SlideShare a Scribd company logo
Frontier Energy Services, LLC
Managing Project Transitions
Energy Pipeline Management Summit
July 15 – 17, 2019 New Orleans, Louisiana
2
Overview
Transitions
• Overview
• Discipline Transitions
• Functional Transitions
• Project Phase/Gate Transitions
• Transition Pitfalls
• Wrap Up
3
Overview
• Overview
• Discipline Transitions
• Functional Transitions
• Project Phase/Gate Transitions
• Transition Pitfalls
• Wrap Up
4
Overview
Phase / Gate 1 Phase / Gate 2 Phase / Gate 3 Phase / Gate 4 Phase / Gate 5
5
Overview
Transition Planning
Time
Productivity
On-Going Work Next Activity
Productivity impacts at the
beginning of transitions can be
mitigated by planning and
communication
Management
provides
leadership in
balancing needs of
the on-going work
with planning the
transition.
6
Overview
Steps Applicable to all Transitions:
•Key Staff Identified & Involved
•Logistics & Resources
•Transfer of Knowledge
•Scheduling Transition
•Identifying Key Issues & Risks
Transition Management Plan
7
Overview
Transition Management Plan
• Determine activities to mitigate issues & risks
• Structured approach to time the transition
• Manage ramp up (systems ready before
needed)
• Address historical problem areas:
o Cold eyes review (internal or by SME)
• Communicate the plan to those involved
…… Implement the Plan
8
Discipline Transitions
• Overview
• Discipline Transitions
• Functional Transitions
• Project Phase/Gate Transitions
• Transition Pitfalls
• Wrap Up
9
Discipline Transitions
Discipline Transitions:
• Below Ground to Above Ground
• Structural to Piping
• Pulling Cable to Terminations
• Foundations to Equipment Setting
• Hydrotest to Tie-Ins & Bolt-ups
• Completions to Load-out
10
Discipline Transitions
General Discipline
Transition
Planning Time
Frame
Phase / Gate 1 Phase / Gate 2 Phase / Gate 3 Phase / Gate 4 Phase / Gate 5
11
Discipline Transitions
Transition Planning Risk Areas Timing
Structural
- Prefabrication
- Erection
• Dimension control &
quality plans
• Welding procedures
and qualifications
• Safety during lifts
• Installation aids
• 30 days prior to
fabrication start
• 30 days prior to
fabrication start
• Lifting plans, JSA’s &
inspections complete
15 days prior to
loadout
• As near load-out as
possible to minimize
paint damage
Example of a Discipline Transition Risk Checklist
12
Functional Transitions
• Overview
• Discipline Transitions
• Functional Transitions
• Project Phase/Gate Transitions
• Transition Pitfalls
• Wrap Up
13
Functional Transitions
Concept through Operations:
• Quality
• Health & Safety
• Environmental
• Construction – Input &
Constructability
• Operations - Input & Operability
14
Construction
Manager Areas of
Impact
Phase / Gate 1 Phase / Gate 2 Phase / Gate 3 Phase / Gate 4 Phase / Gate 5
Functional Transitions
15
Construction - Input & Constructability
16
HU&C to
Operations
Phase / Gate 1 Phase / Gate 2 Phase / Gate 3 Phase / Gate 4 Phase / Gate 5
Operations - Input & Operability
17
Operations - Input & Operability
18
Project Phase/Gate Transitions
• Overview
• Discipline Transitions
• Functional Transitions
• Project Phase/Gate Transitions
• Transition Pitfalls
• Wrap Up
19
Project Phase/Gate Transitions
Project Phase Transitions:
1. Concept to Feasibility
2. Feasibility/FEED to Engineering
3. Engineering to Construction
4. Construction/HU&C to Operations
5. Operations
20
Project Phase/Gate Transitions
Phase / Gate 1 Phase / Gate 2 Phase / Gate 3 Phase / Gate 4 Phase / Gate 5
21
Phase / Gate Approach
Structured Phase / Gate Approach:
• Objectives are Defined for each Phase
/ Gate
• Deliverables are Defined for each Phase /
Gate
• Go / No-Go Decisions Made
 If Go, Move to the Next Phase / Gate
 If No-Go, Additional Definition or
