SlideShare a Scribd company logo
1
CONTENTS
NO. CONTENT PAGE
1. 1.1INTRODUCTION TO POST-TENSIONED
1.2 TYPICAL APPLICATIONS OF POST TENSIONING
1.3 TYPES OF POST TENSIONING
1.3.1 BONDED POST-TENSIONING
1.3.2 UNBONDED POST-TENSIONING
2-5
2. 2.0 ADVANTAGES AND DISADVANTAGES OF POST-
TENSIONING
6
3. 3.0 MANUFACTURING PROCESS OF POST-TENSIONING 7
4. 4.0 PROBLEMS & SOLUTIONS IN POST TENSIONING
STRUCTURAL ELEMENT
8
6. 5.0 REAL LIFE PROJECT [LOCAL & OVERSEA]
5.1 Morocco Mall ,Africa
5.2 Klang Valley, Malaysia
9-11
7. 6.0 REFERENCES 12
2
1.1 POST-TENSIONED
Post-tensioning is simply a method of producing prestressed concrete,masonry,and
other structural elements. The term prestressing is used to describe the process of
introducing internal forces (or stress) into a concrete ormasonryelementduring the
construction process in orderto counteractthe external loads applied when the structure
is put into use (known as service loads).These internal forces are applied by tensioning
high-strength steel, which can be done either before or after the concrete is placed.
When the steel is tensioned after concrete placement, the process is called post-
tensioning.
Post-tensioned means that the concrete is poured and then the tension is applied-butit
is still stressed before the loads are applied so it is still prestressed.Post-tensioned
concrete which is also called as “active reinforcement“, with the primary function to
place concrete structure undercompression in regions where loads causes tensile
stress. Post-tensioning applies compressive stresses on the material, balancing off
tensile stress on the concrete. The tension is applied by the use of a tensioning member
known as “tendons”.
It is a technique for reinforcing concrete. Post-tensioning tendons,which are
prestressing steel cables inside plastic ducts or sleeves,are positioned in the forms
before the concrete is placed.Afterwards, once the concrete has gained strength but
before the service loads are applied,the cables are pulled tight, or tensioned,and
anchored againstthe outer edges of the concrete.
The use of post-tensioning contributes to very demanding geometryrequirements,
including complex shapes andcurvature and variable superelevation.It allows long clear
spans and this result in aestheicaland architectural approach.Also,it would be column-
free and creates more space.In addition, it allows thinner concrete sections, stiffer walls
resisting lateral loads,and stiffer foundations.
Additionally, all construction joints and crack control joints could be eliminated because
the slab was poured monolithically (in one whole single piece)and the post-tensioning
system could provide sufficient pre-compression on the slab.
Tendo
ns
Photo Source : https://static.concretenetwork.com/photo-gallery/images/550x412Exact_0x4/site_26/concretenetwork-com_12578.jpg
3
1.2 TYPICAL APPLICATIONS OF POST TENSIONING
- Suspended slabs like floor slabs and terrace slabs
- Foundation slabs (rafts)
- Slabs on grade (office buildings,multistorey car parks,warehousesetc.)
- Cantilevered structures, such as overhanging building parts.
- Facade elements oflarge area;here light post-tensioning is a simple method of
preventing cracks.
- Main beams in the form of beams,transfer girders,lattice girders or north-light roofs.
1.3 TYPES OF POST TENSIONING
There are mainly (2) types of posttensioning system, bonded orunbonded.
 Bonded -The prestressing steel is installed at the site after the formwork is
erected and typically after concrete is poured.It is housed in a sheating or ductto
preventit from bonding to the surrounding concrete.After the concrete has
hardenered orcured,the prestressing steel is gripped at both ends and then
pulled and anchored to prestress the concrete.The ductwould then be filled with
cementitious grout.
 3 main purposes : protecttendons againstcorrosion,permanently
“ lock-in” the tendon pre-tension ( thereby removing the long-term
reliance upon the end-anchorage systems),improve certain structural
behaviorof the final concrete structure
 Unbonded -It differs by providing each individualcable permanentfreedom of
movement relative to concrete.By so, each individual tendon is coated with a
grease (generallyuse lithium-base)and covered by a plastic sheating formed in
an extrusion process.The transfer of tension to concrete is achieved by the steel
cable acting againststeel anchors embdded in the perimeter of the structural
element.
Single Strand
POST
TENSIONING
a. B o nd e d P o st -
b. Unbonded Post- Tensioning
Single Strand
Multi Strand Flat Duct
Multi Strands Round Duct
4
1.3.1 Bonded Post-Tensioning
BONDED POST-TENSIONING UNBONDED POST-TENSIONING
Develops higher flexural strength Provides greater available level arm
Does notdepend on anchorage after
grouting
Simplifies pre-fabrications of tendons
Localize the effects of damages Grouting not required
Simple technique for demolishing or
providing future opening in slab
Can be constructed faster
End
Cap
Grout
Valve
Pocket
Former
Strands
Examples:
Photo Source: http://pt-structures.com/wp-content/uploads/2010/08/10-
Steps_PT_Floor_Design_US_version1.pdf
[Flat Duct] [Round Duct]
Grout Pipe
Wedges
Strands
Anchor
Head
BearingPlate
Duct
Photo Source: http://ptsindia.net/pt-system.html
5
1.3.2 Unbonded Post- Tensioning
Single Strand
Floor System Reinforced with Grouted
Post-Tensioning System
Post- Tensioned MatFoundation
Using grouted Tendons
Flat Duct
KSA, Photo Source: http://pt-structures.com/wp-content/uploads/2010/08/10-
Steps_PT_Floor_Design_US_version1.pdf
Photo Source: https://lh3.googleusercontent.com/1TjXhdpEiQKGVCeuIpMKZ9DkfOqLi9QyAFQ5GdmOuG9f8CVl2dz-
tN2KughnoLUM6rRCaQ=s160
Photo Source:
https://lh3.googleusercontent.com/x9OONHF854Tjd7z1oDB9rKJbxqXncS5KQJSVXlxzyGICELIpggq
UuBH_qrSgbPgBnF7BVGw=s113
6
2.0 ADVANTAGES AND DISADVANTAGES OF POST-
TENSIONING
ADVANTAGES DISADVANTAGES
MaterialSavings
- Decreased dead load reduces rebar
(60%-75%) and concrete (20%) in
columns and foundation
Accuracy
