ID Task Name Duration Actual Acc Start Finish
1 Replacement of Chilled Water Pipes 91 days 4.95 8/30/16 12/1/16
2 Receipt of P.O. 0 days 100 8/30/16 8/30/16
3 PR of Materials and approval 1 day 100 8/30/16 8/30/16
4 Processing of P.O. to suppliers 7 days 100 8/31/16 9/8/16
5 Mobilization 0 days 50 9/15/16 9/15/16
6 Safety Induction 1 day 0 9/16/16 9/16/16
7 Working at Heights seminar 1 day 0 9/17/16 9/17/16
8 Confined Space training 2 days 0 9/20/16 9/21/16
9 Inspection of Equipment of JEC by PSPC 3 days 0 9/16/16 9/18/16
10 Processing of Shell working permits 3 days 0 9/16/16 9/18/16
11 Processing of Building/Mechanical Permit 30 days 0 9/16/16 10/15/16
12 Delivery of HDPE Pipes 36 days 0 9/9/16 10/15/16
13 Delivery of Materials for Bracket and Initial
HDPE Pipe Delivery
20 days 0 9/9/16 9/29/16
14 Transfer of Shell Employees to another office 2 days 0 10/1/16 10/2/16
15 Fabrication of Pipe Supports 6 days 0 10/3/16 10/8/16
16 Cutting of Metals for Pipe Support 2 days 0 10/3/16 10/4/16
17 Welding of Pipe Support 3 days 0 10/5/16 10/7/16
18 Painting of Pipe Support 1 day 0 10/8/16 10/8/16
19 CHW Installation works 60 days 0 10/3/16 12/1/16
20 Boarding up and Protection of Furnitures 1 day 0 10/3/16 10/3/16
21 Scaffolding for the Removal of Ceiling tiles
and boards
2 days 0 10/4/16 10/5/16
22 Removal of Ceiling Tiles and boards 2 days 0 10/4/16 10/5/16
23 Scaffolding works for Pipe Support
Installation
3 days 0 10/9/16 10/11/16
24 Installation of Pipe Support 4 days 0 10/12/16 10/15/16
25 Installation of HDPE Pipes 17 days 0 10/16/16 11/1/16
26 Fusion of Flange to pipes 3 days 0 10/16/16 10/18/16
27 Fusion of Pipes 6 days 0 10/19/16 10/24/16
28 Scaffolding works for Mounting of Pipes
on Hangers
4 days 0 10/25/16 10/28/16
29 Mounting of pipes on hangers 6 days 0 10/27/16 11/1/16
30 Scaffolding works for Installation of Valves 5 days 0 11/2/16 11/6/16
31 Installation of Valves 9 days 0 11/2/16 11/12/16
32 Installation of Chemical Feeder Tank 3 days 0 10/31/16 11/2/16
33 Fabrication of Chemicak feeder tank
Support
1 day 0 10/31/16 10/31/16
34 Scaffolding works for Chemical feeder
Tank
1 day 0 11/1/16 11/1/16
35 Mounting of Chemical Feeder Tanks 1 day 0 11/2/16 11/2/16
36 Scaffolding works for Drain Line 2 days 0 10/18/16 10/19/16
37 Installation of Drain Lines 1 day 0 10/19/16 10/19/16
38 Leak Testing 5 days 0 11/13/16 11/17/16
39 Installation of testing port 1 day 0 11/13/16 11/13/16
40 charging the system with water 2 days 0 11/14/16 11/15/16
41 data gathering 2 days 0 11/16/16 11/17/16
42 Scaffolding for Insulation of Pipes 3 days 0 11/18/16 11/20/16
43 Insulation of Pipes 5 days 0 11/19/16 11/23/16
44 Insulation of Valves 5 days 0 11/19/16 11/23/16
