SlideShare a Scribd company logo
1
SCHOOL OF ARCHITECTURE, BUILDING &
DESIGN
BACHELOR OF QUANTITY SURVEYING
(HONOURS)
INTEGRATED ASSIGNMENT:
MEASUREMENT I (QSB60104)
CONSTRUCTION TECHNOLOGY I (BLD 60104)
BUILDING MATERIALS (BLD 62003)
SITE VISIT REPORT
Name: Lee Shze Hwa
Student ID: 0320053
Date of Submission: 26th
November 2015
2
Content
No. Title Page
1. Introduction 3
2. Objective 4
3. Content/ Technical Observation 5-8
4. Photos & Description 9- 12
5. Conclusion 13
3
Introduction
The site visit is held on 19th November 2015 (Thursday). It is organized by the programme
director, SR Any Fuey Lin which is our Measurement 1 lecturer as well. Every one of us
were advised to buy a safety helmet due to the safety precautions. Besides, we also required
to wear a proper attire and covered shoe or site boots before we went to the site visit. We
were gathered at Taylor’s Lakeside University around 8:00 am and take attendance with Ms
Azrina. After one and the half hour journey by bus, we finally reached to our site which
located at Sekyen 2A, Antara Gapi, Hulu Selangor, Selangor. The project manager, Mohd
Sobri Bin HJ. AB. Majid briefed to us about the construction site and also introduced his
team to us. After taken the group photo, we started our site visit under the guide of the project
manager and the land surveyor, Mohd Hafizi Mohammad.
The project is the construction of 96 units Semi-detached (40’ x 60’) including the
infrastructure. The developer of this project is Perbadanan Kemajuan Negeri Selangor
(PKNS) and the architect is Zain Hamzah Architect. For the structural engineer is Wawasan
Bersatu Sdn Bhd. While for the mechanical & electrical engineer is ZNVA & Associated.
Moreover, the contractor is AJ-Corp Sdn Bhd. The date of the construction started from 8th
July 2014 and it is currently expected to complete at the date of 4th July 2016.
The project manager had firstly showed us the pile on the site and explained to us about the
process of pilling. Due to the different type of soil condition, some houses was constructed by
using pad footing. The project manager and the land surveyor were showed and explained to
us clearly about the construction process and materials used while guiding us around the
construction site.
4
Objective
The objectives of this technical site visit are:
1. To gain extra knowledge and have a better understanding on the construction process
by observing the workers and listen to what the project manager had explained to us.
2. To apply the theory that we have learnt in books into the practical aspect of the
construction technology.
3. To experience and understand more about the actual working environment in the
construction site.
4. To observe and understand more when the workers operating the construction
mechanical and equipment.
5. To take the opportunity to communicate with the construction professional and
understand more about their scope of work.
6. To understand the important of safety precaution and arise the awareness when
entering the construction site.
7. To explore and distinguish the various types of building materials and the technology
available on the construction site.
8. To take the opportunity to ask and learn extra knowledge to the building materials that
we did not studied on the lecture.
9. To understand the scientific principles about the design and the construction.
10. To understand about the important of teamwork in the construction team that required
to solve and overcome the problem.
5
Content/TechnicalObservation
The types of foundations have separated into shallow foundations and deep foundations.
While for pad foundations, it is lay under the types of shallow foundations. Shallow
foundations transfer the load to subsoil at a point near to the ground floor a building and the
height of the building should be less than 3m from the ground level. Pad foundations are used
when the soil condition are strong enough to support the load of the house and it is not
suitable in highly compressible soils. The design of the building should be simple and not too
complicated. For the construction that we visit, there have several type of Semidetached
which are type 1, type 2A (split down), type 2B (split up) and type 3. Types of foundation
used for type 1 and type 3 are pilling, while the type of foundation used for type 2A and type
2B are pad foundations due to the different condition of the soil. The types of soil for the area
of type 2A and type 2B are red clay which is cohesive soils, therefore, that particular soil area
are suitable for pad foundations. Since type 2B haven start to construct, we will focus on the
type 2A which is still under construction.
Several steps required for the construction of pad footing:
Step 1: Site Clearance
Site clearance is required before excavation work start. In this process, hedges, undergrowth,
bushes, scrub, tree stumps will be removed.
Step 2: Excavation
For the first excavation, topsoil is required to excavate to reach the average depth of 1.60m.
Topsoil obtained from excavation is either will be remove off site or will be preserved in
temporary spoil heaps. After the topsoil was excavated, excavation to reduce level average
depth 1.20m is needed by using excavator. Next, excavation was required to the pits for pad
footings starting from reduce level.
Step 3: Lean Concrete
Moreover, a layer of lean concrete is required to construct before build the pad footing. Lean