- Placementof tendon profiles has to be
accurate
Quicker Construction
- Potential pourcycle of 3-4 days
- Reducing re-shoring requirements
Corrosion
- Since there are a numberoftendons
and
Stressing
Jack
Tendon Tail
(Additional lengthwill be cutoff)
Wedges
Stressing
Anchor
Split Pocket Former with
Intermediate AnchorPocket
Former
Anchorage
Assembly
Photo Source: http://www.amsyscoinc.com/2010/09/14/diagram-of-post-tensioning-slab/
Photo Source: http://pt-structures.com/wp-content/uploads/2010/08/10-
Steps_PT_Floor_Design_US_version1.pdf
Example of a Floor System using
the Unbonded Post-tensioning
System
Fortaleza, Brazil.
MAT FOUNDATION USING
UNBONDED TENDONS
Photo Source: http://pt-structures.com/wp-content/uploads/2010/08/10-
Steps_PT_Floor_Design_US_version1.p
FloorSystem
Reinforcedwith
GroutedPost-
TensioningSystem
7
wire spread inside the posttension slab,
corrosion mayoccur.Tendencyof
corrode depends on the quality of the
material
Increased Performance
- Improve seismic performance and
reduced deflection and vibration
- Improved crack control and
waterproofing
properties
Complexity ofwork
- Post tension can be made only by skilful
professionals.
Reduced Lifetime Costs
- Loweroverall maintenance and lifecycle
costs of the structure
- Reduced building heightalso results in
energysavings,
Poor workmanship leads to accidents
- Main problem ofusing post tension is
that if care is nottaken while making it,
it can lead to future mishaps.If gaps of
tendons and wiring, corrosion mayoccur
which will lead to some untoward events.
Flexible in design
- Designs made are sleek,requires lesser
space and give way to dynamic
contours.
Durability
- Lasts longer,strong substitude of the
normalconcrete
Stronger/More Efficient
- Less concrete and steel are needed for
the same structural capacity that might
form tight.
- Prevents entry of insects and reducing
possible water penetration which can
damage flooring and cause mold
problems
3.0 CONSTRUCTION PROCESS OF POST-TENSIONING SLAB
[Bonded+Unbonded]
8
5. After anchoring a tendon atone end,the
tension is applied at the other end by a
jack. The tensioning of tendons and pre-
compression ofconcrete occur
simultaneously. A system of self-
equilibrating forces develops after the
stretching ofthe tendons.
BONDED POST-TENSIONING UNONDED POST-TENSIONING
Placing ofducts in the reinforcement
1. The ducts for the tendons are placed along with the reinforcement before the casting of concrete. The duct S
are used to prevent contactbetween concrete and the tendons during the tensioning operation. The tendons
are placed in the ducts after the casting ofconcrete.
Casting ofconcrete
1. Concrete is casted and must achieve proper strength before the tendons are tensioned. This is typically 75% of
the concrete's 28-day design strength, and is specified in the projectdocuments.
Grouting the duct
2. Bonded post-tensioning - If the ducts are filled with
grout. The grout is a neat cementpaste or a sand-
cementmortar containing suitable admixture.
The ductis notgrouted
4. Unbonded post-tensioning - Ducts not
grouted and tendon is held by the end
anchorages. The profile ofthe duct depends
on the supportconditions. For a simply
supported member, the ducthas a sagging
profile between the ends. For a continuous
member, the ductsags in the span and hogs
over the support.
Photo Source:https://www.vsl.net/what-post-tensioning
Jacking oftendon
5. After anchoring a tendon at one end, the tension is
applied at the other end by a jack .The tensioning of
tendons and pre-compression ofconcrete occur
simultaneously. A system pfself-equilibrating forces
develops after the stretching oftendons.
Putting on wedges and cut off tendon tail
6. After tensioning is done, they will puton the wedges to
hold the tendons whereby the extra length of tendons,
tendon tails will be cutoff using either oxyacetylene
touch , hydraulic shear, plasma cutter, or abrasive wheel.
9
4.0 PROBLEMS & SOLUTIONS IN POST TENSIONING STRUCTURAL
ELEMENT
Honeycomb in Concrete
Solution: Patching with non-shrink concrete groutmix with an epoxy binder. Grout
strength should equal or exceed specified concrete strength. Do notuse grouts that
contains calcium chloride or other materials containing chloride and whenever patch
has attained proper strength, stressing process may proceed.
Splicing of Tendons
Solution: Tendons are sometimes too shortto reach an edge because of
misplacementor misfabrication. Thus, making tendon couplers are necessary, the
engineer ofrecord and the post-tensioning material supplier should be notified. The
coupler location should be determined by post-tensioning material supplier in such
that the coupler is centered in the member and nota pointof tendon curvature.
Cracking Wedges
Solution: Hairline cracks may appear in the case-hardened surface ofwedges due
to deformation ofthe wedges around the strand at the time of seating. These cracks
do notaffect the integrity of posttensioning system.
Photo Source :
https://lh3.googleusercontent.com/aotgRs0GAdyNUI9
AK5J_HVwG3r35me5yjy8-
PxBMqnOqwMWuWhM9xOthy6gXMr_h84Z2aA=s85
Photo Source :
https://lh3.googleusercontent.com/cHpL8k76
bpBOUhc3Nt3mUt508ADvWHYzNnQLG908Gr
hSZIH4e93weyMk0S1OAfusio37MSI=s90
Photo Source :
https://lh3.googleusercontent.com/A6LxuPDQ1Y0QRnAF
FYGhdPfCKb-
0jyukxWpRV5h38or6iitlyu0vF1EDIMWfp1vm0IArFg=s85
10
5.0 REAL LIFE PROJECT [Overseas]
5.1Morocco Mall ,Africa
Introduction
Project The Morocco Mall
Location ofthe
project
City of Casablanca,Morocco
Cost Approximately US$253-million
Construction
company
SGTM Construction
Size of the project 165,000 m², 650m long structure
Timeline Mid of 2008 – October 2011
CHALLENGE
Large amounts of concrete were to be used in the construction, which would necessitate a large
Photo Source : https://i.ytimg.com/vi/XcS24xN6c0k/maxresdefault.jpgPhoto Source :
https://khamsat.hsoubcdn.com/images/services/755020/5385609b9e808442e509004c
9193ff2a.jpg
11
number of expansion joints, and a large numbers ofprecastslabs were to be manufactured, at odds
