1. ID Task Name Duration Start Finish
1 PEMBANGUNAN [EMBANGKIT LISTRIK TENAGA SURYA (PLTS) BADAK II 126 days 27/12/21 01/05/22
2 SP3MK 1 day 27/12/21 27/12/21
3 PEKERJAAN PERSIAPAN 22 days 30/12/21 20/01/22
4 Kick Of Meeting 1 day 30/12/21 30/12/21
5 Perijinan 14 days 01/01/22 14/01/22
6 Site office, Direksi KIT & Warehouse 14 days 31/12/21 13/01/22
7 Logistik, safety equipment, machinary & mobdemob 21 days 31/12/21 20/01/22
8 ENGINEERING 118 days 31/12/21 27/04/22
9 Kalkulasi & Data Sheet 14 days 31/12/21 13/01/22
10 Drawing 30 days 31/12/21 29/01/22
11 Prosedur 30 days 31/12/21 29/01/22
12 As Build Drawing 21 days 07/04/22 27/04/22
13 PENGADAAN MATERIAL 60 days 14/01/22 14/03/22
14 PV Module 60 days 14/01/22 14/03/22
15 Solar Cable Connector 60 days 14/01/22 14/03/22
16 DC Power Cable 60 days 14/01/22 14/03/22
17 String Inverter 60 days 14/01/22 14/03/22
18 LV Panel 60 days 14/01/22 14/03/22
19 LV Power Cable 60 days 14/01/22 14/03/22
20 Transformer 60 days 14/01/22 14/03/22
21 MV Switchgear 60 days 14/01/22 14/03/22
22 MV Power Cable 60 days 14/01/22 14/03/22
23 Weather Sensor & Monitoring System 45 days 14/01/22 27/02/22
24 Security System 60 days 14/01/22 14/03/22
25 Grounding & Lightning System 45 days 14/01/22 27/02/22
26 Cable Tray, Conduit and Accessories 45 days 14/01/22 27/02/22
27 KONSTRUKSI 89 days 22/01/22 20/04/22
28 Pekerjaan Sipil 62 days 22/01/22 24/03/22
29 Site Preparation 21 days 22/01/22 11/02/22
30 Persiapan Lahan 21 days 22/01/22 11/02/22
31 Survey Koordinat Pondasi 10 days 29/01/22 07/02/22
32 Foundation, Structure, & Mounting for PV Module 40 days 08/02/22 19/03/22
33 Foundation, Structure, & Mounting for Inverter 40 days 08/02/22 19/03/22
34 Foundation for Swicthgear & Transformer Skid 40 days 08/02/22 19/03/22
35 Foundation & Structure for KIOSK 45 days 08/02/22 24/03/22
36 Pekerjaan Elektrikal 37 days 15/03/22 20/04/22
37 Pemasangan PV Modul 30 days 15/03/22 13/04/22
38 Pemasangan Inverter & DC Combiner 21 days 20/03/22 09/04/22
39 Pemasangan Panel & Trafo 14 days 04/04/22 17/04/22
40 Pemasangan Kabel 21 days 15/03/22 04/04/22
41 Wiring 34 days 18/03/22 20/04/22
42 Wiring PV to PV 14 days 02/04/22 15/04/22
43 Wiring PV to Inverter 7 days 14/04/22 20/04/22
44 Wiring Inverter to LV Panel 7 days 05/04/22 11/04/22
45 Wiring LV Panel To Trafo 21 days 18/03/22 07/04/22
46 Wiring MV Panel to eksisting grid 21 days 18/03/22 07/04/22
47 Instalasi Weather Sensor & Monitoring System 14 days 05/04/22 18/04/22
48 Intallasi Grounding & Lightning System 21 days 25/03/22 14/04/22
49 PRE COMMISSIONING, COMMISSIONING & FINISHING 25 days 07/04/22 01/05/22
50 Mechanical Completion 14 days 07/04/22 20/04/22
51 Pre Commissioning 10 days 18/04/22 27/04/22
52 Continuty Test (Semua Kabel) 2 days 21/04/22 22/04/22
53 Megger Test (Kabel AC) 2 days 23/04/22 24/04/22
54 Grounding Test 2 days 25/04/22 26/04/22
55 Individual Test Inverter 1 day 27/04/22 27/04/22
56 SAT Trafo 2 days 18/04/22 19/04/22
57 Commissioning 3 days 28/04/22 30/04/22
58 Running Test Keseluruhan Sistem 3 days 28/04/22 30/04/22
59 Installation Acceptance 1 day 01/05/22 01/05/22
60 Final Acceptance 0 days 01/05/22 01/05/22 01/05
12/12 19/12 26/12 02/01 09/01 16/01 23/01 30/01 06/02 13/02 20/02 27/02 06/03 13/03 20/03 27/03 03/04 10/04 17/04 24/04 01/05 08/05
December January February March April May
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
PEMBANGUNAN [EMBANGKIT LISTRIK TENAGA SURYA (PLTS) BADAK II
Page 1
Project: Jadwal