SlideShare a Scribd company logo
Project Evaluation Review
Technique (PERT)
DR.ANJALATCHI
M.SC(N)MD(AM)MBA(HA)
LEARNING OBJECTIVES
• Introduce the topic
• Definition
• Need /overview
• History
• Concept and terminology
• Network analysis
• Creating PERT chart
• Components of PERT
Continued
• Steps of PERT
• Uses of PERT
• Advantages of PERT
• Disadvantages of PERT
• Limitation of PERT
• Summary
• Conclusion
• References
Introduction PERT
• In project management, the Project Evaluation
Review Technique, or PERT, is used to identify the
time it takes to finish a particular task or activity.
It is a system that helps in proper scheduling and
coordination of all tasks throughout a project. It
also helps in keeping track of the progress, or lack
thereof, of the overall project. In the 1950s, the
Project Evaluation Review Technique was
developed by the US Navy to manage the Polaris
submarine missile program of their Special
Projects Office.
Continued
• Knowing the time it should take to execute a
project is crucial, as it helps project managers
decide on other factors such as the budget
and task delegation. No matter how big or
small a project is, estimates can be too
optimistic or pessimistic, but using a PERT
chart will help determine realistic estimates.
OVERVIEW
Meaning of PERT
• PERT is a project management planning tool
used to calculate the amount of time it will
take to realistically finish a
project. PERT stands for Program Evaluation
Review Technique.
DEFINITION OF PERT
HISTORY
CONCEPT AND TERMS
CONTINUED
CONTINUED
The network diagram
Continued
COMPONENTS
CONTINUED
CONTINUED
PERT CHART
Creating a PERT Chart
• A flowchart is used to depict the Project
Evaluation Review Technique. Nodes
represent the events, indicating the start or
end of activities or tasks. The directorial lines
indicate the tasks that need to be completed,
and the arrows show the sequence of the
activities.
four definitions of time used to
estimate
• There are four definitions of time used to estimate
project time requirements:
• Optimistic time – The least amount of time it can take
to complete a task
• Pessimistic time – The maximum amount of time it
should take to complete a task
• Most likely time – Assuming there are no problems, the
best, or most reasonable, estimate of how long it
should take to complete a task.
• Expected time – Assuming there are problems, the best
estimate of how much time will be required to
Estimate Activity Time
• Optimistic time :generally the shortest time in
which the activity can be completed.
• Most likely Time: the completion time having
the highest probability.
• Pessimistic time: the longest time that having
activity might require.
Steps of PERT analysis
• 1. identify the specific activities and milestones
• 2. determines the proper sequences of the
activities
• 3. construct a network diagram
• 4. estimate the time required for each activity
• 5.determine the critical path
• 6.updates the PERT charts as the project
progresses.
CONTINUED
Four quantities for each activity
• ES-earliest start time
• EF-Earliest Finish time
• LS-latest Start Time
• LF-Latest Finish Time
Here are several terms used in a PERT
chart:
• Float/Slack – Refers to the amount of time a task can be delayed
without resulting in an overall delay in completion of other tasks or
the project
• Critical Path – Indicates the longest possible continuous path from
the start to the end of a task or event
• Critical Path Activity – Refers to an activity without any slack
• Lead Time – Refers to the amount of time needed to finish a task
without affecting subsequent tasks
• Lag Time – The earliest time by which a successor event/task can
follow a prior event/task
• Fast Tracking – Refers to handling tasks or activities in parallel
• Crashing Critical Path – Shortening the amount of time to do a
critical task
To implement a PERT chart:
• Identify the different tasks needed to
complete a project. Make sure to add these in
the right order and indicate the duration of
each task.
• Create a network diagram. Use arrows to
represent the activities and use nodes as
milestones.
• Determine the critical path and possible slack.
UPDATES THE PERT
USES OF PERT
CONTINUED
Advantages of PERT
• Here are several benefits of using PERT in
project management:
• It helps maximize the use of resources.
• It makes project planning more manageable.
• It’s useful even if there is little or no previous
schedule data.
• It enables project managers to better estimate
or determine a more definite completion date.
CONTINUED
Disadvantages of PERT
• Like any other method, PERT comes with its share
of limitations:
• In complex projects, many find PERT hard to
interpret, so they may also use a Gantt Chart,
another popular method for project
management.
• It can be tedious to update, modify, and maintain
the PERT diagram.
• It entails a subjective time analysis of activities
and, for those who are less experienced or are
biased, this may affect the project’s schedule.
Limitation of PERT
• 1. the activity time estimate are some what
subjective and depend on judgments.
• 2. even if the activity times are well estimated
, PERT assume a beta distribution for these
times estimates, but actual distribution may
be different.
• 3.PERT consistently under estimates the
expected project completion time.
LIMITATION
SUMMARY
• Still now we discussed about PERT and its
importance in operation management of
health care services. It includes the
introduction, definition, network analysis,
estimates time, steps , implementation of
PERT, advantages, disadvantages and
limitation of PERT.
Conclusion
• I hope you all understand about PERT analysis
and its significance in health care
management . If you got chance do the PERT
analysis will you able to apply this knowledge
confidently .
References
• Baker, Sunny, G. Michael Campbell, and Kim
Baker. The Complete Idiot's Guide to Project
Management. Alpha Books, 2003.
• Kerzner, Harold. Project Management: A
Systems Approach to Planning, Scheduling,
and Controlling. John Wiley & Sons, 2003.
• Punmia, B.C. and K. Khandelwal. Project
Planning and Control P.E.R.T. and C.P.M.: For
Degree Classes. Laxmi Publications, 2006.
Question related to the topic?
• Define the PERT?
• Discuss the need of PERT analysis?
• Narrate the concept of PERT analysis?
• Describe the Major features of PERT analysis?
• Explain the network analysis of PERT progress?
• Understand the benefits of PERT?
• State the disadvantages of PERT ?
• Demonstrate the one example of PERT analysis?
Thank you for your patience

