SlideShare a Scribd company logo
1 of 47
Download to read offline
Project Scope Management
Dr. Huy Nguyen
Project Management Framework
2
Process Groups & Knowledge Areas Mapping
Knowledge
Areas
Process Groups
Initiating Planning Executing Monitoring & Control Closing
Integration
Develop Project
Charter
Develop Project Management Plan
Direct and Manage Project Work
Manage Project Knowledge
Monitor and Control Project Work
Perform Integrated Change Control
Close Project or Phase
Scope
Plan Scope Management
Collect Requirements
Define Scope
Create WBS
Validate Scope
Control Scope
Schedule
Plan Schedule Management
Define Activities
Sequence Activities
Estimate Activity Durations
Develop Schedule
Control Schedule
Cost
Plan Cost Management
Estimate Costs
Determine Budget
Control Costs
Quality Plan Quality Management Manage Quality Control Quality
Resource
Plan Resource Management
Estimate Activity Resources
Acquire Resources
Develop Team
Manage Team
Control Resources
Communications Plan Communications Management Manage Communications Monitor Communications
Risk
Plan Risk Management
Identify Risks
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Plan Risk Responses
Implement Risk Responses Monitor Risks
Procurement Plan Procurement Management Conduct Procurements Control Procurements
Stakeholder Identify Stakeholders Plan Stakeholder Engagement Manage Stakeholder Engagement Monitor Stakeholder Engagement
3
Project Scope Management
Knowledge
Area
Process Groups
Initiating Planning Executing
Monitoring &
Controlling
Closing
Scope
• Plan Scope Management
• Collect Requirements
• Define Scope
• Create WBS
• Validate Scope
• Control Scope
Enter phase/
Start project
Exit phase/
End project
Initiating
Processes
Closing
Processes
Planning
Processes
Executing
Processes
Monitoring &
Controlling Processes
4
Project Scope Management
• Processes to ensure that the project includes all-and-only the work required to
complete the project successfully;
• Scope can refer to Product Scope & Project Scope;
• Considerations for agile or adaptive environments:
• Don’t assume that requirements were determined before project began (not part of
the project).
• Attitude to say no to unnecessary scope. It should go to project approval process.
5
Predictive Adaptive or Agile
Deliverables are defined at the beginning of the
project. Scope baseline is the approved version of the
project scope statement, WBS, and WBS dictionary.
Deliverables are developed over multiple iterations where a
detailed scope is defined and approved for each iteration when
it begins. The backlogs are used to reflect the current needs.
Changes to the scope are progressively managed by
using the integrated change control process.
Changes go along with the repeated processes of Collect
requirements, Define scope and Create WBS for each iteration.
Validate scope occurs with each deliverable or phase
review and Control scope, Control quality are ongoing
processes.
Validate scope, Control scope and Control quality are repeated
for each iteration.
Project Scope Management
• New trends and emerging practices in align scope management and business
analysis:
– Determine problems and identify business needs;
– Identify and recommend viable solutions for meeting those needs;
– Elicit, document, and manage stakeholder requirements in order to meet
business and project objectives;
– Facilitate the successful implementation of the product, service, or end
result of the program or project.
• Tailoring considerations in the processes of Project Scope Management:
– Knowledge and requirements management;
– Validation and control;
– Development and control;
– Stability of requirements;
– Governance.
6
1 - Plan Scope Management
• Process of creating a scope management plan that documents how the
project scope will be defined, validated, and controlled.
Inputs
1.Project charter
2.Project management plan
• Quality management plan
• Project life cycle description
• Development approach
3.Enterprise environmental factors
4.Organizational process assets
Tools & Techniques
1.Expert judgment
2.Data analysis
• Alternative analysis
3.Meetings
Outputs
1.Scope management plan
2.Requirements
management plan
7
1 - Plan Scope Management
8
Scope Management Plan (Outputs)
• A major input to develop project management plan;
• Describes how the scope will be defined, developed, monitored, controlled,
and validated;
• Includes processes to:
– Prepare a project scope statement;
– Enable the creation of the WBS from the detailed project scope statement;
– Establish how the scope baseline will be approved and maintained;
– Specify how formal acceptance of the completed project deliverables will
be obtained.
9
Requirements Management Plan (Outputs)
• Describes how project and product requirements will be analyzed,
documented and managed;
• Includes the components relating to:
– How requirements activities will be planned, tracked, and reported;
– Configuration management activities relating to how to initiate changes,
analyze impacts and which authorization levels required to approve
changes;
– Requirements prioritization process;
– How and which metrics will be used;
– Traceability structure by a matrix for requirement attributes.
10
2 - Collect Requirements
• Process of determining, documenting, and managing stakeholder needs
and requirements to meet project objectives.
Inputs
1. Project charter
2. Project management plan
• Scope management plan
• Requirements management plan
• Stakeholder management plan
3. Project documents
• Assumption log
• Lesson learned register
• Stakeholder register
4. Business documents
• Business case
5. Agreements
6. Enterprise environmental factors
7. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Data gathering
• Brainstorming, interviews, focus groups
• Benchmarking, questionnaires, surveys
3. Data analysis
• Document analysis
4. Decision making
• Voting and multicriteria decision analysis
5. Data representation
• Affinity diagrams, mind mapping
6. Interpersonal and team skills
• Nominal group technique
• Observations/conversation
• Facilitation
7. Context diagrams
8. Prototypes
Outputs
1. Requirements
documentation
2. Requirements
traceability matrix
11
2 - Collect Requirements
12
Requirements
• Requirements:
– Include conditions or capabilities that are to be met by the project or