concrete provide a straight level surface to the foundation and it also act as a protection for
the foundation from the soil below to prevent moisture and other chemicals such as sulphates
that may weaken the foundation.
6
Step 4: Formwork for Pad Footing
Formwork is then built for the construction of the pad footing. It need to be measure
accurately and placed well to reach the desire area in order to get the correct size of the pad
footing. Formwork consists of side, end planks, yoke, nut and bolts. The end and the two side
planks needed to join by the yokes and the bolts. The joints in the formwork should be tight
against leakage of cement grout.
Step 5: Reinforcement Bar for the Pad Footing and the Column Stump
The reinforced high tensile steel rod reinforcement straight and bent with 16mm diameter
was chosen to use in the pad footing. The reinforcement bars for the column stump should be
placed as well. Before placing the reinforcement bars, concrete cover is needed to place
below the reinforcement bars. This is because it can prevent the reinforcement bars attached
to the ground. Furthermore, concrete cover also avoids the reinforcement bars from corrosion
and act as the barrier to the spread of fire.
Step 6: Filling concrete to pad footing
Reinforced concrete Grade 30 (20-25mm agg.) is then poured into the formwork. The
reinforced concrete required to compact sufficiently and allow the concrete to cure.
Step 7: Removal of formwork
After make sure the reinforced concrete had set to receive its maximum strength, the
formwork is then ready to be remove. Finally, the pad footing is done.
7
Materials involved in constructing a pad footing:
1. Reinforcement Bar
The types of reinforcement bar used is high tensile steel 16mm. Reinforcement bar
also known as rebar. Rebar normally found in foundation, column, beam and floor
slab. The function of rebar is to act as a tension device in reinforced concrete to
increase the strength and support the concrete. Besides, rebar also helps to control the
contraction and expansion of the reinforced concrete due to the change of
temperature. When rebar was placed in slab, it also helps to prevent the cracks. Rebar
should also place at the bottom of the foundation in order to receive the high
performance and able to resist the heavy load. The greater the surface of rebar
exposed to the adherence concrete, the stronger the bond and result in the higher
tension to resist the load. Moreover, the rough surface also provides a better tension.
This is because the rougher the surface of the rebar, the more adhere to the concrete.
2. Formwork
The formwork that used in the construction site to build the pad footing is timber.
Formwork is use to support structures and normally act as temporary or permanent
molds for the fresh concrete to pour in and wait until it is set. The reusable formwork
is called as panel formwork. On the another had, the non-reusable formwork is called
as stationary formwork. Timber formwork can easily be made in different size or
shape. It is economically due to the high availability and low production cost. Since
timber is light in weight, it is easy to carry in the construction site. Furthermore,
timber can be reuse and this had reduced the construction cost.
Part Size
Sheeting for slabs, beam, column 25 to 40 mm
Joints, ledges 50 x 70 mm to 50 x 150 mm
Posts 75 x 100mm to 100 x 100 mm
8
3. Concrete
The concrete in pad footings is reinforced concrete Grade 30. Concrete is the most
used constructions materials around the world due to its strength, durability and
aesthetic value. It can be produced in many grades by mixing the ingredient with
different ratio. Concrete consist of cement, sand and gravel. Cement is functioned as
the bonding agent to adhere the sand and aggregates together. However, water is
required to react with the cement and form bonding agent. Besides, the benefits of
concrete are the excellent performance in terms of safety, security, mold and mildew
resistance and the flexibility for the design. For example, concrete can produce into
different texture and shape and it suitable with different finishing such as paint and
stone cladding.
9
Photosand Description
The information board which located
at the main entrance.
Mind map of the organisation for
the project.
The plan of the construction site. The site office.
10
Straight reinforcement bar.
Mesh Fabrics Reinforcements.
Straight & bend
reinforcement bars.
Links in pile.
Pile after pilling.
Pile.
11
.
Concrete Mixer
Excavator Backhoe
Crane
Truck
Construction joint
12
Clay Bricks Concrete BricksRoof Tiles
Pad Footing
Formwork for column The worker fixing the link to the rebar.
13
Conclusion
After the site visit, I have understood and gain more experience about the
construction site including the hot sun and dirt. I have gain more knowledge about the
construction technology and learnt many extra knowledges that is no in the lecture notes.
Besides, I sincerely thankful to the instructor who guiding us around the site, showed us and
also explained to us patiently about the construction work. Others than that, I also thankful to
Ms Any and Ms Azirina who organized this site visit to us and let us have the opportunity to
experience the real construction site. I have gain a lot of knowledge and taken may photo on
the site for the information to this assignment. Furthermore, I had learnt that teamwork is
very important for the construction team to solve and face the problem occur during
construction.

