SlideShare a Scribd company logo
ID Task Name Duration Start Finish
1 Start Up 288 days Thu 10/22/15 Wed 12/14/16
2 Pre-Construction Meeting 0 days Thu 10/22/15 Thu 10/22/15
3 Overall Project Duration 420 days Thu 10/22/15 Wed 12/14/16
4 Notice To Proceed 0 days Thu 10/22/15 Thu 10/22/15
5 Mobilization 1 day Thu 10/22/15 Thu 10/22/15
6 Pre Construction Submittal Process 30 days Thu 10/22/15 Fri 12/4/15
7 Pre Con Submittals 30 days Thu 10/22/15 Fri 12/4/15
8 Submission and Approval Bc Safety Plan 30 days Thu 10/22/15 Fri 12/4/15
9 Submission and Approval Bc Qa/Qc Plan 30 days Thu 10/22/15 Fri 12/4/15
10 Construction Submittal Process 50 days Thu 10/22/15 Tue 1/5/16
11 Construction Submittals 30 days Thu 10/22/15 Fri 12/4/15
12 Submission and Approval Plumbing Carriers 30 days Thu 10/22/15 Fri 12/4/15
13 Submission and Approval Plumbing Piping 30 days Thu 10/22/15 Fri 12/4/15
14 Submission and Approval Plumbing Fixtures 30 days Thu 10/22/15 Fri 12/4/15
15 Submission and Approval Ductwork For Hvac 30 days Thu 10/22/15 Fri 12/4/15
16 Submission and Approval Piping For Hvac 30 days Thu 10/22/15 Fri 12/4/15
17 Submission and Approval Equipment For Hvac 30 days Thu 10/22/15 Fri 12/4/15
18 Submission and Approval Med Gas Material 30 days Thu 10/22/15 Fri 12/4/15
19 Submission and Approval Electrical Wiring 30 days Thu 10/22/15 Fri 12/4/15
20 Submission and Approval Lighting 30 days Thu 10/22/15 Fri 12/4/15
21 Submission and Approval Raceway And Boxes For Electrical Systems 30 days Thu 10/22/15 Fri 12/4/15
22 Submission and Approval Fire Detection Alarm 30 days Thu 10/22/15 Fri 12/4/15
23 Submission and Approval Cast-In-Place Concrete 30 days Thu 10/22/15 Fri 12/4/15
24 Submission and Approval Building Insulation 30 days Thu 10/22/15 Fri 12/4/15
25 Submission and Approval Framing Plan 30 days Thu 10/22/15 Fri 12/4/15
26 Submission and Approval Foundation Plan 30 days Thu 10/22/15 Fri 12/4/15
27 Submission and Approval Door Hardware 30 days Thu 10/22/15 Fri 12/4/15
28 Submission and Approval Glazing 30 days Thu 10/22/15 Fri 12/4/15
29 Submission and Approval Non Structural Metal Framing 30 days Thu 10/22/15 Fri 12/4/15
30 Submission and Approval Gypsum Board 30 days Thu 10/22/15 Fri 12/4/15
31 Submission and Approval Ceramic Tiling 30 days Thu 10/22/15 Fri 12/4/15
32 Submission and Approval Acoustical Ceilings 30 days Thu 10/22/15 Fri 12/4/15
33 Submission and Approval Flooring 30 days Thu 10/22/15 Fri 12/4/15
34 Submission and Approval Painting 30 days Thu 10/22/15 Fri 12/4/15
35 Submission and Approval Toilet, Bath, And Laundry Accessories 30 days Thu 10/22/15 Fri 12/4/15
36 Submission and Approval Fire Extinguisher Cabinets 30 days Thu 10/22/15 Fri 12/4/15
37 Submission and Approval Wet-Pipe Sprinkler Systmes 30 days Thu 10/22/15 Fri 12/4/15
38 Fabrication and Delivery 20 days Mon 12/7/15 Tue 1/5/16
39 Fabricate & Deliver Drywall 20 days Mon 12/7/15 Tue 1/5/16
40 Fabricate & Deliver Plumbing Pipe 20 days Mon 12/7/15 Tue 1/5/16
41 Fabricate & Deliver Plumbing Carriers 20 days Mon 12/7/15 Tue 1/5/16
42 Fabricate & Deliver Fire Sprinkler Piping 20 days Mon 12/7/15 Tue 1/5/16
43 Fabricate & Deliver Ductwork 20 days Mon 12/7/15 Tue 1/5/16
44 Fabricate & Deliver Lighting Fixtures 20 days Mon 12/7/15 Tue 1/5/16
45 Fabricate & Deliver Plumbing Fixtures 20 days Mon 12/7/15 Tue 1/5/16
46 Fabricate & Deliver Doors & Hardware 20 days Mon 12/7/15 Tue 1/5/16
47 Fabricate & Deliver Ceramic Tile 20 days Mon 12/7/15 Tue 1/5/16
48 Fabricate & Deliver Metal Framing Materials 20 days Mon 12/7/15 Tue 1/5/16
49 Fabricate & Deliver Electrical Conduit 20 days Mon 12/7/15 Tue 1/5/16
50 Construction 288 days Thu 10/22/15 Wed 12/14/16
51 Building 20 & 21& New Additions 288 days Thu 10/22/15 Wed 12/14/16
52 Site Works 288 days Thu 10/22/15 Wed 12/14/16
64 General 288 days Thu 10/22/15 Wed 12/14/16
77 Erosion and Sediment Control 288 days Thu 10/22/15 Wed 12/14/16
70 Rough in of Underground Sanitary Waste Lines 5 days Thu 12/31/15 Thu 1/7/16
65 Install New HVAC Concerete Pad 5 days Fri 1/8/16 Thu 1/14/16
66 Install New Electrical Conduits For Generator 1 day Fri 1/8/16 Fri 1/8/16
76 Install Sanitary Waste Lines 3 days Fri 1/8/16 Tue 1/12/16
67 Install New Generator Pad 1 day Mon 1/11/16 Mon 1/11/16
71 Install New Natural Gas Line 5 days Mon 1/11/16 Fri 1/15/16
68 Install New Transformer Conduits 1 day Tue 1/12/16 Tue 1/12/16
69 Install New Transformer Concerete Pad 1 day Wed 1/13/16 Wed 1/13/16
75 Install Sanitary Vent Lines 3 days Wed 1/13/16 Fri 1/15/16
74 Install Plumbing Water Lines 3 days Tue 1/19/16 Thu 1/21/16
73 Install Storm Pipe 5 days Fri 1/22/16 Thu 1/28/16
78 Grading Sediment Control 2 days Fri 1/29/16 Mon 2/1/16
72 Install Temporary Bollard 5 days Tue 2/2/16 Mon 2/8/16
53 Demolition 17 days Mon 12/7/15 Wed 12/30/15
63 Removal of Trees 5 days Mon 12/7/15 Fri 12/11/15
55 Remove & Cap Sanitary Piping 4 days Fri 12/11/15 Wed 12/16/15
62 Paint Removal Using Sand Blasting of Exterior Walls 5 days Mon 12/14/15 Fri 12/18/15
60 Remove Top Soil 1 day Thu 12/17/15 Thu 12/17/15
61 Remove Abandoned 8'' Water Main 1 day Fri 12/18/15 Fri 12/18/15
10/22
Overall Project Duration
10/22
Mobilization
Submission and Approval Bc Safety Plan
Submission and Approval Bc Qa/Qc Plan
Submission and Approval Plumbing Carriers
Submission and Approval Plumbing Piping
Submission and Approval Plumbing Fixtures
Submission and Approval Ductwork For Hvac
Submission and Approval Piping For Hvac
Submission and Approval Equipment For Hvac
Submission and Approval Med Gas Material
Submission and Approval Electrical Wiring
Submission and Approval Lighting
Submission and Approval Raceway And Boxes For Electrical Systems
Submission and Approval Fire Detection Alarm
Submission and Approval Cast-In-Place Concrete
Submission and Approval Building Insulation
Submission and Approval Framing Plan
Submission and Approval Foundation Plan
Submission and Approval Door Hardware
Submission and Approval Glazing
Submission and Approval Non Structural Metal Framing
Submission and Approval Gypsum Board
Submission and Approval Ceramic Tiling
Submission and Approval Acoustical Ceilings
Submission and Approval Flooring
Submission and Approval Painting
Submission and Approval Toilet, Bath, And Laundry Accessories
Submission and Approval Fire Extinguisher Cabinets
Submission and Approval Wet-Pipe Sprinkler Systmes
Fabricate & Deliver Drywall
Fabricate & Deliver Plumbing Pipe
Fabricate & Deliver Plumbing Carriers
Fabricate & Deliver Fire Sprinkler Piping
Fabricate & Deliver Ductwork
Fabricate & Deliver Lighting Fixtures
Fabricate & Deliver Plumbing Fixtures
Fabricate & Deliver Doors & Hardware
Fabricate & Deliver Ceramic Tile
Fabricate & Deliver Metal Framing Materials
Fabricate & Deliver Electrical Conduit
Erosion and Sediment Control
Rough in of Underground Sanitary Waste Lines
Install New HVAC Concerete Pad
Install New Electrical Conduits For Generator
Install Sanitary Waste Lines
Install New Generator Pad
Install New Natural Gas Line
Install New Transformer Conduits
Install New Transformer Concerete Pad
Install Sanitary Vent Lines
Install Plumbing Water Lines
Install Storm Pipe
Grading Sediment Control
Install Temporary Bollard
Removal of Trees
Remove & Cap Sanitary Piping
Paint Removal Using Sand Blasting of Exterior Walls
Remove Top Soil
Remove Abandoned 8'' Water Main
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
Sep 27, '15 Oct 18, '15 Nov 8, '15 Nov 29, '15 Dec 20, '15 Jan 10, '16 Jan 31, '16 Feb 21, '16 Mar 13, '16 Apr 3, '16 Apr 24, '16 May 15, '16 Jun 5, '16 Jun 26, '16 Jul 17, '16 Aug 7, '16 Aug 28, '16 Sep 18, '16 Oct 9, '16 Oct 30, '16 Nov 20, '16 Dec 11, '16 Jan 1, '17 Jan 22, '17 Feb 12, '17
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 1
Date: Sun 2/28/16
ID Task Name Duration Start Finish
56 Remove Conc.Sidewalk and Con Loading Dock 1 day Mon 12/21/15 Mon 12/21/15
57 Saw Cut BIT CONC 2 days Tue 12/22/15 Wed 12/23/15
58 Remove EX.Gravel Drive 1 day Thu 12/24/15 Thu 12/24/15
59 Remove and Replace Existing Steam Vent as Depicted on C-301 2 days Mon 12/28/15 Tue 12/29/15
54 Remove Bollard 1 day Wed 12/30/15 Wed 12/30/15
79 Building 21 63 days Mon 12/7/15 Tue 3/8/16
80 Demolitions 18 days Mon 12/7/15 Thu 12/31/15
81 Remove Existing CMU 3 days Mon 12/7/15 Wed 12/9/15
82 Remove Portion of Exterior Wall 3 days Thu 12/10/15 Mon 12/14/15
83 Remove Portion of Roofing Material 3 days Tue 12/15/15 Thu 12/17/15
84 Remove Existing Plumbing 3 days Fri 12/18/15 Tue 12/22/15
85 Remove Existing Mechanical 3 days Wed 12/23/15 Mon 12/28/15
86 Demo Hard Ceilings 3 days Tue 12/29/15 Thu 12/31/15
87 First Floor 45 days Mon 1/4/16 Tue 3/8/16
88 Civil Work 5 days Mon 1/4/16 Fri 1/8/16
89 Install New CMU 5 days Mon 1/4/16 Fri 1/8/16
90 Plumbing Works 10 days Mon 1/11/16 Mon 1/25/16
92 Rough In Walls-Plumbing 3 days Mon 1/11/16 Wed 1/13/16
93 Rough In Above Ceiling Plumbing 3 days Thu 1/14/16 Tue 1/19/16
91 Set Plumbing Carriers 2 days Wed 1/20/16 Thu 1/21/16
95 Install Floor Drains 2 days Wed 1/20/16 Thu 1/21/16
94 Trim Out Plumbing 2 days Fri 1/22/16 Mon 1/25/16
96 Electrical /Lighiting Works 9 days Thu 1/14/16 Wed 1/27/16
98 Rough In Electrical Conduit And Wire 3 days Thu 1/14/16 Tue 1/19/16
99 Install Lighting Conduits 2 days Wed 1/20/16 Thu 1/21/16
97 Trim Out Electrical 2 days Fri 1/22/16 Mon 1/25/16
100 Trim Out Lighting 2 days Tue 1/26/16 Wed 1/27/16
101 Mechanical / HVAC / Fire Sprinkler 17 days Thu 1/14/16 Mon 2/8/16
104 Install Ac Ductwork 3 days Thu 1/14/16 Tue 1/19/16
102 Install Vav Cw Hw Piping 2 days Wed 1/20/16 Thu 1/21/16
112 Pressure Test Ductwork 2 days Wed 1/20/16 Thu 1/21/16
113 Insulate Ductwork 2 days Fri 1/22/16 Mon 1/25/16
106 Rough In Low Voltage 2 days Tue 1/26/16 Wed 1/27/16