present in the product, service, or result to satisfy an agreement or other
formally imposed specification;
– Discover, decompose, quantify and document needs and expectations of
the sponsor, customer, and other stakeholders;
– Need to be elicited, analyzed, and recorded in the scope baseline and to
be measured once project execution begins;
– Become the foundation of the WBS, cost, schedule, quality, and
procurement planning.
• Classification of requirements:
– Business;
– Stakeholder;
– Solution: Functional and nonfunctional;
– Transition and readiness;
– Project;
– Quality.
13
Collect Requirements (Tools & Techniques)
• Data gathering:
– Brainstorming: Generate and collect multiple ideas;
– Interviews: Directly talk with stakeholders;
– Focus groups: Interactive discussion with qualified stakeholders & subject
matter experts;
– Questionnaires and surveys: Wide number of respondents;
– Benchmarking: Comparison between planned and comparable practices
to identify best practices.
• Document analysis: Analyzing existing documentation and identifying
information relevant to the requirements.
• Data representation:
– Idea / mind mapping: Consolidate the brainstormed ideas into a single
map to generate new ideas;
– Affinity diagram: Classify ideas into groups.
14
Collect Requirements (Tools & Techniques) (cont.)
• Affinity diagram:
– Requirement classified into groups by similarities;
– Easier to see additional scope (risk) that have not been identified.
15
Collect Requirements (Tools & Techniques) (cont.)
• Interpersonal and team skills:
– Nominal group technique: Enhance brainstorming with voting and
ranking;
– Observation (or job shadowing) and conversation: Viewing individual in
their environment and how they perform their jobs or tasks and carry out
processes;
– Facilitated workshops: Focus cross functional requirements and
reconciling stakeholders differences:
• JAD (Joint application design);
• QFD (Quality function development);
• User stories.
16
Collect Requirements (Tools & Techniques) (cont.)
• Decision making:
– Voting:
• Unanimity: Decision is reached through a single course of action by Delphi
technique;
• Majority: Decision is reached by more than 50 % of the members of the
group;
• Plurality: Decision is reached by the largest block in a group, even if a
majority is not achieved;
– Autocratic decision making (or dictatorship): One individual makes the
decision for the group
– Multicriteria decision analysis: Provide a systematic analytical approach
to evaluate and rank ideas by decision matrix.
17
Collect Requirements (Tools & Techniques) (cont.)
• Prototypes: Early feedback by providing a working model of the expected product.
• Context diagrams: Example of a scope model.
18
Balance Stakeholder’s Requirements
• There is a need to balance stakeholder’s requirements.
• Some issues are so complex they cannot be resolved by project manager
alone.
• Facilitate the resolution of competing requirements by considering:
– Business case;
– Project charter;
– Project scope statement;
– Project constraints.
• What you can do:
– Conflict resolution, team building, meeting, problem solving skills,
escalation, approval from stakeholders.
• Stakeholders request to do or add something that is not related to the reason
of project created should be rejected!
19
Requirements Documentation (Outputs)
• Output of the Collect Requirements process;
• Helps make sure the requirements clear and unambiguous;
• How will we know if the work we do will acceptability meet the requirements?
• Rule of thumb for requirements:
– Specific (Unambiguous);
– Measurable (How will we know we have finished?);
– Achievable (Can we do it?);
– Relevant (Is it the right thing to do?);
– Timed (When will we do it?).
20
Requirements Traceability Matrix (Outputs)
• A grid that links product requirements from their origin to the deliverables that
satisfy them;
• Helps ensure that each requirement adds business value by linking it to the
business and project objectives.
21
3 - Define Scope
• Process of developing a detailed description of the project and product with
major deliverables, risks, assumptions and constraints.
• Can be highly iterative.
Inputs
1.Project charter
2.Project management plan
• Scope management plan
3.Project documents
• Assumption log
• Requirements
documentation
• Risk register
4.Enterprise environmental
factors
5.Organizational process
assets
Tools & Techniques
1.Expert judgment
2.Data analysis
• Alternatives analysis
3.Decision making
• Multicriteria decision
analysis
4.Interpersonal and team skills
• Facilitation
5.Product analysis
Outputs
1.Project scope statement
2.Project document updates
• Assumption log
• Requirements
documentation
• Requirements traceability
matrix
• Stakeholder register
22
3 - Define Scope
23
Define Scope
• Concern with what are and are not included in the project and their
deliverables in detail.
• You should maintain a realistic schedule and budget that can achieve the
project’s scope:
– Iteration process should be done to maintain it;
– Looking for options to adjust the project.
24
Product Analysis (Tools & Techniques)
• Analyze the objectives and high level description of the product stated by the
customer / sponsor and turn them into tangible deliverables.
• Apply in each process and knowledge area in project lifecycle.
25
Project Scope Statement (Outputs)
• Primary result of the Define Scope process;
• Along with the WBS and WBS dictionary, comprise the scope baseline and is
part of project management plan.
• May include:
– Product scope description;
– Deliverables;
– Product acceptance criteria;
– What are not part of the project (out of scope or project exclusions);
• Assumption log:
– Constraints: Factors that affects the execution of a project or process;
– Assumptions: Things that assumed to be true (may not be true) without
proof or demonstration.
26
ComparisonbtwProjectCharter&ProjectScopeStatement
27
Project Charter Project Scope Statement
• Project purpose or justification
• Measurable project objectives and related
success criteria
• High-level requirements
• High-level project description, boundaries,
and key deliverables
• Overall project risks
• Summary milestone schedule
• Preapproved financial resources
• Key stakeholder list
• Project approval requirements
