SlideShare a Scribd company logo
1 of 14
Presented to:
Kentucky Chemical Demilitarization Citizens’ Advisory Commission/
Chemical Destruction Community Advisory Board Meeting
Presented by:
Jeff Brubaker Tom McKinney
Site Project Manager Project Manager
Year In Review
Dec. 11, 2012
A Partnership for Safe Chemical Weapons Destruction
2012 Accomplishments
2
Main Plant
Construction
Support
Infrastructure
Systemization
Activities Begin
Munitions Reverse-
Assembly Equipment
 MDB neutralization
equipment installed
 MDB concrete
completion milestone
 SCWO Process
Building structural
steel completion
 CSB civil
infrastructure
complete
 Laboratory complete
 Nitrogen generation
plant vessel installed,
foundation complete
 Hydrolysate Storage
Area foundation
complete
 Began exterior utility
pipe-rack steel
 Laboratory Building
 Maintenance Building
 Personnel Support
Building
 Utility Power Centers
 Rocket Cutting
Machine fabrication
and testing complete
 Rocket Shear Machine
fabrication and
testing complete
 Munitions Washout
System begins testing
MDB = Munitions Demilitarization Building CSB = Control and Support Building SCWO = Supercritical Water Oxidation
A Partnership for Safe Chemical Weapons Destruction
 Control and Support Building
• Electrical, piping and fire detection systems
• Heating, ventilation and air conditioning (HVAC)
• Facility control system cabinets and infrastructure
 Munitions Demilitarization Building
• Structural steel, paneling, protective coating
• HVAC, electrical, piping, mechanical systems
• MDB filter area foundations
Construction 60 percent complete
Systemization 4 percent complete
• Utility Building
• Exterior pipe rack support steel
• Interior electrical and piping systems
• Nitrogen generation plant equipment
 Supercritical Water Oxidation
Process Building (not visible in photo)
• Exterior siding
 Laboratory Building (not visible in photo)
• Systemization activities
1
2
1
2
3
4
5
3
45
3
A Partnership for Safe Chemical Weapons Destruction
Construction Progress
A Fisher Tank subcontractor works on the installation
of one of the Hydrolysate Storage tanks.
A team installs and fits embeds in the walls of the
Munitions Demilitarization Building blast-containment
area.
Piping work continues in the Control and Support
Building.
Workers prepare to lift and install a component of the
Nitrogen Processing System.
4
A Partnership for Safe Chemical Weapons Destruction
Munitions Demilitarization
Building (MDB)
Inside, electricians are installing the wiring for the Metal Parts Treater (MPT, above left), while outside, ironworkers “fly in” the first of the many housings
for the MDB filter banks (above right). The MPT will thermally decontaminate the metal parts of the munitions after the chemical agent has been
drained, and the filter banks will clean the air exiting the main processing building. Installation of structural steel also continues on the MDB.
5
A Partnership for Safe Chemical Weapons Destruction
Control and Support
Building (CSB)
Deputy Site Project Manager Anthony Reed discusses the project with a group of Eastern Kentucky University honors students in the Control Room
(CON, above left). During plant operations, CON operators will observe and control all aspects of the automated processing of the chemical agent
munitions. Meanwhile, rolls of some of the 177 miles of wiring to be installed in the CSB are staged for installation (above right).
6
A Partnership for Safe Chemical Weapons Destruction
Utility Building (UB)
The UB is surrounded by the pipe rack that will convey processing chemicals to plant operations activities (above left). Inside the UB, sheet metal
workers install air compressor heating, ventilation and air conditioning ductwork (above right). Outside the UB, installation of the Nitrogen Processing
System continues.
7
A Partnership for Safe Chemical Weapons Destruction
Supercritical Water Oxidation
Processing Building (SPB)
Project workers started installing insulated siding on the SPB in November 2011. The building should be fully enclosed by the end of the calendar year,
allowing the workforce to focus on interior work. Workers prepare insulated panels for installation on the building (above, left) and fly the panels in with a
crane workers to install (above, right).
8
A Partnership for Safe Chemical Weapons Destruction
Laboratory Building (Lab)
Laboratory Building construction has been completed and the building has been turned over for systemization activities. Systemization of the building
should be complete in 2013.
9
A Partnership for Safe Chemical Weapons Destruction
Systemization at BGCAPP
10
 Blue Grass team completed the
Systemization Implementation Plan in
2012
− Maps out construction priorities so we
complete projects in most efficient
manner
− Allows team to prepare for hiring
schedule and plan out key milestone
dates
 Construction team turned over 15
systems and three facilities in 2012
 Systemization is four percent
complete
Systemization is the process by which BGCAPP
workers make sure the procedures, people and
the plant itself are prepared to begin chemical
weapons destruction operations
A Partnership for Safe Chemical Weapons Destruction
Project Safety
11
3.9
1.5
2.85
0.28
Recordable Injuries Lost-Time Injuries
Construction Industry
Bechtel Parsons
 Our goal remains Zero Accidents
 January OSHA Voluntary Protection Program
Star Status workforce celebration
 May “Safety Pause” reinforced positive safety culture
 Continuing to address safety concerns
• OSHA VPP Program, worker-based safety teams
• Brothers’ Keeper mindset
 Our safety record consistently compares favorably to
industry standards
A Partnership for Safe Chemical Weapons Destruction
Economic Impact
 Acquisitions to date
― $102.7 million spent with
Kentucky companies
― $62.8 million spent in Madison
and surrounding counties
 Local payroll to date
― $373 million paid
― $437 million more to be paid
during the remainder of
project
 Held vendor forums, job
fairs
 Staffing in Richmond now
exceeds 990
12
A Partnership for Safe Chemical Weapons Destruction
A Look Ahead
13
 Installation of Rocket Cutting and Rocket Shear
Machines
 Complete testing and delivery of the Munitions
Washout System
 Completion of Hydrolysate Storage Area tank
installation
 Set Munitions Demilitarization Building (MDB)
filter banks
 Complete MDB structural steel
 Enclose Supercritical Water Oxidation Processing
Building
 Continue construction focus shift from
civil/structural to large-scale pipe and electrical
commodity installation
A Partnership for Safe Chemical Weapons Destruction
14
Questions?
For more information about the Blue Grass Chemical Agent-Destruction Pilot Plant project,
please contact the Blue Grass Chemical Stockpile Outreach Office
at (859) 626-8944 or bgoutreach@iem.com

