The document outlines a plan to rehabilitate an existing aquaculture facility by upgrading its technology systems in order to conduct future feasibility studies on farming Australian red claw crayfish. The project will receive funding from the Nebraska Soybean Board and partner with the University of Nebraska-Lincoln Agriculture Research and Development Center. The plan details the scope, schedule, budget, resources, communications, risks, and procurement needs for the rehabilitation and technology upgrade work.
How Bell Energy can help you be a Sustainable and Profitable OrganizationChandrashekhar Kulkarni
Welcome to Bell Energy Corporate Presentation where we showcase our value added services and our resources that will help your company manage Process Safety, Health Safety & Environment, Asset Integrity, Corporate Governance and Sustainability.
This presentation was delivered by Bell Energy as part of training program in 2013. It provides the reader, basic to intermediate level of information on the use of Bowties for managing Hazards & Effects. Bowties can be used by any industry whether they are Oil & Gas, Finance, Banks, Aviation, Power, Nuclear, Construction, Infrastructure. To know more about bowties, please visit www.bell-energy.com or contact us on uaeoffice@bell-energy.net
How to optimize ddc systems to save energy in hospitalsPulse Energy
Hospitals and health care facilities are under increasing pressure to save costs by improving their energy performance. Implementing a plan to check, correct, and optimize their facility Direct Digital Control (DDC) systems can generate significant energy savings for very little cost.
This webinar, presented by Pulse Energy and Nancy Myers, Energy Manager for the Vancouver Island Health Authority (VIHA), was on generating savings in health care facilities DDC system optimization. Nancy’s presentation covered:
- her team's plan and process for investigating and optimizing DDC systems
- examples of energy wasting problems that can occur in hospital DDCs
- an action plan to maintain the savings going forward
Asset Integrity Management for purpose-built FPSOs and subsea system facilitiesAdvisian
Abe Nezamian discusses various aspects of ageing related to FPSOs (floating facilities for production, storage and offtake) and outlines the required procedures for maintaining structural integrity.
How Bell Energy can help you be a Sustainable and Profitable OrganizationChandrashekhar Kulkarni
Welcome to Bell Energy Corporate Presentation where we showcase our value added services and our resources that will help your company manage Process Safety, Health Safety & Environment, Asset Integrity, Corporate Governance and Sustainability.
This presentation was delivered by Bell Energy as part of training program in 2013. It provides the reader, basic to intermediate level of information on the use of Bowties for managing Hazards & Effects. Bowties can be used by any industry whether they are Oil & Gas, Finance, Banks, Aviation, Power, Nuclear, Construction, Infrastructure. To know more about bowties, please visit www.bell-energy.com or contact us on uaeoffice@bell-energy.net
How to optimize ddc systems to save energy in hospitalsPulse Energy
Hospitals and health care facilities are under increasing pressure to save costs by improving their energy performance. Implementing a plan to check, correct, and optimize their facility Direct Digital Control (DDC) systems can generate significant energy savings for very little cost.
This webinar, presented by Pulse Energy and Nancy Myers, Energy Manager for the Vancouver Island Health Authority (VIHA), was on generating savings in health care facilities DDC system optimization. Nancy’s presentation covered:
- her team's plan and process for investigating and optimizing DDC systems
- examples of energy wasting problems that can occur in hospital DDCs
- an action plan to maintain the savings going forward
Asset Integrity Management for purpose-built FPSOs and subsea system facilitiesAdvisian
Abe Nezamian discusses various aspects of ageing related to FPSOs (floating facilities for production, storage and offtake) and outlines the required procedures for maintaining structural integrity.
Overcoming the Challenges of Large Capital Programs/ProjectsScottMadden, Inc.
Effective capital program/project delivery is a critical competency for any electric utility to achieve high performance. However, project scope creep, schedule delays, and cost increases have become the rule rather than the exception. Over the past 10 years, the electric utility industry has seen large demands on its projects and construction management organizations to ensure compliance with a number of concerns. Large capital programs/projects come with a variety of complicated planning, implementation, and workforce/vendor management challenges. Using EPU projects as an example, we will provide you with ways to overcome these challenges for any large capital program/project. This article can help you successfully plan, deliver, and control/monitor your large capital program/project.
