SlideShare a Scribd company logo
Our site visit was held on 26th June 2015 which is
located at Bukit Jalil, Kuala Lumpur. This project is
basically a condominium named The Andes. This site
visit is organised to help us in our assignment for 3
subjects which are Measurement 1, Construction
Technology and Building Materials. In this assignment
we are required to produce a report with different
requirement by each subjects. During the site visit we
are required to understand the basics of the construction
process and noted down what we had saw and learnt for
our report.
Overall view of the site.
From the figure above we can saw that the progress of construction for this
project was until basement floor only. This Condominium consists two block which
are Block A with 26 storey and Block B with 25 storey. The Project Manager Mr.Siow
told us that they expected the date of completion of Block A is 30th August 2015 and
Block B is 31st October 2015.
 To understand the basic of the construction process.
 To let us experience the actual working environment in a construction site.
 To let us more understanding the function or usage of different type of
building material involved in the construction site.
 To allow us to learn knowledge about construction that we can’t learn in book.
 To give us a clear vision on those what we had been taught in class before.
 Explore and identify various types of building materials and technology on
site.
 Awareness of the importance of safety on site and understanding of safety
problems and site conditions
 Recognize the items measurable for sub-structure and reinforced concrete
frame works.
When we reached the construction site, there was an information board
placed in front of the entrance. From the information board we can know some
information of this project. The construction site is just located beside a condominium
so the whole area of the construction site was fenced up to avoid any damage or dirt
to the condominium and also other facilities nearby. In the construction site we can
saw few accommodation for workers and also act as a meeting room at the site.
In the site, we can saw parts of the tower crane placed on the floor nearby the
entrance of the site for future use. The uses of tower crane is mainly for lifting heavy
things and transporting them to other places. We can also saw a lot of material
placed on the floor along the site for example timber, reinforcement bars, parts of
scaffolding and others. We saw a few familiar machine for construction in the site
which were excavator, bulldozer and mobile crane.
The type of foundation for this condominium is piling. It supports the structure
and transfer load from the building to the ground. There were also pit that had been
excavated and the sides of the pit was supported by steel sheet piling so that the soil
beside the pit won’t fall back to the pit it also provide high resistance to driving
stresses. In one of the pit we can saw pile cap that have been finished and starter
bar come out from the pile cap. Other than that, we can saw a lot of formwork and
reinforcement bars of columns and slabs in the basement floor which is still under
construction.
Figure 2: Temporary accommodations for
workers.
Figure 1: Information board that placed
at the entrance of the site.
Figure 3: Temporary works – material storage on the site.
Figure 4: Parts of tower crane placed on the
floor in the site. It is mainly used for
lifting heavy things.
Figure 5: This is the reinforcement bars we
measured in beam, column or slab for
measurement that found on the site.
There were also some links and
stirrups on the floor.
Figure 6: This is the links that used for column to
tied the vertical rebar inside the column.
It is measured by length plus 24d.
Figure 7: The workers is inserting the links for
column between the vertical bar.
Figure 8: This is how the reinforcement bar
inside the column look like. There are
also few concrete cover tied in front of
the rebar.
Figure 9: The workers were building the
formwork for column. Its act as a mold
for the concrete that poured inside.
Figure 10: This is the rebar inside the basement
slab. The supervisor told us that they
using reinforcement bar for the
basement slab but start from 1st floor
they will using BRC for the slab.
Figure 11: From this picture can saw that there is
a small pvc pipe insert right through
the rebar for column in between the
vertical bar. It is used to strengthen
the concrete.
Figure 12: The workers were bending the
reinforcement bars with a bar bender
machine.
Figure 13: Formwork has been taken off from
the column.
Figure 14: In this picture can see a pipe coming
out from the pit for piling. It is used to
pumping out the water from
underground.
Figure 15: This is how the pit excavated look like.
We can see the pile cap inside the pit
and starter bar for stump coming out
from the pile cap.
Figure 16: This is the how the bored pile under
the pile cap look like.
Figure 17: This is starter bar come up from
column stump for the column.
Figure 18: This is the rebar for the wall. From
this picture can see there is a blue
thing in between the vertical bar. It is
