PMP®                Sample
                       Questions

PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the
development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every
attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam.
However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially
published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or
expressed by OSP International LLC.
This presentation will showcase free sample
  PMP® questions that will help and guide
    you in studying for your PMP® exam

Find more free sample questions when you visit
    www.free-pm-exam-questions.com and
        free.pm-exam-simulator.com
Sample PMP® Exam Question

Which of the following diagramming techniques is a typical display of
Sensitivity Analysis?

  a. Influence Diagram
  b. Network Diagram
  c. Fishbone Diagram
  d. Tornado Diagram




HINT: It compares relative importance and impact of variables that have a
high degree of uncertainty to those that are more stable.
Answer and Explanation
          The correct answer is D

          One typical display of Sensitivity Analysis is
          the Tornado Diagram, which is useful for
          comparing the relative importance and
          impact of variables that have a high degree
          of uncertainty to those that are more
          stable.
Sample PMP® Exam Question

Which of the following statements regarding WBS
templates is incorrect?

  a. They are always present in Organizational
     Process Assets.
  b. They provide a starting point for WBS
     creation.
  c. They may help determine the appropriate
     level of detail required.
  d. They enhance cross-project WBS consistency.

HINT: WBS templates can help you create your projectWBS.
Answer and Explanation
          The correct answer is A

          WBS Templates can be found in
          Organizational Process Assets but we
          cannot say they will always be available.
Sample PMP® Exam Question

Project Integration Management consists of all of the following activities
except?

  a. Develop Project Charter
  b. Develop Project Management Plan
  c. Perform Integrated Change Control
  d. Collect Requirements




HINT: Project Integration Management includes the processes and activities
to identify, define, combine, unify, and coordinate various processes and
activities.
Answer and Explanation
          The correct answer is D

          Collect Requirements is not a process in
          Project Integration Management. This
          process is contained in Project Scope
          Management.
Sample PMP® Exam Question

The risk shared between the buyer and the seller is determined by which of
the following?

  a. The Scope of Work
  b. The Teaming Agreement
  c. The Contract Type
  d. The Project Charter




HINT: How can you control the project risk while
negotiating the scope of work with a seller?
Answer and Explanation
          The correct answer is C

          The risk shared between the buyer and
          seller is determined by the contract type.
          For example, fixed-price contracts have a
          higher risk for the seller while cost-
          reimbursable contracts have a higher risk
          for the buyer.
Sample PMP® Exam Question

You are developing your IT development project team. Some of the team
members need training on the latest software that you are using in your
project. Which of the following documents is most useful to find out the
information regarding the scheduled training for the team members?

  a. Project Staff Assignments
  b. Training Management Plan
  c. Staffing Management Plan
  d. Human Resource Plan


HINT: Training needs are developed during the
early stages of planning.
Answer and Explanation
          The correct answer is D

          The Human Resource Plan is used to
          document details about training and
          training schedules.

PMP Sample Questions Set 3

  • 1.
    PMP® Sample Questions PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.
  • 2.
    This presentation willshowcase free sample PMP® questions that will help and guide you in studying for your PMP® exam Find more free sample questions when you visit www.free-pm-exam-questions.com and free.pm-exam-simulator.com
  • 3.
    Sample PMP® ExamQuestion Which of the following diagramming techniques is a typical display of Sensitivity Analysis? a. Influence Diagram b. Network Diagram c. Fishbone Diagram d. Tornado Diagram HINT: It compares relative importance and impact of variables that have a high degree of uncertainty to those that are more stable.
  • 4.
    Answer and Explanation The correct answer is D One typical display of Sensitivity Analysis is the Tornado Diagram, which is useful for comparing the relative importance and impact of variables that have a high degree of uncertainty to those that are more stable.
  • 5.
    Sample PMP® ExamQuestion Which of the following statements regarding WBS templates is incorrect? a. They are always present in Organizational Process Assets. b. They provide a starting point for WBS creation. c. They may help determine the appropriate level of detail required. d. They enhance cross-project WBS consistency. HINT: WBS templates can help you create your projectWBS.
  • 6.
    Answer and Explanation The correct answer is A WBS Templates can be found in Organizational Process Assets but we cannot say they will always be available.
  • 7.
    Sample PMP® ExamQuestion Project Integration Management consists of all of the following activities except? a. Develop Project Charter b. Develop Project Management Plan c. Perform Integrated Change Control d. Collect Requirements HINT: Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate various processes and activities.
  • 8.
    Answer and Explanation The correct answer is D Collect Requirements is not a process in Project Integration Management. This process is contained in Project Scope Management.
  • 9.
    Sample PMP® ExamQuestion The risk shared between the buyer and the seller is determined by which of the following? a. The Scope of Work b. The Teaming Agreement c. The Contract Type d. The Project Charter HINT: How can you control the project risk while negotiating the scope of work with a seller?
  • 10.
    Answer and Explanation The correct answer is C The risk shared between the buyer and seller is determined by the contract type. For example, fixed-price contracts have a higher risk for the seller while cost- reimbursable contracts have a higher risk for the buyer.
  • 11.
    Sample PMP® ExamQuestion You are developing your IT development project team. Some of the team members need training on the latest software that you are using in your project. Which of the following documents is most useful to find out the information regarding the scheduled training for the team members? a. Project Staff Assignments b. Training Management Plan c. Staffing Management Plan d. Human Resource Plan HINT: Training needs are developed during the early stages of planning.
  • 12.
    Answer and Explanation The correct answer is D The Human Resource Plan is used to document details about training and training schedules.