Gensol has presented quicks highlights of 1200MW Renewable Energy Tender with assured Peak Power Supply in terms of eligibility criteria, bidders obligations, project capacity (MW), generation criteria, various guarantees, project tariff rate (Rs/kWh) and many more. It's interesting to highlight that SECI has issued tender with no cap in tariff at the same assured peak power supply.
Gensol has summarised the tender issued by SECI for 2.5GW Wind Solar Hybrid ISTS projects.
The document covers major commercial & technical guidelines provided in the tender.
The largest tender by Solar Energy Corporation of India for Floating Solar for 150 MW is up for bidding.
The document is a summary of the tender document and covers the commercial & technical guidelines provided in the tender.
A comparative study has been carried by Gensol on Solar-Wind Hybrid Policies issued by Central Government, Gujarat State & Andhra Pradesh (A.P.) in terms of following:
1) Incentives & Pertinent Charges
2) Evacuation & Metering Scheme
3) Energy Accounting & Banking
4) AC-DC Integration & other important clauses.
Neyveli Lignite Corporation (NLC) has invited bids for installation of 2 x 10 MW (AC) Grid interactive Solar PV Power Project integrated with 28 MWhr Battery Energy Storage System at Attam Pahad and at Dolly Gunj, Port Blair, South Andaman with associated 33 KV Switchyard and grid interconnection at the take off points of Electricity Department of Andaman & Nicobar Administration including Design, Engineering, Manufacture, Inspection at supplier’s works, supply, insurance, transport, storage, erection, testing, commissioning.
The scope of work also includes Operation and Maintenance of the entire system for twenty five years including one year warranty period.
Gensol has carried out state-wise comparative analysis for forecasting, scheduling and deviation settlement mechanism (DSM) of Solar & Wind projects. There has been huge requirement to facilitate large-scale RE integration with grid while maintaining grid stability and security as envisaged under the Grid Code.Following points are highlighted in this presentation:
1) Responsibility & Requirements
2) Available Capacity & Tolerance Band
3) Deviation Settlement Mechanism (DSM)
4) Metering, Energy & Deviation Accounting etc (Click here)
Solar Parks are becoming increasingly popular & MNRE is leaving no stone unturned to make them a success.
The ppt mentions the nuts & bolts of the Solar Park Scheme of MNRE.
The Sate of Tamil Nadu has recently released new solar policy with highly ambitious target of 9GW by 2023. Gensol has highlighted key areas of focus & inferences with respect to incentives, energy accounting, wheeling of power etc.
The presentation throws light on the commercial aspects of developing a solar project in Maharashtra with a view to supply power to a third party through open access.
Specifically, it probes into the spectrum of open access charges that are applicable while the generated power traverses through the state transmission and local distribution grid, starting from the plant end to the consumer end.
Gensol has summarised the tender issued by SECI for 2.5GW Wind Solar Hybrid ISTS projects.
The document covers major commercial & technical guidelines provided in the tender.
The largest tender by Solar Energy Corporation of India for Floating Solar for 150 MW is up for bidding.
The document is a summary of the tender document and covers the commercial & technical guidelines provided in the tender.
A comparative study has been carried by Gensol on Solar-Wind Hybrid Policies issued by Central Government, Gujarat State & Andhra Pradesh (A.P.) in terms of following:
1) Incentives & Pertinent Charges
2) Evacuation & Metering Scheme
3) Energy Accounting & Banking
4) AC-DC Integration & other important clauses.
Neyveli Lignite Corporation (NLC) has invited bids for installation of 2 x 10 MW (AC) Grid interactive Solar PV Power Project integrated with 28 MWhr Battery Energy Storage System at Attam Pahad and at Dolly Gunj, Port Blair, South Andaman with associated 33 KV Switchyard and grid interconnection at the take off points of Electricity Department of Andaman & Nicobar Administration including Design, Engineering, Manufacture, Inspection at supplier’s works, supply, insurance, transport, storage, erection, testing, commissioning.
The scope of work also includes Operation and Maintenance of the entire system for twenty five years including one year warranty period.
Gensol has carried out state-wise comparative analysis for forecasting, scheduling and deviation settlement mechanism (DSM) of Solar & Wind projects. There has been huge requirement to facilitate large-scale RE integration with grid while maintaining grid stability and security as envisaged under the Grid Code.Following points are highlighted in this presentation:
1) Responsibility & Requirements
2) Available Capacity & Tolerance Band
3) Deviation Settlement Mechanism (DSM)
4) Metering, Energy & Deviation Accounting etc (Click here)
Solar Parks are becoming increasingly popular & MNRE is leaving no stone unturned to make them a success.
The ppt mentions the nuts & bolts of the Solar Park Scheme of MNRE.
The Sate of Tamil Nadu has recently released new solar policy with highly ambitious target of 9GW by 2023. Gensol has highlighted key areas of focus & inferences with respect to incentives, energy accounting, wheeling of power etc.
The presentation throws light on the commercial aspects of developing a solar project in Maharashtra with a view to supply power to a third party through open access.
Specifically, it probes into the spectrum of open access charges that are applicable while the generated power traverses through the state transmission and local distribution grid, starting from the plant end to the consumer end.