More Related Content

What's hot

Lab Installation Cools Concerns - Federal Laboratory Renovation
Lab Installation Cools Concerns - Federal Laboratory RenovationLab Installation Cools Concerns - Federal Laboratory Renovation
Lab Installation Cools Concerns - Federal Laboratory RenovationMcKenney's Inc
 
Office Building Constructed in Nine Weeks !
Office Building Constructed in Nine Weeks !Office Building Constructed in Nine Weeks !
Office Building Constructed in Nine Weeks !wesleyvillhard
 
LOU NICKSIC - Industrial - Oil and Gas Resume 041116
LOU NICKSIC - Industrial - Oil and Gas Resume  041116LOU NICKSIC - Industrial - Oil and Gas Resume  041116
LOU NICKSIC - Industrial - Oil and Gas Resume 041116Lou Nicksic
 
Rusty Adkins Resume
Rusty Adkins ResumeRusty Adkins Resume
Rusty Adkins ResumeRusty Adkins
 
7 fire protection_engineering_r2-e-n1-c_0_z5rdz-i34k-pr
7 fire protection_engineering_r2-e-n1-c_0_z5rdz-i34k-pr7 fire protection_engineering_r2-e-n1-c_0_z5rdz-i34k-pr
7 fire protection_engineering_r2-e-n1-c_0_z5rdz-i34k-prHedi Mohamed
 
Blazemaster Cost Saving Report
Blazemaster Cost Saving ReportBlazemaster Cost Saving Report
Blazemaster Cost Saving ReportPoojaShetty87
 
Phillip lacy resume (2) (2)
Phillip lacy resume (2) (2)Phillip lacy resume (2) (2)
Phillip lacy resume (2) (2)Phillip-Lacy
 
Tim Rathsam Work History
Tim Rathsam Work HistoryTim Rathsam Work History
Tim Rathsam Work HistoryTim Rathsam
 