with the tight construction timeless ofproject.
SOLUTION
Replace the reinforced concrete floor slabs and
the precast panels with posttensioned wal
Further challenges faced
Building would need to contain a large number
of expansion joints because the site is located
less than 20 m from the Atlantic Ocean and the
basementlevel is below sea level.Leaks would
therefore not only pose a major inconvenience,
but severely hamper progress.
Also, the parking garage at the base ofbuilding
contained too many supporting column which
severely reduced the number ofparking bays.
The building therefore need redesigned to
accommodate new solution.
Installation
1. Construction Site
2. Anchor Assembly
3. Stressing the
strand
The process being applied to the second floor ofthe
Morocco Mall in the earlier stages ofconstruction. (The
roofof the basementlevel)
The anchor assembly graphically depicted. During the
process, a tendon will have anchors on each end to
transmit the force into the structure. Longer tendons, as
used in the mall, also have intermediate anchors along
their length.
Tension is applied by using a hydraulic stressing jack
which bears against anchors embedded in the concrete,
pulling steel to a predetermined force or stress.
Photo Source :
https://lh3.googleusercontent.com/V2Uo7dfIloE9Dc8ZVubnUb4yD5vGDML86sRvTP5zDB
vZpgLPYcb7_KkkrByFGzqpr4AZ0w=s89
Photo Source :
https://lh3.googleusercontent.com/V2Uo7dfIloE9Dc8ZVubnUb4yD5vGDML86sRvTP5zDB
vZpgLPYcb7_KkkrByFGzqpr4AZ0w=s89
Photo Source : https://lh3.googleusercontent.com/nToIY1SVWS0OSsohns_n29V5nu4-
oDfQJx9eH72MUY8zAiEfb1B7z0xNfaFhJdgvqZlQKw=s152
12
5.0 REAL LIFE PROJECT (Local)
5.2 Klang Valley, Malaysia
Introduction
PROJECT PROFILE
 Construction of rail-based public transportnetwork
 Light rail transit (LRT)
 Monorail
 KTM Komuter
 KLIA Express
 KLIA Transit System
 Aim : Form backbone ofpublic transportfor the Greater KL/ Klang Valley region
It compromise of:
 The external post tension tendons to the erected segmental boxed griders by using a
15.2 m multi-strand system
 HDPE smooth round ducts – house tendons comprising of19 strands each for piers
spanning of 30.00 – 39.50M
in length
 Multi strand tendons – stressed with a hydraulic jack that applies forces equivalentofup to
400 tonnes
Project Klang Valley MRTV 7
Location Kuala Lumpur, Malaysia
Developer GovernmentofMalaysia and Public Transport Commission (SPAD)
Builder Alloy MTD Construction Sdn Bhd.
Value RM 800 Million
Photo Source : https://lh3.googleusercontent.com/XKRKS2agu6gUCTJg_hqxdEoK2_rQ4BRlKup-TBI2F4b3KzzmoeknmxYnOVWdC4fApsb2JA=s148
13
 Total projecthas 106 piers providing structural support
-Light rail frame – spanning 3.6km in length
- 900 tonnes ofposttension strand to be installed by StrongForce
14
6.0 REFERENCES
Robert Sward, a. (2017).Prescribinga Bonded Post-tensioning System. STRUCTURAL TECHNOLOGIES
VSL. Retrieved 20 October 2017,from https://www.vsl.net/article/prescribing-bonded-post- tensioning-
system
Unbonded Monostrand Post-Tensioning.(2017).STRUCTURAL TECHNOLOGIES VSL. Retrieved 20
October 2017, from https://www.vsl.net/product/unbonded-monostrand-post-tensioning
Bonded Post Tensioning - noorps.com. (2017).Noorps.com. Retrieved 20 October 2017,from
http://noorps.com/page.php?6
BBR | What is post-tensioning?.(2017).Bbrnetwork.com. Retrieved 20 October 2017, from
http://www.bbrnetwork.com/technologies/what-is-pt.html
The problem with reinforced concrete. (2017).The Conversation.Retrieved 20 October 2017,
from http://theconversation.com/the-problem-with-reinforced-concrete-56078
Alkhrdaji, T. and Thomas, J. (2017). Structural Strengthening Using External Post-Tensioning Systems. [online]
STRUCTURAL. Available at: https://www.structural.net/article/structural-strengthening-using-external-
post-tensioning-systems
Author,N. (2017). Difference Between Pre-tensioning And Post-tensioning.[online] Daily Civil. Available at:
http://www.dailycivil.com/difference-pre-tensioning-post-tensioning/
Author,N. (2017). POST TENSION SERVICES INDIA PVT. LTD.. [online] Ptsindia.net. Available at:
http://ptsindia.net/pt-system.html
Author,N. (2017). Post-Tension Basics- How Post-Tensioned Slabs Are Built - The Concrete Network.[online]
Concretenetwork.com. Available at: https://www.concretenetwork.com/post-tension/basics.html
Author,N. (2017). What is Post-Tensioning.[online] STRUCTURAL TECHNOLOGIES VSL. Available at:
https://www.vsl.net/what-post-tensioning
Author,N. (2017). What is Post-Tensioning.[online] Available at:
https://buildersshow.com/Documents/course_handouts/Post-
Tensioned%20Concrete%20in%20Residential%20Construction.pdf
Bešta, J. (2017). Post-Tensioning - Post-tensioning system | VSL. [online] En.vsl.cz. Available at:
http://en.vsl.cz/post-tensioning/
Corven, J. and Moreton, A. (2017). Post-Tensioning Tendon Installation and Grouting Manual.[online]
Available at: https://www.fhwa.dot.gov/bridge/construction/pubs/hif13026.pdf
K Sengupta,D. and Menon, D. (2017). Post-tensioning Systems and Devices. [online] Available at:
http://ebooks.bharathuniv.ac.in/gdlc3/ThirdYear/SecondSem/Civil/Prestres sed%20Concrete%20Structures
/Notes/Post%20Tensioning%20Systems%20and%20Devices.pdf
Khosa, N. (2017). Cite a Website - Cite This For Me. [online] Amsyscoinc.com. Available at:
http://www.amsyscoinc.com/2010/09/14/diagram-of-post-tensioning-slab/
O Aalami, D. (2017). 10 - Step Design of Post-Tensioned Floors. [online] Available at: http://pt-
structures.com/wp-content/uploads/2010/08/10-Steps_PT_Floor_Design_US_version1.pdf
Rogers, J. (2017). Cite a Website - Cite This For Me. [online] Concreteconstruction.net.Available at:
http://www.concreteconstruction.net/how-to/construction/post-tensioned-slabs_o
Rogowsky, D. and Marti, P. (2017). DETAILING FOR POST-TENSIONED. [online] Available at:
https://www.ethz.ch/content/dam/ethz/special-interest/baug/ibk/concrete-and-bridge-design-
dam/lehre/masterstudium/Stahlbeton/Unterlagen/Detailing_for_post-tensioning.pdf

