ID Task Name Duration Start Finish
1 Solar PV Project-10 MW 120 days Tue 4/1/14 Tue 7/29/14
2 Site mobilization 2 days Tue 4/1/14 Wed 4/2/14
3 Array Area and General Works 110 days Sat 4/5/14 Wed 7/23/14
4 Civil Works 93 days Sat 4/5/14 Sun 7/6/14
5 Site Levelling and Grading 15 days Sat 4/5/14 Sat 4/19/14
6 Marking and Construction of Boundary Wall 30 days Tue 4/15/14 Wed 5/14/14
7 Foundation and Installation of Main Entry Gate 5 days Fri 4/18/14 Tue 4/22/14
8 Foundation and Construction of Security Cabin 5 days Fri 4/18/14 Tue 4/22/14
9 Construction of Internal Roads 5 days Tue 4/22/14 Sat 4/26/14
10 Foundation Marking for Structures 5 days Mon 4/21/14 Fri 4/25/14
11 Excavation for Structure Foundation 20 days Tue 4/22/14 Sun 5/11/14
12 Module Mounting Structure Casting 30 days Wed 4/23/14 Thu 5/22/14
13 String Monitoring Box Foundation 5 days Sat 5/3/14 Wed 5/7/14
14 Cable trench 7 days Fri 5/23/14 Thu 5/29/14
15 Construction of Water Collection Tank 10 days Fri 5/23/14 Sun 6/1/14
16 Construction of Drainage system 30 days Tue 5/27/14 Wed 6/25/14
17 Borewell works 3 days Fri 5/23/14 Sun 5/25/14
18 Lightening Arrester Foundation 5 days Sun 6/22/14 Thu 6/26/14
19 External Lighting Foundation 15 days Sun 6/22/14 Sun 7/6/14
20 CCTV Camera Foundation 5 days Sun 6/22/14 Thu 6/26/14
21 Earth Pit Works 5 days Thu 6/12/14 Mon 6/16/14
22 Electrical Works 97 days Thu 4/17/14 Wed 7/23/14
23 Structure 57 days Thu 4/17/14 Fri 6/13/14
24 Purchase Order for Structure 0 days Thu 4/17/14 Thu 4/17/14
25 Payment for Structure 0 days Thu 4/24/14 Thu 4/24/14
26 Receiving of Structure 25 days Fri 4/25/14 Mon 5/19/14
27 Installation of Structure 15 days Fri 5/30/14 Fri 6/13/14
28 PV Module 52 days Fri 4/25/14 Sun 6/15/14
29 Purchase Order for PV Module 0 days Fri 4/25/14 Fri 4/25/14
30 Payment for PV Module 7 days Fri 4/25/14 Fri 5/2/14
31 Receiving of PV Module 30 days Fri 5/2/14 Sun 6/1/14
32 Installation of PV Module 15 days Sun 6/1/14 Sun 6/15/14
33 String Monitoring Box 41 days Mon 4/21/14 Sat 5/31/14
34 Purchase Order for SMB 0 days Mon 4/21/14 Mon 4/21/14
35 Payment for SMB 7 days Mon 4/21/14 Mon 4/28/14
36 Receiving of String Monitoring Box 30 days Mon 4/28/14 Wed 5/28/14
37 Installation of String Monitoring Box 4 days Wed 5/28/14 Sat 5/31/14
38 Inverter 69 days Sat 4/19/14 Thu 6/26/14
39 Purchase Order for Inverter 0 days Sat 4/19/14 Sat 4/19/14
40 Payment for Inverter 7 days Sat 4/19/14 Sat 4/26/14
41 Receiving of Inverter 60 days Sat 4/26/14 Wed 6/25/14
42 Installation of Inverter 2 days Wed 6/25/14 Thu 6/26/14
43 DC Cable 64 days Tue 4/29/14 Tue 7/1/14
44 Purchase Order for DC Cable 0 days Tue 4/29/14 Tue 4/29/14
45 Payment for DC Cable 7 days Tue 4/29/14 Tue 5/6/14
46 Receiving of DC Cable 45 days Tue 5/6/14 Fri 6/20/14
47 Laying of DC Cable 7 days Fri 6/20/14 Fri 6/27/14
48 Termination of DC Cable 5 days Fri 6/27/14 Tue 7/1/14
49 OFC 60 days Thu 5/1/14 Sun 6/29/14
50 Purchase Order for OFC 0 days Thu 5/1/14 Thu 5/1/14
51 Payment for OFC 7 days Thu 5/1/14 Thu 5/8/14
52 Receiving of OFC 45 days Thu 5/8/14 Sun 6/22/14
53 Laying of OFC 5 days Sun 6/22/14 Fri 6/27/14
