SlideShare a Scribd company logo
CASE STUDY ON CHUNNEL TUNNEL PROJECT
Team 5
Overview:
• Designed to create spur in Economic Development
• Improve the trade relations with alternate high speed transportation
• One of the largest privately funded construction Project between two countries
• 51.5 Km long double rail tunnel.
• Project was initially estimated at 5.5 Billion dollars on completion the cost increased
to 14.9 Billion dollars
Chunnel Tunnel Group/French
Manche (BOT basis)
Transmanche Link
(TML) (Construction)
French and
British Govts.,
Scope Management
Inception
• Lack of defined
scope
• Scope defined in
Lump sum basis
• Difficulty in
Resource
planning
• Formation of
IGC
Development
• Enormous scope
• Measures to
prevent the
scope creep was
not put in place
• Project
Planning, cost
estimation,
Funding was
affected due to
scope change
Implementation
• IGC had major
control over
scope
• Frequent
change in scope
• Door and A/c
System
contributed to
major scope
changes
Closeout
• Even when the
tunnel was
deemed to
complete, there
were
discrepancies
over scope of
some works.
Rating :
2
2
2 22
Time Management
Inception
• Hasty Bidding
and concept
development
• Not enough time
provided to
complete
detailed design
studies
Development
• Change in
requirement by
IGC caused delay
• Approval of
drawings
mandated from
both
governments
• Very good
tracking with
hefty status
report
Implementation
• Faster Tunneling
• Rail and car
systems were
delivered late
• Alteration of
passenger door
sizes caused
delay for 9
months.
Closeout
• Cascading effects
of previous
phases
• 19 month delay
• Project
management
team could not
be held
responsible
Rating :
3
3
3 2
2
Cost Management
Inception
• Estimated cost
of USD 5.5 bn.
• Initial Cost
Estimates were
not detailed
out.
• Financing
arranged via
equity and
capital market
Development
• USD 2.25 Bn
claim against
Eutotunnel by
contractor was
not anticipated
• Use of
sophesticted
equipment not
anticipated
Implementation
• Unnecessary
use of costly
technologies in
some cases like
grouting.
• Wrong
selection of
TBM.
Closeout
• Efforts were
driven towards
settlemnt of
claims rather
than analysing
on sources of
cost overrun.
Rating :
2
1
2
1
2
Quality Management
Inception
• Difference in
standards ->
Higher
standard
• Latest laser
and computer
technology
proposed to
bore the
tunnel.
Development
• Good PAC was
framed.
• No margin for
errors
• Formation of
IGC
Implementation
• Stringent
requirements
from IGC
• Very high
accuracy
maintained.
Closeout
• Quality
parameters
achieved
were above
industry
average.
Rating :
5
4
5
5
5
Human Resources Management
Inception
• Team work
envisaged
• Good structure
with proper
responsibilities
formed.
Development
• Every British
team member
had French
counter part
Implementation
• Managed
15,000 workers
in good
manner
• Workers from
different
cultures were
engaged with
high level of
efficiency
Closeout
• Most of the
persons were
demotivated
due to non
settlement of
claims.
• Win-win
situation was
lost
Rating :
3
3
3 2
3
Communications Management
Inception
• Difference in
languages of
two countries
Development
• Limited
communication
between two
teams since
both of them
were trying to
meet in
middle.
• This lead to
difference of
opinion at later
stages
Implementation
• Delay in
communication
regarding
specification
change.
Closeout
• Negotiations
not proper at
Closeout since
bankers did not
settle for
claims.
Rating :
2
3
3 1
2
Risk Management
Inception
• Technical risk only
considered
• Process and
approval risk were
not envisaged
• Both governments
denied to provide
financial
guarantee.
• Social cost benefit
analysis not done.
Development
• Over management
of risk – advanced
techniques
considered
• Contingencies and
margins were
barest mimimum.
• Contractors forced
to consider best
situation.
• Risk assessment
plan was not
made.
Implementation
• Fast tracking of
design and
construction
processes done
without risk
analysis.
• New unproven
technology
increased risk
• Banks were
involved for
minimising the
risk, however IGC
was controlling.
Closeout
• Courts ruled in
favour of
contractor.
Rating :
2
2
2
2
2
Procurement Management
Inception
• Rigorous time
constraints
caused hasty
procurement
plan/contracts.
• Procurement of
rolling stock and
associated major
equipment
finalised on cost
plus percentage
fee basis
Development
• Procurement
delayed since
scope/
specification was
changing.
Implementation
• Fixed price
contracts with
several
contractors
• Differences in
goals since many
contractors were
having equity.
Closeout
• Cascading effect
of
implementation