• Project exit criteria
• Assigned project manager, responsibility,
and authority level
• Name and authority of the sponsor
• Project scope description
• Acceptance criteria
• Project deliverables
• Project exclusions
4 - Create WBS
• Process of subdividing project deliverables and project work into smaller,
more manageable components.
Inputs
1.Project management plan
• Scope management plan
2.Project documents
• Project scope statement
• Requirements documentation
3.Enterprise environmental factors
4.Organizational process assets
Tools & Techniques
1.Expert judgment
2.Decomposition
Outputs
1.Scope baseline
2.Project document
updates
• Assumption log
• Requirements
documentation
• WBS does not show dependencies.
• Dividing work package into activities is part of the project schedule
management process (Define activities).
28
4 - Create WBS
29
Create WBS
• WBS is a hierarchical decomposition of the total scope of work to be carried
out by the project team to accomplish the project objectives and create the
required deliverables.
• Work package: Lowest level WBS component which can be scheduled, cost
estimated, monitored and controlled.
• Work refers to result of activity (products or deliverables), not to activity ifself.
• WBS structure can be organized by:
– Work packages;
– Phases;
– Major deliverables;
– Subprojects e.g. contracted work.
• Control account: Management control point for performance measurement
(one or more work packages).
• WBS dictionary provides more detailed components, e.g. description of work,
responsible organization, acceptance criteria.
• Agreed scope baseline includes project scope statement, WBS, WBS
dictionary.
30
Decomposition (Tools & Techniques)
• Decomposition is dividing deliverables or components into their most
fundamental elements, where they represent verifiable products, services, or
results.
• Verification of the decomposition correctness is determining the lower-level
WBS components are necessary and sufficient for completion of the
corresponding higher-level components.
• Different deliverables can have different levels of decomposition.
• More decomposition can:
– Enhance ability to plan, manage, and control the work;
– Lead to non-productive management effort, and inefficient use of
resources;
– Decrease efficiency in performing the work, and increase difficulty in
aggregating data over different levels of the WBS.
31
Decomposition (Tools & Techniques)
• Decomposition activities:
– Identifying and analyzing the deliverables and related work;
– Structuring and organizing the WBS;
– Decomposing the upper WBS levels into lower-level detailed
components;
– Developing and assigning identification codes to the WBS components;
– Verifying that the degree of decomposition of the deliverables is
appropriate.
32
Sample WBS
33
WBS
• 100% rule: WBS includes 100% of the work defined by project scope and
capture ALL deliverables (external, internal, interim) in term of work to be
completed including project management.
• WBS creation methods:
– Top down;
– Bottom up;
– Organization specific guidelines;
– WBS standard;
– WBS templates.
• Don’t mind with WBS view:
– Outline view;
– Tabular view;
– Tree structure view (vertical, horizontal, centralized).
34
Sample WBS decomposed by work packages
35
Sample WBS decomposed by phases
36
Sample WBS decomposed by deliverables
37
Scope Baseline (Outputs)
• Components of Scope baseline:
– Project scope statement;
– WBS;
– Work package;
– Planning package;
– WBS dictionary.
38
WBS Dictionary Sample
• Includes (but not limited to):
– Code of account identifier;
– Description of work;
– Responsible organization;
– List of schedule milestone;
– Associated schedule activities;
– Resource required;
– Cost estimates;
– Quality requirements;
– Acceptance criteria;
– Technical references;
– Contract Information.
39
WBS Dictionary Sample (cont.)
40
5 - Validate Scope
• Process of formalizing acceptance of the completed project deliverables.
Inputs
1. Project management plan
• Scope management plan
• Requirements management
plan
2. Project documents:
• Lesson learned register
• Quality reports
• Requirements documentation
• Requirement traceability
matrix
3. Verified deliverables
4. Work performance data
Tools & Techniques
1. Inspection
2. Decision making
• Voting
Outputs
1. Accepted deliverables
2. Work performance
information
3. Change requests
4. Project documents updates
• Lessons learned register
• Requirements
documentation
• Requirements traceability
matrix
41
5 - Validate Scope
42
Validate Scope
• Different with quality control which concerned with correctness of deliverables;
• Can be performed after or parallel with quality control;
• NOT making sure you have the right scope during project planning;
• But, to gain formal acceptance of deliverables during monitoring and control;
• Inspection = reviews, product reviews, audits, walkthroughs:
– Measuring, examining, verifying to determine if work and deliverables
meet requirement & product acceptance criteria.
43
6 - Control Scope
• Process of monitoring the status of the project and product scope and
managing changes to the scope baseline:
Inputs
1. Project management plan
• Scope management plan
• Requirements management
• plan
• Change management plan
• Configuration management
plan
• Scope baseline
• Performance measurement
baseline
2.Project documents:
• Lessons learned register
• Requirements documentation
• Requirement traceability matrix
3. Work performance data
4. Organizational process assets
Tools & Techniques
1. Data analysis
• Variance analysis
• Trend analysis
Outputs
1. Work performance information
2. Change requests
3. Project management plan
updates
• Scope management plan
• Scope baseline
• Schedule baseline
• Cost baseline
• Performance measurement
baseline
4. Project documents updates
• Lessons learned register
• Requirements documentation
• Requirements traceability matrix
44
6 - Control Scope
45
Control Scope
• Relation with Perform Integrated Change Control Process:
Need for scope
change during
Control Scope
Potential impact to scope
found in Control Cost,
Control Schedule, etc.
Perform
Integrated Change Control
* Accept or reject the change? *
Return to Control
Scope to process
the approved
change
46
Thank You
Next topic:
Project Quality Management
47

