SlideShare a Scribd company logo
The Chunnel Project
A learning out of Failure
                                         By
                            Garvit Bharadwaj
                                Piyush Tyagi
                              Pranay Karthik
                               Rachit Anand
                               Rajesh Bhatia
                            Sankarshan Joshi
                              Sumeet Gupta
Channel + Tunnel = Chunnel
19
The Chunnel                                                Months
                                                           Delay




 One of the world’s Largest Privately Funded
  construction project involving
    2 Governments – French and British
    220 banks
    Numerous contractors
    Regulatory Agencies (IGC)
 The project was bid at $5.5 b but completed at $14.9 b




                                                     $8.4b
                                                       Scope creep
The Chunnel - Contracts


French + British   BOT-Contract   CTG/FM
     Govt




    CTG/FM           Contract      TML
Next 15 Minutes


Inception

Development

Execution

Closeout
What is expected?

• Proper risk management

   • Engineering risks

   • Process risks

   • Approval risks

   • Financial risks

   • Business risks
Inception        Development         Execution   Closeout




   • Inception

       • Historical background of the project

       • Objective

       • Political climate

       • Pre-feasibility study
Inception        Development        Execution           Closeout




   • Scope:

       • Fixed transportation (51.5kms)

       • Economic development

   • Pressures causing mishaps:

       • Lack of scope causes resource planning, cost
         estimating & budgeting difficult.

       • Air-conditioning costs

       • Formation of intergovernmental commission
Inception          Development          Execution              Closeout




   • Finance aspects:
       • Treaty says to no government aid
       • Pursued via equity &loan capital markets.


   • Scheduling:
       • Activities related to activity definition, activity
            sequencing, activity duration estimates.
       • Planning 3 tunnels which required 46 contractors to
            complete the design requirements.
       • Changing safety rules created negative variances.
Inception        Development         Execution             Closeout




   • Incompatibility issues could have been avoided by
     stating Initial quality requirement in more detail.

   • Areas of improvement There was much interpretation for
     the agency like IGC .The IGC decision to change 600mm
     doors to 700mm doors itself delay the project to 9
     months.

   • Teamwork & cooperation considering the scope of the
     project was very important.

   • Contractual agreements made teamwork a complex
     activity.

   • It was very difficult to come to a mutually agreeable
     solution to material issues due to incomplete
     requirements, scope changes and thus , risk response
     strategies should have been considered.
Inception        Development         Execution           Closeout




   • Efficient communication is very important in
     preplanning, contract negotiations, financing and
     technical issues during the inception stage.


   • Communication seemed to breakdown in case of issues
     regarding organizational structure , finance and
     contracts as the issues were not timely solved.
Inception        Development         Execution             Closeout




   • Communication plan addressing horizontal and vertical
     communication channels should be in place.

   • Plan should also include information sharing, issue
     tracking and performance reporting.

   • Although , advanced project management tools and
     techniques were used, the decision-making ability to
     address critical issues from centralized position seemed
     insufficient
Inception        Development         Execution           Closeout




   Some critical aspects in development phase:

   • Massive communication barriers.

   • Problems due to huge scope of the project.
      • IGC played critical and detrimental role.

   • Cost planning.
      • Banks played an important role from start.

   • Scheduling was well done but project still faltered on
     deliver date.
      • IGC’s highest standard norm.
Inception        Development          Execution        Closeout




   • Better risk management could have been done.

   • Lack of investment in team building.
      • Two Government's denial to provide financial
         guarantee.

   • Project office’s work lacked detail.

