This document provides a progress summary for various infrastructure projects in Jeddah, Saudi Arabia as of August 2, 2015. It includes summaries of excavation, installation, testing, backfilling and other work completed for storm water, sewage, potable water, irrigation and electrical systems. Percentages of work completed range from 13% to 100% across the different project components. Some project components are 78% completed while others are only 4% finished. The document also provides comparisons of previous and current month's progress along with remaining work for each item.