ScottMadden can help you successfully plan, deliver, and control/monitor your large capital program/project. Contact us to discuss any questions you may have.
ScottMadden’s Capital Program Assessment examines how the capital program is implemented with a look at the PMO and a review of the performance reporting and tools in place.
The uses of automation in the drilling process are expanding and are typically resulting in improved drilling performance. However, many of these projects struggle in the initial stages, often trying to overcome a common set of hurdles. Many of these hurdles are not technical challenges, but instead are related to people issues and the methods for implementing the solutions. This presentation covers the basics of drilling automation and describes the problems and solutions that have been found to improve the startup success for drilling automation. IDEA TO TAKE AWAY - For automation to be successful, the key users, especially the driller, must be involved in every step of design and implementation.
At Effluent Treatment Innovations our Wastewater Treatment Consultancy Service approaches wastewater treatment through a unique process of Risk Assessment from the water source to the effluent discharge and then provides the client with a detailed Risk Management Plan to reach and maintain consistent discharge Compliance.
Overcoming the Challenges of Large Capital Programs/ProjectsScottMadden, Inc.
Effective capital program/project delivery is a critical competency for any electric utility to achieve high performance. However, project scope creep, schedule delays, and cost increases have become the rule rather than the exception. Over the past 10 years, the electric utility industry has seen large demands on its projects and construction management organizations to ensure compliance with a number of concerns. Large capital programs/projects come with a variety of complicated planning, implementation, and workforce/vendor management challenges. Using EPU projects as an example, we will provide you with ways to overcome these challenges for any large capital program/project. This article can help you successfully plan, deliver, and control/monitor your large capital program/project.
ScottMadden can help you successfully plan, deliver, and control/monitor your large capital program/project. Contact us to discuss any questions you may have.
ScottMadden’s Capital Program Assessment examines how the capital program is implemented with a look at the PMO and a review of the performance reporting and tools in place.
The uses of automation in the drilling process are expanding and are typically resulting in improved drilling performance. However, many of these projects struggle in the initial stages, often trying to overcome a common set of hurdles. Many of these hurdles are not technical challenges, but instead are related to people issues and the methods for implementing the solutions. This presentation covers the basics of drilling automation and describes the problems and solutions that have been found to improve the startup success for drilling automation. IDEA TO TAKE AWAY - For automation to be successful, the key users, especially the driller, must be involved in every step of design and implementation.
At Effluent Treatment Innovations our Wastewater Treatment Consultancy Service approaches wastewater treatment through a unique process of Risk Assessment from the water source to the effluent discharge and then provides the client with a detailed Risk Management Plan to reach and maintain consistent discharge Compliance.
Presentatie van Ilse Godtschalk tijdens het Cross Media Café 'Video Formats' op dinsdag 2 februari 2016.
Meer informatie? http://www.immovator.nl/agenda/cross-media-cafe-video-formats
Trabajo realizado por: -David Martínez Rodríguez- Clara Sirvent Torregrosa- Manuel Soriano Gil- Para la asignatura 'Teoria de la Arquitectura' en la que se expone la obra de Antonio Maciá Mateu y Jorge Soliva Gasa. Arquitectura de la Universidad de Alicante.
Vaidotas Rutkauskas, el. parduotuvės 1A.lt vadovas konferencijoje "El. komercija '14" skaitė pranešimą apie 1A.lt sėkmės istoriją.
Konferencijos tinklalapis: http://e-komercija.eu/
Rytis Laurinavičius, Soundest direktorius el. komercijos konferencijoje "E-komercija '14" skaitė pranešimą El. pašto rinkodaros tendencijos.
Konferencijos tinklalapis: http://e-komercija.eu/
EN ESTE POWERPOINT VEREMOS LOS MOVIMIENTOS DE UN GESTO DEPORTIVO , EL CUAL TE EDUCARA SOBRE LOS MÚSCULOS AGONISTAS , SINERGISTAS , Y ANTAGONISTAS DE LOS MOVIMIENTOS DE UN CHUTE DE FUTBOL
Curso de Musculación y entrenamiento personal.
Lic. Javier Mazzone.