   • All in all, given the facts, the project delay and cost
     overrun were almost foregone conclusions
Inception        Development     Execution          Closeout




  Too Early A Start


                                                          New
                            Approval Issues               Technology
Design
                                               Underground
         Construction       Enggineering       Construction
                            Risks
Inception            Development              Execution                Closeout




   Bureaucratic Pressures

        French + British                               Fixed Price
                              Control Costs          Implications for
        Govt. Pressures                                    TML




           Squeezing         Low Bid Prices
                                                      “Winner Takes
          Revenue via        with Best Case
                                                        All” Issue
         Change orders          Scenario




        Project cost Rise          TO                     $7 billion
        from $4.3 billion
Inception          Development     Execution           Closeout




Controls in Wrong Hands

                            Controls
                                       Construction
             Financing Banks
                                       Companies


            Profit Maximization    Risk Minimization




                  NO IMPORTANCE TO OPERATIONS
Inception     Development        Execution      Closeout




Communication Issues

                     Different
                     Cultures             Different
  Different
  Countries                              Specification



                    Internal
               Communication
                     Limited
Inception        Development         Execution          Closeout




   The immense amount of Litigation and Claim against
   project.

   • Scope: Scope of the project increases due to overall
     changes request through out the life of project.

   • Cost & Schedule Management: Max. Efforts to
     analyzing the source of overrun cost and blaming
     participating organization.

   • Team work and Communication: Team work and
     communication had broken down in several key area.
     Like Financial banker focus on minimizing their losses ,so
     they refused to negotiate any settlement. Clearly win-win
     negotiation far from mind between the parties.
Inception        Development         Execution         Closeout




   • Time Over shoot: the greatest impact of ROI.

   • Quality of project: Quality of a project is up to the
     mark as per engineering design and expectation. Even
     no. of accident was less as per industrial avg. during
     project running time.

   • Effective Change Management: They ready to make
     changes as per demand without additional funding during
     close out.
Learning's

• Equal importance should be give to the technical as
  well as functional aspects of project management.

• Project contracts and financing agreements should
  not be rushed and should provide for contingency.

• External Stakeholders should only play monitoring
  role and should not take part in day-to-day operations.

• Large projects like Chunnel Construction requires
  leveraging of new technology and lessons learned from
  existing project.
Thank You!!!! No Questions Please.


       We Know You Cant Control,
      So Go Ahead And Shoot Your
              Questions!

If learned from, Mistakes can be converted into Experiences.

More Related Content

What's hot

Channel Tunnel Report
Channel Tunnel ReportChannel Tunnel Report
Channel Tunnel ReportVidur Pandit
 
Project management basics
Project management basicsProject management basics
Project management basics
Planning School
 
Pmp communication chapter 10
Pmp communication chapter 10Pmp communication chapter 10
Pmp communication chapter 10
Ahmed Elshaboury,PMP,LEED GA
 
Design-Build Procurement Approaches
Design-Build Procurement ApproachesDesign-Build Procurement Approaches
Design-Build Procurement Approaches
Water Design-Build Council
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparison
helensuni
 
Risk management
Risk managementRisk management
Risk management
nashaat algrara
 
Why EPC
Why EPCWhy EPC
Why EPC
vivektmax
 
Project management
Project managementProject management
Project management
meena velmurugan
 
Project & Project managment
Project & Project managmentProject & Project managment
Project & Project managment
Pramod Sharma
 
Project management professional (pmi) study guide
Project management professional (pmi) study guideProject management professional (pmi) study guide
Project management professional (pmi) study guide
Trainerkart Learning Solutions
 
Contracting Strategy
Contracting StrategyContracting Strategy
Contracting Strategy
Iceland Geothermal
 
The Three Projects Of The Panama Canal V.1.3
The Three Projects Of The Panama Canal V.1.3The Three Projects Of The Panama Canal V.1.3
The Three Projects Of The Panama Canal V.1.3Roberto Toledo
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
Mohamed Loey
 
PMP Chapter 1 of 6 introduction (Based on PMBOK 6th edition)
PMP Chapter 1 of 6  introduction (Based on PMBOK 6th edition)PMP Chapter 1 of 6  introduction (Based on PMBOK 6th edition)
PMP Chapter 1 of 6 introduction (Based on PMBOK 6th edition)
Shamil Habet
 
Project communications management
Project communications managementProject communications management
Project communications management
Sanket Gandhi
 
Alliance Contracting
Alliance ContractingAlliance Contracting
Alliance Contracting
Water Design-Build Council
 
