SlideShare a Scribd company logo
1 of 1
Download to read offline
ID Task Name Duration Start Finish
1 PEMBANGUNAN [EMBANGKIT LISTRIK TENAGA SURYA (PLTS) BADAK II 126 days 27/12/21 01/05/22
2 SP3MK 1 day 27/12/21 27/12/21
3 PEKERJAAN PERSIAPAN 22 days 30/12/21 20/01/22
4 Kick Of Meeting 1 day 30/12/21 30/12/21
5 Perijinan 14 days 01/01/22 14/01/22
6 Site office, Direksi KIT & Warehouse 14 days 31/12/21 13/01/22
7 Logistik, safety equipment, machinary & mobdemob 21 days 31/12/21 20/01/22
8 ENGINEERING 118 days 31/12/21 27/04/22
9 Kalkulasi & Data Sheet 14 days 31/12/21 13/01/22
10 Drawing 30 days 31/12/21 29/01/22
11 Prosedur 30 days 31/12/21 29/01/22
12 As Build Drawing 21 days 07/04/22 27/04/22
13 PENGADAAN MATERIAL 60 days 14/01/22 14/03/22
14 PV Module 60 days 14/01/22 14/03/22
15 Solar Cable Connector 60 days 14/01/22 14/03/22
16 DC Power Cable 60 days 14/01/22 14/03/22
17 String Inverter 60 days 14/01/22 14/03/22
18 LV Panel 60 days 14/01/22 14/03/22
19 LV Power Cable 60 days 14/01/22 14/03/22
20 Transformer 60 days 14/01/22 14/03/22
21 MV Switchgear 60 days 14/01/22 14/03/22
22 MV Power Cable 60 days 14/01/22 14/03/22
23 Weather Sensor & Monitoring System 45 days 14/01/22 27/02/22
24 Security System 60 days 14/01/22 14/03/22
25 Grounding & Lightning System 45 days 14/01/22 27/02/22
26 Cable Tray, Conduit and Accessories 45 days 14/01/22 27/02/22
27 KONSTRUKSI 89 days 22/01/22 20/04/22
28 Pekerjaan Sipil 62 days 22/01/22 24/03/22
29 Site Preparation 21 days 22/01/22 11/02/22
30 Persiapan Lahan 21 days 22/01/22 11/02/22
31 Survey Koordinat Pondasi 10 days 29/01/22 07/02/22
32 Foundation, Structure, & Mounting for PV Module 40 days 08/02/22 19/03/22
33 Foundation, Structure, & Mounting for Inverter 40 days 08/02/22 19/03/22
34 Foundation for Swicthgear & Transformer Skid 40 days 08/02/22 19/03/22
35 Foundation & Structure for KIOSK 45 days 08/02/22 24/03/22
36 Pekerjaan Elektrikal 37 days 15/03/22 20/04/22
37 Pemasangan PV Modul 30 days 15/03/22 13/04/22
38 Pemasangan Inverter & DC Combiner 21 days 20/03/22 09/04/22
39 Pemasangan Panel & Trafo 14 days 04/04/22 17/04/22
40 Pemasangan Kabel 21 days 15/03/22 04/04/22
41 Wiring 34 days 18/03/22 20/04/22
42 Wiring PV to PV 14 days 02/04/22 15/04/22
43 Wiring PV to Inverter 7 days 14/04/22 20/04/22
44 Wiring Inverter to LV Panel 7 days 05/04/22 11/04/22
45 Wiring LV Panel To Trafo 21 days 18/03/22 07/04/22
46 Wiring MV Panel to eksisting grid 21 days 18/03/22 07/04/22
47 Instalasi Weather Sensor & Monitoring System 14 days 05/04/22 18/04/22
48 Intallasi Grounding & Lightning System 21 days 25/03/22 14/04/22
49 PRE COMMISSIONING, COMMISSIONING & FINISHING 25 days 07/04/22 01/05/22
50 Mechanical Completion 14 days 07/04/22 20/04/22
51 Pre Commissioning 10 days 18/04/22 27/04/22
52 Continuty Test (Semua Kabel) 2 days 21/04/22 22/04/22
53 Megger Test (Kabel AC) 2 days 23/04/22 24/04/22
54 Grounding Test 2 days 25/04/22 26/04/22
55 Individual Test Inverter 1 day 27/04/22 27/04/22
56 SAT Trafo 2 days 18/04/22 19/04/22
57 Commissioning 3 days 28/04/22 30/04/22
58 Running Test Keseluruhan Sistem 3 days 28/04/22 30/04/22
59 Installation Acceptance 1 day 01/05/22 01/05/22
60 Final Acceptance 0 days 01/05/22 01/05/22 01/05
12/12 19/12 26/12 02/01 09/01 16/01 23/01 30/01 06/02 13/02 20/02 27/02 06/03 13/03 20/03 27/03 03/04 10/04 17/04 24/04 01/05 08/05
December January February March April May
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
PEMBANGUNAN [EMBANGKIT LISTRIK TENAGA SURYA (PLTS) BADAK II
Page 1
Project: Jadwal