SE PERMITE Y ALIENTA LA REPRODUCCIÓN PARCIAL O TOTAL DE ESTE CONTENIDO CITANDO AL AUTOR Y A "PURO ENTRENAMIENTO"
Prezentacija apie prenumeratorių pritraukimo kampanijas el. verslams. Buvo naudota Webakademijos ir Webseminarų laidoje, kur diskutavo Webakademijos vadovas Vladas Sapranavičius ir Soundest vadovas Rytis Laurinavičius.
Daugiau apie šią laidą ir įrašą rasite laidos puslapyje: http://www.webconsulting.lt/naujienlaiskio-prenumeratoriu-pritraukimas-webinaro-irasas/
Scheme for the construction of water channelsmirzaqadeer
we are giving only idea for making water channel for poor less un economical area for different counties where people need water for drinking we present presentation in univsty CIIT
Incorporating a predictive maintenance strategy has been proven to provide savings. Learn how to use your pressure and temperature gauges as part of your initiatives.
Danh sách kiểm tra sản xuất cho công ty khởi nghiệp công nghệ sinh học
Xem thêm các tài liệu khác trên kênh của Công ty Cổ phần Tư vấn Thiết kế GMP EU.
Monetizing Risks - A Prioritization & Optimization SolutionBlack & Veatch
This presentation explains a budget prioritization process and model that assists utilities with managing the important balance of asset/system performance, cost, and risk. Originally presentation at Texas Water 2015. Learn more at www.bv.com
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docxsmile790243
Leadership Theories
Write a 700- to 1,050-word paper that addresses the following:
· Describe a current event within your health care organization that requires leadership attention.
· From your readings this week, apply a leadership theory that most closely represents your approach to addressing the situation.
· Explain why your selection would accommodate a desirable outcome.
Format your paper according to APA guidelines.
Plagiarism ready.
Add the highlighted information to the project.
•Schedule PERT Analysis
•Schedule reduction (project crash) ◦Including Recommendations to reduce the schedule length and calculate impact on the budget (include examples of outsourcing with applicable example contracts)
•Resource loading and leveling
•Schedule baseline
•Budget management plan ◦From Plan Cost Management, Section 7 of PMBOK® Guide 5 (Submitted in WBS 6)
•Project Budget
•Including time phased cash flow plan
•Earned Value Analysis and Report
Project Objective:
This project will transition the SMS LAB Engineering helicopter production line from its current location in Barstow, CA to a newer and more centralized location, just south collocated with a local regional airport in Aerial Acres, CA. The move will be completed in 6 weeks (42 calendar days), safely and with a cost not to exceed $1.2 million.
Rationale for Project:
There is a business need to move the helicopter production line from its current facility that is 50 miles from the flight test center to a newer location more centralized to the overall organization’s operations. Once the new location is operational there will be a realized savings in lease costs, reduced risk, and reduced transportation costs of moving the helicopters to the flight test center.
Currently the lease for the building where the production line is located is ending and the organization has decided to not renew due to budgetary constraints and have opted to centralize operations.
Stakeholders Analysis:
The stakeholders that are involved with the movement of the helicopter production line from the Barstow facility to the new Aerial Acres facility are spread amongst the entire company. The stakeholders will be evaluated and classified using a power/influence grid method. It is important to be able to keep all participant levels of the project informed and with this grid evaluation, status updates and meetings can be tailored to the requirements of that specific group of stakeholders.
As depicted in the grid evaluation there are four main groups of stakeholders. All have different levels of power and participation/influence over the execution and overall outcome of the project. Upper management has high power but not as much influence as the middle managers because the middle managers will be actually working hands on with the project move while upper management will just be given updates as the project pr ...