Information is Needed
22
Phase / Gate Approach
Phase / Gate 1 Primary Objective:
• Frame the opportunity
• Develop an Evaluation/Appraisal Plan
• Perform an economic assessment of alternatives
reflecting the range of uncertainties and risks to
establish the value proposition
• Develop an Execution Plan (scope, staffing,
budget, and schedule) for Phase 2
• Decision to move into Phase / Gate 2
23
Phase / Gate Approach
Phase / Gate 2 Primary Objective:
• Develop and evaluate a range of alternatives
based on the endorsed project Frame
• Select the alternative that generates the
highest value for the business (not always
lowest cost)
• Develop Plan for Phase 3
• Decision to move into Phase / Gate 3
24
Phase / Gate Approach
Phase / Gate 3 Primary Objective:
• Define project (scope, execution plans, drilling,
production, commercial agreements, etc.)
• Develop CAPEX, OPEX, schedule, & production
estimates
• Identify and quantify the full range of risks
• Economic analyses – Develop AFE
• Plan for Phase 4
• Final Investment Decision (FID) for project – Issue
AFE - Move to Phase / Gate 4
25
Phase / Gate Approach
Phase / Gate 4 Primary Objective:
• Safely execute and deliver the project as
described in the AFE and other FID
commitments.
• Move to Phase / Gate 5
26
Phase / Gate Approach
Phase / Gate 5 Primary Objective:
• Successfully start up and transition the
completed project to Operations.
27
Transition Pitfalls
• Overview
• Discipline Transitions
• Functional Transitions
• Project Phase Transitions
• Transition Pitfalls
• Wrap Up
28
Transition Pitfalls - Discipline
Pitfall Potential Cause Potential Results
• Progress / Pace of
work not sustainable
• Work started without
sufficient design
maturity
• Insufficient detail in
plans
• Work site operating
at or near capacity
• Failure to identify and
disseminate lessons
learned prior to
transition
• Contractor claims
• Repetition of past
mistakes; repetition
of the “learning
curve”
• Re-work or budget
over runs
• Schedule busts
29
Transition Pitfalls - Common
Pitfall Potential Cause Potential Results
 Timing of the
transition can be
disruptive - often
conflicting priorities
cause poorly timed
transitions (too early
or too late)
 Insufficient planning
prior to transition
 Lack of
communication to
affected work groups.
 Lack of readiness by
the effected work
groups (i.e. work
processes between
work groups not
established)
 Poor construction
productivities
 Schedule slippage
 Errors and omissions
 Budget over runs
30
Transition Pitfalls - Common
Pitfall Potential Cause Potential Results
• Conflicting priorities
between teams
responsible for
various phases (i.e.
engineering and
construction;
construction and
operations)
• Interfaces and
interface parties not
well defined
• Inadequate
communication
• Insufficient planning
prior to transition
• Failure to team build
• Disagreements over
responsibilities for
shared costs
• Disagreement over
temporary use of
permanent facility
• Failure to monitor
operation and
maintain permanent
facility during
temporary use
• Budget & schedule
impacts
31
Transition Wrap Up
• Overview
• Discipline Transitions
• Functional Transitions
• Project Phase Transitions
• Transition Pitfalls
• Wrap Up
32
Management of Transitions is Often
Overlooked (Fighting Today’s “Fire“)…..
Which Will Result in Exposure to Significant
Disruptions From Poor Timing (Transitions
Too Early or Late) – Schedule and/or Budget
Impacts
While One Activity is Underway, Plan the
Transition to the Next.
Transition Wrap Up
33
Prepare a Transition Plan:
• Identify Activities to Mitigate
Impacts of Transitions
• Structured Approach to Time the
Transition
• Get Organizations & Systems
Ready Before Needed
Transition Wrap Up
34
Last Slide……!!!!
Questions
Answers
and

