PMP & CAPM
Exam Preparation
  January 29, 2013
Sessions
1. About the exam
2. Integration & Scope Management
3. Time & Cost Management
4. Quality & HR Management
5. Communication & Risk
   Management
6. Procurement Management
Last Session Key point

• General concepts
   – Project management processes
   – Input, Tools & Techniques, Output
   – Organizational Structure
   – Enterprise environment factors
   – Organizational process assets
   – Exam formula
Last Session Key point – cont’d

•   CAPM and PMP exam differences
•   Exam preparation
•   Study plan
•   General concepts
     – 5 Process Groups
     – 9 Knowledge Areas
     – Projects vs Operations
     – Projects vs Programs vs Portfolio
     – Project documents vs Project management plan
Project Integration Management
Project Integration Management
• Develop Project Charter
Project Integration Management
• Develop Project Charter – I
  – SOW
     • Business needs, Product scope description, Strategic
       plan
  – BC
     • Market demand, Organizational need, Customer
       request, Technological advance, Legal
       requirement, Ecological impact, Social need
  – Contract
Project Integration Management
• Develop Project Charter – I (cont’d)
  – EEF
     • Governmental or industry standards, Organization
       structure, marketplace condition
  – OPA
     • Organizational standard
       processes, policies, standardized process
       definitions, Templates, Historical information, and
       lesson learned knowledge base
Project Integration Management
• Develop Project Charter – TT
  – Expert judgment
     • Consultants, stakeholders, industry groups, subject
       matter experts, PMO
Project Integration Management
• Develop Project Charter – O
  – Project Charter
     • Project purpose and justification
     • Measurable project objectives and related success
       criteria
     • High level requirements
     • High level project description
     • High level risks
     • Summary milestone schedule
     • Summary budget
Project Integration Management
• Develop Project Charter – O (cont’d)
  – Project Charter
     • Project approval requirements
     • Assigned project manager, responsibility, and authority
       level
     • Name and authority of the sponsor or other person(s)
       authorizing the project charter
Project Integration Management
• Develop Project Management Plan
Project Integration Management
• Develop Project Management Plan – I
  – PC
  – Output from other planning processes
     • Any baselines and subsidiary management plans that
       are an output from other planning processes
     • E.g.: Project scope statement, scope
       baseline, requirements document, requirements
       management plan, cost performance
       baseline, schedule baseline, quality management
       plan, process improvement plan, human resource
       plan, communications management plan, risk and
       procurement management plan
Project Integration Management
• Develop Project Management Plan – I (cont’d)
  – EEF
  – OPA
Project Integration Management
• Develop Project Management Plan – TT
  – Expert Judgment
Project Integration Management
• Develop Project Management Plan – O
  – Project Management Plan
     • Consolidates all subsidiary management plan
        – Project life cycle
        – Implementation level in each processes
        – How to accomplish those processes
        – Dependencies and interactions between processes
        – How to execute
        – Configuration management plan
        – How to measure baseline (e.g.: scope, cost, and schedule
          baseline)
        – Communication technique
        – Key management involvement / support
Project Integration Management
• Direct and Manage Project Execution
Project Integration Management
• Direct and Manage Project Execution
Project Integration Management
Project Integration Management
• Direct and Manage Project Execution – I
  – PMP
  – Approved CR
     • Documented, authorized changes
  – EEF
  – OPA
Project Integration Management
• Direct and Manage Project Execution – TT
  – Expert Judgment
  – Project Management Information System
     • Tools (e.g.: scheduling tools)
     • Configuration management
        – To manage approved changes and baselines
        – To provide opportunity to continuously improve the project
          while considering changes impact
     • Information collection and distribution tools
Project Integration Management
• Direct and Manage Project Execution – O
  – Deliverables
  – Work Performance Information
     • Deliverable status, schedule progress, costs incurred
  – CR
  – PMP U
  – PD U
Project Integration Management
• Monitor and Control Project Work
Project Integration Management
• Monitor and Control Project Work
Project Integration Management
• Monitor and Control Project Work – I
  – PMP
  – Performance reports
     • Current status, accomplishments, next
       activities, forecasts, issues
  – EEF
  – OPA
Project Integration Management
• Monitor and Control Project Work – TT
  – Expert Judgment
Project Integration Management
• Monitor and Control Project Work – O
  – CR (corrective, preventive, defect repair)
  – PMP U
  – PD U
Project Integration Management
• Perform Integrated Change Control
Project Integration Management