2. Executive Summary
NOAA: 2011 US edible fishery imports valued at 16.6 Billion
Harvard Study: 1/3 US population eats seafood once per week
Ocean fishery levels will plateau and eventually decline
One solution for providing the US Population with fresh edible fish:
Indoor Aquaculture utilizing existing, empty livestock building
Previous project attempted this with Freshwater Prawns at the University of
Nebraska Lincoln-Agriculture Research Development Center (UNL-ARDC)
Red Claw Aquatics (RCA) has an interest in using the existing facility for
future feasibility studies with Australian Red Clawed Crayfish
3. Executive Summary
Red Claw Aquatics (RCA) received a
grant from Nebraska Soybean Board
RCA has formed a partnership with the
University of Nebraska Lincoln-
Agriculture Research and Development
Center (UNL-ARDC)
Rehabilitate and Upgrade the
Technology in an existing facility on the
grounds of the UNL-ARDC
This project plan is for the Rehab and
Tech. Upgrades only, it will not cover
costs for feasibility studies
6. Communications Management
Stakeholders
Create Stakeholder Register
9 individual stakeholders identified in project
Determine their influence/interest
Establish Issue Log & Change Request Log to track stakeholder interaction
Performance Reporting
Performance metrics from the other sections of the project management plan
Project Manager will update them on a weekly basis to track project progress vs baseline
Performance reports will track: schedule, cost, risk
7. Communications Management
Communications Plan
Work with stakeholders early on to understand their preferences for communication type &
frequency
Create a Communications Schedule detailing type, frequency, and responsibility for
transmitting information
Sample of
Communications
Plan
8. Scope Management Plan
Establishes the work required to rehabilitate the facility
Describes the project assumptions, constraints, and exclusions
Scope was defined through site visit , consultation with stakeholders, research
Key deliverables
Describes the project phases , deliverables, and acceptance criteria
9. Scope Management Plan
Includes aWork Breakdown Structure for the project phases
Includes aWBS Dictionary
Establishes scope verification tasks
Establishes scope control process
10. Human Resources Management
Developed using theWBS and stakeholder register
Assigns team member roles
Organization Chart
11. Outlines team member responsibilities forWBS work packages.
Establishes staffing management mechanisms and the chain of command.
Provides a resource calendar
Human Resources Management
12. Human Resources Management
Clarifies human resource employment rules for team members
Provides a protocol for staffing release
13. Time Management Plan
Schedule developed by breaking down work packages inWBS, usingWBS Dictionary
and creating activity list
Provides baseline project schedule
Includes methods used to measure, monitor and control schedule
Indicates parameters for taking corrective action
Considers lead times needed to procure equipment
Includes lag times for potential unforeseen conditions for certain work packages based
on risk assessment of schedule activities
Establishes clear process for change management
15. Cost Management Plan
Developed using bottom up estimating process
Established by utilizing schedule,WBS andWBS Dictionary
Includes cost to rehabilitate and upgrade facility, equipment and salaries
Provides project budget baseline
Management Reserve and ConstructionContingency
Outlines processes used to measure, monitor and control budget
Monthly project expenditures
Establishes clear process for change management
16.
17. Quality will be measured in the following ways:
Physical work preformed
Comparing the actual schedule or budget to the respective baselines
Content and dissemination or reports
Quality Management Plan Outlines:
How Quality will be determined
How Work will be accepted
Necessary actions required by the Project Manager and project team
Quality is the Ultimate Responsibility of the Project Manager!!!!
Quality ManagementQuality Planning
18. Quality Management
Quality Management Control
Quality Checklist Document
Must be completed by the PM, UNL-ARDC, and Matt Kaminski for each work package
prior to work being formally accepted
Checklist Comments Document
Any comments for acceptance or denial of work will be documented
Status Reports
Monthly reports generated by the PM updating the NBS status of the Budget and Schedule
Weekly Meetings
PM, UNL-ARDC, Matt Kaminski to discuss Schedule and Budget, and if any changed need to be
made to the project management plan.
19. Risk Management
Risk Management Planning
Risk Identification
Risk Assessment – Qualitative
Plan Risk Response
Monitor and Control Risk
21. Risk Register
Risk Risk Category Probability Impact Risk Score
Risk
Ranking
Risk Response Trigger Risk Owner
Programming is incorrect for PLC upon system install and turn up Technical 8 9 72 1
Contact Vendor for programming fixwith report of
what is not working correctly in the current
programming
PLC does not function correctly during testing and
install based on programming requirements
provided to Vendor.
Vendor
Contractors (Carpenters, Electricians, or Plumbers) are unavailble to start
project on time
External 7 8 56 2
Work with UNL-ARDC to determine the new
availability and negotiate with them for outside
resources if they are not available.