created 17
months delay.
• Non settlement
of extra claims
Rating :
2
2
2
2
3
Integration Management
Inception
• Various
international
agencies took part
for
conceptualisation.
• Mistrust among
agencies since
both govts didn’t
provide guarantee
but placed
requirements.
Development
• 46 contractors
were deployed for
design
• 7 Lakh
shareholders, 220
Lending banks
were involved for
financing.
Implementation
• Huge resources,
huge scope of
work were
managed in best
of industry
standards.
• Logistical and
communication
challenges.
Close out
• Teams not
integrated due to
poor
communication.
• Each party tried to
focus on their own
interests.
• International
chamber of
commerce
engaged for
dispute resolution
Rating :
3
2
3 2
3
Project
Management Area
Inception
Phase
Developme
nt Phase
Implementa
tion Phase
Closeout
Phase
Average
Scope Mgt 2 2 2 2 2
Time Mgt 3 3 2 2 3
Cost Mgt 1 2 2 1 2
Quality Mgt 4 5 5 5 5
HRM 3 3 3 2 3
Communications
Mgt
3 3 2 1 2
Risk Mgt 2 2 2 2 2
Procurement Mgt 2 2 3 2 2
Integration Mgt 2 3 3 2 3
Rating Scale - Summary
Rating Scale : 5-Excellent, 4- Very Good, 3- Good, 2- Poor, 1- Very Poor
Key Dates
Year Key Developments
1802 Albert Mathieu put forward a cross channel proposal
1875 Channel Tunnel Company Ltd began preliminary trials
1882
Experimental work on both sides of the Channel started but soon idea was
abandoned citing national defense security.
1975 A UK–France government backed scheme that started in 1974 was cancelled
1984
British & French govt. agreed to common safety, environmental & security
concern, prior opening up the project to bidder
1985 British & French govt. asked for proposals.
1986
Project awarded to Eurotunnel on BOOT basis with 55 year concession
period with initial cost of US$ 5.5 billion.
June 1988 In France, first tunneling was started
December
1988
Tunneling operation was started in UK
May 1994
Tunnel was formally inaugurated & started functioning. Project was
completed with cost & time over run.
Major Area of Strength Managing this Project
QUALITY
MANAGEMENT
• Quality management was implemented successfully.
• Technical expertise .
TEAM WORK
• Excellent team work between two groups.
• Construction of tunnel completed 3 months ahead of schedule.
• Project office support was excellent.
SAFETY
MANAGEMENT
• Accidents below industry average.
• 15000 workmen, numerous engineers, handled precisely.
Major Opportunities for improvement from Management P.O.V
SCOPE
MANAGEMENT
• Detailed Functional requirement & Technical specification
• Consideration of Scope contingency
CONTRACT
MANAGEMENT
• Applicability of Single Contract to both group.
• Coverage of risk exposures
COMMUNICATION
MANAGEMENT
• Communication protocol preparation
• Protocol for escalating unresolved / pending issue
• Tracking & monitoring
Major Opportunities for improvement from Management P.O.V (cont.)
RISK
MANAGEMENT
• Project process & approval risk was overlooked.
• Not prepared to handle the degree of IGC supervision & change
management controls.
• Contingencies for known & unknown risk & a strategy for handling
change management missing.
COST
MANAGEMENT
• Use a standardized change-control management to eliminate cost
considerations issues imposed by out-of-control-change management
control processes.
• Specification and validation of functional and technical requirements at
front.
• Replacement of material, equipment with alternate option of same
specification.
STAKEHOLDER
MANAGEMENT
• Project Stakeholder management plan was not prepared in detailed and
also not followed throughout project life cycle. By implementing this,
variance in cost, schedule and extra claims could have been minimized.
Major Project Management Lessons learned
Review past engineering studies & take
them in consideration
Technical as well functional aspects of
project management should be given
equal importance
Detailed risk analysis required in
inception stage & needs to be tracked,
monitored during PLC of project
Major Project Management Lessons learned
Maintaining communication throughout the
life of project yields better operational
project results.
In large international construction projects of
the involving countries, Govt. support &
communication channels should be roped in.
Whole hearted effort to be made right from
the inception of project in order to avoid
adverse situation at the end
Conclusion:
• Time Over run – 19 months delay
• Cost Over run – USD 9.4 Bn
• Trail of unhappy investors and stakeholders
• Key learnings
• Modern Engineering Marvel
• Undoubted Public benefit
Summary chunnel tunnel project management

