A comparative study has been carried by Gensol on Solar-Wind Hybrid Policies issued by Central Government, Gujarat State & Andhra Pradesh (A.P.) in terms of following:
1) Incentives & Pertinent Charges
2) Evacuation & Metering Scheme
3) Energy Accounting & Banking
4) AC-DC Integration & other important clauses.
Solar Parks are becoming increasingly popular & MNRE is leaving no stone unturned to make them a success.
The ppt mentions the nuts & bolts of the Solar Park Scheme of MNRE.
Gensol has carried out state-wise comparative analysis for forecasting, scheduling and deviation settlement mechanism (DSM) of Solar & Wind projects. There has been huge requirement to facilitate large-scale RE integration with grid while maintaining grid stability and security as envisaged under the Grid Code.Following points are highlighted in this presentation:
1) Responsibility & Requirements
2) Available Capacity & Tolerance Band
3) Deviation Settlement Mechanism (DSM)
4) Metering, Energy & Deviation Accounting etc (Click here)
Here is first in the series of making Gujarat State the ‘Solar Rooftop Success’ in India! We talk about Gujarat’s Open Access charges here and present a ready reckoner for the rainy days.
Open Access was introduced in the Electricity Act, 2003 by Central Electricity Regulatory Commission. It is to provide “Non-Discriminatory” usage of transmission lines and distribution lines or associated facilities with such lines or system by any licensee or consumer or a person engaged in generation in accordance with the regulations specified by Appropriate Electricity Regulatory Committee. Open Access allows large users of power having connected load of 1 MW and above to buy cheaper power from the open market.
Any Open Access consumer, in lieu of usage of network/ services, shall have to pay Transmission Charges to the STU/ Transmission Licensee, Wheeling Charges to the Distribution Licensee and Operating Charges to the State Load Dispatch Centre. In addition the Open Access consumer shall have to pay to the Distribution Licensee, Additional Surcharge to meet the fixed cost of such Distribution Licensee arising out of his obligation to supply and the Cross Subsidy Surcharge which is a compensatory charge payable to the distribution licensee of the area where the electricity is delivered to the consumer. This Cross Subsidy Surcharge shall be utilized by the Distribution Licensee to meet the requirements of current level of cross subsidy within the area of supply. Also, an Open Access customer has to bear Transmission loss, if using the Transmission lines, Wheeling loss and Distribution loss, if using the Distribution lines. The losses vary as per injection and drawl voltage.
These charges and losses vary from state to state and are revised every year by the State Electricity Regulatory Committee based on petitions filed by the Transmission and Distribution Utilities of the State.
Open Access is categorized based on the period for which open access is allowed. This period may vary from state to state.
This presentation highlights on the following :
Need of wind-solar hybrid systems
Indian policy support to hybrid systems - MNRE & Gujarat State
Renewable Energy integration with grid,
Cost savings in hybrid for AC-AC & DC-DC coupling systems,
Case studies
The Sate of Tamil Nadu has recently released new solar policy with highly ambitious target of 9GW by 2023. Gensol has highlighted key areas of focus & inferences with respect to incentives, energy accounting, wheeling of power etc.
The technical risks in solar PV projects are arising mainly in modules, inverters, other equipment. These risks are unpredictable and can be occurred in any phases of life cycle of PV project like development, installation, commissioning and operation leading to plant outage or reduction in energy output. The presentation covers the various risks and associated mitigation measures.
Solar Parks are becoming increasingly popular & MNRE is leaving no stone unturned to make them a success.
The ppt mentions the nuts & bolts of the Solar Park Scheme of MNRE.
Gensol has carried out state-wise comparative analysis for forecasting, scheduling and deviation settlement mechanism (DSM) of Solar & Wind projects. There has been huge requirement to facilitate large-scale RE integration with grid while maintaining grid stability and security as envisaged under the Grid Code.Following points are highlighted in this presentation:
1) Responsibility & Requirements
2) Available Capacity & Tolerance Band
3) Deviation Settlement Mechanism (DSM)
4) Metering, Energy & Deviation Accounting etc (Click here)
Here is first in the series of making Gujarat State the ‘Solar Rooftop Success’ in India! We talk about Gujarat’s Open Access charges here and present a ready reckoner for the rainy days.