Infrastrcture project management
Infrastrcture project managementInfrastrcture project management
Infrastrcture project management
Sanjeev Deshmukh
 
PMI knowledge areas and processes
PMI knowledge areas and processesPMI knowledge areas and processes
PMI knowledge areas and processesWiktor Kabatc
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
Michael Pink
 

What's hot (20)

Channel Tunnel Report
Channel Tunnel ReportChannel Tunnel Report
Channel Tunnel Report
 
Channel tunnel
Channel tunnelChannel tunnel
Channel tunnel
 
Project management basics
Project management basicsProject management basics
Project management basics
 
Pmp communication chapter 10
Pmp communication chapter 10Pmp communication chapter 10
Pmp communication chapter 10
 
Design-Build Procurement Approaches
Design-Build Procurement ApproachesDesign-Build Procurement Approaches
Design-Build Procurement Approaches
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparison
 
Risk management
Risk managementRisk management
Risk management
 
Why EPC
Why EPCWhy EPC
Why EPC
 
Project management
Project managementProject management
Project management
 
Project & Project managment
Project & Project managmentProject & Project managment
Project & Project managment
 
Project management professional (pmi) study guide
Project management professional (pmi) study guideProject management professional (pmi) study guide
Project management professional (pmi) study guide
 
Contracting Strategy
Contracting StrategyContracting Strategy
Contracting Strategy
 
The Three Projects Of The Panama Canal V.1.3
The Three Projects Of The Panama Canal V.1.3The Three Projects Of The Panama Canal V.1.3
The Three Projects Of The Panama Canal V.1.3
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
 
PMP Chapter 1 of 6 introduction (Based on PMBOK 6th edition)
PMP Chapter 1 of 6  introduction (Based on PMBOK 6th edition)PMP Chapter 1 of 6  introduction (Based on PMBOK 6th edition)
PMP Chapter 1 of 6 introduction (Based on PMBOK 6th edition)
 
Project communications management
Project communications managementProject communications management
Project communications management
 
Alliance Contracting
Alliance ContractingAlliance Contracting
Alliance Contracting
 
Infrastrcture project management
Infrastrcture project managementInfrastrcture project management
Infrastrcture project management
 
PMI knowledge areas and processes
PMI knowledge areas and processesPMI knowledge areas and processes
PMI knowledge areas and processes
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 

Viewers also liked

Channel Tunnel
Channel TunnelChannel Tunnel
Channel TunnelTim Howell
 
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
peter747
 
Euro tunnel
Euro tunnelEuro tunnel
Euro tunnel
Fatih Taylı
 
Port Development 2.0
Port Development 2.0Port Development 2.0
Port Development 2.0InduStreams
 
Wootton port development
Wootton port developmentWootton port development
Wootton port development
osama Aboul Magd
 
tunneling & its effects
tunneling & its effectstunneling & its effects
tunneling & its effects
Budarapu Venkat Pranay
 
Eurotunnel
EurotunnelEurotunnel
Eurotunnel
marhielymarce
 
Eurotunnel
EurotunnelEurotunnel
Eurotunnel
marhielymarce
 
Construction plan 29.08. 14
Construction plan 29.08. 14Construction plan 29.08. 14
Construction plan 29.08. 14Winter Sonata
 
Capital budgeting analysis
Capital budgeting analysisCapital budgeting analysis
Capital budgeting analysissoumya
 
EUROTUNNEL -World Bank presentation May 2009
EUROTUNNEL -World Bank presentation May 2009EUROTUNNEL -World Bank presentation May 2009
EUROTUNNEL -World Bank presentation May 2009
Louise ROUSSEL English writing and translation services
 
Eurotunnel
EurotunnelEurotunnel
Eurotunnel
marhielymarce
 
Eurotunnel
EurotunnelEurotunnel
Eurotunnel
marhielymarce
 
Diaporama angleterre
Diaporama angleterreDiaporama angleterre
Diaporama angleterrenBesnard
 
RAAM Construction Limited (Drone Presentation)
RAAM Construction Limited (Drone Presentation)RAAM Construction Limited (Drone Presentation)
RAAM Construction Limited (Drone Presentation)
Grafic.guru
 
