SlideShare a Scribd company logo
INDEX
Exploration
-Design 1
-Design 2
1
2
Mock up model
-Structural Analysis
-Failure Analysis
3
4
Final Model
- Construction Process
- Structural Analysis
- Model Testing 1 -Timelapse
-Model Testing 2- Timelapse
-Success & Failure Analysis
5
6
7
8-9
10
Conclusion 11
1
Exploration –DESIGN 1
100mm away from the tip of the popsicle stick, a
2mm x 50mm slit is cut to enable interlocking of
popsicles sticks to form a interlocked square as
horizontal component of the tower.
Using the same method above, the slit is cut in the
middle of the popsicle sticks.
Cross bracing is created in order to transfer force
diagonally.
Cross bracing is slot into the vertical and horizontal
components and will be tied to the connecting point.
Advantages
•Cross bracing helps to spread the load evenly to the both sides.
•A total number of eight vertical components help to strengthen the load
carry capacity of the structure.
Disadvantages
•High shearing force between the components as the cross bracings are
not tie together with the vertical and horizontal
components.
•Middle part of the horizontal component breaks easily when a load
applies to it as it only supported by the vertical component.
1
Exploration - DESIGN 2
• A slit is cut on diagonal structure to connect to the vertical
and horizontal component.
• String is then used to tie all three components together to
overcome shear stress.
• Vertical and horizontal component are connected
with toothpick and string to create one surface.
• A slit is cut 5mm away from the hole on the horizontal
component.
• Two surfaces are connected by interlocking the
horizontal components.
Advantages
•Toothpick acts as a support to the whole structure.
•High friction between the components and the toothpick gives a
small shearing force to the components.
•A total number of eight vertical components help to strengthen the
load carry capacity of the structure.
Disadvantages
•Horizontal component cracks easily when the slit is cut too near to
the hole which as a result weakens the load carry capacity of it.
•The popsicle stick cracks easily when a force applies to the pin is
press directly into it.
•A big slit is cut in the narrow area of the diagonal component which
as a result causing it to crack.
2
From design 1 and 2, a problem that we found
was the joining part of the vertical component as
we have no idea how to connect the upper part
of the vertical component to the lower part.
Before that, we planned to join the upper part of
vertical component by overlapping it end to end
to the lower part of vertical component. However,
we found that force is not transmit vertically from
part to the other part. So, we couldn’t use the
overlapping method in these designs.
Force can’t transmit vertically to
the lower part of the vertical
component
Force transmit vertically to the
lower part of the vertical
component
In order to make the force transmits
vertically downward, we decided to join
them by connecting them end to end to
each other. In order to make them more
stable, we cut out the rounded part of
the vertical components and crafted a
inverted ‘V’. To increase their strength,
we doubled them by joining them with
toothpick.
For the horizontal components, we cut a
slit from 1cm away in the end of them and
then joined them by interlocking them to
each other to create a surface. After that,
we connect it to the vertical component
with toothpick and string like the method
of Design 1.
For the bracing, initially, we planned
to use cross bracing. However, we
found that we had overused the
popsicle stick as we only allow to use
maximum 100 sticks. So, we decided
to diagonal bracing only.
The reasons that we added bracing
was to avoid the whole structure from
shearing and also it helps to transfer
force diagonally to the next component.
Besides, we also added bracing at the
bottom of the structure to reduce force
of the vertical component and to make
the whole structure stable.
MOCK UP MODEL’s STRUCTURAL ANALYSIS
3
Inappropriate installation of the bracings
When the uneven force exerted on the tower,
compression occurred at one side of the bracings,
however bracings of opposite side will experience
tension. Due to the uneven spreading of load, the
tower will tend to fall on the side where compression
occurred.
Uneven Contact point with the load and floor
Due to the uneven length of vertical members, not
every members contact to the floor and the load
above. This will directly affect the stability of the
tower which is also the main cause for the falling of
tower when carrying load
Incompatible vertical members
The connection of the vertical members are not
consistent due to the lack of accuracy. The inverted
“V” of the vertical members were not crafted
accurately.T he contact points of the vertical
members had gaps after the tying stage. Due to the
lack of efficiency, the vertical members are crooked.
Slot to slot horizontal bracings
The cut slots weaken the load carrying capacity of
the popsicle sticks.This is due to the narrow surface
area of the lock and key joints. This had result in an
uneven surface of the square.