• Perform Integrated Change Control
Project Integration Management
• Perform Integrated Change Control
Project Integration Management
• Perform Integrated Change Control – I
  – PMP
  – WPI
  – CR
  – EEF
  – OPA
Project Integration Management
• Perform Integrated Change Control – TT
  – Expert Judgment
  – Change Control Meeting
Project Integration Management
• Perform Integrated Change Control – O
  – CR Status Update
  – PMP U
  – PD U
Project Integration Management
• Close Project or Phase
Project Integration Management
• Close Project or Phase – I
  – PMP
  – Accepted Deliverables
  – OPA
Project Integration Management
• Close Project or Phase – TT
  – Expert Judgment
Project Integration Management
• Close Project or Phase – O
  – Final product, service, or result transition
  – OPA U
Project Scope Management
Project Scope Management
• Collect Requirements
Project Scope Management
• Collect Requirements – I
  – PC
  – Stakeholder Register
Project Scope Management
• Collect Requirements – TT
  – Interview
  – Focus Groups
     • Interactive discussions with prequalified stakeholders
       and SME
  – Facilitated Workshops
     • Focused session with cross-functional stakeholders to
       get stakeholders’ agreement
     • E.g.: JAD (Joint Application Development)
     • E.g.: QFD (Quality Function Deployment)
     • E.g.: VOC (Voice of Customer)
Project Scope Management
• Collect Requirements – TT (cont’d)
  – Group Creativity Techniques
     • Brainstorming
     • Nominal Group Technique
        – A brainstorming with voting process, ranking, and
          prioritization
     • The Delphi Technique
        – Anonymous questionnaire for a selected expert group
     • Idea / Mind Mapping
     • Affinity Diagram
        – Sorting large numbers of ideas for review and analysis
Project Scope Management
• Collect Requirements – TT (cont’d)
  – Group Decision Making Techniques
Project Scope Management
• Collect Requirements – TT (cont’d)
  – Questionnaires and Surveys
  – Observations
  – Prototypes
Project Scope Management
• Collect Requirements – O
  – Requirements Documentation
Project Scope Management
• Collect Requirements – O (cont’d)
  – Requirements Management Plan
     • How requirements activities will be
       planned, tracked, and reported
     • Configuration management
        – Changes management initiation
        – Changes impact analysis
        – Changes authorization / approval level
     • Requirements prioritization
     • Product metrics
     • Traceability structure to trace project documents
Project Scope Management
• Collect Requirements – O (cont’d)
  – Requirement Traceability Matrix
Project Scope Management
• Collect Requirements – O (cont’d)
  – Requirement Traceability Matrix
     • Typical Attributes:
        –   Unique id
        –   Description
        –   Reasons
        –   Owner
        –   Source
        –   Priority
        –   Version
        –   Status
        –   Date Completed
Project Scope Management
• Define Scope
Project Scope Management
• Define Scope – I
  – PC
  – ReqDoc
  – OPA
Project Scope Management
• Define Scope – TT
  – Expert Judgment
  – Product Analysis
  – Alternative Identification
  – Facilitated Workshops
Project Scope Management
• Define Scope – O
  – Project Scope Statement (description of project
    deliverables and the work required to create those
    deliverables)
     • Product scope description (product, service, or result
       characteristics)
     • Product acceptance criteria
     • Project deliverables
     • Project exclusions
     • Project constraints
     • Project assumptions
Project Scope Management
• Define Scope – O (cont’d)
  – PD U
Project Scope Management
• Create WBS
Project Scope Management
• Create WBS – I
  – Project Scope Statement
  – ReqDoc
  – OPA
Project Scope Management
• Create WBS – TT
  – Decomposition
Project Scope Management
• Create WBS – TT (cont’d)
  – Decomposition
Project Scope Management
• Create WBS – O
  – WBS
  – WBS Dictionary
    • Provides detailed descriptions of the components in
      the WBS, e.g.: code of account identifier, cost
      estimates, acceptance criteria, technical
      reference, work description,
  – Scope Baseline (Project Scope
    Statement, WBS, WBS Dictionary)
  – PD U
Project Scope Management
• Verify Scope
Project Scope Management
• Verify Scope – I
  – PMP
  – ReqDoc
  – ReqTrac Matrix
  – Validated Deliverables
Project Scope Management
• Verify Scope – TT
  – Inspection
     • Measuring, examining, and verifying to determine
       whether work and deliverables meet the requirements
       and product acceptance criteria
     • Might be called: audits, product review, walkthrough
Project Scope Management
• Verify Scope – O
  – Accepted Deliverables
  – CR
  – PD U
Project Scope Management
• Control Scope
Project Scope Management
• Control Scope – I
  – PMP
  – WPI
  – ReqDoc
  – ReqTrac Matrix
  – OPA
Project Scope Management
• Control Scope – TT
  – Variance Analysis
     • Assessment on variation magnitude from the original
       baseline including root cause analyses, degree of
       variance, and action requirement
Project Scope Management
• Control Scope – O
  – Work Performance Measurements
     • Actual vs planned performance
  – OPA U
  – CR
  – PMP U
  – PD U
Sample Questions

