Program Evaluation and Review Technique procedure, BBA Notes, Estimating Activity Times, Optimistic Time(t0), Most Likely Time, Pessimistic Time, PERT, Steps involved in PERT calculations, te=to+4tm+tp /6
The critical path method (CPM) is a step-by-step project management technique for process planning that defines critical and non-critical tasks with the goal of preventing time-frame problems and process bottlenecks. The CPM is ideally suited to projects consisting of numerous activities that interact in a complex manner.
Network Techniques for Project ManagementIshan Gandhi
Undertaking a Project and Looking to manage the Time and Resources? This presentation provides a complete guide on how to manage the time and resources of a project.
Objectives of Network Analysis for Project Management:
1. To minimize idle resources.
2. To minimize the total project cost.
3. To trade-off between time and cost of the project.
4. To minimize production delays, interruptions and conflicts.
5. To minimize the total project duration.
Pert program evaluation and preview technique, PERTBalasri Kamarapu
Program Evaluation and Review Technique procedure, BBA Notes, Estimating Activity Times, Optimistic Time(t0), Most Likely Time, Pessimistic Time, PERT, Steps involved in PERT calculations, te=to+4tm+tp /6
The critical path method (CPM) is a step-by-step project management technique for process planning that defines critical and non-critical tasks with the goal of preventing time-frame problems and process bottlenecks. The CPM is ideally suited to projects consisting of numerous activities that interact in a complex manner.
Network Techniques for Project ManagementIshan Gandhi
Undertaking a Project and Looking to manage the Time and Resources? This presentation provides a complete guide on how to manage the time and resources of a project.
Objectives of Network Analysis for Project Management:
1. To minimize idle resources.
2. To minimize the total project cost.
3. To trade-off between time and cost of the project.
4. To minimize production delays, interruptions and conflicts.
5. To minimize the total project duration.
Free float and total float - PMP/CAPM from PMIMudassir Iqbal
https://www.mudassiriqbal.net/project-management-terms-and-concepts
There are many concepts and definitions which require special attention by all PMP Aspirants as the terminologies are largely used interchangeably in the real world.
Free float and total float - PMP/CAPM from PMIMudassir Iqbal
https://www.mudassiriqbal.net/project-management-terms-and-concepts
There are many concepts and definitions which require special attention by all PMP Aspirants as the terminologies are largely used interchangeably in the real world.
Generating a custom Ruby SDK for your web service or Rails API using Smithyg2nightmarescribd
Have you ever wanted a Ruby client API to communicate with your web service? Smithy is a protocol-agnostic language for defining services and SDKs. Smithy Ruby is an implementation of Smithy that generates a Ruby SDK using a Smithy model. In this talk, we will explore Smithy and Smithy Ruby to learn how to generate custom feature-rich SDKs that can communicate with any web service, such as a Rails JSON API.
JMeter webinar - integration with InfluxDB and GrafanaRTTS
Watch this recorded webinar about real-time monitoring of application performance. See how to integrate Apache JMeter, the open-source leader in performance testing, with InfluxDB, the open-source time-series database, and Grafana, the open-source analytics and visualization application.
In this webinar, we will review the benefits of leveraging InfluxDB and Grafana when executing load tests and demonstrate how these tools are used to visualize performance metrics.
Length: 30 minutes
Session Overview
-------------------------------------------
During this webinar, we will cover the following topics while demonstrating the integrations of JMeter, InfluxDB and Grafana:
- What out-of-the-box solutions are available for real-time monitoring JMeter tests?
- What are the benefits of integrating InfluxDB and Grafana into the load testing stack?
- Which features are provided by Grafana?
- Demonstration of InfluxDB and Grafana using a practice web application
To view the webinar recording, go to:
https://www.rttsweb.com/jmeter-integration-webinar
Connector Corner: Automate dynamic content and events by pushing a buttonDianaGray10
Here is something new! In our next Connector Corner webinar, we will demonstrate how you can use a single workflow to:
Create a campaign using Mailchimp with merge tags/fields
Send an interactive Slack channel message (using buttons)
Have the message received by managers and peers along with a test email for review
But there’s more:
In a second workflow supporting the same use case, you’ll see:
Your campaign sent to target colleagues for approval
If the “Approve” button is clicked, a Jira/Zendesk ticket is created for the marketing design team
But—if the “Reject” button is pushed, colleagues will be alerted via Slack message
Join us to learn more about this new, human-in-the-loop capability, brought to you by Integration Service connectors.
And...
Speakers:
Akshay Agnihotri, Product Manager
Charlie Greenberg, Host
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Ramesh Iyer
In today's fast-changing business world, Companies that adapt and embrace new ideas often need help to keep up with the competition. However, fostering a culture of innovation takes much work. It takes vision, leadership and willingness to take risks in the right proportion. Sachin Dev Duggal, co-founder of Builder.ai, has perfected the art of this balance, creating a company culture where creativity and growth are nurtured at each stage.
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...UiPathCommunity
💥 Speed, accuracy, and scaling – discover the superpowers of GenAI in action with UiPath Document Understanding and Communications Mining™:
See how to accelerate model training and optimize model performance with active learning
Learn about the latest enhancements to out-of-the-box document processing – with little to no training required
Get an exclusive demo of the new family of UiPath LLMs – GenAI models specialized for processing different types of documents and messages
This is a hands-on session specifically designed for automation developers and AI enthusiasts seeking to enhance their knowledge in leveraging the latest intelligent document processing capabilities offered by UiPath.