Unattached joints
Load cannot transfer straight down through the
unattached “V” joints. In contrast, toothpicks
withstand the load
FAILURE ANALYSIS OF MOCK UP MODEL
4
FINAL MODEL‘s CONSTRUCTION PROCESS
5
Zig Zag Pattern of Bracing Installation
Due to the uneven load distribution of the single diagonal bracing arrange in
parallel way, we change the arrangement of bracing to zigzag pattern. This is
because if one side of the tower experience greater force than the other side
,the compressive force will be offsetting by the tensile force exerting on the
opposite bracing. This will increase the strength of the tower. Other than that
,compressive force will not only concentrate on one side if uneven force
exerted
Horizontal Bracing at the Bottom
Instead of allowing only four contacting point to the floor, we improved
our design by adding one more horizontal bracing to the bottom of tower
,to increase the surface area contacting to the floor. This will further
enhance the stability of the tower and compensate the minor unequal
length of vertical members due to human error.
Changing V joints to flat joints
Due to the technical difficulty, we replaced V join by using flat join , The
straight cut surface allowed full contact with the adjoining members. When
load was applied, load can transfer straight down through the well joined
vertical members .
Using Vertical Core as Formwork
The eight vertical members are temporary attach to a vertical wooden block which
function as a guideline which result having a straight structure. BY using this
mechanism , less error will be occurred as different parts were able to collaborate
well during assembly process .As a result, the structure was firm even before the
tying process. This vertical block was also increase the accuracy and efficiency for
the construction of tower
Increased layers of thread on the joins
Bracings, vertical and horizontal members are tied as one so they are
not likely to slide or shear off. It will hold and fix the members to
prevent movement of members in pressure.
STRUCTURE ANALYSIS OF FINAL MODEL
6
Four 10kg load was put on the
model
Six 5kg load was added on
Total : 40 + 30 = 70kg
Six 2.5kg load was added on
Total :70+ 15 = 85 kg
Ten 1.25kg load was added on
Total: 85+12.5= 97.5kg
Four 5kg and four 2.5kg was added on
Total : 97.5 +30 = 127.5
One 10kg load was added was added
Total = 127.5 + 10 = 137.5
Model Testing 1 -Timelapse
7
Model testing 2 time-lapse
20kg was put on the
model.
20kg was added on
to the model.
Total: 40kg
(15+15+15kg)=
45kg was added on
to the model.
Total: 85kg (10+10+10kg)=
30kg was added on
to the model.
Total: 115kg
10kg was added on
to the model.
Total: 125kg
8
(2.5+2.5+2.5kg)=
7.5kg was added on
to the model.
Total: 162.5kg
(15+10+10+10kg)=
30kg was added on
to the model.
Total: 155kg
(2.5+2.5+2.5+1.25+
1.25kg+)= 10kg was
added on to the
model.
Total: 172.5kg
(1.25+1.25+1.25kg)
= 3.75kg was added
on to the model.
Total: 176.25kg
The upper part of
the model was
bended toward the
right.
The model
collapsed at the load
of 176.25kg.
9
ANALYSIS OF FINAL MODEL (AFTER TESTING)
After the testing, we have noticed that the breaking points
are at the connections of the vertical component. This is
because when the vertical component is under compression,
the vertical component tend to bend. When the vertical
components are bent, it becomes weaker as only one stick is
holding the weight of the load.
This problem can be overcome by reinforcing the
connections with more thread.
Before After
Efficiency = Load Held (Kg) / Mass of Tower (Grams) x Height of Tower (cm)
= 176.25kg / 108g x 30cm
= 48.96Success
The efficiency of our model is relatively high. This is due to the success of our design and
our design process. At the breaking point of our model, it can be seen that the load fell quite
vertically compared to our mock up model. This is due to the more even base of the final
model and also the stacking of the loads. In our final testing, we have ensured that the
weights are put in such a way that load is distributed evenly to the ground.
The double layer vertical component had made the model successful. We have estimated
that the load will be transferred vertically downward, hence, we reinforced the vertical
components by putting double layer. The horizontal and diagonal components have
successfully held and braced the vertical component to avoid shearing and compression.
Failure
compression
compression
compression
compression
Strength of popsicle
sticks do not
weaken when bent
Strength decreased
as only one popsicle
stick is holding the
load transmitted
through it.
10
Conclusion
From project 1, we have a better understanding of skeletal structure, its relevant structural
components, understand how a skeletal structure reacts under loading, understanding of how
it works and even be able to manipulate it to solve an oblique design problem. Therefore, we
can apply the technique into construction system design by considering the issues of
strength, stiffness and stability of structures including modes of structural systems, forces,
stress and strain and laws of static.
11