Factors affecting demand and supply of oil
Factors affecting demand and supply of oilFactors affecting demand and supply of oil
Factors affecting demand and supply of oil
Academic Research Paper Writing Services
 
Port Development - a handbook for planners in developing countries
Port Development - a handbook for planners in developing countries Port Development - a handbook for planners in developing countries
Port Development - a handbook for planners in developing countries
zubeditufail
 
Crude oil demand and supply
Crude oil demand and supplyCrude oil demand and supply
Crude oil demand and supplyUdayan Sikdar
 

Viewers also liked (19)

Channel Tunnel
Channel TunnelChannel Tunnel
Channel Tunnel
 
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
 
Euro tunnel
Euro tunnelEuro tunnel
Euro tunnel
 
Port Development 2.0
Port Development 2.0Port Development 2.0
Port Development 2.0
 
Wootton port development
Wootton port developmentWootton port development
Wootton port development
 
tunneling & its effects
tunneling & its effectstunneling & its effects
tunneling & its effects
 
Eurotunnel
EurotunnelEurotunnel
Eurotunnel
 
Eurotunnel
EurotunnelEurotunnel
Eurotunnel
 
Construction plan 29.08. 14
Construction plan 29.08. 14Construction plan 29.08. 14
Construction plan 29.08. 14
 
Capital budgeting analysis
Capital budgeting analysisCapital budgeting analysis
Capital budgeting analysis
 
EUROTUNNEL -World Bank presentation May 2009
EUROTUNNEL -World Bank presentation May 2009EUROTUNNEL -World Bank presentation May 2009
EUROTUNNEL -World Bank presentation May 2009
 
Eurotunnel
EurotunnelEurotunnel
Eurotunnel
 
Eurotunnel
EurotunnelEurotunnel
Eurotunnel
 
Diaporama angleterre
Diaporama angleterreDiaporama angleterre
Diaporama angleterre
 
RAAM Construction Limited (Drone Presentation)
RAAM Construction Limited (Drone Presentation)RAAM Construction Limited (Drone Presentation)
RAAM Construction Limited (Drone Presentation)
 
Factors affecting demand and supply of oil
Factors affecting demand and supply of oilFactors affecting demand and supply of oil
Factors affecting demand and supply of oil
 
Port Development - a handbook for planners in developing countries
Port Development - a handbook for planners in developing countries Port Development - a handbook for planners in developing countries
Port Development - a handbook for planners in developing countries
 
Kuwait oil field
Kuwait oil fieldKuwait oil field
Kuwait oil field
 
Crude oil demand and supply
Crude oil demand and supplyCrude oil demand and supply
Crude oil demand and supply
 

Similar to Chunnel ppt

Project management case study.pptx
Project management case study.pptxProject management case study.pptx
Project management case study.pptx
DrRRajalakshmi
 
Lindgren Combined 18may10
Lindgren Combined 18may10Lindgren Combined 18may10
Lindgren Combined 18may10
Jaylindgren
 
Capital Project Risk Survey
Capital Project Risk SurveyCapital Project Risk Survey
Capital Project Risk SurveyEric Ho
 
Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...
Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...
Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...
Loay Ghazaleh MBA, BSc Civil Eng.
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
Gregoire Lesecq
 
Boeing's Virtual Fence(Barriers) Nagarajan.pptx
Boeing's Virtual Fence(Barriers)  Nagarajan.pptxBoeing's Virtual Fence(Barriers)  Nagarajan.pptx
Boeing's Virtual Fence(Barriers) Nagarajan.pptx
DrRRajalakshmi
 
CHAPTER 3PROJECT MANAGEMENTT.docx
CHAPTER 3PROJECT MANAGEMENTT.docxCHAPTER 3PROJECT MANAGEMENTT.docx
CHAPTER 3PROJECT MANAGEMENTT.docx
walterl4
 
Achieving predictable project costs in an unpredictable world
Achieving predictable project costs in an unpredictable worldAchieving predictable project costs in an unpredictable world
Achieving predictable project costs in an unpredictable worldSourabh Bhasin
 