105 Trim Out Low Voltage 2 days Thu 1/28/16 Fri 1/29/16
107 Rough In Mechanical 2 days Thu 1/28/16 Fri 1/29/16
108 Rough In Med Gas 2 days Mon 2/1/16 Tue 2/2/16
109 Trim Out Mechanical 2 days Mon 2/1/16 Tue 2/2/16
103 Rough In For Fire Sprinkler Pipe 2 days Wed 2/3/16 Thu 2/4/16
110 Trim Out Med Gas 2 days Wed 2/3/16 Thu 2/4/16
111 Trim Out Fire Sprinkler 2 days Fri 2/5/16 Mon 2/8/16
114 Finishing 20 days Tue 2/9/16 Tue 3/8/16
125 Prime And First Coat Walls And Hard Ceilings 2 days Tue 2/9/16 Wed 2/10/16
123 Hang Drywall 2 days Thu 2/11/16 Fri 2/12/16
124 Finish Drywall 2 days Tue 2/16/16 Wed 2/17/16
117 Install Vinyl Flooring 2 days Thu 2/18/16 Fri 2/19/16
126 Epoxy Painting 2 days Thu 2/18/16 Fri 2/19/16
116 Final Coat Painting 2 days Mon 2/22/16 Tue 2/23/16
127 Doors & Hdw Installation 2 days Wed 2/24/16 Thu 2/25/16
128 Interior Glass Installation 2 days Fri 2/26/16 Mon 2/29/16
115 Install Equipment-Security System 1 day Tue 3/1/16 Tue 3/1/16
121 Install Equipment-Fire Alarm 1 day Wed 3/2/16 Wed 3/2/16
122 Install Va Equipment-Cabinetry 1 day Thu 3/3/16 Thu 3/3/16
119 Install Va Equipment-Appliances 1 day Fri 3/4/16 Fri 3/4/16
120 Install Equipment-Motorized Windowshades 1 day Mon 3/7/16 Mon 3/7/16
118 Install Va Equipment-Furniture 1 day Tue 3/8/16 Tue 3/8/16
129 Building 20 & New Additions 216 days Mon 12/7/15 Thu 10/13/16
130 Demolitions 26 days Mon 12/7/15 Wed 1/13/16
135 Disconnect Hvac 1 day Mon 12/7/15 Mon 12/7/15
142 Disconnect Medical Gas 1 day Mon 12/7/15 Mon 12/7/15
145 Disconnect Power 1 day Mon 12/7/15 Mon 12/7/15
149 Demo Abatement 7 days Mon 12/7/15 Tue 12/15/15
132 Demo Fire Sprinkler System 3 days Tue 12/8/15 Thu 12/10/15
133 Demo Ac Ductwork 3 days Tue 12/8/15 Thu 12/10/15
141 Disconnect Domestic Water 1 day Tue 12/8/15 Tue 12/8/15
143 Disconnect Low Voltage Systems 1 day Tue 12/8/15 Tue 12/8/15
148 Demo and Remove of Portion of Building 20 7 days Tue 12/8/15 Wed 12/16/15
134 Demo Plumbing Piping 2 days Wed 12/9/15 Thu 12/10/15
136 Remove Plumbing Fixtures 3 days Thu 12/17/15 Mon 12/21/15
138 Demo Electric Power Conduit & Wire 3 days Tue 12/22/15 Thu 12/24/15
139 Demo Low Voltage Systems 2 days Mon 12/28/15 Tue 12/29/15
144 Demo/Remove Ceiling Tile 2 days Wed 12/30/15 Thu 12/31/15
131 Demo Walls 3 days Mon 1/4/16 Wed 1/6/16
140 Install Negative Air Machines 2 days Mon 1/4/16 Tue 1/5/16
Remove Conc.Sidewalk and Con Loading Dock
Saw Cut BIT CONC
Remove EX.Gravel Drive
Remove and Replace Existing Steam Vent as Depicted on C-301
Remove Bollard
Remove Existing CMU
Remove Portion of Exterior Wall
Remove Portion of Roofing Material
Remove Existing Plumbing
Remove Existing Mechanical
Demo Hard Ceilings
Install New CMU
Rough In Walls-Plumbing
Rough In Above Ceiling Plumbing
Set Plumbing Carriers
Install Floor Drains
Trim Out Plumbing
Rough In Electrical Conduit And Wire
Install Lighting Conduits
Trim Out Electrical
Trim Out Lighting
Install Ac Ductwork
Install Vav Cw Hw Piping
Pressure Test Ductwork
Insulate Ductwork
Rough In Low Voltage
Trim Out Low Voltage
Rough In Mechanical
Rough In Med Gas
Trim Out Mechanical
Rough In For Fire Sprinkler Pipe
Trim Out Med Gas
Trim Out Fire Sprinkler
Prime And First Coat Walls And Hard Ceilings
Hang Drywall
Finish Drywall
Install Vinyl Flooring
Epoxy Painting
Final Coat Painting
Doors & Hdw Installation
Interior Glass Installation
Install Equipment-Security System
Install Equipment-Fire Alarm
Install Va Equipment-Cabinetry
Install Va Equipment-Appliances
Install Equipment-Motorized Windowshades
Install Va Equipment-Furniture
Disconnect Hvac
Disconnect Medical Gas
Disconnect Power
Demo Abatement
Demo Fire Sprinkler System
Demo Ac Ductwork
Disconnect Domestic Water
Disconnect Low Voltage Systems
Demo and Remove of Portion of Building 20
Demo Plumbing Piping
Remove Plumbing Fixtures
Demo Electric Power Conduit & Wire
Demo Low Voltage Systems
Demo/Remove Ceiling Tile
Demo Walls
Install Negative Air Machines
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
Sep 27, '15 Oct 18, '15 Nov 8, '15 Nov 29, '15 Dec 20, '15 Jan 10, '16 Jan 31, '16 Feb 21, '16 Mar 13, '16 Apr 3, '16 Apr 24, '16 May 15, '16 Jun 5, '16 Jun 26, '16 Jul 17, '16 Aug 7, '16 Aug 28, '16 Sep 18, '16 Oct 9, '16 Oct 30, '16 Nov 20, '16 Dec 11, '16 Jan 1, '17 Jan 22, '17 Feb 12, '17
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 2
Date: Sun 2/28/16
ID Task Name Duration Start Finish
147 Demo/Remove Lights Grills & Diffusers 3 days Mon 1/4/16 Wed 1/6/16
146 Rework Fire Sprinkler Heads For Demo 3 days Wed 1/6/16 Fri 1/8/16
137 Remove Existing Equipment 3 days Mon 1/11/16 Wed 1/13/16
150 First Floor 155 days Thu 12/31/15 Wed 8/10/16
151 Concrete Work 36 days Thu 12/31/15 Tue 2/23/16
152 Excavation of Foundations @ Area A 7 days Thu 12/31/15 Mon 1/11/16
153 Dewatering 3 days Tue 1/12/16 Thu 1/14/16
154 Load out Excavation Materials 3 days Tue 1/12/16 Thu 1/14/16
156 Form / Pour Foundation Footers 5 days Fri 1/15/16 Fri 1/22/16
157 Form / Pour Foundation Walls 5 days Mon 1/25/16 Fri 1/29/16
155 Backfill Foundation 4 days Mon 2/1/16 Thu 2/4/16
158 Form / Pour Concrete Slab on Grade 5 days Wed 2/17/16 Tue 2/23/16
181 Plumbing Works 75 days Fri 2/5/16 Fri 5/20/16
187 Plumbing Rough In Under Slab 7 days Fri 2/5/16 Tue 2/16/16
188 Plumbing Rough In -Sanitary Waste lines 7 days Fri 2/5/16 Tue 2/16/16
189 Plumbing Rough In -Storm Drain lines 7 days Fri 2/5/16 Tue 2/16/16
183 Rough In Walls-Plumbing 4 days Fri 4/29/16 Wed 5/4/16
184 Rough In Above Ceiling Plumbing 4 days Thu 5/5/16 Tue 5/10/16
182 Set Plumbing Carriers 3 days Wed 5/11/16 Fri 5/13/16
186 Install Floor Drains 4 days Wed 5/11/16 Mon 5/16/16
185 Trim Out Plumbing 4 days Tue 5/17/16 Fri 5/20/16
159 Structure Steel 25 days Wed 2/24/16 Tue 3/29/16
161 Install Bass Plates / Columns 5 days Wed 2/24/16 Tue 3/1/16
162 Install Steel Framing 5 days Wed 3/2/16 Tue 3/8/16
163 Install Steel Bracing 5 days Wed 3/9/16 Tue 3/15/16
164 Install Metal Decking 5 days Wed 3/16/16 Tue 3/22/16
160 Install CMU 5 days Wed 3/23/16 Tue 3/29/16
165 Cold Formed Metal Framing 11 days Wed 3/23/16 Wed 4/6/16
168 Install batt insulation 2 days Wed 3/23/16 Thu 3/24/16
167 Frame wall openings 2 days Fri 3/25/16 Mon 3/28/16
166 Install Batt insulation 1 day Tue 3/29/16 Tue 3/29/16
169 Install interiol dans - glass sheathing 3 days Wed 3/30/16 Fri 4/1/16
170 Install pvc wainscot 3 days Mon 4/4/16 Wed 4/6/16
171 Metal Wall Panels 8 days Thu 4/7/16 Mon 4/18/16
172 Install Extrior Dens Glass Sheathing 2 days Thu 4/7/16 Fri 4/8/16
173 Install J-Channel , Z-Girts 2 days Mon 4/11/16 Tue 4/12/16
174 Install Water Resistive Barrier 1 day Wed 4/13/16 Wed 4/13/16
175 Install Metal Wall Panels 3 days Thu 4/14/16 Mon 4/18/16
176 Metal Roof Panels 8 days Tue 4/19/16 Thu 4/28/16
177 Install Rigid Insulation 2 days Tue 4/19/16 Wed 4/20/16
178 Install Roof Dens-Deck 2 days Thu 4/21/16 Fri 4/22/16
179 Install Metal Roof Panels 2 days Mon 4/25/16 Tue 4/26/16
180 Install Gutters / Downspouts 2 days Wed 4/27/16 Thu 4/28/16
190 Electrical /Lighiting Works 20 days Fri 4/29/16 Thu 5/26/16
191 Rough In Electrical Conduit And Wire 5 days Fri 4/29/16 Thu 5/5/16
193 Install Lighting Conduits 5 days Fri 5/6/16 Thu 5/12/16
192 Trim Out Electrical 5 days Fri 5/13/16 Thu 5/19/16
194 Trim Out Lighting 5 days Fri 5/20/16 Thu 5/26/16
209 Finishing 72 days Fri 4/29/16 Wed 8/10/16
226 Installation of Exterior Window 5 days Fri 4/29/16 Thu 5/5/16
213 Drop In Ceiling Tile 4 days Mon 5/23/16 Thu 5/26/16
217 Install Ceramic Tile In Bathrooms 2 days Fri 5/27/16 Tue 5/31/16
222 Prime And First Coat Walls And Hard Ceilings 4 days Wed 6/1/16 Mon 6/6/16
220 Hang Drywall 3 days Tue 6/7/16 Thu 6/9/16
221 Finish Drywall 3 days Fri 6/10/16 Tue 6/14/16
212 Install Vinyl Flooring 4 days Wed 6/15/16 Mon 6/20/16
223 Epoxy Painting 3 days Wed 6/15/16 Fri 6/17/16
227 Installation of Suspended Ceiling Grid 7 days Wed 6/15/16 Thu 6/23/16
211 Final Coat Painting 3 days Tue 6/21/16 Thu 6/23/16
224 Doors & Hdw Installation 4 days Thu 7/7/16 Tue 7/12/16
225 Interior Glass Installation 3 days Wed 7/13/16 Fri 7/15/16
210 Install Equipment-Security System 3 days Mon 7/18/16 Wed 7/20/16
218 Install Equipment-Fire Alarm 3 days Thu 7/21/16 Mon 7/25/16
219 Install Va Equipment-Cabinetry 3 days Tue 7/26/16 Thu 7/28/16
215 Install Va Equipment-Appliances 3 days Fri 7/29/16 Tue 8/2/16
216 Install Equipment-Motorized Windowshades 3 days Wed 8/3/16 Fri 8/5/16
214 Install Va Equipment-Furniture 3 days Mon 8/8/16 Wed 8/10/16
195 Mechanical / HVAC / Fire Sprinkler 43 days Thu 5/5/16 Wed 7/6/16
197 Install Ac Ductwork 5 days Thu 5/5/16 Wed 5/11/16
198 Install Vav Cw Hw Piping 5 days Thu 5/12/16 Wed 5/18/16
208 Install Penthouse Central Utilities Plant 7 days Tue 5/17/16 Wed 5/25/16
205 Insulate Ductwork 3 days Thu 5/19/16 Mon 5/23/16
196 Pressure Test Ductwork 3 days Tue 5/24/16 Thu 5/26/16
Demo/Remove Lights Grills & Diffusers
Rework Fire Sprinkler Heads For Demo
Remove Existing Equipment
Excavation of Foundations @ Area A
Dewatering
Load out Excavation Materials
Form / Pour Foundation Footers
Form / Pour Foundation Walls
Backfill Foundation
Form / Pour Concrete Slab on Grade
Plumbing Rough In Under Slab
Plumbing Rough In -Sanitary Waste lines
Plumbing Rough In -Storm Drain lines
Rough In Walls-Plumbing
Rough In Above Ceiling Plumbing
Set Plumbing Carriers
Install Floor Drains
Trim Out Plumbing
Install Bass Plates / Columns
Install Steel Framing
Install Steel Bracing
Install Metal Decking
Install CMU
Install batt insulation
Frame wall openings
Install Batt insulation
Install interiol dans - glass sheathing
Install pvc wainscot
Install Extrior Dens Glass Sheathing
Install J-Channel , Z-Girts
Install Water Resistive Barrier
Install Metal Wall Panels
Install Rigid Insulation
Install Roof Dens-Deck
Install Metal Roof Panels