More Related Content

Similar to Jadwal Pelaksanaan PPI.pdf

ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0Ahmed Khaled
 
ADCO Time plan.pdf
ADCO Time plan.pdfADCO Time plan.pdf
ADCO Time plan.pdfabdo badr
 
Bgl solar update210614
Bgl solar update210614Bgl solar update210614
Bgl solar update210614Tejas Kale
 
Engineering Design Center Project Schedule
Engineering Design Center Project ScheduleEngineering Design Center Project Schedule
Engineering Design Center Project ScheduleVirginia Kam
 
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design ScheduleFitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design ScheduleGary Hayes
 
Offshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocolOffshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocolAllan Leyte
 
Sunshine_ W2 Dec'23_09.12.23.pptx
Sunshine_ W2 Dec'23_09.12.23.pptxSunshine_ W2 Dec'23_09.12.23.pptx
Sunshine_ W2 Dec'23_09.12.23.pptxabirsengupta9
 
Assignment 1 - Water Pump Station
Assignment 1 - Water Pump StationAssignment 1 - Water Pump Station
Assignment 1 - Water Pump StationKai Yun Pang
 

Similar to Jadwal Pelaksanaan PPI.pdf (11)

ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0
 
ADCO Time plan.pdf
ADCO Time plan.pdfADCO Time plan.pdf
ADCO Time plan.pdf
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
Bgl solar update210614
Bgl solar update210614Bgl solar update210614
Bgl solar update210614
 
Engineering Design Center Project Schedule
Engineering Design Center Project ScheduleEngineering Design Center Project Schedule
Engineering Design Center Project Schedule
 
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design ScheduleFitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
 
Offshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocolOffshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocol
 
Sunshine_ W2 Dec'23_09.12.23.pptx
Sunshine_ W2 Dec'23_09.12.23.pptxSunshine_ W2 Dec'23_09.12.23.pptx
Sunshine_ W2 Dec'23_09.12.23.pptx
 
Assignment 1 - Water Pump Station
Assignment 1 - Water Pump StationAssignment 1 - Water Pump Station
Assignment 1 - Water Pump Station
 
Slide4 mp psht1of6
Slide4 mp psht1of6Slide4 mp psht1of6
Slide4 mp psht1of6
 
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
 

Recently uploaded

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 

Recently uploaded (20)