More Related Content

What's hot

Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction ppt
Being Deepak
 
Ground and upper floor
Ground and upper floorGround and upper floor
Ground and upper floor
Divya Vishnoi
 
Types of construction
Types of constructionTypes of construction
Types of construction
Pralhad Kore
 
Site Report
Site Report Site Report
Site Report
Sow Wei Henn
 
Site report
Site reportSite report
Site report
Penny3688
 
house construction
house constructionhouse construction
house construction
Abhinav Saha
 
Chapter 4 (d) hollow concrete block masonry
Chapter 4 (d) hollow concrete block masonryChapter 4 (d) hollow concrete block masonry
Chapter 4 (d) hollow concrete block masonry
KHUSHBU SHAH
 
Pouring concrete into formwork
Pouring concrete into formwork Pouring concrete into formwork
Pouring concrete into formwork
Dosy21
 
Types of masonry and its failure types
Types of masonry and its failure typesTypes of masonry and its failure types
Types of masonry and its failure types
Udayram Patil
 
Lecture bricks and blocks masonry
Lecture bricks and blocks masonryLecture bricks and blocks masonry
Lecture bricks and blocks masonry
Est
 
Ch5 masonry construction
Ch5 masonry constructionCh5 masonry construction
Ch5 masonry construction
hsaam hsaam
 
3. building stones, tiles and site orientation
3. building stones, tiles  and site orientation3. building stones, tiles  and site orientation
3. building stones, tiles and site orientation
muhammadumairallahdi
 
Ct bm measurement report
Ct bm measurement reportCt bm measurement report
Ct bm measurement report
Kailyn Lee
 
BRICK MASONRY PPT BY SUBHENDU SAMUI
BRICK MASONRY PPT BY SUBHENDU SAMUIBRICK MASONRY PPT BY SUBHENDU SAMUI
BRICK MASONRY PPT BY SUBHENDU SAMUI
SUBHENDU SAMUI
 
CONSTRUCTION ENGINEERING
CONSTRUCTION ENGINEERINGCONSTRUCTION ENGINEERING
CONSTRUCTION ENGINEERING
Atiq Iqbal
 
2. intro to construction material
2. intro to construction material2. intro to construction material
2. intro to construction material
Noshad Ahmed Wahocho
 
