170 40 2009
7. MVRDC Mumbai 156 35 2009
8. Shreepati acard Mumbai 153 45 2002
9. Vasant polaris Mumbai 151 34 2009
10. Belvedere court Mumbai 149.35 40 2008
A cluster of concepts concerned with
“the arrangement of urban public
space.”
Two types of patterns :
I. Spatial pattern of population
distribution within built up area
II. Pattern of population movement
around the city during the day
SPATIAL REPRESENTATION OF POPULATION
We can define USS using no. of indicators
3 main indicators :
1) Land consumption (density)
2) Density profile
3) Degree of monocentricity (share of trips
with central destination)
BUILT-UP DENSITIES AROUND THE WORLD
1) Land consumption per person :
• Higher the density the lower the consumption of
land per person
• Density = city population / built up area
2) Pattern of daily trips within built-up area :
I. Monocentric model (exist only in master plans)
II. Polycentric model (common in North American
Cities
III. Mixed mono-polycentric model (more common)
Urban planner should analyse and monitor
the evolution of the city
Planner should identify the type of urban
structure which is compatible with
municipal strategy
Definition: The application of
predetermined force or a moment to
structural member in such a manner
that the resulting stresses due to this
force or moment and external loading
will be confined within specified limits
I. Pre-tensioning
II. Post-tensioning
(a) Pre-tensioning :
• Steel tendons are placed in position in the framework
• Predetermined tensile force P is applied to the tendons are kept in
stretched condition
• Concrete is now placed in formwork and allowed to cure to gets its
design strength
• Tendon become bounded to concrete throughout their length
• The tendon tend to regain their original length by shortening
• Method is useful for small elements like railway sleepers, electric
poles, pipes etc.
Jack
Abutment
Tendon
Beam or block
Prestressing bed
Jack
2) Post-tensioning:
• Concrete is cast while there is no stress in the tendon
• When concrete is hardened, the tendons are stretched through
hydraulic member through hydraulic jacks bearing against the
concrete
• The tendon force is transferred to the member through wedges or
blocks at the end of the member
• The flexible hose or rubber tube may be used to house the tendons
so that bond is not developed between the wires and concrete
• After the tendon has been stressed, the void space between the
tendon and hose is filled with grout
• The tendon becomes bounded to concrete and corrosion of steel is
prevented
Hollow duct for tendon
Anchor plate
Jacking deviceBeam
• As the entire prestressed concrete section is in compression, it is
free from tensile cracks
• It eliminates corrosion of steel when structure is expose to
weather
• Pre-stressed concrete section are much smaller than those in
reinforced concrete cement structure, because dead load
moments are neutralised by prestressing moments and shear
stresses are also reduced
• In prestressed concrete, entire section is utilised for resisting loads.
This will reduce the size of members and dead weight of the
structure.
• As the self weight of the structure reduces, the foundation cost will
also reduce
• Under service loads, deflection of member will be less
• It has high live load carrying capacity
• It requires high strength concrete (minimum
M-30) and high strength steel
• It requires end anchors and bearing plates
• It requires better quality control
• It requires complicated formwork
• Labour cost may be higher
1. Discuss important points to be considered while constructing tall
structure.
2. Discuss important points to be considered while constructing spatial
structure
3. What is tall structure? What is need of tall structure?
4. List names of any 5 tall structure in India
5. List names of any 5 tall structure in world
6. Enumerate the factor affecting growth, height and structure form of tall
structure
7. Explain various design consideration of tall structure
8. Explain with sketches various structural framing system used for tall
structure
9. What are urban spatial structure?
10. Write short note on ‘urban densities’.
11. What is pre-stressing? Explain concept of pre-stressing.
12. Give advantages and disadvantages of pre-stressing.
13. Explain equipment and accessorises used in pre-stressing.
ACE special structures

More Related Content

What's hot

What's hot (20)

slab concrete
slab concreteslab concrete
slab concrete
 
Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed Concrete
 
Connections in steel structures
Connections in steel structuresConnections in steel structures
Connections in steel structures
 
