SlideShare a Scribd company logo
PCAPP Update
28 May 2014
Presented to:
Citizens’ Advisory Commission
Presented by:
Paul Dent
Operational Readiness Review
(ORR) Manager
What is an ORR?
Per ACWA Policy Statement 26, “ORRs will be
conducted to verify the readiness of the
ACWA Pilot Plants to safely begin operations
involving chemical agents, explosives, or
other highly hazardous materials.”
 The ORR process is used to validate
that PCAPP “plant, paper, and people”
collectively meet the required criteria
to allow a new operation to begin.
 PCAPP ORR process is led by the
system-contractor (SC) to support a
declaration of readiness.
 ACWA provides ORR oversight;
independent validation is used to
support the SC’s declaration of
readiness.
 Stakeholders are invited to observe
the ORR process.
2
Plant
PeoplePaper
Achieve Readiness – by Responsible Managers
Validate Readiness – by ORR Board
Declare Readiness – by Project Manager
Accept Readiness – by ACWA
5
ORR Major Milestones
NOT YET STARTED
IN PROGRESS
COMPLETE
* Major Milestones per
the PCAPP Baseline
IMS. PCAPP goal is to
declare readiness 60
days sooner
* Incremental Readiness
Assessments will
overlap – they are not
strictly sequential
1
7
9
8
4
3
2
6
14
15
16
Lab Dilute Agent Operations Mini-ORR OCT 2013 – 52 Criteria
Boiler Ignition Readiness Assessment DEC 2012 –
19 Criteria
Integrated Operations Demonstrations (IODs)
JUN 2015 – 11 Criteria
Agent Entry Readiness and Agent Containment and Confinement Controls SEP 2014 –
49 Criteria
ERB Provisional Operations SEP-2014 – 75 Criteria
APB Provisional Operations NOV 2014 – 32
Criteria
Contingency Training Readiness/Crew Certification JAN 2015
– 59 Criteria
Security/Surety (Soft-Lockdown) Readiness Review
FEB 2015 – 16 Criteria
BTA Provisional Operations NOV 2014 – 13
Criteria
Yard Provisional Operations JUL-2014 – 111 Criteria
Initial Agent Operations -
Readiness Declared JUL 2015 –
6 Criteria
ACWA Readiness
Endorsement SEP 2015
Training Facility Available for Practical Factors – Readiness Check JUN 2014 Forecast
Pre-Systemization Complete NOV 2013
Training Facility Available for TAT – Readiness Check JAN 2014
10
11
13
12
Environmental Readiness FEB 2015 –
14 Criteria
3
Scope of ORR for
Initial Agent Operations
 Criteria are defined in the Initial
Agent Operations ORR procedure
― Defines ORR criteria that reflect
project requirements
― Summarizes proposed Integrated
Operations Demonstrations (IODs)
― Include normal and off-normal
exercises to be performed
― Evaluation teams will observe
and critique each
demonstration
4
# Functional Area
# of
criteria
1 Acquisitions 10
2 Emergency Preparedness 14
3 Engineering 26
4 Environmental 14
5 Government Interfaces 13
6 Human Resources 3
7 Information Systems & Technology 5
8 Laboratory 21
9 Maintenance 11
10 Medical 21
11 Office and Administrative Services 6
12 Operations 49
13 Operations Support 22
14 Pilot Test Preparedness 3
15 Plant Support (Treaty) 8
16 Project and Plant Management 15
17 Quality Assurance/Quality Control 7
18 Safety 38
19 Security 13
20 Start-up/ Systemization 50
21 Surety 7
22 Training 15
23 Work Control 15
386
 Each of the four shifts will
perform IODs for readiness
validation.
 Upon successful completion of
IODs and closeout of required
findings, System Contractor will
declare readiness.
Criteria Review Resources Engaged
 Chris Midgett – Chair of Executive Board:
― Brings extensive experience in managing chem-demil work
― Liaison to ACWA and stakeholder executive functions
 Sierra Lobo, Inc. – Independent engineering resource
― Testing & evaluation expertise
― Clients include NASA & Department of Defense
 Blue Grass Subject Matter Experts (SMEs):
― Will use BGCAPP SMEs for independent review
― Bring an excellent understanding of standards & recent operating
experience
― ORR experience provides benefits to both projects
5
IAO ORR Status
ORR work will be paced by Systemization work.
Data as of 22-May-2014
ORR Documents
Total
Required
Issued for
Completion
Board
Reviewed
Board Accepted
Affidavits 386 135 55 34
CRADS 386 15 0 0
6
ORR Oversight
 Review ORR documents, attend Board meetings, and observe
demonstrations
 Provide immediate feedback on ORR issues, process, and
documentation
 Provide independent validation of 20% of ORR criteria in
accordance with their oversight procedure
 Coordinate stakeholder involvement in ORR process
 Lead a monthly meeting with representatives from the Blue
Grass project, Pueblo Chemical Depot, and stakeholders to
communicate ORR status, schedule, issues, and lessons learned
ACWA representatives also assess the System Contractor’s
readiness for initial agent operations:
7
Questions?
8