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 

Jadwal Pelaksanaan PPI.pdf

  • 1. ID Task Name Duration Start Finish 1 PEMBANGUNAN [EMBANGKIT LISTRIK TENAGA SURYA (PLTS) BADAK II 126 days 27/12/21 01/05/22 2 SP3MK 1 day 27/12/21 27/12/21 3 PEKERJAAN PERSIAPAN 22 days 30/12/21 20/01/22 4 Kick Of Meeting 1 day 30/12/21 30/12/21 5 Perijinan 14 days 01/01/22 14/01/22 6 Site office, Direksi KIT & Warehouse 14 days 31/12/21 13/01/22 7 Logistik, safety equipment, machinary & mobdemob 21 days 31/12/21 20/01/22 8 ENGINEERING 118 days 31/12/21 27/04/22 9 Kalkulasi & Data Sheet 14 days 31/12/21 13/01/22 10 Drawing 30 days 31/12/21 29/01/22 11 Prosedur 30 days 31/12/21 29/01/22 12 As Build Drawing 21 days 07/04/22 27/04/22 13 PENGADAAN MATERIAL 60 days 14/01/22 14/03/22 14 PV Module 60 days 14/01/22 14/03/22 15 Solar Cable Connector 60 days 14/01/22 14/03/22 16 DC Power Cable 60 days 14/01/22 14/03/22 17 String Inverter 60 days 14/01/22 14/03/22 18 LV Panel 60 days 14/01/22 14/03/22 19 LV Power Cable 60 days 14/01/22 14/03/22 20 Transformer 60 days 14/01/22 14/03/22 21 MV Switchgear 60 days 14/01/22 14/03/22 22 MV Power Cable 60 days 14/01/22 14/03/22 23 Weather Sensor & Monitoring System 45 days 14/01/22 27/02/22 24 Security System 60 days 14/01/22 14/03/22 25 Grounding & Lightning System 45 days 14/01/22 27/02/22 26 Cable Tray, Conduit and Accessories 45 days 14/01/22 27/02/22 27 KONSTRUKSI 89 days 22/01/22 20/04/22 28 Pekerjaan Sipil 62 days 22/01/22 24/03/22 29 Site Preparation 21 days 22/01/22 11/02/22 30 Persiapan Lahan 21 days 22/01/22 11/02/22 31 Survey Koordinat Pondasi 10 days 29/01/22 07/02/22 32 Foundation, Structure, & Mounting for PV Module 40 days 08/02/22 19/03/22 33 Foundation, Structure, & Mounting for Inverter 40 days 08/02/22 19/03/22 34 Foundation for Swicthgear & Transformer Skid 40 days 08/02/22 19/03/22 35 Foundation & Structure for KIOSK 45 days 08/02/22 24/03/22 36 Pekerjaan Elektrikal 37 days 15/03/22 20/04/22 37 Pemasangan PV Modul 30 days 15/03/22 13/04/22 38 Pemasangan Inverter & DC Combiner 21 days 20/03/22 09/04/22 39 Pemasangan Panel & Trafo 14 days 04/04/22 17/04/22 40 Pemasangan Kabel 21 days 15/03/22 04/04/22 41 Wiring 34 days 18/03/22 20/04/22 42 Wiring PV to PV 14 days 02/04/22 15/04/22 43 Wiring PV to Inverter 7 days 14/04/22 20/04/22 44 Wiring Inverter to LV Panel 7 days 05/04/22 11/04/22 45 Wiring LV Panel To Trafo 21 days 18/03/22 07/04/22 46 Wiring MV Panel to eksisting grid 21 days 18/03/22 07/04/22 47 Instalasi Weather Sensor & Monitoring System 14 days 05/04/22 18/04/22 48 Intallasi Grounding & Lightning System 21 days 25/03/22 14/04/22 49 PRE COMMISSIONING, COMMISSIONING & FINISHING 25 days 07/04/22 01/05/22 50 Mechanical Completion 14 days 07/04/22 20/04/22 51 Pre Commissioning 10 days 18/04/22 27/04/22 52 Continuty Test (Semua Kabel) 2 days 21/04/22 22/04/22 53 Megger Test (Kabel AC) 2 days 23/04/22 24/04/22 54 Grounding Test 2 days 25/04/22 26/04/22 55 Individual Test Inverter 1 day 27/04/22 27/04/22 56 SAT Trafo 2 days 18/04/22 19/04/22 57 Commissioning 3 days 28/04/22 30/04/22 58 Running Test Keseluruhan Sistem 3 days 28/04/22 30/04/22 59 Installation Acceptance 1 day 01/05/22 01/05/22 60 Final Acceptance 0 days 01/05/22 01/05/22 01/05 12/12 19/12 26/12 02/01 09/01 16/01 23/01 30/01 06/02 13/02 20/02 27/02 06/03 13/03 20/03 27/03 03/04 10/04 17/04 24/04 01/05 08/05 December January February March April May Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress PEMBANGUNAN [EMBANGKIT LISTRIK TENAGA SURYA (PLTS) BADAK II Page 1 Project: Jadwal