Sample PMP Exam
Questions
Sample PMP Exam Questions
Q1-) Which of the following is NOT true for a project?
A-) Projects are constrained by limited resources
B-) Projects are planned, executed, and controlled
C-) Projects create a unique product or service
D-) Projects are ongoing and repetitive
Sample PMP Exam Questions
Q1-) Which of the following is NOT true for a project?
A-) Projects are constrained by limited resources
B-) Projects are planned, executed, and controlled
C-) Projects create a unique product or service
D-) Projects are ongoing and repetitive
A project is a temporary endeavor undertaken to create a unique product, service,
or result. The temporary nature of projects indicates a definite beginning and
ending.
Reference: PMBOK Guide Fifth Edition, Page 3, Knowledge Area: N/A
(Introduction)
Sample PMP Exam Questions
Q2-) Which of the following documents include code of account identifier,
description of work, responsible organization, and list of schedule
milestones?
A-) PERT/CPM Charts
B-) WBS
C-) WBS Dictionary
D-) Roles and Responsibilities Matrix
Visit:
http://masterofproject.com/cours
es/realistic-pmp-exam-math-rev-
readiness-check-for-real-exam
for full PMP Exams
Sample PMP Exam Questions
Q2-) Which of the following documents include code of account identifier, description
of work, responsible organization, and list of schedule milestones?
A-) PERT/CPM Charts
B-) WBS
C-) WBS Dictionary
D-) Roles and Responsibilities Matrix
The WBS dictionary is a document that provides detailed deliverable, activity, and scheduling
information about each component in the WBS. WBS dictionary may include, but is not limited
to, code of account identifier, description of work, responsible organization, list of schedule
milestones, etc.
Reference: PMBOK Guide Fifth Edition, Page 132, Knowledge Area: Scope Management
Sample PMP Exam Questions
Q3-) All the following statements relating to the project management team and the
project team are correct EXCEPT:
A-)The project team is responsible for activities like planning, executing, and closing.
B-) The project management team can be called as the core, executive, or leadership
team.
C-) The project management team is also a part of the project team.
D-) In a small project, the project management responsibilities can be shared by team
members instead of a project manager.
Visit: http://masterofproject.com/courses/realistic-pmp-exam-math-rev-
readiness-check-for-real-exam for full PMP Exams
Sample PMP Exam Questions
Q3-) All the following statements relating to the project management team and the
project team are correct EXCEPT:
A-)The project team is responsible for activities like planning, executing, and closing.
B-) The project management team can be called as the core, executive, or leadership
team.
C-) The project management team is also a part of the project team.
D-) In a small project, the project management responsibilities can be shared by team
members instead of a project manager.
The project management team is a subset of the project team and is responsible for the Project management and
leadership activities such as initiating, planning, executing, monitoring, controlling, and closing the various project
phases. This group can also be referred to as the core, executive, or leadership team. For smaller projects, the project
management responsibilities can be shared by the entire team or administered solely by the project manager.
Reference: PMBOK Guide Fifth Edition, Page 256, Knowledge Area: Human Resource Management
Sample PMP Exam Questions
Q4-) You are a project manager trying to decide whether to buy or make a testing tool for your project.
If you want to buy, the cost of the tool is $60,000, and the proceeding the procurement, additional cost
of integration of the tool in your company is $ 1,000. If you build it yourself, the tool will be developed
by eight engineers working for two months. The salary of each software engineer is $4,000 per month. If
you build it yourself, the other related various costs will be $2,000.
Which option will you prefer?
A-) Buying the testing tool
B-) Building the testing tool
C-) Neither build nor buy testing tool
D-) Need more information on costs to take a further decision
Visit:
http://masterofproject.com/courses/realistic
-pmp-exam-math-rev-readiness-check-for-
real-exam for full PMP Exams
Sample PMP Exam Questions
Q4-) You are a project manager trying to decide whether to buy or make a testing tool for your project.
If you want to buy, the cost of the tool is $60,000, and the proceeding the procurement, additional cost
of integration of the tool in your company is $ 1,000. If you build it yourself, the tool will be developed
by eight engineers working for two months. The salary of each software engineer is $4,000 per month. If
you build it yourself, the other related various costs will be $2,000.
Which option will you prefer?
A-) Buying the testing tool
B-) Building the testing tool
C-) Neither build nor buy testing tool
D-) Need more information on costs to take a further decision
Sample PMP Exam Questions
Budget constraints may influence make -or-buy decisions. If a buy decision is to be made,
then a further decision of whether to purchase or lease is also made. A make -or- buy
analysis should consider all related costs -both direct costs as well as indirect costs.
For example, the buy side of the analysis includes both the actual out -of- pocket costs to
purchase the product, as well as the indirect costs of supporting the purchasing process
and purchased item.
Cost of buying the tool: $60,000 + $1000 = $61,000
Cost of building the tool: $4,000x8x2 + $2,000 = $66,000
So, buying is cheaper than building. Buying is preferable
Reference: PMBOK Guide Fifth Edition, Page 365, Knowledge Area: Procurement
Management
Sample PMP Exam Questions
Q5-) When referring to inputs for Develop Schedule process,
responsibility (i.e., who will perform the work), activity type (i.e.,
summary or detailed), and WBS lassification are belonging to:
A-) Risks
B-) Account identifier
C-) Activity attributes
D-) Activity estimations
Visit:
http://masterofproject.com/courses/realistic
-pmp-exam-math-rev-readiness-check-for-
real-exam for full PMP Exams
Sample PMP Exam Questions
Q5-) When referring to inputs for Develop Schedule process,
responsibility (i.e., who will perform the work), activity type (i.e.,
summary or detailed), and WBS lassification are belonging to:
A-) Risks
B-) Account identifier
C-) Activity attributes
D-) Activity estimations
Activity attributes can be used to identify the person responsible for executing the work, geographic area, or place
where the work has to be performed, and activity type such as level of effort (LOE), discrete effort, and apportioned
effort (AE). Activity attributes are used for schedule
development and for selecting, ordering, and sorting the planned schedule activities in various ways within
reports.
Reference: PMBOK Guide Fifth Edition, Page 153,Knowledge Area: Time Management
Visit:
http://masterofproject.com/courses/realistic
-pmp-exam-math-rev-readiness-check-for-
real-exam for full PMP Exams