More Related Content

What's hot

ETI Wastewater Consulting Presentation
ETI Wastewater Consulting PresentationETI Wastewater Consulting Presentation
ETI Wastewater Consulting Presentation
BasilDonaldson
 
BlueScape California Industrial Storm Water Compliance Webinar 090816
BlueScape California Industrial Storm Water Compliance Webinar 090816BlueScape California Industrial Storm Water Compliance Webinar 090816
BlueScape California Industrial Storm Water Compliance Webinar 090816
BlueScape
 
Comissioning & qualification vol.5 (2nd eddition)
Comissioning & qualification vol.5 (2nd eddition)Comissioning & qualification vol.5 (2nd eddition)
Comissioning & qualification vol.5 (2nd eddition)
Ravindra Kushwaha
 
Krishnan basics of calibrations and pv non analytical instruments
Krishnan basics of calibrations and pv non analytical instrumentsKrishnan basics of calibrations and pv non analytical instruments
Krishnan basics of calibrations and pv non analytical instruments
eslamgouda
 
Internal quality audit operational procedure
Internal quality audit operational procedureInternal quality audit operational procedure
Internal quality audit operational procedure
Tuan Anh Nguyen
 
Devin Gavin Summer Intern
Devin Gavin Summer InternDevin Gavin Summer Intern
Devin Gavin Summer InternDevin Gavin
 
Lean Calibration Management
Lean Calibration ManagementLean Calibration Management
Lean Calibration Management
bossawines
 
Improvement in the turn around time
Improvement in the turn around timeImprovement in the turn around time
Improvement in the turn around time
Dr Jasbeer Singh
 
Interim Monitoring Visits
Interim Monitoring VisitsInterim Monitoring Visits
Interim Monitoring Visits
Dan Sfera
 
Impacts of U.S. EPA Region 6 Guidance on CMS Downtime and Data Calculations
Impacts of U.S. EPA Region 6 Guidance on CMS Downtime and Data CalculationsImpacts of U.S. EPA Region 6 Guidance on CMS Downtime and Data Calculations
Impacts of U.S. EPA Region 6 Guidance on CMS Downtime and Data Calculations
All4 Inc.
 
WCL Audit Services.ppt
WCL Audit Services.pptWCL Audit Services.ppt
WCL Audit Services.pptDave Haddock
 
OSHA PSM Regulations
OSHA PSM RegulationsOSHA PSM Regulations
OSHA PSM Regulations
sanjeev saraf
 
ISO 9000
ISO 9000ISO 9000
ISO 9000
Haroon Abbu
 
Gas Service Excellence Presentation 20 May 2010 Ms Final
Gas Service Excellence Presentation   20 May 2010   Ms   FinalGas Service Excellence Presentation   20 May 2010   Ms   Final
Gas Service Excellence Presentation 20 May 2010 Ms Final
mseaborn
 

What's hot (20)

Resume
ResumeResume
Resume
 
ETI Wastewater Consulting Presentation
ETI Wastewater Consulting PresentationETI Wastewater Consulting Presentation
ETI Wastewater Consulting Presentation
 
BlueScape California Industrial Storm Water Compliance Webinar 090816
BlueScape California Industrial Storm Water Compliance Webinar 090816BlueScape California Industrial Storm Water Compliance Webinar 090816
BlueScape California Industrial Storm Water Compliance Webinar 090816
 
QMS-Implementation
QMS-ImplementationQMS-Implementation
QMS-Implementation
 
Prdz_resume_march16
Prdz_resume_march16Prdz_resume_march16
Prdz_resume_march16
 
PCAPP Update 30 January 2013
PCAPP Update 30 January 2013PCAPP Update 30 January 2013
PCAPP Update 30 January 2013
 
