SlideShare a Scribd company logo
PHASE II : THE DEVELOPMENT
PHASE
THE CHUNNEL TUNNEL
PROJECT
BRIEF INTRODUCTION
1. Introduction to Chunnel Project
2. Introduction to Development Phase of the Project
2
CHUNNEL PROJECT
DEVELOPMENT PHASE
CHANNEL + TUNNEL =
CHUNNEL
3
CHUNNEL PROJECT
DEVELOPMENT PHASE
Chunnel Project : Introduction
“The Channel Tunnel (Chunnel) Project was
launched to create a connection between
England and France via dedicated
underground tunnel”
 Scope of the Project:
 To create a fixed transportation link between
England and France
 Objective of the Project:
 To spur economic development in the region
 Improve European trade environment
 Provide alternative high speed transportation
method
4
CHUNNEL PROJECT
DEVELOPMENT PHASE
Chunnel Project : Introduction
 The Channel Tunnel comprises three tunnels -
two main rail tunnels : Northbound and
Southbound; with a service tunnel of smaller
diameter passing from in between them
5
CHUNNEL PROJECT
DEVELOPMENT PHASE
Chunnel Project : Contracts
6
CHUNNEL PROJECT
DEVELOPMENT PHASE
Chunnel Project : Life Cycle
 Inception Phase:
Historical background, nature of project, political
climate and pre-feasibility studies.
 Development Phase:
Planning, financing and conceptual designing.
 Implementation Phase:
Detailed
designing, construction, installation, testing and
commissioning.
 Closeout Phase:
Overall performance, settlement of
claims, financial status and post-project
evaluation.7
CHUNNEL PROJECT
DEVELOPMENT PHASE
Chunnel Project : Development
Ph.
 Development may also be interpreted as
planning, scheduling, design and primary
engineering.
 It address development of plan for various project
parameters i.e. risk, quality, resources etc.
 It includes finalizing the project charter and
obtaining approval to proceed with the project.
“This was an important phase for the project
because of the sheer size and complexity of
the project”
8
CHUNNEL PROJECT
DEVELOPMENT PHASE
Chunnel Project : Development
Ph.
Some Critical Aspects in Development Phase:
 Massive communication barriers
 Problems due to huge scope of the project
 IGC played critical and detrimental role
 Cost management
 Banks played an influential role from the beginning
 Well worked out schedules, but project still
faltered on the delivery date
 Better risk management could have been done
9
CHUNNEL PROJECT
DEVELOPMENT PHASE
CASE ASSESSMENT
QUESTION 01:
Evaluation of Project Management
During Development Phase
10
CHUNNEL PROJECT
DEVELOPMENT PHASE
INCEPTION
PHASE
DEVELOPMENT
PHASE
EXECUTION
PHASE
CLOSE-OUT
PHASE
Development Phase:
Scope Management
 Lack of a Define Scope made lots of things
difficult, viz. – resource planning, cost estimating
and budgeting.
 This factor alone would have placed the scope
management at the rating level of very poor but
for the quarterly status reports it got placed at
poor level.
 The status report, prepared every three
months, for the investors contributed to keeping
the project somewhat on track.
11
CHUNNEL PROJECT
DEVELOPMENT PHASE
Development Phase:
Time Management
 The schedule planning during the development
phase was more or less adequate.
 True the project finished a year later than it was
due but it was often because of things beyond the
project management team‟s control.
 Hence, the project management team couldn’t
be held wholly responsible for improper time
management and hence placed at an average
rating of good.
12
CHUNNEL PROJECT
DEVELOPMENT PHASE
Development Phase:
Cost Management
 Scope Creep played a large part in the
substantial increase from its initial cost estimates
 IGC was allowed to have a scope control without
the ability to approve additional funding
 At times an over-management of risks led to
unnecessary expenses which could have been
avoided
 Based on the above mentioned factor, Cost
Management is placed at the lowly rating of
very poor
13
CHUNNEL PROJECT
DEVELOPMENT PHASE
Development Phase:
Quality Management
 IGC mandated – „whenever a difference occurred
in standards between the two countries, the
higher of the two standards kept‟
 Most advanced technological equipment and very
little margin for error allowed for quality to be an
extremely important attribute while planning
during this phase
 Thus IGC’s involvement made a huge impact
on the quality management of the project but
adversely affected other areas and the phase
received a high rating of very good but not an
excellent rating
14
CHUNNEL PROJECT
DEVELOPMENT PHASE
Development Phase:
Human Resource Management
 For every British team member, the French had a
matching counterpart
 IGC was also a part of this factor and IGC played
an important role in maintaining the quality of the
project
 Teamwork was helped by the focus on fairness
that was followed by the two governments
involved
 All these above mentioned justify the very good
rating given to the human resource
management factor for this phase
15
CHUNNEL PROJECT
DEVELOPMENT PHASE
Development Phase:
Communications Management
 Communication between the French and English
side was limited
 Each side worked toward a goal and did not feel
the need to communicate because the
assumption was that they were both working
towards meeting in the middle
 Just because, they were clear about the
objective and initial communication was
good, the rating for this phase is put at poor