More Related Content

What's hot

Chunnel project project cost management
Chunnel  project project cost managementChunnel  project project cost management
Chunnel project project cost management
Sagar Rana
 
Delhi Metro Rail Project Management
Delhi Metro Rail Project ManagementDelhi Metro Rail Project Management
Delhi Metro Rail Project Management
Anurag Sureka
 
Project Planning and Management of Millau Viaduct Bridge, France
Project Planning and Management of Millau Viaduct Bridge, FranceProject Planning and Management of Millau Viaduct Bridge, France
Project Planning and Management of Millau Viaduct Bridge, France
Rakibul Hasan,MEng,EIT
 
Project management failure case study
Project management failure case studyProject management failure case study
Project management failure case studyManisha Mishra
 
Project management basics
Project management basicsProject management basics
Project management basics
Planning School
 
The Eurotunnel Project - Cam Ready.pdf
The Eurotunnel Project - Cam Ready.pdfThe Eurotunnel Project - Cam Ready.pdf
The Eurotunnel Project - Cam Ready.pdf
Ankur829275
 
The Untold Story of Konkan Railway
The Untold Story of Konkan RailwayThe Untold Story of Konkan Railway
The Untold Story of Konkan Railway
Rohit Dhoundiyal
 
Integrating project life cycle with process groups
Integrating project life cycle with process groupsIntegrating project life cycle with process groups
Integrating project life cycle with process groups
SUKAD Group - Project Management Solutions
 
Project Resource Management
Project Resource ManagementProject Resource Management
Project Resource Management
Crysanthus Raharjo, PMP
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource management
Amit Kumbar
 
Project & Project managment
Project & Project managmentProject & Project managment
Project & Project managment
Pramod Sharma
 
Risk management
Risk managementRisk management
Risk management
nashaat algrara
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparison
helensuni
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
Procept Associates
 
Contracting Strategy
Contracting StrategyContracting Strategy
Contracting Strategy
Iceland Geothermal
 
Delhi metro project evaluation
Delhi metro project evaluationDelhi metro project evaluation
Delhi metro project evaluationgouravranjan27
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
Ajeesh Mk
 

What's hot (20)

Chunnel project project cost management
Chunnel  project project cost managementChunnel  project project cost management
Chunnel project project cost management
 
Channel tunnel
Channel tunnelChannel tunnel
Channel tunnel
 
Delhi Metro Rail Project Management
Delhi Metro Rail Project ManagementDelhi Metro Rail Project Management
Delhi Metro Rail Project Management
 
Project termination
Project terminationProject termination
Project termination
 
Project Planning and Management of Millau Viaduct Bridge, France
Project Planning and Management of Millau Viaduct Bridge, FranceProject Planning and Management of Millau Viaduct Bridge, France
Project Planning and Management of Millau Viaduct Bridge, France
 
Project management failure case study
Project management failure case studyProject management failure case study
Project management failure case study
 
Project Team Building
Project Team BuildingProject Team Building
Project Team Building
 
