This document provides sample questions to help prepare for the PMP certification exam. It begins with introductory information about PMP certification and a disclaimer. The body consists of multiple sample questions covering topics like risk management strategies, storing project schedules, and processes involved in project planning. Each question is followed by an explanation of the correct answer. The questions aim to mirror the format and difficulty of actual PMP exam questions.
Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
Full Exams at: http://masterofproject.com/courses/realistic-pmp-exam-math-rev-readiness-check-for-real-exam
PMP® Exams & Math Lectures training from Master of Project Academy is designed to ensure that you clear the PMP exam in the first attempt. After you complete your PMP® Exam preparation, take these exams. If you can score over 65% from these exams, you can be confident to schedule your PMP® Exam.
Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
Full Exams at: http://masterofproject.com/courses/realistic-pmp-exam-math-rev-readiness-check-for-real-exam
PMP® Exams & Math Lectures training from Master of Project Academy is designed to ensure that you clear the PMP exam in the first attempt. After you complete your PMP® Exam preparation, take these exams. If you can score over 65% from these exams, you can be confident to schedule your PMP® Exam.
#PMPChat: Your PMP Exam Prep Questions Answered in 140 Characters or Less!OSP International LLC
Cornelius Fichtner is hosting an open PMP Exam prep chat on February 13th at 9am to 11am PST.
In this open Twitter chat, Cornelius answers your questions about your PMP exam preparation.
http://bit.ly/pmpchat
Project Management Professional (PMP) is an internationally recognized professional designation offered by the PMI. There are currently 773,840 active PMP certified individuals and 286 chartered chapters across 210 countries and territories worldwide. The exam is based on the PMI Project Management Body of Knowledge (PMBOK), and the prerequisites are:
Secondary degree (high school diploma, associate’s degree or the global equivalent)
7,500 hours leading and directing projects
35 hours of project management education
OR
Four-year degree
4,500 hours leading and directing projects
35 hours of project management education
A candidate who passes the exam and meets the professional requirements is awarded the PMP certification.
We are starting a series of questions and answers targeting PMP examination for PMP aspirants. Check out below video for first series of 25 questions with answers and explanation about answer.
Dear students get fully solved SMU MBA Fall 2014 assignments
Send your semester & Specialization name to our mail id :
“ help.mbaassignments@gmail.com ”
or
Call us at : 08263069601
Dear students get fully solved SMU MBA assignments
Send your semester & Specialization name to our mail id :
“ help.mbaassignments@gmail.com ”
or
Call us at : 08263069601
Dear students get fully solved assignments
Send your semester & Specialization name to our mail id :
“ help.mbaassignments@gmail.com ”
or
Call us at : 08263069601
Here is our free CAPM exam sample question from the PM Exam Simulator.
*Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.
Here is our free PMP exam sample question from the PM Exam Simulator.
*Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.
1. PMP® Sample
Questions
PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in
the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or
content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the
PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a
replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such
guarantees or warranties are implied or expressed by OSP International LLC.
2. This presentation will showcase free
sample PMP® questions that will help
and guide you in studying for your
PMP® exam
Find more free sample questions when you
visit www.free-pm-exam-questions.com
and free.pm-exam-simulator.com
3. Sample PMP® Exam Question
In a project, several risk response strategies are used to effectively
manage project risks. The strategy or mix of strategies should be used
when planning for risk responses. Which of the following statements
best describes an 'accept' strategy for negative risks or threats?
a. Adopting less complex processes is an accept strategy.
b. Use of insurance is part of an accept strategy.
c. Using contingency reserve is part of accept strategy.
d. Extending schedule is part of an accept strategy.
HINT: A risk acceptance strategy is adopted because it is
seldom possible to eliminate all threats from a project. One of
the risk acceptance strategies is performed in the early stages of
planning. Find the option which is performed during planning.
4. Answer and Explanation
The correct answer is C
The most common risk acceptance strategy
in a project is to establish contingency
reserves.
5. Sample PMP® Exam Question
You developed alternative schedules based on
the best-case and worst-case scenarios in your
project. You want to keep these alternative
schedules stored in your project, in case of
changes in project resources.
Where would you store alternative schedules?
a. Schedule Baseline
b. Schedule Data
c. Project documents
d. Project scope statement
HINT: Alternative schedules are output of develop
schedule process. Look for the outputs of develop
schedule process to see where these schedules are
stored.
6. Answer and Explanation
The correct answer is B
Schedule data contains alternative
schedules such as best-case or worst-case
scenario. This is an output of develop
schedule process.
7. Sample PMP® Exam Question
Tim is working on an electronic manufacturing
project. In his project he wants to establish a
warranty for some of the precision parts he is
buying.
What risk response strategy is he using?
a. Mitigate
b. Avoid
c. Accept
d. Transfer
HINT: Tim is shifting the negative impact of the risk.
8. Answer and Explanation
The correct answer is D
Risk transfer requires shifting some or all of
the negative impact of a threat, along with
the ownership of the response. Taking out
insurance or a warranty transfers the risk
from the owner to the other party.
9. Sample PMP® Exam Question
What is risk tolerance?
a. Risks created by tolerating customer behavior.
b. Willingness to accept varying degrees of risk.
c. Risks created by zero tolerance.
d. Being tolerant if stakeholders are willing to
accept risks.
HINT: Look for the “least strange” answer.
10. Answer and Explanation
The correct answer is B
Do you feel that A, C and D are odd?
Correct, they are and they were included
intentionally. Sometimes you can expect to
find some “funny” answer choices.
Risk tolerance is the stakeholders'
willingness to accept varying degrees of
risk. Choice B is the only correct answer to
this question.
11. Sample PMP® Exam Question
You are managing a software development project. You want to create the
basis that will be used later on for estimating, scheduling, executing,
monitoring, and controlling the project work.
Which process performs this activity?
a. Create WBS
b. Define Scope
c. Define Activities
d. Create Project Management Plan
HINT: Estimating is performed when the activities
are defined and the schedule is prepared.
12. Answer and Explanation
The correct answer is C
Activities form a basis for estimating,
scheduling, executing, and monitoring and
controlling the project work. This is
performed in the Define Activities process.
13. Sample PMP® Exam Question
You are considering using WBS templates to
create your project's WBS.
Where would you most likely find these
templates?
a. PMI's Practice Standard for WBS
b. Microsoft Project Web Site
c. Organizational Process Assets
d. All of the above
HINT: Get your mind out of the PMBOK Guide and
think freely for this question.
14. Answer and Explanation
The correct answer is D
This question isn't asking about "inputs" to
the Create WBS process. The question is
simply asking: Where could you find
templates to help you build a WBS? All of
the answer choices are possible sources for
WBS templates.