and not very poor
 This factor of project management can be
summarized as the following chart on the next
slide
16
CHUNNEL PROJECT
DEVELOPMENT PHASE
Development Phase:
Communications Management
17
CHUNNEL PROJECT
DEVELOPMENT PHASE
Two Countries Two Languages
Two Governments Two Standards
Communication
Issues
were a result of:
This resulted in:
LIMITED INTERNAL
COMMUNICATION
Development Phase:
Risk Management
 Risk could have been better researched and
evaluated when it came to the technical side of
the project
 At times there were cases of over managing risk
which led to cost increases and delays
 At the same time, leeway given to the banks –
focus shifted to minimizing risks, which worked in
the project‟s favor until it was taken to the
extremes
 For the aforementioned reason, risk
management for the phase has been given a
good rating18
CHUNNEL PROJECT
DEVELOPMENT PHASE
Development Phase:
Procurement Management
 Over management of risks led to use of
sophisticated and advanced
equipment, procurement of which was handled
well
 IGC‟s involvement and mandatory – “better of the
two methods”, made it necessary for the team to
procure advanced technological equipments and
maintain quality – which was again handled very
well
 But of course, this resulted in increased costs
 Hence it is safe to give a rating of very good to
the procurement management factor of the
phase
19
CHUNNEL PROJECT
DEVELOPMENT PHASE
Development Phase:
Integration Management
 Teamwork concept was sidelined when the two
governments refused to guarantee the project
financially
 Two teams working on opposite ends didn‟t feel
the need to communicate and integrate leading to
differences in opinions in project‟s later stages
 These factors prove the lack of integration
between the teams on the two ends and hence a
low rating of poor
20
CHUNNEL PROJECT
DEVELOPMENT PHASE
PROJECT MANAGEMENT AREA RATING
Scope Management 2
Time Management 3
Cost Management 1
Quality Management 4
Human Resource Management 4
Communications Management 2
Risk Management 3
Procurement Management 4
Integration Management 2
Average Rating for the Phase 2.78 ~ 3 (approx.)
CHUNNEL PROJECT
DEVELOPMENT PHASE21
Rating Scale:
5:Excellent 4:Very Good 3:Good 2:Poor
1:Very Poor
CASE ASSESSMENT
QUESTION 02:
Major Areas of Strength
During Development Phase
22
CHUNNEL PROJECT
DEVELOPMENT PHASE
INCEPTION
PHASE
DEVELOPMENT
PHASE
EXECUTION
PHASE
CLOSE-OUT
PHASE
Development Phase:
Major Areas of Strength
 Quality Management
The project was delivered with a relatively high
degree of quality because the free reign given to
the IGC
 Project Office
The project office did an adequate job and
followed the planning, designing and retailing
phases required in this phase of project. Project
management in this phase was hopeful and
project management practices in place did
provide an mechanism for achieving success
23
CHUNNEL PROJECT
DEVELOPMENT PHASE
Development Phase:
Major Areas of Strength
 Project Team
The project team did a very reasonable job in
planning the technical equipment and
understanding the complexity involved
 Team Work
The focus on fairness was followed by the both
governments involved (teamwork concept was
lost in later phases)
 Planning and Scheduling
The schedule planning during the development
phase seemed to be adequate - the project
finished a year late but due to things beyond the
project team control24
CHUNNEL PROJECT
DEVELOPMENT PHASE
CASE ASSESSMENT
QUESTION 03:
Major Opportunities for Improvement
During Development Phase
25
CHUNNEL PROJECT
DEVELOPMENT PHASE
INCEPTION
PHASE
DEVELOPMENT
PHASE
EXECUTION
PHASE
CLOSE-OUT
PHASE
Development Phase:
Major Opportunities for Improvement
 Communication
Communication plays a very vital role in a
project, not only for the project managers but also
for the rest of the team members - this is one of
the factors driving a project to success or failure
 Control Given to IGC
There was much debate on the free reign given to
IGC because of the delays and cost increments
caused by the decisions of IGC
26
CHUNNEL PROJECT
DEVELOPMENT PHASE
Development Phase:
Major Opportunities for Improvement
 Technical Specifications
Scope, functional requirement and technical
specifications need to be defined and validated at
an early stage - although the data from past
projects was taken into account and studies, the
learning from those projects was not implemented
when planning of the project was being done;
because of need to do too much in too little time
 Risk Management
Risk management definitely needed looking into
because it was either over managed or under
managed27
CHUNNEL PROJECT
DEVELOPMENT PHASE
CONCLUSION
Key Lessons Learnt
From The Development Phase
28
CHUNNEL PROJECT
DEVELOPMENT PHASE
Development Phase:
Key Lessons Learnt
 Scope needs to be properly defined at the very
beginning to avoid delays
 Technical and Functional Requirements need to
be given due and equal importance and lessons
learnt from earlier projects need proper
implementation (wherever required) while
planning for a complex project like Chunnel
Project
 Communication plays a major role in the success
of a project – it can lead the project either on the
road to success or failure
29
CHUNNEL PROJECT
DEVELOPMENT PHASE
THANK YOU…
Presented By: Khyati G. Tewari
30
CHUNNEL PROJECT
DEVELOPMENT PHASE