54 Termination of OFC 3 days Fri 6/27/14 Sun 6/29/14
55 CCTV SYSTEM 40 days Sat 5/31/14 Wed 7/9/14
56 Purchase Order for CCTV 0 days Sat 5/31/14 Sat 5/31/14
57 Payment for CCTV 7 days Sat 5/31/14 Sat 6/7/14
58 Receiving of CCTV 30 days Sat 6/7/14 Mon 7/7/14
59 Installation of CCTV 3 days Mon 7/7/14 Wed 7/9/14
60 Lightening Arrestor 41 days Sat 5/31/14 Thu 7/10/14
61 Purchase order for Lightening Arrestor 0 days Sat 5/31/14 Sat 5/31/14
62 Payment for Lightening Arrestor 7 days Sat 5/31/14 Sat 6/7/14
63 Receiving of Lightening Arrestor 30 days Sat 6/7/14 Mon 7/7/14
64 Installation of Lightening Arrestor 4 days Mon 7/7/14 Thu 7/10/14
65 SCADA System 72 days Tue 5/13/14 Wed 7/23/14
66 Purchase Order for SCADA System 0 days Tue 5/13/14 Tue 5/13/14
67 Payment for SCADA System 7 days Tue 5/13/14 Tue 5/20/14
68 Receiving of SCADA 60 days Tue 5/20/14 Sat 7/19/14
/1 4/2
4/5 4/19
4/15 5/14
4/18 4/22
4/18 4/22
4/22 4/26
4/21 4/25
4/22 5/11
4/23 5/22
5/3 5/7
5/23 5/29
5/23 6/1
5/27 6/25
5/23 5/25
6/22 6/26
6/22 7/6
6/22 6/26
6/12 6/16
4/17
4/24
4/25 5/19
5/30 6/13
4/25
4/25 5/2
5/2 6/1
6/1 6/15
4/21
4/21 4/28
4/28 5/28
5/28 5/31
4/19
4/19 4/26
4/26 6/25
6/25 6/26
4/29
4/29 5/6
5/6 6/20
6/20 6/27
6/27 7/1
5/1
5/1 5/8
5/8 6/22
6/22 6/27
6/27 6/29
5/31
5/31 6/7
6/7 7/7
7/7 7/9
5/31
5/31 6/7
6/7 7/7
7/7 7/10
5/13
5/13 5/20
5/20 7/19
30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28
April 2014 May 2014 June 2014 July 2014
Task
Progress
Milestone
Summary
Rolled Up Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Deadline
Page 1
Project: Template PIS
Date: Wed 3/19/14
ID Task Name Duration Start Finish
69 Installation and Termination of SCADA system 5 days Sat 7/19/14 Wed 7/23/14
70 External Lighting 57 days Wed 5/21/14 Wed 7/16/14
71 Purchase Order for Poles and Lights 0 days Wed 5/21/14 Wed 5/21/14
72 Payment for Lighting System 7 days Wed 5/21/14 Wed 5/28/14
73 Receiving of Lighting System 40 days Wed 5/28/14 Mon 7/7/14
74 Installation and Termination of Lighting System 10 days Mon 7/7/14 Wed 7/16/14
75 Array Earthing 57 days Sun 5/18/14 Sun 7/13/14
76 Purchase Order for Earthing Equipments 0 days Sun 5/18/14 Sun 5/18/14
77 Payment for Earthing Equipments 7 days Sun 5/18/14 Sun 5/25/14
78 Receiving of Earthing Equipments 40 days Sun 5/25/14 Fri 7/4/14
79 Array Earthing Installation and Connection 10 days Fri 7/4/14 Sun 7/13/14
80 Main Control Room & Substation 86 days Thu 4/24/14 Fri 7/18/14
81 Civil Work in MCR & Substation 60 days Sat 4/26/14 Tue 6/24/14
82 Marking 2 days Sat 4/26/14 Sun 4/27/14
83 Excavation 3 days Mon 4/28/14 Wed 4/30/14
84 RCC Foundation 20 days Thu 5/1/14 Tue 5/20/14
85 Brick work 15 days Wed 5/21/14 Wed 6/4/14
86 Internal Plaster 7 days Thu 6/5/14 Wed 6/11/14
87 Flooring & Trenching 7 days Thu 6/12/14 Wed 6/18/14
88 Windows & Doors Fixing 7 days Thu 6/12/14 Wed 6/18/14
89 Painting work 7 days Thu 6/12/14 Wed 6/18/14
90 Finishing work of Substation Building 10 days Sun 6/15/14 Tue 6/24/14
91 Power and Aux. Transformer Foundation 15 days Tue 5/6/14 Tue 5/20/14
92 Switch Yard Earthing Mat Construction 7 days Fri 5/16/14 Thu 5/22/14