More Related Content

What's hot

Mega prefab post tension catalog
Mega prefab post tension catalog Mega prefab post tension catalog
Mega prefab post tension catalog
bassamnakfour
 
Post-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for ContractorsPost-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for Contractors
AMSYSCO Inc.
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
Parag Pal
 
2015 10 06_sem_pref_watanabe_chile_presentationoct2015(part2)
2015 10 06_sem_pref_watanabe_chile_presentationoct2015(part2)2015 10 06_sem_pref_watanabe_chile_presentationoct2015(part2)
2015 10 06_sem_pref_watanabe_chile_presentationoct2015(part2)
Instituto del cemento y Hormigón de Chile
 
Prestressed
PrestressedPrestressed
Prestressed
Anjith Augustine
 
Prestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh GhuraiyaPrestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Mukesh Singh Ghuraiya
 
Pre stress concrete
Pre stress concretePre stress concrete
Pre stress concrete
Surendra Gurjar
 
What Is Post Tensioning
What Is Post TensioningWhat Is Post Tensioning
What Is Post Tensioning
AMSYSCO Inc.
 
C:\fakepath\dsi bridge pt presentation
C:\fakepath\dsi bridge pt presentationC:\fakepath\dsi bridge pt presentation
C:\fakepath\dsi bridge pt presentationmbarroca
 
Advance Prestress Bridge
Advance Prestress BridgeAdvance Prestress Bridge
Advance Prestress Bridge
University of Tikrit
 
Prestressed construction
Prestressed constructionPrestressed construction
Prestressed construction
Vishvendu pandey
 
DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
 DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
faishalniet
 
Prestressed Concrete Basics
Prestressed Concrete BasicsPrestressed Concrete Basics
Prestressed Concrete Basics
Sachin Kulkarni
 
Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12hlksd
 
Post tensioning شد لاحق - مسبق الاجهاد
Post tensioning   شد لاحق - مسبق الاجهادPost tensioning   شد لاحق - مسبق الاجهاد
Post tensioning شد لاحق - مسبق الاجهاد
Dr.Youssef Hammida
 
Prestress concrete
Prestress concretePrestress concrete
Prestress concrete
Dhrumil Pandya
 
prestressed concrete
prestressed concreteprestressed concrete
prestressed concrete
Parag Pal
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
ghildiyal8811
 
Post Tensioning
Post TensioningPost Tensioning
Post Tensioning
Sarchia Khursheed
 
2015 10 06_sem_pref_watanabe_chile_presentationoct2015(part1)
2015 10 06_sem_pref_watanabe_chile_presentationoct2015(part1)2015 10 06_sem_pref_watanabe_chile_presentationoct2015(part1)
2015 10 06_sem_pref_watanabe_chile_presentationoct2015(part1)
Instituto del cemento y Hormigón de Chile
 

What's hot (20)

Mega prefab post tension catalog
Mega prefab post tension catalog Mega prefab post tension catalog
Mega prefab post tension catalog
 
Post-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for ContractorsPost-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for Contractors
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
2015 10 06_sem_pref_watanabe_chile_presentationoct2015(part2)
2015 10 06_sem_pref_watanabe_chile_presentationoct2015(part2)2015 10 06_sem_pref_watanabe_chile_presentationoct2015(part2)
2015 10 06_sem_pref_watanabe_chile_presentationoct2015(part2)
 
Prestressed
PrestressedPrestressed
Prestressed
 
Prestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh GhuraiyaPrestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh Ghuraiya
 
Pre stress concrete
Pre stress concretePre stress concrete
Pre stress concrete
 
What Is Post Tensioning
What Is Post TensioningWhat Is Post Tensioning
What Is Post Tensioning
 
C:\fakepath\dsi bridge pt presentation
C:\fakepath\dsi bridge pt presentationC:\fakepath\dsi bridge pt presentation
C:\fakepath\dsi bridge pt presentation
 
Advance Prestress Bridge
Advance Prestress BridgeAdvance Prestress Bridge
Advance Prestress Bridge
 
Prestressed construction
Prestressed constructionPrestressed construction
Prestressed construction
 
DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
 DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
 
Prestressed Concrete Basics
Prestressed Concrete BasicsPrestressed Concrete Basics
Prestressed Concrete Basics
 
Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12
 
Post tensioning شد لاحق - مسبق الاجهاد
Post tensioning   شد لاحق - مسبق الاجهادPost tensioning   شد لاحق - مسبق الاجهاد
Post tensioning شد لاحق - مسبق الاجهاد
 
Prestress concrete
Prestress concretePrestress concrete
Prestress concrete
 
prestressed concrete
prestressed concreteprestressed concrete
prestressed concrete
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
 
Post Tensioning
Post TensioningPost Tensioning
Post Tensioning
 
2015 10 06_sem_pref_watanabe_chile_presentationoct2015(part1)
2015 10 06_sem_pref_watanabe_chile_presentationoct2015(part1)2015 10 06_sem_pref_watanabe_chile_presentationoct2015(part1)
2015 10 06_sem_pref_watanabe_chile_presentationoct2015(part1)
 

Similar to CT3 Group Assignment Report

Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
Rajesh Burde
 
Acm Unit 1
Acm Unit 1Acm Unit 1
Acm Unit 1
Aaqib Iqbal
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
ghildiyal8811
 
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
RijuDasgupta
 
slides construction engineering 2024.pptx
slides construction engineering 2024.pptxslides construction engineering 2024.pptx
slides construction engineering 2024.pptx
nishalini16
 
Post formed holes-in_post-tensioned_slabs
Post formed holes-in_post-tensioned_slabsPost formed holes-in_post-tensioned_slabs
Post formed holes-in_post-tensioned_slabsCCL Concrete
 
Prestressing ppt
Prestressing pptPrestressing ppt
Prestressing ppt
Sudhan Sathe
 
Pre stressed concrete
Pre stressed concretePre stressed concrete
Pre stressed concretefroskhan08
 
Prestressing Concept, Materilas and Prestressing System
Prestressing Concept, Materilas and Prestressing SystemPrestressing Concept, Materilas and Prestressing System
Prestressing Concept, Materilas and Prestressing System
Latif Hyder Wadho
 
Pre stressed & pre-cast concrete technology - ce462
Pre stressed & pre-cast concrete technology - ce462Pre stressed & pre-cast concrete technology - ce462
Pre stressed & pre-cast concrete technology - ce462
Saqib Imran
 
prestressing_manual.pdf
prestressing_manual.pdfprestressing_manual.pdf
prestressing_manual.pdf
RiturajR
 
1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs
632k18BilalAhmad
 
Precast compound wall
Precast compound wallPrecast compound wall
Precast compound wall
Harsh Bothra
 
Acm assignment
Acm assignmentAcm assignment
Acm assignment
Aaqib Iqbal
 
Pre stressed concrete
Pre stressed concretePre stressed concrete
Pre stressed concrete
GPT Stvd
 
Pre-stressed concrete
Pre-stressed concrete Pre-stressed concrete
Pre-stressed concrete
aishwaryasanap
 
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURESREVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
IRJET Journal
 

Similar to CT3 Group Assignment Report (20)

Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Acm Unit 1
Acm Unit 1Acm Unit 1
Acm Unit 1
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
 
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
 
Presentation1
Presentation1Presentation1
Presentation1
 
slides construction engineering 2024.pptx
slides construction engineering 2024.pptxslides construction engineering 2024.pptx
slides construction engineering 2024.pptx
 
Post formed holes-in_post-tensioned_slabs
Post formed holes-in_post-tensioned_slabsPost formed holes-in_post-tensioned_slabs
Post formed holes-in_post-tensioned_slabs
 
Prestressing ppt
Prestressing pptPrestressing ppt
Prestressing ppt
 
Pre stressed concrete
Pre stressed concretePre stressed concrete
Pre stressed concrete
 
Prestressing Concept, Materilas and Prestressing System
Prestressing Concept, Materilas and Prestressing SystemPrestressing Concept, Materilas and Prestressing System
Prestressing Concept, Materilas and Prestressing System
 
Pre stressed & pre-cast concrete technology - ce462
Pre stressed & pre-cast concrete technology - ce462Pre stressed & pre-cast concrete technology - ce462
Pre stressed & pre-cast concrete technology - ce462
 
F029031036
F029031036F029031036
F029031036
 
FinalReport
FinalReportFinalReport
FinalReport
 
prestressing_manual.pdf
prestressing_manual.pdfprestressing_manual.pdf
prestressing_manual.pdf
 