More Related Content

What's hot

DISSOCIATIVE DISORDERS
DISSOCIATIVE DISORDERSDISSOCIATIVE DISORDERS
DISSOCIATIVE DISORDERS
ANCYBS
 
Material management
Material managementMaterial management
Material management
Dr. Rahul B. Pandit
 
Crisis management
Crisis managementCrisis management
Crisis management
Mahmoud Shaqria
 
Essential community health service
Essential community health serviceEssential community health service
Essential community health service
anjalatchi
 
Quality Assurance - Nursing Management
Quality Assurance - Nursing ManagementQuality Assurance - Nursing Management
Quality Assurance - Nursing Management
Jaice Mary Joy
 
Mental health act 1987
Mental health act 1987Mental health act 1987
Mental health act 1987
Dr. Parvaiz A Khan
 
ORGANIC DISORDERS
ORGANIC DISORDERSORGANIC DISORDERS
ORGANIC DISORDERS
Richard Asare
 
Affiliation Trends in Health Care: Answers to Key Questions
Affiliation Trends in Health Care: Answers to Key QuestionsAffiliation Trends in Health Care: Answers to Key Questions
Affiliation Trends in Health Care: Answers to Key Questions
PYA, P.C.
 
Personality and Stress
Personality and StressPersonality and Stress
Personality and Stress
Dr. Sinem Bulkan
 
DSM IV & DSM-5 differences
DSM IV & DSM-5 differencesDSM IV & DSM-5 differences
DSM IV & DSM-5 differences
Simmi Waraich
 
Niti aayog
Niti aayogNiti aayog
Niti aayog
Meenakshi Gupta
 
Audit and nursing audit
Audit and nursing auditAudit and nursing audit
Audit and nursing audit
Ekta Patel
 
Planning
PlanningPlanning
Theories of Motivation
Theories of MotivationTheories of Motivation
Theories of Motivation
vinayakgaware
 
Psychiatric emergencies
Psychiatric emergenciesPsychiatric emergencies
Psychiatric emergencies
Shimla
 
Alternative systems of health
Alternative systems of healthAlternative systems of health
Alternative systems of health
rohit mengar
 
Mental health act
Mental health actMental health act
Mental health act
gusainrahul
 
GENERAL CAUSES OF MENTAL DISORDERS
GENERAL CAUSES OF MENTAL DISORDERSGENERAL CAUSES OF MENTAL DISORDERS
GENERAL CAUSES OF MENTAL DISORDERS
Abenezel NIYOMURENGEZI
 
Health care reforms
Health care reformsHealth care reforms
Health care reforms
Jyothi Chinnasamy
 
Somatoform & sleep disorder
Somatoform & sleep disorderSomatoform & sleep disorder
Somatoform & sleep disorder
Harshitha Poojary
 

What's hot (20)

DISSOCIATIVE DISORDERS
DISSOCIATIVE DISORDERSDISSOCIATIVE DISORDERS
DISSOCIATIVE DISORDERS
 
Material management
Material managementMaterial management
Material management
 
Crisis management
Crisis managementCrisis management
Crisis management
 
Essential community health service
Essential community health serviceEssential community health service
Essential community health service
 
Quality Assurance - Nursing Management
Quality Assurance - Nursing ManagementQuality Assurance - Nursing Management
Quality Assurance - Nursing Management
 
Mental health act 1987
Mental health act 1987Mental health act 1987
Mental health act 1987
 
ORGANIC DISORDERS
ORGANIC DISORDERSORGANIC DISORDERS
ORGANIC DISORDERS
 
Affiliation Trends in Health Care: Answers to Key Questions
Affiliation Trends in Health Care: Answers to Key QuestionsAffiliation Trends in Health Care: Answers to Key Questions
Affiliation Trends in Health Care: Answers to Key Questions
 