93 Switch Yard Equipment Foundation 15 days Fri 5/23/14 Fri 6/6/14
94 Foundation for Transmission Towers 30 days Fri 5/23/14 Sat 6/21/14
95 Electrical Works 86 days Thu 4/24/14 Fri 7/18/14
96 Transformers(Power and Aux.) 72 days Thu 4/24/14 Fri 7/4/14
97 Purchase Order for Transformer 0 days Thu 4/24/14 Thu 4/24/14
98 Payment for Transformer 7 days Thu 4/24/14 Thu 5/1/14
99 Receiving of Transformer 60 days Thu 5/1/14 Mon 6/30/14
100 Installation of Transformer 5 days Mon 6/30/14 Fri 7/4/14
101 33 kV bay station 73 days Tue 4/29/14 Thu 7/10/14
102 Purchase Order for VCB,Conductors,Isolator,CT,PT,Structure2 days Tue 4/29/14 Thu 5/1/14
103 Payment for VCB,Conductors,Isolator,CT,PT,Structure7 days Thu 5/1/14 Thu 5/8/14
104 Receiving of Equipments 50 days Thu 5/8/14 Fri 6/27/14
105 Installation of Equipments 7 days Fri 6/27/14 Thu 7/3/14
106 Termination of Conductors 7 days Fri 7/4/14 Thu 7/10/14
107 HT Panels 61 days Fri 5/9/14 Tue 7/8/14
108 Purchase Order for HT Panels 0 days Fri 5/9/14 Fri 5/9/14
109 Payment for HT Panels 7 days Fri 5/9/14 Fri 5/16/14
110 Receiving of HT Panels 50 days Fri 5/16/14 Sat 7/5/14
111 Installation of HT Panels 4 days Sat 7/5/14 Tue 7/8/14
112 LT Panels 61 days Fri 5/9/14 Tue 7/8/14
113 Purchase Order for LT Panels 0 days Fri 5/9/14 Fri 5/9/14
114 Payment for LT Panels 7 days Fri 5/9/14 Fri 5/16/14
115 Receiving of LT Panels 50 days Fri 5/16/14 Sat 7/5/14
116 Installation of LT Panels 4 days Sat 7/5/14 Tue 7/8/14
117 LT Cable 72 days Sat 5/3/14 Sun 7/13/14
118 Purchase Order for LT Cable 0 days Sat 5/3/14 Sat 5/3/14
119 Payment for LT Cable 7 days Sat 5/3/14 Sat 5/10/14
120 Receiving of LT Cable 50 days Sat 5/10/14 Sun 6/29/14
121 Laying of LT Cable 5 days Sun 6/29/14 Thu 7/3/14
122 Terination of LT Cable 5 days Wed 7/9/14 Sun 7/13/14
123 HT Cable & Conductors 70 days Mon 5/5/14 Sun 7/13/14
124 Purchase Order for HT Cable 0 days Mon 5/5/14 Mon 5/5/14
125 Payment for HT Cable 7 days Mon 5/5/14 Mon 5/12/14
126 Receiving of HT Cables 50 days Mon 5/12/14 Tue 7/1/14
127 Laying of HT Cable 5 days Tue 7/1/14 Sat 7/5/14
128 Termination of HT Cable 5 days Wed 7/9/14 Sun 7/13/14
129 Control Cable 63 days Sat 5/10/14 Fri 7/11/14
130 Purchase Order for Control Cable 0 days Sat 5/10/14 Sat 5/10/14
131 Payment for Control Cable 7 days Sat 5/10/14 Sat 5/17/14
132 Receiving of Control Cables 45 days Sat 5/17/14 Tue 7/1/14
133 Laying of Control Cable 4 days Tue 7/1/14 Fri 7/4/14
134 Termination of Control Cable 3 days Wed 7/9/14 Fri 7/11/14
135 Lightening Protection System 32 days Wed 5/21/14 Sat 6/21/14
136 Purchase Order for LA 0 days Wed 5/21/14 Wed 5/21/14
7/19 7/23
5/21
5/21 5/28
5/28 7/7
7/7 7/16
5/18
5/18 5/25
5/25 7/4
7/4 7/13
4/26 4/27
4/28 4/30
5/1 5/20
5/21 6/4
6/5 6/11
6/12 6/18
6/12 6/18
6/12 6/18
6/15 6/24
5/6 5/20
5/16 5/22
5/23 6/6
5/23 6/21
4/24
4/24 5/1
5/1 6/30
6/30 7/4
4/29 5/1
5/1 5/8
5/8 6/27
6/27 7/3
7/4 7/10
5/9
5/9 5/16
5/16 7/5
7/5 7/8
5/9
5/9 5/16
5/16 7/5
7/5 7/8
5/3
5/3 5/10
5/10 6/29
6/29 7/3
7/9 7/13
5/5
5/5 5/12
5/12 7/1
7/1 7/5
7/9 7/13
5/10
5/10 5/17
5/17 7/1
7/1 7/4
7/9 7/11
5/21
30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28
