SlideShare a Scribd company logo
1 of 45
Prepared By :
Prof. Karm Balar
CED,SSASIT, SURAT
FORMWORK
1
OUTLINE OF PRESENTATION
• Definition
• Classification of formwork
• Quality of formwork
• Requirements of formwork
• Formwork for building components
• Removal of formworks
• Cost of formworks
• General formwork systems
• Critical formwork systems
• Advanced formwork systems
• Case study
• References
2
3
Some temporary nature supports and structures are required like
 Formwork (Supporting Structure)
 Scaffoldings (arrangement for working plate forms)
 Shoring (supporting method for unsafe structure)
 Underpinning (Method of strengthening an existing structure’s footing)
What is formwork?
• It should be capable of carrying all imposed dead and live loads
apart from its own weight.
• Formwork is a mould including all supporting structures, used
to shape and support the concrete until it attains sufficient
strength to carry its own weight.
Classification of formwork
1. Classification according to sizes
2. Classification according to material
3. Classification according to nature of operation
5
• Classification according to sizes
 Small-sized formwork
-Operation by workers manually.
-Speedy work and easy operating.
-Timber and plastic
Large-sized formwork
-Crane facilities are required in the
operation.
-Reduce the number of jointing and
to minimize the number of lift.
-Steel and aluminum
6
• Classification according to material
a) Timber
-Most popular formwork material
-Low initial cost
-High adaptability to complicated shape
-Labor intensive and environmental unfriendly
7
8
b) Steel
-Initial cost is high
-Formed sections
-Heavy weight
-Suitable for large-sized panels
9
c) Aluminum
-High quality finish.
-unskilled labour can also erect.
-Pure aluminum chemically attacked by wet Concrete
-High reuse value
10
d) Plastic
-Unusual textures and designs can be molded into the form.
-Damages on the formwork can be easily be repaired.
-Easy to disassemble.
-Light.
11
• Classification According to Nature of
Operation
-Manually operated formwork
-Crane lifted formwork
-Gantry, traveling and tunnel type formwork system
12
Conventional ( Traditional ) Formwork system:
In concrete construction, formwork is commonly provided for the
following structural members.
• Foundations
• Wall
• Column
• Slabs & Beams
• Stairs
13
Formwork for
foundation
Wall foundations
It consists of
- Plywood Sheeting
- Struts
Column Foundations
It consists of
- Side Supports
- Side Planks
- Cleats
14
Cleat
Side Planks
Side Support
Formwork for Column :
Fig-6.1.3 Formwork for Column
•It consists of : Side & End Planks, Yokes, & Nut-Bolts
•Two end & two side planks are joined by the yokes and bolts.
• Yokes are the horizontal member which gives support to the side & end planks.
• Yokes are connected to each other by the help of nut & bolts.
15
STUB COLUMN
STEEL BEAM
SIDE SUPPORT,
PROP
FOUNDATION FORMWORK
COLUMN FORMWORK
STEEL SHUTTER PLATES
18 MM PLY INSIDE
COLUMN / WALL FORMWORK
Formwork for Wall
 It consists of
 Timber sheeting
 Vertical posts
 Horizontal members
 Rackers
 Stakes
 Wedges
 After completing one
side of formwork
reinforcement is
provided at the place
then the second side
formwork is provided.
Vertical Posts
Struts
Formwork for wall 24
6.1.4 Formwork for Slabs & beams
It consists of
• Sole plates
• Wedges
• Props
• Head tree
• Planks
• Batten
• Ledgers
• Beam formwork rests on head tree
• Slab form work rests on battens and joists
25
Lintel or Beam Formwork
SLAB FORMWORK
3. ADJUSTABLE BEAM SIDE EXTN.
1. BEAM FORMING SUPPORT
2. BEAM FORMING SUPPORT EXTN.
AVAILABILITY
600,800, 1000,1200
1
2
BEAM SIDE SUPPORTS
6.1.5 Formwork for Stairs
It consists of
•Vertical & inclined posts
•Inclined members
•Wooden Planks or sheeting
•Stringer
•Riser Planks
31
STAIRCASE FORMWORK
35
Requirements of formwork:
 Material should be cheap and reusable,
 It should be practically water proof, so that it should not
absorb water from concrete,
 Shrinkage should be minimum,
 Strong enough to with stand all external loads,
 Deflection should be minimum,
 Surface should be smooth, and afford easy striping,
 Light in weight, so that easy to transfer,
 Joints should be stiff, so that lateral deformation and leak is
minimum . 36
Time of Removal of formwork:
37
Sr.
No
Structural Member OPC* RHC**
1 Beam sides, walls & Columns 2-3 D 2 D
2 Slab (Vertical Supports remains intact) 4 D 3 D
3 Slab (Complete Formwork removal) 10 D 5 D
4 Beams (Removal of Sheeting, Props remains intact) 8 D 5 D
5
Beams & Arches (Complete formwork removal)
(up to 6 m span)
14 D 5-8 D
6
Beams & Arches (Complete formwork removal)
(more than 6 m span)
21 D 8-10 D
*(Ordinary Portland Cement, **Rapid Hardening Cement)
• Cost of formwork
 For normal works cost of formwork is about 30%-40% of the
concrete cost.
 For special works cost of formwork is about 50%-60% of the
concrete cost.
 Formwork cost is controlled by the following factors
• Formwork Material cost
• Formwork erecting cost
• Formwork removal cost
• Formwork jointing cost (Nails and Cables)
• Labor charges.
38
REVOLA - FRAMED WALL FORM
SYSTEM
• MESA-Revola Wall Form System is designed and manufactured for
concreting of load bearing walls and columns.
• REVOLA System is crane-dependent but admits very high concrete
pressure up to 88 kN/m2 when using suitable tie-rods of diameter
20mm.
39
• Types of REVOLA System and Surface Material:
• Concrete facing materials differs according to demands of the
construction sites.
• REVOLA-S with Steel Plate having 4 mm thickness,
• REVOLA-P Plywood having 21 mm thickness
• REVOLA-L Composite Polypropylene Plate having 20 mm thickness
40
41
• LOGICA - FRAMED WALL FORM SYSTEM
• MESA-Logica Wall Form System is crane-dependent as well as it
could be used without crane due to decreased weights of panels
having 1200 and 1500 mm height. Without taking into account of
rate of displacement of concrete, maximum 2,700 mm height of
concrete could be cast by Logica Wall Form when using tie-rods of
diameter 15mm.
• System also shortens the concreting time due to such a high resistance
to concrete pressure which reaches up to 60 kN/m2.
42
• Types of LOGICA System and Surface Material:
• Available concrete facing materials could be two types;
• LOGICA - P with 15 mm thick Plywood
• LOGICA - L with 15 mm thick Composite Polypropylene Plate
43
44
Thank you
THANK YOU45