Open Access was introduced in the Electricity Act, 2003 by Central Electricity Regulatory Commission. It is to provide “Non-Discriminatory” usage of transmission lines and distribution lines or associated facilities with such lines or system by any licensee or consumer or a person engaged in generation in accordance with the regulations specified by Appropriate Electricity Regulatory Committee. Open Access allows large users of power having connected load of 1 MW and above to buy cheaper power from the open market.
Any Open Access consumer, in lieu of usage of network/ services, shall have to pay Transmission Charges to the STU/ Transmission Licensee, Wheeling Charges to the Distribution Licensee and Operating Charges to the State Load Dispatch Centre. In addition the Open Access consumer shall have to pay to the Distribution Licensee, Additional Surcharge to meet the fixed cost of such Distribution Licensee arising out of his obligation to supply and the Cross Subsidy Surcharge which is a compensatory charge payable to the distribution licensee of the area where the electricity is delivered to the consumer. This Cross Subsidy Surcharge shall be utilized by the Distribution Licensee to meet the requirements of current level of cross subsidy within the area of supply. Also, an Open Access customer has to bear Transmission loss, if using the Transmission lines, Wheeling loss and Distribution loss, if using the Distribution lines. The losses vary as per injection and drawl voltage.
These charges and losses vary from state to state and are revised every year by the State Electricity Regulatory Committee based on petitions filed by the Transmission and Distribution Utilities of the State.
Open Access is categorized based on the period for which open access is allowed. This period may vary from state to state.
This presentation highlights on the following :
Need of wind-solar hybrid systems
Indian policy support to hybrid systems - MNRE & Gujarat State
Renewable Energy integration with grid,
Cost savings in hybrid for AC-AC & DC-DC coupling systems,
Case studies
The Sate of Tamil Nadu has recently released new solar policy with highly ambitious target of 9GW by 2023. Gensol has highlighted key areas of focus & inferences with respect to incentives, energy accounting, wheeling of power etc.
The technical risks in solar PV projects are arising mainly in modules, inverters, other equipment. These risks are unpredictable and can be occurred in any phases of life cycle of PV project like development, installation, commissioning and operation leading to plant outage or reduction in energy output. The presentation covers the various risks and associated mitigation measures.
Solar PV O&M looks easy however maintaining a Solar PV Plant at top performance is a task and based on the experience of Solarig-Gensol in maintaining a 2 GW portfolio of solar plants in India, here are some basics on Solar O&M.
Presentation has the following contents:
a) Balancing Soiling Losses with case study
b) Monitoring & Corrective Maintenance
c) Performance Ratio & Uptime Guarantee
d) Impact of O&M on IRR
What services should a solar project developer expect from solar park & how much each service can be valued.
The ppt clears concept on value add by solar park.
The presentation focuses on the investment opportunities in commercial and industrial rooftop building in India. Sensitivity analysis has been carried out for 11 states to understand the impact on project economics in terms of PIRR, EIRR, and payback periods.
The Power Generated in Karnataka(INDIA) is 7445.91MW and Demand is 8500MWwhich
causes the problem of Load shedding, many states face this problem and are forced to buy the power from
other states which leads to the extra economical burden, this is where the Distributed Generation (DG)
plays a role to cut down the costs of the power purchased. This paper discusses the various aspects of DG
Opportunities, conversion system, technology interconnections and environmental performance. Also
some of the challenges DG system is confronting, an overview of connection between DG system and
Microgrid, the feature aspects of DG and benefits of DG system are also brought out
Request for Proposal (RfP) For Installation of 2 MW Canal Top Grid connecte...Harish Sharma
Request for Proposal (RfP/PV/RREC/Canal top) invited by RREC on behalf of
Water Resource Department, GoR/ IGN Board and Discoms of Rajasthan for selection
of developers for setting up of 2MW Grid connected Solar PV Plant on canal top to
be connected on 11kV level at Discoms 33/11kV Substation in Rajasthan under
Rajasthan Solar Energy Policy, 2014 for sale of power to Rajasthan Discoms
through tariff based competitive bidding process. "EnvironmentFirst Energy Services Pvt. Ltd." is facilitating the bid documentation for the successful project allocation. You contact us at info@environmentfirst.in
Assessment of Photovoltaic Module Failures in the FieldLeonardo ENERGY
This Webinar will present the current status and predictive ability for the power loss of PV modules for specific failure modes. The team describes PV module material interactions and incompatibilities among encapsulation materials and lamination processes so as to better understand PV module failures mechanism.