More Related Content

What's hot

Types of beams
Types of beamsTypes of beams
Types of beams
Nishant Narvekar
 
Bridge Girder Launcher Machine
Bridge Girder Launcher MachineBridge Girder Launcher Machine
Bridge Girder Launcher Machine
Jayanta Sen
 
Advance Construction Technology
Advance Construction Technology Advance Construction Technology
Advance Construction Technology
GAURAV. H .TANDON
 
Reactive powder concrete.ppt
Reactive powder  concrete.pptReactive powder  concrete.ppt
Reactive powder concrete.pptshruthicivil
 
Bridge
BridgeBridge
Bridge
anbuvsb
 
Prestress concrete
Prestress concretePrestress concrete
Prestress concrete
Dhrumil Pandya
 
Difference between control, construction, and expansion joints
Difference between control, construction, and expansion jointsDifference between control, construction, and expansion joints
Difference between control, construction, and expansion joints
scott-miller
 
Combined footing
Combined footingCombined footing
Combined footing
Pankti Gajjar
 
Numerical Modelling of Masonry Infill Walls Participation in the Seismic Beha...
Numerical Modelling of Masonry Infill Walls Participation in the Seismic Beha...Numerical Modelling of Masonry Infill Walls Participation in the Seismic Beha...
Numerical Modelling of Masonry Infill Walls Participation in the Seismic Beha...
openseesdays
 
Bridge inspection,maintenance and repair
Bridge inspection,maintenance and repairBridge inspection,maintenance and repair
Bridge inspection,maintenance and repair
KartikSuryawanshi2
 
ppt on high performance concrete (steel fibre)
ppt on high performance concrete (steel fibre)ppt on high performance concrete (steel fibre)
ppt on high performance concrete (steel fibre)
9597639444
 
Residual stresses in steel
Residual stresses in steelResidual stresses in steel
Residual stresses in steel
Koppolu Abishek
 
Structural Theory II (Part 1/2)
Structural Theory II (Part 1/2)Structural Theory II (Part 1/2)
Structural Theory II (Part 1/2)
National Chung Hsing University
 
Well foundation ppt
Well foundation pptWell foundation ppt
Well foundation ppt
Alauddin aziz khan
 
Bridge Lecture Slide by Micotol
Bridge Lecture Slide by MicotolBridge Lecture Slide by Micotol
Bridge Lecture Slide by Micotol
Micotol
 
steel structural basics
steel structural basicssteel structural basics
steel structural basics
Asan Ibrahim
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Make Mannan
 
About Bridge pier.
About Bridge pier.About Bridge pier.
About Bridge pier.
Tajul Islam
 
Design of reinforced concrete beam
Design of reinforced concrete beamDesign of reinforced concrete beam
Design of reinforced concrete beam
civilengineeringfreedownload
 

What's hot (20)

Types of beams
Types of beamsTypes of beams
Types of beams
 
Bridge Girder Launcher Machine
Bridge Girder Launcher MachineBridge Girder Launcher Machine
Bridge Girder Launcher Machine
 
Advance Construction Technology
Advance Construction Technology Advance Construction Technology
Advance Construction Technology
 
Reactive powder concrete.ppt
Reactive powder  concrete.pptReactive powder  concrete.ppt
Reactive powder concrete.ppt
 
Bridge
BridgeBridge
Bridge
 
Prestress concrete
Prestress concretePrestress concrete
Prestress concrete
 
Difference between control, construction, and expansion joints
Difference between control, construction, and expansion jointsDifference between control, construction, and expansion joints
Difference between control, construction, and expansion joints
 
Combined footing
Combined footingCombined footing
Combined footing
 
Numerical Modelling of Masonry Infill Walls Participation in the Seismic Beha...
Numerical Modelling of Masonry Infill Walls Participation in the Seismic Beha...Numerical Modelling of Masonry Infill Walls Participation in the Seismic Beha...
Numerical Modelling of Masonry Infill Walls Participation in the Seismic Beha...
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Bridge inspection,maintenance and repair
Bridge inspection,maintenance and repairBridge inspection,maintenance and repair
Bridge inspection,maintenance and repair
 
ppt on high performance concrete (steel fibre)
ppt on high performance concrete (steel fibre)ppt on high performance concrete (steel fibre)
ppt on high performance concrete (steel fibre)
 
