SlideShare a Scribd company logo
May 14th
2018
PROJECT QUALITY INITIATIVES
HASBAH OFFSHORE GAS FACILITIES INCREMENT – II
BI: 10-01902-002
List of quality initiatives shared and its benefits:
Developmentand Implementation of Quality ManagementDashboard:
Quality Management Dashboard is a status dashboard where the data of all Major Processes
and quality deliverables as per schedule Q and SAEP 1160 requirements are captured at one
place with graphical presentation for easy understanding which is being updated on weekly
basis.
Benefits:
It gives the real time status of all major activities which are as follows:
 Welding Procedure qualification
 Readiness and approval of Quality Procedures
 Status of Receipt Material
 Status of Manpower compliance
 Status of Quality Notification
 PQI trend
 Status of Project Weekly Repair Rate
 Status of Quality Assurance Activities like Focus assessments, Audits, training and KOM
 Status of RFIs
 Quality Deliverables as per Schedule Q.
Implementation of Schedule Q Compliance Check Matrix.
All Schedule Q requirements were mapped Clause by Clause to identify the Gaps between
Schedule Q requirements and existing Yard Quality System. Accordingly, the applicable
System Procedures, Project Procedures, Check sheets and Controls were defined, modified
and implemented. Total of 219 clausal requirements of Schedule Q were identified as
applicable to yard scope which are being complied and monitored on weekly basis.
Benefits:
It helped to meet the requirements of Schedule Q and eliminate the chances of violations
which might cause impact on Project PQI, progress and schedule.
Implementation and developmentof program for readinessmatrixfor each
new activity starting in 30 days.
Readiness matrix is a program which identifies the pre-requisites (Procedure, ITP, WPS,
Skilled Manpower etc...) along with the startup dates against each planned activity. Each
activity is monitored against the day left for the start-up with respect to readiness of all the
pre-requisites. Each approval in any requirement contributes for increment in readiness
score. An alert system is made for the readiness score of each activity vs the days left for
activity startup. This program gives alert in advance about area of concerns which might
cause delay in start of the upcoming activity so that required action can be taken on timely
manner to avoid interruption in the start-up of activity.
Benefits:
As of now, all the activities in the project were started as per the planned schedule with
100% readiness which helped to eliminate major issues in the project. KOM were conducted
on time prior to start of the activities with the help of this quality tool.
Zero punch pointdrive to deliver the facilities with zero punch pointbefore sail
away
Zero punch point drive is a program developed with the aim to deliver the facilities with
zero punch point. ZERO punch point drive will be achieved by Advance reporting & closing of
Punch Points by the project quality team prior to final official walkthroughs, categorizing the
punch points by time limits to accelerate the closeout on timely manners and weekly review
of open punch items. Preliminary walkthroughs for each modules have been planned level
wise on weekly basis. Assurance of program implementation, planning of walkthroughs and
tracking and follow up of punch points will be monitored by Contractor QA Manager and
supervised by Company Inspection representative.
Benefits:
It will help to identify the potential punch points at advance stage and to minimize the work
at offshore.
Implementation of additionalQuality assurance focusassessment:
Apart from the weekly focus assessments, additional QA assessments are being conducted
by Company inspection for ongoing critical activities. Total 57 numbers of QA assessments
are planned during the project construction phase out of which 31 have been conducted so
far.
Benefits:
It helps to verify the compliance to Project quality requirements at activity level and
effectiveness of the Contractor’s Quality System.
Weekly walkthroughsfor verification of equipment’spreservation
requirements:
Company inspection along with contractor conduct weekly walkthroughs dedicated for
verification of equipment preservation. Procedural requirement along with the manufacture
recommendation are mapped in the preservation matrix which is monitored regularly
during the walkthroughs.
Benefits:
It helps to verify the compliance to preservation requirement as per SAMMS &
Manufacturer’s recommendations. As of now, there is no any major violations identified
with respect to preservation of materials. Senior Management from vendor (M/S Lewa) had
appreciated the implementation of preservation system at yard.
In addition to above, following Initiatives were also shared with the Hazira
Team:
 Readiness Verification of Equipment storage facility as per storage area classification like
Enclosed & Climatic, Enclosed Non Climatic Controlled and Open storage.
 Implementation of Dimensional Check sheet for received materials during receiving
inspection.
 Established proactive approach by initiating more number of proactive notification to
avoid violation LBEs