used for waterproof.
Figure 19: This is how the concrete cover been
casted.
Construction Technology 1
Type of foundation used in the site: Piled Foundation (Bored Pile)
 Piled foundation is a group of piles that supports a superstructure. It is a deep
foundation.
 Piled foundation is usually for multi storey buildings because it can transmit
heavier load.
 It is a foundations relying on driven piles often have groups of piles connected
by a pile cap.
Reason of using piled foundation:
This project is a condominium and it’s consist of Block A and Block B with 26
storey for Block A and 25 storey for Block B. So piled foundation is the best choice
for this building because it can transmit more load than other foundation.
Bored Pile
What is Bored Pile?
Bored pile is used for those tall buildings or massive industrial complexes,
which require foundations that can bear the load of thousands of tons, most probably
in unstable or difficult soil conditions. The method of drilling bored pile is different
from RC square pile or spun pile, which is using driving method. Bored pilling works
required specialist bored piling contractor to follow up instead of hiring general piling
contractor.
Bored Pile Pilecap on the pile
Advantages and Disadvantages of Piled Foundation
Advantages Disadvantages
Can be placed deep into soil Requires heavy equipment for handling &
driving
Can transmit heavy loads Noisy installation cause environment
impact/ vibration affect neighbour
properties
It prevent any shifting or collapse Not suitable in soils of poor drainage
qualities (driven pile)
Piles can be precast to the required
specifications
Advance planning is required for handling
and driving
Less material is required for
construction while extensive excavation
of ground material can be avoided
Can be affected by insects / salt water
(timber pile)
Building Materials
The grade of reinforced concrete:
The grade of reinforced concrete used for the construction of the building is
Grade 35 reinforced concrete.
Advantages of Grade 35 reinforced concrete:
o It have better resistance to fire
o Long service life with low maintenance cost
o Cheaper than Grade 45 reinforced concrete and it is more common used in
construction area
o Can be casted in any required
Disadvantages of Grade 35 reinforced concrete:
o Low compressive strength if compared to Grade 45 reinforced concrete
o Lower grade of reinforced concrete will easily cracked under service load
o Lower ductility than higher grade of reinforced concrete
Building elements with 35 reinforced concrete in the site
Pilecap, Slab, Wall and Beam
Grade 45 reinforced concrete
Advantages of Grade 45 reinforced concrete:
o Higher strength concrete resists loads that cannot resisted by normal-strength
concrete.
o Using higher grade concrete means that column size can be reduced.
o Higher compressive strength
o Extended life cycles
Disadvantages of Grade 45 reinforced concrete:
o More expensive than Grade 35 reinforced concrete
o It is weak in handling tension
o It do no retain heat very well. The surface of the concrete will be cold during
the winter
Building elements with 40 reinforced concrete in the site
Column
Learning outcomes/ Conclusion
This is the first time I when to a site visit at a construction site. I learnt a
lot of things in this site visits. I learnt that it is important to have a good
communication or teamwork with the construction team members on site for a
successful and good quality of project.
In this site visit I also have a clear vision and able to understand on a
lot of things that had been taught in class but never seen it before for example
I saw how the reinforcement bar in column, slab, or wall look like. I also have
a clear vision on how a pilecap or pile inside a pit look like. From this site visit
I also understand how they actually construct the formwork for a column or
wall. I learnt that actually before poured concrete in to a column they will
insert a pipe in between the vertical bar to strengthen the concrete, this is
what I never know before this site visit. I also learnt that safety is really
important in a construction site.
Most important is that we have a chance to go to a construction site
and experience the actual working environment in a construction site on a
uncertainty circumstances especially under hot sun.
In conclusion, this is a very great chance to gain more knowledge
about construction site. I am very happy to have a chance to go for this site
visits because I learnt a lot of knowledge of construction.
SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN
BACHELOER OF QUANTITY SURVEYING (HONOURS)
MARCH INTAKE 2015
SEMESTER 1
[QSB 60104] MEASUREMENT 1
Sr. Ang Fuey Lin
[BLD60104] CONSTRUCTION TECHNOLOGY 1
Pn. Azrina Md Yaakob
[BLD62003] BUILDING MATERIAL
Pn. Myzatual Aisah Kamarazaly
Construction Site Report
Individual Assignment
Yong Sing Yew 0318766
Table of Content
No Title Pages
1. Cover Page 1
2. Table of Content 2
3. Introduction and Objectives 3-4
4. Content/Technical Observation 5
5. Photo and Description 6-9
6. Construction Technology 1 10-12
7. Building Material 13-14
8. Learning Outcomes/Conclusion 15