More Related Content

What's hot

Concrete framework
Concrete frameworkConcrete framework
Concrete frameworkJustin Myint
 
Reinforcement ppt assignment
Reinforcement ppt assignmentReinforcement ppt assignment
Reinforcement ppt assignmenthailnur1794
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formworkKHUSHBU SHAH
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle SlabAkshay Gawade
 
8. formwork and scaffolding
8. formwork and scaffolding8. formwork and scaffolding
8. formwork and scaffoldingHamdija Velagic
 
Ntpc summer training 2017
Ntpc summer training 2017Ntpc summer training 2017
Ntpc summer training 2017ktx500
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsHamdija Velagic
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete constructionJenilPatel22
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyI'mMiss Lily
 
From work & shuttering
From work & shutteringFrom work & shuttering
From work & shutteringhamidgujjar
 

What's hot (19)

Formwork
FormworkFormwork
Formwork
 
Costruction ppt
Costruction pptCostruction ppt
Costruction ppt
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
Concrete framework
Concrete frameworkConcrete framework
Concrete framework
 
Reinforcement ppt assignment
Reinforcement ppt assignmentReinforcement ppt assignment
Reinforcement ppt assignment
 
Fromwork
FromworkFromwork
Fromwork
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle Slab
 
8. formwork and scaffolding
8. formwork and scaffolding8. formwork and scaffolding
8. formwork and scaffolding
 
Formwork
FormworkFormwork
Formwork
 
Formwork
Formwork Formwork
Formwork
 
Ntpc summer training 2017
Ntpc summer training 2017Ntpc summer training 2017
Ntpc summer training 2017
 
Formwork
FormworkFormwork
Formwork
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
Waffle slab
Waffle slabWaffle slab
Waffle slab
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction Technology
 