Chap16 cbm&cw
Chap16 cbm&cwChap16 cbm&cw
Chap16 cbm&cw
Amynaah Amye
 
2 brick,brick masonary and manufacturing of bricks - copy
2 brick,brick masonary and manufacturing of bricks - copy2 brick,brick masonary and manufacturing of bricks - copy
2 brick,brick masonary and manufacturing of bricks - copy
muhammadumairallahdi
 
Building Materials & Construction Module-1 Building Materials
Building Materials & Construction   Module-1 Building Materials Building Materials & Construction   Module-1 Building Materials
Building Materials & Construction Module-1 Building Materials
Abhilash B L
 

What's hot (20)

Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction ppt
 
Ground and upper floor
Ground and upper floorGround and upper floor
Ground and upper floor
 
Types of construction
Types of constructionTypes of construction
Types of construction
 
Site Report
Site Report Site Report
Site Report
 
Site report
Site reportSite report
Site report
 
house construction
house constructionhouse construction
house construction
 
Chapter 4 (d) hollow concrete block masonry
Chapter 4 (d) hollow concrete block masonryChapter 4 (d) hollow concrete block masonry
Chapter 4 (d) hollow concrete block masonry
 
Pouring concrete into formwork
Pouring concrete into formwork Pouring concrete into formwork
Pouring concrete into formwork
 
Brick masonry
Brick masonryBrick masonry
Brick masonry
 
Types of masonry and its failure types
Types of masonry and its failure typesTypes of masonry and its failure types
Types of masonry and its failure types
 
Lecture bricks and blocks masonry
Lecture bricks and blocks masonryLecture bricks and blocks masonry
Lecture bricks and blocks masonry
 
Ch5 masonry construction
Ch5 masonry constructionCh5 masonry construction
Ch5 masonry construction
 
3. building stones, tiles and site orientation
3. building stones, tiles  and site orientation3. building stones, tiles  and site orientation
3. building stones, tiles and site orientation
 
Ct bm measurement report
Ct bm measurement reportCt bm measurement report
Ct bm measurement report
 
BRICK MASONRY PPT BY SUBHENDU SAMUI
BRICK MASONRY PPT BY SUBHENDU SAMUIBRICK MASONRY PPT BY SUBHENDU SAMUI
BRICK MASONRY PPT BY SUBHENDU SAMUI
 
CONSTRUCTION ENGINEERING
CONSTRUCTION ENGINEERINGCONSTRUCTION ENGINEERING
CONSTRUCTION ENGINEERING
 
2. intro to construction material
2. intro to construction material2. intro to construction material
2. intro to construction material
 
Chap16 cbm&cw
Chap16 cbm&cwChap16 cbm&cw
Chap16 cbm&cw
 
2 brick,brick masonary and manufacturing of bricks - copy
2 brick,brick masonary and manufacturing of bricks - copy2 brick,brick masonary and manufacturing of bricks - copy
2 brick,brick masonary and manufacturing of bricks - copy
 
Building Materials & Construction Module-1 Building Materials
Building Materials & Construction   Module-1 Building Materials Building Materials & Construction   Module-1 Building Materials
Building Materials & Construction Module-1 Building Materials
 

Similar to Site-Report (1).docx

Site report
Site reportSite report
Site report
HuiYik
 
Site report
Site reportSite report
Site report
Joyce HweeMin
 
Site visit report
Site visit reportSite visit report
Site visit report
Monnie Bao Jia
 
Site visit report
Site visit reportSite visit report
Site visit reportDoreen Yeo
 
Construction of Brick Wall
Construction of Brick WallConstruction of Brick Wall
Construction of Brick Wall
I'mMiss Lily
 
Site Report
Site ReportSite Report
Site Report
khaikeat16
 
Site visit report
Site visit reportSite visit report
Site visit report
Jordon Wong
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit report
Momo Poyi
 
Assignment of Site Report
Assignment of Site Report Assignment of Site Report
Assignment of Site Report
I'mMiss Lily
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)
I'mMiss Lily
 
Ez
EzEz
Sem 1 degree ct assignment 1
Sem 1 degree ct assignment 1Sem 1 degree ct assignment 1
Sem 1 degree ct assignment 1Parham Farhadpoor
 