45 Flushing 2 days 0 11/18/16 11/19/16
46 Interconnection to Existing CHW line 2 days 0 11/18/16 11/19/16
47 Scaffolding Works for the dismantling of
Existing CHW Pipes
3 days 0 11/20/16 11/22/16
48 Dismantling of Old Chilled water pipes 3 days 0 11/24/16 11/26/16
49 Punchlisting 3 days 0 11/27/16 11/29/16
50 Scaffolding for the Restoration of Ceiling 2 days 0 11/30/16 12/1/16
51 Restoration of Ceiling 2 days 0 11/30/16 12/1/16
52 Turnover 0 days 0 12/1/16 12/1/16
8/30 12/1
4%
8/30 8/30
100%
8/30 8/30
100%
8/31 9/8
100%
9/15 9/15
50%
9/16 9/16
0%
9/17 9/17
0%
9/20 9/21
0%
9/16 10/15
0%
9/9 10/15
0%
10/1 10/2
0%
10/3 10/4
0%
10/5 10/7
0%
10/8 10/8
0%
10/3 12/1
0%
10/9 10/11
0%
10/12 10/15
0%
10/16 11/1
0%
10/16 10/18
0%
10/19 10/24
0%
10/25 10/28
0%
10/27 11/1
0%
11/2 11/6
0%
11/2 11/12
0%
10/31 10/31
0%
11/1 11/1
0%
11/2 11/2
0%
10/18 10/19
0%
10/19 10/19
0%
11/13 11/13
0%
11/14 11/15
0%
11/16 11/17
0%
11/18 11/20
0%
11/19 11/23
0%
11/19 11/23
0%
11/18 11/19
0%
11/18 11/19
0%
11/20 11/22
0%
11/24 11/26
0%
11/27 11/29
0%
12/1 12/1
0%
8/28 9/4 9/11 9/18 9/25 10/2 10/9 10/16 10/23 10/30 11/6 11/13 11/20 11/27
September 1 September 21 October 11 November 1 November 21
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: Shell Timetables
Prepared by: Jess Bustamante
Date: 9/14/16

Chw piping works rev 6

  • 1.
    ID Task NameDuration Actual Acc Start Finish 1 Replacement of Chilled Water Pipes 91 days 4.95 8/30/16 12/1/16 2 Receipt of P.O. 0 days 100 8/30/16 8/30/16 3 PR of Materials and approval 1 day 100 8/30/16 8/30/16 4 Processing of P.O. to suppliers 7 days 100 8/31/16 9/8/16 5 Mobilization 0 days 50 9/15/16 9/15/16 6 Safety Induction 1 day 0 9/16/16 9/16/16 7 Working at Heights seminar 1 day 0 9/17/16 9/17/16 8 Confined Space training 2 days 0 9/20/16 9/21/16 9 Inspection of Equipment of JEC by PSPC 3 days 0 9/16/16 9/18/16 10 Processing of Shell working permits 3 days 0 9/16/16 9/18/16 11 Processing of Building/Mechanical Permit 30 days 0 9/16/16 10/15/16 12 Delivery of HDPE Pipes 36 days 0 9/9/16 10/15/16 13 Delivery of Materials for Bracket and Initial HDPE Pipe Delivery 20 days 0 9/9/16 9/29/16 14 Transfer of Shell Employees to another office 2 days 0 10/1/16 10/2/16 15 Fabrication of Pipe Supports 6 days 0 10/3/16 10/8/16 16 Cutting of Metals for Pipe Support 2 days 0 10/3/16 10/4/16 17 Welding of Pipe Support 3 days 0 10/5/16 10/7/16 18 Painting of Pipe Support 1 day 0 10/8/16 10/8/16 19 CHW Installation works 60 days 0 10/3/16 12/1/16 20 Boarding up and Protection of Furnitures 1 day 0 10/3/16 10/3/16 21 Scaffolding for the Removal of Ceiling tiles and boards 2 days 0 10/4/16 10/5/16 22 Removal