More Related Content

What's hot

Efficient Teams Do Not Happen. They are Designed. It's called DesignOps
Efficient Teams Do Not Happen. They are Designed. It's called DesignOpsEfficient Teams Do Not Happen. They are Designed. It's called DesignOps
Efficient Teams Do Not Happen. They are Designed. It's called DesignOpsPatrizia Bertini
 
Valuing Lost Profits for Litigation Purposes (Series: Valuation 2020)
Valuing Lost Profits for Litigation Purposes (Series: Valuation 2020)   Valuing Lost Profits for Litigation Purposes (Series: Valuation 2020)
Valuing Lost Profits for Litigation Purposes (Series: Valuation 2020) Financial Poise
 
The Project Management Process - Week 1
The Project Management Process -  Week 1The Project Management Process -  Week 1
The Project Management Process - Week 1Craig Brown
 
An Introduction to Project Management
An Introduction to Project Management An Introduction to Project Management
An Introduction to Project Management Krishna Kant
 
Project Manager And Business Analyst Collaboration
Project Manager And Business Analyst CollaborationProject Manager And Business Analyst Collaboration
Project Manager And Business Analyst CollaborationWhy-What-How Consulting, LLC
 
Measuring & Evaluating Your DesignOps Practice
Measuring & Evaluating Your DesignOps PracticeMeasuring & Evaluating Your DesignOps Practice
Measuring & Evaluating Your DesignOps PracticeDave Malouf
 
Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1Mena M. Eissa
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasMazen Zbib
 
Project Manangement Introduction
Project Manangement IntroductionProject Manangement Introduction
Project Manangement Introductionasim78
 
Enterprise risk & risk management - I
Enterprise risk & risk management - IEnterprise risk & risk management - I
Enterprise risk & risk management - IDr. Shiv S Tripathi
 

What's hot (20)

Efficient Teams Do Not Happen. They are Designed. It's called DesignOps
Efficient Teams Do Not Happen. They are Designed. It's called DesignOpsEfficient Teams Do Not Happen. They are Designed. It's called DesignOps
Efficient Teams Do Not Happen. They are Designed. It's called DesignOps
 
Valuing Lost Profits for Litigation Purposes (Series: Valuation 2020)
Valuing Lost Profits for Litigation Purposes (Series: Valuation 2020)   Valuing Lost Profits for Litigation Purposes (Series: Valuation 2020)
Valuing Lost Profits for Litigation Purposes (Series: Valuation 2020)
 
Project Execution
Project ExecutionProject Execution
Project Execution
 
The Project Management Process - Week 1
The Project Management Process -  Week 1The Project Management Process -  Week 1
The Project Management Process - Week 1
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 
An Introduction to Project Management
An Introduction to Project Management An Introduction to Project Management
An Introduction to Project Management
 
Project Manager And Business Analyst Collaboration
Project Manager And Business Analyst CollaborationProject Manager And Business Analyst Collaboration
Project Manager And Business Analyst Collaboration
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Measuring & Evaluating Your DesignOps Practice
Measuring & Evaluating Your DesignOps PracticeMeasuring & Evaluating Your DesignOps Practice
Measuring & Evaluating Your DesignOps Practice
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Project cost management-slides
Project cost management-slidesProject cost management-slides
Project cost management-slides
 
Project portfolio management
Project portfolio managementProject portfolio management
Project portfolio management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Project governance
Project governanceProject governance
Project governance
 
Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areas
 
Project Manangement Introduction
Project Manangement IntroductionProject Manangement Introduction
Project Manangement Introduction
 
Risk management
Risk managementRisk management
Risk management
 
Enterprise risk & risk management - I
Enterprise risk & risk management - IEnterprise risk & risk management - I
Enterprise risk & risk management - I
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 

Similar to Topic 7 - Project Scope Management.pdf

Topic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfTopic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfHuyNguyen657394
 
Project Formulation and Management - Project Scope Management
Project Formulation and Management - Project Scope ManagementProject Formulation and Management - Project Scope Management
Project Formulation and Management - Project Scope ManagementHrishikesh Satpute
 
Online PMP Training Material for PMP Exam - Scope Management Knowledge Area
Online PMP Training Material for PMP Exam - Scope Management Knowledge AreaOnline PMP Training Material for PMP Exam - Scope Management Knowledge Area
Online PMP Training Material for PMP Exam - Scope Management Knowledge AreaGlobalSkillup
 
Projects2016_Franks_Top10ReasonsProjectsFail
Projects2016_Franks_Top10ReasonsProjectsFailProjects2016_Franks_Top10ReasonsProjectsFail
Projects2016_Franks_Top10ReasonsProjectsFailBarbara Franks
 
04 project integration management
04  project integration management04  project integration management
04 project integration managementAla Ibrahim
 
Session 04 - Project Planning
Session 04 - Project PlanningSession 04 - Project Planning
Session 04 - Project PlanningRakeshSinhaPMP
 
Project scope management and planning
Project scope management and planningProject scope management and planning
Project scope management and planningAbubeker mukemil
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagementDhamo daran
 
Topic 4 - Project Management Process.pdf
Topic 4 - Project Management Process.pdfTopic 4 - Project Management Process.pdf
Topic 4 - Project Management Process.pdfHuyNguyen657394
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Agus Suhanto
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project ManagementRasan Samarasinghe
 
PMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part OnePMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part OneHossam Maghrabi
 
Managing the Consulting Engagement
Managing the Consulting EngagementManaging the Consulting Engagement
Managing the Consulting EngagementSaumya Ganguly
 

Similar to Topic 7 - Project Scope Management.pdf (20)

Topic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfTopic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdf
 
PMP-Scope Management area
PMP-Scope Management areaPMP-Scope Management area
PMP-Scope Management area
 
Project Formulation and Management - Project Scope Management
Project Formulation and Management - Project Scope ManagementProject Formulation and Management - Project Scope Management
Project Formulation and Management - Project Scope Management
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
 