PreCast Construction
PreCast ConstructionPreCast Construction
PreCast Construction
 
Pre stressed concrete construction
Pre stressed concrete constructionPre stressed concrete construction
Pre stressed concrete construction
 
Structural steel
Structural steelStructural steel
Structural steel
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated Column
 
TALL BUILDINGS
TALL BUILDINGSTALL BUILDINGS
TALL BUILDINGS
 
Steel & Construction
Steel & ConstructionSteel & Construction
Steel & Construction
 
Shear wall
Shear wallShear wall
Shear wall
 
Base isolation
Base isolationBase isolation
Base isolation
 
Pre-stressing
Pre-stressing  Pre-stressing
Pre-stressing
 
High rise buildings
High rise buildingsHigh rise buildings
High rise buildings
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
 
Mat foundation
Mat foundationMat foundation
Mat foundation
 
Foundation & Footings
Foundation & FootingsFoundation & Footings
Foundation & Footings
 
Temporary structures
Temporary structuresTemporary structures
Temporary structures
 
Retaining walls
Retaining wallsRetaining walls
Retaining walls
 
RCC Elements column, beam.
RCC Elements  column, beam.RCC Elements  column, beam.
RCC Elements column, beam.
 
Prefabrication in construction
Prefabrication in constructionPrefabrication in construction
Prefabrication in construction
 

Similar to ACE special structures

loadanalysisandstructuralconsideration-190126210125-1.pdf
loadanalysisandstructuralconsideration-190126210125-1.pdfloadanalysisandstructuralconsideration-190126210125-1.pdf
loadanalysisandstructuralconsideration-190126210125-1.pdf
nileshsurti
 
Finalppthighrise 130504010636-phpapp02
Finalppthighrise 130504010636-phpapp02Finalppthighrise 130504010636-phpapp02
Finalppthighrise 130504010636-phpapp02
satwik345
 

Similar to ACE special structures (20)

loadanalysisandstructuralconsideration-190126210125-1.pdf
loadanalysisandstructuralconsideration-190126210125-1.pdfloadanalysisandstructuralconsideration-190126210125-1.pdf
loadanalysisandstructuralconsideration-190126210125-1.pdf
 
Load analysis and structural consideration
Load analysis and structural considerationLoad analysis and structural consideration
Load analysis and structural consideration
 
Load analysis and structural consideration
Load analysis and structural considerationLoad analysis and structural consideration
Load analysis and structural consideration
 
Design highrise
Design highriseDesign highrise
Design highrise
 
Type of high rise building
Type of high rise buildingType of high rise building
Type of high rise building
 
Structural systems in high rise building and analysis methods
Structural systems in high rise building and analysis methodsStructural systems in high rise building and analysis methods
Structural systems in high rise building and analysis methods
 
Highrise lecture
Highrise lectureHighrise lecture
Highrise lecture
 
High rise building construction
High rise building constructionHigh rise building construction
High rise building construction
 
high rise building construction
high rise building constructionhigh rise building construction
high rise building construction
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise Buildings
 
Technology materials of tall buildings highrise
Technology materials of tall buildings highriseTechnology materials of tall buildings highrise
Technology materials of tall buildings highrise
 
High rise building design
High rise building design High rise building design
High rise building design
 
Final presentation by Akramul masum from southeast university bangladesh.
Final presentation by Akramul masum from southeast university bangladesh.Final presentation by Akramul masum from southeast university bangladesh.
Final presentation by Akramul masum from southeast university bangladesh.
 