April 2014 May 2014 June 2014 July 2014
Task
Progress
Milestone
Summary
Rolled Up Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Deadline
Page 2
Project: Template PIS
Date: Wed 3/19/14
ID Task Name Duration Start Finish
137 Payment for LA 7 days Wed 5/21/14 Wed 5/28/14
138 Receiving of LA 20 days Wed 5/28/14 Tue 6/17/14
139 Installation of LA 5 days Tue 6/17/14 Sat 6/21/14
140 Battery System 57 days Fri 5/9/14 Fri 7/4/14
141 Purchase Order for Battery Bank 0 days Fri 5/9/14 Fri 5/9/14
142 Payment for Battery Bank 7 days Fri 5/9/14 Fri 5/16/14
143 Receiving of Battery Bank 45 days Fri 5/16/14 Mon 6/30/14
144 Installation of Battery Bank 5 days Mon 6/30/14 Fri 7/4/14
145 Switch Yard Earthing 30 days Sat 4/26/14 Sun 5/25/14
146 Purchase Order for Earthing Equipments 0 days Sat 4/26/14 Sat 4/26/14
147 Payment for Earthing Equipments 7 days Sat 4/26/14 Sat 5/3/14
148 Receiving of Earthing Equipments 20 days Sat 5/3/14 Fri 5/23/14
149 Installation and Connection 3 days Fri 5/23/14 Sun 5/25/14
150 Internal Lightning System 42 days Mon 5/26/14 Sun 7/6/14
151 Purchase Order for Poles and Lights 0 days Mon 5/26/14 Mon 5/26/14
152 Payment for Lighting System 7 days Mon 5/26/14 Mon 6/2/14
153 Receiving of Lighting System 30 days Mon 6/2/14 Wed 7/2/14
154 Installation and Termination of Lighting System 5 days Wed 7/2/14 Sun 7/6/14
155 Misc. Items(SDB,Feeders,ACDB,Industrial Socket) 67 days Tue 4/29/14 Fri 7/4/14
156 Purchase Order for Misc.Items 0 days Tue 4/29/14 Tue 4/29/14
157 Payment for Misc.Items 7 days Tue 4/29/14 Tue 5/6/14
158 Receiving of Misc.Items 50 days Tue 5/6/14 Wed 6/25/14
159 Installation and Termination of Misc.Items 10 days Wed 6/25/14 Fri 7/4/14
160 Weather monitoring system 42 days Sat 6/7/14 Fri 7/18/14
161 Purchase Order for WMS 0 days Sat 6/7/14 Sat 6/7/14
162 Payment for WMS 7 days Sat 6/7/14 Sat 6/14/14
163 Receiving of WMS 30 days Sat 6/14/14 Mon 7/14/14
164 Installation of WMS 5 days Mon 7/14/14 Fri 7/18/14
165 Transmission Line 57 days Fri 5/16/14 Fri 7/11/14
166 Purchase Order for Transmission Line Structures & Equipments0 days Fri 5/16/14 Fri 5/16/14
167 Payment for Transmission Line Structures & Equipments7 days Fri 5/16/14 Fri 5/23/14
168 Receiving of Structures and Equipments 30 days Fri 5/23/14 Sun 6/22/14
169 Installation and Stringing of Equipments 20 days Sun 6/22/14 Fri 7/11/14
170 Fire alarm system works 5 days Wed 7/9/14 Sun 7/13/14
171 Testing and commissioning 10 days Sat 7/19/14 Mon 7/28/14
172 Proposed Commercial Operation Date 1 day Tue 7/29/14 Tue 7/29/14
5/21 5/28
5/28 6/17
6/17 6/21
5/9
5/9 5/16
5/16 6/30
6/30 7/4
4/26
4/26 5/3
5/3 5/23
5/23 5/25
5/26
5/26 6/2
6/2 7/2
7/2 7/6
4/29
4/29 5/6
5/6 6/25
6/25 7/4
6/7
6/7 6/14
6/14 7/14
7/14 7/18
5/16
5/16 5/23
5/23 6/22
6/22 7/11
7/9 7/13
7/19 7/2
7/29 7
30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28
April 2014 May 2014 June 2014 July 2014
Task
Progress
Milestone
Summary
Rolled Up Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Deadline
Page 3
Project: Template PIS
Date: Wed 3/19/14

MS Projects - 10 MW Implementation Schedule

  • 1.