Cost and time overruns in indian construction industry
Cost and time overruns in indian construction industryCost and time overruns in indian construction industry
Cost and time overruns in indian construction industry
Angad Partap Singh Bali
 
Klastorin parte1 1
Klastorin parte1 1Klastorin parte1 1
Klastorin parte1 1cpezoareyes
 
Lessons From IT and Non-IT Projects (by Peter W. G. Morris)
Lessons From IT and Non-IT Projects (by Peter W. G. Morris)Lessons From IT and Non-IT Projects (by Peter W. G. Morris)
Lessons From IT and Non-IT Projects (by Peter W. G. Morris)
Nurhazman Abdul Aziz
 
Another Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham ZeinounAnother Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham Zeinoun
PMILebanonChapter
 
PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...
PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...
PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...
Pedram Danesh-Mand
 
What would you do if government suddenly became a really demanding client? Od...
What would you do if government suddenly became a really demanding client? Od...What would you do if government suddenly became a really demanding client? Od...
What would you do if government suddenly became a really demanding client? Od...commonsenseLT
 
Challenges of it enabled business change in the public sector
Challenges of it enabled business change in the public sectorChallenges of it enabled business change in the public sector
Challenges of it enabled business change in the public sector
iHub
 
Major Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperMajor Projects - Faster Better Cheaper
Major Projects - Faster Better Cheaper
Ian Heptinstall
 
Effective Virtual Projects
Effective Virtual ProjectsEffective Virtual Projects
Effective Virtual Projects
Zebra Management Consulting
 

Similar to Chunnel ppt (20)

Project management case study.pptx
Project management case study.pptxProject management case study.pptx
Project management case study.pptx
 
111212 ppp life cycle project delivery.pptx
111212 ppp life cycle project delivery.pptx111212 ppp life cycle project delivery.pptx
111212 ppp life cycle project delivery.pptx
 
Lindgren Combined 18may10
Lindgren Combined 18may10Lindgren Combined 18may10
Lindgren Combined 18may10
 
Capital Project Risk Survey
Capital Project Risk SurveyCapital Project Risk Survey
Capital Project Risk Survey
 
Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...
Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...
Answer to Soft Economy – Mega Developments Phasing & Sustainability Issue...
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
Boeing's Virtual Fence(Barriers) Nagarajan.pptx
Boeing's Virtual Fence(Barriers)  Nagarajan.pptxBoeing's Virtual Fence(Barriers)  Nagarajan.pptx
Boeing's Virtual Fence(Barriers) Nagarajan.pptx
 
CHAPTER 3PROJECT MANAGEMENTT.docx
CHAPTER 3PROJECT MANAGEMENTT.docxCHAPTER 3PROJECT MANAGEMENTT.docx
CHAPTER 3PROJECT MANAGEMENTT.docx
 
Successful project
Successful projectSuccessful project
Successful project
 
Achieving predictable project costs in an unpredictable world
Achieving predictable project costs in an unpredictable worldAchieving predictable project costs in an unpredictable world
Achieving predictable project costs in an unpredictable world
 
Cost and time overruns in indian construction industry
Cost and time overruns in indian construction industryCost and time overruns in indian construction industry
Cost and time overruns in indian construction industry
 
2008 Ebu Training BBC Scotland From QMD to PQ
2008 Ebu Training BBC Scotland From QMD to PQ2008 Ebu Training BBC Scotland From QMD to PQ
2008 Ebu Training BBC Scotland From QMD to PQ
 
Klastorin parte1 1
Klastorin parte1 1Klastorin parte1 1
Klastorin parte1 1
 
Lessons From IT and Non-IT Projects (by Peter W. G. Morris)
Lessons From IT and Non-IT Projects (by Peter W. G. Morris)Lessons From IT and Non-IT Projects (by Peter W. G. Morris)
Lessons From IT and Non-IT Projects (by Peter W. G. Morris)
 
Another Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham ZeinounAnother Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham Zeinoun
 
PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...
PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...
PD - Contract and Risk Conference - Integrated Schedule Cost Risk Analysis fo...
 