Residual stresses in steel
Residual stresses in steelResidual stresses in steel
Residual stresses in steel
 
Structural Theory II (Part 1/2)
Structural Theory II (Part 1/2)Structural Theory II (Part 1/2)
Structural Theory II (Part 1/2)
 
Well foundation ppt
Well foundation pptWell foundation ppt
Well foundation ppt
 
Bridge Lecture Slide by Micotol
Bridge Lecture Slide by MicotolBridge Lecture Slide by Micotol
Bridge Lecture Slide by Micotol
 
steel structural basics
steel structural basicssteel structural basics
steel structural basics
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)
 
About Bridge pier.
About Bridge pier.About Bridge pier.
About Bridge pier.
 
Design of reinforced concrete beam
Design of reinforced concrete beamDesign of reinforced concrete beam
Design of reinforced concrete beam
 

Viewers also liked

Building Construction 2: Project 2 Fuksas booklet
Building Construction 2: Project 2 Fuksas bookletBuilding Construction 2: Project 2 Fuksas booklet
Building Construction 2: Project 2 Fuksas booklet
hiewyennee
 
Asian Architecture Project 2 booklet
Asian Architecture Project 2 bookletAsian Architecture Project 2 booklet
Asian Architecture Project 2 booklet
ai0819
 
Case study
Case studyCase study
Case study
Alyssia Choo
 
SITE VISIT REPORT
SITE VISIT REPORTSITE VISIT REPORT
SITE VISIT REPORT
Wan Nee
 
CT site visit report
CT site visit report CT site visit report
CT site visit report Yap Xin
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit report
Momo Poyi
 
BUILDING CONSTRUCTION 2 ; PROJECT 1 REPORT
BUILDING CONSTRUCTION 2 ; PROJECT 1 REPORTBUILDING CONSTRUCTION 2 ; PROJECT 1 REPORT
BUILDING CONSTRUCTION 2 ; PROJECT 1 REPORT
Darshiini Vig
 
Building Science 1: Project 1 Nanyang
Building Science 1: Project 1 Nanyang Building Science 1: Project 1 Nanyang
Building Science 1: Project 1 Nanyang
hiewyennee
 
Visiting report
Visiting reportVisiting report
Visiting report
drfez86
 
Building Science 1: Project 1 G- Tower
Building Science 1: Project 1 G- TowerBuilding Science 1: Project 1 G- Tower
Building Science 1: Project 1 G- Tower
hiewyennee
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)Soh Shing
 
electric Site visit
electric Site visitelectric Site visit
electric Site visit
Deepak Sharma
 
Building construction project 1 report
Building construction project 1 reportBuilding construction project 1 report
Building construction project 1 reportchenliang923
 
Contribution of Women in our society
Contribution of Women in our societyContribution of Women in our society
Contribution of Women in our society
Student
 
Building Construction Project 1 Shelter Report
Building Construction Project 1 Shelter ReportBuilding Construction Project 1 Shelter Report
Building Construction Project 1 Shelter ReportJoyeeLee0131
 
Site visit report
Site visit reportSite visit report
Site visit report
Jordon Wong
 
Building construction 2 project 1 report
Building construction 2 project 1 reportBuilding construction 2 project 1 report
Building construction 2 project 1 report
Ong Seng Peng Jeff
 
building construction project 1 report
building construction project 1 reportbuilding construction project 1 report
building construction project 1 report
Yq Chong
 
Site visit report
Site visit report Site visit report
Site visit report
Liming Hiew
 
Site Visit report- Measurement I, Building materials, Construction Technology I
Site Visit report- Measurement I, Building materials, Construction Technology ISite Visit report- Measurement I, Building materials, Construction Technology I
Site Visit report- Measurement I, Building materials, Construction Technology I
kaiwenyeo
 

Viewers also liked (20)

Building Construction 2: Project 2 Fuksas booklet
Building Construction 2: Project 2 Fuksas bookletBuilding Construction 2: Project 2 Fuksas booklet
Building Construction 2: Project 2 Fuksas booklet
 
Asian Architecture Project 2 booklet
Asian Architecture Project 2 bookletAsian Architecture Project 2 booklet
Asian Architecture Project 2 booklet
 