Online PMP Training Material for PMP Exam - Scope Management Knowledge Area
Online PMP Training Material for PMP Exam - Scope Management Knowledge AreaOnline PMP Training Material for PMP Exam - Scope Management Knowledge Area
Online PMP Training Material for PMP Exam - Scope Management Knowledge Area
 
Projects2016_Franks_Top10ReasonsProjectsFail
Projects2016_Franks_Top10ReasonsProjectsFailProjects2016_Franks_Top10ReasonsProjectsFail
Projects2016_Franks_Top10ReasonsProjectsFail
 
04 project integration management
04  project integration management04  project integration management
04 project integration management
 
Session 04 - Project Planning
Session 04 - Project PlanningSession 04 - Project Planning
Session 04 - Project Planning
 
Project scope management and planning
Project scope management and planningProject scope management and planning
Project scope management and planning
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
 
Topic 4 - Project Management Process.pdf
Topic 4 - Project Management Process.pdfTopic 4 - Project Management Process.pdf
Topic 4 - Project Management Process.pdf
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6
 
Pmp scope chapter 5
Pmp scope chapter 5Pmp scope chapter 5
Pmp scope chapter 5
 
PMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope managementPMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope management
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
Session 22 4th edition PMP
Session 22 4th edition PMPSession 22 4th edition PMP
Session 22 4th edition PMP
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
PMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part OnePMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part One
 
Managing the Consulting Engagement
Managing the Consulting EngagementManaging the Consulting Engagement
Managing the Consulting Engagement
 

More from HuyNguyen657394

Topic 15 - Leadership in Project Management.pdf
Topic 15 - Leadership in Project Management.pdfTopic 15 - Leadership in Project Management.pdf
Topic 15 - Leadership in Project Management.pdfHuyNguyen657394
 
Topic 14 - Project Team Management.pdf
Topic 14 - Project Team Management.pdfTopic 14 - Project Team Management.pdf
Topic 14 - Project Team Management.pdfHuyNguyen657394
 
Tips - IT Project Management.pdf
Tips - IT Project Management.pdfTips - IT Project Management.pdf
Tips - IT Project Management.pdfHuyNguyen657394
 
Topic 13 - Project Resource Management.pdf
Topic 13 - Project Resource Management.pdfTopic 13 - Project Resource Management.pdf
Topic 13 - Project Resource Management.pdfHuyNguyen657394
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfHuyNguyen657394
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfHuyNguyen657394
 
Topic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfTopic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfHuyNguyen657394
 
Topic 9 - Project Stakeholder Management.pdf
Topic 9 - Project Stakeholder Management.pdfTopic 9 - Project Stakeholder Management.pdf
Topic 9 - Project Stakeholder Management.pdfHuyNguyen657394
 
Topic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdfTopic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdfHuyNguyen657394
 
Topic 5 - Project Planning.pdf
Topic 5 - Project Planning.pdfTopic 5 - Project Planning.pdf
Topic 5 - Project Planning.pdfHuyNguyen657394
 
Topic 3 - Project Selection & Portfolio Management.pdf
Topic 3 - Project Selection & Portfolio Management.pdfTopic 3 - Project Selection & Portfolio Management.pdf
Topic 3 - Project Selection & Portfolio Management.pdfHuyNguyen657394
 
Topic 2 - Project Life Cycle and Project Management Organization.pdf
Topic 2 - Project Life Cycle and Project Management Organization.pdfTopic 2 - Project Life Cycle and Project Management Organization.pdf
Topic 2 - Project Life Cycle and Project Management Organization.pdfHuyNguyen657394
 
Topic 1 - Introduction of Project Management.pdf
Topic 1 - Introduction of Project Management.pdfTopic 1 - Introduction of Project Management.pdf
Topic 1 - Introduction of Project Management.pdfHuyNguyen657394
 
Topic 0 - General Information.pdf
Topic 0 - General Information.pdfTopic 0 - General Information.pdf
Topic 0 - General Information.pdfHuyNguyen657394
 
Topic 0 - General Information New.pdf
Topic 0 - General Information New.pdfTopic 0 - General Information New.pdf
Topic 0 - General Information New.pdfHuyNguyen657394
 
Nhan thuc ve chuyen doi so.pdf
Nhan thuc ve chuyen doi so.pdfNhan thuc ve chuyen doi so.pdf
Nhan thuc ve chuyen doi so.pdfHuyNguyen657394
 

More from HuyNguyen657394 (16)

Topic 15 - Leadership in Project Management.pdf
Topic 15 - Leadership in Project Management.pdfTopic 15 - Leadership in Project Management.pdf
Topic 15 - Leadership in Project Management.pdf
 
Topic 14 - Project Team Management.pdf
Topic 14 - Project Team Management.pdfTopic 14 - Project Team Management.pdf
Topic 14 - Project Team Management.pdf
 
Tips - IT Project Management.pdf
Tips - IT Project Management.pdfTips - IT Project Management.pdf
Tips - IT Project Management.pdf
 
Topic 13 - Project Resource Management.pdf
Topic 13 - Project Resource Management.pdfTopic 13 - Project Resource Management.pdf
Topic 13 - Project Resource Management.pdf
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
 
Topic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfTopic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdf
 
Topic 9 - Project Stakeholder Management.pdf
Topic 9 - Project Stakeholder Management.pdfTopic 9 - Project Stakeholder Management.pdf
Topic 9 - Project Stakeholder Management.pdf
 
Topic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdfTopic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdf
 
Topic 5 - Project Planning.pdf
Topic 5 - Project Planning.pdfTopic 5 - Project Planning.pdf
Topic 5 - Project Planning.pdf
 
Topic 3 - Project Selection & Portfolio Management.pdf
Topic 3 - Project Selection & Portfolio Management.pdfTopic 3 - Project Selection & Portfolio Management.pdf
Topic 3 - Project Selection & Portfolio Management.pdf
 