Formwork
FormworkFormwork
Formwork
 
From work & shuttering
From work & shutteringFrom work & shuttering
From work & shuttering
 

Similar to CHE :- 6 form work (MODULE 3)

formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdfFaizanSolanki
 
Form-woks-additional.pptx
Form-woks-additional.pptxForm-woks-additional.pptx
Form-woks-additional.pptxssuserc0bf9b
 
Introduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineeringIntroduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineeringUjasPandya2
 
Formwork, by prof. sagar raut
Formwork, by prof. sagar rautFormwork, by prof. sagar raut
Formwork, by prof. sagar rautSAGAR RAUT
 
national building code
national building codenational building code
national building codeRuhiya Garg
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shutteringKishor Ade
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structuresRithika Ravishankar
 
building structures of architectural students.pptx
building structures of architectural students.pptxbuilding structures of architectural students.pptx
building structures of architectural students.pptxkifottoti
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptxssuserc0bf9b
 
Formwork Design-Introduction.pdf
Formwork Design-Introduction.pdfFormwork Design-Introduction.pdf
Formwork Design-Introduction.pdfsumitt6_25730773
 
All you need to know about Construction Formwork
All you need to know about Construction FormworkAll you need to know about Construction Formwork
All you need to know about Construction FormworkAnkit Singhai
 
types of formwork.pdf
types of formwork.pdftypes of formwork.pdf
types of formwork.pdfReigerRoyal
 

Similar to CHE :- 6 form work (MODULE 3) (20)

formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdf
 
Form-woks-additional.pptx
Form-woks-additional.pptxForm-woks-additional.pptx
Form-woks-additional.pptx
 
Introduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineeringIntroduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineering
 
FORMWORK.pptx
FORMWORK.pptxFORMWORK.pptx
FORMWORK.pptx
 
Formwork
FormworkFormwork
Formwork
 
Formwork, by prof. sagar raut
Formwork, by prof. sagar rautFormwork, by prof. sagar raut
Formwork, by prof. sagar raut
 
Formwork
FormworkFormwork
Formwork
 
national building code
national building codenational building code
national building code
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
Formwork
FormworkFormwork
Formwork
 
building structures of architectural students.pptx
building structures of architectural students.pptxbuilding structures of architectural students.pptx
building structures of architectural students.pptx
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptx
 
Site report
Site reportSite report
Site report
 
Basic structure
Basic structureBasic structure
Basic structure
 
Formwork Design-Introduction.pdf
Formwork Design-Introduction.pdfFormwork Design-Introduction.pdf
Formwork Design-Introduction.pdf
 
All you need to know about Construction Formwork
All you need to know about Construction FormworkAll you need to know about Construction Formwork
All you need to know about Construction Formwork
 
Prefabricated structures
Prefabricated structuresPrefabricated structures
Prefabricated structures
 
types of formwork.pdf
types of formwork.pdftypes of formwork.pdf
types of formwork.pdf
 
Types of formwork
Types of formworkTypes of formwork
Types of formwork
 

More from Shree Swami atmanand saraswati inst. of technology, surat

More from Shree Swami atmanand saraswati inst. of technology, surat (20)

INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart citiesINFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
 
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systemsINFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
 
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
 
BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)
 
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
 
MODULE 2 PROJECT ORGANIZATION (updated)
MODULE 2 PROJECT ORGANIZATION (updated)MODULE 2 PROJECT ORGANIZATION (updated)
MODULE 2 PROJECT ORGANIZATION (updated)
 
BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)
 
BCT - Module 5 special work
BCT - Module 5 special workBCT - Module 5 special work
BCT - Module 5 special work
 
Module :- 8 Job layout (PART 2)
Module :- 8 Job layout (PART 2)Module :- 8 Job layout (PART 2)
Module :- 8 Job layout (PART 2)
 
Module :- 8 material management
Module :- 8 material managementModule :- 8 material management
Module :- 8 material management
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
Mod 3 construction economics
Mod 3 construction economicsMod 3 construction economics
Mod 3 construction economics
 
MODULE 2 project organization
MODULE 2 project organizationMODULE 2 project organization
MODULE 2 project organization
 
MODULE 1 Introduction to Construction Management
MODULE 1 Introduction to Construction ManagementMODULE 1 Introduction to Construction Management
MODULE 1 Introduction to Construction Management
 