Site Visit Report CT BM M1
Site Visit Report CT BM M1Site Visit Report CT BM M1
Site Visit Report CT BM M1
Zi Shan
 
Site report
Site reportSite report
Site report
vaylu
 
Assignment 1 - Antara Gapi, Hulu Selangor, Selangor
Assignment 1 - Antara Gapi, Hulu Selangor, SelangorAssignment 1 - Antara Gapi, Hulu Selangor, Selangor
Assignment 1 - Antara Gapi, Hulu Selangor, Selangor
Kai Yun Pang
 
Shinchan presentation.pptx
Shinchan presentation.pptxShinchan presentation.pptx
Shinchan presentation.pptx
RAKESHPANDEY754083
 
Construction-Amit Payal
Construction-Amit PayalConstruction-Amit Payal
Construction-Amit Payal
AMIT PAYAL
 
Fromwork
FromworkFromwork
Fromwork
Jayant Mewara
 
Foundations
FoundationsFoundations
Foundations
kevin porter
 

Similar to Site-Report (1).docx (20)

Site report
Site reportSite report
Site report
 
Site report
Site reportSite report
Site report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Construction of Brick Wall
Construction of Brick WallConstruction of Brick Wall
Construction of Brick Wall
 
Site Report
Site ReportSite Report
Site Report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit report
 
Assignment of Site Report
Assignment of Site Report Assignment of Site Report
Assignment of Site Report
 
Site report
Site reportSite report
Site report
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)
 
Ez
EzEz
Ez
 
Sem 1 degree ct assignment 1
Sem 1 degree ct assignment 1Sem 1 degree ct assignment 1
Sem 1 degree ct assignment 1
 
Site Visit Report CT BM M1
Site Visit Report CT BM M1Site Visit Report CT BM M1
Site Visit Report CT BM M1
 
Site report
Site reportSite report
Site report
 
Assignment 1 - Antara Gapi, Hulu Selangor, Selangor
Assignment 1 - Antara Gapi, Hulu Selangor, SelangorAssignment 1 - Antara Gapi, Hulu Selangor, Selangor
Assignment 1 - Antara Gapi, Hulu Selangor, Selangor
 
Shinchan presentation.pptx
Shinchan presentation.pptxShinchan presentation.pptx
Shinchan presentation.pptx
 
Construction-Amit Payal
Construction-Amit PayalConstruction-Amit Payal
Construction-Amit Payal
 
Fromwork
FromworkFromwork
Fromwork
 
Foundations
FoundationsFoundations
Foundations
 

More from Shze Hwa Lee

Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
Shze Hwa Lee
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
Shze Hwa Lee
 
Cp 24062018 2241
Cp 24062018 2241Cp 24062018 2241
Cp 24062018 2241
Shze Hwa Lee
 
Be finalise a3
Be finalise a3Be finalise a3
Be finalise a3
Shze Hwa Lee
 
Be presentation slides
Be presentation slidesBe presentation slides
Be presentation slides
Shze Hwa Lee
 
Be Report Finalize
Be Report FinalizeBe Report Finalize
Be Report Finalize
Shze Hwa Lee
 
Fm report template
Fm report templateFm report template
Fm report template
Shze Hwa Lee
 
Csi presentation
Csi   presentationCsi   presentation
Csi presentation
Shze Hwa Lee
 
Finased csi report
Finased csi reportFinased csi report
Finased csi report
Shze Hwa Lee
 
Software Presentation Slides
Software Presentation SlidesSoftware Presentation Slides
Software Presentation Slides
Shze Hwa Lee
 
Software Application Report
Software Application ReportSoftware Application Report
Software Application Report
Shze Hwa Lee
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
Shze Hwa Lee
 
Seminar 1 Questions
Seminar 1 QuestionsSeminar 1 Questions
Seminar 1 Questions
Shze Hwa Lee
 