More Related Content

What's hot

How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
Abdelhay Ghanem
 
Balancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBalancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBrown Smith Wallace
 
VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2Jerry Bauers
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
Soe Naing Win
 
Construction delays
Construction delaysConstruction delays
Construction delays
Saida Njim
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
Glen Alleman
 
ESantavicca Resume March-2016
ESantavicca Resume March-2016ESantavicca Resume March-2016
ESantavicca Resume March-2016Ed Santavicca
 
Sxsw 2011 construction enviroment
Sxsw 2011 construction enviromentSxsw 2011 construction enviroment
Sxsw 2011 construction enviromentjuwes
 
Module 6 qaqc training
Module 6 qaqc trainingModule 6 qaqc training
Module 6 qaqc training
Diaz Susetyo
 
construction project planing
 construction project planing construction project planing
construction project planing
SANJEEV Wazir
 
Formandobits - Prince2 Foundation (Apuntes v.1.0412)
Formandobits - Prince2 Foundation (Apuntes v.1.0412)Formandobits - Prince2 Foundation (Apuntes v.1.0412)
Formandobits - Prince2 Foundation (Apuntes v.1.0412)
formandobits
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1
Ahmad Basim Hamza
 
Project closing and methods
Project closing and methodsProject closing and methods
Project closing and methods
Barath Babu Kumar
 
Managing The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy ProjectsManaging The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy Projects
mtingle
 
J.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject constructionJ.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject constructionJ.S. Daniel
 
Ken's_Resume_April 2015 r2
Ken's_Resume_April 2015 r2Ken's_Resume_April 2015 r2
Ken's_Resume_April 2015 r2Kenneth Ifidon
 
J.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of scheduleJ.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of scheduleJ.S. Daniel
 

What's hot (20)

How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
 
Balancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBalancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction Projects
 
VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Construction delays
Construction delaysConstruction delays
Construction delays
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
 
ACH 216 Lecture 06 (Pre Construction Planning)
ACH 216 Lecture 06 (Pre Construction Planning)ACH 216 Lecture 06 (Pre Construction Planning)
ACH 216 Lecture 06 (Pre Construction Planning)
 
ESantavicca Resume March-2016
ESantavicca Resume March-2016ESantavicca Resume March-2016
ESantavicca Resume March-2016
 
Sxsw 2011 construction enviroment
Sxsw 2011 construction enviromentSxsw 2011 construction enviroment
Sxsw 2011 construction enviroment
 
Module 6 qaqc training
Module 6 qaqc trainingModule 6 qaqc training
Module 6 qaqc training
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Formandobits - Prince2 Foundation (Apuntes v.1.0412)
Formandobits - Prince2 Foundation (Apuntes v.1.0412)Formandobits - Prince2 Foundation (Apuntes v.1.0412)
Formandobits - Prince2 Foundation (Apuntes v.1.0412)
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1
 
Project closing and methods
Project closing and methodsProject closing and methods
Project closing and methods
 
Unit 1
Unit 1Unit 1
Unit 1
 
Managing The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy ProjectsManaging The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy Projects
 
J.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject constructionJ.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject construction
 
Ken's_Resume_April 2015 r2
Ken's_Resume_April 2015 r2Ken's_Resume_April 2015 r2
Ken's_Resume_April 2015 r2
 
J.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of scheduleJ.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of schedule
 

Similar to Managing Project Transitions

APM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsAPM Practitioner Qualification revision cards
APM Practitioner Qualification revision cards
Jacobs Engineering
 
Project Management
Project ManagementProject Management
Project Management
Xubitech
 
Introduction to international project management
Introduction to international project managementIntroduction to international project management
Introduction to international project management
prakashnachnani
 
MSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdfMSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdf
ShanthaNimalBandaraA
 
MSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdfMSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdf
ShanthaNimalBandaraA
 
Project management
Project managementProject management
Project management
Heather Marie Wells
 
Heartbeats & Bloodstreams.pptx
Heartbeats & Bloodstreams.pptxHeartbeats & Bloodstreams.pptx
Heartbeats & Bloodstreams.pptx
malikshanii458
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE
S. Sathishkumar
 
Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project Management
Reetesh Gupta
 
Effective project management skills
Effective project management skillsEffective project management skills
Effective project management skills
Charles Cotter, PhD
 
effectiveprojectmanagementskills-140722041532-phpapp02.pdf
effectiveprojectmanagementskills-140722041532-phpapp02.pdfeffectiveprojectmanagementskills-140722041532-phpapp02.pdf
effectiveprojectmanagementskills-140722041532-phpapp02.pdf
ayansamosisa
 
D22MB040_Unit_6.pptx
D22MB040_Unit_6.pptxD22MB040_Unit_6.pptx
D22MB040_Unit_6.pptx
kiranroy6777
 
Episode 20 :PROJECT MANAGEMENT CONTEXT
Episode 20 :PROJECT MANAGEMENT CONTEXTEpisode 20 :PROJECT MANAGEMENT CONTEXT
Episode 20 :PROJECT MANAGEMENT CONTEXT
SAJJAD KHUDHUR ABBAS
 
Project management and project life cycle
Project management and project life cycleProject management and project life cycle
Project management and project life cycle
Institute of Rural Management
 
Introduction to Project Management.pdf
Introduction to Project Management.pdfIntroduction to Project Management.pdf
Introduction to Project Management.pdf
dinushikagunawardhan1
 
04. Project Management
04. Project Management04. Project Management
04. Project Management
BhuWan Khadka
 
Project management essentials 3 day training program
Project management essentials   3 day training programProject management essentials   3 day training program
Project management essentials 3 day training program
Paramjit Arora
 