Project management basics
Project management basicsProject management basics
Project management basics
 
The Eurotunnel Project - Cam Ready.pdf
The Eurotunnel Project - Cam Ready.pdfThe Eurotunnel Project - Cam Ready.pdf
The Eurotunnel Project - Cam Ready.pdf
 
The Untold Story of Konkan Railway
The Untold Story of Konkan RailwayThe Untold Story of Konkan Railway
The Untold Story of Konkan Railway
 
Integrating project life cycle with process groups
Integrating project life cycle with process groupsIntegrating project life cycle with process groups
Integrating project life cycle with process groups
 
Project Resource Management
Project Resource ManagementProject Resource Management
Project Resource Management
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource management
 
Project & Project managment
Project & Project managmentProject & Project managment
Project & Project managment
 
Risk management
Risk managementRisk management
Risk management
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparison
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Contracting Strategy
Contracting StrategyContracting Strategy
Contracting Strategy
 
Delhi metro project evaluation
Delhi metro project evaluationDelhi metro project evaluation
Delhi metro project evaluation
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 

Viewers also liked

Channel Tunnel
Channel TunnelChannel Tunnel
Channel TunnelTim Howell
 
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
peter747
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine mohammadsalikali
 
Channel tunnel
Channel  tunnelChannel  tunnel
Channel tunnel
marhielymarce
 
Eurotunnel
EurotunnelEurotunnel
Eurotunnel
marhielymarce
 
Eurotunnel
EurotunnelEurotunnel
Eurotunnel
marhielymarce
 
tunneling & its effects
tunneling & its effectstunneling & its effects
tunneling & its effects
Budarapu Venkat Pranay
 
ulnar Entrapment Neuropathy and double crush syndrome
ulnar Entrapment Neuropathy and double crush syndromeulnar Entrapment Neuropathy and double crush syndrome
ulnar Entrapment Neuropathy and double crush syndrome
Home~^^
 
E1 - Panama Canal Risk Analysis
E1 - Panama Canal Risk AnalysisE1 - Panama Canal Risk Analysis
E1 - Panama Canal Risk AnalysisS Giancola
 
Embedding quality assurance within procurement
Embedding quality assurance within procurementEmbedding quality assurance within procurement
Embedding quality assurance within procurement
Myron Duncan Burton Betshanger
 
CJM Construction Consulting PowerPoint Presentation
CJM Construction Consulting PowerPoint PresentationCJM Construction Consulting PowerPoint Presentation
CJM Construction Consulting PowerPoint Presentation
Signature Paving & Sealcoating, Inc.
 
Project Success/Failure
Project Success/FailureProject Success/Failure
Project Success/Failure
Peter Salmon
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
jagadish chintu
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineering
Adil Shaikh
 
10 things to improve project management
10 things to improve project management10 things to improve project management
10 things to improve project management
Striking Group Pty Ltd
 
Tunnelling
TunnellingTunnelling
Tunnelling
Usama Zia
 
Opera sydney case study analysis
Opera sydney case study analysisOpera sydney case study analysis
Opera sydney case study analysis
Khaled Eid
 
Hoover dam and the negative effects on environment
Hoover dam and the negative effects on environmentHoover dam and the negative effects on environment
Hoover dam and the negative effects on environment
Lengkengs
 
Seven modern wonders of the world
Seven modern wonders of the worldSeven modern wonders of the world
Seven modern wonders of the worldvvelasco
 
Excavation of Tunnels
Excavation of TunnelsExcavation of Tunnels
Excavation of Tunnels
partha sharma
 

Viewers also liked (20)

Channel Tunnel
Channel TunnelChannel Tunnel
Channel Tunnel
 
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine
 
Channel tunnel
Channel  tunnelChannel  tunnel
Channel tunnel
 
Eurotunnel
EurotunnelEurotunnel
Eurotunnel
 
Eurotunnel
EurotunnelEurotunnel
Eurotunnel
 
tunneling & its effects
tunneling & its effectstunneling & its effects
tunneling & its effects
 
ulnar Entrapment Neuropathy and double crush syndrome
ulnar Entrapment Neuropathy and double crush syndromeulnar Entrapment Neuropathy and double crush syndrome
ulnar Entrapment Neuropathy and double crush syndrome
 
