A 10 MW solar PV project schedule is outlined over 120 days from April 1st to July 29th, 2014. The schedule includes tasks such as site mobilization, civil works like grading and road construction, electrical works including installing modules, inverters and cabling, and commissioning the SCADA system. Major milestones are spaced approximately monthly throughout the implementation period.
A detailed project execution schedule including major and minor milestones for a 10 MW Plant. The EPC has been spread over 4 months. In case of larger or smaller power plants, the activities would remain same while the timeline would change
This is a PDF copy of the Gantt chart from my Scheduling class. This was the schedule created for the construction of a Tenant Improvement in a Warehouse
Title: Comprehensive Implementation Schedule for Power Transformer Project
Abstract:
This document presents a detailed implementation schedule for a power transformer project, encompassing the supply, delivery, manufacturing, installation, testing, and commissioning phases. The project aims to enhance the electricity infrastructure by procuring, manufacturing, and installing a high-capacity transformer. Through meticulous planning and scheduling, the project team seeks to ensure efficient resource utilization, timely delivery, and adherence to quality standards. The implementation schedule delineates key activities, timelines, dependencies, and milestones crucial for the successful execution of the project.
1. Introduction:
The successful execution of a power transformer project demands careful planning and efficient coordination across various phases. The implementation schedule presented herein serves as a roadmap for orchestrating activities related to supply chain management, manufacturing processes, site preparation, testing procedures, and commissioning activities. By delineating clear timelines, dependencies, and resource allocations, the schedule aims to facilitate seamless project execution and mitigate potential risks.
2. Project Overview:
The power transformer project entails the procurement, manufacturing, and installation of a high-capacity transformer to bolster the electricity infrastructure of a designated area. The project's objectives include addressing growing energy demands, improving reliability, and enhancing the resilience of the power distribution network. Through effective project management and adherence to the implementation schedule, the project team endeavors to achieve these objectives while ensuring compliance with regulatory standards and safety protocols.
3. Implementation Schedule:
3.1. Supply Phase:
The supply phase involves procuring raw materials, components, and equipment necessary for transformer manufacturing. Key activities include:
- Conducting market research to identify potential suppliers.
- Issuing requests for proposals (RFPs) and evaluating supplier bids.
- Negotiating contracts and finalizing procurement agreements.
- Monitoring supplier performance and ensuring timely delivery of materials.
The duration of the supply phase typically spans four weeks, allowing sufficient time for supplier selection, contract negotiation, and material acquisition.
3.2. Manufacturing Phase:
During the manufacturing phase, the transformer components are fabricated, assembled, and tested according to specifications. Key activities include:
- Fabricating transformer core and windings.
- Assembling core and windings to form the transformer unit.
- Conducting quality inspections and performance tests.
- Packaging and preparing the transformer for delivery to the installation site.
The manufacturing phase is a critical stage, typically spanning twelve weeks to ensure thorough fabrication, assembly, and testi
A Gantt chart is a type of bar chart, devised by Henry Gantt in the 1910s, that illustrates a project schedule. Gantt charts illustrate the start and finish dates of the terminal elements and summary elements of a project.
For a complete set of Project and other similar documents Please do visit
www.ProjectSupportTools.com
A detailed project execution schedule including major and minor milestones for a 10 MW Plant. The EPC has been spread over 4 months. In case of larger or smaller power plants, the activities would remain same while the timeline would change
This is a PDF copy of the Gantt chart from my Scheduling class. This was the schedule created for the construction of a Tenant Improvement in a Warehouse
Title: Comprehensive Implementation Schedule for Power Transformer Project
Abstract:
This document presents a detailed implementation schedule for a power transformer project, encompassing the supply, delivery, manufacturing, installation, testing, and commissioning phases. The project aims to enhance the electricity infrastructure by procuring, manufacturing, and installing a high-capacity transformer. Through meticulous planning and scheduling, the project team seeks to ensure efficient resource utilization, timely delivery, and adherence to quality standards. The implementation schedule delineates key activities, timelines, dependencies, and milestones crucial for the successful execution of the project.