Steve Davidson Engineering Resume
Steve Davidson Engineering  ResumeSteve Davidson Engineering  Resume
Steve Davidson Engineering ResumeStephen Davidson
 
SpecailtyDrilling_InjectionWellConstruction-v-1
SpecailtyDrilling_InjectionWellConstruction-v-1SpecailtyDrilling_InjectionWellConstruction-v-1
SpecailtyDrilling_InjectionWellConstruction-v-1Tim Oman
 
Diving into innovation
Diving into innovation Diving into innovation
Diving into innovation Saudi Aramco
 
Process Safety Management in Design, Construction & Commissioning | Lalit K...
Process Safety Management in Design, Construction &  Commissioning | Lalit  K...Process Safety Management in Design, Construction &  Commissioning | Lalit  K...
Process Safety Management in Design, Construction & Commissioning | Lalit K...Cairn India Limited
 

What's hot (20)

Lab Installation Cools Concerns - Federal Laboratory Renovation
Lab Installation Cools Concerns - Federal Laboratory RenovationLab Installation Cools Concerns - Federal Laboratory Renovation
Lab Installation Cools Concerns - Federal Laboratory Renovation
 
Office Building Constructed in Nine Weeks !
Office Building Constructed in Nine Weeks !Office Building Constructed in Nine Weeks !
Office Building Constructed in Nine Weeks !
 
LOU NICKSIC - Industrial - Oil and Gas Resume 041116
LOU NICKSIC - Industrial - Oil and Gas Resume  041116LOU NICKSIC - Industrial - Oil and Gas Resume  041116
LOU NICKSIC - Industrial - Oil and Gas Resume 041116
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 13, 2...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 13, 2...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 13, 2...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 13, 2...
 
October 2012 BGCAPP Monthly Status Briefing
October 2012 BGCAPP Monthly Status BriefingOctober 2012 BGCAPP Monthly Status Briefing
October 2012 BGCAPP Monthly Status Briefing
 
Rusty Adkins Resume
Rusty Adkins ResumeRusty Adkins Resume
Rusty Adkins Resume
 
7 fire protection_engineering_r2-e-n1-c_0_z5rdz-i34k-pr
7 fire protection_engineering_r2-e-n1-c_0_z5rdz-i34k-pr7 fire protection_engineering_r2-e-n1-c_0_z5rdz-i34k-pr
7 fire protection_engineering_r2-e-n1-c_0_z5rdz-i34k-pr
 
MEL ROSE DRIZ Resume
MEL ROSE DRIZ ResumeMEL ROSE DRIZ Resume
MEL ROSE DRIZ Resume
 
Blazemaster Cost Saving Report
Blazemaster Cost Saving ReportBlazemaster Cost Saving Report
Blazemaster Cost Saving Report
 
Phillip lacy resume (2) (2)
Phillip lacy resume (2) (2)Phillip lacy resume (2) (2)
Phillip lacy resume (2) (2)
 
Leslie Banks 2016
Leslie Banks 2016Leslie Banks 2016
Leslie Banks 2016
 
Tim Rathsam Work History
Tim Rathsam Work HistoryTim Rathsam Work History
Tim Rathsam Work History
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
 
Steve Davidson Engineering Resume
Steve Davidson Engineering  ResumeSteve Davidson Engineering  Resume
Steve Davidson Engineering Resume
 
SpecailtyDrilling_InjectionWellConstruction-v-1
SpecailtyDrilling_InjectionWellConstruction-v-1SpecailtyDrilling_InjectionWellConstruction-v-1
SpecailtyDrilling_InjectionWellConstruction-v-1
 
Diving into innovation
Diving into innovation Diving into innovation
Diving into innovation
 
Pueblo Chemical Agent-Destruction Pilot Plant Completes Processing Building
Pueblo Chemical Agent-Destruction Pilot Plant Completes Processing BuildingPueblo Chemical Agent-Destruction Pilot Plant Completes Processing Building
Pueblo Chemical Agent-Destruction Pilot Plant Completes Processing Building
 
Process Safety Management in Design, Construction & Commissioning | Lalit K...
Process Safety Management in Design, Construction &  Commissioning | Lalit  K...Process Safety Management in Design, Construction &  Commissioning | Lalit  K...
Process Safety Management in Design, Construction & Commissioning | Lalit K...
 
