The Chunnel Project : Introduction
“The Channel Tunnel (Chunnel) project was launched to
create a connection between England and France via
dedicated underground tunnel.
 Scope of the project:
 To create a fixed transportation link between England and France.

 Objective’s of the project:
 To spur economic development in the region.
 Improve European trade environment.
 Provide alternative high speed transportation method.
Project Life Cycle Evaluation:
 Inception Phase: Historical background, nature of
 project, political climate and pre-feasibility studies.

 Development Phase: Planning, financing and conceptual
 designing.

 Implementation Phase: Detailed designing,
 construction, installation, testing and commissioning.

 Closeout Phase: Overall performance, settlement of
 claims, financial status and post-project evaluation.
Inception Phase:
 In 1986 Anglo-French Treaty signed, Transmanche Link (TML) awarded contract and
   Eurotunnel declared owner for 55 years post completion of the project.

 The proposal included a 32 mile double rail tunnel to accommodate both through-trains and
   special car and truck carrying shuttle trains.

 Original cost estimation of the project was 5.5 billion USD which was eventually increased to
   14.9 billion USD.

 Financing was pursued via equity and loan capital markets forming a large scale 7,00,000
   shareholders and a consortium of almost 220 lending banks worldwide.

 English and French government being party to the project, had created a conducive
   environment to facilitate its success to boost European trade and economy.

 Pre-feasibility study with high level design perspective and respective rough order of
   magnitudes of estimates were appropriated to certain extent.

 State of the art laser and computer technology was used to bore the tunnel and to test every
   part of the rail system.
Assessment and Analysis
Project Management Area    Development Phase
Scope Management                  3
Time Management                   3
Cost Management                   2
Quality Management                4
HR Management                     3
Comminication Management          3
Risk Management                   3
Procurrement Management           3
Integration Management            3
Major areas of strength in the
management of Inception phase
 High level design and respective rough order of magnitude of estimates were appropriate .

 Schedule planning included activity definition, sequencing and duration to develop base line project
   schedule.

 Risk management to have reviewed the scope of the euro-tunnel initial risks with perspective of
   Engineering risks.

 Quality management included quality planning, assurance, and control.

 Team work was explicit given the fact thousands of workers, machinist and engineers worked very
   well over a period of 3.5 years.

 Communication perspective related to project planning, negotiations and its flow was achieved and
   technical problems was solved smoothly.

 Monitoring of project objectives and its progress was accomplished.

 There was a significant value of an effective in decision making following “ best practices” to include
   all key stakeholders.
Major areas of opportunities for
improvement in Inception phase
 Enough time should have been provided for low level design keep the project cost effective and w.r.t
   initial estimation.

 Contractual assessment could have been more precise which led to additional claims to 2.25 billion
   USD.

 Risk management of know or unknown and change control methods could have been more rigorous .

 Incomplete requirements, scope changes and risk responses should have been mitigated to reduce
   likelihood of negative schedule and cost variance.

 Communication within organizational structure, contracts and finances were addressed with
   conflicts.

 Monitoring of project should have been managed to industry specific pratices and agreed upon
   international standards.

 Decision making along with roles and responsibilities of a project management office should have
   been validated.
Thank You.

More Related Content

What's hot

The Chunnel Project - Quality Management
The Chunnel Project - Quality ManagementThe Chunnel Project - Quality Management
The Chunnel Project - Quality ManagementMilind_jagtap_
 
Project Quality Management powerpoint
Project Quality Management powerpointProject Quality Management powerpoint
Project Quality Management powerpointDjamadaMuhamedKAGUSU
 
Project Management case analysis
Project Management case analysisProject Management case analysis
Project Management case analysisWakas Khalid
 
Project Charter Summery
Project Charter SummeryProject Charter Summery
Project Charter SummeryDerek Cooksey
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control ProcurementsDavidMcLachlan1
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Managementhatemk
 
Alpha Case Study - Project Management Plan Sample
Alpha Case Study - Project Management Plan SampleAlpha Case Study - Project Management Plan Sample
Alpha Case Study - Project Management Plan SampleAgatha Maia Duarte de Assis
 
Project Management Case Studies by Terry Hall
Project Management Case Studies by Terry HallProject Management Case Studies by Terry Hall
Project Management Case Studies by Terry HallTerry Hall, PMP
 
Project Management Report
Project Management ReportProject Management Report
Project Management ReportSANKET SENAPATI
 
The Three Projects Of The Panama Canal V.1.3
The Three Projects Of The Panama Canal V.1.3The Three Projects Of The Panama Canal V.1.3
The Three Projects Of The Panama Canal V.1.3Roberto Toledo
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-completeYong Sy
 
MEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATIONMEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATIONFarah Sham
 
Guide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesGuide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesSarah Fox
 

What's hot (20)