Introduction to the Renewable Energy Certificate (REC) MechanismSpark Network
Renewable Energy Certificate (REC) Mechanism issued by Ministry of New & Renewable Energy of India to facilitate interstate transactions of Renewable Energy and to promote RE based projects. This report covers all the basic aspects of REC Mechanism along with the Operational Framewokr of the same.
Developing Solar Projects under REC Mechanism in IndiaBhargav Parmar
Instead of signing MoU, PPA, submitting performance bank guarantee etc for 25 years or participating in cut throat bidding process (project is viable only to module manufacturers for the rate it can be achieved), I suggest to develop the solar project under REC Mechanism, as for selling the power through average exchange rate and realizing the mean value of REC rate for first five years and half of the floor price for next 5 years, yields levellised rate of Rs.10.536*. [Solar Tariff in Gujarat: Rs. 9.28 for project commissioned up to 2013, Rs. 8.63 for project commissioned up to 2014 and Rs. 8.03 for project commissioned up to 2015].
Even if REC floor price is reduced by half for next 5 years and NIL thereafter, developing the project under REC and selling the power through Energy Exchange, would yield rate of Rs.9.647 which is more than maximum rate of NVVN against cost of generation not more than Rs.6.50. [NVVN is the nodal agency of NTPC for procuring solar power to meet their REC requirement. In the 1st phase NVVN finalized bid for 150 MW Solar Projects and in latest bid for 350 MW Solar Projects. In the latest NVVN bid the price offer for solar power projects were minimum Rs.7.49 and maximum Rs.9.44]
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS Harish Sharma
IREDA Loan scheme is for all Solar rooftop power projects having minimum aggregate/Individual installed capacity 1000 kWp. Finance is available upto 75% of project cost with very Low interest rates range from 9.9% to 10.75%.
Net Metering is essential for a Rooftop Solar & many Indian states have their own set of guidelines towards it.
The document helps to summarise the Net Metering Regulations in various Indian states.
Abt meter, Availability Tariff Availability Tariff, particularly in the Indian context, stands for a rational tariff structure for power supply from generating stations, on a contracted basis.
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in PunjabHarish Sharma
As provided in the NRSE Policy-2012 and subsequent amendment, this scheme is introduced for allocation of Solar Power Projects to the land owning farmers of the state of
Punjab. The Government of Punjab endeavors to promote solar energy projects by land owning farmers with a minimum capacity of 1MWp to a maximum capacity of 2.5 MWp (per land owning farmer) in the state for sale of power to Punjab State Power Corporation Ltd (PSPCL)
RFP Document for 300 MW Solar Power Plant in Punjab released by PEDA.
This document is not a work of Headway Solar (http://headwaysolar.com/) and it has been released here for the benefit of the general public.
Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...Harish Sharma
Request for Proposal (hereinafter referred to as RFP) for procurement of power from cumulative
170 MW installed capacity Grid Connect Solar PV Power Projects through Tariff Based
Competitive Bidding Process under Type-I of “Solar Power Policy 2013 of the State of
Uttarakhand”.
On behalf of Uttarakhand Power Corporation Ltd. (UPCL), Dehradun – a Company incorporated
in India and registered under the Companies Act, 1956.
Presentation on the status of "Achievement Under National Solar Mission (NSM)" till July'17.
The key highlight being that 13,115 MW of solar projects have been commissioned. The presentation outlays of how "100 GW" of target shall be achieved based on various schemes under progress. Also last few slides focus on Off Grid Targets under NSM.
200 MW Solar Projects Investor's, Developer's Meet - KERALATahnoon Elahi
This is the presentation of KSEBL happened during Investors Meet for Setting up 200MW Ground Mounted Solar PV Projects in Kerala. This meeting is initial step for attraction of Developers to set up 200MW solar projects in Kerala as a part of Kerala Urja Mission.
Total Target is 1000MW by 2021
Ground Mounted projects 200MW – COD in 2019
Rooftop projects 500MW
Solar Parks 150MW
Floating projects 100MW
Canal top/ Highway projects 50MW
This meeting was presided by the honourable Electricity Minister of the state.
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.Harish Sharma
Himachal Pradesh State Electricity Board Limited to ensure the sustainable growth of Renewal Power is willing to procure solar power from such power producers who wish to install distributed grid connected Solar Projects in the State of Himachal Pradesh with capacities starting 50 kW up to
5 MW.
Introduction to the Renewable Energy Certificate (REC) MechanismSpark Network
Renewable Energy Certificate (REC) Mechanism issued by Ministry of New & Renewable Energy of India to facilitate interstate transactions of Renewable Energy and to promote RE based projects. This report covers all the basic aspects of REC Mechanism along with the Operational Framewokr of the same.
Developing Solar Projects under REC Mechanism in IndiaBhargav Parmar
Instead of signing MoU, PPA, submitting performance bank guarantee etc for 25 years or participating in cut throat bidding process (project is viable only to module manufacturers for the rate it can be achieved), I suggest to develop the solar project under REC Mechanism, as for selling the power through average exchange rate and realizing the mean value of REC rate for first five years and half of the floor price for next 5 years, yields levellised rate of Rs.10.536*. [Solar Tariff in Gujarat: Rs. 9.28 for project commissioned up to 2013, Rs. 8.63 for project commissioned up to 2014 and Rs. 8.03 for project commissioned up to 2015].