Everything You Need to Know About Planning and Executing Your Next Laboratory...
Everything You Need to Know About Planning and Executing Your Next Laboratory...Everything You Need to Know About Planning and Executing Your Next Laboratory...
Everything You Need to Know About Planning and Executing Your Next Laboratory...
Triumvirate Environmental
 

Similar to Managing Project Transitions (20)

APM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsAPM Practitioner Qualification revision cards
APM Practitioner Qualification revision cards
 
Project Management
Project ManagementProject Management
Project Management
 
Introduction to international project management
Introduction to international project managementIntroduction to international project management
Introduction to international project management
 
MSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdfMSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdf
 
MSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdfMSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdf
 
Project management
Project managementProject management
Project management
 
Heartbeats & Bloodstreams.pptx
Heartbeats & Bloodstreams.pptxHeartbeats & Bloodstreams.pptx
Heartbeats & Bloodstreams.pptx
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE
 
Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project Management
 
Chapter 03
Chapter 03Chapter 03
Chapter 03
 
Effective project management skills
Effective project management skillsEffective project management skills
Effective project management skills
 
effectiveprojectmanagementskills-140722041532-phpapp02.pdf
effectiveprojectmanagementskills-140722041532-phpapp02.pdfeffectiveprojectmanagementskills-140722041532-phpapp02.pdf
effectiveprojectmanagementskills-140722041532-phpapp02.pdf
 
D22MB040_Unit_6.pptx
D22MB040_Unit_6.pptxD22MB040_Unit_6.pptx
D22MB040_Unit_6.pptx
 
Episode 20 :PROJECT MANAGEMENT CONTEXT
Episode 20 :PROJECT MANAGEMENT CONTEXTEpisode 20 :PROJECT MANAGEMENT CONTEXT
Episode 20 :PROJECT MANAGEMENT CONTEXT
 
Project management and project life cycle
Project management and project life cycleProject management and project life cycle
Project management and project life cycle
 
Introduction to Project Management.pdf
Introduction to Project Management.pdfIntroduction to Project Management.pdf
Introduction to Project Management.pdf
 
04. Project Management
04. Project Management04. Project Management
04. Project Management
 
Project management essentials 3 day training program
Project management essentials   3 day training programProject management essentials   3 day training program
Project management essentials 3 day training program
 
PEEM 2.pptx
PEEM 2.pptxPEEM 2.pptx
PEEM 2.pptx
 
Everything You Need to Know About Planning and Executing Your Next Laboratory...
Everything You Need to Know About Planning and Executing Your Next Laboratory...Everything You Need to Know About Planning and Executing Your Next Laboratory...
Everything You Need to Know About Planning and Executing Your Next Laboratory...
 

More from Energy Network marcus evans

Transforming Project Delivery in the Petrochem Industry-Jan Shumate, Eastman
Transforming Project Delivery in the Petrochem Industry-Jan Shumate, EastmanTransforming Project Delivery in the Petrochem Industry-Jan Shumate, Eastman
Transforming Project Delivery in the Petrochem Industry-Jan Shumate, Eastman
Energy Network marcus evans
 
Concept to Construction: Design and Build Management-Greg Lamberson, Frontier...
Concept to Construction: Design and Build Management-Greg Lamberson, Frontier...Concept to Construction: Design and Build Management-Greg Lamberson, Frontier...
Concept to Construction: Design and Build Management-Greg Lamberson, Frontier...
Energy Network marcus evans
 
Pipeline Operations in the Era of New Media-William Boyer, Southcross Energy
Pipeline Operations in the Era of New Media-William Boyer, Southcross EnergyPipeline Operations in the Era of New Media-William Boyer, Southcross Energy
Pipeline Operations in the Era of New Media-William Boyer, Southcross Energy
Energy Network marcus evans
 
Pipelines: 2052-James Breaux, Centurion Pipeline Co.
Pipelines: 2052-James Breaux, Centurion Pipeline Co.Pipelines: 2052-James Breaux, Centurion Pipeline Co.
Pipelines: 2052-James Breaux, Centurion Pipeline Co.
Energy Network marcus evans
 
The Future of the Refining Industry - Joseph Israel, News Release
The Future of the Refining Industry -  Joseph Israel, News ReleaseThe Future of the Refining Industry -  Joseph Israel, News Release
The Future of the Refining Industry - Joseph Israel, News Release
Energy Network marcus evans
 