Estimating presentation (question 1)
Estimating presentation (question 1)Estimating presentation (question 1)
Estimating presentation (question 1)
Shze Hwa Lee
 
PP1 presentation
PP1 presentationPP1 presentation
PP1 presentation
Shze Hwa Lee
 
PP1 report group 7 (finalized)
PP1 report group 7 (finalized)PP1 report group 7 (finalized)
PP1 report group 7 (finalized)
Shze Hwa Lee
 
Measurement 4 presentation
Measurement 4 presentation Measurement 4 presentation
Measurement 4 presentation
Shze Hwa Lee
 
ECA presentation
ECA presentationECA presentation
ECA presentation
Shze Hwa Lee
 
Bs 2 group assignment
Bs 2 group assignmentBs 2 group assignment
Bs 2 group assignment
Shze Hwa Lee
 
People dynamic (assingment 1)
People dynamic (assingment 1) People dynamic (assingment 1)
People dynamic (assingment 1)
Shze Hwa Lee
 

More from Shze Hwa Lee (20)

Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
 
Cp 24062018 2241
Cp 24062018 2241Cp 24062018 2241
Cp 24062018 2241
 
Be finalise a3
Be finalise a3Be finalise a3
Be finalise a3
 
Be presentation slides
Be presentation slidesBe presentation slides
Be presentation slides
 
Be Report Finalize
Be Report FinalizeBe Report Finalize
Be Report Finalize
 
Fm report template
Fm report templateFm report template
Fm report template
 
Csi presentation
Csi   presentationCsi   presentation
Csi presentation
 
Finased csi report
Finased csi reportFinased csi report
Finased csi report
 
Software Presentation Slides
Software Presentation SlidesSoftware Presentation Slides
Software Presentation Slides
 
Software Application Report
Software Application ReportSoftware Application Report
Software Application Report
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
 
Seminar 1 Questions
Seminar 1 QuestionsSeminar 1 Questions
Seminar 1 Questions
 
Estimating presentation (question 1)
Estimating presentation (question 1)Estimating presentation (question 1)
Estimating presentation (question 1)
 
PP1 presentation
PP1 presentationPP1 presentation
PP1 presentation
 
PP1 report group 7 (finalized)
PP1 report group 7 (finalized)PP1 report group 7 (finalized)
PP1 report group 7 (finalized)
 
Measurement 4 presentation
Measurement 4 presentation Measurement 4 presentation
Measurement 4 presentation
 
ECA presentation
ECA presentationECA presentation
ECA presentation
 
Bs 2 group assignment
Bs 2 group assignmentBs 2 group assignment
Bs 2 group assignment
 
People dynamic (assingment 1)
People dynamic (assingment 1) People dynamic (assingment 1)
People dynamic (assingment 1)
 