More Related Content

What's hot

The Chunnel Project - Quality Management
The Chunnel Project - Quality ManagementThe Chunnel Project - Quality Management
The Chunnel Project - Quality Management
Milind_jagtap_
 
Pmp communication chapter 10
Pmp communication chapter 10Pmp communication chapter 10
Pmp communication chapter 10
Ahmed Elshaboury,PMP,LEED GA
 
Project management basics
Project management basicsProject management basics
Project management basics
Planning School
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
Mohamed Loey
 
11. Project Communication Management
11. Project Communication Management11. Project Communication Management
11. Project Communication Management
BhuWan Khadka
 
Project charter-template
Project charter-templateProject charter-template
Project management
Project managementProject management
Project management
meena velmurugan
 
Project Management Framework - PMBOK 5
Project Management Framework - PMBOK 5Project Management Framework - PMBOK 5
Project Management Framework - PMBOK 5
pankajsh10
 
Project Resource Management
Project Resource ManagementProject Resource Management
Project Resource Management
Crysanthus Raharjo, PMP
 
Project audit & closure
Project audit & closureProject audit & closure
Project audit & closure
Gopalakrishnan P
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoringharoldtaylor1113
 
Project communications management
Project communications managementProject communications management
Project communications management
Prabudh Dhingra
 
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHIC
PMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHICPMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHIC
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHIC
Jonathan Donado
 
Project Management:Life Cycle & Phases.
Project Management:Life Cycle & Phases.Project Management:Life Cycle & Phases.
Project Management:Life Cycle & Phases.
Ashutosh Mishra
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
NAVNEET KUMAR JHA
 
Project Management Best Practices - Tips and Techniques
Project Management Best Practices  - Tips and TechniquesProject Management Best Practices  - Tips and Techniques
Project Management Best Practices - Tips and Techniques
Invensis Learning
 
Risk management
Risk managementRisk management
Risk management
nashaat algrara
 
Project communication management
Project communication managementProject communication management
Project communication management
Preshan Pradeepa
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
Michael Pink
 

What's hot (20)

The Chunnel Project - Quality Management
The Chunnel Project - Quality ManagementThe Chunnel Project - Quality Management
The Chunnel Project - Quality Management
 
Pmp communication chapter 10
Pmp communication chapter 10Pmp communication chapter 10
Pmp communication chapter 10
 
Project management basics
Project management basicsProject management basics
Project management basics
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
 
Project termination
Project terminationProject termination
Project termination
 
11. Project Communication Management
11. Project Communication Management11. Project Communication Management
11. Project Communication Management
 
Project charter-template
Project charter-templateProject charter-template
Project charter-template
 
Project management
Project managementProject management
Project management
 
Project Management Framework - PMBOK 5
Project Management Framework - PMBOK 5Project Management Framework - PMBOK 5
Project Management Framework - PMBOK 5
 
Project Resource Management
Project Resource ManagementProject Resource Management
Project Resource Management
 