E1 - Panama Canal Risk Analysis
E1 - Panama Canal Risk AnalysisE1 - Panama Canal Risk Analysis
E1 - Panama Canal Risk Analysis
 
Embedding quality assurance within procurement
Embedding quality assurance within procurementEmbedding quality assurance within procurement
Embedding quality assurance within procurement
 
CJM Construction Consulting PowerPoint Presentation
CJM Construction Consulting PowerPoint PresentationCJM Construction Consulting PowerPoint Presentation
CJM Construction Consulting PowerPoint Presentation
 
Project Success/Failure
Project Success/FailureProject Success/Failure
Project Success/Failure
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineering
 
10 things to improve project management
10 things to improve project management10 things to improve project management
10 things to improve project management
 
Tunnelling
TunnellingTunnelling
Tunnelling
 
Opera sydney case study analysis
Opera sydney case study analysisOpera sydney case study analysis
Opera sydney case study analysis
 
Hoover dam and the negative effects on environment
Hoover dam and the negative effects on environmentHoover dam and the negative effects on environment
Hoover dam and the negative effects on environment
 
Seven modern wonders of the world
Seven modern wonders of the worldSeven modern wonders of the world
Seven modern wonders of the world
 
Excavation of Tunnels
Excavation of TunnelsExcavation of Tunnels
Excavation of Tunnels
 

Similar to Summary chunnel tunnel project management

PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE
S. Sathishkumar
 
Warrington Western Link, Robert Holloway
Warrington Western Link, Robert HollowayWarrington Western Link, Robert Holloway
Warrington Western Link, Robert Holloway
Association for Project Management
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
Gregoire Lesecq
 
BASICS OF PROJECT MANAGEMENT
BASICS OF PROJECT MANAGEMENTBASICS OF PROJECT MANAGEMENT
BASICS OF PROJECT MANAGEMENT
Niruban Projoth
 
How to setup and lead a successfully PMO
How to setup and lead a successfully PMOHow to setup and lead a successfully PMO
How to setup and lead a successfully PMO
PMOfficers PMOAcademy
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
NAVNEET KUMAR JHA
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
NAVNEET KUMAR JHA
 
Managing Project Transitions
Managing Project TransitionsManaging Project Transitions
Managing Project Transitions
Energy Network marcus evans
 
projectmanagement-123765482.pdf
projectmanagement-123765482.pdfprojectmanagement-123765482.pdf
projectmanagement-123765482.pdf
AmarDeo7
 
Course Assignment: Financing and Initiating Major Engineering Projects
Course Assignment: Financing and Initiating Major Engineering ProjectsCourse Assignment: Financing and Initiating Major Engineering Projects
Course Assignment: Financing and Initiating Major Engineering Projects
Fragoso Josue Muhae
 
Stephanus Roux_Senior Project Manager
Stephanus Roux_Senior Project ManagerStephanus Roux_Senior Project Manager
Stephanus Roux_Senior Project Manager
Stephanus Roux C Eng , IntPE(uk) , FIET
 
022 a construction productivity (2)
022 a construction productivity (2)022 a construction productivity (2)
022 a construction productivity (2)
Dr Fereidoun Dejahang
 
Project management case study.pptx
Project management case study.pptxProject management case study.pptx
Project management case study.pptx
DrRRajalakshmi
 
Project management
Project managementProject management
Project management
twilight89
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-controlJatindra Malik
 
HISTORY OF PROJECT MANAGEMENT & (1).pptx
HISTORY OF PROJECT MANAGEMENT & (1).pptxHISTORY OF PROJECT MANAGEMENT & (1).pptx
HISTORY OF PROJECT MANAGEMENT & (1).pptx
AaleenKttk
 
Introduction to international project management
Introduction to international project managementIntroduction to international project management
Introduction to international project management
prakashnachnani
 