Even if REC floor price is reduced by half for next 5 years and NIL thereafter, developing the project under REC and selling the power through Energy Exchange, would yield rate of Rs.9.647 which is more than maximum rate of NVVN against cost of generation not more than Rs.6.50. [NVVN is the nodal agency of NTPC for procuring solar power to meet their REC requirement. In the 1st phase NVVN finalized bid for 150 MW Solar Projects and in latest bid for 350 MW Solar Projects. In the latest NVVN bid the price offer for solar power projects were minimum Rs.7.49 and maximum Rs.9.44]
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS Harish Sharma
IREDA Loan scheme is for all Solar rooftop power projects having minimum aggregate/Individual installed capacity 1000 kWp. Finance is available upto 75% of project cost with very Low interest rates range from 9.9% to 10.75%.
Net Metering is essential for a Rooftop Solar & many Indian states have their own set of guidelines towards it.
The document helps to summarise the Net Metering Regulations in various Indian states.
Abt meter, Availability Tariff Availability Tariff, particularly in the Indian context, stands for a rational tariff structure for power supply from generating stations, on a contracted basis.
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in PunjabHarish Sharma
As provided in the NRSE Policy-2012 and subsequent amendment, this scheme is introduced for allocation of Solar Power Projects to the land owning farmers of the state of
Punjab. The Government of Punjab endeavors to promote solar energy projects by land owning farmers with a minimum capacity of 1MWp to a maximum capacity of 2.5 MWp (per land owning farmer) in the state for sale of power to Punjab State Power Corporation Ltd (PSPCL)
RFP Document for 300 MW Solar Power Plant in Punjab released by PEDA.
This document is not a work of Headway Solar (http://headwaysolar.com/) and it has been released here for the benefit of the general public.
Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...Harish Sharma
Request for Proposal (hereinafter referred to as RFP) for procurement of power from cumulative
170 MW installed capacity Grid Connect Solar PV Power Projects through Tariff Based
Competitive Bidding Process under Type-I of “Solar Power Policy 2013 of the State of
Uttarakhand”.
On behalf of Uttarakhand Power Corporation Ltd. (UPCL), Dehradun – a Company incorporated
in India and registered under the Companies Act, 1956.
Presentation on the status of "Achievement Under National Solar Mission (NSM)" till July'17.
The key highlight being that 13,115 MW of solar projects have been commissioned. The presentation outlays of how "100 GW" of target shall be achieved based on various schemes under progress. Also last few slides focus on Off Grid Targets under NSM.
200 MW Solar Projects Investor's, Developer's Meet - KERALATahnoon Elahi
This is the presentation of KSEBL happened during Investors Meet for Setting up 200MW Ground Mounted Solar PV Projects in Kerala. This meeting is initial step for attraction of Developers to set up 200MW solar projects in Kerala as a part of Kerala Urja Mission.
Total Target is 1000MW by 2021
Ground Mounted projects 200MW – COD in 2019
Rooftop projects 500MW
Solar Parks 150MW
Floating projects 100MW
Canal top/ Highway projects 50MW
This meeting was presided by the honourable Electricity Minister of the state.
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.Harish Sharma
Himachal Pradesh State Electricity Board Limited to ensure the sustainable growth of Renewal Power is willing to procure solar power from such power producers who wish to install distributed grid connected Solar Projects in the State of Himachal Pradesh with capacities starting 50 kW up to
5 MW.
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...Harish Sharma
As part of JNNSM Phase-II Batch-III, Tranche-VIII, SECI is inviting proposals for setting up of grid connected Solar PV Projects in Himachal Pradesh, on “Build Own Operate” basis for an aggregate capacity of 50 MW. Projects selected based on this RfS shall be given “Viability Gap Funding” in line with terms and conditions of this RfS. SECI shall enter into Power Purchase Agreement (PPA) with the Bidders selected based on this RfS for purchase of solar power selected for a period of 25 years based on the terms, conditions and provisions of the RfS.
Last Date and Time of Closure of Procurement of Tender Documents is 17 June 2016
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...Harish Sharma
MNRE launched a pilot scheme for promotion of large scale grid-connected roof top solar PV projects and SECI has been designated as implementing agency for this scheme. The generated solar power may be utilized for captive application and the surplus power may be fed to the grid. The scheme aims to reduce the fossil fuel based electricity and make buildings self-sustainable from the point of electricity, to the extent possible.
The bidding process under this rooftop scheme is for 250 MWp capacity under PART-A (CAPEX Only); 200 MWp capacity under PART-B (RESCO Only) and 50 MWp under Part C (CAPEX Only), in different States of India. Bidder shall submit bids for the minimum aggregate bid capacity of 500 kWp under PART- A, 5 MWp and under PART-B and 100 kWp under Part C.
BID DUE DATE
The Bidder should submit the Bids so as to reach the address indicated below by 1430 hrs (IST) on or before 03/06/2016.
Sbi rooftop program, RESCO constructs, owns, operates and maintains the project,Financing Modes,Target Group
Solar Plant, Lease, Chemtrols Solar, jay.ranvir@chemtrolssolar.com
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESHHarish Sharma
As part of JNNSM Phase-II Batch-III, Tranche-VII, SECI has invited setting up of grid connected Solar PV Projects in Uttar Pradesh, on “Build Own Operate” basis for an aggregate capacity of 160 MW. Projects selected based on this RfS shall be given “Viability Gap Funding” in line with terms and conditions of this RfS. SECI shall enter into Power Purchase Agreement (PPA) with the Bidders selected based on this RfS for purchase of solar power selected for a period of 25 years based on the terms, conditions and provisions of the RfS.