More Related Content

What's hot

Project scope management
Project scope managementProject scope management
Project scope managementJody R Flower
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesAnand Bobade
 
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionInstructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionMnbianchi
 
Project management
Project managementProject management
Project managementJay Raval
 
Project quality management - PMI PMBOK Knowledge Area
Project quality management - PMI PMBOK Knowledge AreaProject quality management - PMI PMBOK Knowledge Area
Project quality management - PMI PMBOK Knowledge AreaImran Jamil
 
10 project management knowledge areas
10 project management knowledge areas10 project management knowledge areas
10 project management knowledge areasInsaf Ali Soomro PMP
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation TafseerKishan Solankimbaccepmp
 
PMP Certification Presentation
PMP Certification PresentationPMP Certification Presentation
PMP Certification PresentationSimplilearn
 
Project Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th EditionProject Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th Editionpankajsh10
 
Project Risk Management - PMBOK5
Project Risk Management - PMBOK5Project Risk Management - PMBOK5
Project Risk Management - PMBOK5pankajsh10
 
Project Management
Project ManagementProject Management
Project ManagementMark Roman
 
Project Quality Management - PMBOK
Project Quality Management - PMBOKProject Quality Management - PMBOK
Project Quality Management - PMBOKArief Rahmana
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control ScopeAnand Bobade
 
Project Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsProject Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsThink For A Change
 

What's hot (20)

Project scope management 1
Project scope management 1Project scope management 1
Project scope management 1
 
Project scope management
Project scope managementProject scope management
Project scope management
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management Processes
 
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionInstructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th Edition
 
Online PMP Exam Certification Training - 35 Hours
Online PMP Exam Certification Training - 35 HoursOnline PMP Exam Certification Training - 35 Hours
Online PMP Exam Certification Training - 35 Hours
 
Project Management
Project ManagementProject Management
Project Management
 
Project management
Project managementProject management
Project management
 
Project quality management - PMI PMBOK Knowledge Area
Project quality management - PMI PMBOK Knowledge AreaProject quality management - PMI PMBOK Knowledge Area
Project quality management - PMI PMBOK Knowledge Area
 
Project quality management
Project quality managementProject quality management
Project quality management
 
10 project management knowledge areas
10 project management knowledge areas10 project management knowledge areas
10 project management knowledge areas
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 
PMP Certification Presentation
PMP Certification PresentationPMP Certification Presentation
PMP Certification Presentation
 
Project Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th EditionProject Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th Edition
 
Project Risk Management - PMBOK5
Project Risk Management - PMBOK5Project Risk Management - PMBOK5
Project Risk Management - PMBOK5
 