Similar to Summary chunnel tunnel project management (20)

PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE
 
Warrington Western Link, Robert Holloway
Warrington Western Link, Robert HollowayWarrington Western Link, Robert Holloway
Warrington Western Link, Robert Holloway
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
BASICS OF PROJECT MANAGEMENT
BASICS OF PROJECT MANAGEMENTBASICS OF PROJECT MANAGEMENT
BASICS OF PROJECT MANAGEMENT
 
57086 01 introduction
57086 01 introduction57086 01 introduction
57086 01 introduction
 
slides
slidesslides
slides
 
How to setup and lead a successfully PMO
How to setup and lead a successfully PMOHow to setup and lead a successfully PMO
How to setup and lead a successfully PMO
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
Managing Project Transitions
Managing Project TransitionsManaging Project Transitions
Managing Project Transitions
 
projectmanagement-123765482.pdf
projectmanagement-123765482.pdfprojectmanagement-123765482.pdf
projectmanagement-123765482.pdf
 
Course Assignment: Financing and Initiating Major Engineering Projects
Course Assignment: Financing and Initiating Major Engineering ProjectsCourse Assignment: Financing and Initiating Major Engineering Projects
Course Assignment: Financing and Initiating Major Engineering Projects
 
London 2012 Olympics, Managing and controlling contingency
London 2012 Olympics, Managing and controlling contingencyLondon 2012 Olympics, Managing and controlling contingency
London 2012 Olympics, Managing and controlling contingency
 
Stephanus Roux_Senior Project Manager
Stephanus Roux_Senior Project ManagerStephanus Roux_Senior Project Manager
Stephanus Roux_Senior Project Manager
 
022 a construction productivity (2)
022 a construction productivity (2)022 a construction productivity (2)
022 a construction productivity (2)
 
Project management case study.pptx
Project management case study.pptxProject management case study.pptx
Project management case study.pptx
 
Project management
Project managementProject management
Project management
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
 
HISTORY OF PROJECT MANAGEMENT & (1).pptx
HISTORY OF PROJECT MANAGEMENT & (1).pptxHISTORY OF PROJECT MANAGEMENT & (1).pptx
HISTORY OF PROJECT MANAGEMENT & (1).pptx
 
Introduction to international project management
Introduction to international project managementIntroduction to international project management
Introduction to international project management
 

Recently uploaded

TCS AI for Business Study – Key Findings
TCS AI for Business Study – Key FindingsTCS AI for Business Study – Key Findings
TCS AI for Business Study – Key Findings
Tata Consultancy Services
 
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
gcljeuzdu
 
Training- integrated management system (iso)
Training- integrated management system (iso)Training- integrated management system (iso)
Training- integrated management system (iso)
akaash13
 
Founder-Game Director Workshop (Session 1)
Founder-Game Director  Workshop (Session 1)Founder-Game Director  Workshop (Session 1)
Founder-Game Director Workshop (Session 1)
Amir H. Fassihi
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
Muhammad Adil Jamil
 
W.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest ExperienceW.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest Experience
William (Bill) H. Bender, FCSI
 
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
juniourjohnstone
 
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docxModern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
ssuserf63bd7
 
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
CIOWomenMagazine
 

Recently uploaded (9)

TCS AI for Business Study – Key Findings
TCS AI for Business Study – Key FindingsTCS AI for Business Study – Key Findings
TCS AI for Business Study – Key Findings
 
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
 
Training- integrated management system (iso)
Training- integrated management system (iso)Training- integrated management system (iso)
Training- integrated management system (iso)
 
Founder-Game Director Workshop (Session 1)
Founder-Game Director  Workshop (Session 1)Founder-Game Director  Workshop (Session 1)
Founder-Game Director Workshop (Session 1)
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
 
W.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest ExperienceW.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest Experience
 
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
 
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docxModern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
 