1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs
 
Precast compound wall
Precast compound wallPrecast compound wall
Precast compound wall
 
Acm assignment
Acm assignmentAcm assignment
Acm assignment
 
Pre stressed concrete
Pre stressed concretePre stressed concrete
Pre stressed concrete
 
Pre-stressed concrete
Pre-stressed concrete Pre-stressed concrete
Pre-stressed concrete
 
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURESREVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
 

More from Wan Nee

Presentation 7-pp-final
Presentation 7-pp-finalPresentation 7-pp-final
Presentation 7-pp-final
Wan Nee
 
Professional practice-1-1-1-autosaved (1)
Professional practice-1-1-1-autosaved (1)Professional practice-1-1-1-autosaved (1)
Professional practice-1-1-1-autosaved (1)
Wan Nee
 
Structures final 20th june
Structures final 20th juneStructures final 20th june
Structures final 20th june
Wan Nee
 
Eca presentation slide (group a)
Eca presentation slide (group a)Eca presentation slide (group a)
Eca presentation slide (group a)
Wan Nee
 
Estimating final
Estimating  final Estimating  final
Estimating final
Wan Nee
 
Seminar question
Seminar questionSeminar question
Seminar question
Wan Nee
 
Estimating presentation
Estimating presentation Estimating presentation
Estimating presentation
Wan Nee
 
Evaluation brief qsb2134 tender (1)
Evaluation brief qsb2134 tender (1)Evaluation brief qsb2134 tender (1)
Evaluation brief qsb2134 tender (1)
Wan Nee
 
Estimating Assignment Brief
Estimating Assignment BriefEstimating Assignment Brief
Estimating Assignment Brief
Wan Nee
 
Estimating Assignment
Estimating AssignmentEstimating Assignment
Estimating Assignment
Wan Nee
 
Supply Chain
Supply Chain Supply Chain
Supply Chain
Wan Nee
 
Supply chain
Supply chain  Supply chain
Supply chain
Wan Nee
 
Supply chain
Supply chainSupply chain
Supply chain
Wan Nee
 
Management Science
Management Science Management Science
Management Science
Wan Nee
 
Qsb 2413 group project august 2017
Qsb 2413 group project august 2017 Qsb 2413 group project august 2017
Qsb 2413 group project august 2017
Wan Nee
 
BS 2 PRESENTATION
BS 2 PRESENTATION BS 2 PRESENTATION
BS 2 PRESENTATION
Wan Nee
 
CT 3 Group Assignment Presentation Slide
CT 3 Group Assignment Presentation SlideCT 3 Group Assignment Presentation Slide
CT 3 Group Assignment Presentation Slide
Wan Nee
 
Ct2 latest1-1 (3)
Ct2 latest1-1 (3)Ct2 latest1-1 (3)
Ct2 latest1-1 (3)
Wan Nee
 
SITE VISIT REPORT
SITE VISIT REPORTSITE VISIT REPORT
SITE VISIT REPORT
Wan Nee
 
INTEGRATED ASSIGNMENT - CT BM M
INTEGRATED ASSIGNMENT - CT BM MINTEGRATED ASSIGNMENT - CT BM M
INTEGRATED ASSIGNMENT - CT BM M
Wan Nee
 

More from Wan Nee (20)

Presentation 7-pp-final
Presentation 7-pp-finalPresentation 7-pp-final
Presentation 7-pp-final
 
Professional practice-1-1-1-autosaved (1)
Professional practice-1-1-1-autosaved (1)Professional practice-1-1-1-autosaved (1)
Professional practice-1-1-1-autosaved (1)
 
Structures final 20th june
Structures final 20th juneStructures final 20th june
Structures final 20th june
 
Eca presentation slide (group a)
Eca presentation slide (group a)Eca presentation slide (group a)
Eca presentation slide (group a)
 
Estimating final
Estimating  final Estimating  final
Estimating final
 
Seminar question
Seminar questionSeminar question
Seminar question
 
Estimating presentation
Estimating presentation Estimating presentation
Estimating presentation
 
Evaluation brief qsb2134 tender (1)
Evaluation brief qsb2134 tender (1)Evaluation brief qsb2134 tender (1)
Evaluation brief qsb2134 tender (1)
 
Estimating Assignment Brief
Estimating Assignment BriefEstimating Assignment Brief
Estimating Assignment Brief
 
Estimating Assignment
Estimating AssignmentEstimating Assignment
Estimating Assignment
 
Supply Chain
Supply Chain Supply Chain
Supply Chain
 
Supply chain
Supply chain  Supply chain
Supply chain
 
Supply chain
Supply chainSupply chain
Supply chain
 
Management Science
Management Science Management Science
Management Science
 
Qsb 2413 group project august 2017
Qsb 2413 group project august 2017 Qsb 2413 group project august 2017
Qsb 2413 group project august 2017
 
BS 2 PRESENTATION
BS 2 PRESENTATION BS 2 PRESENTATION
BS 2 PRESENTATION
 
CT 3 Group Assignment Presentation Slide
CT 3 Group Assignment Presentation SlideCT 3 Group Assignment Presentation Slide
CT 3 Group Assignment Presentation Slide
 
Ct2 latest1-1 (3)
Ct2 latest1-1 (3)Ct2 latest1-1 (3)
Ct2 latest1-1 (3)
 
SITE VISIT REPORT
SITE VISIT REPORTSITE VISIT REPORT
SITE VISIT REPORT
 
INTEGRATED ASSIGNMENT - CT BM M
INTEGRATED ASSIGNMENT - CT BM MINTEGRATED ASSIGNMENT - CT BM M
INTEGRATED ASSIGNMENT - CT BM M
 

Recently uploaded

The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
Digital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental DesignDigital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental Design
amberjdewit93
 
Best Digital Marketing Institute In NOIDA
Best Digital Marketing Institute In NOIDABest Digital Marketing Institute In NOIDA
Best Digital Marketing Institute In NOIDA
deeptiverma2406
 
Aficamten in HCM (SEQUOIA HCM TRIAL 2024)
Aficamten in HCM (SEQUOIA HCM TRIAL 2024)Aficamten in HCM (SEQUOIA HCM TRIAL 2024)
Aficamten in HCM (SEQUOIA HCM TRIAL 2024)
Ashish Kohli
 
How to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP ModuleHow to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP Module
Celine George
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
Priyankaranawat4
 
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptxChapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
Advantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO PerspectiveAdvantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO Perspective
Krisztián Száraz
 
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
RitikBhardwaj56
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
Thiyagu K
 
PIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf IslamabadPIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf Islamabad
AyyanKhan40
 
World environment day ppt For 5 June 2024
World environment day ppt For 5 June 2024World environment day ppt For 5 June 2024
World environment day ppt For 5 June 2024
ak6969907
 
DRUGS AND ITS classification slide share
DRUGS AND ITS classification slide shareDRUGS AND ITS classification slide share
DRUGS AND ITS classification slide share
taiba qazi
 
