Presented to:
Kentucky Chemical Demilitarization Citizens’ Advisory Commission/ Chemical Destruction Community Advisory Board Meeting
Presented by:
Jeff Brubaker Tom McKinney
Site Project Manager Project Manager
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, ...
BGCAPP Year in Review Dec. 11, 2012
1. Presented to:
Kentucky Chemical Demilitarization Citizens’ Advisory Commission/
Chemical Destruction Community Advisory Board Meeting
Presented by:
Jeff Brubaker Tom McKinney
Site Project Manager Project Manager
Year In Review
Dec. 11, 2012
2. A Partnership for Safe Chemical Weapons Destruction
2012 Accomplishments
2
Main Plant
Construction
Support
Infrastructure
Systemization
Activities Begin
Munitions Reverse-
Assembly Equipment
MDB neutralization
equipment installed
MDB concrete
completion milestone
SCWO Process
Building structural
steel completion
CSB civil
infrastructure
complete
Laboratory complete
Nitrogen generation
plant vessel installed,
foundation complete
Hydrolysate Storage
Area foundation
complete
Began exterior utility
pipe-rack steel
Laboratory Building
Maintenance Building
Personnel Support
Building
Utility Power Centers
Rocket Cutting
Machine fabrication
and testing complete
Rocket Shear Machine
fabrication and
testing complete
Munitions Washout
System begins testing
MDB = Munitions Demilitarization Building CSB = Control and Support Building SCWO = Supercritical Water Oxidation
3. A Partnership for Safe Chemical Weapons Destruction
Control and Support Building
• Electrical, piping and fire detection systems
• Heating, ventilation and air conditioning (HVAC)
• Facility control system cabinets and infrastructure
Munitions Demilitarization Building
• Structural steel, paneling, protective coating
• HVAC, electrical, piping, mechanical systems
• MDB filter area foundations
Construction 60 percent complete
Systemization 4 percent complete
• Utility Building
• Exterior pipe rack support steel
• Interior electrical and piping systems
• Nitrogen generation plant equipment
Supercritical Water Oxidation
Process Building (not visible in photo)
• Exterior siding
Laboratory Building (not visible in photo)
• Systemization activities
1
2
1
2
3
4
5
3
45
3
4. A Partnership for Safe Chemical Weapons Destruction
Construction Progress
A Fisher Tank subcontractor works on the installation
of one of the Hydrolysate Storage tanks.
A team installs and fits embeds in the walls of the
Munitions Demilitarization Building blast-containment
area.
Piping work continues in the Control and Support
Building.
Workers prepare to lift and install a component of the
Nitrogen Processing System.
4
5. A Partnership for Safe Chemical Weapons Destruction
Munitions Demilitarization
Building (MDB)
Inside, electricians are installing the wiring for the Metal Parts Treater (MPT, above left), while outside, ironworkers “fly in” the first of the many housings
for the MDB filter banks (above right). The MPT will thermally decontaminate the metal parts of the munitions after the chemical agent has been
drained, and the filter banks will clean the air exiting the main processing building. Installation of structural steel also continues on the MDB.
5
6. A Partnership for Safe Chemical Weapons Destruction
Control and Support
Building (CSB)
Deputy Site Project Manager Anthony Reed discusses the project with a group of Eastern Kentucky University honors students in the Control Room
(CON, above left). During plant operations, CON operators will observe and control all aspects of the automated processing of the chemical agent
munitions. Meanwhile, rolls of some of the 177 miles of wiring to be installed in the CSB are staged for installation (above right).
6
7. A Partnership for Safe Chemical Weapons Destruction
Utility Building (UB)
The UB is surrounded by the pipe rack that will convey processing chemicals to plant operations activities (above left). Inside the UB, sheet metal
workers install air compressor heating, ventilation and air conditioning ductwork (above right). Outside the UB, installation of the Nitrogen Processing
System continues.
7
8. A Partnership for Safe Chemical Weapons Destruction
Supercritical Water Oxidation
Processing Building (SPB)
Project workers started installing insulated siding on the SPB in November 2011. The building should be fully enclosed by the end of the calendar year,
allowing the workforce to focus on interior work. Workers prepare insulated panels for installation on the building (above, left) and fly the panels in with a
crane workers to install (above, right).
8
9. A Partnership for Safe Chemical Weapons Destruction
Laboratory Building (Lab)
Laboratory Building construction has been completed and the building has been turned over for systemization activities. Systemization of the building
should be complete in 2013.
9
10. A Partnership for Safe Chemical Weapons Destruction
Systemization at BGCAPP
10
Blue Grass team completed the
Systemization Implementation Plan in
2012
− Maps out construction priorities so we
complete projects in most efficient
manner
− Allows team to prepare for hiring
schedule and plan out key milestone
dates
Construction team turned over 15
systems and three facilities in 2012
Systemization is four percent
complete
Systemization is the process by which BGCAPP
workers make sure the procedures, people and
the plant itself are prepared to begin chemical
weapons destruction operations
11. A Partnership for Safe Chemical Weapons Destruction
Project Safety
11
3.9
1.5
2.85
0.28
Recordable Injuries Lost-Time Injuries
Construction Industry
Bechtel Parsons
Our goal remains Zero Accidents
January OSHA Voluntary Protection Program
Star Status workforce celebration
May “Safety Pause” reinforced positive safety culture
Continuing to address safety concerns
• OSHA VPP Program, worker-based safety teams
• Brothers’ Keeper mindset
Our safety record consistently compares favorably to
industry standards
12. A Partnership for Safe Chemical Weapons Destruction
Economic Impact
Acquisitions to date
― $102.7 million spent with
Kentucky companies
― $62.8 million spent in Madison
and surrounding counties
Local payroll to date
― $373 million paid
― $437 million more to be paid
during the remainder of
project
Held vendor forums, job
fairs
Staffing in Richmond now
exceeds 990
12
13. A Partnership for Safe Chemical Weapons Destruction
A Look Ahead
13
Installation of Rocket Cutting and Rocket Shear
Machines
Complete testing and delivery of the Munitions
Washout System
Completion of Hydrolysate Storage Area tank
installation
Set Munitions Demilitarization Building (MDB)
filter banks
Complete MDB structural steel
Enclose Supercritical Water Oxidation Processing
Building
Continue construction focus shift from
civil/structural to large-scale pipe and electrical
commodity installation
14. A Partnership for Safe Chemical Weapons Destruction
14
Questions?
For more information about the Blue Grass Chemical Agent-Destruction Pilot Plant project,
please contact the Blue Grass Chemical Stockpile Outreach Office
at (859) 626-8944 or bgoutreach@iem.com