   Which of the following issues the project
   charter document?
A. The performing organization’s higher
  management
B. Any stakeholder
C. The customer
D. The project manager
Sample Questions

   What document is the result of the project
   initiation process group?
A. Statement of work
B. Project charter
C. Scope plan document
D. Preliminary scope statement
Sample Questions
   The project charter is important for which of
   the following reasons?
A. It authorizes the sponsor.
B. It names the project manager and authorizes
  the project manager to use the organization’s
  resources for the project.
C. It identifies all the stakeholders.
D. It produces the stakeholder management
  strategy.
Sample Questions

   Which of the following is not included in the
   project charter?
A. The purpose of the project
B. High-level product requirements
C. Budget summary
D. Project schedule
Sample Questions

   Which of the following is not an input to
   identifying stakeholders?
A. Project charter
B. Contract
C. Approved project schedule
D. Stakeholder register template
Sample Questions
   Which of the following lists the documents
   in the order their first drafts are written?
A. Statement of work, project
  charter, stakeholder register
B. Project charter, statement of
  work, stakeholder register
C. Stakeholder register, project
  charter, statement of work
D. Statement of work, stakeholder
  register, project charter
Sample Questions
   You have been named the project manager
   for a project in your company codenamed
   “Thank You Mr. Glad”. The project must
   complete before Thanksgiving Day this year.
   This represents which of the following
   project characteristics?
A. Assumption
B. Constraint
C. Schedule
D. Crashing
Sample Questions
    Which of the following is true about assumptions
    in the project initiation?
A. Because assumptions are a part of the project
   charter that you did not write, you don’t need to
   validate them. Just assume the assumptions are
   true, and if the project fails, it’s not your fault.
B. Because assumptions represent risk, you must
   validate them at various stages of the project.
C. An assumption is a condition that has been verified
   to be true, so you don’t need to validate it.
D. You must not start a project until all the
   assumptions have been proven to be true.
Sample Questions

   Which of the following is not an example of
   a project selection method?
A. Enterprise environmental factors
B. Scoring models
C. Benefit cost ratio
D. Constrained optimization methods
Sample Questions

    Your company runs a website that makes digital music
    downloads available to end users.
    You have been assigned a project that involves adding
    parental guidance warnings
    attached to various downloads. This project originated due
    to which of the following?
A. Business requirements that may include legal requirements
B. Opportunity
C. Problems
D. Internal business needs
Sample Questions

   Which of the following is not an example of
   a project selection method?
A. Enterprise environmental factors
B. Scoring models
C. Benefit cost ratio
D. Constrained optimization methods
Sample Questions

    Which of the following is a false statement about the WBS?
A. Each item in the WBS (not just the work packages) is
   assigned a unique identifier called a code of account
   identifier.
B. You should keep decomposing WBS components to lower
   levels until necessary and sufficient decomposition has been
   achieved.
C. Each work component appears in the WBS once and only
   once.
D. The work packages should appear from left to right in the
   order in which the work will be performed.
Sample Questions

   Which of the following is done first?
A. Creating the scope statement
B. Creating the WBS
C. Creating the requirements documentation
D. Creating the project charter
Sample Questions

   The WBS is the output of which of the
   following processes?
A. The Create WBS process
B. The Define Scope process
C. The Develop WBS process
D. The Project Initiating process
Sample Questions

   The project scope statement is the output of
   which of the following processes?
A. The Create WBS process
B. The Define Scope process
C. The Create Project Scope process
D. The Project Initiating process
Sample Questions

