PMP®           Sample
                 Questions


PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate
in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy
or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for
the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and
not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No
such guarantees or warranties are implied or expressed by OSP International LLC.
This presentation will showcase free
   sample PMP® questions that will help
    and guide you in studying for your
               PMP® exam
Find more free sample questions when you
visit www.free-pm-exam-questions.com and
        free.pm-exam-simulator.com
Sample PMP® Exam Question
Sensitivity Analysis has strong similarities to which of the following?

    a.   Probability Distributions
    b.   Risk Identification
    c.   Design of Experiments
    d.   Statistical Sampling



HINT: Sensitivity Analysis is a risk
      analysis technique not a risk
      identification technique.
Answer and Explanation
           The correct answer is C

           Don't get carried away by choice B. Sensitivity Analysis
           is a risk analysis technique not a risk identification
           technique. It is not a sampling technique or a
           distribution. In Design of Experiments one studies the
           effect of some process or intervention (the treatment)
           on some objects (the experimental units). In Sensitivity
           Analysis one looks at the effect of varying the inputs of
           a mathematical model on the output of the model itself.
           In both disciplines one strives to obtain information
           from the system with a minimum of physical or
           numerical experiments.
Sample PMP® Exam Question
You are performing the Plan Risk Responses process for your
manufacturing project when encounter a critical risk that may have a
high impact on the project completion. All of the following are valid
responses to this new risk except?

    a.   Allocating Contingency Reserves
    b.   Developing Fallback Options
    c.   Conducting Bidder Conferences
    d.   Reviewing risks driven by strategies

HINT: A Fallback Plan is used when a
      primary response plan proves
      to be inadequate.
Answer and Explanation
           The correct answer is C

           Conducting Bidder Conferences is not a strategy
           used in Risk Management. All other answer
           choices are valid risk responses.
Sample PMP® Exam Question
Cultural resistance is the root cause of quality issues according to
whom?

    a.   Deming
    b.   Malcolm Baldridge
    c.   Juran
    d.   Shelby

HINT: Juran is credited for adding
      human dimensions to quality
      management.
Answer and Explanation
           The correct answer is C

           Juran says the cultural resistance or resistance to
           change is the primary reason for quality
           problems.
Sample PMP® Exam Question
You are working on a web development project. You looked on the
internet for some off-the-shelf software to support the project. Your
internet search may lead to better products but which of the following
problems are associated with those products?

    a.   Off-the-shelf-products always charge variable rates.
    b.   Often the software does not work.
    c.   It is difficult to get support after installation.
    d.   Internet search cannot be used for highly complex
         procurements.


HINT: Internet search may be good for procuring small products.
Answer and Explanation
           The correct answer is D

           Highly complex, and high-risk procurement efforts
           that must be closely monitored cannot be
           obtained by internet search.
Sample PMP® Exam Question
Which of the following documents is in a text-oriented format
compared to other documents?

    a.   Organizational Breakdown Structure
    b.   Responsibility Assignment Matrix
    c.   Resource Breakdown Structure
    d.   Role-Responsibility-Authority Forms

HINT: Look for the keyword 'forms'.
Answer and Explanation
           The correct answer is D

           Role-Responsibility-Authority Forms are text-
           oriented forms used as a tool to in the Develop
           Human Resource Plan.
Sample PMP® Exam Question
On your project you handle known risks by performing the Plan Risk
Responses process. Which of the following would you use when you
encounter unknown risks?

    a.   Risk Reserves
    b.   Risk Mitigation
    c.   Risk Transfer
    d.   Risk Acceptance

HINT: Unknown risks cannot be
      managed proactively.
Answer and Explanation
           The correct answer is A

           Unknown risks are handled by applying Risk
           Reserves in the project.

PMP Sample Questions Set 2

  • 1.
    PMP® Sample Questions PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.
  • 2.
    This presentation willshowcase free sample PMP® questions that will help and guide you in studying for your PMP® exam Find more free sample questions when you visit www.free-pm-exam-questions.com and free.pm-exam-simulator.com
  • 3.
    Sample PMP® ExamQuestion Sensitivity Analysis has strong similarities to which of the following? a. Probability Distributions b. Risk Identification c. Design of Experiments d. Statistical Sampling HINT: Sensitivity Analysis is a risk analysis technique not a risk identification technique.
  • 4.
    Answer and Explanation The correct answer is C Don't get carried away by choice B. Sensitivity Analysis is a risk analysis technique not a risk identification technique. It is not a sampling technique or a distribution. In Design of Experiments one studies the effect of some process or intervention (the treatment) on some objects (the experimental units). In Sensitivity Analysis one looks at the effect of varying the inputs of a mathematical model on the output of the model itself. In both disciplines one strives to obtain information from the system with a minimum of physical or numerical experiments.
  • 5.
    Sample PMP® ExamQuestion You are performing the Plan Risk Responses process for your manufacturing project when encounter a critical risk that may have a high impact on the project completion. All of the following are valid responses to this new risk except? a. Allocating Contingency Reserves b. Developing Fallback Options c. Conducting Bidder Conferences d. Reviewing risks driven by strategies HINT: A Fallback Plan is used when a primary response plan proves to be inadequate.
  • 6.
    Answer and Explanation The correct answer is C Conducting Bidder Conferences is not a strategy used in Risk Management. All other answer choices are valid risk responses.
  • 7.
    Sample PMP® ExamQuestion Cultural resistance is the root cause of quality issues according to whom? a. Deming b. Malcolm Baldridge c. Juran d. Shelby HINT: Juran is credited for adding human dimensions to quality management.
  • 8.
    Answer and Explanation The correct answer is C Juran says the cultural resistance or resistance to change is the primary reason for quality problems.
  • 9.
    Sample PMP® ExamQuestion You are working on a web development project. You looked on the internet for some off-the-shelf software to support the project. Your internet search may lead to better products but which of the following problems are associated with those products? a. Off-the-shelf-products always charge variable rates. b. Often the software does not work. c. It is difficult to get support after installation. d. Internet search cannot be used for highly complex procurements. HINT: Internet search may be good for procuring small products.
  • 10.
    Answer and Explanation The correct answer is D Highly complex, and high-risk procurement efforts that must be closely monitored cannot be obtained by internet search.
  • 11.
    Sample PMP® ExamQuestion Which of the following documents is in a text-oriented format compared to other documents? a. Organizational Breakdown Structure b. Responsibility Assignment Matrix c. Resource Breakdown Structure d. Role-Responsibility-Authority Forms HINT: Look for the keyword 'forms'.
  • 12.
    Answer and Explanation The correct answer is D Role-Responsibility-Authority Forms are text- oriented forms used as a tool to in the Develop Human Resource Plan.
  • 13.
    Sample PMP® ExamQuestion On your project you handle known risks by performing the Plan Risk Responses process. Which of the following would you use when you encounter unknown risks? a. Risk Reserves b. Risk Mitigation c. Risk Transfer d. Risk Acceptance HINT: Unknown risks cannot be managed proactively.
  • 14.
    Answer and Explanation The correct answer is A Unknown risks are handled by applying Risk Reserves in the project.