Install Gutters / Downspouts
Rough In Electrical Conduit And Wire
Install Lighting Conduits
Trim Out Electrical
Trim Out Lighting
Installation of Exterior Window
Drop In Ceiling Tile
Install Ceramic Tile In Bathrooms
Prime And First Coat Walls And Hard Ceilings
Hang Drywall
Finish Drywall
Install Vinyl Flooring
Epoxy Painting
Installation of Suspended Ceiling Grid
Final Coat Painting
Doors & Hdw Installation
Interior Glass Installation
Install Equipment-Security System
Install Equipment-Fire Alarm
Install Va Equipment-Cabinetry
Install Va Equipment-Appliances
Install Equipment-Motorized Windowshades
Install Va Equipment-Furniture
Install Ac Ductwork
Install Vav Cw Hw Piping
Install Penthouse Central Utilities Plant
Insulate Ductwork
Pressure Test Ductwork
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
Sep 27, '15 Oct 18, '15 Nov 8, '15 Nov 29, '15 Dec 20, '15 Jan 10, '16 Jan 31, '16 Feb 21, '16 Mar 13, '16 Apr 3, '16 Apr 24, '16 May 15, '16 Jun 5, '16 Jun 26, '16 Jul 17, '16 Aug 7, '16 Aug 28, '16 Sep 18, '16 Oct 9, '16 Oct 30, '16 Nov 20, '16 Dec 11, '16 Jan 1, '17 Jan 22, '17 Feb 12, '17
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 3
Date: Sun 2/28/16
ID Task Name Duration Start Finish
201 Rough In Low Voltage 3 days Fri 5/27/16 Wed 6/1/16
202 Rough In Mechanical 3 days Thu 6/2/16 Mon 6/6/16
203 Rough In Med Gas 3 days Tue 6/7/16 Thu 6/9/16
199 Rough In For Fire Sprinkler Pipe 4 days Fri 6/10/16 Wed 6/15/16
204 Trim Out Mechanical 4 days Fri 6/24/16 Wed 6/29/16
206 Trim Out Fire Sprinkler 4 days Fri 6/24/16 Wed 6/29/16
207 Trim Out Med Gas 4 days Fri 6/24/16 Wed 6/29/16
200 Trim Out Low Voltage 4 days Thu 6/30/16 Wed 7/6/16
228 Roof Floor 116 days Fri 4/29/16 Thu 10/13/16
229 Structure Steel 12 days Fri 4/29/16 Mon 5/16/16
230 Install Bass Plates / Columns 3 days Fri 4/29/16 Tue 5/3/16
231 Install Steel Framing 3 days Wed 5/4/16 Fri 5/6/16
232 Install Steel Bracing 3 days Mon 5/9/16 Wed 5/11/16
233 Install Metal Decking 3 days Thu 5/12/16 Mon 5/16/16
234 Cold Formed Metal Framing 14 days Tue 5/17/16 Mon 6/6/16
237 Install batt insulation 3 days Tue 5/17/16 Thu 5/19/16
236 Frame wall openings 3 days Fri 5/20/16 Tue 5/24/16
235 Install Batt insulation 2 days Wed 5/25/16 Thu 5/26/16
238 Install interiol dans - glass sheathing 3 days Fri 5/27/16 Wed 6/1/16
239 Install pvc wainscot 3 days Thu 6/2/16 Mon 6/6/16
240 Metal Wall Panels 10 days Tue 6/7/16 Mon 6/20/16
241 Install Extrior Dens Glass Sheathing 3 days Tue 6/7/16 Thu 6/9/16
242 Install J-Channel , Z-Girts 2 days Fri 6/10/16 Mon 6/13/16
243 Install Water Resistive Barrier 2 days Tue 6/14/16 Wed 6/15/16
244 Install Metal Wall Panels 3 days Thu 6/16/16 Mon 6/20/16
245 Metal Roof Panels 7 days Tue 6/21/16 Wed 6/29/16
246 Install Rigid Insulation 2 days Tue 6/21/16 Wed 6/22/16
247 Install Roof Dens-Deck 2 days Thu 6/23/16 Fri 6/24/16
248 Install Metal Roof Panels 2 days Mon 6/27/16 Tue 6/28/16
249 Install Gutters / Downspouts 1 day Wed 6/29/16 Wed 6/29/16
250 Plumbing Works 14 days Thu 6/30/16 Wed 7/20/16
252 Rough In Walls-Plumbing 3 days Thu 6/30/16 Tue 7/5/16
253 Rough In Above Ceiling Plumbing 4 days Wed 7/6/16 Mon 7/11/16
251 Set Plumbing Carriers 3 days Tue 7/12/16 Thu 7/14/16
255 Install Floor Drains 4 days Tue 7/12/16 Fri 7/15/16
254 Trim Out Plumbing 3 days Mon 7/18/16 Wed 7/20/16
274 Finishing 73 days Thu 6/30/16 Thu 10/13/16
291 Installation of Exterior Window 5 days Thu 6/30/16 Thu 7/7/16
277 Drop In Ceiling Tile 4 days Mon 7/25/16 Thu 7/28/16
281 Install Ceramic Tile In Bathrooms 2 days Fri 7/29/16 Mon 8/1/16
286 Prime And First Coat Walls And Hard Ceilings 4 days Tue 8/2/16 Fri 8/5/16
284 Hang Drywall 3 days Mon 8/8/16 Wed 8/10/16
285 Finish Drywall 3 days Thu 8/11/16 Mon 8/15/16
292 Installation of Suspended Ceiling Grid 7 days Thu 8/11/16 Fri 8/19/16
276 Install Vinyl Flooring 4 days Tue 8/16/16 Fri 8/19/16
287 Epoxy Painting 3 days Tue 8/30/16 Thu 9/1/16
275 Final Coat Painting 3 days Fri 9/2/16 Wed 9/7/16
288 Doors & Hdw Installation 4 days Thu 9/8/16 Tue 9/13/16
289 Interior Glass Installation 3 days Wed 9/14/16 Fri 9/16/16
278 Install Equipment-Security System 3 days Mon 9/19/16 Wed 9/21/16
282 Install Equipment-Fire Alarm 3 days Thu 9/22/16 Mon 9/26/16
283 Install Va Equipment-Cabinetry 3 days Tue 9/27/16 Thu 9/29/16
279 Install Va Equipment-Appliances 3 days Fri 9/30/16 Tue 10/4/16
280 Install Equipment-Motorized Windowshades 3 days Wed 10/5/16 Fri 10/7/16
290 Install Va Equipment-Furniture 3 days Tue 10/11/16 Thu 10/13/16
256 Electrical /Lighiting Works 13 days Wed 7/6/16 Fri 7/22/16
259 Rough In Electrical Conduit And Wire 4 days Wed 7/6/16 Mon 7/11/16
257 Install Lighting Conduits 3 days Tue 7/12/16 Thu 7/14/16
260 Trim Out Electrical 3 days Fri 7/15/16 Tue 7/19/16
258 Trim Out Lighting 3 days Wed 7/20/16 Fri 7/22/16
261 Mechanical / HVAC / Fire Sprinkler 28 days Thu 7/21/16 Mon 8/29/16
264 Install Ac Ductwork 3 days Thu 7/21/16 Mon 7/25/16
265 Install Vav Cw Hw Piping 3 days Tue 7/26/16 Thu 7/28/16
263 Insulate Ductwork 3 days Fri 7/29/16 Tue 8/2/16
262 Pressure Test Ductwork 2 days Wed 8/3/16 Thu 8/4/16
268 Rough In Low Voltage 2 days Fri 8/5/16 Mon 8/8/16
269 Rough In Mechanical 3 days Tue 8/9/16 Thu 8/11/16
270 Rough In Med Gas 3 days Fri 8/12/16 Tue 8/16/16
266 Rough In For Fire Sprinkler Pipe 3 days Wed 8/17/16 Fri 8/19/16
271 Trim Out Mechanical 4 days Mon 8/22/16 Thu 8/25/16
272 Trim Out Med Gas 4 days Mon 8/22/16 Thu 8/25/16
273 Trim Out Fire Sprinkler 3 days Mon 8/22/16 Wed 8/24/16
267 Trim Out Low Voltage 3 days Thu 8/25/16 Mon 8/29/16
Rough In Low Voltage
Rough In Mechanical
Rough In Med Gas
Rough In For Fire Sprinkler Pipe
Trim Out Mechanical
Trim Out Fire Sprinkler
Trim Out Med Gas
Trim Out Low Voltage
Install Bass Plates / Columns
Install Steel Framing
Install Steel Bracing
Install Metal Decking
Install batt insulation
Frame wall openings
Install Batt insulation
Install interiol dans - glass sheathing
Install pvc wainscot
Install Extrior Dens Glass Sheathing
Install J-Channel , Z-Girts
Install Water Resistive Barrier
Install Metal Wall Panels
Install Rigid Insulation
Install Roof Dens-Deck
Install Metal Roof Panels
Install Gutters / Downspouts
Rough In Walls-Plumbing
Rough In Above Ceiling Plumbing
Set Plumbing Carriers
Install Floor Drains
Trim Out Plumbing
Installation of Exterior Window
Drop In Ceiling Tile
Install Ceramic Tile In Bathrooms
Prime And First Coat Walls And Hard Ceilings
Hang Drywall
Finish Drywall
Installation of Suspended Ceiling Grid
Install Vinyl Flooring
Epoxy Painting
Final Coat Painting
Doors & Hdw Installation
Interior Glass Installation
Install Equipment-Security System
Install Equipment-Fire Alarm
Install Va Equipment-Cabinetry
Install Va Equipment-Appliances
Install Equipment-Motorized Windowshades
Install Va Equipment-Furniture
Rough In Electrical Conduit And Wire
Install Lighting Conduits
Trim Out Electrical
Trim Out Lighting
Install Ac Ductwork
Install Vav Cw Hw Piping
Insulate Ductwork
Pressure Test Ductwork
Rough In Low Voltage
Rough In Mechanical
Rough In Med Gas
Rough In For Fire Sprinkler Pipe
Trim Out Mechanical
Trim Out Med Gas
Trim Out Fire Sprinkler
Trim Out Low Voltage
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
Sep 27, '15 Oct 18, '15 Nov 8, '15 Nov 29, '15 Dec 20, '15 Jan 10, '16 Jan 31, '16 Feb 21, '16 Mar 13, '16 Apr 3, '16 Apr 24, '16 May 15, '16 Jun 5, '16 Jun 26, '16 Jul 17, '16 Aug 7, '16 Aug 28, '16 Sep 18, '16 Oct 9, '16 Oct 30, '16 Nov 20, '16 Dec 11, '16 Jan 1, '17 Jan 22, '17 Feb 12, '17
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 4
Date: Sun 2/28/16
ID Task Name Duration Start Finish
293 Paving and Site Restoration 10 days Fri 10/14/16 Thu 10/27/16
297 BIT CONC Pavement 2 days Fri 10/14/16 Mon 10/17/16
294 Survey Paving 1 day Tue 10/18/16 Tue 10/18/16
295 Heavy - Duty Bituminous Paving 3 days Wed 10/19/16 Fri 10/21/16
296 Fine Grading / Place Gravel 2 days Mon 10/24/16 Tue 10/25/16
298 Site Clearing 2 days Wed 10/26/16 Thu 10/27/16
299 Commissioning & Turn Over 12 days Fri 10/28/16 Tue 11/15/16
305 Submission and Approval Commissioning Procedures 2 days Fri 10/28/16 Mon 10/31/16
304 Perform Test And Balance 2 days Tue 11/1/16 Wed 11/2/16
300 Review And Approve (Va) Test And Balance Report 2 days Thu 11/3/16 Fri 11/4/16
301 Conduct Pre-Commissioning Coordination Meeting 2 days Mon 11/7/16 Tue 11/8/16
302 Conduct Commissioning - Functional Performance Testing 2 days Wed 11/9/16 Thu 11/10/16
303 Review And Approve (Va) Commissioning-Building Systems Report 2 days Mon 11/14/16 Tue 11/15/16
306 Contract Close Out 20 days Tue 11/15/16 Wed 12/14/16
307 Substantial Completion 0 days Tue 11/15/16 Tue 11/15/16
308 Punchlist 10 days Wed 11/16/16 Wed 11/30/16
309 Pass Va Final Inspection 5 days Thu 12/1/16 Wed 12/7/16
311 Demobilization 5 days Thu 12/8/16 Wed 12/14/16
310 Finish Completion 0 days Wed 12/14/16 Wed 12/14/16
BIT CONC Pavement
Survey Paving
Heavy - Duty Bituminous Paving
Fine Grading / Place Gravel
Site Clearing
Submission and Approval Commissioning Procedures
Perform Test And Balance
Review And Approve (Va) Test And Balance Report
Conduct Pre-Commissioning Coordination Meeting
Conduct Commissioning - Functional Performance Testing
Review And Approve (Va) Commissioning-Building Systems Report
11/15
Punchlist
Pass Va Final Inspection
Demobilization
12/14
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
Sep 27, '15 Oct 18, '15 Nov 8, '15 Nov 29, '15 Dec 20, '15 Jan 10, '16 Jan 31, '16 Feb 21, '16 Mar 13, '16 Apr 3, '16 Apr 24, '16 May 15, '16 Jun 5, '16 Jun 26, '16 Jul 17, '16 Aug 7, '16 Aug 28, '16 Sep 18, '16 Oct 9, '16 Oct 30, '16 Nov 20, '16 Dec 11, '16 Jan 1, '17 Jan 22, '17 Feb 12, '17
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 5
Date: Sun 2/28/16