Request for Proposal (RfP) For Installation of 2 MW Canal Top Grid connecte...Harish Sharma
Request for Proposal (RfP/PV/RREC/Canal top) invited by RREC on behalf of
Water Resource Department, GoR/ IGN Board and Discoms of Rajasthan for selection
of developers for setting up of 2MW Grid connected Solar PV Plant on canal top to
be connected on 11kV level at Discoms 33/11kV Substation in Rajasthan under
Rajasthan Solar Energy Policy, 2014 for sale of power to Rajasthan Discoms
through tariff based competitive bidding process. "EnvironmentFirst Energy Services Pvt. Ltd." is facilitating the bid documentation for the successful project allocation. You contact us at info@environmentfirst.in
Draft scheme for allocation of solar power projects for land owning farmersHarish Sharma
After inviting EOI from land owning farmers for the set up of solar power projects of the tune from 1MW to 2.5MW, PEDA has now formulated draft scheme for allocation of solar power projects in Punjab.
MNRE Clarification on the capacity with respect to inverter and eligibility o...Harish Sharma
MNRE Clarification on the eligibility of CFA for rooftop solar plants (with or without net metering/gross metering facility) and for declaring commissioned plant capacity w.r.t installed inverter capacity.
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-IIIHarish Sharma
As part of JNNSM Phase-II Batch-III, Tranche-IX, SECI wishes to invite proposals for setting up of grid connected Solar PV Projects in Puducherry, on “Build Own Operate” basis for an aggregate capacity of 35 MW. Projects selected based on this RfS shall be given “Viability Gap Funding” in line with terms and conditions of this RfS. SECI shall enter into Power Purchase Agreement (PPA) with the Bidders selected based on this RfS for purchase of solar power selected for a period of 25 years based on the terms, conditions and provisions of the RfS.
Last Date for the Closure of Procurement of Tender Documents is 14-Jun-2016 14:00:00 RTZ.
Similar to Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019 (20)
Gensol has estimated Bifacial Gain varying between ~4.0-10.5% when Bifacial PV Modules are configured with Single Axis Tracker (SAT) system depending on system configuration & ground albedo. Various iterations of energy generation were simulated using PVsyst to understand the impact of design considerations and climatic factors on the Bifacial Gain of 1P x 30 Bifacial PV array with SAT system equipped over-torque tube for India & Middle East regions.
Gensol collected Actual Global Tilted Irradiation (AGTI) of 57 sites from operational projects spread across in India. It was then correlated with Expected Global Tilted Irradiation (EGTI) from the following meteo-databases namely:
1) Meteonorm-7.2
2) SolarGIS,
3) NASA (National Aeronautics and Space Administration),
4) NREL (National Renewable Energy Laboratory)
In our report, we find most representative meteo-data set for each site.
Gensol is a leading Solar Advisory and Operation & Maintenance Service Provider with a footprint across 13 countries and 20 GW of projects. This presentation showcase company's business verticals, leadership team, growth trajectory, global presence, major projects executed (National, Government & International).
Blu-Smart has carried out a comparative of India Vs countries like China, Belgium, Germany, Italy and many more with respect to electric vehicle policies, tax benefits & incentives applicable.
Here are the details on 300MW Wind Power Project located in the Western Region of India presented by Gensol on the various phases of construction & execution; starting from :
1)Wind resource assessment,
2)Site feasibility studies,
3)Statuary & legal approvals required,
4)Civil & electrical works,
5)Quality & material inspection,
6)Post erection & monitoring etc.
(Click here to read more..)
The document mentions the following with tentative quantities:
1. List of 17 nos. of main equipment
2. List of 15 nos. of miscellaneous equipment
3. List of 16 nos. of civil works required
4. List of 8 nos. of lattice type equipment
5. List of 11 nos. of foundations required
Gensol has summarized the list of upcoming tenders in India by State & Central Government authorities to achieve National Solar Mission (NSM) targets. This document covers list of EPC & IPP tenders for ground mounted, rooftop solar, floating solar and hybrid projects for various locations in India .
The document summarizes the list of successful bidders, awarded capacity (MW) and ceiling tariff rate (Rs/kWh) for the latest released solar PV tenders.
Module price trend has declined with the increased solar PV demand & competition among the industry. The trend has been studied & forecast has been evaluated by Gensol for the modules supplied from South East Asia especially China to India from September 2013 to January 2019. The following points are highlighted:
1) Global & India Solar PV Installations & Forecast (GW)
2) Solar PV System Cost Trend Global & India 2014-2018
3) Module Price Trend (2014- 2018) & Forecast (2019 -2026)
4) Quarterly Variation in Module Price Trend YoY in %
5) Solar PV Demand in India 2017 Vs 2018
The presentation focuses on the investment opportunities in commercial and industrial rooftop building in India. Sensitivity analysis has been carried out for 11 states to understand the impact on project economics in terms of PIRR, EIRR, and payback periods.