Project Management
Project ManagementProject Management
Project Management
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
 
10- PMP Training - Risk Management
10- PMP Training - Risk Management 10- PMP Training - Risk Management
10- PMP Training - Risk Management
 
Project Quality Management - PMBOK
Project Quality Management - PMBOKProject Quality Management - PMBOK
Project Quality Management - PMBOK
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control Scope
 
Project Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsProject Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management Concepts
 

Similar to Sample PMP Exam Questions

Pega Certified Business Architect (PCBA) Exam | Top 5 Tips
Pega Certified Business Architect (PCBA) Exam | Top 5 TipsPega Certified Business Architect (PCBA) Exam | Top 5 Tips
Pega Certified Business Architect (PCBA) Exam | Top 5 TipsMeghna Arora
 
ServiceNow CIS-PPM Exam | Sample Questions & Answers
ServiceNow CIS-PPM Exam | Sample Questions & AnswersServiceNow CIS-PPM Exam | Sample Questions & Answers
ServiceNow CIS-PPM Exam | Sample Questions & AnswersMeghna Arora
 
Session 8 Everything You Should Know About PMP & CAPM Certifications
Session 8 Everything You Should Know About PMP & CAPM CertificationsSession 8 Everything You Should Know About PMP & CAPM Certifications
Session 8 Everything You Should Know About PMP & CAPM CertificationsSeshne Govender
 
Start Your Preparation for PMI-CP Exam
Start Your Preparation for PMI-CP ExamStart Your Preparation for PMI-CP Exam
Start Your Preparation for PMI-CP ExamMeghna Arora
 
Section-1 250 words Subject Initiating the ProjectR.docx
Section-1 250 words  Subject Initiating the ProjectR.docxSection-1 250 words  Subject Initiating the ProjectR.docx
Section-1 250 words Subject Initiating the ProjectR.docxjeffreye3
 
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...JustAcademy
 
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...JustAcademy
 
pmp-examination-content-outline.pdf
pmp-examination-content-outline.pdfpmp-examination-content-outline.pdf
pmp-examination-content-outline.pdfssuserffe62d
 
project management entrance exam content.pdf
project management entrance exam content.pdfproject management entrance exam content.pdf
project management entrance exam content.pdfbaabaadur
 
Pm0011 project planning and scheduling
Pm0011   project planning and schedulingPm0011   project planning and scheduling
Pm0011 project planning and schedulingsmumbahelp
 
Cmgt 410 cmgt410 cmgt 410 education for service uopstudy.com
Cmgt 410 cmgt410 cmgt 410 education for service   uopstudy.comCmgt 410 cmgt410 cmgt 410 education for service   uopstudy.com
Cmgt 410 cmgt410 cmgt 410 education for service uopstudy.comUOPCourseHelp
 
Session 6 Everything You Should Know About PMP & CAPM Certifications
Session 6 Everything You Should Know About PMP & CAPM CertificationsSession 6 Everything You Should Know About PMP & CAPM Certifications
Session 6 Everything You Should Know About PMP & CAPM CertificationsSeshne Govender
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management FrameworkRahul Sudame
 
PMI Project Management Associate (CAPM) Certification | Study Guide
PMI Project Management Associate (CAPM) Certification | Study GuidePMI Project Management Associate (CAPM) Certification | Study Guide
PMI Project Management Associate (CAPM) Certification | Study GuideMeghna Arora
 
Certification exams pmi 001
Certification exams pmi 001Certification exams pmi 001
Certification exams pmi 001adam_jhon
 

Similar to Sample PMP Exam Questions (20)

Pega Certified Business Architect (PCBA) Exam | Top 5 Tips
Pega Certified Business Architect (PCBA) Exam | Top 5 TipsPega Certified Business Architect (PCBA) Exam | Top 5 Tips
Pega Certified Business Architect (PCBA) Exam | Top 5 Tips
 
ServiceNow CIS-PPM Exam | Sample Questions & Answers
ServiceNow CIS-PPM Exam | Sample Questions & AnswersServiceNow CIS-PPM Exam | Sample Questions & Answers
ServiceNow CIS-PPM Exam | Sample Questions & Answers
 
Session 8 Everything You Should Know About PMP & CAPM Certifications
Session 8 Everything You Should Know About PMP & CAPM CertificationsSession 8 Everything You Should Know About PMP & CAPM Certifications
Session 8 Everything You Should Know About PMP & CAPM Certifications
 
Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017
Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017
Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017
 