More Related Content

What's hot

Site visit report
Site visit reportSite visit report
Site visit report
Jıa Yıı
 
Site visit report
Site visit reportSite visit report
Site visit report
foongmei yap
 
Assignment 1 - Antara Gapi, Hulu Selangor, Selangor
Assignment 1 - Antara Gapi, Hulu Selangor, SelangorAssignment 1 - Antara Gapi, Hulu Selangor, Selangor
Assignment 1 - Antara Gapi, Hulu Selangor, Selangor
Kai Yun Pang
 
Site visit report
Site visit reportSite visit report
Site visit report
Wen Crystal
 
Assignment of Site Report
Assignment of Site Report Assignment of Site Report
Assignment of Site Report
I'mMiss Lily
 
Site visit report
Site visit reportSite visit report
Site visit reportDoreen Yeo
 
Site visit report
Site visit reportSite visit report
Site visit report
Monnie Bao Jia
 
BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit Report
Hasif Alias
 
Site visit-report-nov2015
Site visit-report-nov2015Site visit-report-nov2015
Site visit-report-nov2015
Joyce HweeMin
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit report
Momo Poyi
 
Individual site report brief
Individual site report briefIndividual site report brief
Individual site report brief
Momo Poyi
 
Sem 1 degree ct assignment 1
Sem 1 degree ct assignment 1Sem 1 degree ct assignment 1
Sem 1 degree ct assignment 1Parham Farhadpoor
 
Site visit report
Site visit reportSite visit report
Site visit report
shensin1015
 
Site visit report qs semester 1
Site visit report   qs semester 1Site visit report   qs semester 1
Site visit report qs semester 1
KhangWei Chin
 
Site report algel
Site report algelSite report algel
Site report algelAlgel Yee
 
Get Commercial Building Construction Company Auburn by TopRung LLC
Get Commercial Building Construction Company Auburn by TopRung LLC  Get Commercial Building Construction Company Auburn by TopRung LLC
Get Commercial Building Construction Company Auburn by TopRung LLC
Top Rung - Building Contractors & Building Construction
 
site visit report (final)
site visit report (final)site visit report (final)
site visit report (final)
Jia Hong Mui
 
Site visit report
Site visit report Site visit report
Site visit report
Liming Hiew
 

What's hot (20)

Site visit report
Site visit reportSite visit report
Site visit report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Assignment 1 - Antara Gapi, Hulu Selangor, Selangor
Assignment 1 - Antara Gapi, Hulu Selangor, SelangorAssignment 1 - Antara Gapi, Hulu Selangor, Selangor
Assignment 1 - Antara Gapi, Hulu Selangor, Selangor
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Assignment of Site Report
Assignment of Site Report Assignment of Site Report
Assignment of Site Report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit Report
 
Site visit-report-nov2015
Site visit-report-nov2015Site visit-report-nov2015
Site visit-report-nov2015
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit report
 
Individual site report brief
Individual site report briefIndividual site report brief
Individual site report brief
 
Sem 1 degree ct assignment 1
Sem 1 degree ct assignment 1Sem 1 degree ct assignment 1
Sem 1 degree ct assignment 1
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Site visit report qs semester 1
Site visit report   qs semester 1Site visit report   qs semester 1
Site visit report qs semester 1
 
Site report algel
Site report algelSite report algel
Site report algel
 
Get Commercial Building Construction Company Auburn by TopRung LLC
Get Commercial Building Construction Company Auburn by TopRung LLC  Get Commercial Building Construction Company Auburn by TopRung LLC
Get Commercial Building Construction Company Auburn by TopRung LLC
 
Site report
Site reportSite report
Site report
 
site visit report (final)
site visit report (final)site visit report (final)
site visit report (final)
 
Site visit report
Site visit report Site visit report
Site visit report
 

Similar to Report

Final Report
Final Report Final Report
Final Report
Jack Ng
 
Site report
Site reportSite report
Site report
vaylu
 
Site report
Site reportSite report
Site report
yongseenyee
 
Construction Site Report
Construction Site ReportConstruction Site Report
Construction Site Report
Shao Xun Sean Thun
 