Improving Power Plant Performance & Safety-David Orme, Ranger Steel Inc.
Improving Power Plant Performance & Safety-David Orme, Ranger Steel Inc. Improving Power Plant Performance & Safety-David Orme, Ranger Steel Inc.
Improving Power Plant Performance & Safety-David Orme, Ranger Steel Inc.
Energy Network marcus evans
 
Why a Proactive Approach is a Must for Safety Preparedness - Vic DeMasi News ...
Why a Proactive Approach is a Must for Safety Preparedness - Vic DeMasi News ...Why a Proactive Approach is a Must for Safety Preparedness - Vic DeMasi News ...
Why a Proactive Approach is a Must for Safety Preparedness - Vic DeMasi News ...
Energy Network marcus evans
 
Tackling Emerging Regulatory Changes – An Overview of Current PHMSA Legislati...
Tackling Emerging Regulatory Changes – An Overview of Current PHMSA Legislati...Tackling Emerging Regulatory Changes – An Overview of Current PHMSA Legislati...
Tackling Emerging Regulatory Changes – An Overview of Current PHMSA Legislati...
Energy Network marcus evans
 
Increasing Efficiency and Lowering Costs in a Reduced Oil Price Environment -...
Increasing Efficiency and Lowering Costs in a Reduced Oil Price Environment -...Increasing Efficiency and Lowering Costs in a Reduced Oil Price Environment -...
Increasing Efficiency and Lowering Costs in a Reduced Oil Price Environment -...
Energy Network marcus evans
 
Emphasizing the Importance of Pipeline Safety Management Systems-Bill Lowry, ...
Emphasizing the Importance of Pipeline Safety Management Systems-Bill Lowry, ...Emphasizing the Importance of Pipeline Safety Management Systems-Bill Lowry, ...
Emphasizing the Importance of Pipeline Safety Management Systems-Bill Lowry, ...
Energy Network marcus evans
 
Use of Technology in the Midstream Business: Simple to the Extreme – Focus on...
Use of Technology in the Midstream Business: Simple to the Extreme – Focus on...Use of Technology in the Midstream Business: Simple to the Extreme – Focus on...
Use of Technology in the Midstream Business: Simple to the Extreme – Focus on...
Energy Network marcus evans
 
An Overview on Pipeline Safety from the Railroad Commission of Texas – A Look...
An Overview on Pipeline Safety from the Railroad Commission of Texas – A Look...An Overview on Pipeline Safety from the Railroad Commission of Texas – A Look...
An Overview on Pipeline Safety from the Railroad Commission of Texas – A Look...
Energy Network marcus evans
 
Using Everyday Technology to Make the Midstream Business More Efficient - Chr...
Using Everyday Technology to Make the Midstream Business More Efficient - Chr...Using Everyday Technology to Make the Midstream Business More Efficient - Chr...
Using Everyday Technology to Make the Midstream Business More Efficient - Chr...
Energy Network marcus evans
 
“Hello Down There!” - Bob Taylor, American Electric Power Company
“Hello Down There!” - Bob Taylor, American Electric Power Company“Hello Down There!” - Bob Taylor, American Electric Power Company
“Hello Down There!” - Bob Taylor, American Electric Power Company
Energy Network marcus evans
 
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Energy Network marcus evans
 
Grow Your Business
Grow Your Business Grow Your Business
Grow Your Business
Energy Network marcus evans
 
The one-on-one meetings with potential customers is what matters most
The one-on-one meetings with potential customers is what matters mostThe one-on-one meetings with potential customers is what matters most
The one-on-one meetings with potential customers is what matters most
Energy Network marcus evans
 
Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...
Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...
Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...
Energy Network marcus evans
 
Ensuring Success in the Power Business - Doug Sterbenz, Westar Energy
Ensuring Success in the Power Business - Doug Sterbenz, Westar EnergyEnsuring Success in the Power Business - Doug Sterbenz, Westar Energy
Ensuring Success in the Power Business - Doug Sterbenz, Westar Energy
Energy Network marcus evans
 
Technology Needs for Advancing Wind Power Generation - Stan Rosinski, Electri...
Technology Needs for Advancing Wind Power Generation - Stan Rosinski, Electri...Technology Needs for Advancing Wind Power Generation - Stan Rosinski, Electri...
Technology Needs for Advancing Wind Power Generation - Stan Rosinski, Electri...
Energy Network marcus evans
 

More from Energy Network marcus evans (20)

Transforming Project Delivery in the Petrochem Industry-Jan Shumate, Eastman
Transforming Project Delivery in the Petrochem Industry-Jan Shumate, EastmanTransforming Project Delivery in the Petrochem Industry-Jan Shumate, Eastman
Transforming Project Delivery in the Petrochem Industry-Jan Shumate, Eastman
 
Concept to Construction: Design and Build Management-Greg Lamberson, Frontier...
Concept to Construction: Design and Build Management-Greg Lamberson, Frontier...Concept to Construction: Design and Build Management-Greg Lamberson, Frontier...
Concept to Construction: Design and Build Management-Greg Lamberson, Frontier...
 