Comissioning & qualification vol.5 (2nd eddition)
Comissioning & qualification vol.5 (2nd eddition)Comissioning & qualification vol.5 (2nd eddition)
Comissioning & qualification vol.5 (2nd eddition)
 
Krishnan basics of calibrations and pv non analytical instruments
Krishnan basics of calibrations and pv non analytical instrumentsKrishnan basics of calibrations and pv non analytical instruments
Krishnan basics of calibrations and pv non analytical instruments
 
Internal quality audit operational procedure
Internal quality audit operational procedureInternal quality audit operational procedure
Internal quality audit operational procedure
 
Devin Gavin Summer Intern
Devin Gavin Summer InternDevin Gavin Summer Intern
Devin Gavin Summer Intern
 
Value Stream Map
Value Stream MapValue Stream Map
Value Stream Map
 
Lean Calibration Management
Lean Calibration ManagementLean Calibration Management
Lean Calibration Management
 
Improvement in the turn around time
Improvement in the turn around timeImprovement in the turn around time
Improvement in the turn around time
 
Interim Monitoring Visits
Interim Monitoring VisitsInterim Monitoring Visits
Interim Monitoring Visits
 
Impacts of U.S. EPA Region 6 Guidance on CMS Downtime and Data Calculations
Impacts of U.S. EPA Region 6 Guidance on CMS Downtime and Data CalculationsImpacts of U.S. EPA Region 6 Guidance on CMS Downtime and Data Calculations
Impacts of U.S. EPA Region 6 Guidance on CMS Downtime and Data Calculations
 
WCL Audit Services.ppt
WCL Audit Services.pptWCL Audit Services.ppt
WCL Audit Services.ppt
 
OSHA PSM Regulations
OSHA PSM RegulationsOSHA PSM Regulations
OSHA PSM Regulations
 
ISO 9000
ISO 9000ISO 9000
ISO 9000
 
Gas Service Excellence Presentation 20 May 2010 Ms Final
Gas Service Excellence Presentation   20 May 2010   Ms   FinalGas Service Excellence Presentation   20 May 2010   Ms   Final
Gas Service Excellence Presentation 20 May 2010 Ms Final
 
Resume
ResumeResume
Resume
 

Viewers also liked

Preliminary task
Preliminary taskPreliminary task
Preliminary task
GeorgeKeenooKBA
 
Economic Development Working Group 10 September 2013
Economic Development Working Group 10 September 2013Economic Development Working Group 10 September 2013
Economic Development Working Group 10 September 2013
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Project Win Bharat
Project  Win BharatProject  Win Bharat
Project Win Bharat
Subodh Yadav
 
Pepper Pot Centre Annual Report 2009-10
Pepper Pot Centre Annual Report 2009-10Pepper Pot Centre Annual Report 2009-10
Pepper Pot Centre Annual Report 2009-10
Sadiqa Jabbar
 
Your Business and HR Technology: Is There a Connection? - Anna Langford, AAF ...
Your Business and HR Technology: Is There a Connection? - Anna Langford, AAF ...Your Business and HR Technology: Is There a Connection? - Anna Langford, AAF ...
Your Business and HR Technology: Is There a Connection? - Anna Langford, AAF ...
HR Network marcus evans
 
Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
RepRight Independent Sales Team Solutions
RepRight Independent Sales Team SolutionsRepRight Independent Sales Team Solutions
RepRight Independent Sales Team Solutions
Alice Errett
 
DrugInfo seminar: Information and communication technologies in reducing AOD ...
DrugInfo seminar: Information and communication technologies in reducing AOD ...DrugInfo seminar: Information and communication technologies in reducing AOD ...
DrugInfo seminar: Information and communication technologies in reducing AOD ...
Australian Drug Foundation
 
How to Fix America’s Fiscal Crisis: Reform Lessons from Canada - Chris Edward...
How to Fix America’s Fiscal Crisis: Reform Lessons from Canada - Chris Edward...How to Fix America’s Fiscal Crisis: Reform Lessons from Canada - Chris Edward...
How to Fix America’s Fiscal Crisis: Reform Lessons from Canada - Chris Edward...
Finance Network marcus evans
 
Personal
PersonalPersonal
Magnus Strømnes Bøe: Det siste klikket vs. det store bildet (Webdagene 2012)
Magnus Strømnes Bøe: Det siste klikket vs. det store bildet (Webdagene 2012)Magnus Strømnes Bøe: Det siste klikket vs. det store bildet (Webdagene 2012)
Magnus Strømnes Bøe: Det siste klikket vs. det store bildet (Webdagene 2012)webdagene
 