   Which of the following is a false statement
   about the project scope management plan?
A. It describes how to verify the scope.
B. It describes how to control the scope.
C. It serves as the baseline for the project
  scope.
D. It describes how to create the WBS.
Sample Questions

   What are the components in the lowest level
   of the WBS hierarchy collectively called?
A. Work packages
B. Milestones
C. Phases
D. Features
Sample Questions

   Which of the following is not a constraint
   common to the projects?
A. Resources
B. Imposed date
C. Schedule milestone
D. Skill set
Sample Questions

   Which of the following constitutes the
   project scope baseline?
A. The WBS document and the scope statement
B. The scope statement
C. The WBS document
D. The WBS, the WBS dictionary, and the scope
  statement
Sample Questions

   Who creates the WBS?
A. The project manager alone
B. The upper management in the performing
  organization
C. The customer
D. The project manager with help from the
  project team
Sample Questions

   Which of the following is not included in the
   project scope statement?
A. Project assumptions and constraints
B. The WBS
C. Product description
D. Project deliverables
Sample Questions

   You are in the process of developing the
   scope management plan for your project.
   You will develop this plan:
A. By performing the Scope Planning process
B. By performing the Define Scope process
C. As a part of the effort to develop the project
  management plan
D. During the initiation stage of the project
Sample Questions

   You are in the planning stage of a project. Walking
   down the hallway, your supervisor
   mumbles, “Don’t forget job shadowing.” Job
   shadowing is a technique used in:
A. Defining the project scope
B. Collecting product requirements
C. Creating the WBS
D. Developing the stakeholder management strategy
Sample Questions

    You are planning the scope for your project. You have just
    created the requirements
    documentation after meeting with the stakeholders and
    studying the project charter. This requirements
    documentation can be used in developing:
A. The stakeholder register and project scope statement
B. The project charter and the WBS
C. The stakeholder register and the project charter
D. The project scope statement and the WBS
Sample Questions

    Which of the following is the correct order of
    running processes?
A. Develop project charter, Collect Requirements, and
   Create WBS
B. Collect Requirements, Develop Project Charter, and
   Define WBS
C. Identify Stakeholders, Define Scope, and Collect
   Requirements
D. Collect Requirements, Create WBS, Define Scope
Sample Questions

   You have selected a node in the hierarchy of the
   WBS that you will use to compare
   schedule, cost, and scope with the earned value in
   order to measure the project performance.
This node or component in the WBS is called:
A. Code of accounts
B. Control account
C. Management account
D. Performance node