Speakers:
👨🏫 Andras Palfi, Senior Product Manager, UiPath
👩🏫 Lenka Dulovicova, Product Program Manager, UiPath
GraphRAG is All You need? LLM & Knowledge GraphGuy Korland
Guy Korland, CEO and Co-founder of FalkorDB, will review two articles on the integration of language models with knowledge graphs.
1. Unifying Large Language Models and Knowledge Graphs: A Roadmap.
https://arxiv.org/abs/2306.08302
2. Microsoft Research's GraphRAG paper and a review paper on various uses of knowledge graphs:
https://www.microsoft.com/en-us/research/blog/graphrag-unlocking-llm-discovery-on-narrative-private-data/
Elevating Tactical DDD Patterns Through Object CalisthenicsDorra BARTAGUIZ
After immersing yourself in the blue book and its red counterpart, attending DDD-focused conferences, and applying tactical patterns, you're left with a crucial question: How do I ensure my design is effective? Tactical patterns within Domain-Driven Design (DDD) serve as guiding principles for creating clear and manageable domain models. However, achieving success with these patterns requires additional guidance. Interestingly, we've observed that a set of constraints initially designed for training purposes remarkably aligns with effective pattern implementation, offering a more ‘mechanical’ approach. Let's explore together how Object Calisthenics can elevate the design of your tactical DDD patterns, offering concrete help for those venturing into DDD for the first time!
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf91mobiles
91mobiles recently conducted a Smart TV Buyer Insights Survey in which we asked over 3,000 respondents about the TV they own, aspects they look at on a new TV, and their TV buying preferences.
Neuro-symbolic is not enough, we need neuro-*semantic*Frank van Harmelen
Neuro-symbolic (NeSy) AI is on the rise. However, simply machine learning on just any symbolic structure is not sufficient to really harvest the gains of NeSy. These will only be gained when the symbolic structures have an actual semantics. I give an operational definition of semantics as “predictable inference”.
All of this illustrated with link prediction over knowledge graphs, but the argument is general.
2. • Science Behind SchedulingTopic
• One HourPlanned Duration
• Open
Type of
Interaction
• Management Sciences
Area of
Knowledge
3. Definition
•Brief History and Evaluation of Scheduling
•What is Scheduling
Explanation
•Definition of related terms
•The Process of Schedule Development
Example
•Practical
4. The concept of Scheduling is not new; Sun Tzu
wrote about scheduling and strategy about
5000 years ago from a military prospective
Pyramids in Egypt (3000 years ago approx),
Transcontinental railways (200 years) ago;
None of these could have been accomplished
without some sort of scheduling i.e.,
understanding of activities and sequencing.
5. Henry L Gantt An American engineer and social scientist
invented a bar chart which we know as Gantt Chart - 1917
Kelley and Walker invented CPM -1956-57
The Pert Project invented the name “Critical Path” and
everyone else borrowed it -1957
In 1968 PERT and CPM emerged as a standard
nomenclatures
Dr. Fondhal invented a non- computerized methodology for
scheduling which is being used by every scheduling
computer package today (Precedence Diagramming Method
-1977 )
The Science of Scheduling as defined by Critical Path
Analysis “CPA” celebrated its 50th Anniversary in 2007.
6. The term Schedule means
Arrange or plan (an event) to take place at a
particular time.
Make arrangements for (someone or
something) to do something.
7. Work Breakdown Structure
Work Package
Decomposition
Rolling Wave Planning
Schedule Compression
◦ Crashing
◦ Fast Tracking
9. According to Project Management Institute, The
Following is the process from Start to End in order to
create a Project Schedule
Activity Definition
Activity Sequencing
Activity Resource Estimating
Activity Duration Estimating
Schedule Development
Schedule Control
10. Activity Definition is a process of defining
the Activities which are part of scope of
work in order to complete the Project
We drive the following things after Activity
Definition process
◦ Activity List
◦ Activity Attributes
◦ Milestone List
11. For Activity Sequencing , different
Techniques can be used which are
◦ Precedence Diagramming Method (AON)
◦ Activities can have four types of
dependencies under this method which
are
Finish to Start
Start to Start
Start to Finish
Finish to Finish
12. ◦ Arrow Diagramming Method
◦ Activities can have one type of
dependency under this method which is
Finish to Start
13. Durations in Project Network Diagram are
calculated by using the following
Early Start
Early Finish
Late Start
Late Finish
Forward Pass Calculation
Backward Pass Calculation
14. Activity Resource Estimation is a
process where the resources
(physical, human, infrastructure) are
determined
Top down or
Bottom up
Estimation
15. Activity Duration Estimation is a process where
the duration against each Activity is calculated.
Following Techniques can be used to calculated
Duration for activity
◦ Analogous Estimating
◦ Parametric Estimating
◦ Three Point Estimate or PERT Estimate
Reserve Analysis
18. ◦ Following are some methods to develop
the Project Schedule
◦ Project Network Diagram Method
◦ Critical Path Method, longest path in
project network diagram
◦ Critical Chain Method , adjusted schedule
after incorporating dead lines and
resources constraints in critical path
method
19.
20. Suppose we have a project with Following
Activities
Start
Requirement Analysis -TASK 1 – 3 Days
Development - TASK 2 – 10 Days
Installation - TASK 3 - 6 Days
Deployment - TASK 4 - 8 Days
UAT - TASK 5 - 4 Days
Close
21. Second Step would be to find the
dependencies among activities and draw a
network diagram
Lets say we have only Finish to Start
Relationship between activities as under
Start-TASK 1-TASK 2- TASK 5-End
Start –TASK 1-TASK3-TASK4-TASK5-End
22. Let us Calculate Early Start and Early Finish of
Theses Tasks by Forward Pass.