    ID Task NameDuration Start Finish 1 Solar PV Project-10 MW 120 days Tue 4/1/14 Tue 7/29/14 2 Site mobilization 2 days Tue 4/1/14 Wed 4/2/14 3 Array Area and General Works 110 days Sat 4/5/14 Wed 7/23/14 4 Civil Works 93 days Sat 4/5/14 Sun 7/6/14 5 Site Levelling and Grading 15 days Sat 4/5/14 Sat 4/19/14 6 Marking and Construction of Boundary Wall 30 days Tue 4/15/14 Wed 5/14/14 7 Foundation and Installation of Main Entry Gate 5 days Fri 4/18/14 Tue 4/22/14 8 Foundation and Construction of Security Cabin 5 days Fri 4/18/14 Tue 4/22/14 9 Construction of Internal Roads 5 days Tue 4/22/14 Sat 4/26/14 10 Foundation Marking for Structures 5 days Mon 4/21/14 Fri 4/25/14 11 Excavation for Structure Foundation 20 days Tue 4/22/14 Sun 5/11/14 12 Module Mounting Structure Casting 30 days Wed 4/23/14 Thu 5/22/14 13 String Monitoring Box Foundation 5 days Sat 5/3/14 Wed 5/7/14 14 Cable trench 7 days Fri 5/23/14 Thu 5/29/14 15 Construction of Water Collection Tank 10 days Fri 5/23/14 Sun 6/1/14 16 Construction of Drainage system 30 days Tue 5/27/14 Wed 6/25/14 17 Borewell works 3 days Fri 5/23/14 Sun 5/25/14 18 Lightening Arrester Foundation 5 days Sun 6/22/14 Thu 6/26/14 19 External Lighting Foundation 15 days Sun 6/22/14 Sun 7/6/14 20 CCTV Camera Foundation 5 days Sun 6/22/14 Thu 6/26/14 21 Earth Pit Works 5 days Thu 6/12/14 Mon 6/16/14 22 Electrical Works 97 days Thu 4/17/14 Wed 7/23/14 23 Structure 57 days Thu 4/17/14 Fri 6/13/14 24 Purchase Order for Structure 0 days Thu 4/17/14 Thu 4/17/14 25 Payment for Structure 0 days Thu 4/24/14 Thu 4/24/14 26 Receiving of Structure 25 days Fri 4/25/14 Mon 5/19/14 27 Installation of Structure 15 days Fri 5/30/14 Fri 6/13/14 28 PV Module 52 days Fri 4/25/14 Sun 6/15/14 29 Purchase Order for PV Module 0 days Fri 4/25/14 Fri 4/25/14 30 Payment for PV Module 7 days Fri 4/25/14 Fri 5/2/14 31 Receiving of PV Module 30 days Fri 5/2/14 Sun 6/1/14 32 Installation of PV Module 15 days Sun 6/1/14 Sun 6/15/14 33 String Monitoring Box 41 days Mon 4/21/14 Sat 5/31/14 34 Purchase Order for SMB 0 days Mon 4/21/14 Mon 4/21/14 35 Payment for SMB 7 days Mon 4/21/14 Mon 4/28/14 36 Receiving of String Monitoring Box 30 days Mon 4/28/14 Wed 5/28/14 37 Installation of String Monitoring Box 4 days Wed 5/28/14 Sat 5/31/14 38 Inverter 69 days Sat 4/19/14 Thu 6/26/14 39 Purchase Order for Inverter 0 days Sat 4/19/14 Sat 4/19/14 40 Payment for Inverter 7 days Sat 4/19/14 Sat 4/26/14 41 Receiving of Inverter 60 days Sat 4/26/14 Wed 6/25/14 42 Installation of Inverter 2 days Wed 6/25/14 Thu 6/26/14 43 DC Cable 64 days Tue 4/29/14 Tue 7/1/14 44 Purchase Order for DC Cable 0 days Tue 4/29/14 Tue 4/29/14 45 Payment for DC Cable 7 days Tue 4/29/14 Tue 5/6/14 46 Receiving of DC Cable 45 days Tue 5/6/14 Fri 6/20/14 47 Laying of DC Cable 7 days Fri 6/20/14 Fri 6/27/14 48 Termination of DC Cable 5 days Fri 6/27/14 Tue 7/1/14 49 OFC 60 days Thu 5/1/14 Sun 6/29/14 50 Purchase Order for OFC 0 days Thu 5/1/14 Thu 5/1/14 51 Payment for OFC 7 days Thu 5/1/14 Thu 5/8/14 52 Receiving of OFC 45 days Thu 5/8/14 Sun 6/22/14 53 Laying of OFC 5 days Sun 6/22/14 Fri 6/27/14 54 Termination of OFC 3 days Fri 6/27/14 Sun 6/29/14 55 CCTV SYSTEM 40 days Sat 5/31/14 Wed 7/9/14 