Personality and Stress
Personality and StressPersonality and Stress
Personality and Stress
 
DSM IV & DSM-5 differences
DSM IV & DSM-5 differencesDSM IV & DSM-5 differences
DSM IV & DSM-5 differences
 
Niti aayog
Niti aayogNiti aayog
Niti aayog
 
Audit and nursing audit
Audit and nursing auditAudit and nursing audit
Audit and nursing audit
 
Planning
PlanningPlanning
Planning
 
Theories of Motivation
Theories of MotivationTheories of Motivation
Theories of Motivation
 
Psychiatric emergencies
Psychiatric emergenciesPsychiatric emergencies
Psychiatric emergencies
 
Alternative systems of health
Alternative systems of healthAlternative systems of health
Alternative systems of health
 
Mental health act
Mental health actMental health act
Mental health act
 
GENERAL CAUSES OF MENTAL DISORDERS
GENERAL CAUSES OF MENTAL DISORDERSGENERAL CAUSES OF MENTAL DISORDERS
GENERAL CAUSES OF MENTAL DISORDERS
 
Health care reforms
Health care reformsHealth care reforms
Health care reforms
 
Somatoform & sleep disorder
Somatoform & sleep disorderSomatoform & sleep disorder
Somatoform & sleep disorder
 

Similar to Unit v mha project evaluation review technique (pert)

Unit IV-Project Management
Unit IV-Project ManagementUnit IV-Project Management
Unit IV-Project Management
SSN College of Engineering, Kalavakkam
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapter
preetidamakale
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
PedadaSaikumar
 
Project Management
Project ManagementProject Management
Project Management
BenjaminMuganzi
 
programmed evaluation and review technique,
programmed evaluation and review technique,programmed evaluation and review technique,
programmed evaluation and review technique,
siddhagiri nursing institute kaneri kolhapur
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
Ragjni Govindaraju
 
5. PMP Training - Time management
5. PMP Training - Time management5. PMP Training - Time management
5. PMP Training - Time management
Qais Ur Rehman Rasooli, PMP
 
Project-Time-Line.pdf
Project-Time-Line.pdfProject-Time-Line.pdf
Project-Time-Line.pdf
Nabeel Ahmad
 
Program_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptxProgram_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptx
mamtabisht10
 
2nd and 3rd Lecture (Maintenance).pptx.pdf
2nd and 3rd Lecture (Maintenance).pptx.pdf2nd and 3rd Lecture (Maintenance).pptx.pdf
2nd and 3rd Lecture (Maintenance).pptx.pdf
Ahmedshayor
 
Ppt.pptx
Ppt.pptxPpt.pptx
Ppt.pptx
nayeembanu1
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
Shivangi Saini
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management a
Rai University
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge Area
Joshua Render
 
PERT-CPM for project management .pptx
PERT-CPM for project management    .pptxPERT-CPM for project management    .pptx
PERT-CPM for project management .pptx
Naresh136982
 
EpM
EpMEpM
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
Nicola2903
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
Nicola2903
 
Project management - a practical overview Sue Greener
Project management - a practical overview Sue GreenerProject management - a practical overview Sue Greener
Project management - a practical overview Sue Greener
Sue Greener
 
Pert and mbo
Pert and mboPert and mbo
Pert and mbo
angel90thomas
 

Similar to Unit v mha project evaluation review technique (pert) (20)

Unit IV-Project Management
Unit IV-Project ManagementUnit IV-Project Management
Unit IV-Project Management
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapter
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Project Management
Project ManagementProject Management
Project Management
 
programmed evaluation and review technique,
programmed evaluation and review technique,programmed evaluation and review technique,
programmed evaluation and review technique,
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
5. PMP Training - Time management
5. PMP Training - Time management5. PMP Training - Time management
5. PMP Training - Time management
 
Project-Time-Line.pdf
Project-Time-Line.pdfProject-Time-Line.pdf
Project-Time-Line.pdf
 
Program_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptxProgram_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptx
 
2nd and 3rd Lecture (Maintenance).pptx.pdf
2nd and 3rd Lecture (Maintenance).pptx.pdf2nd and 3rd Lecture (Maintenance).pptx.pdf
2nd and 3rd Lecture (Maintenance).pptx.pdf
 
Ppt.pptx
Ppt.pptxPpt.pptx
Ppt.pptx
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management a
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge Area
 
PERT-CPM for project management .pptx
PERT-CPM for project management    .pptxPERT-CPM for project management    .pptx
PERT-CPM for project management .pptx
 
EpM
EpMEpM
EpM
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
 
Project management - a practical overview Sue Greener
Project management - a practical overview Sue GreenerProject management - a practical overview Sue Greener
Project management - a practical overview Sue Greener
 