Topic 2 - Project Life Cycle and Project Management Organization.pdf
Topic 2 - Project Life Cycle and Project Management Organization.pdfTopic 2 - Project Life Cycle and Project Management Organization.pdf
Topic 2 - Project Life Cycle and Project Management Organization.pdf
 
Topic 1 - Introduction of Project Management.pdf
Topic 1 - Introduction of Project Management.pdfTopic 1 - Introduction of Project Management.pdf
Topic 1 - Introduction of Project Management.pdf
 
Topic 0 - General Information.pdf
Topic 0 - General Information.pdfTopic 0 - General Information.pdf
Topic 0 - General Information.pdf
 
Topic 0 - General Information New.pdf
Topic 0 - General Information New.pdfTopic 0 - General Information New.pdf
Topic 0 - General Information New.pdf
 
Nhan thuc ve chuyen doi so.pdf
Nhan thuc ve chuyen doi so.pdfNhan thuc ve chuyen doi so.pdf
Nhan thuc ve chuyen doi so.pdf
 

Recently uploaded

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 

Recently uploaded (20)

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 

Topic 7 - Project Scope Management.pdf

  • 3. Process Groups & Knowledge Areas Mapping Knowledge Areas Process Groups Initiating Planning Executing Monitoring & Control Closing Integration Develop Project Charter Develop Project Management Plan Direct and Manage Project Work Manage Project Knowledge Monitor and Control Project Work Perform Integrated Change Control Close Project or Phase Scope Plan Scope Management Collect Requirements Define Scope Create WBS Validate Scope Control Scope Schedule Plan Schedule Management Define Activities Sequence Activities Estimate Activity Durations Develop Schedule Control Schedule Cost Plan Cost Management Estimate Costs Determine Budget Control Costs Quality Plan Quality Management Manage Quality Control Quality Resource Plan Resource Management Estimate Activity Resources Acquire Resources Develop Team Manage Team Control Resources Communications Plan Communications Management Manage Communications Monitor Communications Risk Plan Risk Management Identify Risks Perform Qualitative Risk Analysis Perform Quantitative Risk Analysis Plan Risk Responses Implement Risk Responses Monitor Risks Procurement Plan Procurement Management Conduct Procurements Control Procurements Stakeholder Identify Stakeholders Plan Stakeholder Engagement Manage Stakeholder Engagement Monitor Stakeholder Engagement 3
  • 4. Project Scope Management Knowledge Area Process Groups Initiating Planning Executing Monitoring & Controlling Closing Scope • Plan Scope Management • Collect Requirements • Define Scope • Create WBS • Validate Scope • Control Scope Enter phase/ Start project Exit phase/ End project Initiating Processes Closing Processes Planning Processes Executing Processes Monitoring & Controlling Processes 4
  • 5. Project Scope Management • Processes to ensure that the project includes all-and-only the work required to complete the project successfully; • Scope can refer to Product Scope & Project Scope; • Considerations for agile or adaptive environments: • Don’t assume that requirements were determined before project began (not part of the project). • Attitude to say no to unnecessary scope. It should go to project approval process. 5 Predictive Adaptive or Agile Deliverables are defined at the beginning of the project. Scope baseline is the approved version of the project scope statement, WBS, and WBS dictionary. Deliverables are developed over multiple iterations where a detailed scope is defined and approved for each iteration when it begins. The backlogs are used to reflect the current needs. Changes to the scope are progressively managed by using the integrated change control process. Changes go along with the repeated processes of Collect requirements, Define scope and Create WBS for each iteration. Validate scope occurs with each deliverable or phase review and Control scope, Control quality are ongoing processes. Validate scope, Control scope and Control quality are repeated for each iteration.
  • 6. Project Scope Management • New trends and emerging practices in align scope management and business analysis: – Determine problems and identify business needs; – Identify and recommend viable solutions for meeting those needs; – Elicit, document, and manage stakeholder requirements in order to meet business and project objectives; – Facilitate the successful implementation of the product, service, or end result of the program or project. • Tailoring considerations in the processes of Project Scope Management: – Knowledge and requirements management; – Validation and control; – Development and control; – Stability of requirements; – Governance. 6
  • 7. 1 - Plan Scope Management • Process of creating a scope management plan that documents how the project scope will be defined, validated, and controlled. Inputs 1.Project charter 2.Project management plan • Quality management plan • Project life cycle description • Development approach 3.Enterprise environmental factors 4.Organizational process assets Tools & Techniques 1.Expert judgment 2.Data analysis • Alternative analysis 3.Meetings Outputs 1.Scope management plan 2.Requirements management plan 7
  • 8. 1 - Plan Scope Management 8
  • 9. Scope Management Plan (Outputs) • A major input to develop project management plan; • Describes how the scope will be defined, developed, monitored, controlled, and validated; • Includes processes to: – Prepare a project scope statement; – Enable the creation of the WBS from the detailed project scope statement; – Establish how the scope baseline will be approved and maintained; – Specify how formal acceptance of the completed project deliverables will be obtained. 9
  • 10. Requirements Management Plan (Outputs) • Describes how project and product requirements will be analyzed, documented and managed; • Includes the components relating to: – How requirements activities will be planned, tracked, and reported; – Configuration management activities relating to how to initiate changes, analyze impacts and which authorization levels required to approve changes; – Requirements prioritization process; – How and which metrics will be used; – Traceability structure by a matrix for requirement attributes. 10