1. Introduction:
The successful execution of a power transformer project demands careful planning and efficient coordination across various phases. The implementation schedule presented herein serves as a roadmap for orchestrating activities related to supply chain management, manufacturing processes, site preparation, testing procedures, and commissioning activities. By delineating clear timelines, dependencies, and resource allocations, the schedule aims to facilitate seamless project execution and mitigate potential risks.
2. Project Overview:
The power transformer project entails the procurement, manufacturing, and installation of a high-capacity transformer to bolster the electricity infrastructure of a designated area. The project's objectives include addressing growing energy demands, improving reliability, and enhancing the resilience of the power distribution network. Through effective project management and adherence to the implementation schedule, the project team endeavors to achieve these objectives while ensuring compliance with regulatory standards and safety protocols.
3. Implementation Schedule:
3.1. Supply Phase:
The supply phase involves procuring raw materials, components, and equipment necessary for transformer manufacturing. Key activities include:
- Conducting market research to identify potential suppliers.
- Issuing requests for proposals (RFPs) and evaluating supplier bids.
- Negotiating contracts and finalizing procurement agreements.
- Monitoring supplier performance and ensuring timely delivery of materials.
The duration of the supply phase typically spans four weeks, allowing sufficient time for supplier selection, contract negotiation, and material acquisition.
3.2. Manufacturing Phase:
During the manufacturing phase, the transformer components are fabricated, assembled, and tested according to specifications. Key activities include:
- Fabricating transformer core and windings.
- Assembling core and windings to form the transformer unit.
- Conducting quality inspections and performance tests.
- Packaging and preparing the transformer for delivery to the installation site.
The manufacturing phase is a critical stage, typically spanning twelve weeks to ensure thorough fabrication, assembly, and testi
A Gantt chart is a type of bar chart, devised by Henry Gantt in the 1910s, that illustrates a project schedule. Gantt charts illustrate the start and finish dates of the terminal elements and summary elements of a project.
For a complete set of Project and other similar documents Please do visit
www.ProjectSupportTools.com
PDF SubmissionDigital Marketing Institute in NoidaPoojaSaini954651
https://www.safalta.com/online-digital-marketing/advance-digital-marketing-training-in-noidaTop Digital Marketing Institute in Noida: Boost Your Career Fast
[3:29 am, 30/05/2024] +91 83818 43552: Safalta Digital Marketing Institute in Noida also provides advanced classes for individuals seeking to develop their expertise and skills in this field. These classes, led by industry experts with vast experience, focus on specific aspects of digital marketing such as advanced SEO strategies, sophisticated content creation techniques, and data-driven analytics.
Hello everyone! I am thrilled to present my latest portfolio on LinkedIn, marking the culmination of my architectural journey thus far. Over the span of five years, I've been fortunate to acquire a wealth of knowledge under the guidance of esteemed professors and industry mentors. From rigorous academic pursuits to practical engagements, each experience has contributed to my growth and refinement as an architecture student. This portfolio not only showcases my projects but also underscores my attention to detail and to innovative architecture as a profession.
Technoblade The Legacy of a Minecraft Legend.Techno Merch
Technoblade, born Alex on June 1, 1999, was a legendary Minecraft YouTuber known for his sharp wit and exceptional PvP skills. Starting his channel in 2013, he gained nearly 11 million subscribers. His private battle with metastatic sarcoma ended in June 2022, but his enduring legacy continues to inspire millions.
Connect Conference 2022: Passive House - Economic and Environmental Solution...TE Studio
Passive House: The Economic and Environmental Solution for Sustainable Real Estate. Lecture by Tim Eian of TE Studio Passive House Design in November 2022 in Minneapolis.
- The Built Environment
- Let's imagine the perfect building
- The Passive House standard
- Why Passive House targets
- Clean Energy Plans?!
- How does Passive House compare and fit in?
- The business case for Passive House real estate
- Tools to quantify the value of Passive House
- What can I do?