Pert and mbo
Pert and mboPert and mbo
Pert and mbo
 

More from anjalatchi

Unit –IV Nursing Management oragnization M,Sc II year 2023.pptx
Unit –IV Nursing Management oragnization M,Sc II year 2023.pptxUnit –IV Nursing Management oragnization M,Sc II year 2023.pptx
Unit –IV Nursing Management oragnization M,Sc II year 2023.pptx
anjalatchi
 
INTERNATIONAL AND NATIONAL NURSES WEEK SPEECH 12.5.23.pptx
INTERNATIONAL AND NATIONAL NURSES WEEK SPEECH 12.5.23.pptxINTERNATIONAL AND NATIONAL NURSES WEEK SPEECH 12.5.23.pptx
INTERNATIONAL AND NATIONAL NURSES WEEK SPEECH 12.5.23.pptx
anjalatchi
 
VOTE OF THANKS FOR NURSES DAY WEEK CELEBRATION 8.5.23.pptx
VOTE OF THANKS FOR NURSES DAY WEEK CELEBRATION 8.5.23.pptxVOTE OF THANKS FOR NURSES DAY WEEK CELEBRATION 8.5.23.pptx
VOTE OF THANKS FOR NURSES DAY WEEK CELEBRATION 8.5.23.pptx
anjalatchi
 
Unit -III Planning and control M.sc II year.pptx
Unit -III Planning and control M.sc II year.pptxUnit -III Planning and control M.sc II year.pptx
Unit -III Planning and control M.sc II year.pptx
anjalatchi
 
ANTI TOBACCO DAY essay.docx
ANTI TOBACCO DAY essay.docxANTI TOBACCO DAY essay.docx
ANTI TOBACCO DAY essay.docx
anjalatchi
 
PBBSC Nursing Syllabus 2015.docx
PBBSC Nursing Syllabus 2015.docxPBBSC Nursing Syllabus 2015.docx
PBBSC Nursing Syllabus 2015.docx
anjalatchi
 
course Plan For CHN P.B.Sc.docx
course Plan For CHN P.B.Sc.docxcourse Plan For CHN P.B.Sc.docx
course Plan For CHN P.B.Sc.docx
anjalatchi
 
LIST OF CHAPTER FOR P.B.SC CHN BOOK.docx
LIST OF CHAPTER FOR P.B.SC CHN BOOK.docxLIST OF CHAPTER FOR P.B.SC CHN BOOK.docx
LIST OF CHAPTER FOR P.B.SC CHN BOOK.docx
anjalatchi
 
M.SC (N) synopsis format.docx
M.SC (N) synopsis format.docxM.SC (N) synopsis format.docx
M.SC (N) synopsis format.docx
anjalatchi
 
BMWM 2019 GUIDELINESS.pdf
BMWM 2019 GUIDELINESS.pdfBMWM 2019 GUIDELINESS.pdf
BMWM 2019 GUIDELINESS.pdf
anjalatchi
 
Daily ADR Reporting Form April 2023.docx
Daily ADR Reporting Form April 2023.docxDaily ADR Reporting Form April 2023.docx
Daily ADR Reporting Form April 2023.docx
anjalatchi
 
TRAINNING TOPIC FOR ANNUAL SCHEDULE.docx
TRAINNING TOPIC FOR ANNUAL SCHEDULE.docxTRAINNING TOPIC FOR ANNUAL SCHEDULE.docx
TRAINNING TOPIC FOR ANNUAL SCHEDULE.docx
anjalatchi
 
TRAINING SIGN FINAL RECORD.docx
TRAINING SIGN FINAL RECORD.docxTRAINING SIGN FINAL RECORD.docx
TRAINING SIGN FINAL RECORD.docx
anjalatchi
 
slogan competation poster 2.5.23.docx
slogan competation poster 2.5.23.docxslogan competation poster 2.5.23.docx
slogan competation poster 2.5.23.docx
anjalatchi
 
Screening TB format.docx
Screening TB  format.docxScreening TB  format.docx
Screening TB format.docx
anjalatchi
 
report of world glucoma day 2023.docx
report of world glucoma day 2023.docxreport of world glucoma day 2023.docx
report of world glucoma day 2023.docx
anjalatchi
 
REPORT ON WORLD AIDS DAY 2022 CELEBRATION AT ELMCH.docx
REPORT ON WORLD AIDS DAY 2022 CELEBRATION AT ELMCH.docxREPORT ON WORLD AIDS DAY 2022 CELEBRATION AT ELMCH.docx
REPORT ON WORLD AIDS DAY 2022 CELEBRATION AT ELMCH.docx
anjalatchi
 
REPORT OF WORLD TUBERCLOSIS DAY 2023.docx
REPORT  OF WORLD TUBERCLOSIS DAY 2023.docxREPORT  OF WORLD TUBERCLOSIS DAY 2023.docx
REPORT OF WORLD TUBERCLOSIS DAY 2023.docx
anjalatchi
 