Landownership in the Philippines under the Americans-2-pptx.pptx
Landownership in the Philippines under the Americans-2-pptx.pptxLandownership in the Philippines under the Americans-2-pptx.pptx
Landownership in the Philippines under the Americans-2-pptx.pptx
JezreelCabil2
 
MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...
MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...
MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...
NelTorrente
 
Digital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion DesignsDigital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion Designs
chanes7
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
EverAndrsGuerraGuerr
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
Nguyen Thanh Tu Collection
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
Dr. Shivangi Singh Parihar
 

Recently uploaded (20)

The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
Digital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental DesignDigital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental Design
 
Best Digital Marketing Institute In NOIDA
Best Digital Marketing Institute In NOIDABest Digital Marketing Institute In NOIDA
Best Digital Marketing Institute In NOIDA
 
Aficamten in HCM (SEQUOIA HCM TRIAL 2024)
Aficamten in HCM (SEQUOIA HCM TRIAL 2024)Aficamten in HCM (SEQUOIA HCM TRIAL 2024)
Aficamten in HCM (SEQUOIA HCM TRIAL 2024)
 
How to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP ModuleHow to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP Module
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
 
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptxChapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
 
Advantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO PerspectiveAdvantages and Disadvantages of CMS from an SEO Perspective
Advantages and Disadvantages of CMS from an SEO Perspective
 
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
 
PIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf IslamabadPIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf Islamabad
 
World environment day ppt For 5 June 2024
World environment day ppt For 5 June 2024World environment day ppt For 5 June 2024
World environment day ppt For 5 June 2024
 
DRUGS AND ITS classification slide share
DRUGS AND ITS classification slide shareDRUGS AND ITS classification slide share
DRUGS AND ITS classification slide share
 
Landownership in the Philippines under the Americans-2-pptx.pptx
Landownership in the Philippines under the Americans-2-pptx.pptxLandownership in the Philippines under the Americans-2-pptx.pptx
Landownership in the Philippines under the Americans-2-pptx.pptx
 
MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...
MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...
MATATAG CURRICULUM: ASSESSING THE READINESS OF ELEM. PUBLIC SCHOOL TEACHERS I...
 
Digital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion DesignsDigital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion Designs
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
 