High Rise Structures.pptx
High Rise Structures.pptxHigh Rise Structures.pptx
High Rise Structures.pptx
 
structure, technology and materials of highrise buildings
structure, technology and materials of highrise buildingsstructure, technology and materials of highrise buildings
structure, technology and materials of highrise buildings
 
Lecture 8 THigh Rise structures.pdf
Lecture 8 THigh Rise structures.pdfLecture 8 THigh Rise structures.pdf
Lecture 8 THigh Rise structures.pdf
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systems
 
Finalppthighrise 130504010636-phpapp02
Finalppthighrise 130504010636-phpapp02Finalppthighrise 130504010636-phpapp02
Finalppthighrise 130504010636-phpapp02
 
high rise building
high rise buildinghigh rise building
high rise building
 
Tall buildings
Tall buildingsTall buildings
Tall buildings
 

More from Shree Swami atmanand saraswati inst. of technology, surat

More from Shree Swami atmanand saraswati inst. of technology, surat (20)

INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart citiesINFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
 
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systemsINFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
 
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
 
BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)
 
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
 
MODULE 2 PROJECT ORGANIZATION (updated)
MODULE 2 PROJECT ORGANIZATION (updated)MODULE 2 PROJECT ORGANIZATION (updated)
MODULE 2 PROJECT ORGANIZATION (updated)
 
BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)
 
BCT - Module 5 special work
BCT - Module 5 special workBCT - Module 5 special work
BCT - Module 5 special work
 
Module :- 8 Job layout (PART 2)
Module :- 8 Job layout (PART 2)Module :- 8 Job layout (PART 2)
Module :- 8 Job layout (PART 2)
 
Module :- 8 material management
Module :- 8 material managementModule :- 8 material management
Module :- 8 material management
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
Mod 3 construction economics
Mod 3 construction economicsMod 3 construction economics
Mod 3 construction economics
 
MODULE 2 project organization
MODULE 2 project organizationMODULE 2 project organization
MODULE 2 project organization
 
MODULE 1 Introduction to Construction Management
MODULE 1 Introduction to Construction ManagementMODULE 1 Introduction to Construction Management
MODULE 1 Introduction to Construction Management
 
Che 10 engineering fundamental
Che  10 engineering fundamentalChe  10 engineering fundamental
Che 10 engineering fundamental
 
Chapter 9 introduction to construction equipments
Chapter  9 introduction to construction equipmentsChapter  9 introduction to construction equipments
Chapter 9 introduction to construction equipments
 
CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)
 
Che 1 pile foundation
Che 1 pile foundationChe 1 pile foundation
Che 1 pile foundation
 
Ch 5 b remote sensing
Ch 5 b remote sensingCh 5 b remote sensing
Ch 5 b remote sensing
 
Ch 5 a gps
Ch 5 a gpsCh 5 a gps
Ch 5 a gps
 

Recently uploaded

Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
EADTU
 
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lessonQUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
httgc7rh9c
 

Recently uploaded (20)

Our Environment Class 10 Science Notes pdf
Our Environment Class 10 Science Notes pdfOur Environment Class 10 Science Notes pdf
Our Environment Class 10 Science Notes pdf
 
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lessonQUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
 
Details on CBSE Compartment Exam.pptx1111
Details on CBSE Compartment Exam.pptx1111Details on CBSE Compartment Exam.pptx1111
Details on CBSE Compartment Exam.pptx1111
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptx
 
dusjagr & nano talk on open tools for agriculture research and learning
dusjagr & nano talk on open tools for agriculture research and learningdusjagr & nano talk on open tools for agriculture research and learning
dusjagr & nano talk on open tools for agriculture research and learning
 
Play hard learn harder: The Serious Business of Play
Play hard learn harder:  The Serious Business of PlayPlay hard learn harder:  The Serious Business of Play
Play hard learn harder: The Serious Business of Play
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 
Tatlong Kwento ni Lola basyang-1.pdf arts
Tatlong Kwento ni Lola basyang-1.pdf artsTatlong Kwento ni Lola basyang-1.pdf arts
Tatlong Kwento ni Lola basyang-1.pdf arts
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
 
Introduction to TechSoup’s Digital Marketing Services and Use Cases
Introduction to TechSoup’s Digital Marketing  Services and Use CasesIntroduction to TechSoup’s Digital Marketing  Services and Use Cases
Introduction to TechSoup’s Digital Marketing Services and Use Cases
 
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdfFICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
 