Case study
Case studyCase study
Case study
 
SITE VISIT REPORT
SITE VISIT REPORTSITE VISIT REPORT
SITE VISIT REPORT
 
CT site visit report
CT site visit report CT site visit report
CT site visit report
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit report
 
BUILDING CONSTRUCTION 2 ; PROJECT 1 REPORT
BUILDING CONSTRUCTION 2 ; PROJECT 1 REPORTBUILDING CONSTRUCTION 2 ; PROJECT 1 REPORT
BUILDING CONSTRUCTION 2 ; PROJECT 1 REPORT
 
Building Science 1: Project 1 Nanyang
Building Science 1: Project 1 Nanyang Building Science 1: Project 1 Nanyang
Building Science 1: Project 1 Nanyang
 
Visiting report
Visiting reportVisiting report
Visiting report
 
Building Science 1: Project 1 G- Tower
Building Science 1: Project 1 G- TowerBuilding Science 1: Project 1 G- Tower
Building Science 1: Project 1 G- Tower
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)
 
electric Site visit
electric Site visitelectric Site visit
electric Site visit
 
Building construction project 1 report
Building construction project 1 reportBuilding construction project 1 report
Building construction project 1 report
 
Contribution of Women in our society
Contribution of Women in our societyContribution of Women in our society
Contribution of Women in our society
 
Building Construction Project 1 Shelter Report
Building Construction Project 1 Shelter ReportBuilding Construction Project 1 Shelter Report
Building Construction Project 1 Shelter Report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Building construction 2 project 1 report
Building construction 2 project 1 reportBuilding construction 2 project 1 report
Building construction 2 project 1 report
 
building construction project 1 report
building construction project 1 reportbuilding construction project 1 report
building construction project 1 report
 
Site visit report
Site visit report Site visit report
Site visit report
 
Site Visit report- Measurement I, Building materials, Construction Technology I
Site Visit report- Measurement I, Building materials, Construction Technology ISite Visit report- Measurement I, Building materials, Construction Technology I
Site Visit report- Measurement I, Building materials, Construction Technology I
 

Similar to Building Construction 2 Project 1 Report

Bcon report final
Bcon report finalBcon report final
Bcon report final
Teo Kean Hui
 
Bcon report final
Bcon report finalBcon report final
Bcon report final
Christiody Lim
 
Bcon report final
Bcon report finalBcon report final
Bcon report final
Daniel Yap
 
Report - Project 1 [BCON2]
Report - Project 1 [BCON2]Report - Project 1 [BCON2]
Report - Project 1 [BCON2]
Esther Lau
 
Building Construction tower project
Building Construction tower projectBuilding Construction tower project
Building Construction tower project
XingYue0907
 
Report 10.0 bcon xing
Report 10.0 bcon xingReport 10.0 bcon xing
Report 10.0 bcon xingElaine Bong
 
Building construction report
Building construction reportBuilding construction report
Building construction reportmiranazrin
 
Building Construction Project 1 Report
Building Construction Project 1 ReportBuilding Construction Project 1 Report
Building Construction Project 1 Report
Sürayyn Selvan
 
Building construction report
Building construction reportBuilding construction report
Building construction report
Soh Shing
 
Building construction report
Building construction reportBuilding construction report
Building construction reportJannah Jailani
 
Assignment 1 bcons report
Assignment 1 bcons reportAssignment 1 bcons report
Assignment 1 bcons report
Adila Zaas
 
Assignment 1 bcons 2 report
Assignment 1 bcons 2 reportAssignment 1 bcons 2 report
Assignment 1 bcons 2 reportYaseen Syed
 
BCON II PROJECT 1
BCON II PROJECT 1BCON II PROJECT 1
BCON II PROJECT 1
Lim Zhao Yin
 
bus shelter
bus shelterbus shelter
bus shelter
James Ooi
 
Bcon project 1 pdf report
Bcon project 1 pdf reportBcon project 1 pdf report
Bcon project 1 pdf report
Anderson Wong
 
Fettucine Truss Bridge Report
Fettucine Truss Bridge ReportFettucine Truss Bridge Report
Fettucine Truss Bridge Report
kimberlywjs
 
Final project mec e 3
Final project mec e 3Final project mec e 3
Final project mec e 3
Johann Ortiz-Franco
 
ResQJack
ResQJackResQJack
Angle bracket with and without gusset
Angle bracket with and without gussetAngle bracket with and without gusset
Angle bracket with and without gusset
PiyaliDey14
 