Project audit & closure
Project audit & closureProject audit & closure
Project audit & closure
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoring
 
Project communications management
Project communications managementProject communications management
Project communications management
 
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHIC
PMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHICPMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHIC
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHIC
 
Project Management:Life Cycle & Phases.
Project Management:Life Cycle & Phases.Project Management:Life Cycle & Phases.
Project Management:Life Cycle & Phases.
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
Project Management Best Practices - Tips and Techniques
Project Management Best Practices  - Tips and TechniquesProject Management Best Practices  - Tips and Techniques
Project Management Best Practices - Tips and Techniques
 
Risk management
Risk managementRisk management
Risk management
 
Project communication management
Project communication managementProject communication management
Project communication management
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 

Viewers also liked

Channel Tunnel
Channel TunnelChannel Tunnel
Channel TunnelTim Howell
 
Project development new1
Project development new1Project development new1
Project development new1David mbwiga
 
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
peter747
 
Project development cycle
Project development cycleProject development cycle
Project development cycle
Aswin prakash i , Xantus Technologies
 
Taking the Creep Out of Scope Creep
Taking the Creep Out of Scope CreepTaking the Creep Out of Scope Creep
Taking the Creep Out of Scope Creep
Computer Aid, Inc
 
Project management
Project managementProject management
Project management
Jaya Velagapudi
 
Khan Project Scope Creep Presentationin Pdf
Khan   Project Scope Creep Presentationin PdfKhan   Project Scope Creep Presentationin Pdf
Khan Project Scope Creep Presentationin Pdf
ZahidKhan007
 
Maharashtra State_Building bye laws (Gist)
Maharashtra State_Building bye laws (Gist)Maharashtra State_Building bye laws (Gist)
Maharashtra State_Building bye laws (Gist)Khyati Tewari
 
Project development
Project developmentProject development
Project development
Polly Cooper
 
Presentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics ProjectPresentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics ProjectSharad Srivastava
 
Project Development
Project Development Project Development
Project Development
Jo Balucanag - Bitonio
 
Steve Jobs' LEAN STARTUP PROJECT MANAGEMENT: How Steve Jobs Planned, Organize...
Steve Jobs' LEAN STARTUP PROJECT MANAGEMENT: How Steve Jobs Planned, Organize...Steve Jobs' LEAN STARTUP PROJECT MANAGEMENT: How Steve Jobs Planned, Organize...
Steve Jobs' LEAN STARTUP PROJECT MANAGEMENT: How Steve Jobs Planned, Organize...
Rod King, Ph.D.
 
TRAINING DESIGN
TRAINING DESIGNTRAINING DESIGN
TRAINING DESIGN
Nilesh Rajput
 
United colors of benetton
United colors of benettonUnited colors of benetton
United colors of benetton
Swati Kaushik
 

Viewers also liked (15)

Channel Tunnel
Channel TunnelChannel Tunnel
Channel Tunnel
 
Project development new1
Project development new1Project development new1
Project development new1
 
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
 
Project development cycle
Project development cycleProject development cycle
Project development cycle
 
Taking the Creep Out of Scope Creep
Taking the Creep Out of Scope CreepTaking the Creep Out of Scope Creep
Taking the Creep Out of Scope Creep
 
Project management
Project managementProject management
Project management
 
Channel tunnel
Channel tunnelChannel tunnel
Channel tunnel
 
Khan Project Scope Creep Presentationin Pdf
Khan   Project Scope Creep Presentationin PdfKhan   Project Scope Creep Presentationin Pdf
Khan Project Scope Creep Presentationin Pdf
 
Maharashtra State_Building bye laws (Gist)
Maharashtra State_Building bye laws (Gist)Maharashtra State_Building bye laws (Gist)
Maharashtra State_Building bye laws (Gist)
 
Project development
Project developmentProject development
Project development
 
Presentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics ProjectPresentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics Project
 
Project Development
Project Development Project Development
Project Development
 
Steve Jobs' LEAN STARTUP PROJECT MANAGEMENT: How Steve Jobs Planned, Organize...
Steve Jobs' LEAN STARTUP PROJECT MANAGEMENT: How Steve Jobs Planned, Organize...Steve Jobs' LEAN STARTUP PROJECT MANAGEMENT: How Steve Jobs Planned, Organize...
Steve Jobs' LEAN STARTUP PROJECT MANAGEMENT: How Steve Jobs Planned, Organize...
 