CT site visit report
CT site visit report CT site visit report
CT site visit report Yap Xin
 
MCB Final report
MCB Final reportMCB Final report
MCB Final report
Lucas ChinSheng
 
Site report
Site reportSite report
Site report
HuiYik
 
Integrated Assignment : Measurement & CT & BM
Integrated Assignment : Measurement & CT & BMIntegrated Assignment : Measurement & CT & BM
Integrated Assignment : Measurement & CT & BM
Jaey Chai
 
Measurement 1 site report
Measurement 1 site reportMeasurement 1 site report
Measurement 1 site report
Jessyca Than
 
Introduction
IntroductionIntroduction
Introduction
Lam Yu
 
Ct bm measurement report
Ct bm measurement reportCt bm measurement report
Ct bm measurement report
Kailyn Lee
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)
I'mMiss Lily
 
Site-Report (1).docx
Site-Report (1).docxSite-Report (1).docx
Site-Report (1).docxShze Hwa Lee
 
Site Report
Site Report Site Report
Site Report
Sow Wei Henn
 
Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Chin Tze Wei
 
Site report
Site reportSite report
Site report
Joyce HweeMin
 
Bachelor in quantity surveying 2
Bachelor in quantity surveying 2Bachelor in quantity surveying 2
Bachelor in quantity surveying 2Arthur Wilson
 
M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1
Jing Chuang
 
Site visit report.
Site visit report.Site visit report.
Site visit report.
Man Yee
 

Similar to Report (20)

Final Report
Final Report Final Report
Final Report
 
Site report
Site reportSite report
Site report
 
Site report
Site reportSite report
Site report
 
Construction Site Report
Construction Site ReportConstruction Site Report
Construction Site Report
 
Site report
Site reportSite report
Site report
 
CT site visit report
CT site visit report CT site visit report
CT site visit report
 
MCB Final report
MCB Final reportMCB Final report
MCB Final report
 
Site report
Site reportSite report
Site report
 
Integrated Assignment : Measurement & CT & BM
Integrated Assignment : Measurement & CT & BMIntegrated Assignment : Measurement & CT & BM
Integrated Assignment : Measurement & CT & BM
 
Measurement 1 site report
Measurement 1 site reportMeasurement 1 site report
Measurement 1 site report
 
Introduction
IntroductionIntroduction
Introduction
 
Ct bm measurement report
Ct bm measurement reportCt bm measurement report
Ct bm measurement report
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)
 
Site-Report (1).docx
Site-Report (1).docxSite-Report (1).docx
Site-Report (1).docx
 
Site Report
Site Report Site Report
Site Report
 
Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)
 
Site report
Site reportSite report
Site report
 
Bachelor in quantity surveying 2
Bachelor in quantity surveying 2Bachelor in quantity surveying 2
Bachelor in quantity surveying 2
 
M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1
 
Site visit report.
Site visit report.Site visit report.
Site visit report.
 

More from Yong Sy

Pm x de compilation
Pm x de compilationPm x de compilation
Pm x de compilation
Yong Sy
 
Pm only
Pm onlyPm only
Pm only
Yong Sy
 
Vm assignment (5)
Vm assignment (5)Vm assignment (5)
Vm assignment (5)
Yong Sy
 
Cl compilation updated
Cl compilation updatedCl compilation updated
Cl compilation updated
Yong Sy
 
Be presentation rev
Be presentation revBe presentation rev
Be presentation rev
Yong Sy
 
Fm report finalize to be use (1)
Fm report finalize to be use (1)Fm report finalize to be use (1)
Fm report finalize to be use (1)
Yong Sy
 
Chapter 2 lr
Chapter 2 lrChapter 2 lr
Chapter 2 lr
Yong Sy
 
proposal chapter 1
proposal chapter 1proposal chapter 1
proposal chapter 1
Yong Sy
 
PP2 presentation
PP2 presentationPP2 presentation
PP2 presentation
Yong Sy
 
Software report-complete-final
Software report-complete-finalSoftware report-complete-final
Software report-complete-final
Yong Sy
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
Yong Sy
 