More Related Content

What's hot

Layered process audit
Layered process audit Layered process audit
Layered process audit
The Apprentiice
 
Gas Service Excellence Presentation 20 May 2010 Ms Final
Gas Service Excellence Presentation   20 May 2010   Ms   FinalGas Service Excellence Presentation   20 May 2010   Ms   Final
Gas Service Excellence Presentation 20 May 2010 Ms Final
mseaborn
 
Assessment Executive Summary_DENSO
Assessment Executive Summary_DENSOAssessment Executive Summary_DENSO
Assessment Executive Summary_DENSOLuca Pomero
 
Top gun aerospace website presentation
Top gun aerospace website presentationTop gun aerospace website presentation
Top gun aerospace website presentation
seanzeeeee
 
New Product Development Methods & Metrics
New Product Development Methods & MetricsNew Product Development Methods & Metrics
New Product Development Methods & Metrics
Venkadesh Narayanan
 
Marval Release Management - the political process
Marval Release Management - the political processMarval Release Management - the political process
Marval Release Management - the political process
Marval Software
 
Comissioning & qualification vol.5 (2nd eddition)
Comissioning & qualification vol.5 (2nd eddition)Comissioning & qualification vol.5 (2nd eddition)
Comissioning & qualification vol.5 (2nd eddition)
Ravindra Kushwaha
 
Project Quality Management
 Project Quality Management Project Quality Management
Project Quality ManagementSerdar Temiz
 
Commissioning stage compliance certificate
Commissioning stage compliance certificateCommissioning stage compliance certificate
Commissioning stage compliance certificatemsmk228
 
Softexpert apqp ppap
Softexpert apqp ppapSoftexpert apqp ppap
Softexpert apqp ppap
Khalizan Halid
 
SQF Code Edition 9: What's New Since 8.1 & Tips for Your Conversion Plan
SQF Code Edition 9: What's New Since 8.1 & Tips for Your Conversion PlanSQF Code Edition 9: What's New Since 8.1 & Tips for Your Conversion Plan
SQF Code Edition 9: What's New Since 8.1 & Tips for Your Conversion Plan
SafetyChain Software
 
Donald_L_Loocke_Resume_TEr3
Donald_L_Loocke_Resume_TEr3Donald_L_Loocke_Resume_TEr3
Donald_L_Loocke_Resume_TEr3dloocke
 
Webinar on PMS
Webinar on PMSWebinar on PMS
Webinar on PMS
vaibhavsharma_engg
 
Promotion Flow for Mission Critical Enterprise SW
Promotion Flow for Mission Critical Enterprise SWPromotion Flow for Mission Critical Enterprise SW
Promotion Flow for Mission Critical Enterprise SW
Glen Alleman
 
NS Automotive QSP
NS Automotive QSPNS Automotive QSP
NS Automotive QSPNisarg Shah
 
Luxury Lighting Mfr RMA and Production Process Area Project
Luxury Lighting Mfr RMA and Production Process Area ProjectLuxury Lighting Mfr RMA and Production Process Area Project
Luxury Lighting Mfr RMA and Production Process Area ProjectStevelind
 

What's hot (20)

Layered process audit
Layered process audit Layered process audit
Layered process audit
 
Gas Service Excellence Presentation 20 May 2010 Ms Final
Gas Service Excellence Presentation   20 May 2010   Ms   FinalGas Service Excellence Presentation   20 May 2010   Ms   Final
Gas Service Excellence Presentation 20 May 2010 Ms Final
 
Assessment Executive Summary_DENSO
Assessment Executive Summary_DENSOAssessment Executive Summary_DENSO
Assessment Executive Summary_DENSO
 
Felix Martinez Resume
Felix Martinez Resume Felix Martinez Resume
Felix Martinez Resume
 