of Ceiling Tiles and boards 2 days 0 10/4/16 10/5/16 23 Scaffolding works for Pipe Support Installation 3 days 0 10/9/16 10/11/16 24 Installation of Pipe Support 4 days 0 10/12/16 10/15/16 25 Installation of HDPE Pipes 17 days 0 10/16/16 11/1/16 26 Fusion of Flange to pipes 3 days 0 10/16/16 10/18/16 27 Fusion of Pipes 6 days 0 10/19/16 10/24/16 28 Scaffolding works for Mounting of Pipes on Hangers 4 days 0 10/25/16 10/28/16 29 Mounting of pipes on hangers 6 days 0 10/27/16 11/1/16 30 Scaffolding works for Installation of Valves 5 days 0 11/2/16 11/6/16 31 Installation of Valves 9 days 0 11/2/16 11/12/16 32 Installation of Chemical Feeder Tank 3 days 0 10/31/16 11/2/16 33 Fabrication of Chemicak feeder tank Support 1 day 0 10/31/16 10/31/16 34 Scaffolding works for Chemical feeder Tank 1 day 0 11/1/16 11/1/16 35 Mounting of Chemical Feeder Tanks 1 day 0 11/2/16 11/2/16 36 Scaffolding works for Drain Line 2 days 0 10/18/16 10/19/16 37 Installation of Drain Lines 1 day 0 10/19/16 10/19/16 38 Leak Testing 5 days 0 11/13/16 11/17/16 39 Installation of testing port 1 day 0 11/13/16 11/13/16 40 charging the system with water 2 days 0 11/14/16 11/15/16 41 data gathering 2 days 0 11/16/16 11/17/16 42 Scaffolding for Insulation of Pipes 3 days 0 11/18/16 11/20/16 43 Insulation of Pipes 5 days 0 11/19/16 11/23/16 44 Insulation of Valves 5 days 0 11/19/16 11/23/16 45 Flushing 2 days 0 11/18/16 11/19/16 46 Interconnection to Existing CHW line 2 days 0 11/18/16 11/19/16 47 Scaffolding Works for the dismantling of Existing CHW Pipes 3 days 0 11/20/16 11/22/16 48 Dismantling of Old Chilled water pipes 3 days 0 11/24/16 11/26/16 49 Punchlisting 3 days 0 11/27/16 11/29/16 50 Scaffolding for the Restoration of Ceiling 2 days 0 11/30/16 12/1/16 51 Restoration of Ceiling 2 days 0 11/30/16 12/1/16 52 Turnover 0 days 0 12/1/16 12/1/16 8/30 12/1 4% 8/30 8/30 100% 8/30 8/30 100% 8/31 9/8 100% 9/15 9/15 50% 9/16 9/16 0% 9/17 9/17 0% 9/20 9/21 0% 9/16 10/15 0% 9/9 10/15 0% 10/1 10/2 0% 10/3 10/4 0% 10/5 10/7 0% 10/8 10/8 0% 10/3 12/1 0% 10/9 10/11 0% 10/12 10/15 0% 10/16 11/1 0% 10/16 10/18 0% 10/19 10/24 0% 10/25 10/28 0% 10/27 11/1 0% 11/2 11/6 0% 11/2 11/12 0% 10/31 10/31 0% 11/1 11/1 0% 11/2 11/2 0% 10/18 10/19 0% 10/19 10/19 0% 11/13 11/13 0% 11/14 11/15 0% 11/16 11/17 0% 11/18 11/20 0% 11/19 11/23 0% 11/19 11/23 0% 11/18 11/19 0% 11/18 11/19 0% 11/20 11/22 0% 11/24 11/26 0% 11/27 11/29 0% 12/1 12/1 0% 8/28 9/4 9/11 9/18 9/25 10/2 10/9 10/16 10/23 10/30 11/6 11/13 11/20 11/27 September 1 September 21 October 11 November 1 November 21 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: Shell Timetables Prepared by: Jess Bustamante Date: 9/14/16