BGCAPP Meeting with Secondary Waste Working Group Members 28 May 2014
BGCAPP Meeting with Secondary Waste Working Group Members 28 May 2014BGCAPP Meeting with Secondary Waste Working Group Members 28 May 2014
BGCAPP Meeting with Secondary Waste Working Group Members 28 May 2014
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
DrugInfo seminar: Stepping out of the SHADE. The use of ehealth approaches in...
DrugInfo seminar: Stepping out of the SHADE. The use of ehealth approaches in...DrugInfo seminar: Stepping out of the SHADE. The use of ehealth approaches in...
DrugInfo seminar: Stepping out of the SHADE. The use of ehealth approaches in...
Australian Drug Foundation
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update September ...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update September ...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update September ...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update September ...
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Program Executive Office Assembled Chemical Weapons Alternatives Update to ...
Program Executive Office Assembled Chemical Weapons Alternatives Update to ...Program Executive Office Assembled Chemical Weapons Alternatives Update to ...
Program Executive Office Assembled Chemical Weapons Alternatives Update to ...
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Gazzetta 5-9-2011 Serie A Streaming
Gazzetta 5-9-2011 Serie A StreamingGazzetta 5-9-2011 Serie A Streaming
Gazzetta 5-9-2011 Serie A Streamingserieastreaming
 

Viewers also liked (20)

Preliminary task
Preliminary taskPreliminary task
Preliminary task
 
Economic Development Working Group 10 September 2013
Economic Development Working Group 10 September 2013Economic Development Working Group 10 September 2013
Economic Development Working Group 10 September 2013
 
Project Win Bharat
Project  Win BharatProject  Win Bharat
Project Win Bharat
 
Pepper Pot Centre Annual Report 2009-10
Pepper Pot Centre Annual Report 2009-10Pepper Pot Centre Annual Report 2009-10
Pepper Pot Centre Annual Report 2009-10
 
Your Business and HR Technology: Is There a Connection? - Anna Langford, AAF ...
Your Business and HR Technology: Is There a Connection? - Anna Langford, AAF ...Your Business and HR Technology: Is There a Connection? - Anna Langford, AAF ...
Your Business and HR Technology: Is There a Connection? - Anna Langford, AAF ...
 
Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013
 
RepRight Independent Sales Team Solutions
RepRight Independent Sales Team SolutionsRepRight Independent Sales Team Solutions
RepRight Independent Sales Team Solutions
 
April 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status...
April 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status...April 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status...
April 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status...
 
DrugInfo seminar: Information and communication technologies in reducing AOD ...
DrugInfo seminar: Information and communication technologies in reducing AOD ...DrugInfo seminar: Information and communication technologies in reducing AOD ...
DrugInfo seminar: Information and communication technologies in reducing AOD ...
 
How to Fix America’s Fiscal Crisis: Reform Lessons from Canada - Chris Edward...
How to Fix America’s Fiscal Crisis: Reform Lessons from Canada - Chris Edward...How to Fix America’s Fiscal Crisis: Reform Lessons from Canada - Chris Edward...
How to Fix America’s Fiscal Crisis: Reform Lessons from Canada - Chris Edward...
 
Geometry
GeometryGeometry
Geometry
 
Personal
PersonalPersonal
Personal
 
Magnus Strømnes Bøe: Det siste klikket vs. det store bildet (Webdagene 2012)
Magnus Strømnes Bøe: Det siste klikket vs. det store bildet (Webdagene 2012)Magnus Strømnes Bøe: Det siste klikket vs. det store bildet (Webdagene 2012)
Magnus Strømnes Bøe: Det siste klikket vs. det store bildet (Webdagene 2012)
 
BGCAPP Meeting with Secondary Waste Working Group Members 28 May 2014
BGCAPP Meeting with Secondary Waste Working Group Members 28 May 2014BGCAPP Meeting with Secondary Waste Working Group Members 28 May 2014
BGCAPP Meeting with Secondary Waste Working Group Members 28 May 2014
 
DrugInfo seminar: Stepping out of the SHADE. The use of ehealth approaches in...
DrugInfo seminar: Stepping out of the SHADE. The use of ehealth approaches in...DrugInfo seminar: Stepping out of the SHADE. The use of ehealth approaches in...
DrugInfo seminar: Stepping out of the SHADE. The use of ehealth approaches in...
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update September ...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update September ...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update September ...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update September ...
 