ACE special structures

  • 1. SPECIAL STRUCTURES Presented by Karm P Balar Asst. professor SSASIT, SURAT
  • 2.  TALL STRUCTURE – Definition – Needs of tall structure – Types of tall structure – Factor affecting tall structure – Design consideration of tall structure – Structural frame system  URBAN SPATIAL STRUCTURE – How do we measure USS?  PRESTRESSED STRUCTURE – Prestressing effect on beam – Accessories require for pre-stressing – Advantages & disadvantages
  • 3. Definition : A structure or a building having height more than 80 m is known as tall structure. Tall structure are also known as a skyscraper. From structural Engineer’s point of view, a tall building may be defined as one that, because of its height it is affected by lateral forces such as wind force, earthquake forces. BURJ KHALIFA SKYSCRAPER
  • 4. The rapid growth of the urban population and the pressure on limited space have influenced the development of tall structures. Tall structure makes distinctive land marks and tall commercial buildings are developing in city centers as prestige symbols for corporate organizations. The business and tourist community with its increasing mobility has considered the preferable need for more high rise and city Centre hotel accommodation. Tall commercial structures are mainly a response to the demand by business activity to be as close to each other, especially to the city center areas as possible.
  • 5.
  • 8. Cooling tower High rise elevated service reservoirTall chimney
  • 9. 1) Availability of construction materials, equipment (mobile cranes, pumps for concrete) 2) Advancement in new construction technologies 3) Research and development of light weight concrete and light weight framework 4) Development of skeleton structure 5) Advancement in analysis and design of tall structure 6) Availability of advance design software 7) Development of earthquake resistant structural design 8) Energy dissipation base isolation techniques 9) Increased speed of erection 10) Slip form technique and flying formwork 11) Light partitions, glass curtain walls etc.
  • 10. 1) Loading 2) Floor system 3) Strength and stiffness 4) Storey drift 5) Creep, shrinkage and temperature effects 6) Foundation settlement and soil-structure interation 7) Other important services like ventilation, electric power supply, air conditioning, heating, water supply system, waste disposal, vertical transportation (lifts) etc.
  • 11. 1) Loading :  The principal loads considered in the design of tall structures are : • Gravity loads • Dead loads • Wind loads • Earthquake loads  These forces depends on : • Size and shape of the building • Geographical location of building Dead load Earthquake load Gravity load Wind load 2) Floor system :  (a) For R.C.C. structures : • One way slab on beams & joints • Two way slab on beams & joints • Two way flat slab • Waffle flat slab  (b) For steel structures : • One way beam system • Two way beam system • Composite steel concrete floor system
  • 12. 3) Storey drift : The drift in a storey is computed as a difference of deflections of the floors at the top and bottom of the storey. When building is subjected to earthquake forces, the floor are deflected laterally. The total drift in storey is the sum of shear deformations of that storey, axial deformation of floor, axial deformation of column and foundation rotation. Total drift = S.D + A.D of floor + A.D of column + F.R Due to the minimum specified design lateral force, the storey drift in any storey with a partial load factor of 1.0, should not exceed 0.004 times the storey height. Partial load factor < 0.004 (storey height) LIMITATION DURING EARTHQUAKE : To provide human comfort To limit damage to non-structural elements To preserve vertical stability of a structural system To limit the effect of eccentric gravity load To minimize damage due to pounding
  • 13. 4) Strength and stiffness : The structure should have proper strength in lateral as well as in vertical direction. The structure should not collapse even under a worst combination of loads. Stiffness is the property of a structure to resist deformation. Lateral stiffness is the major consideration in the design of tall structures. The stiffness of joints particularly in the design of precast or prefabricated structure, should be given special attention to develop lateral stiffness of the structure and to avoid progressive failure. A brittle structure having more stiffness, proves to be less durable during earthquake, while a ductile structure performs well in earthquake.