UNL-ARDC reports that their staff will not be
available during the agreed upon schedule
UNL-ARDC
Source company for custom PLC program is unable to deliver within the
specified project timelines
External 6 9 54 3
Work with contigency Vendors to source the
required PLC programming
Source Vendor reports that they are unable to
deliver in the agreed upon trameframe
Project Manager
System can't be calibrated because of faulty or incorrectly spec'd system
component
Technical 5 9 45 4
Troubleshoot with assistance of Vendor to isolate
and replace the faulty or incorrect component
System continues to fail calibration on turn up Project Manager
Computer systems are shorted out because of dirty power at the facility External 7 6 42 5
Verify that the facility has ten adequte amount of
protected, clean surge protected power as
required.
Computer do not power on and the breaker and
power has been verified as functional
Project Manager
Damage to other electronics due to lack of a surge preventer/ protector External 6 7 42 6
Verify that the facility has ten adequte amount of
protected, clean surge protected power as
required.
Surge sensitive equipment begins to either
malfunction or perform at less then optimal specs
Project Manager
Force Majeure Event - e.g. Tornado destroying the building, lightning strike,
etc
External 4 10 40 7
verify that all items are secure inside of facilty,
critical items should be secured in a tornado
shelter is available.
Severe Weather Report Watch for the Mead, NE
area
http://www.disastercenter.com/tornado/rank.htm
Project Manager
Risk Identification Risk ResponseQualitative Rating
Sample of Risk
Register
23. Procurement Component and Supply listing
Item to be purchased Area of Use Amount needed Spares Approx. $$ Amount Total Cost WBS # Preferred Vendor
Tank Liners Grow Out 8 rolls 20‘x25’ 1 roll 20‘x25’ $449.69 $4,047.21 3.1.1.1 Bestnest.com
Heaters for Tanks Grow Out 8 1 $300.00 $2,700.00 3.1.1.2 Lowes
Pumps for Heaters Grow Out 8 1 $180.75 $1,626.75 3.1.1.2 Pentair
Pumps for Bio. Filters Grow Out 8 1 $180.75 $1,626.75 3.1.1.3 Pentair
Sand Filter Grow Out 1 0 $1,000.00 $1,000.00 3.1.1.6 Pentair
Ceiling Fans and controls Grow Out 4 0 $250.00 $1,000.00 3.1.1.7 Farmtek.com
Carpenters time for install (HR) Grow Out 0 $50.00 $0.00 3.1.1.7 UNL-ARDC
Electricians time to wire (HR) Grow Out 0 $50.00 $0.00 3.1.1.7 UNL-ARDC
PLC System Grow Out 1 0 $8,000.00 $8,000.00 3.3 3E
Touch Screen Grow Out 1 0 $4,600.00 $4,600.00 3.3.1 3E
Computer for Office Office Area 2 0 $0.00 3.3.1
Programming TIme (HR) Grow Out 120 10 $100.00 $13,000.00 3.3 3E
Water Quality Needs $0.00
Oxygen/Temp Probes Grow Out 8 2 $597.00 $5,970.00 3.3.1.1 Pentair
Ph Probes Grow Out 8 2 $468.00 $4,680.00 3.3.1.1 Pentair
Signal Wire # of ft Grow Out 900 100 $2.91 $2,910.00 3.3.1.2 Pentair
Heater Timer components Grow Out 8 $0.00 3.3.1.1 3E
Auto Feeder Needs $0.00
7.5” Vibrating Feeders Grow Out 16 2 $143.80 $2,588.40 3.3.2.1 Pentair
Copier/Scanner/Fax Office Area 1 0 $200.00 $200.00 3.4.2 Office Depot
General Office Supplies Office Area 1 0 $300.00 $300.00 3.4.4 MYHead
Shop Tools Shop Area 1 0 $2,500.00 $2,500.00 3.5.2 My Head
Generator and switch Entire Facility 1 0 $3,500.00 $3,500.00 2.1.2.2, 3.6
Carpenters time for install (HR) Entire Facility 0 $50.00 UNL-ARDC
Electricians time to wire (HR) Entire Facility 0 $50.00 UNL-ARDC
Total $60,249.11