56 Purchase Order for CCTV 0 days Sat 5/31/14 Sat 5/31/14 57 Payment for CCTV 7 days Sat 5/31/14 Sat 6/7/14 58 Receiving of CCTV 30 days Sat 6/7/14 Mon 7/7/14 59 Installation of CCTV 3 days Mon 7/7/14 Wed 7/9/14 60 Lightening Arrestor 41 days Sat 5/31/14 Thu 7/10/14 61 Purchase order for Lightening Arrestor 0 days Sat 5/31/14 Sat 5/31/14 62 Payment for Lightening Arrestor 7 days Sat 5/31/14 Sat 6/7/14 63 Receiving of Lightening Arrestor 30 days Sat 6/7/14 Mon 7/7/14 64 Installation of Lightening Arrestor 4 days Mon 7/7/14 Thu 7/10/14 65 SCADA System 72 days Tue 5/13/14 Wed 7/23/14 66 Purchase Order for SCADA System 0 days Tue 5/13/14 Tue 5/13/14 67 Payment for SCADA System 7 days Tue 5/13/14 Tue 5/20/14 68 Receiving of SCADA 60 days Tue 5/20/14 Sat 7/19/14 /1 4/2 4/5 4/19 4/15 5/14 4/18 4/22 4/18 4/22 4/22 4/26 4/21 4/25 4/22 5/11 4/23 5/22 5/3 5/7 5/23 5/29 5/23 6/1 5/27 6/25 5/23 5/25 6/22 6/26 6/22 7/6 6/22 6/26 6/12 6/16 4/17 4/24 4/25 5/19 5/30 6/13 4/25 4/25 5/2 5/2 6/1 6/1 6/15 4/21 4/21 4/28 4/28 5/28 5/28 5/31 4/19 4/19 4/26 4/26 6/25 6/25 6/26 4/29 4/29 5/6 5/6 6/20 6/20 6/27 6/27 7/1 5/1 5/1 5/8 5/8 6/22 6/22 6/27 6/27 6/29 5/31 5/31 6/7 6/7 7/7 7/7 7/9 5/31 5/31 6/7 6/7 7/7 7/7 7/10 5/13 5/13 5/20 5/20 7/19 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 April 2014 May 2014 June 2014 July 2014 Task Progress Milestone Summary Rolled Up Task Rolled Up Milestone Rolled Up Progress Split External Tasks Project Summary Group By Summary Deadline Page 1 Project: Template PIS Date: Wed 3/19/14
  • 2.
    ID Task NameDuration Start Finish 69 Installation and Termination of SCADA system 5 days Sat 7/19/14 Wed 7/23/14 70 External Lighting 57 days Wed 5/21/14 Wed 7/16/14 71 Purchase Order for Poles and Lights 0 days Wed 5/21/14 Wed 5/21/14 72 Payment for Lighting System 7 days Wed 5/21/14 Wed 5/28/14 73 Receiving of Lighting System 40 days Wed 5/28/14 Mon 7/7/14 74 Installation and Termination of Lighting System 10 days Mon 7/7/14 Wed 7/16/14 75 Array Earthing 57 days Sun 5/18/14 Sun 7/13/14 76 Purchase Order for Earthing Equipments 0 days Sun 5/18/14 Sun 5/18/14 77 Payment for Earthing Equipments 7 days Sun 5/18/14 Sun 5/25/14 78 Receiving of Earthing Equipments 40 days Sun 5/25/14 Fri 7/4/14 79 Array Earthing Installation and Connection 10 days Fri 7/4/14 Sun 7/13/14 80 Main Control Room & Substation 86 days Thu 4/24/14 Fri 7/18/14 81 Civil Work in MCR & Substation 60 days Sat 4/26/14 Tue 6/24/14 82 Marking 2 days Sat 4/26/14 Sun 4/27/14 83 Excavation 3 days Mon 4/28/14 Wed 4/30/14 84 RCC Foundation 20 days Thu 5/1/14 Tue 5/20/14 85 Brick work 15 days Wed 5/21/14 Wed 6/4/14 86 Internal Plaster 7 days Thu 6/5/14 Wed 6/11/14 87 Flooring & Trenching 7 days Thu 6/12/14 Wed 6/18/14 88 Windows & Doors Fixing 7 days Thu 6/12/14 Wed 6/18/14 89 Painting work 7 days Thu 6/12/14 Wed 6/18/14 90 Finishing work of Substation Building 10 days Sun 6/15/14 Tue 6/24/14 91 Power and Aux. Transformer Foundation 15 days Tue 5/6/14 Tue 5/20/14 92 Switch Yard Earthing Mat Construction 7 days Fri 5/16/14 Thu 5/22/14 93 Switch Yard Equipment Foundation 15 days Fri 5/23/14 Fri 6/6/14 94 Foundation for Transmission Towers 30 days Fri 5/23/14 Sat 6/21/14 95 Electrical Works 86 