Similar to Building Construction 2 Project 1 Report (20)

Bcon report final
Bcon report finalBcon report final
Bcon report final
 
Bcon report final
Bcon report finalBcon report final
Bcon report final
 
Bcon report final
Bcon report finalBcon report final
Bcon report final
 
Report - Project 1 [BCON2]
Report - Project 1 [BCON2]Report - Project 1 [BCON2]
Report - Project 1 [BCON2]
 
Building Construction tower project
Building Construction tower projectBuilding Construction tower project
Building Construction tower project
 
Report 10.0 bcon xing
Report 10.0 bcon xingReport 10.0 bcon xing
Report 10.0 bcon xing
 
Final
FinalFinal
Final
 
Building construction report
Building construction reportBuilding construction report
Building construction report
 
Building Construction Project 1 Report
Building Construction Project 1 ReportBuilding Construction Project 1 Report
Building Construction Project 1 Report
 
Building construction report
Building construction reportBuilding construction report
Building construction report
 
Building construction report
Building construction reportBuilding construction report
Building construction report
 
Assignment 1 bcons report
Assignment 1 bcons reportAssignment 1 bcons report
Assignment 1 bcons report
 
Assignment 1 bcons 2 report
Assignment 1 bcons 2 reportAssignment 1 bcons 2 report
Assignment 1 bcons 2 report
 
BCON II PROJECT 1
BCON II PROJECT 1BCON II PROJECT 1
BCON II PROJECT 1
 
bus shelter
bus shelterbus shelter
bus shelter
 
Bcon project 1 pdf report
Bcon project 1 pdf reportBcon project 1 pdf report
Bcon project 1 pdf report
 
Fettucine Truss Bridge Report
Fettucine Truss Bridge ReportFettucine Truss Bridge Report
Fettucine Truss Bridge Report
 
Final project mec e 3
Final project mec e 3Final project mec e 3
Final project mec e 3
 
ResQJack
ResQJackResQJack
ResQJack
 
Angle bracket with and without gusset
Angle bracket with and without gussetAngle bracket with and without gusset
Angle bracket with and without gusset
 

Recently uploaded

一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
h7j5io0
 
Top 5 Indian Style Modular Kitchen Designs
Top 5 Indian Style Modular Kitchen DesignsTop 5 Indian Style Modular Kitchen Designs
Top 5 Indian Style Modular Kitchen Designs
Finzo Kitchens
 
Common Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid themCommon Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid them
madhavlakhanpal29
 
Top Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdfTop Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdf
PlanitIsrael
 
Expert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting ServicesExpert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting Services
ResDraft
 
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
smpc3nvg
 
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
h7j5io0
 
20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf
ameli25062005
 
Borys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior designBorys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior design
boryssutkowski
 
Transforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting ProfitabilityTransforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting Profitability
aaryangarg12
 
White wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva TschoppWhite wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva Tschopp
Mansi Shah
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
cy0krjxt
 
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
7sd8fier
 
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
jyz59f4j
 
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
9a93xvy
 
CA OFFICE office office office _VIEWS.pdf
CA OFFICE office office office _VIEWS.pdfCA OFFICE office office office _VIEWS.pdf
CA OFFICE office office office _VIEWS.pdf
SudhanshuMandlik
 
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdfPORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
fabianavillanib
 
Portfolio.pdf
Portfolio.pdfPortfolio.pdf
Portfolio.pdf
garcese
 
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
smpc3nvg
 
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
taqyed
 

Recently uploaded (20)

一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
 
Top 5 Indian Style Modular Kitchen Designs
Top 5 Indian Style Modular Kitchen DesignsTop 5 Indian Style Modular Kitchen Designs
Top 5 Indian Style Modular Kitchen Designs
 
Common Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid themCommon Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid them
 
Top Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdfTop Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdf
 
Expert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting ServicesExpert Accessory Dwelling Unit (ADU) Drafting Services
Expert Accessory Dwelling Unit (ADU) Drafting Services
 
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
 
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
 
20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf
 
Borys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior designBorys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior design
 
Transforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting ProfitabilityTransforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting Profitability
 
White wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva TschoppWhite wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva Tschopp
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
 
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
 
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
一比一原版(LSE毕业证书)伦敦政治经济学院毕业证成绩单如何办理
 