Start Your Preparation for PMI-CP Exam
Start Your Preparation for PMI-CP ExamStart Your Preparation for PMI-CP Exam
Start Your Preparation for PMI-CP Exam
 
Section-1 250 words Subject Initiating the ProjectR.docx
Section-1 250 words  Subject Initiating the ProjectR.docxSection-1 250 words  Subject Initiating the ProjectR.docx
Section-1 250 words Subject Initiating the ProjectR.docx
 
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
 
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
 
PMP Sample Questions Set 5
PMP Sample Questions Set 5PMP Sample Questions Set 5
PMP Sample Questions Set 5
 
pmp-examination-content-outline.pdf
pmp-examination-content-outline.pdfpmp-examination-content-outline.pdf
pmp-examination-content-outline.pdf
 
project management entrance exam content.pdf
project management entrance exam content.pdfproject management entrance exam content.pdf
project management entrance exam content.pdf
 
PMP certification
PMP certificationPMP certification
PMP certification
 
Pm0011 project planning and scheduling
Pm0011   project planning and schedulingPm0011   project planning and scheduling
Pm0011 project planning and scheduling
 
PMP Five Sample Questions
PMP Five Sample QuestionsPMP Five Sample Questions
PMP Five Sample Questions
 
Cmgt 410 cmgt410 cmgt 410 education for service uopstudy.com
Cmgt 410 cmgt410 cmgt 410 education for service   uopstudy.comCmgt 410 cmgt410 cmgt 410 education for service   uopstudy.com
Cmgt 410 cmgt410 cmgt 410 education for service uopstudy.com
 
Session 6 Everything You Should Know About PMP & CAPM Certifications
Session 6 Everything You Should Know About PMP & CAPM CertificationsSession 6 Everything You Should Know About PMP & CAPM Certifications
Session 6 Everything You Should Know About PMP & CAPM Certifications
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
PMI Project Management Associate (CAPM) Certification | Study Guide
PMI Project Management Associate (CAPM) Certification | Study GuidePMI Project Management Associate (CAPM) Certification | Study Guide
PMI Project Management Associate (CAPM) Certification | Study Guide
 
Certification exams pmi 001
Certification exams pmi 001Certification exams pmi 001
Certification exams pmi 001
 
PMP Exam Sample Questions Set 6
PMP Exam Sample Questions Set 6PMP Exam Sample Questions Set 6
PMP Exam Sample Questions Set 6
 

Recently uploaded

Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitolTechU
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
MICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxMICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxabhijeetpadhi001
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementmkooblal
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfMahmoud M. Sallam
 
CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxJiesonDelaCerna
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxDr.Ibrahim Hassaan
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 

Recently uploaded (20)

Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
MICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxMICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptx
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of management
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdf
 
CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptx
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptx
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 