TRAINING DESIGN
TRAINING DESIGNTRAINING DESIGN
TRAINING DESIGN
 
United colors of benetton
United colors of benettonUnited colors of benetton
United colors of benetton
 

Similar to Chunnel Project_Development Phase

Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptx
FawadAfridi6
 
Ppt project mgt. syllabus
Ppt project mgt.  syllabusPpt project mgt.  syllabus
Ppt project mgt. syllabus
Drneetu2
 
project management (1).pdf
project management (1).pdfproject management (1).pdf
project management (1).pdf
Shree Bhargava and Associate
 
Running head FINAL ASSIGNMENT1FINAL ASSIGNMENT.docx
Running head FINAL ASSIGNMENT1FINAL ASSIGNMENT.docxRunning head FINAL ASSIGNMENT1FINAL ASSIGNMENT.docx
Running head FINAL ASSIGNMENT1FINAL ASSIGNMENT.docx
cowinhelen
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
PRIYANSHU KUMAR
 
Here are 5 phases of project management professional .pdf
Here are 5 phases of  project management professional .pdfHere are 5 phases of  project management professional .pdf
Here are 5 phases of project management professional .pdf
arjunnegi34
 
Project Life Cycle final.pptx
Project Life Cycle final.pptxProject Life Cycle final.pptx
Project Life Cycle final.pptx
PranshiGoyal2
 
Addressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsAddressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega Projects
Ibrahim Al-Hudhaif
 
Project lifecycle in IT industry
Project lifecycle in IT industryProject lifecycle in IT industry
Project lifecycle in IT industry
sharansankarasigamani
 
Wind energy Project Strategy revised
Wind energy Project Strategy revisedWind energy Project Strategy revised
Wind energy Project Strategy revised
leif2016
 
Project XYC Project PlanEric Malone, Jennifer Napier, .docx
Project XYC  Project PlanEric Malone, Jennifer Napier, .docxProject XYC  Project PlanEric Malone, Jennifer Napier, .docx
Project XYC Project PlanEric Malone, Jennifer Napier, .docx
wkyra78
 
Project Management SIBPM
Project Management SIBPMProject Management SIBPM
Project Management SIBPM
DR. SHAJAHAN mba phd
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
SAJID ALI RUK
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedWaqar Ahmed
 
RISK MANAGEMENT PLAN SCOPE AND IDENTIFICATION5Christopher Mi.docx
RISK MANAGEMENT PLAN SCOPE AND IDENTIFICATION5Christopher Mi.docxRISK MANAGEMENT PLAN SCOPE AND IDENTIFICATION5Christopher Mi.docx
RISK MANAGEMENT PLAN SCOPE AND IDENTIFICATION5Christopher Mi.docx
SUBHI7
 
Session four- project execution.pptx
Session four- project execution.pptxSession four- project execution.pptx
Session four- project execution.pptx
yuduf1
 
The Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project SuccessThe Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project Success
IRJET Journal
 
PM.pdf
PM.pdfPM.pdf
PM.pdf
PM.pdfPM.pdf
PM office this fueje se siehesjksjrwl jsmsof india.pdf
PM office this fueje se siehesjksjrwl jsmsof india.pdfPM office this fueje se siehesjksjrwl jsmsof india.pdf
PM office this fueje se siehesjksjrwl jsmsof india.pdf
gauravkumar4594
 

Similar to Chunnel Project_Development Phase (20)

Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptx
 
Ppt project mgt. syllabus
Ppt project mgt.  syllabusPpt project mgt.  syllabus
Ppt project mgt. syllabus
 
project management (1).pdf
project management (1).pdfproject management (1).pdf
project management (1).pdf
 
Running head FINAL ASSIGNMENT1FINAL ASSIGNMENT.docx
Running head FINAL ASSIGNMENT1FINAL ASSIGNMENT.docxRunning head FINAL ASSIGNMENT1FINAL ASSIGNMENT.docx
Running head FINAL ASSIGNMENT1FINAL ASSIGNMENT.docx
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Here are 5 phases of project management professional .pdf
Here are 5 phases of  project management professional .pdfHere are 5 phases of  project management professional .pdf
Here are 5 phases of project management professional .pdf
 
Project Life Cycle final.pptx
Project Life Cycle final.pptxProject Life Cycle final.pptx
Project Life Cycle final.pptx
 
Addressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsAddressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega Projects
 
Project lifecycle in IT industry
Project lifecycle in IT industryProject lifecycle in IT industry
Project lifecycle in IT industry
 