Pipeline Operations in the Era of New Media-William Boyer, Southcross Energy
Pipeline Operations in the Era of New Media-William Boyer, Southcross EnergyPipeline Operations in the Era of New Media-William Boyer, Southcross Energy
Pipeline Operations in the Era of New Media-William Boyer, Southcross Energy
 
Pipelines: 2052-James Breaux, Centurion Pipeline Co.
Pipelines: 2052-James Breaux, Centurion Pipeline Co.Pipelines: 2052-James Breaux, Centurion Pipeline Co.
Pipelines: 2052-James Breaux, Centurion Pipeline Co.
 
The Future of the Refining Industry - Joseph Israel, News Release
The Future of the Refining Industry -  Joseph Israel, News ReleaseThe Future of the Refining Industry -  Joseph Israel, News Release
The Future of the Refining Industry - Joseph Israel, News Release
 
Improving Power Plant Performance & Safety-David Orme, Ranger Steel Inc.
Improving Power Plant Performance & Safety-David Orme, Ranger Steel Inc. Improving Power Plant Performance & Safety-David Orme, Ranger Steel Inc.
Improving Power Plant Performance & Safety-David Orme, Ranger Steel Inc.
 
Why a Proactive Approach is a Must for Safety Preparedness - Vic DeMasi News ...
Why a Proactive Approach is a Must for Safety Preparedness - Vic DeMasi News ...Why a Proactive Approach is a Must for Safety Preparedness - Vic DeMasi News ...
Why a Proactive Approach is a Must for Safety Preparedness - Vic DeMasi News ...
 
Tackling Emerging Regulatory Changes – An Overview of Current PHMSA Legislati...
Tackling Emerging Regulatory Changes – An Overview of Current PHMSA Legislati...Tackling Emerging Regulatory Changes – An Overview of Current PHMSA Legislati...
Tackling Emerging Regulatory Changes – An Overview of Current PHMSA Legislati...
 
Increasing Efficiency and Lowering Costs in a Reduced Oil Price Environment -...
Increasing Efficiency and Lowering Costs in a Reduced Oil Price Environment -...Increasing Efficiency and Lowering Costs in a Reduced Oil Price Environment -...
Increasing Efficiency and Lowering Costs in a Reduced Oil Price Environment -...
 
Emphasizing the Importance of Pipeline Safety Management Systems-Bill Lowry, ...
Emphasizing the Importance of Pipeline Safety Management Systems-Bill Lowry, ...Emphasizing the Importance of Pipeline Safety Management Systems-Bill Lowry, ...
Emphasizing the Importance of Pipeline Safety Management Systems-Bill Lowry, ...
 
Use of Technology in the Midstream Business: Simple to the Extreme – Focus on...
Use of Technology in the Midstream Business: Simple to the Extreme – Focus on...Use of Technology in the Midstream Business: Simple to the Extreme – Focus on...
Use of Technology in the Midstream Business: Simple to the Extreme – Focus on...
 
An Overview on Pipeline Safety from the Railroad Commission of Texas – A Look...
An Overview on Pipeline Safety from the Railroad Commission of Texas – A Look...An Overview on Pipeline Safety from the Railroad Commission of Texas – A Look...
An Overview on Pipeline Safety from the Railroad Commission of Texas – A Look...
 
Using Everyday Technology to Make the Midstream Business More Efficient - Chr...
Using Everyday Technology to Make the Midstream Business More Efficient - Chr...Using Everyday Technology to Make the Midstream Business More Efficient - Chr...
Using Everyday Technology to Make the Midstream Business More Efficient - Chr...
 
“Hello Down There!” - Bob Taylor, American Electric Power Company
“Hello Down There!” - Bob Taylor, American Electric Power Company“Hello Down There!” - Bob Taylor, American Electric Power Company
“Hello Down There!” - Bob Taylor, American Electric Power Company
 
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
Meeting the Challenge: Maintaining System Reliability While Meeting Both Econ...
 
Grow Your Business
Grow Your Business Grow Your Business
Grow Your Business
 
The one-on-one meetings with potential customers is what matters most
The one-on-one meetings with potential customers is what matters mostThe one-on-one meetings with potential customers is what matters most
The one-on-one meetings with potential customers is what matters most
 
Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...
Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...
Improving Electric Grid Reliability and Resiliency: Lessons Learned from Supe...
 