  • 11. 2 - Collect Requirements • Process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives. Inputs 1. Project charter 2. Project management plan • Scope management plan • Requirements management plan • Stakeholder management plan 3. Project documents • Assumption log • Lesson learned register • Stakeholder register 4. Business documents • Business case 5. Agreements 6. Enterprise environmental factors 7. Organizational process assets Tools & Techniques 1. Expert judgment 2. Data gathering • Brainstorming, interviews, focus groups • Benchmarking, questionnaires, surveys 3. Data analysis • Document analysis 4. Decision making • Voting and multicriteria decision analysis 5. Data representation • Affinity diagrams, mind mapping 6. Interpersonal and team skills • Nominal group technique • Observations/conversation • Facilitation 7. Context diagrams 8. Prototypes Outputs 1. Requirements documentation 2. Requirements traceability matrix 11
  • 12. 2 - Collect Requirements 12
  • 13. Requirements • Requirements: – Include conditions or capabilities that are to be met by the project or present in the product, service, or result to satisfy an agreement or other formally imposed specification; – Discover, decompose, quantify and document needs and expectations of the sponsor, customer, and other stakeholders; – Need to be elicited, analyzed, and recorded in the scope baseline and to be measured once project execution begins; – Become the foundation of the WBS, cost, schedule, quality, and procurement planning. • Classification of requirements: – Business; – Stakeholder; – Solution: Functional and nonfunctional; – Transition and readiness; – Project; – Quality. 13
  • 14. Collect Requirements (Tools & Techniques) • Data gathering: – Brainstorming: Generate and collect multiple ideas; – Interviews: Directly talk with stakeholders; – Focus groups: Interactive discussion with qualified stakeholders & subject matter experts; – Questionnaires and surveys: Wide number of respondents; – Benchmarking: Comparison between planned and comparable practices to identify best practices. • Document analysis: Analyzing existing documentation and identifying information relevant to the requirements. • Data representation: – Idea / mind mapping: Consolidate the brainstormed ideas into a single map to generate new ideas; – Affinity diagram: Classify ideas into groups. 14
  • 15. Collect Requirements (Tools & Techniques) (cont.) • Affinity diagram: – Requirement classified into groups by similarities; – Easier to see additional scope (risk) that have not been identified. 15
  • 16. Collect Requirements (Tools & Techniques) (cont.) • Interpersonal and team skills: – Nominal group technique: Enhance brainstorming with voting and ranking; – Observation (or job shadowing) and conversation: Viewing individual in their environment and how they perform their jobs or tasks and carry out processes; – Facilitated workshops: Focus cross functional requirements and reconciling stakeholders differences: • JAD (Joint application design); • QFD (Quality function development); • User stories. 16
  • 17. Collect Requirements (Tools & Techniques) (cont.) • Decision making: – Voting: • Unanimity: Decision is reached through a single course of action by Delphi technique; • Majority: Decision is reached by more than 50 % of the members of the group; • Plurality: Decision is reached by the largest block in a group, even if a majority is not achieved; – Autocratic decision making (or dictatorship): One individual makes the decision for the group – Multicriteria decision analysis: Provide a systematic analytical approach to evaluate and rank ideas by decision matrix. 17
  • 18. Collect Requirements (Tools & Techniques) (cont.) • Prototypes: Early feedback by providing a working model of the expected product. • Context diagrams: Example of a scope model. 18
  • 19. Balance Stakeholder’s Requirements • There is a need to balance stakeholder’s requirements. • Some issues are so complex they cannot be resolved by project manager alone. • Facilitate the resolution of competing requirements by considering: – Business case; – Project charter; – Project scope statement; – Project constraints. • What you can do: – Conflict resolution, team building, meeting, problem solving skills, escalation, approval from stakeholders. • Stakeholders request to do or add something that is not related to the reason of project created should be rejected! 19
  • 20. Requirements Documentation (Outputs) • Output of the Collect Requirements process; • Helps make sure the requirements clear and unambiguous; • How will we know if the work we do will acceptability meet the requirements? • Rule of thumb for requirements: – Specific (Unambiguous); – Measurable (How will we know we have finished?); – Achievable (Can we do it?); – Relevant (Is it the right thing to do?); – Timed (When will we do it?). 20
  • 21. Requirements Traceability Matrix (Outputs) • A grid that links product requirements from their origin to the deliverables that satisfy them; • Helps ensure that each requirement adds business value by linking it to the business and project objectives. 21
  • 22. 3 - Define Scope • Process of developing a detailed description of the project and product with major deliverables, risks, assumptions and constraints. • Can be highly iterative. Inputs 1.Project charter 2.Project management plan • Scope management plan 3.Project documents • Assumption log • Requirements documentation • Risk register 4.Enterprise environmental factors 5.Organizational process assets Tools & Techniques 1.Expert judgment 2.Data analysis • Alternatives analysis 3.Decision making • Multicriteria decision analysis 4.Interpersonal and team skills • Facilitation 5.Product analysis Outputs 1.Project scope statement 2.Project document updates • Assumption log • Requirements documentation • Requirements traceability matrix • Stakeholder register 22
  • 23. 3 - Define Scope 23
  • 24. Define Scope • Concern with what are and are not included in the project and their deliverables in detail. • You should maintain a realistic schedule and budget that can achieve the project’s scope: – Iteration process should be done to maintain it; – Looking for options to adjust the project. 24
  • 25. Product Analysis (Tools & Techniques) • Analyze the objectives and high level description of the product stated by the customer / sponsor and turn them into tangible deliverables. • Apply in each process and knowledge area in project lifecycle. 25
  • 26. Project Scope Statement (Outputs) • Primary result of the Define Scope process; • Along with the WBS and WBS dictionary, comprise the scope baseline and is part of project management plan. • May include: – Product scope description; – Deliverables; – Product acceptance criteria; – What are not part of the project (out of scope or project exclusions); • Assumption log: – Constraints: Factors that affects the execution of a project or process; – Assumptions: Things that assumed to be true (may not be true) without proof or demonstration. 26