Pmp session 2

  • 1.
    PMP & CAPM ExamPreparation January 29, 2013
  • 2.
    Sessions 1. About theexam 2. Integration & Scope Management 3. Time & Cost Management 4. Quality & HR Management 5. Communication & Risk Management 6. Procurement Management
  • 3.
    Last Session Keypoint • General concepts – Project management processes – Input, Tools & Techniques, Output – Organizational Structure – Enterprise environment factors – Organizational process assets – Exam formula
  • 4.
    Last Session Keypoint – cont’d • CAPM and PMP exam differences • Exam preparation • Study plan • General concepts – 5 Process Groups – 9 Knowledge Areas – Projects vs Operations – Projects vs Programs vs Portfolio – Project documents vs Project management plan
  • 5.
  • 6.
    Project Integration Management •Develop Project Charter
  • 7.
    Project Integration Management •Develop Project Charter – I – SOW • Business needs, Product scope description, Strategic plan – BC • Market demand, Organizational need, Customer request, Technological advance, Legal requirement, Ecological impact, Social need – Contract
  • 8.
    Project Integration Management •Develop Project Charter – I (cont’d) – EEF • Governmental or industry standards, Organization structure, marketplace condition – OPA • Organizational standard processes, policies, standardized process definitions, Templates, Historical information, and lesson learned knowledge base
  • 9.
    Project Integration Management •Develop Project Charter – TT – Expert judgment • Consultants, stakeholders, industry groups, subject matter experts, PMO
  • 10.
    Project Integration Management •Develop Project Charter – O – Project Charter • Project purpose and justification • Measurable project objectives and related success criteria • High level requirements • High level project description • High level risks • Summary milestone schedule • Summary budget
  • 11.
    Project Integration Management •Develop Project Charter – O (cont’d) – Project Charter • Project approval requirements • Assigned project manager, responsibility, and authority level • Name and authority of the sponsor or other person(s) authorizing the project charter
  • 12.
    Project Integration Management •Develop Project Management Plan
  • 13.
    Project Integration Management •Develop Project Management Plan – I – PC – Output from other planning processes • Any baselines and subsidiary management plans that are an output from other planning processes • E.g.: Project scope statement, scope baseline, requirements document, requirements management plan, cost performance baseline, schedule baseline, quality management plan, process improvement plan, human resource plan, communications management plan, risk and procurement management plan
  • 14.
    Project Integration Management •Develop Project Management Plan – I (cont’d) – EEF – OPA
  • 15.
    Project Integration Management •Develop Project Management Plan – TT – Expert Judgment
  • 16.
    Project Integration Management •Develop Project Management Plan – O – Project Management Plan • Consolidates all subsidiary management plan – Project life cycle – Implementation level in each processes – How to accomplish those processes – Dependencies and interactions between processes – How to execute – Configuration management plan – How to measure baseline (e.g.: scope, cost, and schedule baseline) – Communication technique – Key management involvement / support
  • 17.
    Project Integration Management •Direct and Manage Project Execution
  • 18.
    Project Integration Management •Direct and Manage Project Execution
  • 19.
  • 20.
    Project Integration Management •Direct and Manage Project Execution – I – PMP – Approved CR • Documented, authorized changes – EEF – OPA
  • 21.
    Project Integration Management •Direct and Manage Project Execution – TT – Expert Judgment – Project Management Information System • Tools (e.g.: scheduling tools) • Configuration management – To manage approved changes and baselines – To provide opportunity to continuously improve the project while considering changes impact • Information collection and distribution tools
  • 22.
    Project Integration Management •Direct and Manage Project Execution – O – Deliverables – Work Performance Information • Deliverable status, schedule progress, costs incurred – CR – PMP U – PD U
  • 23.
    Project Integration Management •Monitor and Control Project Work
  • 24.
    Project Integration Management •Monitor and Control Project Work
  • 25.
    Project Integration Management •Monitor and Control Project Work – I – PMP – Performance reports • Current status, accomplishments, next activities, forecasts, issues – EEF – OPA
  • 26.
    Project Integration Management •Monitor and Control Project Work – TT – Expert Judgment
  • 27.
    Project Integration Management •Monitor and Control Project Work – O – CR (corrective, preventive, defect repair) – PMP U – PD U
  • 28.
    Project Integration Management •Perform Integrated Change Control
  • 29.
    Project Integration Management •Perform Integrated Change Control
  • 30.
    Project Integration Management •Perform Integrated Change Control
  • 31.
    Project Integration Management •Perform Integrated Change Control – I – PMP – WPI – CR – EEF – OPA
  • 32.
    Project Integration Management •Perform Integrated Change Control – TT – Expert Judgment – Change Control Meeting
  • 33.
    Project Integration Management •Perform Integrated Change Control – O – CR Status Update – PMP U – PD U
  • 34.
    Project Integration Management •Close Project or Phase
  • 35.
    Project Integration Management •Close Project or Phase – I – PMP – Accepted Deliverables – OPA
  • 36.
    Project Integration Management •Close Project or Phase – TT – Expert Judgment
  • 37.