NURSING OFFICER EXAM ON MCQ MODEL PAPER.docx
NURSING OFFICER EXAM ON  MCQ MODEL PAPER.docxNURSING OFFICER EXAM ON  MCQ MODEL PAPER.docx
NURSING OFFICER EXAM ON MCQ MODEL PAPER.docx
anjalatchi
 
International nurses week celebration 13.5 PPT.pptx
International nurses week celebration 13.5 PPT.pptxInternational nurses week celebration 13.5 PPT.pptx
International nurses week celebration 13.5 PPT.pptx
anjalatchi
 

More from anjalatchi (20)

Unit –IV Nursing Management oragnization M,Sc II year 2023.pptx
Unit –IV Nursing Management oragnization M,Sc II year 2023.pptxUnit –IV Nursing Management oragnization M,Sc II year 2023.pptx
Unit –IV Nursing Management oragnization M,Sc II year 2023.pptx
 
INTERNATIONAL AND NATIONAL NURSES WEEK SPEECH 12.5.23.pptx
INTERNATIONAL AND NATIONAL NURSES WEEK SPEECH 12.5.23.pptxINTERNATIONAL AND NATIONAL NURSES WEEK SPEECH 12.5.23.pptx
INTERNATIONAL AND NATIONAL NURSES WEEK SPEECH 12.5.23.pptx
 
VOTE OF THANKS FOR NURSES DAY WEEK CELEBRATION 8.5.23.pptx
VOTE OF THANKS FOR NURSES DAY WEEK CELEBRATION 8.5.23.pptxVOTE OF THANKS FOR NURSES DAY WEEK CELEBRATION 8.5.23.pptx
VOTE OF THANKS FOR NURSES DAY WEEK CELEBRATION 8.5.23.pptx
 
Unit -III Planning and control M.sc II year.pptx
Unit -III Planning and control M.sc II year.pptxUnit -III Planning and control M.sc II year.pptx
Unit -III Planning and control M.sc II year.pptx
 
ANTI TOBACCO DAY essay.docx
ANTI TOBACCO DAY essay.docxANTI TOBACCO DAY essay.docx
ANTI TOBACCO DAY essay.docx
 
PBBSC Nursing Syllabus 2015.docx
PBBSC Nursing Syllabus 2015.docxPBBSC Nursing Syllabus 2015.docx
PBBSC Nursing Syllabus 2015.docx
 
course Plan For CHN P.B.Sc.docx
course Plan For CHN P.B.Sc.docxcourse Plan For CHN P.B.Sc.docx
course Plan For CHN P.B.Sc.docx
 
LIST OF CHAPTER FOR P.B.SC CHN BOOK.docx
LIST OF CHAPTER FOR P.B.SC CHN BOOK.docxLIST OF CHAPTER FOR P.B.SC CHN BOOK.docx
LIST OF CHAPTER FOR P.B.SC CHN BOOK.docx
 
M.SC (N) synopsis format.docx
M.SC (N) synopsis format.docxM.SC (N) synopsis format.docx
M.SC (N) synopsis format.docx
 
BMWM 2019 GUIDELINESS.pdf
BMWM 2019 GUIDELINESS.pdfBMWM 2019 GUIDELINESS.pdf
BMWM 2019 GUIDELINESS.pdf
 
Daily ADR Reporting Form April 2023.docx
Daily ADR Reporting Form April 2023.docxDaily ADR Reporting Form April 2023.docx
Daily ADR Reporting Form April 2023.docx
 
TRAINNING TOPIC FOR ANNUAL SCHEDULE.docx
TRAINNING TOPIC FOR ANNUAL SCHEDULE.docxTRAINNING TOPIC FOR ANNUAL SCHEDULE.docx
TRAINNING TOPIC FOR ANNUAL SCHEDULE.docx
 
TRAINING SIGN FINAL RECORD.docx
TRAINING SIGN FINAL RECORD.docxTRAINING SIGN FINAL RECORD.docx
TRAINING SIGN FINAL RECORD.docx
 
slogan competation poster 2.5.23.docx
slogan competation poster 2.5.23.docxslogan competation poster 2.5.23.docx
slogan competation poster 2.5.23.docx
 
Screening TB format.docx
Screening TB  format.docxScreening TB  format.docx
Screening TB format.docx
 
report of world glucoma day 2023.docx
report of world glucoma day 2023.docxreport of world glucoma day 2023.docx
report of world glucoma day 2023.docx
 
REPORT ON WORLD AIDS DAY 2022 CELEBRATION AT ELMCH.docx
REPORT ON WORLD AIDS DAY 2022 CELEBRATION AT ELMCH.docxREPORT ON WORLD AIDS DAY 2022 CELEBRATION AT ELMCH.docx
REPORT ON WORLD AIDS DAY 2022 CELEBRATION AT ELMCH.docx
 