Wind energy Project Strategy revised
Wind energy Project Strategy revisedWind energy Project Strategy revised
Wind energy Project Strategy revised
 
Project XYC Project PlanEric Malone, Jennifer Napier, .docx
Project XYC  Project PlanEric Malone, Jennifer Napier, .docxProject XYC  Project PlanEric Malone, Jennifer Napier, .docx
Project XYC Project PlanEric Malone, Jennifer Napier, .docx
 
Project Management SIBPM
Project Management SIBPMProject Management SIBPM
Project Management SIBPM
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javed
 
RISK MANAGEMENT PLAN SCOPE AND IDENTIFICATION5Christopher Mi.docx
RISK MANAGEMENT PLAN SCOPE AND IDENTIFICATION5Christopher Mi.docxRISK MANAGEMENT PLAN SCOPE AND IDENTIFICATION5Christopher Mi.docx
RISK MANAGEMENT PLAN SCOPE AND IDENTIFICATION5Christopher Mi.docx
 
Session four- project execution.pptx
Session four- project execution.pptxSession four- project execution.pptx
Session four- project execution.pptx
 
The Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project SuccessThe Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project Success
 
PM.pdf
PM.pdfPM.pdf
PM.pdf
 
PM.pdf
PM.pdfPM.pdf
PM.pdf
 
PM office this fueje se siehesjksjrwl jsmsof india.pdf
PM office this fueje se siehesjksjrwl jsmsof india.pdfPM office this fueje se siehesjksjrwl jsmsof india.pdf
PM office this fueje se siehesjksjrwl jsmsof india.pdf
 

More from Khyati Tewari

REAL ESTATE REGULATORY AUTHORITY (RERA) ACT 2016
REAL ESTATE REGULATORY AUTHORITY (RERA) ACT 2016REAL ESTATE REGULATORY AUTHORITY (RERA) ACT 2016
REAL ESTATE REGULATORY AUTHORITY (RERA) ACT 2016
Khyati Tewari
 
Bhuj : A Living Cultural Heritage
Bhuj : A Living Cultural HeritageBhuj : A Living Cultural Heritage
Bhuj : A Living Cultural Heritage
Khyati Tewari
 
Air : A Vital Resource
Air : A Vital ResourceAir : A Vital Resource
Air : A Vital Resource
Khyati Tewari
 
Bye Laws and City Planning
Bye Laws and City PlanningBye Laws and City Planning
Bye Laws and City Planning
Khyati Tewari
 
Delhi : A City of Cities
Delhi : A City of CitiesDelhi : A City of Cities
Delhi : A City of Cities
Khyati Tewari
 
Housing Typology of Vadodara
Housing Typology of VadodaraHousing Typology of Vadodara
Housing Typology of Vadodara
Khyati Tewari
 
Changing Social Scenario of Por Village
Changing Social Scenario of Por VillageChanging Social Scenario of Por Village
Changing Social Scenario of Por Village
Khyati Tewari
 

More from Khyati Tewari (8)

REAL ESTATE REGULATORY AUTHORITY (RERA) ACT 2016
REAL ESTATE REGULATORY AUTHORITY (RERA) ACT 2016REAL ESTATE REGULATORY AUTHORITY (RERA) ACT 2016
REAL ESTATE REGULATORY AUTHORITY (RERA) ACT 2016
 
Bhuj : A Living Cultural Heritage
Bhuj : A Living Cultural HeritageBhuj : A Living Cultural Heritage
Bhuj : A Living Cultural Heritage
 
Air : A Vital Resource
Air : A Vital ResourceAir : A Vital Resource
Air : A Vital Resource
 
Bye Laws and City Planning
Bye Laws and City PlanningBye Laws and City Planning
Bye Laws and City Planning
 
Delhi : A City of Cities
Delhi : A City of CitiesDelhi : A City of Cities
Delhi : A City of Cities
 
Housing Typology of Vadodara
Housing Typology of VadodaraHousing Typology of Vadodara
Housing Typology of Vadodara
 
Changing Social Scenario of Por Village
Changing Social Scenario of Por VillageChanging Social Scenario of Por Village
Changing Social Scenario of Por Village
 
The lithium fire
The lithium fireThe lithium fire
The lithium fire
 

Recently uploaded

一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
taqyed
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
Ben Wann
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
agatadrynko
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
HumanResourceDimensi1
 
amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05
marketing317746
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
fakeloginn69
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
Lviv Startup Club
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
marketingjdass
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
seoforlegalpillers
 