- Resources
1. SlideShare
Home
Explore
Search
Submit Search
Upload
B
You
MS Projects - 10 MW Implementation Schedule
Gensol Engineering Limited
Gensol Engineering Limited
•
Mar. 23, 2014
•
10 likes
•
9,155 views
Download Now
243
ID Task Name Duration Start Finish
1 Solar PV Project-10 MW 120 days Tue 4/1/14 Tue 7/29/14
2 Site mobilization 2 days Tue...ID Task Name Duration Start Finish
69 Installation and Termination of SCADA system 5 days Sat 7/19/14 Wed 7/23/14
70 Exter...
1 of 3
A detailed project execution schedule including major and minor milestones for a 10
MW Plant. The EPC has been spread over 4 months. In case of larger or smaller power
plants, the activities would remain same while the timeline would change
Read more
Technology
Recommended
Project master schedule daughter station cng mini plant
Project master schedule daughter station cng mini plant
PT. ANSI MEGA INSTRUMENINDO, Gunawan Widihardjo
Solar mango corporate presentation
Solar mango corporate presentation
Anjali Khandelwal
progress of work till date
progress of work till date
Mohsen Almashharawi
CV SAIF UR REHMAN
CV SAIF UR REHMAN
Saif kharal
2. C v surveyor( Mumtaz )
C v surveyor( Mumtaz )
Mumtaz Ahmad
Sample Project Works
Sample Project Works
Rahim Virani
Management Control System- Delhi Metro_10042016
Management Control System- Delhi Metro_10042016
Anil Kumar Gupta
MS project Sample gantt chart
MS project Sample gantt chart
Dhawal Thakkar PMP
Work breakdown structure & project life cycle
Work breakdown structure & project life cycle
Sayandeep Dasgupta
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
Gensol Engineering Limited
More Related Content
You Might Also Like
Related Books
Free with a 30 day trial from Scribd
See all
Related Audiobooks
Free with a 30 day trial from Scribd
See all
MS Projects - 10 MW Implementation Schedule
1. ID Task Name Duration Start Finish 1 Solar PV Project-10 MW 120 days Tue 4/1/14
Tue 7/29/14 2 Site mobilization 2 days Tue 4/1/14 Wed 4/2/14 3 Array Area and
General Works 110 days Sat 4/5/14 Wed 7/23/14 4 Civil Works 93 days Sat 4/5/14 Sun
7/6/14 5 Site Levelling and Grading 15 days Sat 4/5/14 Sat 4/19/14 6 Marking and
Construction of Boundary Wall 30 days Tue 4/15/14 Wed 5/14/14 7 Foundation and
Installation of Main Entry Gate 5 days Fri 4/18/14 Tue 4/22/14 8 Foundation and
Construction of Security Cabin 5 days Fri 4/18/14 Tue 4/22/14 9 Construction of
Internal Roads 5 days Tue 4/22/14 Sat 4/26/14 10 Foundation Marking for Structures
5 days Mon 4/21/14 Fri 4/25/14 11 Excavation for Structure Foundation 20 days Tue
4/22/14 Sun 5/11/14 12 Module Mounting Structure Casting 30 days Wed 4/23/14 Thu
5/22/14 13 String Monitoring Box Foundation 5 days Sat 5/3/14 Wed 5/7/14 14 Cable
trench 7 days Fri 5/23/14 Thu 5/29/14 15 Construction of Water Collection Tank 10
days Fri 5/23/14 Sun 6/1/14 16 Construction of Drainage system 30 days Tue 5/27/14