The Chunnel Project - Quality Management
The Chunnel Project - Quality ManagementThe Chunnel Project - Quality Management
The Chunnel Project - Quality Management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project Quality Management powerpoint
Project Quality Management powerpointProject Quality Management powerpoint
Project Quality Management powerpoint
 
Project Management case analysis
Project Management case analysisProject Management case analysis
Project Management case analysis
 
Standard Forms of Construction Contracts
Standard Forms of Construction ContractsStandard Forms of Construction Contracts
Standard Forms of Construction Contracts
 
Channel tunnel
Channel tunnelChannel tunnel
Channel tunnel
 
Project Charter Summery
Project Charter SummeryProject Charter Summery
Project Charter Summery
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Management
 
Alpha Case Study - Project Management Plan Sample
Alpha Case Study - Project Management Plan SampleAlpha Case Study - Project Management Plan Sample
Alpha Case Study - Project Management Plan Sample
 
assignment on project planning
assignment on project planningassignment on project planning
assignment on project planning
 
Project Management Case Studies by Terry Hall
Project Management Case Studies by Terry HallProject Management Case Studies by Terry Hall
Project Management Case Studies by Terry Hall
 
Project Management Report
Project Management ReportProject Management Report
Project Management Report
 
The Three Projects Of The Panama Canal V.1.3
The Three Projects Of The Panama Canal V.1.3The Three Projects Of The Panama Canal V.1.3
The Three Projects Of The Panama Canal V.1.3
 
Epc
EpcEpc
Epc
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
 
Claims
ClaimsClaims
Claims
 
MEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATIONMEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATION
 
Guide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesGuide to Construction Procurement Strategies
Guide to Construction Procurement Strategies
 
Project closeout-report
Project closeout-reportProject closeout-report
Project closeout-report
 

Viewers also liked

Channel Tunnel
Channel TunnelChannel Tunnel
Channel TunnelTim Howell
 
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...peter747
 
Seven modern wonders of the world
Seven modern wonders of the worldSeven modern wonders of the world
Seven modern wonders of the worldvvelasco
 
United colors of benetton
United colors of benettonUnited colors of benetton
United colors of benettonSwati Kaushik
 
Microsoft word presentation
Microsoft word presentationMicrosoft word presentation
Microsoft word presentationegirshovich
 

Viewers also liked (9)

Channel Tunnel
Channel TunnelChannel Tunnel
Channel Tunnel
 
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
 
Channel tunnel
Channel  tunnelChannel  tunnel
Channel tunnel
 
Eurotunnel
EurotunnelEurotunnel
Eurotunnel
 
Eurotunnel
EurotunnelEurotunnel
Eurotunnel
 
CJM Construction Consulting PowerPoint Presentation
CJM Construction Consulting PowerPoint PresentationCJM Construction Consulting PowerPoint Presentation
CJM Construction Consulting PowerPoint Presentation
 
Seven modern wonders of the world
Seven modern wonders of the worldSeven modern wonders of the world
Seven modern wonders of the world
 
United colors of benetton
United colors of benettonUnited colors of benetton
United colors of benetton
 
Microsoft word presentation
Microsoft word presentationMicrosoft word presentation
Microsoft word presentation
 

Similar to The chunnel project

Construction project management
Construction project managementConstruction project management
Construction project managementsaif hasan
 
PPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudevaPPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudevaNarendra Vasudeva
 
Project management review ppt
Project management review  pptProject management review  ppt
Project management review pptVatsalaPG
 
I0313048051
I0313048051I0313048051
I0313048051theijes
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 
Project 27663255255255781771777166162666
Project 27663255255255781771777166162666Project 27663255255255781771777166162666
Project 27663255255255781771777166162666MilkiasMuse
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptpisal3
 
Project XYC Project PlanEric Malone, Jennifer Napier, .docx
Project XYC  Project PlanEric Malone, Jennifer Napier, .docxProject XYC  Project PlanEric Malone, Jennifer Napier, .docx
Project XYC Project PlanEric Malone, Jennifer Napier, .docxwkyra78
 
presentation slide
 presentation slide presentation slide
presentation slideSmit Javiya
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business planfarouq umar
 
CV Clive V2 180612 A
CV Clive V2 180612 ACV Clive V2 180612 A
CV Clive V2 180612 AClive Price
 
CV_PhilMorris_2015
CV_PhilMorris_2015CV_PhilMorris_2015
CV_PhilMorris_2015Phil Morris
 
The Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project SuccessThe Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project SuccessIRJET Journal
 
Course Assignment: Financing and Initiating Major Engineering Projects
Course Assignment: Financing and Initiating Major Engineering ProjectsCourse Assignment: Financing and Initiating Major Engineering Projects
Course Assignment: Financing and Initiating Major Engineering ProjectsFragoso Josue Muhae
 
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisC:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisInSync Conference
 

Similar to The chunnel project (20)