Compilation
CompilationCompilation
Compilation
Yong Sy
 
Management science slide
Management science slideManagement science slide
Management science slide
Yong Sy
 
Mt presentation
Mt presentationMt presentation
Mt presentation
Yong Sy
 
Ohsa turorial-4
Ohsa turorial-4Ohsa turorial-4
Ohsa turorial-4
Yong Sy
 
Ieq presentation
Ieq presentationIeq presentation
Ieq presentation
Yong Sy
 
Ieq presentation (1)
Ieq presentation (1)Ieq presentation (1)
Ieq presentation (1)
Yong Sy
 
Indoor environmental-quality-in-healthcare (3)
Indoor environmental-quality-in-healthcare (3)Indoor environmental-quality-in-healthcare (3)
Indoor environmental-quality-in-healthcare (3)
Yong Sy
 
Ct
CtCt
Psy final-write-up (1)
Psy final-write-up (1)Psy final-write-up (1)
Psy final-write-up (1)
Yong Sy
 

More from Yong Sy (20)

Pm x de compilation
Pm x de compilationPm x de compilation
Pm x de compilation
 
Pm only
Pm onlyPm only
Pm only
 
Vm assignment (5)
Vm assignment (5)Vm assignment (5)
Vm assignment (5)
 
Cl compilation updated
Cl compilation updatedCl compilation updated
Cl compilation updated
 
Be presentation rev
Be presentation revBe presentation rev
Be presentation rev
 
Fm report finalize to be use (1)
Fm report finalize to be use (1)Fm report finalize to be use (1)
Fm report finalize to be use (1)
 
Chapter 2 lr
Chapter 2 lrChapter 2 lr
Chapter 2 lr
 
proposal chapter 1
proposal chapter 1proposal chapter 1
proposal chapter 1
 
PP2 presentation
PP2 presentationPP2 presentation
PP2 presentation
 
Software report-complete-final
Software report-complete-finalSoftware report-complete-final
Software report-complete-final
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
 
Compilation
CompilationCompilation
Compilation
 
Management science slide
Management science slideManagement science slide
Management science slide
 
Mt presentation
Mt presentationMt presentation
Mt presentation
 
Ohsa turorial-4
Ohsa turorial-4Ohsa turorial-4
Ohsa turorial-4
 
Ieq presentation
Ieq presentationIeq presentation
Ieq presentation
 
Ieq presentation (1)
Ieq presentation (1)Ieq presentation (1)
Ieq presentation (1)
 
Indoor environmental-quality-in-healthcare (3)
Indoor environmental-quality-in-healthcare (3)Indoor environmental-quality-in-healthcare (3)
Indoor environmental-quality-in-healthcare (3)
 
Ct
CtCt
Ct
 
Psy final-write-up (1)
Psy final-write-up (1)Psy final-write-up (1)
Psy final-write-up (1)
 

Recently uploaded

growbilliontrees.com-Trees for Granddaughter (1).pdf
growbilliontrees.com-Trees for Granddaughter (1).pdfgrowbilliontrees.com-Trees for Granddaughter (1).pdf
growbilliontrees.com-Trees for Granddaughter (1).pdf
yadavakashagra
 
Natural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptxNatural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptx
sidjena70
 
Summary of the Climate and Energy Policy of Australia
Summary of the Climate and Energy Policy of AustraliaSummary of the Climate and Energy Policy of Australia
Summary of the Climate and Energy Policy of Australia
yasmindemoraes1
 
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian AmazonAlert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
CIFOR-ICRAF
 
Navigating the complex landscape of AI governance
Navigating the complex landscape of AI governanceNavigating the complex landscape of AI governance
Navigating the complex landscape of AI governance
Piermenotti Mauro
 
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdfPresentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Innovation and Technology for Development Centre
 
Q&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service PlaybookQ&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service Playbook
World Resources Institute (WRI)
 
International+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shopInternational+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shop
laozhuseo02
 
Environmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. SinghEnvironmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. Singh
AhmadKhan917612
 
ppt on beauty of the nature by Palak.pptx
ppt on  beauty of the nature by Palak.pptxppt on  beauty of the nature by Palak.pptx
ppt on beauty of the nature by Palak.pptx
RaniJaiswal16
 
NRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation StrategyNRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation Strategy
Robin Grant
 
DRAFT NRW Recreation Strategy - People and Nature thriving together
DRAFT NRW Recreation Strategy - People and Nature thriving togetherDRAFT NRW Recreation Strategy - People and Nature thriving together
DRAFT NRW Recreation Strategy - People and Nature thriving together
Robin Grant
 
UNDERSTANDING WHAT GREEN WASHING IS!.pdf
UNDERSTANDING WHAT GREEN WASHING IS!.pdfUNDERSTANDING WHAT GREEN WASHING IS!.pdf
UNDERSTANDING WHAT GREEN WASHING IS!.pdf
JulietMogola
 
Prevalence, biochemical and hematological study of diabetic patients
Prevalence, biochemical and hematological study of diabetic patientsPrevalence, biochemical and hematological study of diabetic patients
Prevalence, biochemical and hematological study of diabetic patients
Open Access Research Paper
 
IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...
IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...
IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...
ipcc-media
 
Daan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like itDaan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like it
a0966109726
 
Sustainable farming practices in India .pptx
Sustainable farming  practices in India .pptxSustainable farming  practices in India .pptx
Sustainable farming practices in India .pptx
chaitaliambole
 
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptxAGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
BanitaDsouza
 
Bhopal Gas Leak Tragedy - A Night of death
Bhopal Gas Leak Tragedy - A Night of deathBhopal Gas Leak Tragedy - A Night of death
Bhopal Gas Leak Tragedy - A Night of death
upasana742003
 
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business VenturesWillie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
greendigital
 

Recently uploaded (20)

growbilliontrees.com-Trees for Granddaughter (1).pdf
growbilliontrees.com-Trees for Granddaughter (1).pdfgrowbilliontrees.com-Trees for Granddaughter (1).pdf
growbilliontrees.com-Trees for Granddaughter (1).pdf
 
Natural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptxNatural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptx
 
Summary of the Climate and Energy Policy of Australia
Summary of the Climate and Energy Policy of AustraliaSummary of the Climate and Energy Policy of Australia
Summary of the Climate and Energy Policy of Australia
 
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian AmazonAlert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
 
Navigating the complex landscape of AI governance
Navigating the complex landscape of AI governanceNavigating the complex landscape of AI governance
Navigating the complex landscape of AI governance
 
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdfPresentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
 
Q&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service PlaybookQ&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service Playbook
 
International+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shopInternational+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shop
 
Environmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. SinghEnvironmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. Singh
 
ppt on beauty of the nature by Palak.pptx
ppt on  beauty of the nature by Palak.pptxppt on  beauty of the nature by Palak.pptx
ppt on beauty of the nature by Palak.pptx
 
NRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation StrategyNRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation Strategy
 
DRAFT NRW Recreation Strategy - People and Nature thriving together
DRAFT NRW Recreation Strategy - People and Nature thriving togetherDRAFT NRW Recreation Strategy - People and Nature thriving together
DRAFT NRW Recreation Strategy - People and Nature thriving together
 
UNDERSTANDING WHAT GREEN WASHING IS!.pdf
UNDERSTANDING WHAT GREEN WASHING IS!.pdfUNDERSTANDING WHAT GREEN WASHING IS!.pdf
UNDERSTANDING WHAT GREEN WASHING IS!.pdf
 
Prevalence, biochemical and hematological study of diabetic patients
Prevalence, biochemical and hematological study of diabetic patientsPrevalence, biochemical and hematological study of diabetic patients
Prevalence, biochemical and hematological study of diabetic patients
 
IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...
IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...
IPCC Vice Chair Ladislaus Change Central Asia Climate Change Conference 27 Ma...
 