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
 

Summary chunnel tunnel project management

  • 1. CASE STUDY ON CHUNNEL TUNNEL PROJECT Team 5
  • 2. Overview: • Designed to create spur in Economic Development • Improve the trade relations with alternate high speed transportation • One of the largest privately funded construction Project between two countries • 51.5 Km long double rail tunnel. • Project was initially estimated at 5.5 Billion dollars on completion the cost increased to 14.9 Billion dollars Chunnel Tunnel Group/French Manche (BOT basis) Transmanche Link (TML) (Construction) French and British Govts.,
  • 3. Scope Management Inception • Lack of defined scope • Scope defined in Lump sum basis • Difficulty in Resource planning • Formation of IGC Development • Enormous scope • Measures to prevent the scope creep was not put in place • Project Planning, cost estimation, Funding was affected due to scope change Implementation • IGC had major control over scope • Frequent change in scope • Door and A/c System contributed to major scope changes Closeout • Even when the tunnel was deemed to complete, there were discrepancies over scope of some works. Rating : 2 2 2 22
  • 4. Time Management Inception • Hasty Bidding and concept development • Not enough time provided to complete detailed design studies Development • Change in requirement by IGC caused delay • Approval of drawings mandated from both governments • Very good tracking with hefty status report Implementation • Faster Tunneling • Rail and car systems were delivered late • Alteration of passenger door sizes caused delay for 9 months. Closeout • Cascading effects of previous phases • 19 month delay • Project management team could not be held responsible Rating : 3 3 3 2 2
  • 5. Cost Management Inception • Estimated cost of USD 5.5 bn. • Initial Cost Estimates were not detailed out. • Financing arranged via equity and capital market Development • USD 2.25 Bn claim against Eutotunnel by contractor was not anticipated • Use of sophesticted equipment not anticipated Implementation • Unnecessary use of costly technologies in some cases like grouting. • Wrong selection of TBM. Closeout • Efforts were driven towards settlemnt of claims rather than analysing on sources of cost overrun. Rating : 2 1 2 1 2
  • 6. Quality Management Inception • Difference in standards -> Higher standard • Latest laser and computer technology proposed to bore the tunnel. Development • Good PAC was framed. • No margin for errors • Formation of IGC Implementation • Stringent requirements from IGC • Very high accuracy maintained. Closeout • Quality parameters achieved were above industry average. Rating : 5 4 5 5 5
  • 7. Human Resources Management Inception • Team work envisaged • Good structure with proper responsibilities formed. Development • Every British team member had French counter part Implementation • Managed 15,000 workers in good manner • Workers from different cultures were engaged with high level of efficiency Closeout • Most of the persons were demotivated due to non settlement of claims. • Win-win situation was lost Rating : 3 3 3 2 3
  • 8. Communications Management Inception • Difference in languages of two countries Development • Limited communication between two teams since both of them were trying to meet in middle. • This lead to difference of opinion at later stages Implementation • Delay in communication regarding specification change. Closeout • Negotiations not proper at Closeout since bankers did not settle for claims. Rating : 2 3 3 1 2
  • 9. Risk Management Inception • Technical risk only considered • Process and approval risk were not envisaged • Both governments denied to provide financial guarantee. • Social cost benefit analysis not done. Development • Over management of risk – advanced techniques considered • Contingencies and margins were barest mimimum. • Contractors forced to consider best situation. • Risk assessment plan was not made. Implementation • Fast tracking of design and construction processes done without risk analysis. • New unproven technology increased risk • Banks were involved for minimising the risk, however IGC was controlling. Closeout • Courts ruled in favour of contractor. Rating : 2 2 2 2 2
  • 10. Procurement Management Inception • Rigorous time constraints caused hasty procurement plan/contracts. • Procurement of rolling stock and associated major equipment finalised on cost plus percentage fee basis Development • Procurement delayed since scope/ specification was changing. Implementation • Fixed price contracts with several contractors • Differences in goals since many contractors were having equity. Closeout • Cascading effect of implementation created 17 months delay. • Non settlement of extra claims Rating : 2 2 2 2 3