days Thu 4/24/14 Fri 7/18/14 96 Transformers(Power and Aux.) 72 days Thu 4/24/14 Fri 7/4/14 97 Purchase Order for Transformer 0 days Thu 4/24/14 Thu 4/24/14 98 Payment for Transformer 7 days Thu 4/24/14 Thu 5/1/14 99 Receiving of Transformer 60 days Thu 5/1/14 Mon 6/30/14 100 Installation of Transformer 5 days Mon 6/30/14 Fri 7/4/14 101 33 kV bay station 73 days Tue 4/29/14 Thu 7/10/14 102 Purchase Order for VCB,Conductors,Isolator,CT,PT,Structure2 days Tue 4/29/14 Thu 5/1/14 103 Payment for VCB,Conductors,Isolator,CT,PT,Structure7 days Thu 5/1/14 Thu 5/8/14 104 Receiving of Equipments 50 days Thu 5/8/14 Fri 6/27/14 105 Installation of Equipments 7 days Fri 6/27/14 Thu 7/3/14 106 Termination of Conductors 7 days Fri 7/4/14 Thu 7/10/14 107 HT Panels 61 days Fri 5/9/14 Tue 7/8/14 108 Purchase Order for HT Panels 0 days Fri 5/9/14 Fri 5/9/14 109 Payment for HT Panels 7 days Fri 5/9/14 Fri 5/16/14 110 Receiving of HT Panels 50 days Fri 5/16/14 Sat 7/5/14 111 Installation of HT Panels 4 days Sat 7/5/14 Tue 7/8/14 112 LT Panels 61 days Fri 5/9/14 Tue 7/8/14 113 Purchase Order for LT Panels 0 days Fri 5/9/14 Fri 5/9/14 114 Payment for LT Panels 7 days Fri 5/9/14 Fri 5/16/14 115 Receiving of LT Panels 50 days Fri 5/16/14 Sat 7/5/14 116 Installation of LT Panels 4 days Sat 7/5/14 Tue 7/8/14 117 LT Cable 72 days Sat 5/3/14 Sun 7/13/14 118 Purchase Order for LT Cable 0 days Sat 5/3/14 Sat 5/3/14 119 Payment for LT Cable 7 days Sat 5/3/14 Sat 5/10/14 120 Receiving of LT Cable 50 days Sat 5/10/14 Sun 6/29/14 121 Laying of LT Cable 5 days Sun 6/29/14 Thu 7/3/14 122 Terination of LT Cable 5 days Wed 7/9/14 Sun 7/13/14 123 HT Cable & Conductors 70 days Mon 5/5/14 Sun 7/13/14 124 Purchase Order for HT Cable 0 days Mon 5/5/14 Mon 5/5/14 125 Payment for HT Cable 7 days Mon 5/5/14 Mon 5/12/14 126 Receiving of HT Cables 50 days Mon 5/12/14 Tue 7/1/14 127 Laying of HT Cable 5 days Tue 7/1/14 Sat 7/5/14 128 Termination of HT Cable 5 days Wed 7/9/14 Sun 7/13/14 129 Control Cable 63 days Sat 5/10/14 Fri 7/11/14 130 Purchase Order for Control Cable 0 days Sat 5/10/14 Sat 5/10/14 131 Payment for Control Cable 7 days Sat 5/10/14 Sat 5/17/14 132 Receiving of Control Cables 45 days Sat 5/17/14 Tue 7/1/14 133 Laying of Control Cable 4 days Tue 7/1/14 Fri 7/4/14 134 Termination of Control Cable 3 days Wed 7/9/14 Fri 7/11/14 135 Lightening Protection System 32 days Wed 5/21/14 Sat 6/21/14 136 Purchase Order for LA 0 days Wed 5/21/14 Wed 5/21/14 7/19 7/23 5/21 5/21 5/28 5/28 7/7 7/7 7/16 5/18 5/18 5/25 5/25 7/4 7/4 7/13 4/26 4/27 4/28 4/30 5/1 5/20 5/21 6/4 6/5 6/11 6/12 6/18 6/12 6/18 6/12 6/18 6/15 6/24 5/6 5/20 5/16 5/22 5/23 6/6 5/23 6/21 4/24 4/24 5/1 5/1 6/30 6/30 7/4 4/29 5/1 5/1 5/8 5/8 6/27 6/27 7/3 7/4 7/10 5/9 5/9 5/16 5/16 7/5 7/5 7/8 5/9 5/9 5/16 5/16 7/5 7/5 7/8 5/3 5/3 5/10 5/10 6/29 6/29 7/3 7/9 7/13 5/5 5/5 5/12 5/12 7/1 7/1 7/5 7/9 7/13 5/10 5/10 5/17 5/17 7/1 7/1 7/4 7/9 7/11 5/21 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 April 2014 May 2014 June 2014 July 2014 Task Progress Milestone Summary Rolled Up Task Rolled Up Milestone Rolled Up Progress Split External Tasks Project Summary Group By Summary Deadline Page 2 Project: Template PIS Date: Wed 3/19/14
  • 3.