Che 10 engineering fundamental
Che  10 engineering fundamentalChe  10 engineering fundamental
Che 10 engineering fundamental
 
Chapter 9 introduction to construction equipments
Chapter  9 introduction to construction equipmentsChapter  9 introduction to construction equipments
Chapter 9 introduction to construction equipments
 
Che 1 pile foundation
Che 1 pile foundationChe 1 pile foundation
Che 1 pile foundation
 
Ch 5 b remote sensing
Ch 5 b remote sensingCh 5 b remote sensing
Ch 5 b remote sensing
 
Ch 5 a gps
Ch 5 a gpsCh 5 a gps
Ch 5 a gps
 
Ch 5 levelling
Ch 5 levellingCh 5 levelling
Ch 5 levelling
 

Recently uploaded

Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxDr.Ibrahim Hassaan
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomnelietumpap1
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
Planning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptxPlanning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptxLigayaBacuel1
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
Quarter 4 Peace-education.pptx Catch Up Friday
Quarter 4 Peace-education.pptx Catch Up FridayQuarter 4 Peace-education.pptx Catch Up Friday
Quarter 4 Peace-education.pptx Catch Up FridayMakMakNepo
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfSpandanaRallapalli
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Romantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxRomantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxsqpmdrvczh
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.arsicmarija21
 

Recently uploaded (20)

Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptx
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choom
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
Planning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptxPlanning a health career 4th Quarter.pptx
Planning a health career 4th Quarter.pptx
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
Quarter 4 Peace-education.pptx Catch Up Friday
Quarter 4 Peace-education.pptx Catch Up FridayQuarter 4 Peace-education.pptx Catch Up Friday
Quarter 4 Peace-education.pptx Catch Up Friday
 
Rapple "Scholarly Communications and the Sustainable Development Goals"
Rapple "Scholarly Communications and the Sustainable Development Goals"Rapple "Scholarly Communications and the Sustainable Development Goals"
Rapple "Scholarly Communications and the Sustainable Development Goals"
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdf
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Romantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxRomantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptx
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.
 

CHE :- 6 form work (MODULE 3)