Wed 6/25/14 17 Borewell works 3 days Fri 5/23/14 Sun 5/25/14 18 Lightening Arrester
Foundation 5 days Sun 6/22/14 Thu 6/26/14 19 External Lighting Foundation 15 days
Sun 6/22/14 Sun 7/6/14 20 CCTV Camera Foundation 5 days Sun 6/22/14 Thu 6/26/14 21
Earth Pit Works 5 days Thu 6/12/14 Mon 6/16/14 22 Electrical Works 97 days Thu
4/17/14 Wed 7/23/14 23 Structure 57 days Thu 4/17/14 Fri 6/13/14 24 Purchase Order
for Structure 0 days Thu 4/17/14 Thu 4/17/14 25 Payment for Structure 0 days Thu
4/24/14 Thu 4/24/14 26 Receiving of Structure 25 days Fri 4/25/14 Mon 5/19/14 27
Installation of Structure 15 days Fri 5/30/14 Fri 6/13/14 28 PV Module 52 days Fri
4/25/14 Sun 6/15/14 29 Purchase Order for PV Module 0 days Fri 4/25/14 Fri 4/25/14
30 Payment for PV Module 7 days Fri 4/25/14 Fri 5/2/14 31 Receiving of PV Module 30
3. days Fri 5/2/14 Sun 6/1/14 32 Installation of PV Module 15 days Sun 6/1/14 Sun
6/15/14 33 String Monitoring Box 41 days Mon 4/21/14 Sat 5/31/14 34 Purchase Order
for SMB 0 days Mon 4/21/14 Mon 4/21/14 35 Payment for SMB 7 days Mon 4/21/14 Mon
4/28/14 36 Receiving of String Monitoring Box 30 days Mon 4/28/14 Wed 5/28/14 37
Installation of String Monitoring Box 4 days Wed 5/28/14 Sat 5/31/14 38 Inverter 69
days Sat 4/19/14 Thu 6/26/14 39 Purchase Order for Inverter 0 days Sat 4/19/14 Sat
4/19/14 40 Payment for Inverter 7 days Sat 4/19/14 Sat 4/26/14 41 Receiving of
Inverter 60 days Sat 4/26/14 Wed 6/25/14 42 Installation of Inverter 2 days Wed
6/25/14 Thu 6/26/14 43 DC Cable 64 days Tue 4/29/14 Tue 7/1/14 44 Purchase Order
for DC Cable 0 days Tue 4/29/14 Tue 4/29/14 45 Payment for DC Cable 7 days Tue
4/29/14 Tue 5/6/14 46 Receiving of DC Cable 45 days Tue 5/6/14 Fri 6/20/14 47
Laying of DC Cable 7 days Fri 6/20/14 Fri 6/27/14 48 Termination of DC Cable 5 days
Fri 6/27/14 Tue 7/1/14 49 OFC 60 days Thu 5/1/14 Sun 6/29/14 50 Purchase Order for
OFC 0 days Thu 5/1/14 Thu 5/1/14 51 Payment for OFC 7 days Thu 5/1/14 Thu 5/8/14 52
Receiving of OFC 45 days Thu 5/8/14 Sun 6/22/14 53 Laying of OFC 5 days Sun 6/22/14
Fri 6/27/14 54 Termination of OFC 3 days Fri 6/27/14 Sun 6/29/14 55 CCTV SYSTEM 40
days Sat 5/31/14 Wed 7/9/14 56 Purchase Order for CCTV 0 days Sat 5/31/14 Sat
5/31/14 57 Payment for CCTV 7 days Sat 5/31/14 Sat 6/7/14 58 Receiving of CCTV 30
days Sat 6/7/14 Mon 7/7/14 59 Installation of CCTV 3 days Mon 7/7/14 Wed 7/9/14 60
Lightening Arrestor 41 days Sat 5/31/14 Thu 7/10/14 61 Purchase order for
Lightening Arrestor 0 days Sat 5/31/14 Sat 5/31/14 62 Payment for Lightening
Arrestor 7 days Sat 5/31/14 Sat 6/7/14 63 Receiving of Lightening Arrestor 30 days
Sat 6/7/14 Mon 7/7/14 64 Installation of Lightening Arrestor 4 days Mon 7/7/14 Thu
7/10/14 65 SCADA System 72 days Tue 5/13/14 Wed 7/23/14 66 Purchase Order for SCADA
System 0 days Tue 5/13/14 Tue 5/13/14 67 Payment for SCADA System 7 days Tue
5/13/14 Tue 5/20/14 68 Receiving of SCADA 60 days Tue 5/20/14 Sat 7/19/14 /1 4/2