    ID Task NameDuration Start Finish 137 Payment for LA 7 days Wed 5/21/14 Wed 5/28/14 138 Receiving of LA 20 days Wed 5/28/14 Tue 6/17/14 139 Installation of LA 5 days Tue 6/17/14 Sat 6/21/14 140 Battery System 57 days Fri 5/9/14 Fri 7/4/14 141 Purchase Order for Battery Bank 0 days Fri 5/9/14 Fri 5/9/14 142 Payment for Battery Bank 7 days Fri 5/9/14 Fri 5/16/14 143 Receiving of Battery Bank 45 days Fri 5/16/14 Mon 6/30/14 144 Installation of Battery Bank 5 days Mon 6/30/14 Fri 7/4/14 145 Switch Yard Earthing 30 days Sat 4/26/14 Sun 5/25/14 146 Purchase Order for Earthing Equipments 0 days Sat 4/26/14 Sat 4/26/14 147 Payment for Earthing Equipments 7 days Sat 4/26/14 Sat 5/3/14 148 Receiving of Earthing Equipments 20 days Sat 5/3/14 Fri 5/23/14 149 Installation and Connection 3 days Fri 5/23/14 Sun 5/25/14 150 Internal Lightning System 42 days Mon 5/26/14 Sun 7/6/14 151 Purchase Order for Poles and Lights 0 days Mon 5/26/14 Mon 5/26/14 152 Payment for Lighting System 7 days Mon 5/26/14 Mon 6/2/14 153 Receiving of Lighting System 30 days Mon 6/2/14 Wed 7/2/14 154 Installation and Termination of Lighting System 5 days Wed 7/2/14 Sun 7/6/14 155 Misc. Items(SDB,Feeders,ACDB,Industrial Socket) 67 days Tue 4/29/14 Fri 7/4/14 156 Purchase Order for Misc.Items 0 days Tue 4/29/14 Tue 4/29/14 157 Payment for Misc.Items 7 days Tue 4/29/14 Tue 5/6/14 158 Receiving of Misc.Items 50 days Tue 5/6/14 Wed 6/25/14 159 Installation and Termination of Misc.Items 10 days Wed 6/25/14 Fri 7/4/14 160 Weather monitoring system 42 days Sat 6/7/14 Fri 7/18/14 161 Purchase Order for WMS 0 days Sat 6/7/14 Sat 6/7/14 162 Payment for WMS 7 days Sat 6/7/14 Sat 6/14/14 163 Receiving of WMS 30 days Sat 6/14/14 Mon 7/14/14 164 Installation of WMS 5 days Mon 7/14/14 Fri 7/18/14 165 Transmission Line 57 days Fri 5/16/14 Fri 7/11/14 166 Purchase Order for Transmission Line Structures & Equipments0 days Fri 5/16/14 Fri 5/16/14 167 Payment for Transmission Line Structures & Equipments7 days Fri 5/16/14 Fri 5/23/14 168 Receiving of Structures and Equipments 30 days Fri 5/23/14 Sun 6/22/14 169 Installation and Stringing of Equipments 20 days Sun 6/22/14 Fri 7/11/14 170 Fire alarm system works 5 days Wed 7/9/14 Sun 7/13/14 171 Testing and commissioning 10 days Sat 7/19/14 Mon 7/28/14 172 Proposed Commercial Operation Date 1 day Tue 7/29/14 Tue 7/29/14 5/21 5/28 5/28 6/17 6/17 6/21 5/9 5/9 5/16 5/16 6/30 6/30 7/4 4/26 4/26 5/3 5/3 5/23 5/23 5/25 5/26 5/26 6/2 6/2 7/2 7/2 7/6 4/29 4/29 5/6 5/6 6/25 6/25 7/4 6/7 6/7 6/14 6/14 7/14 7/14 7/18 5/16 5/16 5/23 5/23 6/22 6/22 7/11 7/9 7/13 7/19 7/2 7/29 7 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 April 2014 May 2014 June 2014 July 2014 Task Progress Milestone Summary Rolled Up Task Rolled Up Milestone Rolled Up Progress Split External Tasks Project Summary Group By Summary Deadline Page 3 Project: Template PIS Date: Wed 3/19/14