Chicken soup for the soul
Chicken soup for the soulChicken soup for the soul
Chicken soup for the soul
 
Web properties
Web propertiesWeb properties
Web properties
 
Program Executive Office Assembled Chemical Weapons Alternatives Update to ...
Program Executive Office Assembled Chemical Weapons Alternatives Update to ...Program Executive Office Assembled Chemical Weapons Alternatives Update to ...
Program Executive Office Assembled Chemical Weapons Alternatives Update to ...
 
Gazzetta 5-9-2011 Serie A Streaming
Gazzetta 5-9-2011 Serie A StreamingGazzetta 5-9-2011 Serie A Streaming
Gazzetta 5-9-2011 Serie A Streaming
 

Similar to PCAPP Update 28 May 2014

CAC Meeting 18 September 2013
CAC Meeting 18 September 2013CAC Meeting 18 September 2013
Fmq lqos introduction npi rev 2
Fmq  lqos introduction npi rev 2Fmq  lqos introduction npi rev 2
Fmq lqos introduction npi rev 2
amitsonuksms
 
Ajai K. Asthana CV
Ajai K. Asthana CVAjai K. Asthana CV
Ajai K. Asthana CVAjay Asthana
 
Contamination Control Cleaning Validation.pdf
Contamination Control Cleaning Validation.pdfContamination Control Cleaning Validation.pdf
Contamination Control Cleaning Validation.pdf
HassanHani5
 
validation ppt.pptx
validation ppt.pptxvalidation ppt.pptx
validation ppt.pptx
PawanDhamala1
 
Pharmaceutical Qualification & Validation
Pharmaceutical Qualification & ValidationPharmaceutical Qualification & Validation
Pharmaceutical Qualification & Validation
Pharmaceutical
 
EMA Qualification & Validation Requirements
EMA Qualification & Validation Requirements EMA Qualification & Validation Requirements
EMA Qualification & Validation Requirements
GMP EDUCATION : Not for Profit Organization
 
Validation and calibration master plan
Validation and calibration master planValidation and calibration master plan
Validation and calibration master plan
Bharatlal Sain
 
presentation quality awareness draft02.pptx
presentation quality awareness draft02.pptxpresentation quality awareness draft02.pptx
presentation quality awareness draft02.pptx
AhmedAltantawi
 
Rel maint-final
Rel maint-finalRel maint-final
Rel maint-final
amar sadi
 
Vendor certification
Vendor certificationVendor certification
Vendor certification
Yachita Rajwadwala
 
Pharmaceutical Process validation
Pharmaceutical Process validationPharmaceutical Process validation
Pharmaceutical Process validation
Dr Rakesh Kumar Sharma
 
Clinical QbD Best Practices When Outsourcing
Clinical QbD Best Practices When OutsourcingClinical QbD Best Practices When Outsourcing
Clinical QbD Best Practices When Outsourcing
The Avoca Group
 
Validation master plan
Validation master planValidation master plan
Validation master plan
Priyanka Kandhare
 
PetroSync - API 580 & API 581 Risk Based Inspection & Base Resource Document
PetroSync - API 580 & API 581 Risk Based Inspection & Base Resource DocumentPetroSync - API 580 & API 581 Risk Based Inspection & Base Resource Document
PetroSync - API 580 & API 581 Risk Based Inspection & Base Resource Document
PetroSync
 
Mechanical Integrity.pdf
Mechanical Integrity.pdfMechanical Integrity.pdf
Mechanical Integrity.pdf
aashir14
 

Similar to PCAPP Update 28 May 2014 (20)

CAC Meeting 18 September 2013
CAC Meeting 18 September 2013CAC Meeting 18 September 2013
CAC Meeting 18 September 2013
 
Fmq lqos introduction npi rev 2
Fmq  lqos introduction npi rev 2Fmq  lqos introduction npi rev 2
Fmq lqos introduction npi rev 2
 
Ajai K. Asthana CV
Ajai K. Asthana CVAjai K. Asthana CV
Ajai K. Asthana CV
 
Contamination Control Cleaning Validation.pdf
Contamination Control Cleaning Validation.pdfContamination Control Cleaning Validation.pdf
Contamination Control Cleaning Validation.pdf
 
validation ppt.pptx
validation ppt.pptxvalidation ppt.pptx
validation ppt.pptx
 
Pharmaceutical Qualification & Validation
Pharmaceutical Qualification & ValidationPharmaceutical Qualification & Validation
Pharmaceutical Qualification & Validation
 