Top gun aerospace website presentation
Top gun aerospace website presentationTop gun aerospace website presentation
Top gun aerospace website presentation
 
New Product Development Methods & Metrics
New Product Development Methods & MetricsNew Product Development Methods & Metrics
New Product Development Methods & Metrics
 
Marval Release Management - the political process
Marval Release Management - the political processMarval Release Management - the political process
Marval Release Management - the political process
 
Change control and variations
Change control and variationsChange control and variations
Change control and variations
 
Comissioning & qualification vol.5 (2nd eddition)
Comissioning & qualification vol.5 (2nd eddition)Comissioning & qualification vol.5 (2nd eddition)
Comissioning & qualification vol.5 (2nd eddition)
 
Project Quality Management
 Project Quality Management Project Quality Management
Project Quality Management
 
Commissioning stage compliance certificate
Commissioning stage compliance certificateCommissioning stage compliance certificate
Commissioning stage compliance certificate
 
Softexpert apqp ppap
Softexpert apqp ppapSoftexpert apqp ppap
Softexpert apqp ppap
 
SQF Code Edition 9: What's New Since 8.1 & Tips for Your Conversion Plan
SQF Code Edition 9: What's New Since 8.1 & Tips for Your Conversion PlanSQF Code Edition 9: What's New Since 8.1 & Tips for Your Conversion Plan
SQF Code Edition 9: What's New Since 8.1 & Tips for Your Conversion Plan
 
Sanjeev - cv
Sanjeev - cvSanjeev - cv
Sanjeev - cv
 
Donald_L_Loocke_Resume_TEr3
Donald_L_Loocke_Resume_TEr3Donald_L_Loocke_Resume_TEr3
Donald_L_Loocke_Resume_TEr3
 
Webinar on PMS
Webinar on PMSWebinar on PMS
Webinar on PMS
 
Promotion Flow for Mission Critical Enterprise SW
Promotion Flow for Mission Critical Enterprise SWPromotion Flow for Mission Critical Enterprise SW
Promotion Flow for Mission Critical Enterprise SW
 
NS Automotive QSP
NS Automotive QSPNS Automotive QSP
NS Automotive QSP
 
Sanjeev - cv
Sanjeev - cvSanjeev - cv
Sanjeev - cv
 
Luxury Lighting Mfr RMA and Production Process Area Project
Luxury Lighting Mfr RMA and Production Process Area ProjectLuxury Lighting Mfr RMA and Production Process Area Project
Luxury Lighting Mfr RMA and Production Process Area Project
 

Similar to Project qulaity initiative report

5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider
Olivia Wilson
 
Introduction to software quality assurance by QuontraSolutions
Introduction to software quality assurance by QuontraSolutionsIntroduction to software quality assurance by QuontraSolutions
Introduction to software quality assurance by QuontraSolutions
QUONTRASOLUTIONS
 
Software quality assurance
Software quality assuranceSoftware quality assurance
Software quality assuranceEr. Nancy
 
Introduction To Software Quality Assurance
Introduction To Software Quality AssuranceIntroduction To Software Quality Assurance
Introduction To Software Quality Assurance
ruth_reategui
 
BEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORSBEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORS
Olivia Wilson
 
BEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORSBEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORS
Olivia Wilson
 
In computing, a database is an organized collection of data or a type of data...
In computing, a database is an organized collection of data or a type of data...In computing, a database is an organized collection of data or a type of data...
In computing, a database is an organized collection of data or a type of data...
MugizhanNagendiran
 
presentation quality awareness draft02.pptx
presentation quality awareness draft02.pptxpresentation quality awareness draft02.pptx
presentation quality awareness draft02.pptx
AhmedAltantawi
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
ignitetribes
 
Fmq lqos introduction npi rev 2
Fmq  lqos introduction npi rev 2Fmq  lqos introduction npi rev 2
Fmq lqos introduction npi rev 2
amitsonuksms
 