This presentation highlights on the following :
Need of wind-solar hybrid systems
Indian policy support to hybrid systems - MNRE & Gujarat State
Renewable Energy integration with grid,
Cost savings in hybrid for AC-AC & DC-DC coupling systems,
Case studies
WTG has many components & the audit checklist helps to maintain the WTG. Checklist covers the following options -
a) Transformer
b) Isolator
c) VCB Panel & Switch Yard
d) Power Panel
e) Capacitor Panel
f) DFIG Panel
g) Control Panel
h) Junction Box
i) Tubular Tower Shell
j) Climb Arrestor
k) Cables
l) Yaw System
m) Main Bearing
n) Gear Box
o) Generator
p) Rotor Brake
q) Hydraulic Unit
r) Hub Lock
s) Nacelle Control Panel
t) Anemometer & Wind Pane
u) Rotor Blade
v) Battery Bank
w) Nose Cone
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...Gensol Engineering Limited
The presentation is a detailed study on the following:
a) Impact of solar module component on reliability
b) Raw Material - Quality Assurance
c) Manufacturing Process - Quality Assurance
d) Lab Inspection
e) On site module inspection
The technical risks in solar PV projects are arising mainly in modules, inverters, other equipment. These risks are unpredictable and can be occurred in any phases of life cycle of PV project like development, installation, commissioning and operation leading to plant outage or reduction in energy output. The presentation covers the various risks and associated mitigation measures.
Gensol has achieved 2 GW of Lender Engineer Credentials at various states of India for both Ground-mounted and Rooftop projects. Gensol has provided Lenders Independent services to major lenders like Power Finance Corporation (PFC), IDBI, IndusInd, SBI, Tata Cleantech etc.
Solar PV O&M looks easy however maintaining a Solar PV Plant at top performance is a task and based on the experience of Solarig-Gensol in maintaining a 2 GW portfolio of solar plants in India, here are some basics on Solar O&M.
Presentation has the following contents:
a) Balancing Soiling Losses with case study
b) Monitoring & Corrective Maintenance
c) Performance Ratio & Uptime Guarantee
d) Impact of O&M on IRR
Floating Solar is a 10 GW opportunity in India & the ppt is an introduction to Floating Solar with the following content:
a) Floating Solar Market Outlook
b) Benefits of Floating Solar
c) Working Methodology & Design of Floating Solar
d) Case Studies
The presentation highlights the following :
a) Current status of Renewable Energy in India
b) The issue of duck curve due to high volume of solar energy
c) Demand increase due to Electric Vehicle (EV) will lead to more demand for Renewable Energy
d) Global & Indian Market Scenario for Electric Vehicle (EV)
e) Recommendation of Niti Aayog for development of Electric Vehicle (EV) market in India
Gensol Group Profile - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)Gensol Engineering Limited
Gensol is the largest Solar Advisory Firm with 7900 MW of solar projects under advisory (including design, lenders engineer, owner engineer) , 49 MW of solar projects under Engineering Procurement and Construction (EPC) & 2200 MW of solar projects under Operation and Maintenance.
Multiple Energy Storage Technologies are being developed & are maturing, Gensol did an analysis of 1635 Energy Storage Projects developed globally to come up with which technology has captured market share.
The presentation also has multiple case studies.
[Note: This is a partial preview. To download this presentation, visit:
https://www.oeconsulting.com.sg/training-presentations]
Sustainability has become an increasingly critical topic as the world recognizes the need to protect our planet and its resources for future generations. Sustainability means meeting our current needs without compromising the ability of future generations to meet theirs. It involves long-term planning and consideration of the consequences of our actions. The goal is to create strategies that ensure the long-term viability of People, Planet, and Profit.
Leading companies such as Nike, Toyota, and Siemens are prioritizing sustainable innovation in their business models, setting an example for others to follow. In this Sustainability training presentation, you will learn key concepts, principles, and practices of sustainability applicable across industries. This training aims to create awareness and educate employees, senior executives, consultants, and other key stakeholders, including investors, policymakers, and supply chain partners, on the importance and implementation of sustainability.
LEARNING OBJECTIVES
1. Develop a comprehensive understanding of the fundamental principles and concepts that form the foundation of sustainability within corporate environments.
2. Explore the sustainability implementation model, focusing on effective measures and reporting strategies to track and communicate sustainability efforts.
3. Identify and define best practices and critical success factors essential for achieving sustainability goals within organizations.
CONTENTS
1. Introduction and Key Concepts of Sustainability
2. Principles and Practices of Sustainability
3. Measures and Reporting in Sustainability
4. Sustainability Implementation & Best Practices
To download the complete presentation, visit: https://www.oeconsulting.com.sg/training-presentations
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s DholeraAvirahi City Dholera
The Tata Group, a titan of Indian industry, is making waves with its advanced talks with Taiwanese chipmakers Powerchip Semiconductor Manufacturing Corporation (PSMC) and UMC Group. The goal? Establishing a cutting-edge semiconductor fabrication unit (fab) in Dholera, Gujarat. This isn’t just any project; it’s a potential game changer for India’s chipmaking aspirations and a boon for investors seeking promising residential projects in dholera sir.
Visit : https://www.avirahi.com/blog/tata-group-dials-taiwan-for-its-chipmaking-ambition-in-gujarats-dholera/
Skye Residences | Extended Stay Residences Near Toronto Airportmarketingjdass
Experience unparalleled EXTENDED STAY and comfort at Skye Residences located just minutes from Toronto Airport. Discover sophisticated accommodations tailored for discerning travelers.