EMA Qualification & Validation Requirements
EMA Qualification & Validation Requirements EMA Qualification & Validation Requirements
EMA Qualification & Validation Requirements
 
Validation and calibration master plan
Validation and calibration master planValidation and calibration master plan
Validation and calibration master plan
 
presentation quality awareness draft02.pptx
presentation quality awareness draft02.pptxpresentation quality awareness draft02.pptx
presentation quality awareness draft02.pptx
 
Implement Process Validation
Implement Process ValidationImplement Process Validation
Implement Process Validation
 
Rel maint-final
Rel maint-finalRel maint-final
Rel maint-final
 
CV_Goh Yeu Shan, Aaron
CV_Goh Yeu Shan, AaronCV_Goh Yeu Shan, Aaron
CV_Goh Yeu Shan, Aaron
 
Vendor certification
Vendor certificationVendor certification
Vendor certification
 
Pharmaceutical Process validation
Pharmaceutical Process validationPharmaceutical Process validation
Pharmaceutical Process validation
 
NM CV 041114
NM CV 041114NM CV 041114
NM CV 041114
 
Clinical QbD Best Practices When Outsourcing
Clinical QbD Best Practices When OutsourcingClinical QbD Best Practices When Outsourcing
Clinical QbD Best Practices When Outsourcing
 
Validation master plan
Validation master planValidation master plan
Validation master plan
 
PetroSync - API 580 & API 581 Risk Based Inspection & Base Resource Document
PetroSync - API 580 & API 581 Risk Based Inspection & Base Resource DocumentPetroSync - API 580 & API 581 Risk Based Inspection & Base Resource Document
PetroSync - API 580 & API 581 Risk Based Inspection & Base Resource Document
 
Mechanical Integrity.pdf
Mechanical Integrity.pdfMechanical Integrity.pdf
Mechanical Integrity.pdf
 
kshitij_resume_Ln
kshitij_resume_Lnkshitij_resume_Ln
kshitij_resume_Ln
 

More from Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)

CAC/CDCAB Vent Recommendation 5 March 2013
CAC/CDCAB Vent Recommendation 5 March 2013CAC/CDCAB Vent Recommendation 5 March 2013
Secondary Waste Working Group 12 March 2014
Secondary Waste Working Group 12 March 2014Secondary Waste Working Group 12 March 2014
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
M55 Rocket Separation Operation 11 Dec 2013
M55 Rocket Separation Operation 11 Dec 2013M55 Rocket Separation Operation 11 Dec 2013
2015 ACWA Funding 11 June 2014
2015 ACWA Funding 11 June 20142015 ACWA Funding 11 June 2014
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
BGCAPP Year in Review Dec. 11, 2013
BGCAPP Year in Review Dec. 11, 2013BGCAPP Year in Review Dec. 11, 2013
BGCAPP Year in Review Dec. 11, 2012
BGCAPP Year in Review Dec. 11, 2012BGCAPP Year in Review Dec. 11, 2012
Chemical Weapons Convention Update 13 June 2012
Chemical Weapons Convention Update 13 June 2012Chemical Weapons Convention Update 13 June 2012
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons ConventionOPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
CDCAB Working Group Updates 11 December 2012
CDCAB Working Group Updates 11 December 2012CDCAB Working Group Updates 11 December 2012
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Economic Development Working Group Update
Economic Development Working Group UpdateEconomic Development Working Group Update

More from Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA) (20)

CAC/CDCAB Vent Recommendation 5 March 2013
CAC/CDCAB Vent Recommendation 5 March 2013CAC/CDCAB Vent Recommendation 5 March 2013
CAC/CDCAB Vent Recommendation 5 March 2013
 
Secondary Waste Working Group 12 March 2014
Secondary Waste Working Group 12 March 2014Secondary Waste Working Group 12 March 2014
Secondary Waste Working Group 12 March 2014
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
 
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
 
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
 
June '13 cdcab
June '13 cdcabJune '13 cdcab
June '13 cdcab
 
M55 Rocket Separation Operation 11 Dec 2013
M55 Rocket Separation Operation 11 Dec 2013M55 Rocket Separation Operation 11 Dec 2013
M55 Rocket Separation Operation 11 Dec 2013
 