  • 11. Integration Management Inception • Various international agencies took part for conceptualisation. • Mistrust among agencies since both govts didn’t provide guarantee but placed requirements. Development • 46 contractors were deployed for design • 7 Lakh shareholders, 220 Lending banks were involved for financing. Implementation • Huge resources, huge scope of work were managed in best of industry standards. • Logistical and communication challenges. Close out • Teams not integrated due to poor communication. • Each party tried to focus on their own interests. • International chamber of commerce engaged for dispute resolution Rating : 3 2 3 2 3
  • 12. Project Management Area Inception Phase Developme nt Phase Implementa tion Phase Closeout Phase Average Scope Mgt 2 2 2 2 2 Time Mgt 3 3 2 2 3 Cost Mgt 1 2 2 1 2 Quality Mgt 4 5 5 5 5 HRM 3 3 3 2 3 Communications Mgt 3 3 2 1 2 Risk Mgt 2 2 2 2 2 Procurement Mgt 2 2 3 2 2 Integration Mgt 2 3 3 2 3 Rating Scale - Summary Rating Scale : 5-Excellent, 4- Very Good, 3- Good, 2- Poor, 1- Very Poor
  • 13. Key Dates Year Key Developments 1802 Albert Mathieu put forward a cross channel proposal 1875 Channel Tunnel Company Ltd began preliminary trials 1882 Experimental work on both sides of the Channel started but soon idea was abandoned citing national defense security. 1975 A UK–France government backed scheme that started in 1974 was cancelled 1984 British & French govt. agreed to common safety, environmental & security concern, prior opening up the project to bidder 1985 British & French govt. asked for proposals. 1986 Project awarded to Eurotunnel on BOOT basis with 55 year concession period with initial cost of US$ 5.5 billion. June 1988 In France, first tunneling was started December 1988 Tunneling operation was started in UK May 1994 Tunnel was formally inaugurated & started functioning. Project was completed with cost & time over run.
  • 14. Major Area of Strength Managing this Project QUALITY MANAGEMENT • Quality management was implemented successfully. • Technical expertise . TEAM WORK • Excellent team work between two groups. • Construction of tunnel completed 3 months ahead of schedule. • Project office support was excellent. SAFETY MANAGEMENT • Accidents below industry average. • 15000 workmen, numerous engineers, handled precisely.
  • 15. Major Opportunities for improvement from Management P.O.V SCOPE MANAGEMENT • Detailed Functional requirement & Technical specification • Consideration of Scope contingency CONTRACT MANAGEMENT • Applicability of Single Contract to both group. • Coverage of risk exposures COMMUNICATION MANAGEMENT • Communication protocol preparation • Protocol for escalating unresolved / pending issue • Tracking & monitoring
  • 16. Major Opportunities for improvement from Management P.O.V (cont.) RISK MANAGEMENT • Project process & approval risk was overlooked. • Not prepared to handle the degree of IGC supervision & change management controls. • Contingencies for known & unknown risk & a strategy for handling change management missing. COST MANAGEMENT • Use a standardized change-control management to eliminate cost considerations issues imposed by out-of-control-change management control processes. • Specification and validation of functional and technical requirements at front. • Replacement of material, equipment with alternate option of same specification. STAKEHOLDER MANAGEMENT • Project Stakeholder management plan was not prepared in detailed and also not followed throughout project life cycle. By implementing this, variance in cost, schedule and extra claims could have been minimized.
  • 17. Major Project Management Lessons learned Review past engineering studies & take them in consideration Technical as well functional aspects of project management should be given equal importance Detailed risk analysis required in inception stage & needs to be tracked, monitored during PLC of project
  • 18. Major Project Management Lessons learned Maintaining communication throughout the life of project yields better operational project results. In large international construction projects of the involving countries, Govt. support & communication channels should be roped in. Whole hearted effort to be made right from the inception of project in order to avoid adverse situation at the end
  • 19. Conclusion: • Time Over run – 19 months delay • Cost Over run – USD 9.4 Bn • Trail of unhappy investors and stakeholders • Key learnings • Modern Engineering Marvel • Undoubted Public benefit