Sample PMP Exam Questions

  • 2. Sample PMP Exam Questions Q1-) Which of the following is NOT true for a project? A-) Projects are constrained by limited resources B-) Projects are planned, executed, and controlled C-) Projects create a unique product or service D-) Projects are ongoing and repetitive
  • 3. Sample PMP Exam Questions Q1-) Which of the following is NOT true for a project? A-) Projects are constrained by limited resources B-) Projects are planned, executed, and controlled C-) Projects create a unique product or service D-) Projects are ongoing and repetitive A project is a temporary endeavor undertaken to create a unique product, service, or result. The temporary nature of projects indicates a definite beginning and ending. Reference: PMBOK Guide Fifth Edition, Page 3, Knowledge Area: N/A (Introduction)
  • 4. Sample PMP Exam Questions Q2-) Which of the following documents include code of account identifier, description of work, responsible organization, and list of schedule milestones? A-) PERT/CPM Charts B-) WBS C-) WBS Dictionary D-) Roles and Responsibilities Matrix Visit: http://masterofproject.com/cours es/realistic-pmp-exam-math-rev- readiness-check-for-real-exam for full PMP Exams
  • 5. Sample PMP Exam Questions Q2-) Which of the following documents include code of account identifier, description of work, responsible organization, and list of schedule milestones? A-) PERT/CPM Charts B-) WBS C-) WBS Dictionary D-) Roles and Responsibilities Matrix The WBS dictionary is a document that provides detailed deliverable, activity, and scheduling information about each component in the WBS. WBS dictionary may include, but is not limited to, code of account identifier, description of work, responsible organization, list of schedule milestones, etc. Reference: PMBOK Guide Fifth Edition, Page 132, Knowledge Area: Scope Management
  • 6. Sample PMP Exam Questions Q3-) All the following statements relating to the project management team and the project team are correct EXCEPT: A-)The project team is responsible for activities like planning, executing, and closing. B-) The project management team can be called as the core, executive, or leadership team. C-) The project management team is also a part of the project team. D-) In a small project, the project management responsibilities can be shared by team members instead of a project manager. Visit: http://masterofproject.com/courses/realistic-pmp-exam-math-rev- readiness-check-for-real-exam for full PMP Exams
  • 7. Sample PMP Exam Questions Q3-) All the following statements relating to the project management team and the project team are correct EXCEPT: A-)The project team is responsible for activities like planning, executing, and closing. B-) The project management team can be called as the core, executive, or leadership team. C-) The project management team is also a part of the project team. D-) In a small project, the project management responsibilities can be shared by team members instead of a project manager. The project management team is a subset of the project team and is responsible for the Project management and leadership activities such as initiating, planning, executing, monitoring, controlling, and closing the various project phases. This group can also be referred to as the core, executive, or leadership team. For smaller projects, the project management responsibilities can be shared by the entire team or administered solely by the project manager. Reference: PMBOK Guide Fifth Edition, Page 256, Knowledge Area: Human Resource Management
  • 8. Sample PMP Exam Questions Q4-) You are a project manager trying to decide whether to buy or make a testing tool for your project. If you want to buy, the cost of the tool is $60,000, and the proceeding the procurement, additional cost of integration of the tool in your company is $ 1,000. If you build it yourself, the tool will be developed by eight engineers working for two months. The salary of each software engineer is $4,000 per month. If you build it yourself, the other related various costs will be $2,000. Which option will you prefer? A-) Buying the testing tool B-) Building the testing tool C-) Neither build nor buy testing tool D-) Need more information on costs to take a further decision Visit: http://masterofproject.com/courses/realistic -pmp-exam-math-rev-readiness-check-for- real-exam for full PMP Exams
  • 9. Sample PMP Exam Questions Q4-) You are a project manager trying to decide whether to buy or make a testing tool for your project. If you want to buy, the cost of the tool is $60,000, and the proceeding the procurement, additional cost of integration of the tool in your company is $ 1,000. If you build it yourself, the tool will be developed by eight engineers working for two months. The salary of each software engineer is $4,000 per month. If you build it yourself, the other related various costs will be $2,000. Which option will you prefer? A-) Buying the testing tool B-) Building the testing tool C-) Neither build nor buy testing tool D-) Need more information on costs to take a further decision
  • 10. Sample PMP Exam Questions Budget constraints may influence make -or-buy decisions. If a buy decision is to be made, then a further decision of whether to purchase or lease is also made. A make -or- buy analysis should consider all related costs -both direct costs as well as indirect costs. For example, the buy side of the analysis includes both the actual out -of- pocket costs to purchase the product, as well as the indirect costs of supporting the purchasing process and purchased item. Cost of buying the tool: $60,000 + $1000 = $61,000 Cost of building the tool: $4,000x8x2 + $2,000 = $66,000 So, buying is cheaper than building. Buying is preferable Reference: PMBOK Guide Fifth Edition, Page 365, Knowledge Area: Procurement Management
  • 11. Sample PMP Exam Questions Q5-) When referring to inputs for Develop Schedule process, responsibility (i.e., who will perform the work), activity type (i.e., summary or detailed), and WBS lassification are belonging to: A-) Risks B-) Account identifier C-) Activity attributes D-) Activity estimations Visit: http://masterofproject.com/courses/realistic -pmp-exam-math-rev-readiness-check-for- real-exam for full PMP Exams
  • 12. Sample PMP Exam Questions Q5-) When referring to inputs for Develop Schedule process, responsibility (i.e., who will perform the work), activity type (i.e., summary or detailed), and WBS lassification are belonging to: A-) Risks B-) Account identifier C-) Activity attributes D-) Activity estimations Activity attributes can be used to identify the person responsible for executing the work, geographic area, or place where the work has to be performed, and activity type such as level of effort (LOE), discrete effort, and apportioned effort (AE). Activity attributes are used for schedule development and for selecting, ordering, and sorting the planned schedule activities in various ways within reports. Reference: PMBOK Guide Fifth Edition, Page 153,Knowledge Area: Time Management Visit: http://masterofproject.com/courses/realistic -pmp-exam-math-rev-readiness-check-for- real-exam for full PMP Exams