CV-lizhihui
CV-lizhihuiCV-lizhihui
CV-lizhihui
 
Hse alert 55 hot works fire risk
Hse alert 55 hot works fire riskHse alert 55 hot works fire risk
Hse alert 55 hot works fire risk
 

Similar to BGCAPP Year in Review Dec. 11, 2012

INDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTINDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTNur Ain Samsudin
 
Engineering & Project Management
Engineering & Project ManagementEngineering & Project Management
Engineering & Project ManagementJames Gilmore
 
CV 08 May 2015 ncd
CV 08 May 2015 ncdCV 08 May 2015 ncd
CV 08 May 2015 ncdDavid Bates
 
Design,construction of Pilot plant for NCEs
Design,construction of Pilot plant for NCEsDesign,construction of Pilot plant for NCEs
Design,construction of Pilot plant for NCEsMutyala Naidu G
 

Similar to BGCAPP Year in Review Dec. 11, 2012 (20)

January 2013 BGCAPP Monthly Status Briefing
January 2013 BGCAPP Monthly Status BriefingJanuary 2013 BGCAPP Monthly Status Briefing
January 2013 BGCAPP Monthly Status Briefing
 
August 2012 BGCAPP Monthly Status Briefing
August 2012 BGCAPP Monthly Status BriefingAugust 2012 BGCAPP Monthly Status Briefing
August 2012 BGCAPP Monthly Status Briefing
 
December 2012 BGCAPP Monthly Status Briefing
December 2012 BGCAPP Monthly Status BriefingDecember 2012 BGCAPP Monthly Status Briefing
December 2012 BGCAPP Monthly Status Briefing
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update Sept. 10...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update Sept. 10...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update Sept. 10...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update Sept. 10...
 
September 2012 BGCAPP Monthly Status Briefing
September 2012 BGCAPP Monthly Status BriefingSeptember 2012 BGCAPP Monthly Status Briefing
September 2012 BGCAPP Monthly Status Briefing
 
July 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status ...
July 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status ...July 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status ...
July 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status ...
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, ...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, ...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, ...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, ...
 
March 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status...
March 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status...March 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status...
March 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status...
 
BGCAPP Monthly Status Briefing October 2011
BGCAPP Monthly Status Briefing October 2011BGCAPP Monthly Status Briefing October 2011
BGCAPP Monthly Status Briefing October 2011
 
April 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status...
April 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status...April 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status...
April 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status...
 
February 2013 BGCAPP Monthly Status Briefing
February 2013 BGCAPP Monthly Status BriefingFebruary 2013 BGCAPP Monthly Status Briefing
February 2013 BGCAPP Monthly Status Briefing
 
March 2013 BGCAPP Monthly Status Briefing
March 2013 BGCAPP Monthly Status BriefingMarch 2013 BGCAPP Monthly Status Briefing
March 2013 BGCAPP Monthly Status Briefing
 
INDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTINDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORT
 
May 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status B...
May 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status B...May 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status B...
May 2012 - Blue Grass Chemical Agent-Destruction Pilot Plant Monthly Status B...
 
PCAPP Update 27 June 2012
PCAPP Update 27 June 2012PCAPP Update 27 June 2012
PCAPP Update 27 June 2012
 
Engineering & Project Management
Engineering & Project ManagementEngineering & Project Management
Engineering & Project Management
 
BGCAPP Monthly Status Briefing - September 2011
BGCAPP Monthly Status Briefing - September 2011BGCAPP Monthly Status Briefing - September 2011
BGCAPP Monthly Status Briefing - September 2011
 
CV 08 May 2015 ncd
CV 08 May 2015 ncdCV 08 May 2015 ncd
CV 08 May 2015 ncd
 
Design,construction of Pilot plant for NCEs
Design,construction of Pilot plant for NCEsDesign,construction of Pilot plant for NCEs
Design,construction of Pilot plant for NCEs
 

More from Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)

More from Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA) (20)