More Related Content

What's hot

Portfolio Civil / Structural Engineer | Designer | Manager
Portfolio Civil / Structural Engineer | Designer | ManagerPortfolio Civil / Structural Engineer | Designer | Manager
Portfolio Civil / Structural Engineer | Designer | Manager
Oleg Kilchevskiy
 
Planning For Engineering
Planning For EngineeringPlanning For Engineering
Planning For Engineering
Joe Kalchbrenner
 
Project management plan for Global Project Management Conference (GPM)
Project management plan for Global Project Management Conference (GPM)Project management plan for Global Project Management Conference (GPM)
Project management plan for Global Project Management Conference (GPM)
Lúcia Dénis
 
CV-Mechanical Engineer.
CV-Mechanical Engineer.CV-Mechanical Engineer.
CV-Mechanical Engineer.
AZHAR QAZI
 
Basic engineering_Checklist
Basic engineering_ChecklistBasic engineering_Checklist
Basic engineering_Checklist
Stephanus Roux C Eng , IntPE(uk) , FIET
 
Advanced Work Packaging: Implementation Challenges
Advanced Work Packaging: Implementation ChallengesAdvanced Work Packaging: Implementation Challenges
Advanced Work Packaging: Implementation Challenges
The Advanced Work Packaging Institute
 
Jacket
JacketJacket
Jacket
esa subakti
 
Tanveer Sr Planning Engineer
Tanveer Sr Planning EngineerTanveer Sr Planning Engineer
Tanveer Sr Planning Engineer
Tanveer Ahmed Niazi
 
RAMESH_Resume
RAMESH_ResumeRAMESH_Resume
RAMESH_Resume
Kurupati Ramesh Babu
 
Estimation Engineer
Estimation EngineerEstimation Engineer
Estimation Engineer
Zafar Ali
 
Epc presentation robert foxpresentation
Epc presentation robert foxpresentationEpc presentation robert foxpresentation
Epc presentation robert foxpresentation
raghunathan janarthanan
 
Sample wbs for_upstream_epcic_project
Sample wbs for_upstream_epcic_projectSample wbs for_upstream_epcic_project
Sample wbs for_upstream_epcic_project
ignitetribes
 
PMP Process Chart - 6th Edition
PMP Process Chart - 6th EditionPMP Process Chart - 6th Edition
PMP Process Chart - 6th Edition
Nasser Al mohimeed,PMP
 
new cv
new cvnew cv
new cv
surjya malik
 
Advanced project scheduling: proper practices for integrated project schedules
Advanced project scheduling: proper practices for integrated project schedulesAdvanced project scheduling: proper practices for integrated project schedules
Advanced project scheduling: proper practices for integrated project schedules
Jeremie Averous
 
Metode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.pptMetode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.ppt
MFaridGeonova
 
WORKFLOW
WORKFLOW WORKFLOW
WORKFLOW
TW Carl
 
Project Management Methodologies - Mind Map
Project Management Methodologies - Mind MapProject Management Methodologies - Mind Map
Project Management Methodologies - Mind Map
WAJAHAT IQBAL
 
role of project manager in PMC
role of project manager in PMCrole of project manager in PMC
role of project manager in PMC
Mayank Kumar
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
M Maged Hegazy, LLM, MBA, CCP, P3O
 

What's hot (20)

Portfolio Civil / Structural Engineer | Designer | Manager
Portfolio Civil / Structural Engineer | Designer | ManagerPortfolio Civil / Structural Engineer | Designer | Manager
Portfolio Civil / Structural Engineer | Designer | Manager
 
Planning For Engineering
Planning For EngineeringPlanning For Engineering
Planning For Engineering
 
Project management plan for Global Project Management Conference (GPM)
Project management plan for Global Project Management Conference (GPM)Project management plan for Global Project Management Conference (GPM)
Project management plan for Global Project Management Conference (GPM)
 
CV-Mechanical Engineer.
CV-Mechanical Engineer.CV-Mechanical Engineer.
CV-Mechanical Engineer.
 
Basic engineering_Checklist
Basic engineering_ChecklistBasic engineering_Checklist
Basic engineering_Checklist
 
Advanced Work Packaging: Implementation Challenges
Advanced Work Packaging: Implementation ChallengesAdvanced Work Packaging: Implementation Challenges
Advanced Work Packaging: Implementation Challenges
 
Jacket
JacketJacket
Jacket
 
Tanveer Sr Planning Engineer
Tanveer Sr Planning EngineerTanveer Sr Planning Engineer
Tanveer Sr Planning Engineer
 
RAMESH_Resume
RAMESH_ResumeRAMESH_Resume
RAMESH_Resume
 
Estimation Engineer
Estimation EngineerEstimation Engineer
Estimation Engineer
 
Epc presentation robert foxpresentation
Epc presentation robert foxpresentationEpc presentation robert foxpresentation
Epc presentation robert foxpresentation
 
Sample wbs for_upstream_epcic_project
Sample wbs for_upstream_epcic_projectSample wbs for_upstream_epcic_project
Sample wbs for_upstream_epcic_project
 
PMP Process Chart - 6th Edition
PMP Process Chart - 6th EditionPMP Process Chart - 6th Edition
PMP Process Chart - 6th Edition
 
new cv
new cvnew cv
new cv
 
Advanced project scheduling: proper practices for integrated project schedules
Advanced project scheduling: proper practices for integrated project schedulesAdvanced project scheduling: proper practices for integrated project schedules
Advanced project scheduling: proper practices for integrated project schedules
 
Metode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.pptMetode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.ppt
 
WORKFLOW
WORKFLOW WORKFLOW
WORKFLOW
 
Project Management Methodologies - Mind Map
Project Management Methodologies - Mind MapProject Management Methodologies - Mind Map
Project Management Methodologies - Mind Map
 
role of project manager in PMC
role of project manager in PMCrole of project manager in PMC
role of project manager in PMC
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 

Viewers also liked

Project Charter Template - Document for Project Initiation
Project Charter Template - Document for Project InitiationProject Charter Template - Document for Project Initiation
Project Charter Template - Document for Project Initiation
Dhawal Thakkar PMP
 
Bottom up estimating worksheet : Ready template
Bottom up estimating worksheet : Ready templateBottom up estimating worksheet : Ready template
Bottom up estimating worksheet : Ready template
Dhawal Thakkar PMP
 
Cost management plan : Ready template
Cost management plan : Ready templateCost management plan : Ready template
Cost management plan : Ready template
Dhawal Thakkar PMP
 
Change management plan : Ready template
Change management plan : Ready templateChange management plan : Ready template
Change management plan : Ready template
Dhawal Thakkar PMP
 
Project Management Activity Cost Estimate
Project Management Activity Cost EstimateProject Management Activity Cost Estimate
Project Management Activity Cost Estimate
Dhawal Thakkar PMP
 
Activity Duration Estimate - Ready template
Activity Duration Estimate - Ready templateActivity Duration Estimate - Ready template
Activity Duration Estimate - Ready template
Dhawal Thakkar PMP
 
human resource management plan : ready template
human resource management plan : ready templatehuman resource management plan : ready template
human resource management plan : ready template
Dhawal Thakkar PMP
 
WBS dictionary: Work Breakdown Structure Dictionary
WBS dictionary: Work Breakdown Structure DictionaryWBS dictionary: Work Breakdown Structure Dictionary
WBS dictionary: Work Breakdown Structure Dictionary
Dhawal Thakkar PMP
 
Gantt Charts
Gantt ChartsGantt Charts
Gantt Charts
Nadine Fisher
 
Lecture5---Gantt Chart
Lecture5---Gantt ChartLecture5---Gantt Chart
Lecture5---Gantt Chart
danishrafiq
 
Inm410 work-breakdown-schedule v2
Inm410 work-breakdown-schedule v2Inm410 work-breakdown-schedule v2
Inm410 work-breakdown-schedule v2
Jonah Sherman-Waterman
 
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo
 
Construction Photo Essay Project
Construction Photo Essay ProjectConstruction Photo Essay Project
Construction Photo Essay Project
Timothy Shih
 
J press Stainless Steel piping
J press Stainless Steel pipingJ press Stainless Steel piping
J press Stainless Steel piping
Pravin Goel
 
World of bathrooms 2010 - Villeroy & Boch | Hùng Hiền Luxury Co., Ltd
World of bathrooms 2010 - Villeroy & Boch | Hùng Hiền Luxury Co., LtdWorld of bathrooms 2010 - Villeroy & Boch | Hùng Hiền Luxury Co., Ltd
World of bathrooms 2010 - Villeroy & Boch | Hùng Hiền Luxury Co., Ltd
Hùng Hiền Luxury
 

Viewers also liked (15)

Project Charter Template - Document for Project Initiation
Project Charter Template - Document for Project InitiationProject Charter Template - Document for Project Initiation
Project Charter Template - Document for Project Initiation
 
Bottom up estimating worksheet : Ready template
Bottom up estimating worksheet : Ready templateBottom up estimating worksheet : Ready template
Bottom up estimating worksheet : Ready template
 
Cost management plan : Ready template
Cost management plan : Ready templateCost management plan : Ready template
Cost management plan : Ready template
 
Change management plan : Ready template
Change management plan : Ready templateChange management plan : Ready template
Change management plan : Ready template
 
Project Management Activity Cost Estimate
Project Management Activity Cost EstimateProject Management Activity Cost Estimate
Project Management Activity Cost Estimate
 
Activity Duration Estimate - Ready template
Activity Duration Estimate - Ready templateActivity Duration Estimate - Ready template
Activity Duration Estimate - Ready template
 
human resource management plan : ready template
human resource management plan : ready templatehuman resource management plan : ready template
human resource management plan : ready template
 
WBS dictionary: Work Breakdown Structure Dictionary
WBS dictionary: Work Breakdown Structure DictionaryWBS dictionary: Work Breakdown Structure Dictionary
WBS dictionary: Work Breakdown Structure Dictionary
 
Gantt Charts
Gantt ChartsGantt Charts
Gantt Charts
 
Lecture5---Gantt Chart
Lecture5---Gantt ChartLecture5---Gantt Chart
Lecture5---Gantt Chart
 
Inm410 work-breakdown-schedule v2
Inm410 work-breakdown-schedule v2Inm410 work-breakdown-schedule v2
Inm410 work-breakdown-schedule v2
 
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
 
Construction Photo Essay Project
Construction Photo Essay ProjectConstruction Photo Essay Project
Construction Photo Essay Project
 
J press Stainless Steel piping
J press Stainless Steel pipingJ press Stainless Steel piping
J press Stainless Steel piping
 
World of bathrooms 2010 - Villeroy & Boch | Hùng Hiền Luxury Co., Ltd
World of bathrooms 2010 - Villeroy & Boch | Hùng Hiền Luxury Co., LtdWorld of bathrooms 2010 - Villeroy & Boch | Hùng Hiền Luxury Co., Ltd
World of bathrooms 2010 - Villeroy & Boch | Hùng Hiền Luxury Co., Ltd
 