Site-Report (1).docx

  • 1. 1 SCHOOL OF ARCHITECTURE, BUILDING & DESIGN BACHELOR OF QUANTITY SURVEYING (HONOURS) INTEGRATED ASSIGNMENT: MEASUREMENT I (QSB60104) CONSTRUCTION TECHNOLOGY I (BLD 60104) BUILDING MATERIALS (BLD 62003) SITE VISIT REPORT Name: Lee Shze Hwa Student ID: 0320053 Date of Submission: 26th November 2015
  • 2. 2 Content No. Title Page 1. Introduction 3 2. Objective 4 3. Content/ Technical Observation 5-8 4. Photos & Description 9- 12 5. Conclusion 13
  • 3. 3 Introduction The site visit is held on 19th November 2015 (Thursday). It is organized by the programme director, SR Any Fuey Lin which is our Measurement 1 lecturer as well. Every one of us were advised to buy a safety helmet due to the safety precautions. Besides, we also required to wear a proper attire and covered shoe or site boots before we went to the site visit. We were gathered at Taylor’s Lakeside University around 8:00 am and take attendance with Ms Azrina. After one and the half hour journey by bus, we finally reached to our site which located at Sekyen 2A, Antara Gapi, Hulu Selangor, Selangor. The project manager, Mohd Sobri Bin HJ. AB. Majid briefed to us about the construction site and also introduced his team to us. After taken the group photo, we started our site visit under the guide of the project manager and the land surveyor, Mohd Hafizi Mohammad. The project is the construction of 96 units Semi-detached (40’ x 60’) including the infrastructure. The developer of this project is Perbadanan Kemajuan Negeri Selangor (PKNS) and the architect is Zain Hamzah Architect. For the structural engineer is Wawasan Bersatu Sdn Bhd. While for the mechanical & electrical engineer is ZNVA & Associated. Moreover, the contractor is AJ-Corp Sdn Bhd. The date of the construction started from 8th July 2014 and it is currently expected to complete at the date of 4th July 2016. The project manager had firstly showed us the pile on the site and explained to us about the process of pilling. Due to the different type of soil condition, some houses was constructed by using pad footing. The project manager and the land surveyor were showed and explained to us clearly about the construction process and materials used while guiding us around the construction site.
  • 4. 4 Objective The objectives of this technical site visit are: 1. To gain extra knowledge and have a better understanding on the construction process by observing the workers and listen to what the project manager had explained to us. 2. To apply the theory that we have learnt in books into the practical aspect of the construction technology. 3. To experience and understand more about the actual working environment in the construction site. 4. To observe and understand more when the workers operating the construction mechanical and equipment. 5. To take the opportunity to communicate with the construction professional and understand more about their scope of work. 6. To understand the important of safety precaution and arise the awareness when entering the construction site. 7. To explore and distinguish the various types of building materials and the technology available on the construction site. 8. To take the opportunity to ask and learn extra knowledge to the building materials that we did not studied on the lecture. 9. To understand the scientific principles about the design and the construction. 10. To understand about the important of teamwork in the construction team that required to solve and overcome the problem.
  • 5. 5 Content/TechnicalObservation The types of foundations have separated into shallow foundations and deep foundations. While for pad foundations, it is lay under the types of shallow foundations. Shallow foundations transfer the load to subsoil at a point near to the ground floor a building and the height of the building should be less than 3m from the ground level. Pad foundations are used when the soil condition are strong enough to support the load of the house and it is not suitable in highly compressible soils. The design of the building should be simple and not too complicated. For the construction that we visit, there have several type of Semidetached which are type 1, type 2A (split down), type 2B (split up) and type 3. Types of foundation used for type 1 and type 3 are pilling, while the type of foundation used for type 2A and type 2B are pad foundations due to the different condition of the soil. The types of soil for the area of type 2A and type 2B are red clay which is cohesive soils, therefore, that particular soil area are suitable for pad foundations. Since type 2B haven start to construct, we will focus on the type 2A which is still under construction. Several steps required for the construction of pad footing: Step 1: Site Clearance Site clearance is required before excavation work start. In this process, hedges, undergrowth, bushes, scrub, tree stumps will be removed. Step 2: Excavation For the first excavation, topsoil is required to excavate to reach the average depth of 1.60m. Topsoil obtained from excavation is either will be remove off site or will be preserved in temporary spoil heaps. After the topsoil was excavated, excavation to reduce level average depth 1.20m is needed by using excavator. Next, excavation was required to the pits for pad footings starting from reduce level. Step 3: Lean Concrete Moreover, a layer of lean concrete is required to construct before build the pad footing. Lean concrete provide a straight level surface to the foundation and it also act as a protection for the foundation from the soil below to prevent moisture and other chemicals such as sulphates that may weaken the foundation.