Construction project management
Construction project managementConstruction project management
Construction project management
 
PPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudevaPPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudeva
 
H1303055462
H1303055462H1303055462
H1303055462
 
Project management review ppt
Project management review  pptProject management review  ppt
Project management review ppt
 
I0313048051
I0313048051I0313048051
I0313048051
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
Project 27663255255255781771777166162666
Project 27663255255255781771777166162666Project 27663255255255781771777166162666
Project 27663255255255781771777166162666
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
 
RESUME
RESUMERESUME
RESUME
 
4
44
4
 
Project XYC Project PlanEric Malone, Jennifer Napier, .docx
Project XYC  Project PlanEric Malone, Jennifer Napier, .docxProject XYC  Project PlanEric Malone, Jennifer Napier, .docx
Project XYC Project PlanEric Malone, Jennifer Napier, .docx
 
KWKCV16
KWKCV16KWKCV16
KWKCV16
 
presentation slide
 presentation slide presentation slide
presentation slide
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business plan
 
CV Clive V2 180612 A
CV Clive V2 180612 ACV Clive V2 180612 A
CV Clive V2 180612 A
 
CV_PhilMorris_2015
CV_PhilMorris_2015CV_PhilMorris_2015
CV_PhilMorris_2015
 
The Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project SuccessThe Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project Success
 
Course Assignment: Financing and Initiating Major Engineering Projects
Course Assignment: Financing and Initiating Major Engineering ProjectsCourse Assignment: Financing and Initiating Major Engineering Projects
Course Assignment: Financing and Initiating Major Engineering Projects
 
Project planning: A career path
Project planning: A career pathProject planning: A career path
Project planning: A career path
 
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisC:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
 

The chunnel project

  • 1. Madhur Agarwal Priya Pandharipande Ameya Bhome Lalit Belorkar
  • 2. The Chunnel Project : Introduction “The Channel Tunnel (Chunnel) project was launched to create a connection between England and France via dedicated underground tunnel.  Scope of the project:  To create a fixed transportation link between England and France.  Objective’s of the project:  To spur economic development in the region.  Improve European trade environment.  Provide alternative high speed transportation method.
  • 3. Project Life Cycle Evaluation:  Inception Phase: Historical background, nature of project, political climate and pre-feasibility studies.  Development Phase: Planning, financing and conceptual designing.  Implementation Phase: Detailed designing, construction, installation, testing and commissioning.  Closeout Phase: Overall performance, settlement of claims, financial status and post-project evaluation.
  • 4. Inception Phase:  In 1986 Anglo-French Treaty signed, Transmanche Link (TML) awarded contract and Eurotunnel declared owner for 55 years post completion of the project.  The proposal included a 32 mile double rail tunnel to accommodate both through-trains and special car and truck carrying shuttle trains.  Original cost estimation of the project was 5.5 billion USD which was eventually increased to 14.9 billion USD.  Financing was pursued via equity and loan capital markets forming a large scale 7,00,000 shareholders and a consortium of almost 220 lending banks worldwide.  English and French government being party to the project, had created a conducive environment to facilitate its success to boost European trade and economy.  Pre-feasibility study with high level design perspective and respective rough order of magnitudes of estimates were appropriated to certain extent.  State of the art laser and computer technology was used to bore the tunnel and to test every part of the rail system.
  • 5. Assessment and Analysis Project Management Area Development Phase Scope Management 3 Time Management 3 Cost Management 2 Quality Management 4 HR Management 3 Comminication Management 3 Risk Management 3 Procurrement Management 3 Integration Management 3
  • 6. Major areas of strength in the management of Inception phase  High level design and respective rough order of magnitude of estimates were appropriate .  Schedule planning included activity definition, sequencing and duration to develop base line project schedule.  Risk management to have reviewed the scope of the euro-tunnel initial risks with perspective of Engineering risks.  Quality management included quality planning, assurance, and control.  Team work was explicit given the fact thousands of workers, machinist and engineers worked very well over a period of 3.5 years.  Communication perspective related to project planning, negotiations and its flow was achieved and technical problems was solved smoothly.  Monitoring of project objectives and its progress was accomplished.  There was a significant value of an effective in decision making following “ best practices” to include all key stakeholders.
  • 7. Major areas of opportunities for improvement in Inception phase  Enough time should have been provided for low level design keep the project cost effective and w.r.t initial estimation.  Contractual assessment could have been more precise which led to additional claims to 2.25 billion USD.  Risk management of know or unknown and change control methods could have been more rigorous .  Incomplete requirements, scope changes and risk responses should have been mitigated to reduce likelihood of negative schedule and cost variance.  Communication within organizational structure, contracts and finances were addressed with conflicts.  Monitoring of project should have been managed to industry specific pratices and agreed upon international standards.  Decision making along with roles and responsibilities of a project management office should have been validated.