Similar to MS project Sample gantt chart

program
programprogram
Engineering Design Center Project Schedule
Engineering Design Center Project ScheduleEngineering Design Center Project Schedule
Engineering Design Center Project Schedule
Virginia Kam
 
Chw piping works rev 6
  Chw piping works rev 6  Chw piping works rev 6
Chw piping works rev 6
JESSEREY BUSTAMANTE
 
Projec
ProjecProjec
Encanex - Hebron Access, Captens Brdidge, Power, Cement Barge and ICS Basket...
Encanex - Hebron  Access, Captens Brdidge, Power, Cement Barge and ICS Basket...Encanex - Hebron  Access, Captens Brdidge, Power, Cement Barge and ICS Basket...
Encanex - Hebron Access, Captens Brdidge, Power, Cement Barge and ICS Basket...
Ali Yousef
 
Popop
PopopPopop
MS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation ScheduleMS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation Schedule
Gensol Engineering Limited
 
Single Family Gantt Chart-John Mueller
Single Family Gantt Chart-John MuellerSingle Family Gantt Chart-John Mueller
Single Family Gantt Chart-John Mueller
John Mueller
 
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)  WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
Ali Yousef
 
Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis
Ayon Pal
 
Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis
ayonpal
 
ADCO Time plan.pdf
ADCO Time plan.pdfADCO Time plan.pdf
ADCO Time plan.pdf
abdo badr
 
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design ScheduleFitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
Gary Hayes
 
38 Avenue Road- Rev 1, Detailed Programme
38 Avenue Road- Rev 1, Detailed Programme38 Avenue Road- Rev 1, Detailed Programme
38 Avenue Road- Rev 1, Detailed Programme
Beenish Ali
 
Jadwal Pelaksanaan PPI.pdf
Jadwal Pelaksanaan PPI.pdfJadwal Pelaksanaan PPI.pdf
Jadwal Pelaksanaan PPI.pdf
GaluhWulandari10
 
ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0
Ahmed Khaled
 
IHH Healthcare Tender Programme.pdf
IHH Healthcare Tender Programme.pdfIHH Healthcare Tender Programme.pdf
IHH Healthcare Tender Programme.pdf
SubramanianSaravanan8
 
Nework digram .pdf
Nework digram .pdfNework digram .pdf
Nework digram .pdf
dks
 
ABC_3rd Progress Mtg Briefing_050115_draft.ppt
ABC_3rd Progress Mtg Briefing_050115_draft.pptABC_3rd Progress Mtg Briefing_050115_draft.ppt
ABC_3rd Progress Mtg Briefing_050115_draft.ppt
KingHaroldDeLeon
 
Residential Conctruction Gantt Chart
Residential Conctruction Gantt ChartResidential Conctruction Gantt Chart
Residential Conctruction Gantt Chart
Adrian Cocorocchio
 

Similar to MS project Sample gantt chart (20)

program
programprogram
program
 
Engineering Design Center Project Schedule
Engineering Design Center Project ScheduleEngineering Design Center Project Schedule
Engineering Design Center Project Schedule
 
Chw piping works rev 6
  Chw piping works rev 6  Chw piping works rev 6
Chw piping works rev 6
 
Projec
ProjecProjec
Projec
 
Encanex - Hebron Access, Captens Brdidge, Power, Cement Barge and ICS Basket...
Encanex - Hebron  Access, Captens Brdidge, Power, Cement Barge and ICS Basket...Encanex - Hebron  Access, Captens Brdidge, Power, Cement Barge and ICS Basket...
Encanex - Hebron Access, Captens Brdidge, Power, Cement Barge and ICS Basket...
 
Popop
PopopPopop
Popop
 
MS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation ScheduleMS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation Schedule
 
Single Family Gantt Chart-John Mueller
Single Family Gantt Chart-John MuellerSingle Family Gantt Chart-John Mueller
Single Family Gantt Chart-John Mueller
 
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)  WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
 
Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis
 
Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis
 
ADCO Time plan.pdf
ADCO Time plan.pdfADCO Time plan.pdf
ADCO Time plan.pdf
 
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design ScheduleFitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
 
38 Avenue Road- Rev 1, Detailed Programme
38 Avenue Road- Rev 1, Detailed Programme38 Avenue Road- Rev 1, Detailed Programme
38 Avenue Road- Rev 1, Detailed Programme
 
Jadwal Pelaksanaan PPI.pdf
Jadwal Pelaksanaan PPI.pdfJadwal Pelaksanaan PPI.pdf
Jadwal Pelaksanaan PPI.pdf
 
ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0
 
IHH Healthcare Tender Programme.pdf
IHH Healthcare Tender Programme.pdfIHH Healthcare Tender Programme.pdf
IHH Healthcare Tender Programme.pdf
 
Nework digram .pdf
Nework digram .pdfNework digram .pdf
Nework digram .pdf
 
ABC_3rd Progress Mtg Briefing_050115_draft.ppt
ABC_3rd Progress Mtg Briefing_050115_draft.pptABC_3rd Progress Mtg Briefing_050115_draft.ppt
ABC_3rd Progress Mtg Briefing_050115_draft.ppt
 
Residential Conctruction Gantt Chart
Residential Conctruction Gantt ChartResidential Conctruction Gantt Chart
Residential Conctruction Gantt Chart
 

More from Dhawal Thakkar PMP

PMP 35 hrs Training details- by www.ProjectSupportTools.com
PMP 35 hrs Training details- by www.ProjectSupportTools.comPMP 35 hrs Training details- by www.ProjectSupportTools.com
PMP 35 hrs Training details- by www.ProjectSupportTools.com
Dhawal Thakkar PMP
 
Inter requirement traceability matrix : Ready template
Inter requirement traceability matrix : Ready templateInter requirement traceability matrix : Ready template
Inter requirement traceability matrix : Ready template
Dhawal Thakkar PMP
 
Risk register or Risk log - A template to list down all the indentified Risk
Risk register or Risk log - A template to list down all the indentified Risk Risk register or Risk log - A template to list down all the indentified Risk
Risk register or Risk log - A template to list down all the indentified Risk
Dhawal Thakkar PMP
 
Risk data sheet - a template to collect risk data attributes
Risk data sheet - a template to collect risk data attributes Risk data sheet - a template to collect risk data attributes
Risk data sheet - a template to collect risk data attributes
Dhawal Thakkar PMP
 
Assumption and Constrains log - A Project Management Document.
Assumption and Constrains log - A Project Management Document.Assumption and Constrains log - A Project Management Document.
Assumption and Constrains log - A Project Management Document.
Dhawal Thakkar PMP
 
Stakeholder register - From Applica Consultany
Stakeholder register - From Applica ConsultanyStakeholder register - From Applica Consultany
Stakeholder register - From Applica Consultany
Dhawal Thakkar PMP
 
How to search a job on Naukri.com and how does the SEO of Naukri.com works
How to search a job on Naukri.com and how does the SEO of Naukri.com works How to search a job on Naukri.com and how does the SEO of Naukri.com works
How to search a job on Naukri.com and how does the SEO of Naukri.com works
Dhawal Thakkar PMP
 

More from Dhawal Thakkar PMP (7)

PMP 35 hrs Training details- by www.ProjectSupportTools.com
PMP 35 hrs Training details- by www.ProjectSupportTools.comPMP 35 hrs Training details- by www.ProjectSupportTools.com
PMP 35 hrs Training details- by www.ProjectSupportTools.com
 
Inter requirement traceability matrix : Ready template
Inter requirement traceability matrix : Ready templateInter requirement traceability matrix : Ready template
Inter requirement traceability matrix : Ready template
 
Risk register or Risk log - A template to list down all the indentified Risk
Risk register or Risk log - A template to list down all the indentified Risk Risk register or Risk log - A template to list down all the indentified Risk
Risk register or Risk log - A template to list down all the indentified Risk
 
Risk data sheet - a template to collect risk data attributes
Risk data sheet - a template to collect risk data attributes Risk data sheet - a template to collect risk data attributes
Risk data sheet - a template to collect risk data attributes
 
Assumption and Constrains log - A Project Management Document.
Assumption and Constrains log - A Project Management Document.Assumption and Constrains log - A Project Management Document.
Assumption and Constrains log - A Project Management Document.
 
Stakeholder register - From Applica Consultany
Stakeholder register - From Applica ConsultanyStakeholder register - From Applica Consultany
Stakeholder register - From Applica Consultany
 
How to search a job on Naukri.com and how does the SEO of Naukri.com works
How to search a job on Naukri.com and how does the SEO of Naukri.com works How to search a job on Naukri.com and how does the SEO of Naukri.com works
How to search a job on Naukri.com and how does the SEO of Naukri.com works
 

Recently uploaded

How to Manage Your Lost Opportunities in Odoo 17 CRM
How to Manage Your Lost Opportunities in Odoo 17 CRMHow to Manage Your Lost Opportunities in Odoo 17 CRM
How to Manage Your Lost Opportunities in Odoo 17 CRM
Celine George
 
Main Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docxMain Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docx
adhitya5119
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
chanes7
 
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
National Information Standards Organization (NISO)
 
The basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptxThe basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptx
heathfieldcps1
 
S1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptxS1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptx
tarandeep35
 
Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
adhitya5119
 
Group Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana BuscigliopptxGroup Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana Buscigliopptx
ArianaBusciglio
 
South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)
Academy of Science of South Africa
 
MARY JANE WILSON, A “BOA MÃE” .
MARY JANE WILSON, A “BOA MÃE”           .MARY JANE WILSON, A “BOA MÃE”           .
MARY JANE WILSON, A “BOA MÃE” .
Colégio Santa Teresinha
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
eBook.com.bd (প্রয়োজনীয় বাংলা বই)
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
Levi Shapiro
 
Film vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movieFilm vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movie
Nicholas Montgomery
 
Azure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHatAzure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHat
Scholarhat
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
Peter Windle
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
thanhdowork
 
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat  Leveraging AI for Diversity, Equity, and InclusionExecutive Directors Chat  Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
TechSoup
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
Jean Carlos Nunes Paixão
 
Pride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School DistrictPride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School District
David Douglas School District
 
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
IreneSebastianRueco1
 

Recently uploaded (20)

How to Manage Your Lost Opportunities in Odoo 17 CRM
How to Manage Your Lost Opportunities in Odoo 17 CRMHow to Manage Your Lost Opportunities in Odoo 17 CRM
How to Manage Your Lost Opportunities in Odoo 17 CRM
 
Main Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docxMain Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docx
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
 
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
 
The basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptxThe basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptx
 
S1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptxS1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptx
 
Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
 
Group Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana BuscigliopptxGroup Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana Buscigliopptx
 
South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)
 
MARY JANE WILSON, A “BOA MÃE” .
MARY JANE WILSON, A “BOA MÃE”           .MARY JANE WILSON, A “BOA MÃE”           .
MARY JANE WILSON, A “BOA MÃE” .
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
 
Film vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movieFilm vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movie
 
Azure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHatAzure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHat
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
 
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat  Leveraging AI for Diversity, Equity, and InclusionExecutive Directors Chat  Leveraging AI for Diversity, Equity, and Inclusion
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
 
Pride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School DistrictPride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School District
 