What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?
Hybrid Power System is the integration of number of generating plants those are working together serve a particular region. They may be off grid or may not be.
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Headway Solar
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Power Plants Punjab 2014
This document is not a work of Headway Solar (http://headwaysolar.com/) and it has been released here for the benefit of the general public.
Solar PV O&M looks easy however maintaining a Solar PV Plant at top performance is a task and based on the experience of Solarig-Gensol in maintaining a 2 GW portfolio of solar plants in India, here are some basics on Solar O&M.
Presentation has the following contents:
a) Balancing Soiling Losses with case study
b) Monitoring & Corrective Maintenance
c) Performance Ratio & Uptime Guarantee
d) Impact of O&M on IRR
What services should a solar project developer expect from solar park & how much each service can be valued.
The ppt clears concept on value add by solar park.
The presentation focuses on the investment opportunities in commercial and industrial rooftop building in India. Sensitivity analysis has been carried out for 11 states to understand the impact on project economics in terms of PIRR, EIRR, and payback periods.
The Power Generated in Karnataka(INDIA) is 7445.91MW and Demand is 8500MWwhich
causes the problem of Load shedding, many states face this problem and are forced to buy the power from
other states which leads to the extra economical burden, this is where the Distributed Generation (DG)
plays a role to cut down the costs of the power purchased. This paper discusses the various aspects of DG
Opportunities, conversion system, technology interconnections and environmental performance. Also
some of the challenges DG system is confronting, an overview of connection between DG system and
Microgrid, the feature aspects of DG and benefits of DG system are also brought out
Request for Proposal (RfP) For Installation of 2 MW Canal Top Grid connecte...Harish Sharma
Request for Proposal (RfP/PV/RREC/Canal top) invited by RREC on behalf of
Water Resource Department, GoR/ IGN Board and Discoms of Rajasthan for selection
of developers for setting up of 2MW Grid connected Solar PV Plant on canal top to
be connected on 11kV level at Discoms 33/11kV Substation in Rajasthan under
Rajasthan Solar Energy Policy, 2014 for sale of power to Rajasthan Discoms
through tariff based competitive bidding process. "EnvironmentFirst Energy Services Pvt. Ltd." is facilitating the bid documentation for the successful project allocation. You contact us at info@environmentfirst.in
Assessment of Photovoltaic Module Failures in the FieldLeonardo ENERGY
This Webinar will present the current status and predictive ability for the power loss of PV modules for specific failure modes. The team describes PV module material interactions and incompatibilities among encapsulation materials and lamination processes so as to better understand PV module failures mechanism.
What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?
Hybrid Power System is the integration of number of generating plants those are working together serve a particular region. They may be off grid or may not be.
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Headway Solar
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Power Plants Punjab 2014
This document is not a work of Headway Solar (http://headwaysolar.com/) and it has been released here for the benefit of the general public.
Net metering requirements in punjab for grid interactive rooftop SPV Power PlantHarish Sharma
All the consumers of the State Distribution licensee or PSPCL who intend to encourage solar energy and set up solar PV plants at available places on roof-tops of Individual households, industries, Government or Semi-Government or Local Body offices, commercial establishments, institutions, residential complexes shall be eligible with project capacity ranging from minimum 1 KWp upto 1MWp (AC side) with or without battery back-up support. Consumers may generate solar power for self consumption and may feed excess power into the grid to be adjusted.
MNRE Clarification on the capacity with respect to inverter and eligibility o...Harish Sharma
MNRE Clarification on the eligibility of CFA for rooftop solar plants (with or without net metering/gross metering facility) and for declaring commissioned plant capacity w.r.t installed inverter capacity.