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
 
CA OFFICE office office office _VIEWS.pdf
CA OFFICE office office office _VIEWS.pdfCA OFFICE office office office _VIEWS.pdf
CA OFFICE office office office _VIEWS.pdf
 
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdfPORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
 
Portfolio.pdf
Portfolio.pdfPortfolio.pdf
Portfolio.pdf
 
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
 
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
 

Building Construction 2 Project 1 Report

  • 1. INDEX Exploration -Design 1 -Design 2 1 2 Mock up model -Structural Analysis -Failure Analysis 3 4 Final Model - Construction Process - Structural Analysis - Model Testing 1 -Timelapse -Model Testing 2- Timelapse -Success & Failure Analysis 5 6 7 8-9 10 Conclusion 11 1
  • 2. Exploration –DESIGN 1 100mm away from the tip of the popsicle stick, a 2mm x 50mm slit is cut to enable interlocking of popsicles sticks to form a interlocked square as horizontal component of the tower. Using the same method above, the slit is cut in the middle of the popsicle sticks. Cross bracing is created in order to transfer force diagonally. Cross bracing is slot into the vertical and horizontal components and will be tied to the connecting point. Advantages •Cross bracing helps to spread the load evenly to the both sides. •A total number of eight vertical components help to strengthen the load carry capacity of the structure. Disadvantages •High shearing force between the components as the cross bracings are not tie together with the vertical and horizontal components. •Middle part of the horizontal component breaks easily when a load applies to it as it only supported by the vertical component. 1
  • 3. Exploration - DESIGN 2 • A slit is cut on diagonal structure to connect to the vertical and horizontal component. • String is then used to tie all three components together to overcome shear stress. • Vertical and horizontal component are connected with toothpick and string to create one surface. • A slit is cut 5mm away from the hole on the horizontal component. • Two surfaces are connected by interlocking the horizontal components. Advantages •Toothpick acts as a support to the whole structure. •High friction between the components and the toothpick gives a small shearing force to the components. •A total number of eight vertical components help to strengthen the load carry capacity of the structure. Disadvantages •Horizontal component cracks easily when the slit is cut too near to the hole which as a result weakens the load carry capacity of it. •The popsicle stick cracks easily when a force applies to the pin is press directly into it. •A big slit is cut in the narrow area of the diagonal component which as a result causing it to crack. 2
  • 4. From design 1 and 2, a problem that we found was the joining part of the vertical component as we have no idea how to connect the upper part of the vertical component to the lower part. Before that, we planned to join the upper part of vertical component by overlapping it end to end to the lower part of vertical component. However, we found that force is not transmit vertically from part to the other part. So, we couldn’t use the overlapping method in these designs. Force can’t transmit vertically to the lower part of the vertical component Force transmit vertically to the lower part of the vertical component In order to make the force transmits vertically downward, we decided to join them by connecting them end to end to each other. In order to make them more stable, we cut out the rounded part of the vertical components and crafted a inverted ‘V’. To increase their strength, we doubled them by joining them with toothpick. For the horizontal components, we cut a slit from 1cm away in the end of them and then joined them by interlocking them to each other to create a surface. After that, we connect it to the vertical component with toothpick and string like the method of Design 1. For the bracing, initially, we planned to use cross bracing. However, we found that we had overused the popsicle stick as we only allow to use maximum 100 sticks. So, we decided to diagonal bracing only. The reasons that we added bracing was to avoid the whole structure from shearing and also it helps to transfer force diagonally to the next component. Besides, we also added bracing at the bottom of the structure to reduce force of the vertical component and to make the whole structure stable. MOCK UP MODEL’s STRUCTURAL ANALYSIS 3
  • 5. Inappropriate installation of the bracings When the uneven force exerted on the tower, compression occurred at one side of the bracings, however bracings of opposite side will experience tension. Due to the uneven spreading of load, the tower will tend to fall on the side where compression occurred. Uneven Contact point with the load and floor Due to the uneven length of vertical members, not every members contact to the floor and the load above. This will directly affect the stability of the tower which is also the main cause for the falling of tower when carrying load Incompatible vertical members The connection of the vertical members are not consistent due to the lack of accuracy. The inverted “V” of the vertical members were not crafted accurately.T he contact points of the vertical members had gaps after the tying stage. Due to the lack of efficiency, the vertical members are crooked. Slot to slot horizontal bracings The cut slots weaken the load carrying capacity of the popsicle sticks.This is due to the narrow surface area of the lock and key joints. This had result in an uneven surface of the square. Unattached joints Load cannot transfer straight down through the unattached “V” joints. In contrast, toothpicks withstand the load FAILURE ANALYSIS OF MOCK UP MODEL 4