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
 

MS project Sample gantt chart

  • 1. ID Task Name Duration Start Finish 1 Start Up 288 days Thu 10/22/15 Wed 12/14/16 2 Pre-Construction Meeting 0 days Thu 10/22/15 Thu 10/22/15 3 Overall Project Duration 420 days Thu 10/22/15 Wed 12/14/16 4 Notice To Proceed 0 days Thu 10/22/15 Thu 10/22/15 5 Mobilization 1 day Thu 10/22/15 Thu 10/22/15 6 Pre Construction Submittal Process 30 days Thu 10/22/15 Fri 12/4/15 7 Pre Con Submittals 30 days Thu 10/22/15 Fri 12/4/15 8 Submission and Approval Bc Safety Plan 30 days Thu 10/22/15 Fri 12/4/15 9 Submission and Approval Bc Qa/Qc Plan 30 days Thu 10/22/15 Fri 12/4/15 10 Construction Submittal Process 50 days Thu 10/22/15 Tue 1/5/16 11 Construction Submittals 30 days Thu 10/22/15 Fri 12/4/15 12 Submission and Approval Plumbing Carriers 30 days Thu 10/22/15 Fri 12/4/15 13 Submission and Approval Plumbing Piping 30 days Thu 10/22/15 Fri 12/4/15 14 Submission and Approval Plumbing Fixtures 30 days Thu 10/22/15 Fri 12/4/15 15 Submission and Approval Ductwork For Hvac 30 days Thu 10/22/15 Fri 12/4/15 16 Submission and Approval Piping For Hvac 30 days Thu 10/22/15 Fri 12/4/15 17 Submission and Approval Equipment For Hvac 30 days Thu 10/22/15 Fri 12/4/15 18 Submission and Approval Med Gas Material 30 days Thu 10/22/15 Fri 12/4/15 19 Submission and Approval Electrical Wiring 30 days Thu 10/22/15 Fri 12/4/15 20 Submission and Approval Lighting 30 days Thu 10/22/15 Fri 12/4/15 21 Submission and Approval Raceway And Boxes For Electrical Systems 30 days Thu 10/22/15 Fri 12/4/15 22 Submission and Approval Fire Detection Alarm 30 days Thu 10/22/15 Fri 12/4/15 23 Submission and Approval Cast-In-Place Concrete 30 days Thu 10/22/15 Fri 12/4/15 24 Submission and Approval Building Insulation 30 days Thu 10/22/15 Fri 12/4/15 25 Submission and Approval Framing Plan 30 days Thu 10/22/15 Fri 12/4/15 26 Submission and Approval Foundation Plan 30 days Thu 10/22/15 Fri 12/4/15 27 Submission and Approval Door Hardware 30 days Thu 10/22/15 Fri 12/4/15 28 Submission and Approval Glazing 30 days Thu 10/22/15 Fri 12/4/15 29 Submission and Approval Non Structural Metal Framing 30 days Thu 10/22/15 Fri 12/4/15 30 Submission and Approval Gypsum Board 30 days Thu 10/22/15 Fri 12/4/15 31 Submission and Approval Ceramic Tiling 30 days Thu 10/22/15 Fri 12/4/15 32 Submission and Approval Acoustical Ceilings 30 days Thu 10/22/15 Fri 12/4/15 33 Submission and Approval Flooring 30 days Thu 10/22/15 Fri 12/4/15 34 Submission and Approval Painting 30 days Thu 10/22/15 Fri 12/4/15 35 Submission and Approval Toilet, Bath, And Laundry Accessories 30 days Thu 10/22/15 Fri 12/4/15 36 Submission and Approval Fire Extinguisher Cabinets 30 days Thu 10/22/15 Fri 12/4/15 37 Submission and Approval Wet-Pipe Sprinkler Systmes 30 days Thu 10/22/15 Fri 12/4/15 38 Fabrication and Delivery 20 days Mon 12/7/15 Tue 1/5/16 39 Fabricate & Deliver Drywall 20 days Mon 12/7/15 Tue 1/5/16 40 Fabricate & Deliver Plumbing Pipe 20 days Mon 12/7/15 Tue 1/5/16 41 Fabricate & Deliver Plumbing Carriers 20 days Mon 12/7/15 Tue 1/5/16 42 Fabricate & Deliver Fire Sprinkler Piping 20 days Mon 12/7/15 Tue 1/5/16 43 Fabricate & Deliver Ductwork 20 days Mon 12/7/15 Tue 1/5/16 44 Fabricate & Deliver Lighting Fixtures 20 days Mon 12/7/15 Tue 1/5/16 45 Fabricate & Deliver Plumbing Fixtures 20 days Mon 12/7/15 Tue 1/5/16 46 Fabricate & Deliver Doors & Hardware 20 days Mon 12/7/15 Tue 1/5/16 47 Fabricate & Deliver Ceramic Tile 20 days Mon 12/7/15 Tue 1/5/16 48 Fabricate & Deliver Metal Framing Materials 20 days Mon 12/7/15 Tue 1/5/16 49 Fabricate & Deliver Electrical Conduit 20 days Mon 12/7/15 Tue 1/5/16 50 Construction 288 days Thu 10/22/15 Wed 12/14/16 51 Building 20 & 21& New Additions 288 days Thu 10/22/15 Wed 12/14/16 52 Site Works 288 days Thu 10/22/15 Wed 12/14/16 64 General 288 days Thu 10/22/15 Wed 12/14/16 77 Erosion and Sediment Control 288 days Thu 10/22/15 Wed 12/14/16 70 Rough in of Underground Sanitary Waste Lines 5 days Thu 12/31/15 Thu 1/7/16 65 Install New HVAC Concerete Pad 5 days Fri 1/8/16 Thu 1/14/16 66 Install New Electrical Conduits For Generator 1 day Fri 1/8/16 Fri 1/8/16 76 Install Sanitary Waste Lines 3 days Fri 1/8/16 Tue 1/12/16 67 Install New Generator Pad 1 day Mon 1/11/16 Mon 1/11/16 71 Install New Natural Gas Line 5 days Mon 1/11/16 Fri 1/15/16 68 Install New Transformer Conduits 1 day Tue 1/12/16 Tue 1/12/16 69 Install New Transformer Concerete Pad 1 day Wed 1/13/16 Wed 1/13/16 75 Install Sanitary Vent Lines 3 days Wed 1/13/16 Fri 1/15/16 74 Install Plumbing Water Lines 3 days Tue 1/19/16 Thu 1/21/16 73 Install Storm Pipe 5 days Fri 1/22/16 Thu 1/28/16 78 Grading Sediment Control 2 days Fri 1/29/16 Mon 2/1/16 72 Install Temporary Bollard 5 days Tue 2/2/16 Mon 2/8/16 53 Demolition 17 days Mon 12/7/15 Wed 12/30/15 63 Removal of Trees 5 days Mon 12/7/15 Fri 12/11/15 55 Remove & Cap Sanitary Piping 4 days Fri 12/11/15 Wed 12/16/15 62 Paint Removal Using Sand Blasting of Exterior Walls 5 days Mon 12/14/15 Fri 12/18/15 60 Remove Top Soil 1 day Thu 12/17/15 Thu 12/17/15 61 Remove Abandoned 8'' Water Main 1 day Fri 12/18/15 Fri 12/18/15 10/22 Overall Project Duration 10/22 Mobilization Submission and Approval Bc Safety Plan Submission and Approval Bc Qa/Qc Plan Submission and Approval Plumbing Carriers Submission and Approval Plumbing Piping Submission and Approval Plumbing Fixtures Submission and Approval Ductwork For Hvac Submission and Approval Piping For Hvac Submission and Approval Equipment For Hvac Submission and Approval Med Gas Material Submission and Approval Electrical Wiring Submission and Approval Lighting Submission and Approval Raceway And Boxes For Electrical Systems Submission and Approval Fire Detection Alarm Submission and Approval Cast-In-Place Concrete Submission and Approval Building Insulation Submission and Approval Framing Plan Submission and Approval Foundation Plan Submission and Approval Door Hardware Submission and Approval Glazing Submission and Approval Non Structural Metal Framing Submission and Approval Gypsum Board Submission and Approval Ceramic Tiling Submission and Approval Acoustical Ceilings Submission and Approval Flooring Submission and Approval Painting Submission and Approval Toilet, Bath, And Laundry Accessories Submission and Approval Fire Extinguisher Cabinets Submission and Approval Wet-Pipe Sprinkler Systmes Fabricate & Deliver Drywall Fabricate & Deliver Plumbing Pipe Fabricate & Deliver Plumbing Carriers Fabricate & Deliver Fire Sprinkler Piping Fabricate & Deliver Ductwork Fabricate & Deliver Lighting Fixtures Fabricate & Deliver Plumbing Fixtures Fabricate & Deliver Doors & Hardware Fabricate & Deliver Ceramic Tile Fabricate & Deliver Metal Framing Materials Fabricate & Deliver Electrical Conduit Erosion and Sediment Control Rough in of Underground Sanitary Waste Lines Install New HVAC Concerete Pad Install New Electrical Conduits For Generator Install Sanitary Waste Lines Install New Generator Pad Install New Natural Gas Line Install New Transformer Conduits Install New Transformer Concerete Pad Install Sanitary Vent Lines Install Plumbing Water Lines Install Storm Pipe Grading Sediment Control Install Temporary Bollard Removal of Trees Remove & Cap Sanitary Piping Paint Removal Using Sand Blasting of Exterior Walls Remove Top Soil Remove Abandoned 8'' Water Main M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T Sep 27, '15 Oct 18, '15 Nov 8, '15 Nov 29, '15 Dec 20, '15 Jan 10, '16 Jan 31, '16 Feb 21, '16 Mar 13, '16 Apr 3, '16 Apr 24, '16 May 15, '16 Jun 5, '16 Jun 26, '16 Jul 17, '16 Aug 7, '16 Aug 28, '16 Sep 18, '16 Oct 9, '16 Oct 30, '16 Nov 20, '16 Dec 11, '16 Jan 1, '17 Jan 22, '17 Feb 12, '17 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 1 Date: Sun 2/28/16
  • 2. ID Task Name Duration Start Finish 56 Remove Conc.Sidewalk and Con Loading Dock 1 day Mon 12/21/15 Mon 12/21/15 57 Saw Cut BIT CONC 2 days Tue 12/22/15 Wed 12/23/15 58 Remove EX.Gravel Drive 1 day Thu 12/24/15 Thu 12/24/15 59 Remove and Replace Existing Steam Vent as Depicted on C-301 2 days Mon 12/28/15 Tue 12/29/15 54 Remove Bollard 1 day Wed 12/30/15 Wed 12/30/15 79 Building 21 63 days Mon 12/7/15 Tue 3/8/16 80 Demolitions 18 days Mon 12/7/15 Thu 12/31/15 81 Remove Existing CMU 3 days Mon 12/7/15 Wed 12/9/15 82 Remove Portion of Exterior Wall 3 days Thu 12/10/15 Mon 12/14/15 83 Remove Portion of Roofing Material 3 days Tue 12/15/15 Thu 12/17/15 84 Remove Existing Plumbing 3 days Fri 12/18/15 Tue 12/22/15 85 Remove Existing Mechanical 3 days Wed 12/23/15 Mon 12/28/15 86 Demo Hard Ceilings 3 days Tue 12/29/15 Thu 12/31/15 87 First Floor 45 days Mon 1/4/16 Tue 3/8/16 88 Civil Work 5 days Mon 1/4/16 Fri 1/8/16 89 Install New CMU 5 days Mon 1/4/16 Fri 1/8/16 90 Plumbing Works 10 days Mon 1/11/16 Mon 1/25/16 92 Rough In Walls-Plumbing 3 days Mon 1/11/16 Wed 1/13/16 93 Rough In Above Ceiling Plumbing 3 days Thu 1/14/16 Tue 1/19/16 91 Set Plumbing Carriers 2 days Wed 1/20/16 Thu 1/21/16 95 Install Floor Drains 2 days Wed 1/20/16 Thu 1/21/16 94 Trim Out Plumbing 2 days Fri 1/22/16 Mon 1/25/16 96 Electrical /Lighiting Works 9 days Thu 1/14/16 Wed 1/27/16 98 Rough In Electrical Conduit And Wire 3 days Thu 1/14/16 Tue 1/19/16 99 Install Lighting Conduits 2 days Wed 1/20/16 Thu 1/21/16 97 Trim Out Electrical 2 days Fri 1/22/16 Mon 1/25/16 100 Trim Out Lighting 2 days Tue 1/26/16 Wed 1/27/16 101 Mechanical / HVAC / Fire Sprinkler 17 days Thu 1/14/16 Mon 2/8/16 104 Install Ac Ductwork 3 days Thu 1/14/16 Tue 1/19/16 102 Install Vav Cw Hw Piping 2 days Wed 1/20/16 Thu 1/21/16 112 Pressure Test Ductwork 2 days Wed 1/20/16 Thu 1/21/16 113 Insulate Ductwork 2 days Fri 1/22/16 Mon 1/25/16 106 Rough In Low Voltage 2 days Tue 1/26/16 