2. Sample PMP Exam Questions
Q1-) Which of the following is NOT true for a project?
A-) Projects are constrained by limited resources
B-) Projects are planned, executed, and controlled
C-) Projects create a unique product or service
D-) Projects are ongoing and repetitive
3. Sample PMP Exam Questions
Q1-) Which of the following is NOT true for a project?
A-) Projects are constrained by limited resources
B-) Projects are planned, executed, and controlled
C-) Projects create a unique product or service
D-) Projects are ongoing and repetitive
A project is a temporary endeavor undertaken to create a unique product, service,
or result. The temporary nature of projects indicates a definite beginning and
ending.
Reference: PMBOK Guide Fifth Edition, Page 3, Knowledge Area: N/A
(Introduction)
4. Sample PMP Exam Questions
Q2-) Which of the following documents include code of account identifier,
description of work, responsible organization, and list of schedule
milestones?
A-) PERT/CPM Charts
B-) WBS
C-) WBS Dictionary
D-) Roles and Responsibilities Matrix
Visit:
http://masterofproject.com/cours
es/realistic-pmp-exam-math-rev-
readiness-check-for-real-exam
for full PMP Exams
5. Sample PMP Exam Questions
Q2-) Which of the following documents include code of account identifier, description
of work, responsible organization, and list of schedule milestones?
A-) PERT/CPM Charts
B-) WBS
C-) WBS Dictionary
D-) Roles and Responsibilities Matrix
The WBS dictionary is a document that provides detailed deliverable, activity, and scheduling
information about each component in the WBS. WBS dictionary may include, but is not limited
to, code of account identifier, description of work, responsible organization, list of schedule
milestones, etc.
Reference: PMBOK Guide Fifth Edition, Page 132, Knowledge Area: Scope Management
6. Sample PMP Exam Questions
Q3-) All the following statements relating to the project management team and the
project team are correct EXCEPT:
A-)The project team is responsible for activities like planning, executing, and closing.
B-) The project management team can be called as the core, executive, or leadership
team.
C-) The project management team is also a part of the project team.
D-) In a small project, the project management responsibilities can be shared by team
members instead of a project manager.
Visit: http://masterofproject.com/courses/realistic-pmp-exam-math-rev-
readiness-check-for-real-exam for full PMP Exams
7. Sample PMP Exam Questions
Q3-) All the following statements relating to the project management team and the
project team are correct EXCEPT:
A-)The project team is responsible for activities like planning, executing, and closing.
B-) The project management team can be called as the core, executive, or leadership
team.
C-) The project management team is also a part of the project team.
D-) In a small project, the project management responsibilities can be shared by team
members instead of a project manager.
The project management team is a subset of the project team and is responsible for the Project management and
leadership activities such as initiating, planning, executing, monitoring, controlling, and closing the various project
phases. This group can also be referred to as the core, executive, or leadership team. For smaller projects, the project
management responsibilities can be shared by the entire team or administered solely by the project manager.
Reference: PMBOK Guide Fifth Edition, Page 256, Knowledge Area: Human Resource Management
8. Sample PMP Exam Questions
Q4-) You are a project manager trying to decide whether to buy or make a testing tool for your project.
If you want to buy, the cost of the tool is $60,000, and the proceeding the procurement, additional cost
of integration of the tool in your company is $ 1,000. If you build it yourself, the tool will be developed
by eight engineers working for two months. The salary of each software engineer is $4,000 per month. If
you build it yourself, the other related various costs will be $2,000.
Which option will you prefer?
A-) Buying the testing tool
B-) Building the testing tool
C-) Neither build nor buy testing tool
D-) Need more information on costs to take a further decision
Visit:
http://masterofproject.com/courses/realistic
-pmp-exam-math-rev-readiness-check-for-
real-exam for full PMP Exams
9. Sample PMP Exam Questions
Q4-) You are a project manager trying to decide whether to buy or make a testing tool for your project.
If you want to buy, the cost of the tool is $60,000, and the proceeding the procurement, additional cost
of integration of the tool in your company is $ 1,000. If you build it yourself, the tool will be developed
by eight engineers working for two months. The salary of each software engineer is $4,000 per month. If
you build it yourself, the other related various costs will be $2,000.
Which option will you prefer?
A-) Buying the testing tool
B-) Building the testing tool
C-) Neither build nor buy testing tool
D-) Need more information on costs to take a further decision
10. Sample PMP Exam Questions
Budget constraints may influence make -or-buy decisions. If a buy decision is to be made,
then a further decision of whether to purchase or lease is also made. A make -or- buy
analysis should consider all related costs -both direct costs as well as indirect costs.
For example, the buy side of the analysis includes both the actual out -of- pocket costs to
purchase the product, as well as the indirect costs of supporting the purchasing process
and purchased item.
Cost of buying the tool: $60,000 + $1000 = $61,000
Cost of building the tool: $4,000x8x2 + $2,000 = $66,000
So, buying is cheaper than building. Buying is preferable
Reference: PMBOK Guide Fifth Edition, Page 365, Knowledge Area: Procurement
Management
11. Sample PMP Exam Questions
Q5-) When referring to inputs for Develop Schedule process,
responsibility (i.e., who will perform the work), activity type (i.e.,
summary or detailed), and WBS lassification are belonging to:
A-) Risks
B-) Account identifier
C-) Activity attributes
D-) Activity estimations
Visit:
http://masterofproject.com/courses/realistic
-pmp-exam-math-rev-readiness-check-for-
real-exam for full PMP Exams
12. Sample PMP Exam Questions
Q5-) When referring to inputs for Develop Schedule process,
responsibility (i.e., who will perform the work), activity type (i.e.,
summary or detailed), and WBS lassification are belonging to:
A-) Risks
B-) Account identifier
C-) Activity attributes
D-) Activity estimations
Activity attributes can be used to identify the person responsible for executing the work, geographic area, or place
where the work has to be performed, and activity type such as level of effort (LOE), discrete effort, and apportioned
effort (AE). Activity attributes are used for schedule
development and for selecting, ordering, and sorting the planned schedule activities in various ways within
reports.
Reference: PMBOK Guide Fifth Edition, Page 153,Knowledge Area: Time Management