  • 7. Zig Zag Pattern of Bracing Installation Due to the uneven load distribution of the single diagonal bracing arrange in parallel way, we change the arrangement of bracing to zigzag pattern. This is because if one side of the tower experience greater force than the other side ,the compressive force will be offsetting by the tensile force exerting on the opposite bracing. This will increase the strength of the tower. Other than that ,compressive force will not only concentrate on one side if uneven force exerted Horizontal Bracing at the Bottom Instead of allowing only four contacting point to the floor, we improved our design by adding one more horizontal bracing to the bottom of tower ,to increase the surface area contacting to the floor. This will further enhance the stability of the tower and compensate the minor unequal length of vertical members due to human error. Changing V joints to flat joints Due to the technical difficulty, we replaced V join by using flat join , The straight cut surface allowed full contact with the adjoining members. When load was applied, load can transfer straight down through the well joined vertical members . Using Vertical Core as Formwork The eight vertical members are temporary attach to a vertical wooden block which function as a guideline which result having a straight structure. BY using this mechanism , less error will be occurred as different parts were able to collaborate well during assembly process .As a result, the structure was firm even before the tying process. This vertical block was also increase the accuracy and efficiency for the construction of tower Increased layers of thread on the joins Bracings, vertical and horizontal members are tied as one so they are not likely to slide or shear off. It will hold and fix the members to prevent movement of members in pressure. STRUCTURE ANALYSIS OF FINAL MODEL 6
  • 8. Four 10kg load was put on the model Six 5kg load was added on Total : 40 + 30 = 70kg Six 2.5kg load was added on Total :70+ 15 = 85 kg Ten 1.25kg load was added on Total: 85+12.5= 97.5kg Four 5kg and four 2.5kg was added on Total : 97.5 +30 = 127.5 One 10kg load was added was added Total = 127.5 + 10 = 137.5 Model Testing 1 -Timelapse 7
  • 9. Model testing 2 time-lapse 20kg was put on the model. 20kg was added on to the model. Total: 40kg (15+15+15kg)= 45kg was added on to the model. Total: 85kg (10+10+10kg)= 30kg was added on to the model. Total: 115kg 10kg was added on to the model. Total: 125kg 8
  • 10. (2.5+2.5+2.5kg)= 7.5kg was added on to the model. Total: 162.5kg (15+10+10+10kg)= 30kg was added on to the model. Total: 155kg (2.5+2.5+2.5+1.25+ 1.25kg+)= 10kg was added on to the model. Total: 172.5kg (1.25+1.25+1.25kg) = 3.75kg was added on to the model. Total: 176.25kg The upper part of the model was bended toward the right. The model collapsed at the load of 176.25kg. 9
  • 11. ANALYSIS OF FINAL MODEL (AFTER TESTING) After the testing, we have noticed that the breaking points are at the connections of the vertical component. This is because when the vertical component is under compression, the vertical component tend to bend. When the vertical components are bent, it becomes weaker as only one stick is holding the weight of the load. This problem can be overcome by reinforcing the connections with more thread. Before After Efficiency = Load Held (Kg) / Mass of Tower (Grams) x Height of Tower (cm) = 176.25kg / 108g x 30cm = 48.96Success The efficiency of our model is relatively high. This is due to the success of our design and our design process. At the breaking point of our model, it can be seen that the load fell quite vertically compared to our mock up model. This is due to the more even base of the final model and also the stacking of the loads. In our final testing, we have ensured that the weights are put in such a way that load is distributed evenly to the ground. The double layer vertical component had made the model successful. We have estimated that the load will be transferred vertically downward, hence, we reinforced the vertical components by putting double layer. The horizontal and diagonal components have successfully held and braced the vertical component to avoid shearing and compression. Failure compression compression compression compression Strength of popsicle sticks do not weaken when bent Strength decreased as only one popsicle stick is holding the load transmitted through it. 10
  • 12. Conclusion From project 1, we have a better understanding of skeletal structure, its relevant structural components, understand how a skeletal structure reacts under loading, understanding of how it works and even be able to manipulate it to solve an oblique design problem. Therefore, we can apply the technique into construction system design by considering the issues of strength, stiffness and stability of structures including modes of structural systems, forces, stress and strain and laws of static. 11