Wed 1/27/16 105 Trim Out Low Voltage 2 days Thu 1/28/16 Fri 1/29/16 107 Rough In Mechanical 2 days Thu 1/28/16 Fri 1/29/16 108 Rough In Med Gas 2 days Mon 2/1/16 Tue 2/2/16 109 Trim Out Mechanical 2 days Mon 2/1/16 Tue 2/2/16 103 Rough In For Fire Sprinkler Pipe 2 days Wed 2/3/16 Thu 2/4/16 110 Trim Out Med Gas 2 days Wed 2/3/16 Thu 2/4/16 111 Trim Out Fire Sprinkler 2 days Fri 2/5/16 Mon 2/8/16 114 Finishing 20 days Tue 2/9/16 Tue 3/8/16 125 Prime And First Coat Walls And Hard Ceilings 2 days Tue 2/9/16 Wed 2/10/16 123 Hang Drywall 2 days Thu 2/11/16 Fri 2/12/16 124 Finish Drywall 2 days Tue 2/16/16 Wed 2/17/16 117 Install Vinyl Flooring 2 days Thu 2/18/16 Fri 2/19/16 126 Epoxy Painting 2 days Thu 2/18/16 Fri 2/19/16 116 Final Coat Painting 2 days Mon 2/22/16 Tue 2/23/16 127 Doors & Hdw Installation 2 days Wed 2/24/16 Thu 2/25/16 128 Interior Glass Installation 2 days Fri 2/26/16 Mon 2/29/16 115 Install Equipment-Security System 1 day Tue 3/1/16 Tue 3/1/16 121 Install Equipment-Fire Alarm 1 day Wed 3/2/16 Wed 3/2/16 122 Install Va Equipment-Cabinetry 1 day Thu 3/3/16 Thu 3/3/16 119 Install Va Equipment-Appliances 1 day Fri 3/4/16 Fri 3/4/16 120 Install Equipment-Motorized Windowshades 1 day Mon 3/7/16 Mon 3/7/16 118 Install Va Equipment-Furniture 1 day Tue 3/8/16 Tue 3/8/16 129 Building 20 & New Additions 216 days Mon 12/7/15 Thu 10/13/16 130 Demolitions 26 days Mon 12/7/15 Wed 1/13/16 135 Disconnect Hvac 1 day Mon 12/7/15 Mon 12/7/15 142 Disconnect Medical Gas 1 day Mon 12/7/15 Mon 12/7/15 145 Disconnect Power 1 day Mon 12/7/15 Mon 12/7/15 149 Demo Abatement 7 days Mon 12/7/15 Tue 12/15/15 132 Demo Fire Sprinkler System 3 days Tue 12/8/15 Thu 12/10/15 133 Demo Ac Ductwork 3 days Tue 12/8/15 Thu 12/10/15 141 Disconnect Domestic Water 1 day Tue 12/8/15 Tue 12/8/15 143 Disconnect Low Voltage Systems 1 day Tue 12/8/15 Tue 12/8/15 148 Demo and Remove of Portion of Building 20 7 days Tue 12/8/15 Wed 12/16/15 134 Demo Plumbing Piping 2 days Wed 12/9/15 Thu 12/10/15 136 Remove Plumbing Fixtures 3 days Thu 12/17/15 Mon 12/21/15 138 Demo Electric Power Conduit & Wire 3 days Tue 12/22/15 Thu 12/24/15 139 Demo Low Voltage Systems 2 days Mon 12/28/15 Tue 12/29/15 144 Demo/Remove Ceiling Tile 2 days Wed 12/30/15 Thu 12/31/15 131 Demo Walls 3 days Mon 1/4/16 Wed 1/6/16 140 Install Negative Air Machines 2 days Mon 1/4/16 Tue 1/5/16 Remove Conc.Sidewalk and Con Loading Dock Saw Cut BIT CONC Remove EX.Gravel Drive Remove and Replace Existing Steam Vent as Depicted on C-301 Remove Bollard Remove Existing CMU Remove Portion of Exterior Wall Remove Portion of Roofing Material Remove Existing Plumbing Remove Existing Mechanical Demo Hard Ceilings Install New CMU Rough In Walls-Plumbing Rough In Above Ceiling Plumbing Set Plumbing Carriers Install Floor Drains Trim Out Plumbing Rough In Electrical Conduit And Wire Install Lighting Conduits Trim Out Electrical Trim Out Lighting Install Ac Ductwork Install Vav Cw Hw Piping Pressure Test Ductwork Insulate Ductwork Rough In Low Voltage Trim Out Low Voltage Rough In Mechanical Rough In Med Gas Trim Out Mechanical Rough In For Fire Sprinkler Pipe Trim Out Med Gas Trim Out Fire Sprinkler Prime And First Coat Walls And Hard Ceilings Hang Drywall Finish Drywall Install Vinyl Flooring Epoxy Painting Final Coat Painting Doors & Hdw Installation Interior Glass Installation Install Equipment-Security System Install Equipment-Fire Alarm Install Va Equipment-Cabinetry Install Va Equipment-Appliances Install Equipment-Motorized Windowshades Install Va Equipment-Furniture Disconnect Hvac Disconnect Medical Gas Disconnect Power Demo Abatement Demo Fire Sprinkler System Demo Ac Ductwork Disconnect Domestic Water Disconnect Low Voltage Systems Demo and Remove of Portion of Building 20 Demo Plumbing Piping Remove Plumbing Fixtures Demo Electric Power Conduit & Wire Demo Low Voltage Systems Demo/Remove Ceiling Tile Demo Walls Install Negative Air Machines M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T Sep 27, '15 Oct 18, '15 Nov 8, '15 Nov 29, '15 Dec 20, '15 Jan 10, '16 Jan 31, '16 Feb 21, '16 Mar 13, '16 Apr 3, '16 Apr 24, '16 May 15, '16 Jun 5, '16 Jun 26, '16 Jul 17, '16 Aug 7, '16 Aug 28, '16 Sep 18, '16 Oct 9, '16 Oct 30, '16 Nov 20, '16 Dec 11, '16 Jan 1, '17 Jan 22, '17 Feb 12, '17 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 2 Date: Sun 2/28/16
  • 3. ID Task Name Duration Start Finish 147 Demo/Remove Lights Grills & Diffusers 3 days Mon 1/4/16 Wed 1/6/16 146 Rework Fire Sprinkler Heads For Demo 3 days Wed 1/6/16 Fri 1/8/16 137 Remove Existing Equipment 3 days Mon 1/11/16 Wed 1/13/16 150 First Floor 155 days Thu 12/31/15 Wed 8/10/16 151 Concrete Work 36 days Thu 12/31/15 Tue 2/23/16 152 Excavation of Foundations @ Area A 7 days Thu 12/31/15 Mon 1/11/16 153 Dewatering 3 days Tue 1/12/16 Thu 1/14/16 154 Load out Excavation Materials 3 days Tue 1/12/16 Thu 1/14/16 156 Form / Pour Foundation Footers 5 days Fri 1/15/16 Fri 1/22/16 157 Form / Pour Foundation Walls 5 days Mon 1/25/16 Fri 1/29/16 155 Backfill Foundation 4 days Mon 2/1/16 Thu 2/4/16 158 Form / Pour Concrete Slab on Grade 5 days Wed 2/17/16 Tue 2/23/16 181 Plumbing Works 75 days Fri 2/5/16 Fri 5/20/16 187 Plumbing Rough In Under Slab 7 days Fri 2/5/16 Tue 2/16/16 188 Plumbing Rough In -Sanitary Waste lines 7 days Fri 2/5/16 Tue 2/16/16 189 Plumbing Rough In -Storm Drain lines 7 days Fri 2/5/16 Tue 2/16/16 183 Rough In Walls-Plumbing 4 days Fri 4/29/16 Wed 5/4/16 184 Rough In Above Ceiling Plumbing 4 days Thu 5/5/16 Tue 5/10/16 182 Set Plumbing Carriers 3 days Wed 5/11/16 Fri 5/13/16 186 Install Floor Drains 4 days Wed 5/11/16 Mon 5/16/16 185 Trim Out Plumbing 4 days Tue 5/17/16 Fri 5/20/16 159 Structure Steel 25 days Wed 2/24/16 Tue 3/29/16 161 Install Bass Plates / Columns 5 days Wed 2/24/16 Tue 3/1/16 162 Install Steel Framing 5 days Wed 3/2/16 Tue 3/8/16 163 Install Steel Bracing 5 days Wed 3/9/16 Tue 3/15/16 164 Install Metal Decking 5 days Wed 3/16/16 Tue 3/22/16 160 Install CMU 5 days Wed 3/23/16 Tue 3/29/16 165 Cold Formed Metal Framing 11 days Wed 3/23/16 Wed 4/6/16 168 Install batt insulation 2 days Wed 3/23/16 Thu 3/24/16 167 Frame wall openings 2 days Fri 3/25/16 Mon 3/28/16 166 Install Batt insulation 1 day Tue 3/29/16 Tue 3/29/16 169 Install interiol dans - glass sheathing 3 days Wed 3/30/16 Fri 4/1/16 170 Install pvc wainscot 3 days Mon 4/4/16 Wed 4/6/16 171 Metal Wall Panels 8 days Thu 4/7/16 Mon 4/18/16 172 Install Extrior Dens Glass Sheathing 2 days Thu 4/7/16 Fri 4/8/16 173 Install J-Channel , Z-Girts 2 days Mon 4/11/16 Tue 4/12/16 174 Install Water Resistive Barrier 1 day Wed 4/13/16 Wed 4/13/16 175 Install Metal Wall Panels 3 days Thu 4/14/16 Mon 4/18/16 176 Metal Roof Panels 8 days Tue 4/19/16 Thu 4/28/16 177 Install Rigid Insulation 2 days Tue 4/19/16 Wed 4/20/16 178 Install Roof Dens-Deck 2 days Thu 4/21/16 Fri 4/22/16 179 Install Metal Roof Panels 2 days Mon 4/25/16 Tue 4/26/16 180 Install Gutters / Downspouts 2 days Wed 4/27/16 Thu 4/28/16 190 Electrical /Lighiting Works 20 days Fri 4/29/16 Thu 5/26/16 191 Rough In Electrical Conduit And Wire 5 days Fri 4/29/16 Thu 5/5/16 193 Install Lighting Conduits 5 days Fri 5/6/16 Thu 5/12/16 192 Trim Out Electrical 5 days Fri 5/13/16 Thu 5/19/16 194 Trim Out Lighting 5 days Fri 5/20/16 Thu 5/26/16 209 Finishing 72 days Fri 4/29/16 Wed 8/10/16 226 Installation of Exterior Window 5 days Fri 4/29/16 Thu 5/5/16 213 Drop In Ceiling Tile 4 days Mon 5/23/16 Thu 5/26/16 217 Install Ceramic Tile In Bathrooms 2 days Fri 5/27/16 Tue 5/31/16 222 Prime And First Coat Walls And Hard Ceilings 4 days Wed 6/1/16 Mon 6/6/16 220 Hang Drywall 3 days Tue 6/7/16 Thu 6/9/16 221 Finish Drywall 3 days Fri 6/10/16 Tue 6/14/16 212 Install Vinyl Flooring 4 days Wed 6/15/16 Mon 6/20/16 223 Epoxy Painting 3 days Wed 6/15/16 Fri 6/17/16 227 Installation of Suspended Ceiling Grid 7 days Wed 6/15/16 Thu 6/23/16 211 Final Coat Painting 3 days Tue 6/21/16 Thu 6/23/16 224 Doors & Hdw Installation 4 days Thu 7/7/16 Tue 7/12/16 225 Interior Glass Installation 3 days Wed 7/13/16 Fri 7/15/16 210 Install Equipment-Security System 3 days Mon 7/18/16 Wed 7/20/16 218 Install Equipment-Fire Alarm 3 days Thu 7/21/16 Mon 7/25/16 219 Install Va Equipment-Cabinetry 3 days Tue 7/26/16 Thu 7/28/16 215 Install Va Equipment-Appliances 3 days Fri 7/29/16 Tue 8/2/16 216 Install Equipment-Motorized Windowshades 3 days Wed 8/3/16 Fri 8/5/16 214 Install Va Equipment-Furniture 3 days Mon 8/8/16 Wed 8/10/16 195 Mechanical / HVAC / Fire Sprinkler 43 days Thu 5/5/16 Wed 7/6/16 197 Install Ac Ductwork 5 days Thu 5/5/16 Wed 5/11/16 198 Install Vav Cw Hw Piping 5 days Thu 5/12/16 Wed 5/18/16 208 Install Penthouse Central Utilities Plant 7 days Tue 5/17/16 Wed 5/25/16 205 Insulate Ductwork 3 days Thu 5/19/16 Mon 5/23/16 196 Pressure Test Ductwork 3 days Tue 5/24/16 Thu 5/26/16 Demo/Remove Lights Grills & Diffusers Rework Fire Sprinkler Heads For Demo Remove Existing Equipment Excavation of Foundations @ Area A Dewatering Load out Excavation Materials Form / Pour Foundation Footers Form / Pour Foundation Walls Backfill Foundation Form / Pour Concrete Slab on Grade Plumbing Rough In Under Slab Plumbing Rough In -Sanitary Waste lines Plumbing Rough In -Storm Drain lines Rough In Walls-Plumbing Rough In Above Ceiling Plumbing Set Plumbing Carriers Install Floor Drains Trim Out Plumbing Install Bass Plates / Columns Install Steel Framing Install Steel Bracing Install Metal Decking Install CMU Install batt insulation Frame wall openings Install Batt insulation Install interiol dans - glass sheathing Install pvc wainscot Install Extrior Dens Glass Sheathing Install J-Channel , Z-Girts Install Water Resistive Barrier Install Metal Wall Panels Install Rigid Insulation Install Roof Dens-Deck Install Metal Roof Panels Install Gutters / Downspouts Rough In Electrical Conduit And Wire Install Lighting Conduits Trim Out Electrical Trim Out Lighting Installation of Exterior Window Drop In Ceiling Tile Install Ceramic Tile In Bathrooms Prime And First Coat Walls And Hard Ceilings Hang Drywall Finish Drywall Install Vinyl Flooring Epoxy Painting Installation of Suspended Ceiling Grid Final Coat Painting Doors & Hdw Installation Interior Glass Installation Install Equipment-Security System Install Equipment-Fire Alarm Install Va Equipment-Cabinetry Install Va Equipment-Appliances Install Equipment-Motorized Windowshades Install Va Equipment-Furniture Install Ac Ductwork Install Vav Cw Hw Piping Install Penthouse Central Utilities Plant Insulate Ductwork Pressure Test Ductwork M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T Sep 27, '15 Oct 18, '15 Nov 8, '15 Nov 29, '15 Dec 20, '15 Jan 10, '16 Jan 31, '16 Feb 21, '16 Mar 13, '16 Apr 3, '16 Apr 24, '16 May 15, '16 Jun 5, '16 Jun 26, '16 Jul 17, '16 Aug 7, '16 Aug 28, '16 Sep 18, '16 Oct 9, '16 Oct 30, '16 Nov 20, '16 Dec 11, '16 Jan 1, '17 Jan 22, '17 Feb 12, '17 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 3 Date: Sun 2/28/16