CAC/CDCAB Vent Recommendation 5 March 2013
CAC/CDCAB Vent Recommendation 5 March 2013CAC/CDCAB Vent Recommendation 5 March 2013
CAC/CDCAB Vent Recommendation 5 March 2013
 
Secondary Waste Working Group 12 March 2014
Secondary Waste Working Group 12 March 2014Secondary Waste Working Group 12 March 2014
Secondary Waste Working Group 12 March 2014
 
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
 
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
 
June '13 cdcab
June '13 cdcabJune '13 cdcab
June '13 cdcab
 
M55 Rocket Separation Operation 11 Dec 2013
M55 Rocket Separation Operation 11 Dec 2013M55 Rocket Separation Operation 11 Dec 2013
M55 Rocket Separation Operation 11 Dec 2013
 
2015 ACWA Funding 11 June 2014
2015 ACWA Funding 11 June 20142015 ACWA Funding 11 June 2014
2015 ACWA Funding 11 June 2014
 
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
 
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
 
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
 
Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014
 
Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013
 
Chemical Weapons Convention Update 13 June 2012
Chemical Weapons Convention Update 13 June 2012Chemical Weapons Convention Update 13 June 2012
Chemical Weapons Convention Update 13 June 2012
 
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons ConventionOPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
 
CDCAB Working Group Updates 11 December 2012
CDCAB Working Group Updates 11 December 2012CDCAB Working Group Updates 11 December 2012
CDCAB Working Group Updates 11 December 2012
 
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
 
Economic Development Working Group Update
Economic Development Working Group UpdateEconomic Development Working Group Update
Economic Development Working Group Update
 
Blue Grass Chemical Activity Update 12 September 2012
Blue Grass Chemical Activity Update 12 September 2012Blue Grass Chemical Activity Update 12 September 2012
Blue Grass Chemical Activity Update 12 September 2012
 
Explosive Destruction Technologies Summary 23 October 2013
Explosive Destruction Technologies Summary 23 October 2013Explosive Destruction Technologies Summary 23 October 2013
Explosive Destruction Technologies Summary 23 October 2013
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, ...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, ...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, ...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 4, ...
 