Ensuring Success in the Power Business - Doug Sterbenz, Westar Energy
Ensuring Success in the Power Business - Doug Sterbenz, Westar EnergyEnsuring Success in the Power Business - Doug Sterbenz, Westar Energy
Ensuring Success in the Power Business - Doug Sterbenz, Westar Energy
 
Technology Needs for Advancing Wind Power Generation - Stan Rosinski, Electri...
Technology Needs for Advancing Wind Power Generation - Stan Rosinski, Electri...Technology Needs for Advancing Wind Power Generation - Stan Rosinski, Electri...
Technology Needs for Advancing Wind Power Generation - Stan Rosinski, Electri...
 

Recently uploaded

Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
Lviv Startup Club
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
fakeloginn69
 
The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
Adam Smith
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Lviv Startup Club
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
KaiNexus
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
HumanResourceDimensi1
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
fisherameliaisabella
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
sarahvanessa51503
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
agatadrynko
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
uae taxgpt
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
ofm712785
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
Lital Barkan
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
Ben Wann
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
RajPriye
 
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).pptENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
zechu97
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
Nicola Wreford-Howard
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
SynapseIndia
 

Recently uploaded (20)

Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
 
The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
 
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).pptENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
 

Managing Project Transitions

  • 1. Frontier Energy Services, LLC Managing Project Transitions Energy Pipeline Management Summit July 15 – 17, 2019 New Orleans, Louisiana
  • 2. 2 Overview Transitions • Overview • Discipline Transitions • Functional Transitions • Project Phase/Gate Transitions • Transition Pitfalls • Wrap Up
  • 3. 3 Overview • Overview • Discipline Transitions • Functional Transitions • Project Phase/Gate Transitions • Transition Pitfalls • Wrap Up
  • 4. 4 Overview Phase / Gate 1 Phase / Gate 2 Phase / Gate 3 Phase / Gate 4 Phase / Gate 5
  • 5. 5 Overview Transition Planning Time Productivity On-Going Work Next Activity Productivity impacts at the beginning of transitions can be mitigated by planning and communication Management provides leadership in balancing needs of the on-going work with planning the transition.
  • 6. 6 Overview Steps Applicable to all Transitions: •Key Staff Identified & Involved •Logistics & Resources •Transfer of Knowledge •Scheduling Transition •Identifying Key Issues & Risks Transition Management Plan
  • 7. 7 Overview Transition Management Plan • Determine activities to mitigate issues & risks • Structured approach to time the transition • Manage ramp up (systems ready before needed) • Address historical problem areas: o Cold eyes review (internal or by SME) • Communicate the plan to those involved …… Implement the Plan
  • 8. 8 Discipline Transitions • Overview • Discipline Transitions • Functional Transitions • Project Phase/Gate Transitions • Transition Pitfalls • Wrap Up
  • 9. 9 Discipline Transitions Discipline Transitions: • Below Ground to Above Ground • Structural to Piping • Pulling Cable to Terminations • Foundations to Equipment Setting • Hydrotest to Tie-Ins & Bolt-ups • Completions to Load-out
  • 10. 10 Discipline Transitions General Discipline Transition Planning Time Frame Phase / Gate 1 Phase / Gate 2 Phase / Gate 3 Phase / Gate 4 Phase / Gate 5
  • 11. 11 Discipline Transitions Transition Planning Risk Areas Timing Structural - Prefabrication - Erection • Dimension control & quality plans • Welding procedures and qualifications • Safety during lifts • Installation aids • 30 days prior to fabrication start • 30 days prior to fabrication start • Lifting plans, JSA’s & inspections complete 15 days prior to loadout • As near load-out as possible to minimize paint damage Example of a Discipline Transition Risk Checklist
  • 12. 12 Functional Transitions • Overview • Discipline Transitions • Functional Transitions • Project Phase/Gate Transitions • Transition Pitfalls • Wrap Up
  • 13. 13 Functional Transitions Concept through Operations: • Quality • Health & Safety • Environmental • Construction – Input & Constructability • Operations - Input & Operability