Website Link :
https://skyeresidences.com/
https://skyeresidences.com/about-us/
https://skyeresidences.com/gallery/
https://skyeresidences.com/rooms/
https://skyeresidences.com/near-by-attractions/
https://skyeresidences.com/commute/
https://skyeresidences.com/contact/
https://skyeresidences.com/queen-suite-with-sofa-bed/
https://skyeresidences.com/queen-suite-with-sofa-bed-and-balcony/
https://skyeresidences.com/queen-suite-with-sofa-bed-accessible/
https://skyeresidences.com/2-bedroom-deluxe-queen-suite-with-sofa-bed/
https://skyeresidences.com/2-bedroom-deluxe-king-queen-suite-with-sofa-bed/
https://skyeresidences.com/2-bedroom-deluxe-queen-suite-with-sofa-bed-accessible/
#Skye Residences Etobicoke, #Skye Residences Near Toronto Airport, #Skye Residences Toronto, #Skye Hotel Toronto, #Skye Hotel Near Toronto Airport, #Hotel Near Toronto Airport, #Near Toronto Airport Accommodation, #Suites Near Toronto Airport, #Etobicoke Suites Near Airport, #Hotel Near Toronto Pearson International Airport, #Toronto Airport Suite Rentals, #Pearson Airport Hotel Suites
Unveiling the Secrets How Does Generative AI Work.pdfSam H
At its core, generative artificial intelligence relies on the concept of generative models, which serve as engines that churn out entirely new data resembling their training data. It is like a sculptor who has studied so many forms found in nature and then uses this knowledge to create sculptures from his imagination that have never been seen before anywhere else. If taken to cyberspace, gans work almost the same way.
Business Valuation Principles for EntrepreneursBen Wann
This insightful presentation is designed to equip entrepreneurs with the essential knowledge and tools needed to accurately value their businesses. Understanding business valuation is crucial for making informed decisions, whether you're seeking investment, planning to sell, or simply want to gauge your company's worth.
Improving profitability for small businessBen Wann
In this comprehensive presentation, we will explore strategies and practical tips for enhancing profitability in small businesses. Tailored to meet the unique challenges faced by small enterprises, this session covers various aspects that directly impact the bottom line. Attendees will learn how to optimize operational efficiency, manage expenses, and increase revenue through innovative marketing and customer engagement techniques.
Kseniya Leshchenko: Shared development support service model as the way to ma...Lviv Startup Club
Kseniya Leshchenko: Shared development support service model as the way to make small projects with small budgets profitable for the company (UA)
Kyiv PMDay 2024 Summer
Website – www.pmday.org
Youtube – https://www.youtube.com/startuplviv
FB – https://www.facebook.com/pmdayconference
The world of search engine optimization (SEO) is buzzing with discussions after Google confirmed that around 2,500 leaked internal documents related to its Search feature are indeed authentic. The revelation has sparked significant concerns within the SEO community. The leaked documents were initially reported by SEO experts Rand Fishkin and Mike King, igniting widespread analysis and discourse. For More Info:- https://news.arihantwebtech.com/search-disrupted-googles-leaked-documents-rock-the-seo-world/
What is the TDS Return Filing Due Date for FY 2024-25.pdfseoforlegalpillers
It is crucial for the taxpayers to understand about the TDS Return Filing Due Date, so that they can fulfill your TDS obligations efficiently. Taxpayers can avoid penalties by sticking to the deadlines and by accurate filing of TDS. Timely filing of TDS will make sure about the availability of tax credits. You can also seek the professional guidance of experts like Legal Pillers for timely filing of the TDS Return.
Digital Transformation and IT Strategy Toolkit and TemplatesAurelien Domont, MBA
This Digital Transformation and IT Strategy Toolkit was created by ex-McKinsey, Deloitte and BCG Management Consultants, after more than 5,000 hours of work. It is considered the world's best & most comprehensive Digital Transformation and IT Strategy Toolkit. It includes all the Frameworks, Best Practices & Templates required to successfully undertake the Digital Transformation of your organization and define a robust IT Strategy.
Editable Toolkit to help you reuse our content: 700 Powerpoint slides | 35 Excel sheets | 84 minutes of Video training
This PowerPoint presentation is only a small preview of our Toolkits. For more details, visit www.domontconsulting.com
The effects of customers service quality and online reviews on customer loyal...
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
1. Tender Summary (26-08-2019)
Solar Energy Corporation of India Limited
Selection of Project Developers for setting up of 1200 MW ISTS-Connected RE Projects with
Assured Peak Power Supply in India (ISTS-VII)
S.No Major Terms Details Page No
1 Project Name
Selection of Project Developers for setting up of 1200 MW ISTS-Connected RE Projects with
assured Peak Power Supply in India (ISTS-VII). Land, Connectivity and Long Term Open Access
shall be in the scope of the Hybrid Power Developer on Build-Own-Operate (BOO) basis.
