This document contains a master schedule for the preparation and processing of the twelfth floor of a headquarters building in Garden City. The schedule outlines 76 activities with original durations and planned start and finish dates from March 31, 2015 to June 14, 2015. Key milestones include establishing electrical, plumbing and HVAC by April 24, 50% of work done by May 16, 80% done including painting by June 4, and completing the project by June 14. The schedule also provides details on architectural works, MEP works including plumbing, electrical, and HVAC installation and testing.