4/5 4/19 4/15 5/14 4/18 4/22 4/18 4/22 4/22 4/26 4/21 4/25 4/22 5/11 4/23 5/22 5/3
5/7 5/23 5/29 5/23 6/1 5/27 6/25 5/23 5/25 6/22 6/26 6/22 7/6 6/22 6/26 6/12 6/16
4/17 4/24 4/25 5/19 5/30 6/13 4/25 4/25 5/2 5/2 6/1 6/1 6/15 4/21 4/21 4/28 4/28
5/28 5/28 5/31 4/19 4/19 4/26 4/26 6/25 6/25 6/26 4/29 4/29 5/6 5/6 6/20 6/20 6/27
6/27 7/1 5/1 5/1 5/8 5/8 6/22 6/22 6/27 6/27 6/29 5/31 5/31 6/7 6/7 7/7 7/7 7/9
5/31 5/31 6/7 6/7 7/7 7/7 7/10 5/13 5/13 5/20 5/20 7/19 30 2 5 8 11 14 17 20 23 26
29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28
April 2014 May 2014 June 2014 July 2014 Task Progress Milestone Summary Rolled Up
Task Rolled Up Milestone Rolled Up Progress Split External Tasks Project Summary
Group By Summary Deadline Page 1 Project: Template PIS Date: Wed 3/19/14
2. ID Task Name Duration Start Finish 69 Installation and Termination of SCADA
system 5 days Sat 7/19/14 Wed 7/23/14 70 External Lighting 57 days Wed 5/21/14 Wed
7/16/14 71 Purchase Order for Poles and Lights 0 days Wed 5/21/14 Wed 5/21/14 72
Payment for Lighting System 7 days Wed 5/21/14 Wed 5/28/14 73 Receiving of Lighting
System 40 days Wed 5/28/14 Mon 7/7/14 74 Installation and Termination of Lighting
System 10 days Mon 7/7/14 Wed 7/16/14 75 Array Earthing 57 days Sun 5/18/14 Sun
7/13/14 76 Purchase Order for Earthing Equipments 0 days Sun 5/18/14 Sun 5/18/14 77
Payment for Earthing Equipments 7 days Sun 5/18/14 Sun 5/25/14 78 Receiving of
Earthing Equipments 40 days Sun 5/25/14 Fri 7/4/14 79 Array Earthing Installation
and Connection 10 days Fri 7/4/14 Sun 7/13/14 80 Main Control Room & Substation 86
days Thu 4/24/14 Fri 7/18/14 81 Civil Work in MCR & Substation 60 days Sat 4/26/14
Tue 6/24/14 82 Marking 2 days Sat 4/26/14 Sun 4/27/14 83 Excavation 3 days Mon
4/28/14 Wed 4/30/14 84 RCC Foundation 20 days Thu 5/1/14 Tue 5/20/14 85 Brick work
15 days Wed 5/21/14 Wed 6/4/14 86 Internal Plaster 7 days Thu 6/5/14 Wed 6/11/14 87
4. Flooring & Trenching 7 days Thu 6/12/14 Wed 6/18/14 88 Windows & Doors Fixing 7
days Thu 6/12/14 Wed 6/18/14 89 Painting work 7 days Thu 6/12/14 Wed 6/18/14 90
Finishing work of Substation Building 10 days Sun 6/15/14 Tue 6/24/14 91 Power and
Aux. Transformer Foundation 15 days Tue 5/6/14 Tue 5/20/14 92 Switch Yard Earthing
Mat Construction 7 days Fri 5/16/14 Thu 5/22/14 93 Switch Yard Equipment Foundation
15 days Fri 5/23/14 Fri 6/6/14 94 Foundation for Transmission Towers 30 days Fri
5/23/14 Sat 6/21/14 95 Electrical Works 86 days Thu 4/24/14 Fri 7/18/14 96
Transformers(Power and Aux.) 72 days Thu 4/24/14 Fri 7/4/14 97 Purchase Order for
Transformer 0 days Thu 4/24/14 Thu 4/24/14 98 Payment for Transformer 7 days Thu
4/24/14 Thu 5/1/14 99 Receiving of Transformer 60 days Thu 5/1/14 Mon 6/30/14 100
Installation of Transformer 5 days Mon 6/30/14 Fri 7/4/14 101 33 kV bay station 73
days Tue 4/29/14 Thu 7/10/14 102 Purchase Order for
VCB,Conductors,Isolator,CT,PT,Structure2 days Tue 4/29/14 Thu 5/1/14 103 Payment