REPORT OF WORLD TUBERCLOSIS DAY 2023.docx
REPORT  OF WORLD TUBERCLOSIS DAY 2023.docxREPORT  OF WORLD TUBERCLOSIS DAY 2023.docx
REPORT OF WORLD TUBERCLOSIS DAY 2023.docx
 
NURSING OFFICER EXAM ON MCQ MODEL PAPER.docx
NURSING OFFICER EXAM ON  MCQ MODEL PAPER.docxNURSING OFFICER EXAM ON  MCQ MODEL PAPER.docx
NURSING OFFICER EXAM ON MCQ MODEL PAPER.docx
 
International nurses week celebration 13.5 PPT.pptx
International nurses week celebration 13.5 PPT.pptxInternational nurses week celebration 13.5 PPT.pptx
International nurses week celebration 13.5 PPT.pptx
 

Recently uploaded

怎么办理(umiami毕业证书)美国迈阿密大学毕业证文凭证书实拍图原版一模一样
怎么办理(umiami毕业证书)美国迈阿密大学毕业证文凭证书实拍图原版一模一样怎么办理(umiami毕业证书)美国迈阿密大学毕业证文凭证书实拍图原版一模一样
怎么办理(umiami毕业证书)美国迈阿密大学毕业证文凭证书实拍图原版一模一样
rtunex8r
 
Bangalore Call Girls 9079923931 With -Cuties' Hot Call Girls
Bangalore Call Girls 9079923931 With -Cuties' Hot Call GirlsBangalore Call Girls 9079923931 With -Cuties' Hot Call Girls
Bangalore Call Girls 9079923931 With -Cuties' Hot Call Girls
narwatsonia7
 
cyber crime.pptx..........................
cyber crime.pptx..........................cyber crime.pptx..........................
cyber crime.pptx..........................
GNAMBIKARAO
 
Decentralized Justice in Gaming and Esports
Decentralized Justice in Gaming and EsportsDecentralized Justice in Gaming and Esports
Decentralized Justice in Gaming and Esports
Federico Ast
 
Bengaluru Dreamin' 24 - Personal Branding
Bengaluru Dreamin' 24 - Personal BrandingBengaluru Dreamin' 24 - Personal Branding
Bengaluru Dreamin' 24 - Personal Branding
Tarandeep Singh
 
How to make a complaint to the police for Social Media Fraud.pdf
How to make a complaint to the police for Social Media Fraud.pdfHow to make a complaint to the police for Social Media Fraud.pdf
How to make a complaint to the police for Social Media Fraud.pdf
Infosec train
 
一比一原版(uc毕业证书)加拿大卡尔加里大学毕业证如何办理
一比一原版(uc毕业证书)加拿大卡尔加里大学毕业证如何办理一比一原版(uc毕业证书)加拿大卡尔加里大学毕业证如何办理
一比一原版(uc毕业证书)加拿大卡尔加里大学毕业证如何办理
dtagbe
 
KubeCon & CloudNative Con 2024 Artificial Intelligent
KubeCon & CloudNative Con 2024 Artificial IntelligentKubeCon & CloudNative Con 2024 Artificial Intelligent
KubeCon & CloudNative Con 2024 Artificial Intelligent
Emre Gündoğdu
 
快速办理(新加坡SMU毕业证书)新加坡管理大学毕业证文凭证书一模一样
快速办理(新加坡SMU毕业证书)新加坡管理大学毕业证文凭证书一模一样快速办理(新加坡SMU毕业证书)新加坡管理大学毕业证文凭证书一模一样
快速办理(新加坡SMU毕业证书)新加坡管理大学毕业证文凭证书一模一样
3a0sd7z3
 
一比一原版新西兰林肯大学毕业证(Lincoln毕业证书)学历如何办理
一比一原版新西兰林肯大学毕业证(Lincoln毕业证书)学历如何办理一比一原版新西兰林肯大学毕业证(Lincoln毕业证书)学历如何办理
一比一原版新西兰林肯大学毕业证(Lincoln毕业证书)学历如何办理
thezot
 
Securing BGP: Operational Strategies and Best Practices for Network Defenders...
Securing BGP: Operational Strategies and Best Practices for Network Defenders...Securing BGP: Operational Strategies and Best Practices for Network Defenders...
Securing BGP: Operational Strategies and Best Practices for Network Defenders...
APNIC
 
Honeypots Unveiled: Proactive Defense Tactics for Cyber Security, Phoenix Sum...
Honeypots Unveiled: Proactive Defense Tactics for Cyber Security, Phoenix Sum...Honeypots Unveiled: Proactive Defense Tactics for Cyber Security, Phoenix Sum...
Honeypots Unveiled: Proactive Defense Tactics for Cyber Security, Phoenix Sum...
APNIC
 
快速办理(Vic毕业证书)惠灵顿维多利亚大学毕业证完成信一模一样
快速办理(Vic毕业证书)惠灵顿维多利亚大学毕业证完成信一模一样快速办理(Vic毕业证书)惠灵顿维多利亚大学毕业证完成信一模一样
快速办理(Vic毕业证书)惠灵顿维多利亚大学毕业证完成信一模一样
3a0sd7z3
 