Page 3
2
Tender Reference
Number
SECI/C&P/HPD/ISTS-VII/RfS/1200MW/082019 Page 3
3 Authority Solar Energy Corporation of India Limited (A Government of India Enterprise) Page 3
4
E-tender Online
Submission Date
17th
September 2019
2. 5 Pre-Bid Meeting
Date and Time: 21.08.2019 at 11:00 AM
Place: D - 3, 1 Floor, Wing - A, Prius Platinum Building, District Centre, Saket, New Delhi - 110017
Page 4
6
Tender submission
Website
https://www.bharat-electronictender.com Page 5
7
Earnest Money
Deposit (EMD)
INR 6,00,000/- (Indian Rupees Six Lakhs) per MW per Project Page 4
8 Tender Fees INR 29,500/- Inclusive of GST @ 18 % Page 3
9 Bid Processing Fees
Rs. 5 Lakh +18% GST for each Project from 50 MW up to 90 MW capacity,
Rs. 15 Lakh + 18% GST for each Project from 100 MW and above capacity.
Page 4
10 Bid Validity 180 days Page 55
11 Project Period 25 years as per provisions of PPA. Page 39
12 Tariff of the Projects
The selected projects will be eligible for “Peak Tariff” and “Off-Peak Tariff” as defined in the RfS.
Energy generated during the Off-Peak Hours shall be eligible for a fixed tariff payment @
Rs. 2.70/kWh, i.e. the Off-Peak Tariff.
Energy generated during the Peak Hours shall be purchased at the fixed tariff
discovered through e-Reverse Auction, i.e. the Peak tariff. The bidders shall quote only
for the Peak tariff.
This shall be inclusive of all statutory taxes, duties, levies, cess etc. if applicable as on the last date
of bid submission.
Page 15
13
Total Project
Capacity
1200 MW capacity
(Minimum capacity = 50 MW; Maximum capacity = 600 MW)
Page 22
14
Maximum Eligibility
for Project
A Bidder including its Parent, Affiliate or Ultimate Parent or any Group Company can
submit a single bid application for a minimum capacity of 50 MW up to 600 MW, which
shall be quoted only in multiples of 10 MW.
The capacity of a single Project shall range between (& including) 50 MW to 300 MW.
Page 25
15
Project
Configuration
A Project comprises of minimum two ‘components’ - one being the ESS component, and
the renewable energy generating component, which can be either a solar PV system,
or a wind power system, or a combination thereof. In case of a single generation source
Page 23 &
24
3. in addition to the ESS, the Contracted capacity of the Project shall be the rated capacity
of the wind or solar PV capacity installed in the Project.
The HPD shall set up the Project, including the dedicated transmission network up to the
Interconnection/ Delivery Point, at its own cost in accordance to the provisions of this
RfS document. All approvals, permits and clearances required for setting up of the Project
and/ or dedicated transmission network up to interconnection/ delivery point (including
connectivity and LTA) will be in the scope of the HPD.
16
Connectivity with
Grid
The Projects are required to be designed for inter-connection with transmission network of CTU
at voltage level of 220 kV or above. Page 22
17
Criteria for
Generation
The declared annual CUF shall in no case be less than 40% or 3.504 Million Units per MW on an
annual basis. Page 30
18 Success Charges
The Selected Bidders have to pay INR 1.00 Lakh/ MW/ Project + 18% GST to SECI towards
administrative overheads, coordination with State Authorities and others, DISCOM/ STU/ CTU,
pre-commissioning and commissioning expense. The payment has to be made by the HPD in the
form of DD/ Pay Order/ NEFT/ RTGS within 30 days of issuance of LoA.
Page 38
19
Payment Security
Deposit
Prior to declaration of commissioning of first part capacity of the Project, the SPD shall furnish a
Payment Security Deposit (PSD) @Rs.5 lakh/MW/Project, to SECI through DD/NEFT/RTGS. This
fund shall be non-refundable, and shall form part of the Payment Security Fund maintained by
SECI for the Projects. The above amount shall be credited to SECI pro-rata to the part capacity
being commissioned at that stage.
Page 39
20
Performance Bank
Guarantee (PBG)
Selected Bidders have to submit Performance Guarantee for a value @ INR 30 Lakh/ MW
within 30 days of issuance of Letter of Award (LoA) or before signing of PPA. It may be
noted that successful Bidders shall submit the Performance Guarantee according to the
Format 7.3B with a validity period of 27 months from the Effective Date of the PPA
Page 36 &
37
4. Delay upto 1 month from due date of submission of PBG: Delay charges @1% of the PBG
amount per month +18% GST levied on per day basis shall be paid by the HPD to SECI in
addition to the PBG amount.
In case of delay in making full payment of above delay charges, upto the date of PBG
submission, interest shall be levied on the delay charges @ one year SBI MCLR+18%GST.
The amount paid, if any until the above deadline, along with interest, shall be first
reduced from the total amount due towards the delay charges and interest amount (i.e.
rate of interest as stated below). Further, balance amount to be paid shall attract Interest
rate @ one year SBI MCLR rate /annum +18% GST on pro-rata basis.
Delay beyond 1 month from the due date of submission of PBG: The BG against EMD
submitted by the WPD shall be encashed by SECI and the Project shall stand terminated.
21 Land Arrangements
The HPD shall be entirely responsible for acquiring the land required for setting up the project
and SECI shall not in any manner be responsible for the same.