Daan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like itDaan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like it
 
Sustainable farming practices in India .pptx
Sustainable farming  practices in India .pptxSustainable farming  practices in India .pptx
Sustainable farming practices in India .pptx
 
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptxAGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
 
Bhopal Gas Leak Tragedy - A Night of death
Bhopal Gas Leak Tragedy - A Night of deathBhopal Gas Leak Tragedy - A Night of death
Bhopal Gas Leak Tragedy - A Night of death
 
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business VenturesWillie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
 

Report

  • 1. Our site visit was held on 26th June 2015 which is located at Bukit Jalil, Kuala Lumpur. This project is basically a condominium named The Andes. This site visit is organised to help us in our assignment for 3 subjects which are Measurement 1, Construction Technology and Building Materials. In this assignment we are required to produce a report with different requirement by each subjects. During the site visit we are required to understand the basics of the construction process and noted down what we had saw and learnt for our report. Overall view of the site. From the figure above we can saw that the progress of construction for this project was until basement floor only. This Condominium consists two block which are Block A with 26 storey and Block B with 25 storey. The Project Manager Mr.Siow told us that they expected the date of completion of Block A is 30th August 2015 and Block B is 31st October 2015.
  • 2.  To understand the basic of the construction process.  To let us experience the actual working environment in a construction site.  To let us more understanding the function or usage of different type of building material involved in the construction site.  To allow us to learn knowledge about construction that we can’t learn in book.  To give us a clear vision on those what we had been taught in class before.  Explore and identify various types of building materials and technology on site.  Awareness of the importance of safety on site and understanding of safety problems and site conditions  Recognize the items measurable for sub-structure and reinforced concrete frame works.
  • 3. When we reached the construction site, there was an information board placed in front of the entrance. From the information board we can know some information of this project. The construction site is just located beside a condominium so the whole area of the construction site was fenced up to avoid any damage or dirt to the condominium and also other facilities nearby. In the construction site we can saw few accommodation for workers and also act as a meeting room at the site. In the site, we can saw parts of the tower crane placed on the floor nearby the entrance of the site for future use. The uses of tower crane is mainly for lifting heavy things and transporting them to other places. We can also saw a lot of material placed on the floor along the site for example timber, reinforcement bars, parts of scaffolding and others. We saw a few familiar machine for construction in the site which were excavator, bulldozer and mobile crane. The type of foundation for this condominium is piling. It supports the structure and transfer load from the building to the ground. There were also pit that had been excavated and the sides of the pit was supported by steel sheet piling so that the soil beside the pit won’t fall back to the pit it also provide high resistance to driving stresses. In one of the pit we can saw pile cap that have been finished and starter bar come out from the pile cap. Other than that, we can saw a lot of formwork and reinforcement bars of columns and slabs in the basement floor which is still under construction. Figure 2: Temporary accommodations for workers. Figure 1: Information board that placed at the entrance of the site. Figure 3: Temporary works – material storage on the site.
  • 4. Figure 4: Parts of tower crane placed on the floor in the site. It is mainly used for lifting heavy things. Figure 5: This is the reinforcement bars we measured in beam, column or slab for measurement that found on the site. There were also some links and stirrups on the floor. Figure 6: This is the links that used for column to tied the vertical rebar inside the column. It is measured by length plus 24d. Figure 7: The workers is inserting the links for column between the vertical bar.
  • 5. Figure 8: This is how the reinforcement bar inside the column look like. There are also few concrete cover tied in front of the rebar. Figure 9: The workers were building the formwork for column. Its act as a mold for the concrete that poured inside. Figure 10: This is the rebar inside the basement slab. The supervisor told us that they using reinforcement bar for the basement slab but start from 1st floor they will using BRC for the slab. Figure 11: From this picture can saw that there is a small pvc pipe insert right through the rebar for column in between the vertical bar. It is used to strengthen the concrete.
  • 6. Figure 12: The workers were bending the reinforcement bars with a bar bender machine. Figure 13: Formwork has been taken off from the column. Figure 14: In this picture can see a pipe coming out from the pit for piling. It is used to pumping out the water from underground. Figure 15: This is how the pit excavated look like. We can see the pile cap inside the pit and starter bar for stump coming out from the pile cap.
