The Chunnel Tunnel project connecting France and the UK suffered from significant cost overruns and delays. Originally estimated at $5.5 billion, the final cost increased to $14.9 billion. While the tunnel was a technical success and opened 19 months behind schedule, poor scope management, lack of risk planning, and issues with contractors and changing requirements led to budgetary problems and left investors unhappy. However, it provided an important new transportation link between the two countries.
This presentation provides a keen insight into the issues that arose during the construction of the Channel Tunnel (Chunnel), that forms a 50.5 km rail lifeline between France and UK.
This is a team presentation, we presented, of our analysis on the "Channel Tunnel" (Euro tunnel) project, as our term project for the course "International Project Management & Professional Responsibility" of "Project Management" program.
This presentation provides a keen insight into the issues that arose during the construction of the Channel Tunnel (Chunnel), that forms a 50.5 km rail lifeline between France and UK.
This is a team presentation, we presented, of our analysis on the "Channel Tunnel" (Euro tunnel) project, as our term project for the course "International Project Management & Professional Responsibility" of "Project Management" program.
Project Management is a discipline of planning, organizing, motivating, controlling resources to achieve specific goals. The presentation tell you about "Konkan Railway Project" undertaken by Indian government. It in details tells you about the challenges faced, problems occurred, Risk involved, new technology used and many other details.
In this presentation we share information on how to map / integrated the PMBOK Guide Process Groups with a Project Life Cycle. The project life cycle can be a generic model or per the SUKAD CAM2P™ Model (The Customizable and Adaptable Methodology for Managing Projects™).
We share this topic because it is a common area of confusion among PMPs and those studying the PMBOK Guide.
PMBoK 6 - Chapter 9 for Project Resource Management.
This presentation material is presented for CAPM students of Telkom University Bandung, Indonesia on 16 December 2018.
Project management final report ENG3004 Griffith University Guri Dam & Chunne...peter747
3004ENG: Project Management Principles
Griffith School of Engineering
Griffith University Gold Coast
guri dam venezuela
chunnel project case study
The Chunnel Tunnel Project
project management report engineering
Project Management is a discipline of planning, organizing, motivating, controlling resources to achieve specific goals. The presentation tell you about "Konkan Railway Project" undertaken by Indian government. It in details tells you about the challenges faced, problems occurred, Risk involved, new technology used and many other details.
In this presentation we share information on how to map / integrated the PMBOK Guide Process Groups with a Project Life Cycle. The project life cycle can be a generic model or per the SUKAD CAM2P™ Model (The Customizable and Adaptable Methodology for Managing Projects™).
We share this topic because it is a common area of confusion among PMPs and those studying the PMBOK Guide.
PMBoK 6 - Chapter 9 for Project Resource Management.
This presentation material is presented for CAPM students of Telkom University Bandung, Indonesia on 16 December 2018.
Project management final report ENG3004 Griffith University Guri Dam & Chunne...peter747
3004ENG: Project Management Principles
Griffith School of Engineering
Griffith University Gold Coast
guri dam venezuela
chunnel project case study
The Chunnel Tunnel Project
project management report engineering
CJM Construction Consulting is a unique global construction management and consulting firm that performs construction management, project estimating, energy efficiency & sustainability consulting, disaster recovery, contractor/supplier vetting, and facility condition assessment for a variety of high-profile clients. We perform general construction and high voltage project estimating and quantity take-off for construction projects and clients all over the globe.
Presentation to ISACA Governance Event 11 Sept 2009 on factors affecting Project Success/Failure referencing ISO38500, Project Management, Standish and the CHAOS Report, also Sauer et all, Cadbury and drawing on Peter Salmon's varied and extnesive personal experience
Presentation slides provided by Robert Holloway from Stantec on 10 May 2022 at the North West Branch Conference in Manchester on the Warrington Western Link project.
Nature- Need for Project Management – types of projects – Project Management Knowledge areas and processes – Project skills – The role of Project Manager – Project Management Processes – Impact of Delays in Project Completions – Essential of Project Management Philosophy – Project Management Principles
Objective: To share how to shift focus on some of the human and psychological aspects of change, to balance the usual concentration on process that helped to setup, build & lead the APM PMO of the Year 2020 from the Government of Montserrat.
Presentation delivered by Greg Lamberson, Vice President, Planning, Frontier Energy Services, LLC at the marcus evans Energy Pipeline Summit 2019 held in New Orleans LA
Course Assignment: Financing and Initiating Major Engineering ProjectsFragoso Josue Muhae
Development of an industrial major project as part of the Managing Major Engineering Projects specialization. The project is premised on the development of a 5-6 km conveyor belt system (ABC Belt) that will service the expansion area towards the south and southwest of the original pit and will depart from current operational area to the processing plants (CPPs).
Artificial intelligence (AI) offers new opportunities to radically reinvent the way we do business. This study explores how CEOs and top decision makers around the world are responding to the transformative potential of AI.