  • 14. 14 Construction Manager Areas of Impact Phase / Gate 1 Phase / Gate 2 Phase / Gate 3 Phase / Gate 4 Phase / Gate 5 Functional Transitions
  • 15. 15 Construction - Input & Constructability
  • 16. 16 HU&C to Operations Phase / Gate 1 Phase / Gate 2 Phase / Gate 3 Phase / Gate 4 Phase / Gate 5 Operations - Input & Operability
  • 17. 17 Operations - Input & Operability
  • 18. 18 Project Phase/Gate Transitions • Overview • Discipline Transitions • Functional Transitions • Project Phase/Gate Transitions • Transition Pitfalls • Wrap Up
  • 19. 19 Project Phase/Gate Transitions Project Phase Transitions: 1. Concept to Feasibility 2. Feasibility/FEED to Engineering 3. Engineering to Construction 4. Construction/HU&C to Operations 5. Operations
  • 20. 20 Project Phase/Gate Transitions Phase / Gate 1 Phase / Gate 2 Phase / Gate 3 Phase / Gate 4 Phase / Gate 5
  • 21. 21 Phase / Gate Approach Structured Phase / Gate Approach: • Objectives are Defined for each Phase / Gate • Deliverables are Defined for each Phase / Gate • Go / No-Go Decisions Made  If Go, Move to the Next Phase / Gate  If No-Go, Additional Definition or Information is Needed
  • 22. 22 Phase / Gate Approach Phase / Gate 1 Primary Objective: • Frame the opportunity • Develop an Evaluation/Appraisal Plan • Perform an economic assessment of alternatives reflecting the range of uncertainties and risks to establish the value proposition • Develop an Execution Plan (scope, staffing, budget, and schedule) for Phase 2 • Decision to move into Phase / Gate 2
  • 23. 23 Phase / Gate Approach Phase / Gate 2 Primary Objective: • Develop and evaluate a range of alternatives based on the endorsed project Frame • Select the alternative that generates the highest value for the business (not always lowest cost) • Develop Plan for Phase 3 • Decision to move into Phase / Gate 3
  • 24. 24 Phase / Gate Approach Phase / Gate 3 Primary Objective: • Define project (scope, execution plans, drilling, production, commercial agreements, etc.) • Develop CAPEX, OPEX, schedule, & production estimates • Identify and quantify the full range of risks • Economic analyses – Develop AFE • Plan for Phase 4 • Final Investment Decision (FID) for project – Issue AFE - Move to Phase / Gate 4
  • 25. 25 Phase / Gate Approach Phase / Gate 4 Primary Objective: • Safely execute and deliver the project as described in the AFE and other FID commitments. • Move to Phase / Gate 5
  • 26. 26 Phase / Gate Approach Phase / Gate 5 Primary Objective: • Successfully start up and transition the completed project to Operations.
  • 27. 27 Transition Pitfalls • Overview • Discipline Transitions • Functional Transitions • Project Phase Transitions • Transition Pitfalls • Wrap Up
  • 28. 28 Transition Pitfalls - Discipline Pitfall Potential Cause Potential Results • Progress / Pace of work not sustainable • Work started without sufficient design maturity • Insufficient detail in plans • Work site operating at or near capacity • Failure to identify and disseminate lessons learned prior to transition • Contractor claims • Repetition of past mistakes; repetition of the “learning curve” • Re-work or budget over runs • Schedule busts
  • 29. 29 Transition Pitfalls - Common Pitfall Potential Cause Potential Results  Timing of the transition can be disruptive - often conflicting priorities cause poorly timed transitions (too early or too late)  Insufficient planning prior to transition  Lack of communication to affected work groups.  Lack of readiness by the effected work groups (i.e. work processes between work groups not established)  Poor construction productivities  Schedule slippage  Errors and omissions  Budget over runs
  • 30. 30 Transition Pitfalls - Common Pitfall Potential Cause Potential Results • Conflicting priorities between teams responsible for various phases (i.e. engineering and construction; construction and operations) • Interfaces and interface parties not well defined • Inadequate communication • Insufficient planning prior to transition • Failure to team build • Disagreements over responsibilities for shared costs • Disagreement over temporary use of permanent facility • Failure to monitor operation and maintain permanent facility during temporary use • Budget & schedule impacts
  • 31. 31 Transition Wrap Up • Overview • Discipline Transitions • Functional Transitions • Project Phase Transitions • Transition Pitfalls • Wrap Up
  • 32. 32 Management of Transitions is Often Overlooked (Fighting Today’s “Fire“)….. Which Will Result in Exposure to Significant Disruptions From Poor Timing (Transitions Too Early or Late) – Schedule and/or Budget Impacts While One Activity is Underway, Plan the Transition to the Next. Transition Wrap Up
  • 33. 33 Prepare a Transition Plan: • Identify Activities to Mitigate Impacts of Transitions • Structured Approach to Time the Transition • Get Organizations & Systems Ready Before Needed Transition Wrap Up