What would you do if government suddenly became a really demanding client? Od...
What would you do if government suddenly became a really demanding client? Od...What would you do if government suddenly became a really demanding client? Od...
What would you do if government suddenly became a really demanding client? Od...
 
Challenges of it enabled business change in the public sector
Challenges of it enabled business change in the public sectorChallenges of it enabled business change in the public sector
Challenges of it enabled business change in the public sector
 
Major Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperMajor Projects - Faster Better Cheaper
Major Projects - Faster Better Cheaper
 
Effective Virtual Projects
Effective Virtual ProjectsEffective Virtual Projects
Effective Virtual Projects
 

More from sankarshanjoshi

Madhya pradesh tourism brand analysis
Madhya pradesh tourism brand analysisMadhya pradesh tourism brand analysis
Madhya pradesh tourism brand analysis
sankarshanjoshi
 
Normal Distribution Presentation
Normal Distribution PresentationNormal Distribution Presentation
Normal Distribution Presentationsankarshanjoshi
 
Analysis of 4P's of Westside
Analysis of 4P's of WestsideAnalysis of 4P's of Westside
Analysis of 4P's of Westside
sankarshanjoshi
 

More from sankarshanjoshi (6)

Madhya pradesh tourism brand analysis
Madhya pradesh tourism brand analysisMadhya pradesh tourism brand analysis
Madhya pradesh tourism brand analysis
 
Retail Forecasting
Retail ForecastingRetail Forecasting
Retail Forecasting
 
Normal Distribution Presentation
Normal Distribution PresentationNormal Distribution Presentation
Normal Distribution Presentation
 
SaaS Presentation
SaaS PresentationSaaS Presentation
SaaS Presentation
 
Report on Westside
Report on WestsideReport on Westside
Report on Westside
 
Analysis of 4P's of Westside
Analysis of 4P's of WestsideAnalysis of 4P's of Westside
Analysis of 4P's of Westside
 

Recently uploaded

FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
LR1709MUSIC
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
Operational Excellence Consulting
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
Erika906060
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Arihant Webtech Pvt. Ltd
 
Role of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in MiningRole of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in Mining
Naaraayani Minerals Pvt.Ltd
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
taqyed
 
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxTaurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
my Pandit
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
awaisafdar
 
Global Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdfGlobal Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdf
Henry Tapper
 
Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
HARSHITHV26
 
Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
YourLegal Accounting
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
RajPriye
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
Ben Wann
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
seoforlegalpillers
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
SynapseIndia
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
HajeJanKamps
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
NathanBaughman3
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
fakeloginn69
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
zoyaansari11365
 

Recently uploaded (20)

FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
 
Role of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in MiningRole of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in Mining
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
 
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxTaurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
 
Global Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdfGlobal Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdf
 
Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
 
Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
 

Chunnel ppt

  • 1. The Chunnel Project A learning out of Failure By Garvit Bharadwaj Piyush Tyagi Pranay Karthik Rachit Anand Rajesh Bhatia Sankarshan Joshi Sumeet Gupta
  • 2.
  • 3. Channel + Tunnel = Chunnel
  • 4. 19 The Chunnel Months Delay  One of the world’s Largest Privately Funded construction project involving  2 Governments – French and British  220 banks  Numerous contractors  Regulatory Agencies (IGC)  The project was bid at $5.5 b but completed at $14.9 b $8.4b Scope creep
  • 5. The Chunnel - Contracts French + British BOT-Contract CTG/FM Govt CTG/FM Contract TML
  • 7. What is expected? • Proper risk management • Engineering risks • Process risks • Approval risks • Financial risks • Business risks
  • 8. Inception Development Execution Closeout • Inception • Historical background of the project • Objective • Political climate • Pre-feasibility study
  • 9. Inception Development Execution Closeout • Scope: • Fixed transportation (51.5kms) • Economic development • Pressures causing mishaps: • Lack of scope causes resource planning, cost estimating & budgeting difficult. • Air-conditioning costs • Formation of intergovernmental commission
  • 10. Inception Development Execution Closeout • Finance aspects: • Treaty says to no government aid • Pursued via equity &loan capital markets. • Scheduling: • Activities related to activity definition, activity sequencing, activity duration estimates. • Planning 3 tunnels which required 46 contractors to complete the design requirements. • Changing safety rules created negative variances.
  • 11. Inception Development Execution Closeout • Incompatibility issues could have been avoided by stating Initial quality requirement in more detail. • Areas of improvement There was much interpretation for the agency like IGC .The IGC decision to change 600mm doors to 700mm doors itself delay the project to 9 months. • Teamwork & cooperation considering the scope of the project was very important. • Contractual agreements made teamwork a complex activity. • It was very difficult to come to a mutually agreeable solution to material issues due to incomplete requirements, scope changes and thus , risk response strategies should have been considered.
  • 12. Inception Development Execution Closeout • Efficient communication is very important in preplanning, contract negotiations, financing and technical issues during the inception stage. • Communication seemed to breakdown in case of issues regarding organizational structure , finance and contracts as the issues were not timely solved.
  • 13. Inception Development Execution Closeout • Communication plan addressing horizontal and vertical communication channels should be in place. • Plan should also include information sharing, issue tracking and performance reporting. • Although , advanced project management tools and techniques were used, the decision-making ability to address critical issues from centralized position seemed insufficient
  • 14. Inception Development Execution Closeout Some critical aspects in development phase: • Massive communication barriers. • Problems due to huge scope of the project. • IGC played critical and detrimental role. • Cost planning. • Banks played an important role from start. • Scheduling was well done but project still faltered on deliver date. • IGC’s highest standard norm.
  • 15. Inception Development Execution Closeout • Better risk management could have been done. • Lack of investment in team building. • Two Government's denial to provide financial guarantee. • Project office’s work lacked detail. • All in all, given the facts, the project delay and cost overrun were almost foregone conclusions
  • 16. Inception Development Execution Closeout Too Early A Start New Approval Issues Technology Design Underground Construction Enggineering Construction Risks
  • 17. Inception Development Execution Closeout Bureaucratic Pressures French + British Fixed Price Control Costs Implications for Govt. Pressures TML Squeezing Low Bid Prices “Winner Takes Revenue via with Best Case All” Issue Change orders Scenario Project cost Rise TO $7 billion from $4.3 billion
  • 18. Inception Development Execution Closeout Controls in Wrong Hands Controls Construction Financing Banks Companies Profit Maximization Risk Minimization NO IMPORTANCE TO OPERATIONS
  • 19. Inception Development Execution Closeout Communication Issues Different Cultures Different Different Countries Specification Internal Communication Limited
  • 20. Inception Development Execution Closeout The immense amount of Litigation and Claim against project. • Scope: Scope of the project increases due to overall changes request through out the life of project. • Cost & Schedule Management: Max. Efforts to analyzing the source of overrun cost and blaming participating organization. • Team work and Communication: Team work and communication had broken down in several key area. Like Financial banker focus on minimizing their losses ,so they refused to negotiate any settlement. Clearly win-win negotiation far from mind between the parties.
  • 21. Inception Development Execution Closeout • Time Over shoot: the greatest impact of ROI. • Quality of project: Quality of a project is up to the mark as per engineering design and expectation. Even no. of accident was less as per industrial avg. during project running time. • Effective Change Management: They ready to make changes as per demand without additional funding during close out.
  • 22. Learning's • Equal importance should be give to the technical as well as functional aspects of project management. • Project contracts and financing agreements should not be rushed and should provide for contingency. • External Stakeholders should only play monitoring role and should not take part in day-to-day operations. • Large projects like Chunnel Construction requires leveraging of new technology and lessons learned from existing project.
  • 23. Thank You!!!! No Questions Please. We Know You Cant Control, So Go Ahead And Shoot Your Questions! If learned from, Mistakes can be converted into Experiences.

Editor's Notes

  1. IGC – Inter govt. Commission
  2. CTG – channel tunnelgrpFM – francemanache