The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
Adam Smith
 
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).pptENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
zechu97
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
SynapseIndia
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
fisherameliaisabella
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
Sam H
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
DerekIwanaka1
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
Nicola Wreford-Howard
 

Recently uploaded (20)

一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 
amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
 
The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
 
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).pptENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
 

Chunnel Project_Development Phase

  • 1. PHASE II : THE DEVELOPMENT PHASE THE CHUNNEL TUNNEL PROJECT
  • 2. BRIEF INTRODUCTION 1. Introduction to Chunnel Project 2. Introduction to Development Phase of the Project 2 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 3. CHANNEL + TUNNEL = CHUNNEL 3 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 4. Chunnel Project : Introduction “The Channel Tunnel (Chunnel) Project was launched to create a connection between England and France via dedicated underground tunnel”  Scope of the Project:  To create a fixed transportation link between England and France  Objective of the Project:  To spur economic development in the region  Improve European trade environment  Provide alternative high speed transportation method 4 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 5. Chunnel Project : Introduction  The Channel Tunnel comprises three tunnels - two main rail tunnels : Northbound and Southbound; with a service tunnel of smaller diameter passing from in between them 5 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 6. Chunnel Project : Contracts 6 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 7. Chunnel Project : Life Cycle  Inception Phase: Historical background, nature of project, political climate and pre-feasibility studies.  Development Phase: Planning, financing and conceptual designing.  Implementation Phase: Detailed designing, construction, installation, testing and commissioning.  Closeout Phase: Overall performance, settlement of claims, financial status and post-project evaluation.7 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 8. Chunnel Project : Development Ph.  Development may also be interpreted as planning, scheduling, design and primary engineering.  It address development of plan for various project parameters i.e. risk, quality, resources etc.  It includes finalizing the project charter and obtaining approval to proceed with the project. “This was an important phase for the project because of the sheer size and complexity of the project” 8 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 9. Chunnel Project : Development Ph. Some Critical Aspects in Development Phase:  Massive communication barriers  Problems due to huge scope of the project  IGC played critical and detrimental role  Cost management  Banks played an influential role from the beginning  Well worked out schedules, but project still faltered on the delivery date  Better risk management could have been done 9 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 10. CASE ASSESSMENT QUESTION 01: Evaluation of Project Management During Development Phase 10 CHUNNEL PROJECT DEVELOPMENT PHASE INCEPTION PHASE DEVELOPMENT PHASE EXECUTION PHASE CLOSE-OUT PHASE
  • 11. Development Phase: Scope Management  Lack of a Define Scope made lots of things difficult, viz. – resource planning, cost estimating and budgeting.  This factor alone would have placed the scope management at the rating level of very poor but for the quarterly status reports it got placed at poor level.  The status report, prepared every three months, for the investors contributed to keeping the project somewhat on track. 11 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 12. Development Phase: Time Management  The schedule planning during the development phase was more or less adequate.  True the project finished a year later than it was due but it was often because of things beyond the project management team‟s control.  Hence, the project management team couldn’t be held wholly responsible for improper time management and hence placed at an average rating of good. 12 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 13. Development Phase: Cost Management  Scope Creep played a large part in the substantial increase from its initial cost estimates  IGC was allowed to have a scope control without the ability to approve additional funding  At times an over-management of risks led to unnecessary expenses which could have been avoided  Based on the above mentioned factor, Cost Management is placed at the lowly rating of very poor 13 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 14. Development Phase: Quality Management  IGC mandated – „whenever a difference occurred in standards between the two countries, the higher of the two standards kept‟  Most advanced technological equipment and very little margin for error allowed for quality to be an extremely important attribute while planning during this phase  Thus IGC’s involvement made a huge impact on the quality management of the project but adversely affected other areas and the phase received a high rating of very good but not an excellent rating 14 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 15. Development Phase: Human Resource Management  For every British team member, the French had a matching counterpart  IGC was also a part of this factor and IGC played an important role in maintaining the quality of the project  Teamwork was helped by the focus on fairness that was followed by the two governments involved  All these above mentioned justify the very good rating given to the human resource management factor for this phase 15 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 16. Development Phase: Communications Management  Communication between the French and English side was limited  Each side worked toward a goal and did not feel the need to communicate because the assumption was that they were both working towards meeting in the middle  Just because, they were clear about the objective and initial communication was good, the rating for this phase is put at poor and not very poor  This factor of project management can be summarized as the following chart on the next slide 16 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 17. Development Phase: Communications Management 17 CHUNNEL PROJECT DEVELOPMENT PHASE Two Countries Two Languages Two Governments Two Standards Communication Issues were a result of: This resulted in: LIMITED INTERNAL COMMUNICATION