The Team Member and Guest Experience - Lead and Take Care of your restaurant team. They are the people closest to and delivering Hospitality to your paying Guests!
Make the call, and we can assist you.
408-784-7371
Foodservice Consulting + Design
Modern Database Management 12th Global Edition by Hoffer solution manual.docxssuserf63bd7
https://qidiantiku.com/solution-manual-for-modern-database-management-12th-global-edition-by-hoffer.shtml
name:Solution manual for Modern Database Management 12th Global Edition by Hoffer
Edition:12th Global Edition
author:by Hoffer
ISBN:ISBN 10: 0133544613 / ISBN 13: 9780133544619
type:solution manual
format:word/zip
All chapter include
Focusing on what leading database practitioners say are the most important aspects to database development, Modern Database Management presents sound pedagogy, and topics that are critical for the practical success of database professionals. The 12th Edition further facilitates learning with illustrations that clarify important concepts and new media resources that make some of the more challenging material more engaging. Also included are general updates and expanded material in the areas undergoing rapid change due to improved managerial practices, database design tools and methodologies, and database technology.
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...CIOWomenMagazine
This person is none other than Oprah Winfrey, a highly influential figure whose impact extends beyond television. This article will delve into the remarkable life and lasting legacy of Oprah. Her story serves as a reminder of the importance of perseverance, compassion, and firm determination.
2. Overview:
• Designed to create spur in Economic Development
• Improve the trade relations with alternate high speed transportation
• One of the largest privately funded construction Project between two countries
• 51.5 Km long double rail tunnel.
• Project was initially estimated at 5.5 Billion dollars on completion the cost increased
to 14.9 Billion dollars
Chunnel Tunnel Group/French
Manche (BOT basis)
Transmanche Link
(TML) (Construction)
French and
British Govts.,
3. Scope Management
Inception
• Lack of defined
scope
• Scope defined in
Lump sum basis
• Difficulty in
Resource
planning
• Formation of
IGC
Development
• Enormous scope
• Measures to
prevent the
scope creep was
not put in place
• Project
Planning, cost
estimation,
Funding was
affected due to
scope change
Implementation
• IGC had major
control over
scope
• Frequent
change in scope
• Door and A/c
System
contributed to
major scope
changes
Closeout
• Even when the
tunnel was
deemed to
complete, there
were
discrepancies
over scope of
some works.
Rating :
2
2
2 22
4. Time Management
Inception
• Hasty Bidding
and concept
development
• Not enough time
provided to
complete
detailed design
studies
Development
• Change in
requirement by
IGC caused delay
• Approval of
drawings
mandated from
both
governments
• Very good
tracking with
hefty status
report
Implementation
• Faster Tunneling
• Rail and car
systems were
delivered late
• Alteration of
passenger door
sizes caused
delay for 9
months.
Closeout
• Cascading effects
of previous
phases
• 19 month delay
• Project
management
team could not
be held
responsible
Rating :
3
3
3 2
2
5. Cost Management
Inception
• Estimated cost
of USD 5.5 bn.
• Initial Cost
Estimates were
not detailed
out.
• Financing
arranged via
equity and
capital market
Development
• USD 2.25 Bn
claim against
Eutotunnel by
contractor was
not anticipated
• Use of
sophesticted
equipment not
anticipated
Implementation
• Unnecessary
use of costly
technologies in
some cases like
grouting.
• Wrong
selection of
TBM.
Closeout
• Efforts were
driven towards
settlemnt of
claims rather
than analysing
on sources of
cost overrun.
Rating :
2
1
2
1
2
6. Quality Management
Inception
• Difference in
standards ->
Higher
standard
• Latest laser
and computer
technology
proposed to
bore the
tunnel.
Development
• Good PAC was
framed.
• No margin for
errors
• Formation of
IGC
Implementation
• Stringent
requirements
from IGC
• Very high
accuracy
maintained.
Closeout
• Quality
parameters
achieved
were above
industry
average.
Rating :
5
4
5
5
5
7. Human Resources Management
Inception
• Team work
envisaged
• Good structure
with proper
responsibilities
formed.
Development
• Every British
team member
had French
counter part
Implementation
• Managed
15,000 workers
in good
manner
• Workers from
different
cultures were
engaged with
high level of
efficiency
Closeout
• Most of the
persons were
demotivated
due to non
settlement of
claims.
• Win-win
situation was
lost
Rating :
3
3
3 2
3
8. Communications Management
Inception
• Difference in
languages of
two countries
Development
• Limited
communication
between two
teams since
both of them
were trying to
meet in
middle.
• This lead to
difference of
opinion at later
stages
Implementation
• Delay in
communication
regarding
specification
change.
Closeout
• Negotiations
not proper at
Closeout since
bankers did not
settle for
claims.