BGCAPP Year in Review Dec. 11, 2012

  • 1. Presented to: Kentucky Chemical Demilitarization Citizens’ Advisory Commission/ Chemical Destruction Community Advisory Board Meeting Presented by: Jeff Brubaker Tom McKinney Site Project Manager Project Manager Year In Review Dec. 11, 2012
  • 2. A Partnership for Safe Chemical Weapons Destruction 2012 Accomplishments 2 Main Plant Construction Support Infrastructure Systemization Activities Begin Munitions Reverse- Assembly Equipment  MDB neutralization equipment installed  MDB concrete completion milestone  SCWO Process Building structural steel completion  CSB civil infrastructure complete  Laboratory complete  Nitrogen generation plant vessel installed, foundation complete  Hydrolysate Storage Area foundation complete  Began exterior utility pipe-rack steel  Laboratory Building  Maintenance Building  Personnel Support Building  Utility Power Centers  Rocket Cutting Machine fabrication and testing complete  Rocket Shear Machine fabrication and testing complete  Munitions Washout System begins testing MDB = Munitions Demilitarization Building CSB = Control and Support Building SCWO = Supercritical Water Oxidation
  • 3. A Partnership for Safe Chemical Weapons Destruction  Control and Support Building • Electrical, piping and fire detection systems • Heating, ventilation and air conditioning (HVAC) • Facility control system cabinets and infrastructure  Munitions Demilitarization Building • Structural steel, paneling, protective coating • HVAC, electrical, piping, mechanical systems • MDB filter area foundations Construction 60 percent complete Systemization 4 percent complete • Utility Building • Exterior pipe rack support steel • Interior electrical and piping systems • Nitrogen generation plant equipment  Supercritical Water Oxidation Process Building (not visible in photo) • Exterior siding  Laboratory Building (not visible in photo) • Systemization activities 1 2 1 2 3 4 5 3 45 3
  • 4. A Partnership for Safe Chemical Weapons Destruction Construction Progress A Fisher Tank subcontractor works on the installation of one of the Hydrolysate Storage tanks. A team installs and fits embeds in the walls of the Munitions Demilitarization Building blast-containment area. Piping work continues in the Control and Support Building. Workers prepare to lift and install a component of the Nitrogen Processing System. 4
  • 5. A Partnership for Safe Chemical Weapons Destruction Munitions Demilitarization Building (MDB) Inside, electricians are installing the wiring for the Metal Parts Treater (MPT, above left), while outside, ironworkers “fly in” the first of the many housings for the MDB filter banks (above right). The MPT will thermally decontaminate the metal parts of the munitions after the chemical agent has been drained, and the filter banks will clean the air exiting the main processing building. Installation of structural steel also continues on the MDB. 5
  • 6. A Partnership for Safe Chemical Weapons Destruction Control and Support Building (CSB) Deputy Site Project Manager Anthony Reed discusses the project with a group of Eastern Kentucky University honors students in the Control Room (CON, above left). During plant operations, CON operators will observe and control all aspects of the automated processing of the chemical agent munitions. Meanwhile, rolls of some of the 177 miles of wiring to be installed in the CSB are staged for installation (above right). 6
  • 7. A Partnership for Safe Chemical Weapons Destruction Utility Building (UB) The UB is surrounded by the pipe rack that will convey processing chemicals to plant operations activities (above left). Inside the UB, sheet metal workers install air compressor heating, ventilation and air conditioning ductwork (above right). Outside the UB, installation of the Nitrogen Processing System continues. 7
  • 8. A Partnership for Safe Chemical Weapons Destruction Supercritical Water Oxidation Processing Building (SPB) Project workers started installing insulated siding on the SPB in November 2011. The building should be fully enclosed by the end of the calendar year, allowing the workforce to focus on interior work. Workers prepare insulated panels for installation on the building (above, left) and fly the panels in with a crane workers to install (above, right). 8
  • 9. A Partnership for Safe Chemical Weapons Destruction Laboratory Building (Lab) Laboratory Building construction has been completed and the building has been turned over for systemization activities. Systemization of the building should be complete in 2013. 9
  • 10. A Partnership for Safe Chemical Weapons Destruction Systemization at BGCAPP 10  Blue Grass team completed the Systemization Implementation Plan in 2012 − Maps out construction priorities so we complete projects in most efficient manner − Allows team to prepare for hiring schedule and plan out key milestone dates  Construction team turned over 15 systems and three facilities in 2012  Systemization is four percent complete Systemization is the process by which BGCAPP workers make sure the procedures, people and the plant itself are prepared to begin chemical weapons destruction operations
  • 11. A Partnership for Safe Chemical Weapons Destruction Project Safety 11 3.9 1.5 2.85 0.28 Recordable Injuries Lost-Time Injuries Construction Industry Bechtel Parsons  Our goal remains Zero Accidents  January OSHA Voluntary Protection Program Star Status workforce celebration  May “Safety Pause” reinforced positive safety culture  Continuing to address safety concerns • OSHA VPP Program, worker-based safety teams • Brothers’ Keeper mindset  Our safety record consistently compares favorably to industry standards
  • 12. A Partnership for Safe Chemical Weapons Destruction Economic Impact  Acquisitions to date ― $102.7 million spent with Kentucky companies ― $62.8 million spent in Madison and surrounding counties  Local payroll to date ― $373 million paid ― $437 million more to be paid during the remainder of project  Held vendor forums, job fairs  Staffing in Richmond now exceeds 990 12
  • 13. A Partnership for Safe Chemical Weapons Destruction A Look Ahead 13  Installation of Rocket Cutting and Rocket Shear Machines  Complete testing and delivery of the Munitions Washout System  Completion of Hydrolysate Storage Area tank installation  Set Munitions Demilitarization Building (MDB) filter banks  Complete MDB structural steel  Enclose Supercritical Water Oxidation Processing Building  Continue construction focus shift from civil/structural to large-scale pipe and electrical commodity installation
  • 14. A Partnership for Safe Chemical Weapons Destruction 14 Questions? For more information about the Blue Grass Chemical Agent-Destruction Pilot Plant project, please contact the Blue Grass Chemical Stockpile Outreach Office at (859) 626-8944 or bgoutreach@iem.com