  • 18. Development Phase: Risk Management  Risk could have been better researched and evaluated when it came to the technical side of the project  At times there were cases of over managing risk which led to cost increases and delays  At the same time, leeway given to the banks – focus shifted to minimizing risks, which worked in the project‟s favor until it was taken to the extremes  For the aforementioned reason, risk management for the phase has been given a good rating18 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 19. Development Phase: Procurement Management  Over management of risks led to use of sophisticated and advanced equipment, procurement of which was handled well  IGC‟s involvement and mandatory – “better of the two methods”, made it necessary for the team to procure advanced technological equipments and maintain quality – which was again handled very well  But of course, this resulted in increased costs  Hence it is safe to give a rating of very good to the procurement management factor of the phase 19 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 20. Development Phase: Integration Management  Teamwork concept was sidelined when the two governments refused to guarantee the project financially  Two teams working on opposite ends didn‟t feel the need to communicate and integrate leading to differences in opinions in project‟s later stages  These factors prove the lack of integration between the teams on the two ends and hence a low rating of poor 20 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 21. PROJECT MANAGEMENT AREA RATING Scope Management 2 Time Management 3 Cost Management 1 Quality Management 4 Human Resource Management 4 Communications Management 2 Risk Management 3 Procurement Management 4 Integration Management 2 Average Rating for the Phase 2.78 ~ 3 (approx.) CHUNNEL PROJECT DEVELOPMENT PHASE21 Rating Scale: 5:Excellent 4:Very Good 3:Good 2:Poor 1:Very Poor
  • 22. CASE ASSESSMENT QUESTION 02: Major Areas of Strength During Development Phase 22 CHUNNEL PROJECT DEVELOPMENT PHASE INCEPTION PHASE DEVELOPMENT PHASE EXECUTION PHASE CLOSE-OUT PHASE
  • 23. Development Phase: Major Areas of Strength  Quality Management The project was delivered with a relatively high degree of quality because the free reign given to the IGC  Project Office The project office did an adequate job and followed the planning, designing and retailing phases required in this phase of project. Project management in this phase was hopeful and project management practices in place did provide an mechanism for achieving success 23 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 24. Development Phase: Major Areas of Strength  Project Team The project team did a very reasonable job in planning the technical equipment and understanding the complexity involved  Team Work The focus on fairness was followed by the both governments involved (teamwork concept was lost in later phases)  Planning and Scheduling The schedule planning during the development phase seemed to be adequate - the project finished a year late but due to things beyond the project team control24 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 25. CASE ASSESSMENT QUESTION 03: Major Opportunities for Improvement During Development Phase 25 CHUNNEL PROJECT DEVELOPMENT PHASE INCEPTION PHASE DEVELOPMENT PHASE EXECUTION PHASE CLOSE-OUT PHASE
  • 26. Development Phase: Major Opportunities for Improvement  Communication Communication plays a very vital role in a project, not only for the project managers but also for the rest of the team members - this is one of the factors driving a project to success or failure  Control Given to IGC There was much debate on the free reign given to IGC because of the delays and cost increments caused by the decisions of IGC 26 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 27. Development Phase: Major Opportunities for Improvement  Technical Specifications Scope, functional requirement and technical specifications need to be defined and validated at an early stage - although the data from past projects was taken into account and studies, the learning from those projects was not implemented when planning of the project was being done; because of need to do too much in too little time  Risk Management Risk management definitely needed looking into because it was either over managed or under managed27 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 28. CONCLUSION Key Lessons Learnt From The Development Phase 28 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 29. Development Phase: Key Lessons Learnt  Scope needs to be properly defined at the very beginning to avoid delays  Technical and Functional Requirements need to be given due and equal importance and lessons learnt from earlier projects need proper implementation (wherever required) while planning for a complex project like Chunnel Project  Communication plays a major role in the success of a project – it can lead the project either on the road to success or failure 29 CHUNNEL PROJECT DEVELOPMENT PHASE
  • 30. THANK YOU… Presented By: Khyati G. Tewari 30 CHUNNEL PROJECT DEVELOPMENT PHASE