Recently uploaded (13)

怎么办理(umiami毕业证书)美国迈阿密大学毕业证文凭证书实拍图原版一模一样
怎么办理(umiami毕业证书)美国迈阿密大学毕业证文凭证书实拍图原版一模一样怎么办理(umiami毕业证书)美国迈阿密大学毕业证文凭证书实拍图原版一模一样
怎么办理(umiami毕业证书)美国迈阿密大学毕业证文凭证书实拍图原版一模一样
 
Bangalore Call Girls 9079923931 With -Cuties' Hot Call Girls
Bangalore Call Girls 9079923931 With -Cuties' Hot Call GirlsBangalore Call Girls 9079923931 With -Cuties' Hot Call Girls
Bangalore Call Girls 9079923931 With -Cuties' Hot Call Girls
 
cyber crime.pptx..........................
cyber crime.pptx..........................cyber crime.pptx..........................
cyber crime.pptx..........................
 
Decentralized Justice in Gaming and Esports
Decentralized Justice in Gaming and EsportsDecentralized Justice in Gaming and Esports
Decentralized Justice in Gaming and Esports
 
Bengaluru Dreamin' 24 - Personal Branding
Bengaluru Dreamin' 24 - Personal BrandingBengaluru Dreamin' 24 - Personal Branding
Bengaluru Dreamin' 24 - Personal Branding
 
How to make a complaint to the police for Social Media Fraud.pdf
How to make a complaint to the police for Social Media Fraud.pdfHow to make a complaint to the police for Social Media Fraud.pdf
How to make a complaint to the police for Social Media Fraud.pdf
 
一比一原版(uc毕业证书)加拿大卡尔加里大学毕业证如何办理
一比一原版(uc毕业证书)加拿大卡尔加里大学毕业证如何办理一比一原版(uc毕业证书)加拿大卡尔加里大学毕业证如何办理
一比一原版(uc毕业证书)加拿大卡尔加里大学毕业证如何办理
 
KubeCon & CloudNative Con 2024 Artificial Intelligent
KubeCon & CloudNative Con 2024 Artificial IntelligentKubeCon & CloudNative Con 2024 Artificial Intelligent
KubeCon & CloudNative Con 2024 Artificial Intelligent
 
快速办理(新加坡SMU毕业证书)新加坡管理大学毕业证文凭证书一模一样
快速办理(新加坡SMU毕业证书)新加坡管理大学毕业证文凭证书一模一样快速办理(新加坡SMU毕业证书)新加坡管理大学毕业证文凭证书一模一样
快速办理(新加坡SMU毕业证书)新加坡管理大学毕业证文凭证书一模一样
 
一比一原版新西兰林肯大学毕业证(Lincoln毕业证书)学历如何办理
一比一原版新西兰林肯大学毕业证(Lincoln毕业证书)学历如何办理一比一原版新西兰林肯大学毕业证(Lincoln毕业证书)学历如何办理
一比一原版新西兰林肯大学毕业证(Lincoln毕业证书)学历如何办理
 
Securing BGP: Operational Strategies and Best Practices for Network Defenders...
Securing BGP: Operational Strategies and Best Practices for Network Defenders...Securing BGP: Operational Strategies and Best Practices for Network Defenders...
Securing BGP: Operational Strategies and Best Practices for Network Defenders...
 
Honeypots Unveiled: Proactive Defense Tactics for Cyber Security, Phoenix Sum...
Honeypots Unveiled: Proactive Defense Tactics for Cyber Security, Phoenix Sum...Honeypots Unveiled: Proactive Defense Tactics for Cyber Security, Phoenix Sum...
Honeypots Unveiled: Proactive Defense Tactics for Cyber Security, Phoenix Sum...
 
快速办理(Vic毕业证书)惠灵顿维多利亚大学毕业证完成信一模一样
快速办理(Vic毕业证书)惠灵顿维多利亚大学毕业证完成信一模一样快速办理(Vic毕业证书)惠灵顿维多利亚大学毕业证完成信一模一样
快速办理(Vic毕业证书)惠灵顿维多利亚大学毕业证完成信一模一样
 

Unit v mha project evaluation review technique (pert)