In case of the Project comprising only a solar PV and ESS component:
The HPD shall demonstrate possession of 100% (hundred percent) of the land identified
for the Project within 12 months from the Effective Date of the PPA (for e.g. if Effective
Date of the PPA is 07.03.2019, then the above deadline shall be 07.03.2020). The HPD
shall be required to demonstrate possession of a minimum area of 1.5 ha/MW for the
Project Capacity. In this regard, the HPD shall submit documents/Lease Agreement to
establish possession/right to use 100% of the required land in the same of the SPD or its
Affiliate. In case the land is in the name of the Affiliate, the land should be transferred in
the name of the HPD prior to the SCD. Wherever leasing of private land is involved, the
lease should allow transfer of land to the lenders or SECI, in case of default of the HPD.
In case the entire land as identified by the HPD for the Project is not under 100%
possession of the HPD within 12 months from the Effective Date of the PPA, the extension
Page 41 &
42
5. charges @Rs. 1,000/MW/day shall be levied on pro-rata basis to the land not acquired
until the SCD.
In all other cases:
The HPD shall demonstrate clear possession and right to use 100% (hundred percent) of the land
identified for the Project, on or before the Scheduled Commissioning Date of the Project. In this
regard, the HPD shall submit documents/lease agreement to establish possession/right to use
100% of the required land in the same of the HPD. Wherever leasing of private land is involved,
the lease should allow transfer of land to the lenders or SECI, in case of default of the HPD.
22 General Criteria
The Bidder should be a body incorporated in India under the Companies Act, 1956 or
2013 including any amendment thereto, Government owned Enterprises who are
registered and incorporated in India
Bidding Consortium with one of the Companies as Lead member. The shortlisted
Consortium has to necessarily form a Project Company and get it registered under the
Companies Act, 2013 prior to signing of PPA, keeping the original shareholding of the
Bidding Consortium unchanged. In case applications for multiple Projects have been
made by a Consortium, separate Project Companies can be formed for each Project.
Page 58
23 Technical Criteria
Under this RfS, it is proposed to promote only commercially established and operational
technologies to minimize the technology risk and to achieve timely commissioning of the
Projects. The Bidder may indicate regarding the selection of technology and its details at
the time of submission of bids in the prescribed Format.
The Projects shall achieve Financial Closure within 12 (twelve) months from the Effective
Date of the Power Purchase Agreement (PPA) (for e.g. if Effective Date of the PPA is
07.03.2019, then scheduled Financial Closure date shall be 07.03.2020).
An extension can however be considered, on the sole request of HPD, on advance
payment of extension charges of INR 1,000/- per day per MW.
Page 40,
41 & 59
6. 24 Financial Criteria
The Net Worth of the Bidder should be equal to or greater than INR 1.5 Crores per MW
of the quoted capacity, as on the last date of previous Financial Year, i.e. FY 2018-19, if
available, or 2017-18, or as on the date at least 7 days prior to the date of bid submission.
A minimum annual turnover of INR 1.02 Crores/MW of the quoted capacity during the
previous financial year, i.e. FY 2018-19.
Internal resource generation capability, in the form of Profit Before Depreciation
Interest and Taxes (PBDIT) for a minimum amount of INR 20 Lakhs/ MW of the quoted
capacity, as on the last date of previous financial year, i.e. FY 2018-19
In-principle sanction letter from the lending institutions/ banks of the Bidder,
committing a Line of Credit for a minimum amount of INR 25 Lakhs/ MW of the quoted
capacity, towards meeting the working capital requirement of the project quoted under
this RfS. Such letter can also be obtained by the Affiliate(s) of the Bidder.
Page 60 &
61
25
Joint Venture &
Consortium
Conditions
In case the response to RfS is submitted by a Consortium, then the financial requirement (both
the Net-Worth and Liquidity requirements) to be met by each Member of the Consortium shall
be computed in proportion to the equity commitment made by each of them in the Project
Company.
Page 62
26
Commissioning
Schedule of the
Project
In case of the Project comprising only a solar PV and ESS component:
The Scheduled Commissioning Date (SCD) for commissioning of the full capacity of the
Project shall be the date as on 18 months from the Effective Date of the PPA.
The maximum time period allowed for commissioning of the full Project Capacity shall be
limited to 24 months from the Effective Date of the PPA.
In all other cases:
The Project shall be fully commissioned within 18 months from the Effective date of the
PPA, or from the Effective Date of PSA, whichever is later i.e. the Scheduled
Page 44
7. Commissioning Date (SCD) In this regard, a duly constituted committee will physically
inspect and certify successful commissioning of the Project.
The maximum deadline allowed for commissioning of the full Project Capacity shall be
limited to the date as on 270 days from the SCD.
27 Liquidated Damages
In case of the Project comprising only a solar PV and ESS component:
In case of delay in commissioning of the Project beyond the SCD until the date as
indicated in Clause 16.b.i.b. above, as part of the liquidated damages, the total PBG
amount for the Project shall be encashed on per-day-basis and proportionate to the
balance capacity not commissioned. For the purpose of calculations of the liquidated
damages, ‘month’ shall be considered consisting of 30 days
In all other cases:
In case of delay in commissioning of the Project beyond the SCD until the deadline as per
Clause 16.b.ii.b. above, as part of the liquidated damages, the total PBG amount for the
Project shall be encashed on per-day basis and proportionate to the balance capacity not
commissioned
Page 44