CT3 Group Assignment Report

  • 1. 1 CONTENTS NO. CONTENT PAGE 1. 1.1INTRODUCTION TO POST-TENSIONED 1.2 TYPICAL APPLICATIONS OF POST TENSIONING 1.3 TYPES OF POST TENSIONING 1.3.1 BONDED POST-TENSIONING 1.3.2 UNBONDED POST-TENSIONING 2-5 2. 2.0 ADVANTAGES AND DISADVANTAGES OF POST- TENSIONING 6 3. 3.0 MANUFACTURING PROCESS OF POST-TENSIONING 7 4. 4.0 PROBLEMS & SOLUTIONS IN POST TENSIONING STRUCTURAL ELEMENT 8 6. 5.0 REAL LIFE PROJECT [LOCAL & OVERSEA] 5.1 Morocco Mall ,Africa 5.2 Klang Valley, Malaysia 9-11 7. 6.0 REFERENCES 12
  • 2. 2 1.1 POST-TENSIONED Post-tensioning is simply a method of producing prestressed concrete,masonry,and other structural elements. The term prestressing is used to describe the process of introducing internal forces (or stress) into a concrete ormasonryelementduring the construction process in orderto counteractthe external loads applied when the structure is put into use (known as service loads).These internal forces are applied by tensioning high-strength steel, which can be done either before or after the concrete is placed. When the steel is tensioned after concrete placement, the process is called post- tensioning. Post-tensioned means that the concrete is poured and then the tension is applied-butit is still stressed before the loads are applied so it is still prestressed.Post-tensioned concrete which is also called as “active reinforcement“, with the primary function to place concrete structure undercompression in regions where loads causes tensile stress. Post-tensioning applies compressive stresses on the material, balancing off tensile stress on the concrete. The tension is applied by the use of a tensioning member known as “tendons”. It is a technique for reinforcing concrete. Post-tensioning tendons,which are prestressing steel cables inside plastic ducts or sleeves,are positioned in the forms before the concrete is placed.Afterwards, once the concrete has gained strength but before the service loads are applied,the cables are pulled tight, or tensioned,and anchored againstthe outer edges of the concrete. The use of post-tensioning contributes to very demanding geometryrequirements, including complex shapes andcurvature and variable superelevation.It allows long clear spans and this result in aestheicaland architectural approach.Also,it would be column- free and creates more space.In addition, it allows thinner concrete sections, stiffer walls resisting lateral loads,and stiffer foundations. Additionally, all construction joints and crack control joints could be eliminated because the slab was poured monolithically (in one whole single piece)and the post-tensioning system could provide sufficient pre-compression on the slab. Tendo ns Photo Source : https://static.concretenetwork.com/photo-gallery/images/550x412Exact_0x4/site_26/concretenetwork-com_12578.jpg
  • 3. 3 1.2 TYPICAL APPLICATIONS OF POST TENSIONING - Suspended slabs like floor slabs and terrace slabs - Foundation slabs (rafts) - Slabs on grade (office buildings,multistorey car parks,warehousesetc.) - Cantilevered structures, such as overhanging building parts. - Facade elements oflarge area;here light post-tensioning is a simple method of preventing cracks. - Main beams in the form of beams,transfer girders,lattice girders or north-light roofs. 1.3 TYPES OF POST TENSIONING There are mainly (2) types of posttensioning system, bonded orunbonded.  Bonded -The prestressing steel is installed at the site after the formwork is erected and typically after concrete is poured.It is housed in a sheating or ductto preventit from bonding to the surrounding concrete.After the concrete has hardenered orcured,the prestressing steel is gripped at both ends and then pulled and anchored to prestress the concrete.The ductwould then be filled with cementitious grout.  3 main purposes : protecttendons againstcorrosion,permanently “ lock-in” the tendon pre-tension ( thereby removing the long-term reliance upon the end-anchorage systems),improve certain structural behaviorof the final concrete structure  Unbonded -It differs by providing each individualcable permanentfreedom of movement relative to concrete.By so, each individual tendon is coated with a grease (generallyuse lithium-base)and covered by a plastic sheating formed in an extrusion process.The transfer of tension to concrete is achieved by the steel cable acting againststeel anchors embdded in the perimeter of the structural element. Single Strand POST TENSIONING a. B o nd e d P o st - b. Unbonded Post- Tensioning Single Strand Multi Strand Flat Duct Multi Strands Round Duct
  • 4. 4 1.3.1 Bonded Post-Tensioning BONDED POST-TENSIONING UNBONDED POST-TENSIONING Develops higher flexural strength Provides greater available level arm Does notdepend on anchorage after grouting Simplifies pre-fabrications of tendons Localize the effects of damages Grouting not required Simple technique for demolishing or providing future opening in slab Can be constructed faster End Cap Grout Valve Pocket Former Strands Examples: Photo Source: http://pt-structures.com/wp-content/uploads/2010/08/10- Steps_PT_Floor_Design_US_version1.pdf [Flat Duct] [Round Duct] Grout Pipe Wedges Strands Anchor Head BearingPlate Duct Photo Source: http://ptsindia.net/pt-system.html
  • 5. 5 1.3.2 Unbonded Post- Tensioning Single Strand Floor System Reinforced with Grouted Post-Tensioning System Post- Tensioned MatFoundation Using grouted Tendons Flat Duct KSA, Photo Source: http://pt-structures.com/wp-content/uploads/2010/08/10- Steps_PT_Floor_Design_US_version1.pdf Photo Source: https://lh3.googleusercontent.com/1TjXhdpEiQKGVCeuIpMKZ9DkfOqLi9QyAFQ5GdmOuG9f8CVl2dz- tN2KughnoLUM6rRCaQ=s160 Photo Source: https://lh3.googleusercontent.com/x9OONHF854Tjd7z1oDB9rKJbxqXncS5KQJSVXlxzyGICELIpggq UuBH_qrSgbPgBnF7BVGw=s113
  • 6. 6 2.0 ADVANTAGES AND DISADVANTAGES OF POST- TENSIONING ADVANTAGES DISADVANTAGES MaterialSavings - Decreased dead load reduces rebar (60%-75%) and concrete (20%) in columns and foundation Accuracy - Placementof tendon profiles has to be accurate Quicker Construction - Potential pourcycle of 3-4 days - Reducing re-shoring requirements Corrosion - Since there are a numberoftendons and Stressing Jack Tendon Tail (Additional lengthwill be cutoff) Wedges Stressing Anchor Split Pocket Former with Intermediate AnchorPocket Former Anchorage Assembly Photo Source: http://www.amsyscoinc.com/2010/09/14/diagram-of-post-tensioning-slab/ Photo Source: http://pt-structures.com/wp-content/uploads/2010/08/10- Steps_PT_Floor_Design_US_version1.pdf Example of a Floor System using the Unbonded Post-tensioning System Fortaleza, Brazil. MAT FOUNDATION USING UNBONDED TENDONS Photo Source: http://pt-structures.com/wp-content/uploads/2010/08/10- Steps_PT_Floor_Design_US_version1.p FloorSystem Reinforcedwith GroutedPost- TensioningSystem
  • 7. 7 wire spread inside the posttension slab, corrosion mayoccur.Tendencyof corrode depends on the quality of the material Increased Performance - Improve seismic performance and reduced deflection and vibration - Improved crack control and waterproofing properties Complexity ofwork - Post tension can be made only by skilful professionals. Reduced Lifetime Costs - Loweroverall maintenance and lifecycle costs of the structure - Reduced building heightalso results in energysavings, Poor workmanship leads to accidents - Main problem ofusing post tension is that if care is nottaken while making it, it can lead to future mishaps.If gaps of tendons and wiring, corrosion mayoccur which will lead to some untoward events. Flexible in design - Designs made are sleek,requires lesser space and give way to dynamic contours. Durability - Lasts longer,strong substitude of the normalconcrete Stronger/More Efficient - Less concrete and steel are needed for the same structural capacity that might form tight. - Prevents entry of insects and reducing possible water penetration which can damage flooring and cause mold problems 3.0 CONSTRUCTION PROCESS OF POST-TENSIONING SLAB [Bonded+Unbonded]
  • 8. 8 5. After anchoring a tendon atone end,the tension is applied at the other end by a jack. The tensioning of tendons and pre- compression ofconcrete occur simultaneously. A system of self- equilibrating forces develops after the stretching ofthe tendons. BONDED POST-TENSIONING UNONDED POST-TENSIONING Placing ofducts in the reinforcement 1. The ducts for the tendons are placed along with the reinforcement before the casting of concrete. The duct S are used to prevent contactbetween concrete and the tendons during the tensioning operation. The tendons are placed in the ducts after the casting ofconcrete. Casting ofconcrete 1. Concrete is casted and must achieve proper strength before the tendons are tensioned. This is typically 75% of the concrete's 28-day design strength, and is specified in the projectdocuments. Grouting the duct 2. Bonded post-tensioning - If the ducts are filled with grout. The grout is a neat cementpaste or a sand- cementmortar containing suitable admixture. The ductis notgrouted 4. Unbonded post-tensioning - Ducts not grouted and tendon is held by the end anchorages. The profile ofthe duct depends on the supportconditions. For a simply supported member, the ducthas a sagging profile between the ends. For a continuous member, the ductsags in the span and hogs over the support. Photo Source:https://www.vsl.net/what-post-tensioning Jacking oftendon 5. After anchoring a tendon at one end, the tension is applied at the other end by a jack .The tensioning of tendons and pre-compression ofconcrete occur simultaneously. A system pfself-equilibrating forces develops after the stretching oftendons. Putting on wedges and cut off tendon tail 6. After tensioning is done, they will puton the wedges to hold the tendons whereby the extra length of tendons, tendon tails will be cutoff using either oxyacetylene touch , hydraulic shear, plasma cutter, or abrasive wheel.