Rating :
2
3
3 1
2
9. Risk Management
Inception
• Technical risk only
considered
• Process and
approval risk were
not envisaged
• Both governments
denied to provide
financial
guarantee.
• Social cost benefit
analysis not done.
Development
• Over management
of risk – advanced
techniques
considered
• Contingencies and
margins were
barest mimimum.
• Contractors forced
to consider best
situation.
• Risk assessment
plan was not
made.
Implementation
• Fast tracking of
design and
construction
processes done
without risk
analysis.
• New unproven
technology
increased risk
• Banks were
involved for
minimising the
risk, however IGC
was controlling.
Closeout
• Courts ruled in
favour of
contractor.
Rating :
2
2
2
2
2
10. Procurement Management
Inception
• Rigorous time
constraints
caused hasty
procurement
plan/contracts.
• Procurement of
rolling stock and
associated major
equipment
finalised on cost
plus percentage
fee basis
Development
• Procurement
delayed since
scope/
specification was
changing.
Implementation
• Fixed price
contracts with
several
contractors
• Differences in
goals since many
contractors were
having equity.
Closeout
• Cascading effect
of
implementation
created 17
months delay.
• Non settlement
of extra claims
Rating :
2
2
2
2
3
11. Integration Management
Inception
• Various
international
agencies took part
for
conceptualisation.
• Mistrust among
agencies since
both govts didn’t
provide guarantee
but placed
requirements.
Development
• 46 contractors
were deployed for
design
• 7 Lakh
shareholders, 220
Lending banks
were involved for
financing.
Implementation
• Huge resources,
huge scope of
work were
managed in best
of industry
standards.
• Logistical and
communication
challenges.
Close out
• Teams not
integrated due to
poor
communication.
• Each party tried to
focus on their own
interests.
• International
chamber of
commerce
engaged for
dispute resolution
Rating :
3
2
3 2
3
13. Key Dates
Year Key Developments
1802 Albert Mathieu put forward a cross channel proposal
1875 Channel Tunnel Company Ltd began preliminary trials
1882
Experimental work on both sides of the Channel started but soon idea was
abandoned citing national defense security.
1975 A UK–France government backed scheme that started in 1974 was cancelled
1984
British & French govt. agreed to common safety, environmental & security
concern, prior opening up the project to bidder
1985 British & French govt. asked for proposals.
1986
Project awarded to Eurotunnel on BOOT basis with 55 year concession
period with initial cost of US$ 5.5 billion.
June 1988 In France, first tunneling was started
December
1988
Tunneling operation was started in UK
May 1994
Tunnel was formally inaugurated & started functioning. Project was
completed with cost & time over run.
14. Major Area of Strength Managing this Project
QUALITY
MANAGEMENT
• Quality management was implemented successfully.
• Technical expertise .
TEAM WORK
• Excellent team work between two groups.
• Construction of tunnel completed 3 months ahead of schedule.
• Project office support was excellent.
SAFETY
MANAGEMENT
• Accidents below industry average.
• 15000 workmen, numerous engineers, handled precisely.
15. Major Opportunities for improvement from Management P.O.V
SCOPE
MANAGEMENT
• Detailed Functional requirement & Technical specification
• Consideration of Scope contingency
CONTRACT
MANAGEMENT
• Applicability of Single Contract to both group.
• Coverage of risk exposures
COMMUNICATION
MANAGEMENT
• Communication protocol preparation
• Protocol for escalating unresolved / pending issue
• Tracking & monitoring
16. Major Opportunities for improvement from Management P.O.V (cont.)
RISK
MANAGEMENT
• Project process & approval risk was overlooked.
• Not prepared to handle the degree of IGC supervision & change
management controls.
• Contingencies for known & unknown risk & a strategy for handling
change management missing.
COST
MANAGEMENT
• Use a standardized change-control management to eliminate cost
considerations issues imposed by out-of-control-change management
control processes.
• Specification and validation of functional and technical requirements at
front.
• Replacement of material, equipment with alternate option of same
specification.
STAKEHOLDER
MANAGEMENT
• Project Stakeholder management plan was not prepared in detailed and
also not followed throughout project life cycle. By implementing this,
variance in cost, schedule and extra claims could have been minimized.
17. Major Project Management Lessons learned
Review past engineering studies & take
them in consideration
Technical as well functional aspects of
project management should be given
equal importance
Detailed risk analysis required in
inception stage & needs to be tracked,
monitored during PLC of project
18. Major Project Management Lessons learned
Maintaining communication throughout the
life of project yields better operational
project results.
In large international construction projects of
the involving countries, Govt. support &
communication channels should be roped in.
Whole hearted effort to be made right from
the inception of project in order to avoid
adverse situation at the end
19. Conclusion:
• Time Over run – 19 months delay
• Cost Over run – USD 9.4 Bn
• Trail of unhappy investors and stakeholders
• Key learnings
• Modern Engineering Marvel
• Undoubted Public benefit