  • 1. Project Evaluation Review Technique (PERT) DR.ANJALATCHI M.SC(N)MD(AM)MBA(HA)
  • 2. LEARNING OBJECTIVES • Introduce the topic • Definition • Need /overview • History • Concept and terminology • Network analysis • Creating PERT chart • Components of PERT
  • 3. Continued • Steps of PERT • Uses of PERT • Advantages of PERT • Disadvantages of PERT • Limitation of PERT • Summary • Conclusion • References
  • 4. Introduction PERT • In project management, the Project Evaluation Review Technique, or PERT, is used to identify the time it takes to finish a particular task or activity. It is a system that helps in proper scheduling and coordination of all tasks throughout a project. It also helps in keeping track of the progress, or lack thereof, of the overall project. In the 1950s, the Project Evaluation Review Technique was developed by the US Navy to manage the Polaris submarine missile program of their Special Projects Office.
  • 5. Continued • Knowing the time it should take to execute a project is crucial, as it helps project managers decide on other factors such as the budget and task delegation. No matter how big or small a project is, estimates can be too optimistic or pessimistic, but using a PERT chart will help determine realistic estimates.
  • 7. Meaning of PERT • PERT is a project management planning tool used to calculate the amount of time it will take to realistically finish a project. PERT stands for Program Evaluation Review Technique.
  • 17.
  • 20.
  • 21. Creating a PERT Chart • A flowchart is used to depict the Project Evaluation Review Technique. Nodes represent the events, indicating the start or end of activities or tasks. The directorial lines indicate the tasks that need to be completed, and the arrows show the sequence of the activities.
  • 22. four definitions of time used to estimate • There are four definitions of time used to estimate project time requirements: • Optimistic time – The least amount of time it can take to complete a task • Pessimistic time – The maximum amount of time it should take to complete a task • Most likely time – Assuming there are no problems, the best, or most reasonable, estimate of how long it should take to complete a task. • Expected time – Assuming there are problems, the best estimate of how much time will be required to
  • 23. Estimate Activity Time • Optimistic time :generally the shortest time in which the activity can be completed. • Most likely Time: the completion time having the highest probability. • Pessimistic time: the longest time that having activity might require.
  • 24. Steps of PERT analysis • 1. identify the specific activities and milestones • 2. determines the proper sequences of the activities • 3. construct a network diagram • 4. estimate the time required for each activity • 5.determine the critical path • 6.updates the PERT charts as the project progresses.
  • 26. Four quantities for each activity • ES-earliest start time • EF-Earliest Finish time • LS-latest Start Time • LF-Latest Finish Time
  • 27. Here are several terms used in a PERT chart: • Float/Slack – Refers to the amount of time a task can be delayed without resulting in an overall delay in completion of other tasks or the project • Critical Path – Indicates the longest possible continuous path from the start to the end of a task or event • Critical Path Activity – Refers to an activity without any slack • Lead Time – Refers to the amount of time needed to finish a task without affecting subsequent tasks • Lag Time – The earliest time by which a successor event/task can follow a prior event/task • Fast Tracking – Refers to handling tasks or activities in parallel • Crashing Critical Path – Shortening the amount of time to do a critical task
  • 28. To implement a PERT chart: • Identify the different tasks needed to complete a project. Make sure to add these in the right order and indicate the duration of each task. • Create a network diagram. Use arrows to represent the activities and use nodes as milestones. • Determine the critical path and possible slack.
  • 32. Advantages of PERT • Here are several benefits of using PERT in project management: • It helps maximize the use of resources. • It makes project planning more manageable. • It’s useful even if there is little or no previous schedule data. • It enables project managers to better estimate or determine a more definite completion date.
  • 34. Disadvantages of PERT • Like any other method, PERT comes with its share of limitations: • In complex projects, many find PERT hard to interpret, so they may also use a Gantt Chart, another popular method for project management. • It can be tedious to update, modify, and maintain the PERT diagram. • It entails a subjective time analysis of activities and, for those who are less experienced or are biased, this may affect the project’s schedule.
  • 35. Limitation of PERT • 1. the activity time estimate are some what subjective and depend on judgments. • 2. even if the activity times are well estimated , PERT assume a beta distribution for these times estimates, but actual distribution may be different. • 3.PERT consistently under estimates the expected project completion time.
  • 37. SUMMARY • Still now we discussed about PERT and its importance in operation management of health care services. It includes the introduction, definition, network analysis, estimates time, steps , implementation of PERT, advantages, disadvantages and limitation of PERT.
  • 38. Conclusion • I hope you all understand about PERT analysis and its significance in health care management . If you got chance do the PERT analysis will you able to apply this knowledge confidently .
  • 39. References • Baker, Sunny, G. Michael Campbell, and Kim Baker. The Complete Idiot's Guide to Project Management. Alpha Books, 2003. • Kerzner, Harold. Project Management: A Systems Approach to Planning, Scheduling, and Controlling. John Wiley & Sons, 2003. • Punmia, B.C. and K. Khandelwal. Project Planning and Control P.E.R.T. and C.P.M.: For Degree Classes. Laxmi Publications, 2006.
  • 40. Question related to the topic? • Define the PERT? • Discuss the need of PERT analysis? • Narrate the concept of PERT analysis? • Describe the Major features of PERT analysis? • Explain the network analysis of PERT progress? • Understand the benefits of PERT? • State the disadvantages of PERT ? • Demonstrate the one example of PERT analysis?
  • 41. Thank you for your patience