  • 9. 9 4.0 PROBLEMS & SOLUTIONS IN POST TENSIONING STRUCTURAL ELEMENT Honeycomb in Concrete Solution: Patching with non-shrink concrete groutmix with an epoxy binder. Grout strength should equal or exceed specified concrete strength. Do notuse grouts that contains calcium chloride or other materials containing chloride and whenever patch has attained proper strength, stressing process may proceed. Splicing of Tendons Solution: Tendons are sometimes too shortto reach an edge because of misplacementor misfabrication. Thus, making tendon couplers are necessary, the engineer ofrecord and the post-tensioning material supplier should be notified. The coupler location should be determined by post-tensioning material supplier in such that the coupler is centered in the member and nota pointof tendon curvature. Cracking Wedges Solution: Hairline cracks may appear in the case-hardened surface ofwedges due to deformation ofthe wedges around the strand at the time of seating. These cracks do notaffect the integrity of posttensioning system. Photo Source : https://lh3.googleusercontent.com/aotgRs0GAdyNUI9 AK5J_HVwG3r35me5yjy8- PxBMqnOqwMWuWhM9xOthy6gXMr_h84Z2aA=s85 Photo Source : https://lh3.googleusercontent.com/cHpL8k76 bpBOUhc3Nt3mUt508ADvWHYzNnQLG908Gr hSZIH4e93weyMk0S1OAfusio37MSI=s90 Photo Source : https://lh3.googleusercontent.com/A6LxuPDQ1Y0QRnAF FYGhdPfCKb- 0jyukxWpRV5h38or6iitlyu0vF1EDIMWfp1vm0IArFg=s85
  • 10. 10 5.0 REAL LIFE PROJECT [Overseas] 5.1Morocco Mall ,Africa Introduction Project The Morocco Mall Location ofthe project City of Casablanca,Morocco Cost Approximately US$253-million Construction company SGTM Construction Size of the project 165,000 m², 650m long structure Timeline Mid of 2008 – October 2011 CHALLENGE Large amounts of concrete were to be used in the construction, which would necessitate a large Photo Source : https://i.ytimg.com/vi/XcS24xN6c0k/maxresdefault.jpgPhoto Source : https://khamsat.hsoubcdn.com/images/services/755020/5385609b9e808442e509004c 9193ff2a.jpg
  • 11. 11 number of expansion joints, and a large numbers ofprecastslabs were to be manufactured, at odds with the tight construction timeless ofproject. SOLUTION Replace the reinforced concrete floor slabs and the precast panels with posttensioned wal Further challenges faced Building would need to contain a large number of expansion joints because the site is located less than 20 m from the Atlantic Ocean and the basementlevel is below sea level.Leaks would therefore not only pose a major inconvenience, but severely hamper progress. Also, the parking garage at the base ofbuilding contained too many supporting column which severely reduced the number ofparking bays. The building therefore need redesigned to accommodate new solution. Installation 1. Construction Site 2. Anchor Assembly 3. Stressing the strand The process being applied to the second floor ofthe Morocco Mall in the earlier stages ofconstruction. (The roofof the basementlevel) The anchor assembly graphically depicted. During the process, a tendon will have anchors on each end to transmit the force into the structure. Longer tendons, as used in the mall, also have intermediate anchors along their length. Tension is applied by using a hydraulic stressing jack which bears against anchors embedded in the concrete, pulling steel to a predetermined force or stress. Photo Source : https://lh3.googleusercontent.com/V2Uo7dfIloE9Dc8ZVubnUb4yD5vGDML86sRvTP5zDB vZpgLPYcb7_KkkrByFGzqpr4AZ0w=s89 Photo Source : https://lh3.googleusercontent.com/V2Uo7dfIloE9Dc8ZVubnUb4yD5vGDML86sRvTP5zDB vZpgLPYcb7_KkkrByFGzqpr4AZ0w=s89 Photo Source : https://lh3.googleusercontent.com/nToIY1SVWS0OSsohns_n29V5nu4- oDfQJx9eH72MUY8zAiEfb1B7z0xNfaFhJdgvqZlQKw=s152
  • 12. 12 5.0 REAL LIFE PROJECT (Local) 5.2 Klang Valley, Malaysia Introduction PROJECT PROFILE  Construction of rail-based public transportnetwork  Light rail transit (LRT)  Monorail  KTM Komuter  KLIA Express  KLIA Transit System  Aim : Form backbone ofpublic transportfor the Greater KL/ Klang Valley region It compromise of:  The external post tension tendons to the erected segmental boxed griders by using a 15.2 m multi-strand system  HDPE smooth round ducts – house tendons comprising of19 strands each for piers spanning of 30.00 – 39.50M in length  Multi strand tendons – stressed with a hydraulic jack that applies forces equivalentofup to 400 tonnes Project Klang Valley MRTV 7 Location Kuala Lumpur, Malaysia Developer GovernmentofMalaysia and Public Transport Commission (SPAD) Builder Alloy MTD Construction Sdn Bhd. Value RM 800 Million Photo Source : https://lh3.googleusercontent.com/XKRKS2agu6gUCTJg_hqxdEoK2_rQ4BRlKup-TBI2F4b3KzzmoeknmxYnOVWdC4fApsb2JA=s148
  • 13. 13  Total projecthas 106 piers providing structural support -Light rail frame – spanning 3.6km in length - 900 tonnes ofposttension strand to be installed by StrongForce
  • 14. 14 6.0 REFERENCES Robert Sward, a. (2017).Prescribinga Bonded Post-tensioning System. STRUCTURAL TECHNOLOGIES VSL. Retrieved 20 October 2017,from https://www.vsl.net/article/prescribing-bonded-post- tensioning- system Unbonded Monostrand Post-Tensioning.(2017).STRUCTURAL TECHNOLOGIES VSL. Retrieved 20 October 2017, from https://www.vsl.net/product/unbonded-monostrand-post-tensioning Bonded Post Tensioning - noorps.com. (2017).Noorps.com. Retrieved 20 October 2017,from http://noorps.com/page.php?6 BBR | What is post-tensioning?.(2017).Bbrnetwork.com. Retrieved 20 October 2017, from http://www.bbrnetwork.com/technologies/what-is-pt.html The problem with reinforced concrete. (2017).The Conversation.Retrieved 20 October 2017, from http://theconversation.com/the-problem-with-reinforced-concrete-56078 Alkhrdaji, T. and Thomas, J. (2017). Structural Strengthening Using External Post-Tensioning Systems. [online] STRUCTURAL. Available at: https://www.structural.net/article/structural-strengthening-using-external- post-tensioning-systems Author,N. (2017). Difference Between Pre-tensioning And Post-tensioning.[online] Daily Civil. Available at: http://www.dailycivil.com/difference-pre-tensioning-post-tensioning/ Author,N. (2017). POST TENSION SERVICES INDIA PVT. LTD.. [online] Ptsindia.net. Available at: http://ptsindia.net/pt-system.html Author,N. (2017). Post-Tension Basics- How Post-Tensioned Slabs Are Built - The Concrete Network.[online] Concretenetwork.com. Available at: https://www.concretenetwork.com/post-tension/basics.html Author,N. (2017). What is Post-Tensioning.[online] STRUCTURAL TECHNOLOGIES VSL. Available at: https://www.vsl.net/what-post-tensioning Author,N. (2017). What is Post-Tensioning.[online] Available at: https://buildersshow.com/Documents/course_handouts/Post- Tensioned%20Concrete%20in%20Residential%20Construction.pdf Bešta, J. (2017). Post-Tensioning - Post-tensioning system | VSL. [online] En.vsl.cz. Available at: http://en.vsl.cz/post-tensioning/ Corven, J. and Moreton, A. (2017). Post-Tensioning Tendon Installation and Grouting Manual.[online] Available at: https://www.fhwa.dot.gov/bridge/construction/pubs/hif13026.pdf K Sengupta,D. and Menon, D. (2017). Post-tensioning Systems and Devices. [online] Available at: http://ebooks.bharathuniv.ac.in/gdlc3/ThirdYear/SecondSem/Civil/Prestres sed%20Concrete%20Structures /Notes/Post%20Tensioning%20Systems%20and%20Devices.pdf Khosa, N. (2017). Cite a Website - Cite This For Me. [online] Amsyscoinc.com. Available at: http://www.amsyscoinc.com/2010/09/14/diagram-of-post-tensioning-slab/ O Aalami, D. (2017). 10 - Step Design of Post-Tensioned Floors. [online] Available at: http://pt- structures.com/wp-content/uploads/2010/08/10-Steps_PT_Floor_Design_US_version1.pdf Rogers, J. (2017). Cite a Website - Cite This For Me. [online] Concreteconstruction.net.Available at: http://www.concreteconstruction.net/how-to/construction/post-tensioned-slabs_o Rogowsky, D. and Marti, P. (2017). DETAILING FOR POST-TENSIONED. [online] Available at: https://www.ethz.ch/content/dam/ethz/special-interest/baug/ibk/concrete-and-bridge-design- dam/lehre/masterstudium/Stahlbeton/Unterlagen/Detailing_for_post-tensioning.pdf