Chapter 5 Software Quality Assurance-Finalised_BW.ppt
Chapter 5 Software Quality Assurance-Finalised_BW.pptChapter 5 Software Quality Assurance-Finalised_BW.ppt
Chapter 5 Software Quality Assurance-Finalised_BW.ppt
Bule Hora University
 
Test Automation Strategies in a Continuous Delivery Ecosystem
Test Automation Strategies in a Continuous Delivery EcosystemTest Automation Strategies in a Continuous Delivery Ecosystem
Test Automation Strategies in a Continuous Delivery Ecosystem
Cognizant
 
Project management assignment slides
Project management assignment slidesProject management assignment slides
Project management assignment slides
Doreen Yeo
 
5 Great Tips for Improving Your Project QAQC
5 Great Tips for Improving Your Project QAQC5 Great Tips for Improving Your Project QAQC
5 Great Tips for Improving Your Project QAQC
Nico Cottone
 
EPC Construction CQA Program
EPC Construction CQA ProgramEPC Construction CQA Program
EPC Construction CQA ProgramDan Stehling
 
Module 6 qaqc training
Module 6 qaqc trainingModule 6 qaqc training
Module 6 qaqc training
Diaz Susetyo
 

Similar to Project qulaity initiative report (20)

5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider
 
Introduction to software quality assurance by QuontraSolutions
Introduction to software quality assurance by QuontraSolutionsIntroduction to software quality assurance by QuontraSolutions
Introduction to software quality assurance by QuontraSolutions
 
Software quality assurance
Software quality assuranceSoftware quality assurance
Software quality assurance
 
Introduction To Software Quality Assurance
Introduction To Software Quality AssuranceIntroduction To Software Quality Assurance
Introduction To Software Quality Assurance
 
Verification process
Verification processVerification process
Verification process
 
BEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORSBEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORS
 
BEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORSBEST PRACTICE COMMISSIONING FACTORS
BEST PRACTICE COMMISSIONING FACTORS
 
MydhiliVadlamaniCV
MydhiliVadlamaniCVMydhiliVadlamaniCV
MydhiliVadlamaniCV
 
In computing, a database is an organized collection of data or a type of data...
In computing, a database is an organized collection of data or a type of data...In computing, a database is an organized collection of data or a type of data...
In computing, a database is an organized collection of data or a type of data...
 
presentation quality awareness draft02.pptx
presentation quality awareness draft02.pptxpresentation quality awareness draft02.pptx
presentation quality awareness draft02.pptx
 
PM
PMPM
PM
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
CV_Vineet_Kumar
CV_Vineet_KumarCV_Vineet_Kumar
CV_Vineet_Kumar
 
Fmq lqos introduction npi rev 2
Fmq  lqos introduction npi rev 2Fmq  lqos introduction npi rev 2
Fmq lqos introduction npi rev 2
 
Chapter 5 Software Quality Assurance-Finalised_BW.ppt
Chapter 5 Software Quality Assurance-Finalised_BW.pptChapter 5 Software Quality Assurance-Finalised_BW.ppt
Chapter 5 Software Quality Assurance-Finalised_BW.ppt
 
Test Automation Strategies in a Continuous Delivery Ecosystem
Test Automation Strategies in a Continuous Delivery EcosystemTest Automation Strategies in a Continuous Delivery Ecosystem
Test Automation Strategies in a Continuous Delivery Ecosystem
 
Project management assignment slides
Project management assignment slidesProject management assignment slides
Project management assignment slides
 
5 Great Tips for Improving Your Project QAQC
5 Great Tips for Improving Your Project QAQC5 Great Tips for Improving Your Project QAQC
5 Great Tips for Improving Your Project QAQC
 
EPC Construction CQA Program
EPC Construction CQA ProgramEPC Construction CQA Program
EPC Construction CQA Program
 
Module 6 qaqc training
Module 6 qaqc trainingModule 6 qaqc training
Module 6 qaqc training
 

Recently uploaded

Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 

Recently uploaded (20)

Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 

Project qulaity initiative report

  • 1. May 14th 2018 PROJECT QUALITY INITIATIVES HASBAH OFFSHORE GAS FACILITIES INCREMENT – II BI: 10-01902-002
  • 2. List of quality initiatives shared and its benefits: Developmentand Implementation of Quality ManagementDashboard: Quality Management Dashboard is a status dashboard where the data of all Major Processes and quality deliverables as per schedule Q and SAEP 1160 requirements are captured at one place with graphical presentation for easy understanding which is being updated on weekly basis. Benefits: It gives the real time status of all major activities which are as follows:  Welding Procedure qualification  Readiness and approval of Quality Procedures  Status of Receipt Material  Status of Manpower compliance  Status of Quality Notification  PQI trend  Status of Project Weekly Repair Rate  Status of Quality Assurance Activities like Focus assessments, Audits, training and KOM  Status of RFIs  Quality Deliverables as per Schedule Q. Implementation of Schedule Q Compliance Check Matrix. All Schedule Q requirements were mapped Clause by Clause to identify the Gaps between Schedule Q requirements and existing Yard Quality System. Accordingly, the applicable System Procedures, Project Procedures, Check sheets and Controls were defined, modified and implemented. Total of 219 clausal requirements of Schedule Q were identified as applicable to yard scope which are being complied and monitored on weekly basis. Benefits: It helped to meet the requirements of Schedule Q and eliminate the chances of violations which might cause impact on Project PQI, progress and schedule.
  • 3. Implementation and developmentof program for readinessmatrixfor each new activity starting in 30 days. Readiness matrix is a program which identifies the pre-requisites (Procedure, ITP, WPS, Skilled Manpower etc...) along with the startup dates against each planned activity. Each activity is monitored against the day left for the start-up with respect to readiness of all the pre-requisites. Each approval in any requirement contributes for increment in readiness score. An alert system is made for the readiness score of each activity vs the days left for activity startup. This program gives alert in advance about area of concerns which might cause delay in start of the upcoming activity so that required action can be taken on timely manner to avoid interruption in the start-up of activity. Benefits: As of now, all the activities in the project were started as per the planned schedule with 100% readiness which helped to eliminate major issues in the project. KOM were conducted on time prior to start of the activities with the help of this quality tool. Zero punch pointdrive to deliver the facilities with zero punch pointbefore sail away Zero punch point drive is a program developed with the aim to deliver the facilities with zero punch point. ZERO punch point drive will be achieved by Advance reporting & closing of Punch Points by the project quality team prior to final official walkthroughs, categorizing the punch points by time limits to accelerate the closeout on timely manners and weekly review of open punch items. Preliminary walkthroughs for each modules have been planned level wise on weekly basis. Assurance of program implementation, planning of walkthroughs and tracking and follow up of punch points will be monitored by Contractor QA Manager and supervised by Company Inspection representative. Benefits: It will help to identify the potential punch points at advance stage and to minimize the work at offshore.
  • 4. Implementation of additionalQuality assurance focusassessment: Apart from the weekly focus assessments, additional QA assessments are being conducted by Company inspection for ongoing critical activities. Total 57 numbers of QA assessments are planned during the project construction phase out of which 31 have been conducted so far. Benefits: It helps to verify the compliance to Project quality requirements at activity level and effectiveness of the Contractor’s Quality System. Weekly walkthroughsfor verification of equipment’spreservation requirements: Company inspection along with contractor conduct weekly walkthroughs dedicated for verification of equipment preservation. Procedural requirement along with the manufacture recommendation are mapped in the preservation matrix which is monitored regularly during the walkthroughs. Benefits: It helps to verify the compliance to preservation requirement as per SAMMS & Manufacturer’s recommendations. As of now, there is no any major violations identified with respect to preservation of materials. Senior Management from vendor (M/S Lewa) had appreciated the implementation of preservation system at yard. In addition to above, following Initiatives were also shared with the Hazira Team:  Readiness Verification of Equipment storage facility as per storage area classification like Enclosed & Climatic, Enclosed Non Climatic Controlled and Open storage.  Implementation of Dimensional Check sheet for received materials during receiving inspection.  Established proactive approach by initiating more number of proactive notification to avoid violation LBEs