    Project Integration Management •Close Project or Phase – O – Final product, service, or result transition – OPA U
  • 38.
  • 39.
    Project Scope Management •Collect Requirements
  • 40.
    Project Scope Management •Collect Requirements – I – PC – Stakeholder Register
  • 41.
    Project Scope Management •Collect Requirements – TT – Interview – Focus Groups • Interactive discussions with prequalified stakeholders and SME – Facilitated Workshops • Focused session with cross-functional stakeholders to get stakeholders’ agreement • E.g.: JAD (Joint Application Development) • E.g.: QFD (Quality Function Deployment) • E.g.: VOC (Voice of Customer)
  • 42.
    Project Scope Management •Collect Requirements – TT (cont’d) – Group Creativity Techniques • Brainstorming • Nominal Group Technique – A brainstorming with voting process, ranking, and prioritization • The Delphi Technique – Anonymous questionnaire for a selected expert group • Idea / Mind Mapping • Affinity Diagram – Sorting large numbers of ideas for review and analysis
  • 43.
    Project Scope Management •Collect Requirements – TT (cont’d) – Group Decision Making Techniques
  • 44.
    Project Scope Management •Collect Requirements – TT (cont’d) – Questionnaires and Surveys – Observations – Prototypes
  • 45.
    Project Scope Management •Collect Requirements – O – Requirements Documentation
  • 46.
    Project Scope Management •Collect Requirements – O (cont’d) – Requirements Management Plan • How requirements activities will be planned, tracked, and reported • Configuration management – Changes management initiation – Changes impact analysis – Changes authorization / approval level • Requirements prioritization • Product metrics • Traceability structure to trace project documents
  • 47.
    Project Scope Management •Collect Requirements – O (cont’d) – Requirement Traceability Matrix
  • 48.
    Project Scope Management •Collect Requirements – O (cont’d) – Requirement Traceability Matrix • Typical Attributes: – Unique id – Description – Reasons – Owner – Source – Priority – Version – Status – Date Completed
  • 49.
  • 50.
    Project Scope Management •Define Scope – I – PC – ReqDoc – OPA
  • 51.
    Project Scope Management •Define Scope – TT – Expert Judgment – Product Analysis – Alternative Identification – Facilitated Workshops
  • 52.
    Project Scope Management •Define Scope – O – Project Scope Statement (description of project deliverables and the work required to create those deliverables) • Product scope description (product, service, or result characteristics) • Product acceptance criteria • Project deliverables • Project exclusions • Project constraints • Project assumptions
  • 53.
    Project Scope Management •Define Scope – O (cont’d) – PD U
  • 54.
  • 55.
    Project Scope Management •Create WBS – I – Project Scope Statement – ReqDoc – OPA
  • 56.
    Project Scope Management •Create WBS – TT – Decomposition
  • 57.
    Project Scope Management •Create WBS – TT (cont’d) – Decomposition
  • 58.
    Project Scope Management •Create WBS – O – WBS – WBS Dictionary • Provides detailed descriptions of the components in the WBS, e.g.: code of account identifier, cost estimates, acceptance criteria, technical reference, work description, – Scope Baseline (Project Scope Statement, WBS, WBS Dictionary) – PD U
  • 59.
  • 60.
    Project Scope Management •Verify Scope – I – PMP – ReqDoc – ReqTrac Matrix – Validated Deliverables
  • 61.
    Project Scope Management •Verify Scope – TT – Inspection • Measuring, examining, and verifying to determine whether work and deliverables meet the requirements and product acceptance criteria • Might be called: audits, product review, walkthrough
  • 62.
    Project Scope Management •Verify Scope – O – Accepted Deliverables – CR – PD U
  • 63.
  • 64.
    Project Scope Management •Control Scope – I – PMP – WPI – ReqDoc – ReqTrac Matrix – OPA
  • 65.
    Project Scope Management •Control Scope – TT – Variance Analysis • Assessment on variation magnitude from the original baseline including root cause analyses, degree of variance, and action requirement
  • 66.
    Project Scope Management •Control Scope – O – Work Performance Measurements • Actual vs planned performance – OPA U – CR – PMP U – PD U
  • 67.
    Sample Questions Which of the following issues the project charter document? A. The performing organization’s higher management B. Any stakeholder C. The customer D. The project manager
  • 68.
    Sample Questions What document is the result of the project initiation process group? A. Statement of work B. Project charter C. Scope plan document D. Preliminary scope statement
  • 69.
    Sample Questions The project charter is important for which of the following reasons? A. It authorizes the sponsor. B. It names the project manager and authorizes the project manager to use the organization’s resources for the project. C. It identifies all the stakeholders. D. It produces the stakeholder management strategy.
  • 70.
    Sample Questions Which of the following is not included in the project charter? A. The purpose of the project B. High-level product requirements C. Budget summary D. Project schedule
  • 71.
    Sample Questions Which of the following is not an input to identifying stakeholders? A. Project charter B. Contract C. Approved project schedule D. Stakeholder register template
  • 72.
    Sample Questions Which of the following lists the documents in the order their first drafts are written? A. Statement of work, project charter, stakeholder register B. Project charter, statement of work, stakeholder register C. Stakeholder register, project charter, statement of work D. Statement of work, stakeholder register, project charter
  • 73.