  • 7. Figure 16: This is the how the bored pile under the pile cap look like. Figure 17: This is starter bar come up from column stump for the column. Figure 18: This is the rebar for the wall. From this picture can see there is a blue thing in between the vertical bar. It is used for waterproof. Figure 19: This is how the concrete cover been casted.
  • 8. Construction Technology 1 Type of foundation used in the site: Piled Foundation (Bored Pile)  Piled foundation is a group of piles that supports a superstructure. It is a deep foundation.  Piled foundation is usually for multi storey buildings because it can transmit heavier load.  It is a foundations relying on driven piles often have groups of piles connected by a pile cap. Reason of using piled foundation: This project is a condominium and it’s consist of Block A and Block B with 26 storey for Block A and 25 storey for Block B. So piled foundation is the best choice for this building because it can transmit more load than other foundation.
  • 9. Bored Pile What is Bored Pile? Bored pile is used for those tall buildings or massive industrial complexes, which require foundations that can bear the load of thousands of tons, most probably in unstable or difficult soil conditions. The method of drilling bored pile is different from RC square pile or spun pile, which is using driving method. Bored pilling works required specialist bored piling contractor to follow up instead of hiring general piling contractor. Bored Pile Pilecap on the pile
  • 10. Advantages and Disadvantages of Piled Foundation Advantages Disadvantages Can be placed deep into soil Requires heavy equipment for handling & driving Can transmit heavy loads Noisy installation cause environment impact/ vibration affect neighbour properties It prevent any shifting or collapse Not suitable in soils of poor drainage qualities (driven pile) Piles can be precast to the required specifications Advance planning is required for handling and driving Less material is required for construction while extensive excavation of ground material can be avoided Can be affected by insects / salt water (timber pile)
  • 11. Building Materials The grade of reinforced concrete: The grade of reinforced concrete used for the construction of the building is Grade 35 reinforced concrete. Advantages of Grade 35 reinforced concrete: o It have better resistance to fire o Long service life with low maintenance cost o Cheaper than Grade 45 reinforced concrete and it is more common used in construction area o Can be casted in any required Disadvantages of Grade 35 reinforced concrete: o Low compressive strength if compared to Grade 45 reinforced concrete o Lower grade of reinforced concrete will easily cracked under service load o Lower ductility than higher grade of reinforced concrete Building elements with 35 reinforced concrete in the site Pilecap, Slab, Wall and Beam
  • 12. Grade 45 reinforced concrete Advantages of Grade 45 reinforced concrete: o Higher strength concrete resists loads that cannot resisted by normal-strength concrete. o Using higher grade concrete means that column size can be reduced. o Higher compressive strength o Extended life cycles Disadvantages of Grade 45 reinforced concrete: o More expensive than Grade 35 reinforced concrete o It is weak in handling tension o It do no retain heat very well. The surface of the concrete will be cold during the winter Building elements with 40 reinforced concrete in the site Column
  • 13. Learning outcomes/ Conclusion This is the first time I when to a site visit at a construction site. I learnt a lot of things in this site visits. I learnt that it is important to have a good communication or teamwork with the construction team members on site for a successful and good quality of project. In this site visit I also have a clear vision and able to understand on a lot of things that had been taught in class but never seen it before for example I saw how the reinforcement bar in column, slab, or wall look like. I also have a clear vision on how a pilecap or pile inside a pit look like. From this site visit I also understand how they actually construct the formwork for a column or wall. I learnt that actually before poured concrete in to a column they will insert a pipe in between the vertical bar to strengthen the concrete, this is what I never know before this site visit. I also learnt that safety is really important in a construction site. Most important is that we have a chance to go to a construction site and experience the actual working environment in a construction site on a uncertainty circumstances especially under hot sun. In conclusion, this is a very great chance to gain more knowledge about construction site. I am very happy to have a chance to go for this site visits because I learnt a lot of knowledge of construction.
  • 14. SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN BACHELOER OF QUANTITY SURVEYING (HONOURS) MARCH INTAKE 2015 SEMESTER 1 [QSB 60104] MEASUREMENT 1 Sr. Ang Fuey Lin [BLD60104] CONSTRUCTION TECHNOLOGY 1 Pn. Azrina Md Yaakob [BLD62003] BUILDING MATERIAL Pn. Myzatual Aisah Kamarazaly Construction Site Report Individual Assignment Yong Sing Yew 0318766
  • 15. Table of Content No Title Pages 1. Cover Page 1 2. Table of Content 2 3. Introduction and Objectives 3-4 4. Content/Technical Observation 5 5. Photo and Description 6-9 6. Construction Technology 1 10-12 7. Building Material 13-14 8. Learning Outcomes/Conclusion 15