  • 14. 5) Creep, Shrinkage and temperature effect : The vertical deformation due to creep and shrinkage may cause distress in non-structural elements like flooring, cladding, partition etc. Temperature difference between the exterior and interior columns, induces stresses in the structural elements. 6) Foundation settlement and soil-structure interation : In tall structures gravity forces and lateral forces (earthquake force, wind force) are very large . So, the foundation should be capable of transmitting these loads to the under ground strata without exceeding permissible settlement. For tall structure deep foundation ( pile foundation, deep caisson ) are provided.
  • 15. Earthquake causes shaking of ground in all three direction along the two horizontal directions ( X and Y ) and vertical direction (Z). There are main four structural systems to resist lateral loads : (a)Load bearing wall system (b)Moment resisting frame system (c)Dual system ( frame + shear wall/bracing ) (d)Tube systems
  • 16. (a) Load bearing wall system : • Suitable for low rise building • Very weak in resisting lateral loads • Seldom recommended for multi storey building (b) Moment resisting frame system : • The ability of multistorey building to resist the lateral forces depends on the rigidity of joints between the beams and columns. • When this joints are fully rigid, the structure is capable of resisting the lateral loads. The frame is called moment resisting frame. • Strength and stiffness are not sufficient
  • 17. • M.R.F. may be strengthened by incorporating the following structural components such type of system is known as dual system. 1. Load bearing shear wall 2. Shear wall with column 3. Infilled shear walls 4. Bracing 5. Diaphragms 1. Load bearing shear wall : • Useful in preventing the failure of non structural component • May be of RCC, steel, composite and masonry • Thickness :150 mm , height :400 mm (c) Dual system :
  • 18. 2. Shear wall with column : • Provided along both length and width of building • Vertically oriented wide beams that can carry earthquake loads from diaphragms and transmit them to the ground 3. Bracing : • It may be offer lower resistance depending on their design and construction • Section may be steel rolled, circular bar or tube • Vibration may cause the bracing to elongated or compress • Ductility is very important in designing the bracing 4. Diaphrams : • Horizontal resisting elements like floors, roofs • Transfer the lateral forces between vertical resisting elements • Acts as the web of beam and edges as flanges
  • 19. Pure frame Load bearing shear walls Shear wall with column
  • 20. Infilled shear wall Braced frame Whole building braced
  • 21. • Building taller than about 40 storey the lateral force becomes very intense. In this case tube system is more economical. • Classification of tube system 1. Framed tube 2. Trussed tube 3. Tube in tube 4. Bundled tube (d) Tube system :
  • 22. 1. Framed tube system • closely spaced columns • tied at each floor level by deep spandrel beams 2. Trussed tube system • The diagonal members along with grinder and columns, form a truss system that imparts a great deal of stiffness to the building. 3. Tube in tube • Consist of an exterior tube that resist the bending moment due to lateral forces and an interior slender tube, which resist the shear produced by the lateral forces. 4. Bundled tube • Made up of a number of tubes separated by shear walls • The tubes rise to various heights • Each tube is designed independently
  • 23. FRAME TUBE TRUSSED TUBE BUNDLED TUBE
  • 25.
  • 26.  Construction:21 Sept 2004-4 Jan2010  Design: Adrian Smith and his team  Place: Chicago office of SOM (skidmore,owings and Merrill)  Height: 828 m  NOS of floors: 160+  Area of tower: 280,000 sq m  Total Cost: 4.2 Billion Dollars  22 million man hours to construct  Concrete used: 250000 cu.m  Steel rebars: 39,000 tonnes  Curtain walls: 83,600 sq.m glass 27900 sq.m of metal
  • 27.  Status: on hold  Type: Hotel, residential retail  Location: Marin line, Mumbai  Coordinates: 18.950159˚N 72.821348˚E  Construction: started 2010  Estimated completion: 2010  Height: 700 m  NOS of floors: 126  Design and construction: Architect Foster and Partners
  • 28.  Opened : 2010  Height: 210 m  Floor: 60  Address: Mumbai  Architect: Hafeez construction IMPERICAL TOWER
  • 29. PLANET GODREJ City: Mumbai Year: 2010 Height: 181 m Floor: 51