    Sample Questions You have been named the project manager for a project in your company codenamed “Thank You Mr. Glad”. The project must complete before Thanksgiving Day this year. This represents which of the following project characteristics? A. Assumption B. Constraint C. Schedule D. Crashing
  • 74.
    Sample Questions Which of the following is true about assumptions in the project initiation? A. Because assumptions are a part of the project charter that you did not write, you don’t need to validate them. Just assume the assumptions are true, and if the project fails, it’s not your fault. B. Because assumptions represent risk, you must validate them at various stages of the project. C. An assumption is a condition that has been verified to be true, so you don’t need to validate it. D. You must not start a project until all the assumptions have been proven to be true.
  • 75.
    Sample Questions Which of the following is not an example of a project selection method? A. Enterprise environmental factors B. Scoring models C. Benefit cost ratio D. Constrained optimization methods
  • 76.
    Sample Questions Your company runs a website that makes digital music downloads available to end users. You have been assigned a project that involves adding parental guidance warnings attached to various downloads. This project originated due to which of the following? A. Business requirements that may include legal requirements B. Opportunity C. Problems D. Internal business needs
  • 77.
    Sample Questions Which of the following is not an example of a project selection method? A. Enterprise environmental factors B. Scoring models C. Benefit cost ratio D. Constrained optimization methods
  • 78.
    Sample Questions Which of the following is a false statement about the WBS? A. Each item in the WBS (not just the work packages) is assigned a unique identifier called a code of account identifier. B. You should keep decomposing WBS components to lower levels until necessary and sufficient decomposition has been achieved. C. Each work component appears in the WBS once and only once. D. The work packages should appear from left to right in the order in which the work will be performed.
  • 79.
    Sample Questions Which of the following is done first? A. Creating the scope statement B. Creating the WBS C. Creating the requirements documentation D. Creating the project charter
  • 80.
    Sample Questions The WBS is the output of which of the following processes? A. The Create WBS process B. The Define Scope process C. The Develop WBS process D. The Project Initiating process
  • 81.
    Sample Questions The project scope statement is the output of which of the following processes? A. The Create WBS process B. The Define Scope process C. The Create Project Scope process D. The Project Initiating process
  • 82.
    Sample Questions Which of the following is a false statement about the project scope management plan? A. It describes how to verify the scope. B. It describes how to control the scope. C. It serves as the baseline for the project scope. D. It describes how to create the WBS.
  • 83.
    Sample Questions What are the components in the lowest level of the WBS hierarchy collectively called? A. Work packages B. Milestones C. Phases D. Features
  • 84.
    Sample Questions Which of the following is not a constraint common to the projects? A. Resources B. Imposed date C. Schedule milestone D. Skill set
  • 85.
    Sample Questions Which of the following constitutes the project scope baseline? A. The WBS document and the scope statement B. The scope statement C. The WBS document D. The WBS, the WBS dictionary, and the scope statement
  • 86.
    Sample Questions Who creates the WBS? A. The project manager alone B. The upper management in the performing organization C. The customer D. The project manager with help from the project team
  • 87.
    Sample Questions Which of the following is not included in the project scope statement? A. Project assumptions and constraints B. The WBS C. Product description D. Project deliverables
  • 88.
    Sample Questions You are in the process of developing the scope management plan for your project. You will develop this plan: A. By performing the Scope Planning process B. By performing the Define Scope process C. As a part of the effort to develop the project management plan D. During the initiation stage of the project
  • 89.
    Sample Questions You are in the planning stage of a project. Walking down the hallway, your supervisor mumbles, “Don’t forget job shadowing.” Job shadowing is a technique used in: A. Defining the project scope B. Collecting product requirements C. Creating the WBS D. Developing the stakeholder management strategy
  • 90.
    Sample Questions You are planning the scope for your project. You have just created the requirements documentation after meeting with the stakeholders and studying the project charter. This requirements documentation can be used in developing: A. The stakeholder register and project scope statement B. The project charter and the WBS C. The stakeholder register and the project charter D. The project scope statement and the WBS
  • 91.
    Sample Questions Which of the following is the correct order of running processes? A. Develop project charter, Collect Requirements, and Create WBS B. Collect Requirements, Develop Project Charter, and Define WBS C. Identify Stakeholders, Define Scope, and Collect Requirements D. Collect Requirements, Create WBS, Define Scope
  • 92.
    Sample Questions You have selected a node in the hierarchy of the WBS that you will use to compare schedule, cost, and scope with the earned value in order to measure the project performance. This node or component in the WBS is called: A. Code of accounts B. Control account C. Management account D. Performance node