  • 27. ComparisonbtwProjectCharter&ProjectScopeStatement 27 Project Charter Project Scope Statement • Project purpose or justification • Measurable project objectives and related success criteria • High-level requirements • High-level project description, boundaries, and key deliverables • Overall project risks • Summary milestone schedule • Preapproved financial resources • Key stakeholder list • Project approval requirements • Project exit criteria • Assigned project manager, responsibility, and authority level • Name and authority of the sponsor • Project scope description • Acceptance criteria • Project deliverables • Project exclusions
  • 28. 4 - Create WBS • Process of subdividing project deliverables and project work into smaller, more manageable components. Inputs 1.Project management plan • Scope management plan 2.Project documents • Project scope statement • Requirements documentation 3.Enterprise environmental factors 4.Organizational process assets Tools & Techniques 1.Expert judgment 2.Decomposition Outputs 1.Scope baseline 2.Project document updates • Assumption log • Requirements documentation • WBS does not show dependencies. • Dividing work package into activities is part of the project schedule management process (Define activities). 28
  • 29. 4 - Create WBS 29
  • 30. Create WBS • WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. • Work package: Lowest level WBS component which can be scheduled, cost estimated, monitored and controlled. • Work refers to result of activity (products or deliverables), not to activity ifself. • WBS structure can be organized by: – Work packages; – Phases; – Major deliverables; – Subprojects e.g. contracted work. • Control account: Management control point for performance measurement (one or more work packages). • WBS dictionary provides more detailed components, e.g. description of work, responsible organization, acceptance criteria. • Agreed scope baseline includes project scope statement, WBS, WBS dictionary. 30
  • 31. Decomposition (Tools & Techniques) • Decomposition is dividing deliverables or components into their most fundamental elements, where they represent verifiable products, services, or results. • Verification of the decomposition correctness is determining the lower-level WBS components are necessary and sufficient for completion of the corresponding higher-level components. • Different deliverables can have different levels of decomposition. • More decomposition can: – Enhance ability to plan, manage, and control the work; – Lead to non-productive management effort, and inefficient use of resources; – Decrease efficiency in performing the work, and increase difficulty in aggregating data over different levels of the WBS. 31
  • 32. Decomposition (Tools & Techniques) • Decomposition activities: – Identifying and analyzing the deliverables and related work; – Structuring and organizing the WBS; – Decomposing the upper WBS levels into lower-level detailed components; – Developing and assigning identification codes to the WBS components; – Verifying that the degree of decomposition of the deliverables is appropriate. 32
  • 34. WBS • 100% rule: WBS includes 100% of the work defined by project scope and capture ALL deliverables (external, internal, interim) in term of work to be completed including project management. • WBS creation methods: – Top down; – Bottom up; – Organization specific guidelines; – WBS standard; – WBS templates. • Don’t mind with WBS view: – Outline view; – Tabular view; – Tree structure view (vertical, horizontal, centralized). 34
  • 35. Sample WBS decomposed by work packages 35
  • 36. Sample WBS decomposed by phases 36
  • 37. Sample WBS decomposed by deliverables 37
  • 38. Scope Baseline (Outputs) • Components of Scope baseline: – Project scope statement; – WBS; – Work package; – Planning package; – WBS dictionary. 38
  • 39. WBS Dictionary Sample • Includes (but not limited to): – Code of account identifier; – Description of work; – Responsible organization; – List of schedule milestone; – Associated schedule activities; – Resource required; – Cost estimates; – Quality requirements; – Acceptance criteria; – Technical references; – Contract Information. 39
  • 40. WBS Dictionary Sample (cont.) 40
  • 41. 5 - Validate Scope • Process of formalizing acceptance of the completed project deliverables. Inputs 1. Project management plan • Scope management plan • Requirements management plan 2. Project documents: • Lesson learned register • Quality reports • Requirements documentation • Requirement traceability matrix 3. Verified deliverables 4. Work performance data Tools & Techniques 1. Inspection 2. Decision making • Voting Outputs 1. Accepted deliverables 2. Work performance information 3. Change requests 4. Project documents updates • Lessons learned register • Requirements documentation • Requirements traceability matrix 41
  • 42. 5 - Validate Scope 42
  • 43. Validate Scope • Different with quality control which concerned with correctness of deliverables; • Can be performed after or parallel with quality control; • NOT making sure you have the right scope during project planning; • But, to gain formal acceptance of deliverables during monitoring and control; • Inspection = reviews, product reviews, audits, walkthroughs: – Measuring, examining, verifying to determine if work and deliverables meet requirement & product acceptance criteria. 43
  • 44. 6 - Control Scope • Process of monitoring the status of the project and product scope and managing changes to the scope baseline: Inputs 1. Project management plan • Scope management plan • Requirements management • plan • Change management plan • Configuration management plan • Scope baseline • Performance measurement baseline 2.Project documents: • Lessons learned register • Requirements documentation • Requirement traceability matrix 3. Work performance data 4. Organizational process assets Tools & Techniques 1. Data analysis • Variance analysis • Trend analysis Outputs 1. Work performance information 2. Change requests 3. Project management plan updates • Scope management plan • Scope baseline • Schedule baseline • Cost baseline • Performance measurement baseline 4. Project documents updates • Lessons learned register • Requirements documentation • Requirements traceability matrix 44
  • 45. 6 - Control Scope 45
  • 46. Control Scope • Relation with Perform Integrated Change Control Process: Need for scope change during Control Scope Potential impact to scope found in Control Cost, Control Schedule, etc. Perform Integrated Change Control * Accept or reject the change? * Return to Control Scope to process the approved change 46
  • 47. Thank You Next topic: Project Quality Management 47