  • 1. Prepared By : Prof. Karm Balar CED,SSASIT, SURAT FORMWORK 1
  • 2. OUTLINE OF PRESENTATION • Definition • Classification of formwork • Quality of formwork • Requirements of formwork • Formwork for building components • Removal of formworks • Cost of formworks • General formwork systems • Critical formwork systems • Advanced formwork systems • Case study • References 2
  • 3. 3 Some temporary nature supports and structures are required like  Formwork (Supporting Structure)  Scaffoldings (arrangement for working plate forms)  Shoring (supporting method for unsafe structure)  Underpinning (Method of strengthening an existing structure’s footing)
  • 4. What is formwork? • It should be capable of carrying all imposed dead and live loads apart from its own weight. • Formwork is a mould including all supporting structures, used to shape and support the concrete until it attains sufficient strength to carry its own weight.
  • 5. Classification of formwork 1. Classification according to sizes 2. Classification according to material 3. Classification according to nature of operation 5
  • 6. • Classification according to sizes  Small-sized formwork -Operation by workers manually. -Speedy work and easy operating. -Timber and plastic Large-sized formwork -Crane facilities are required in the operation. -Reduce the number of jointing and to minimize the number of lift. -Steel and aluminum 6
  • 7. • Classification according to material a) Timber -Most popular formwork material -Low initial cost -High adaptability to complicated shape -Labor intensive and environmental unfriendly 7
  • 8. 8
  • 9. b) Steel -Initial cost is high -Formed sections -Heavy weight -Suitable for large-sized panels 9
  • 10. c) Aluminum -High quality finish. -unskilled labour can also erect. -Pure aluminum chemically attacked by wet Concrete -High reuse value 10
  • 11. d) Plastic -Unusual textures and designs can be molded into the form. -Damages on the formwork can be easily be repaired. -Easy to disassemble. -Light. 11
  • 12. • Classification According to Nature of Operation -Manually operated formwork -Crane lifted formwork -Gantry, traveling and tunnel type formwork system 12
  • 13. Conventional ( Traditional ) Formwork system: In concrete construction, formwork is commonly provided for the following structural members. • Foundations • Wall • Column • Slabs & Beams • Stairs 13
  • 14. Formwork for foundation Wall foundations It consists of - Plywood Sheeting - Struts Column Foundations It consists of - Side Supports - Side Planks - Cleats 14 Cleat Side Planks Side Support
  • 15. Formwork for Column : Fig-6.1.3 Formwork for Column •It consists of : Side & End Planks, Yokes, & Nut-Bolts •Two end & two side planks are joined by the yokes and bolts. • Yokes are the horizontal member which gives support to the side & end planks. • Yokes are connected to each other by the help of nut & bolts. 15
  • 16.
  • 17.
  • 20. COLUMN FORMWORK STEEL SHUTTER PLATES 18 MM PLY INSIDE
  • 21. COLUMN / WALL FORMWORK
  • 22.
  • 23. Formwork for Wall  It consists of  Timber sheeting  Vertical posts  Horizontal members  Rackers  Stakes  Wedges  After completing one side of formwork reinforcement is provided at the place then the second side formwork is provided. Vertical Posts Struts
  • 25. 6.1.4 Formwork for Slabs & beams It consists of • Sole plates • Wedges • Props • Head tree • Planks • Batten • Ledgers • Beam formwork rests on head tree • Slab form work rests on battens and joists 25
  • 26. Lintel or Beam Formwork
  • 28.
  • 29. 3. ADJUSTABLE BEAM SIDE EXTN. 1. BEAM FORMING SUPPORT 2. BEAM FORMING SUPPORT EXTN. AVAILABILITY 600,800, 1000,1200 1 2
  • 31. 6.1.5 Formwork for Stairs It consists of •Vertical & inclined posts •Inclined members •Wooden Planks or sheeting •Stringer •Riser Planks 31
  • 33.
  • 34.
  • 35. 35
  • 36. Requirements of formwork:  Material should be cheap and reusable,  It should be practically water proof, so that it should not absorb water from concrete,  Shrinkage should be minimum,  Strong enough to with stand all external loads,  Deflection should be minimum,  Surface should be smooth, and afford easy striping,  Light in weight, so that easy to transfer,  Joints should be stiff, so that lateral deformation and leak is minimum . 36
  • 37. Time of Removal of formwork: 37 Sr. No Structural Member OPC* RHC** 1 Beam sides, walls & Columns 2-3 D 2 D 2 Slab (Vertical Supports remains intact) 4 D 3 D 3 Slab (Complete Formwork removal) 10 D 5 D 4 Beams (Removal of Sheeting, Props remains intact) 8 D 5 D 5 Beams & Arches (Complete formwork removal) (up to 6 m span) 14 D 5-8 D 6 Beams & Arches (Complete formwork removal) (more than 6 m span) 21 D 8-10 D *(Ordinary Portland Cement, **Rapid Hardening Cement)
  • 38. • Cost of formwork  For normal works cost of formwork is about 30%-40% of the concrete cost.  For special works cost of formwork is about 50%-60% of the concrete cost.  Formwork cost is controlled by the following factors • Formwork Material cost • Formwork erecting cost • Formwork removal cost • Formwork jointing cost (Nails and Cables) • Labor charges. 38
  • 39. REVOLA - FRAMED WALL FORM SYSTEM • MESA-Revola Wall Form System is designed and manufactured for concreting of load bearing walls and columns. • REVOLA System is crane-dependent but admits very high concrete pressure up to 88 kN/m2 when using suitable tie-rods of diameter 20mm. 39
  • 40. • Types of REVOLA System and Surface Material: • Concrete facing materials differs according to demands of the construction sites. • REVOLA-S with Steel Plate having 4 mm thickness, • REVOLA-P Plywood having 21 mm thickness • REVOLA-L Composite Polypropylene Plate having 20 mm thickness 40
  • 41. 41
  • 42. • LOGICA - FRAMED WALL FORM SYSTEM • MESA-Logica Wall Form System is crane-dependent as well as it could be used without crane due to decreased weights of panels having 1200 and 1500 mm height. Without taking into account of rate of displacement of concrete, maximum 2,700 mm height of concrete could be cast by Logica Wall Form when using tie-rods of diameter 15mm. • System also shortens the concreting time due to such a high resistance to concrete pressure which reaches up to 60 kN/m2. 42
  • 43. • Types of LOGICA System and Surface Material: • Available concrete facing materials could be two types; • LOGICA - P with 15 mm thick Plywood • LOGICA - L with 15 mm thick Composite Polypropylene Plate 43
  • 44. 44