2015 ACWA Funding 11 June 2014
2015 ACWA Funding 11 June 20142015 ACWA Funding 11 June 2014
2015 ACWA Funding 11 June 2014
 
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
 
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
 
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
 
Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014
 
BGCAPP Year in Review Dec. 11, 2013
BGCAPP Year in Review Dec. 11, 2013BGCAPP Year in Review Dec. 11, 2013
BGCAPP Year in Review Dec. 11, 2013
 
BGCAPP Year in Review Dec. 11, 2012
BGCAPP Year in Review Dec. 11, 2012BGCAPP Year in Review Dec. 11, 2012
BGCAPP Year in Review Dec. 11, 2012
 
Chemical Weapons Convention Update 13 June 2012
Chemical Weapons Convention Update 13 June 2012Chemical Weapons Convention Update 13 June 2012
Chemical Weapons Convention Update 13 June 2012
 
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons ConventionOPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
 
CDCAB Working Group Updates 11 December 2012
CDCAB Working Group Updates 11 December 2012CDCAB Working Group Updates 11 December 2012
CDCAB Working Group Updates 11 December 2012
 
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
 
Economic Development Working Group Update
Economic Development Working Group UpdateEconomic Development Working Group Update
Economic Development Working Group Update
 

Recently uploaded

What is the point of small housing associations.pptx
What is the point of small housing associations.pptxWhat is the point of small housing associations.pptx
What is the point of small housing associations.pptx
Paul Smith
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
ahcitycouncil
 
Up the Ratios Bylaws - a Comprehensive Process of Our Organization
Up the Ratios Bylaws - a Comprehensive Process of Our OrganizationUp the Ratios Bylaws - a Comprehensive Process of Our Organization
Up the Ratios Bylaws - a Comprehensive Process of Our Organization
uptheratios
 
PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
Mohammed325561
 
Counting Class for Micro Observers 2024.pptx
Counting Class for Micro Observers 2024.pptxCounting Class for Micro Observers 2024.pptx
Counting Class for Micro Observers 2024.pptx
Revenue Department Kerala State
 
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
ehbuaw
 
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
ehbuaw
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
Antti Rautiainen
 
2024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 372024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 37
JSchaus & Associates
 
PPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933FPPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933F
ahcitycouncil
 
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) AmendmentPPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
ahcitycouncil
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
oklahomajudicialproc1
 
PPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930FPPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930F
ahcitycouncil
 
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
850fcj96
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
850fcj96
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
JSchaus & Associates
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
SERUDS INDIA
 
ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
Saeed Al Dhaheri
 
Canadian Immigration Tracker March 2024 - Key Slides
Canadian Immigration Tracker March 2024 - Key SlidesCanadian Immigration Tracker March 2024 - Key Slides
Canadian Immigration Tracker March 2024 - Key Slides
Andrew Griffith
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
ehbuaw
 

Recently uploaded (20)

What is the point of small housing associations.pptx
What is the point of small housing associations.pptxWhat is the point of small housing associations.pptx
What is the point of small housing associations.pptx
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
 
Up the Ratios Bylaws - a Comprehensive Process of Our Organization
Up the Ratios Bylaws - a Comprehensive Process of Our OrganizationUp the Ratios Bylaws - a Comprehensive Process of Our Organization
Up the Ratios Bylaws - a Comprehensive Process of Our Organization
 
PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
 
Counting Class for Micro Observers 2024.pptx
Counting Class for Micro Observers 2024.pptxCounting Class for Micro Observers 2024.pptx
Counting Class for Micro Observers 2024.pptx
 
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
 
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
 
2024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 372024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 37
 
PPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933FPPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933F
 
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) AmendmentPPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
 
PPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930FPPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930F
 
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
 
ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
 
Canadian Immigration Tracker March 2024 - Key Slides
Canadian Immigration Tracker March 2024 - Key SlidesCanadian Immigration Tracker March 2024 - Key Slides
Canadian Immigration Tracker March 2024 - Key Slides
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
 