for VCB,Conductors,Isolator,CT,PT,Structure7 days Thu 5/1/14 Thu 5/8/14 104
Receiving of Equipments 50 days Thu 5/8/14 Fri 6/27/14 105 Installation of
Equipments 7 days Fri 6/27/14 Thu 7/3/14 106 Termination of Conductors 7 days Fri
7/4/14 Thu 7/10/14 107 HT Panels 61 days Fri 5/9/14 Tue 7/8/14 108 Purchase Order
for HT Panels 0 days Fri 5/9/14 Fri 5/9/14 109 Payment for HT Panels 7 days Fri
5/9/14 Fri 5/16/14 110 Receiving of HT Panels 50 days Fri 5/16/14 Sat 7/5/14 111
Installation of HT Panels 4 days Sat 7/5/14 Tue 7/8/14 112 LT Panels 61 days Fri
5/9/14 Tue 7/8/14 113 Purchase Order for LT Panels 0 days Fri 5/9/14 Fri 5/9/14 114
Payment for LT Panels 7 days Fri 5/9/14 Fri 5/16/14 115 Receiving of LT Panels 50
days Fri 5/16/14 Sat 7/5/14 116 Installation of LT Panels 4 days Sat 7/5/14 Tue
7/8/14 117 LT Cable 72 days Sat 5/3/14 Sun 7/13/14 118 Purchase Order for LT Cable
0 days Sat 5/3/14 Sat 5/3/14 119 Payment for LT Cable 7 days Sat 5/3/14 Sat 5/10/14
120 Receiving of LT Cable 50 days Sat 5/10/14 Sun 6/29/14 121 Laying of LT Cable 5
days Sun 6/29/14 Thu 7/3/14 122 Terination of LT Cable 5 days Wed 7/9/14 Sun
7/13/14 123 HT Cable & Conductors 70 days Mon 5/5/14 Sun 7/13/14 124 Purchase Order
for HT Cable 0 days Mon 5/5/14 Mon 5/5/14 125 Payment for HT Cable 7 days Mon
5/5/14 Mon 5/12/14 126 Receiving of HT Cables 50 days Mon 5/12/14 Tue 7/1/14 127
Laying of HT Cable 5 days Tue 7/1/14 Sat 7/5/14 128 Termination of HT Cable 5 days
Wed 7/9/14 Sun 7/13/14 129 Control Cable 63 days Sat 5/10/14 Fri 7/11/14 130
Purchase Order for Control Cable 0 days Sat 5/10/14 Sat 5/10/14 131 Payment for
Control Cable 7 days Sat 5/10/14 Sat 5/17/14 132 Receiving of Control Cables 45
days Sat 5/17/14 Tue 7/1/14 133 Laying of Control Cable 4 days Tue 7/1/14 Fri
7/4/14 134 Termination of Control Cable 3 days Wed 7/9/14 Fri 7/11/14 135
Lightening Protection System 32 days Wed 5/21/14 Sat 6/21/14 136 Purchase Order for
LA 0 days Wed 5/21/14 Wed 5/21/14 7/19 7/23 5/21 5/21 5/28 5/28 7/7 7/7 7/16 5/18
5/18 5/25 5/25 7/4 7/4 7/13 4/26 4/27 4/28 4/30 5/1 5/20 5/21 6/4 6/5 6/11 6/12
6/18 6/12 6/18 6/12 6/18 6/15 6/24 5/6 5/20 5/16 5/22 5/23 6/6 5/23 6/21 4/24 4/24
5/1 5/1 6/30 6/30 7/4 4/29 5/1 5/1 5/8 5/8 6/27 6/27 7/3 7/4 7/10 5/9 5/9 5/16 5/16
7/5 7/5 7/8 5/9 5/9 5/16 5/16 7/5 7/5 7/8 5/3 5/3 5/10 5/10 6/29 6/29 7/3 7/9 7/13
5/5 5/5 5/12 5/12 7/1 7/1 7/5 7/9 7/13 5/10 5/10 5/17 5/17 7/1 7/1 7/4 7/9 7/11
5/21 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22
25 28 1 4 7 10 13 16 19 22 25 28 April 2014 May 2014 June 2014 July 2014 Task
Progress Milestone Summary Rolled Up Task Rolled Up Milestone Rolled Up Progress
Split External Tasks Project Summary Group By Summary Deadline Page 2 Project:
Template PIS Date: Wed 3/19/14
3. ID Task Name Duration Start Finish 137 Payment for LA 7 days Wed 5/21/14 Wed
5/28/14 138 Receiving of LA 20 days Wed 5/28/14 Tue 6/17/14 139 Installation of LA