  • 31. NO. NAME CITY HEIGHT (m) FLOORS YEAR 1. Imperial tower Mumbai 249 60 2010 2. Lodha Bellissimo Mumbai 197 48 Under const. 3. Planet Godrej Mumbai 181 51 2009 4. Ashok Tower I Mumbai 193 49 2009 5. RNA Mirage Mumbai 180 40 2009 6. Oberoi woods tower Mumbai 170 40 2009 7. MVRDC Mumbai 156 35 2009 8. Shreepati acard Mumbai 153 45 2002 9. Vasant polaris Mumbai 151 34 2009 10. Belvedere court Mumbai 149.35 40 2008
  • 32. A cluster of concepts concerned with “the arrangement of urban public space.” Two types of patterns : I. Spatial pattern of population distribution within built up area II. Pattern of population movement around the city during the day
  • 34. We can define USS using no. of indicators 3 main indicators : 1) Land consumption (density) 2) Density profile 3) Degree of monocentricity (share of trips with central destination)
  • 36. 1) Land consumption per person : • Higher the density the lower the consumption of land per person • Density = city population / built up area 2) Pattern of daily trips within built-up area : I. Monocentric model (exist only in master plans) II. Polycentric model (common in North American Cities III. Mixed mono-polycentric model (more common)
  • 37. Urban planner should analyse and monitor the evolution of the city Planner should identify the type of urban structure which is compatible with municipal strategy
  • 38. Definition: The application of predetermined force or a moment to structural member in such a manner that the resulting stresses due to this force or moment and external loading will be confined within specified limits
  • 39.
  • 41. (a) Pre-tensioning : • Steel tendons are placed in position in the framework • Predetermined tensile force P is applied to the tendons are kept in stretched condition • Concrete is now placed in formwork and allowed to cure to gets its design strength • Tendon become bounded to concrete throughout their length • The tendon tend to regain their original length by shortening • Method is useful for small elements like railway sleepers, electric poles, pipes etc. Jack Abutment Tendon Beam or block Prestressing bed Jack
  • 42. 2) Post-tensioning: • Concrete is cast while there is no stress in the tendon • When concrete is hardened, the tendons are stretched through hydraulic member through hydraulic jacks bearing against the concrete • The tendon force is transferred to the member through wedges or blocks at the end of the member • The flexible hose or rubber tube may be used to house the tendons so that bond is not developed between the wires and concrete • After the tendon has been stressed, the void space between the tendon and hose is filled with grout • The tendon becomes bounded to concrete and corrosion of steel is prevented Hollow duct for tendon Anchor plate Jacking deviceBeam
  • 43. • As the entire prestressed concrete section is in compression, it is free from tensile cracks • It eliminates corrosion of steel when structure is expose to weather • Pre-stressed concrete section are much smaller than those in reinforced concrete cement structure, because dead load moments are neutralised by prestressing moments and shear stresses are also reduced • In prestressed concrete, entire section is utilised for resisting loads. This will reduce the size of members and dead weight of the structure. • As the self weight of the structure reduces, the foundation cost will also reduce • Under service loads, deflection of member will be less • It has high live load carrying capacity
  • 44. • It requires high strength concrete (minimum M-30) and high strength steel • It requires end anchors and bearing plates • It requires better quality control • It requires complicated formwork • Labour cost may be higher
  • 45. 1. Discuss important points to be considered while constructing tall structure. 2. Discuss important points to be considered while constructing spatial structure 3. What is tall structure? What is need of tall structure? 4. List names of any 5 tall structure in India 5. List names of any 5 tall structure in world 6. Enumerate the factor affecting growth, height and structure form of tall structure 7. Explain various design consideration of tall structure 8. Explain with sketches various structural framing system used for tall structure 9. What are urban spatial structure? 10. Write short note on ‘urban densities’. 11. What is pre-stressing? Explain concept of pre-stressing. 12. Give advantages and disadvantages of pre-stressing. 13. Explain equipment and accessorises used in pre-stressing.