PCAPP Update 28 May 2014

  • 1. PCAPP Update 28 May 2014 Presented to: Citizens’ Advisory Commission Presented by: Paul Dent Operational Readiness Review (ORR) Manager
  • 2. What is an ORR? Per ACWA Policy Statement 26, “ORRs will be conducted to verify the readiness of the ACWA Pilot Plants to safely begin operations involving chemical agents, explosives, or other highly hazardous materials.”  The ORR process is used to validate that PCAPP “plant, paper, and people” collectively meet the required criteria to allow a new operation to begin.  PCAPP ORR process is led by the system-contractor (SC) to support a declaration of readiness.  ACWA provides ORR oversight; independent validation is used to support the SC’s declaration of readiness.  Stakeholders are invited to observe the ORR process. 2 Plant PeoplePaper Achieve Readiness – by Responsible Managers Validate Readiness – by ORR Board Declare Readiness – by Project Manager Accept Readiness – by ACWA
  • 3. 5 ORR Major Milestones NOT YET STARTED IN PROGRESS COMPLETE * Major Milestones per the PCAPP Baseline IMS. PCAPP goal is to declare readiness 60 days sooner * Incremental Readiness Assessments will overlap – they are not strictly sequential 1 7 9 8 4 3 2 6 14 15 16 Lab Dilute Agent Operations Mini-ORR OCT 2013 – 52 Criteria Boiler Ignition Readiness Assessment DEC 2012 – 19 Criteria Integrated Operations Demonstrations (IODs) JUN 2015 – 11 Criteria Agent Entry Readiness and Agent Containment and Confinement Controls SEP 2014 – 49 Criteria ERB Provisional Operations SEP-2014 – 75 Criteria APB Provisional Operations NOV 2014 – 32 Criteria Contingency Training Readiness/Crew Certification JAN 2015 – 59 Criteria Security/Surety (Soft-Lockdown) Readiness Review FEB 2015 – 16 Criteria BTA Provisional Operations NOV 2014 – 13 Criteria Yard Provisional Operations JUL-2014 – 111 Criteria Initial Agent Operations - Readiness Declared JUL 2015 – 6 Criteria ACWA Readiness Endorsement SEP 2015 Training Facility Available for Practical Factors – Readiness Check JUN 2014 Forecast Pre-Systemization Complete NOV 2013 Training Facility Available for TAT – Readiness Check JAN 2014 10 11 13 12 Environmental Readiness FEB 2015 – 14 Criteria 3
  • 4. Scope of ORR for Initial Agent Operations  Criteria are defined in the Initial Agent Operations ORR procedure ― Defines ORR criteria that reflect project requirements ― Summarizes proposed Integrated Operations Demonstrations (IODs) ― Include normal and off-normal exercises to be performed ― Evaluation teams will observe and critique each demonstration 4 # Functional Area # of criteria 1 Acquisitions 10 2 Emergency Preparedness 14 3 Engineering 26 4 Environmental 14 5 Government Interfaces 13 6 Human Resources 3 7 Information Systems & Technology 5 8 Laboratory 21 9 Maintenance 11 10 Medical 21 11 Office and Administrative Services 6 12 Operations 49 13 Operations Support 22 14 Pilot Test Preparedness 3 15 Plant Support (Treaty) 8 16 Project and Plant Management 15 17 Quality Assurance/Quality Control 7 18 Safety 38 19 Security 13 20 Start-up/ Systemization 50 21 Surety 7 22 Training 15 23 Work Control 15 386  Each of the four shifts will perform IODs for readiness validation.  Upon successful completion of IODs and closeout of required findings, System Contractor will declare readiness.
  • 5. Criteria Review Resources Engaged  Chris Midgett – Chair of Executive Board: ― Brings extensive experience in managing chem-demil work ― Liaison to ACWA and stakeholder executive functions  Sierra Lobo, Inc. – Independent engineering resource ― Testing & evaluation expertise ― Clients include NASA & Department of Defense  Blue Grass Subject Matter Experts (SMEs): ― Will use BGCAPP SMEs for independent review ― Bring an excellent understanding of standards & recent operating experience ― ORR experience provides benefits to both projects 5
  • 6. IAO ORR Status ORR work will be paced by Systemization work. Data as of 22-May-2014 ORR Documents Total Required Issued for Completion Board Reviewed Board Accepted Affidavits 386 135 55 34 CRADS 386 15 0 0 6
  • 7. ORR Oversight  Review ORR documents, attend Board meetings, and observe demonstrations  Provide immediate feedback on ORR issues, process, and documentation  Provide independent validation of 20% of ORR criteria in accordance with their oversight procedure  Coordinate stakeholder involvement in ORR process  Lead a monthly meeting with representatives from the Blue Grass project, Pueblo Chemical Depot, and stakeholders to communicate ORR status, schedule, issues, and lessons learned ACWA representatives also assess the System Contractor’s readiness for initial agent operations: 7