  • 6. 6 Step 4: Formwork for Pad Footing Formwork is then built for the construction of the pad footing. It need to be measure accurately and placed well to reach the desire area in order to get the correct size of the pad footing. Formwork consists of side, end planks, yoke, nut and bolts. The end and the two side planks needed to join by the yokes and the bolts. The joints in the formwork should be tight against leakage of cement grout. Step 5: Reinforcement Bar for the Pad Footing and the Column Stump The reinforced high tensile steel rod reinforcement straight and bent with 16mm diameter was chosen to use in the pad footing. The reinforcement bars for the column stump should be placed as well. Before placing the reinforcement bars, concrete cover is needed to place below the reinforcement bars. This is because it can prevent the reinforcement bars attached to the ground. Furthermore, concrete cover also avoids the reinforcement bars from corrosion and act as the barrier to the spread of fire. Step 6: Filling concrete to pad footing Reinforced concrete Grade 30 (20-25mm agg.) is then poured into the formwork. The reinforced concrete required to compact sufficiently and allow the concrete to cure. Step 7: Removal of formwork After make sure the reinforced concrete had set to receive its maximum strength, the formwork is then ready to be remove. Finally, the pad footing is done.
  • 7. 7 Materials involved in constructing a pad footing: 1. Reinforcement Bar The types of reinforcement bar used is high tensile steel 16mm. Reinforcement bar also known as rebar. Rebar normally found in foundation, column, beam and floor slab. The function of rebar is to act as a tension device in reinforced concrete to increase the strength and support the concrete. Besides, rebar also helps to control the contraction and expansion of the reinforced concrete due to the change of temperature. When rebar was placed in slab, it also helps to prevent the cracks. Rebar should also place at the bottom of the foundation in order to receive the high performance and able to resist the heavy load. The greater the surface of rebar exposed to the adherence concrete, the stronger the bond and result in the higher tension to resist the load. Moreover, the rough surface also provides a better tension. This is because the rougher the surface of the rebar, the more adhere to the concrete. 2. Formwork The formwork that used in the construction site to build the pad footing is timber. Formwork is use to support structures and normally act as temporary or permanent molds for the fresh concrete to pour in and wait until it is set. The reusable formwork is called as panel formwork. On the another had, the non-reusable formwork is called as stationary formwork. Timber formwork can easily be made in different size or shape. It is economically due to the high availability and low production cost. Since timber is light in weight, it is easy to carry in the construction site. Furthermore, timber can be reuse and this had reduced the construction cost. Part Size Sheeting for slabs, beam, column 25 to 40 mm Joints, ledges 50 x 70 mm to 50 x 150 mm Posts 75 x 100mm to 100 x 100 mm
  • 8. 8 3. Concrete The concrete in pad footings is reinforced concrete Grade 30. Concrete is the most used constructions materials around the world due to its strength, durability and aesthetic value. It can be produced in many grades by mixing the ingredient with different ratio. Concrete consist of cement, sand and gravel. Cement is functioned as the bonding agent to adhere the sand and aggregates together. However, water is required to react with the cement and form bonding agent. Besides, the benefits of concrete are the excellent performance in terms of safety, security, mold and mildew resistance and the flexibility for the design. For example, concrete can produce into different texture and shape and it suitable with different finishing such as paint and stone cladding.
  • 9. 9 Photosand Description The information board which located at the main entrance. Mind map of the organisation for the project. The plan of the construction site. The site office.
  • 10. 10 Straight reinforcement bar. Mesh Fabrics Reinforcements. Straight & bend reinforcement bars. Links in pile. Pile after pilling. Pile.
  • 12. 12 Clay Bricks Concrete BricksRoof Tiles Pad Footing Formwork for column The worker fixing the link to the rebar.
  • 13. 13 Conclusion After the site visit, I have understood and gain more experience about the construction site including the hot sun and dirt. I have gain more knowledge about the construction technology and learnt many extra knowledges that is no in the lecture notes. Besides, I sincerely thankful to the instructor who guiding us around the site, showed us and also explained to us patiently about the construction work. Others than that, I also thankful to Ms Any and Ms Azirina who organized this site visit to us and let us have the opportunity to experience the real construction site. I have gain a lot of knowledge and taken may photo on the site for the information to this assignment. Furthermore, I had learnt that teamwork is very important for the construction team to solve and face the problem occur during construction.