  • 4. ID Task Name Duration Start Finish 201 Rough In Low Voltage 3 days Fri 5/27/16 Wed 6/1/16 202 Rough In Mechanical 3 days Thu 6/2/16 Mon 6/6/16 203 Rough In Med Gas 3 days Tue 6/7/16 Thu 6/9/16 199 Rough In For Fire Sprinkler Pipe 4 days Fri 6/10/16 Wed 6/15/16 204 Trim Out Mechanical 4 days Fri 6/24/16 Wed 6/29/16 206 Trim Out Fire Sprinkler 4 days Fri 6/24/16 Wed 6/29/16 207 Trim Out Med Gas 4 days Fri 6/24/16 Wed 6/29/16 200 Trim Out Low Voltage 4 days Thu 6/30/16 Wed 7/6/16 228 Roof Floor 116 days Fri 4/29/16 Thu 10/13/16 229 Structure Steel 12 days Fri 4/29/16 Mon 5/16/16 230 Install Bass Plates / Columns 3 days Fri 4/29/16 Tue 5/3/16 231 Install Steel Framing 3 days Wed 5/4/16 Fri 5/6/16 232 Install Steel Bracing 3 days Mon 5/9/16 Wed 5/11/16 233 Install Metal Decking 3 days Thu 5/12/16 Mon 5/16/16 234 Cold Formed Metal Framing 14 days Tue 5/17/16 Mon 6/6/16 237 Install batt insulation 3 days Tue 5/17/16 Thu 5/19/16 236 Frame wall openings 3 days Fri 5/20/16 Tue 5/24/16 235 Install Batt insulation 2 days Wed 5/25/16 Thu 5/26/16 238 Install interiol dans - glass sheathing 3 days Fri 5/27/16 Wed 6/1/16 239 Install pvc wainscot 3 days Thu 6/2/16 Mon 6/6/16 240 Metal Wall Panels 10 days Tue 6/7/16 Mon 6/20/16 241 Install Extrior Dens Glass Sheathing 3 days Tue 6/7/16 Thu 6/9/16 242 Install J-Channel , Z-Girts 2 days Fri 6/10/16 Mon 6/13/16 243 Install Water Resistive Barrier 2 days Tue 6/14/16 Wed 6/15/16 244 Install Metal Wall Panels 3 days Thu 6/16/16 Mon 6/20/16 245 Metal Roof Panels 7 days Tue 6/21/16 Wed 6/29/16 246 Install Rigid Insulation 2 days Tue 6/21/16 Wed 6/22/16 247 Install Roof Dens-Deck 2 days Thu 6/23/16 Fri 6/24/16 248 Install Metal Roof Panels 2 days Mon 6/27/16 Tue 6/28/16 249 Install Gutters / Downspouts 1 day Wed 6/29/16 Wed 6/29/16 250 Plumbing Works 14 days Thu 6/30/16 Wed 7/20/16 252 Rough In Walls-Plumbing 3 days Thu 6/30/16 Tue 7/5/16 253 Rough In Above Ceiling Plumbing 4 days Wed 7/6/16 Mon 7/11/16 251 Set Plumbing Carriers 3 days Tue 7/12/16 Thu 7/14/16 255 Install Floor Drains 4 days Tue 7/12/16 Fri 7/15/16 254 Trim Out Plumbing 3 days Mon 7/18/16 Wed 7/20/16 274 Finishing 73 days Thu 6/30/16 Thu 10/13/16 291 Installation of Exterior Window 5 days Thu 6/30/16 Thu 7/7/16 277 Drop In Ceiling Tile 4 days Mon 7/25/16 Thu 7/28/16 281 Install Ceramic Tile In Bathrooms 2 days Fri 7/29/16 Mon 8/1/16 286 Prime And First Coat Walls And Hard Ceilings 4 days Tue 8/2/16 Fri 8/5/16 284 Hang Drywall 3 days Mon 8/8/16 Wed 8/10/16 285 Finish Drywall 3 days Thu 8/11/16 Mon 8/15/16 292 Installation of Suspended Ceiling Grid 7 days Thu 8/11/16 Fri 8/19/16 276 Install Vinyl Flooring 4 days Tue 8/16/16 Fri 8/19/16 287 Epoxy Painting 3 days Tue 8/30/16 Thu 9/1/16 275 Final Coat Painting 3 days Fri 9/2/16 Wed 9/7/16 288 Doors & Hdw Installation 4 days Thu 9/8/16 Tue 9/13/16 289 Interior Glass Installation 3 days Wed 9/14/16 Fri 9/16/16 278 Install Equipment-Security System 3 days Mon 9/19/16 Wed 9/21/16 282 Install Equipment-Fire Alarm 3 days Thu 9/22/16 Mon 9/26/16 283 Install Va Equipment-Cabinetry 3 days Tue 9/27/16 Thu 9/29/16 279 Install Va Equipment-Appliances 3 days Fri 9/30/16 Tue 10/4/16 280 Install Equipment-Motorized Windowshades 3 days Wed 10/5/16 Fri 10/7/16 290 Install Va Equipment-Furniture 3 days Tue 10/11/16 Thu 10/13/16 256 Electrical /Lighiting Works 13 days Wed 7/6/16 Fri 7/22/16 259 Rough In Electrical Conduit And Wire 4 days Wed 7/6/16 Mon 7/11/16 257 Install Lighting Conduits 3 days Tue 7/12/16 Thu 7/14/16 260 Trim Out Electrical 3 days Fri 7/15/16 Tue 7/19/16 258 Trim Out Lighting 3 days Wed 7/20/16 Fri 7/22/16 261 Mechanical / HVAC / Fire Sprinkler 28 days Thu 7/21/16 Mon 8/29/16 264 Install Ac Ductwork 3 days Thu 7/21/16 Mon 7/25/16 265 Install Vav Cw Hw Piping 3 days Tue 7/26/16 Thu 7/28/16 263 Insulate Ductwork 3 days Fri 7/29/16 Tue 8/2/16 262 Pressure Test Ductwork 2 days Wed 8/3/16 Thu 8/4/16 268 Rough In Low Voltage 2 days Fri 8/5/16 Mon 8/8/16 269 Rough In Mechanical 3 days Tue 8/9/16 Thu 8/11/16 270 Rough In Med Gas 3 days Fri 8/12/16 Tue 8/16/16 266 Rough In For Fire Sprinkler Pipe 3 days Wed 8/17/16 Fri 8/19/16 271 Trim Out Mechanical 4 days Mon 8/22/16 Thu 8/25/16 272 Trim Out Med Gas 4 days Mon 8/22/16 Thu 8/25/16 273 Trim Out Fire Sprinkler 3 days Mon 8/22/16 Wed 8/24/16 267 Trim Out Low Voltage 3 days Thu 8/25/16 Mon 8/29/16 Rough In Low Voltage Rough In Mechanical Rough In Med Gas Rough In For Fire Sprinkler Pipe Trim Out Mechanical Trim Out Fire Sprinkler Trim Out Med Gas Trim Out Low Voltage Install Bass Plates / Columns Install Steel Framing Install Steel Bracing Install Metal Decking Install batt insulation Frame wall openings Install Batt insulation Install interiol dans - glass sheathing Install pvc wainscot Install Extrior Dens Glass Sheathing Install J-Channel , Z-Girts Install Water Resistive Barrier Install Metal Wall Panels Install Rigid Insulation Install Roof Dens-Deck Install Metal Roof Panels Install Gutters / Downspouts Rough In Walls-Plumbing Rough In Above Ceiling Plumbing Set Plumbing Carriers Install Floor Drains Trim Out Plumbing Installation of Exterior Window Drop In Ceiling Tile Install Ceramic Tile In Bathrooms Prime And First Coat Walls And Hard Ceilings Hang Drywall Finish Drywall Installation of Suspended Ceiling Grid Install Vinyl Flooring Epoxy Painting Final Coat Painting Doors & Hdw Installation Interior Glass Installation Install Equipment-Security System Install Equipment-Fire Alarm Install Va Equipment-Cabinetry Install Va Equipment-Appliances Install Equipment-Motorized Windowshades Install Va Equipment-Furniture Rough In Electrical Conduit And Wire Install Lighting Conduits Trim Out Electrical Trim Out Lighting Install Ac Ductwork Install Vav Cw Hw Piping Insulate Ductwork Pressure Test Ductwork Rough In Low Voltage Rough In Mechanical Rough In Med Gas Rough In For Fire Sprinkler Pipe Trim Out Mechanical Trim Out Med Gas Trim Out Fire Sprinkler Trim Out Low Voltage M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T Sep 27, '15 Oct 18, '15 Nov 8, '15 Nov 29, '15 Dec 20, '15 Jan 10, '16 Jan 31, '16 Feb 21, '16 Mar 13, '16 Apr 3, '16 Apr 24, '16 May 15, '16 Jun 5, '16 Jun 26, '16 Jul 17, '16 Aug 7, '16 Aug 28, '16 Sep 18, '16 Oct 9, '16 Oct 30, '16 Nov 20, '16 Dec 11, '16 Jan 1, '17 Jan 22, '17 Feb 12, '17 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 4 Date: Sun 2/28/16
  • 5. ID Task Name Duration Start Finish 293 Paving and Site Restoration 10 days Fri 10/14/16 Thu 10/27/16 297 BIT CONC Pavement 2 days Fri 10/14/16 Mon 10/17/16 294 Survey Paving 1 day Tue 10/18/16 Tue 10/18/16 295 Heavy - Duty Bituminous Paving 3 days Wed 10/19/16 Fri 10/21/16 296 Fine Grading / Place Gravel 2 days Mon 10/24/16 Tue 10/25/16 298 Site Clearing 2 days Wed 10/26/16 Thu 10/27/16 299 Commissioning & Turn Over 12 days Fri 10/28/16 Tue 11/15/16 305 Submission and Approval Commissioning Procedures 2 days Fri 10/28/16 Mon 10/31/16 304 Perform Test And Balance 2 days Tue 11/1/16 Wed 11/2/16 300 Review And Approve (Va) Test And Balance Report 2 days Thu 11/3/16 Fri 11/4/16 301 Conduct Pre-Commissioning Coordination Meeting 2 days Mon 11/7/16 Tue 11/8/16 302 Conduct Commissioning - Functional Performance Testing 2 days Wed 11/9/16 Thu 11/10/16 303 Review And Approve (Va) Commissioning-Building Systems Report 2 days Mon 11/14/16 Tue 11/15/16 306 Contract Close Out 20 days Tue 11/15/16 Wed 12/14/16 307 Substantial Completion 0 days Tue 11/15/16 Tue 11/15/16 308 Punchlist 10 days Wed 11/16/16 Wed 11/30/16 309 Pass Va Final Inspection 5 days Thu 12/1/16 Wed 12/7/16 311 Demobilization 5 days Thu 12/8/16 Wed 12/14/16 310 Finish Completion 0 days Wed 12/14/16 Wed 12/14/16 BIT CONC Pavement Survey Paving Heavy - Duty Bituminous Paving Fine Grading / Place Gravel Site Clearing Submission and Approval Commissioning Procedures Perform Test And Balance Review And Approve (Va) Test And Balance Report Conduct Pre-Commissioning Coordination Meeting Conduct Commissioning - Functional Performance Testing Review And Approve (Va) Commissioning-Building Systems Report 11/15 Punchlist Pass Va Final Inspection Demobilization 12/14 M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T Sep 27, '15 Oct 18, '15 Nov 8, '15 Nov 29, '15 Dec 20, '15 Jan 10, '16 Jan 31, '16 Feb 21, '16 Mar 13, '16 Apr 3, '16 Apr 24, '16 May 15, '16 Jun 5, '16 Jun 26, '16 Jul 17, '16 Aug 7, '16 Aug 28, '16 Sep 18, '16 Oct 9, '16 Oct 30, '16 Nov 20, '16 Dec 11, '16 Jan 1, '17 Jan 22, '17 Feb 12, '17 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 5 Date: Sun 2/28/16