The minimum voltage tevel for interfacing of NRSE/CPP projects with State Gri...HARTEK POWER
As per recent policy by PSPCL published on june 8 2015. It talks about the minimum voltage level (depending upon nearest grid substation) for interfacing of NRSE/CPP projects with State Grid(Punjab) will be as follows
- upto 2.5 MW - 11KV
- upto 2.5 MW - 25 MW - 33KV/66KV
-above 25 MW - 132KV/220KV
Official Document of the Manipur solar policy 2014.
This document is not a work of Headway Solar (http://headwaysolar.com/) and it has been released here for the benefit of the general public.
Hybrid Controller | Design 150KW PV with DG1:700KWEyad Adnan
Hybrid Fuel /PV controller is specifically designed to power systems that combine diesel and renewable forms of power generation.
see complete project:150KW PV design
eyad_adnan@yahoo.com
Tariff policy of India: Salient Points Amitava Nag
Revised Tariff Policy notified by MoP on 28.01.2016.State Government can notify a policy to encourage investment in the State by allowing setting up of generating plants, including from renewable energy sources out of which a maximum of 35% of the installed capacity can be procured by the Distribution Licensees of that State for which the tariff may be determined under Section 62 of the Electricity Act, 2003.
Gensol has summarised the tender issued by SECI for 2.5GW Wind Solar Hybrid ISTS projects.
The document covers major commercial & technical guidelines provided in the tender.
Gensol has estimated Bifacial Gain varying between ~4.0-10.5% when Bifacial PV Modules are configured with Single Axis Tracker (SAT) system depending on system configuration & ground albedo. Various iterations of energy generation were simulated using PVsyst to understand the impact of design considerations and climatic factors on the Bifacial Gain of 1P x 30 Bifacial PV array with SAT system equipped over-torque tube for India & Middle East regions.
Gensol collected Actual Global Tilted Irradiation (AGTI) of 57 sites from operational projects spread across in India. It was then correlated with Expected Global Tilted Irradiation (EGTI) from the following meteo-databases namely:
1) Meteonorm-7.2
2) SolarGIS,
3) NASA (National Aeronautics and Space Administration),
4) NREL (National Renewable Energy Laboratory)
In our report, we find most representative meteo-data set for each site.
Gensol is a leading Solar Advisory and Operation & Maintenance Service Provider with a footprint across 13 countries and 20 GW of projects. This presentation showcase company's business verticals, leadership team, growth trajectory, global presence, major projects executed (National, Government & International).
Blu-Smart has carried out a comparative of India Vs countries like China, Belgium, Germany, Italy and many more with respect to electric vehicle policies, tax benefits & incentives applicable.
Here are the details on 300MW Wind Power Project located in the Western Region of India presented by Gensol on the various phases of construction & execution; starting from :
1)Wind resource assessment,
2)Site feasibility studies,
3)Statuary & legal approvals required,
4)Civil & electrical works,
5)Quality & material inspection,
6)Post erection & monitoring etc.
(Click here to read more..)
Gensol has presented quicks highlights of 1200MW Renewable Energy Tender with assured Peak Power Supply in terms of eligibility criteria, bidders obligations, project capacity (MW), generation criteria, various guarantees, project tariff rate (Rs/kWh) and many more. It's interesting to highlight that SECI has issued tender with no cap in tariff at the same assured peak power supply.
The document mentions the following with tentative quantities:
1. List of 17 nos. of main equipment
2. List of 15 nos. of miscellaneous equipment
3. List of 16 nos. of civil works required
4. List of 8 nos. of lattice type equipment
5. List of 11 nos. of foundations required
Gensol has summarized the list of upcoming tenders in India by State & Central Government authorities to achieve National Solar Mission (NSM) targets. This document covers list of EPC & IPP tenders for ground mounted, rooftop solar, floating solar and hybrid projects for various locations in India .
The document summarizes the list of successful bidders, awarded capacity (MW) and ceiling tariff rate (Rs/kWh) for the latest released solar PV tenders.
Module price trend has declined with the increased solar PV demand & competition among the industry. The trend has been studied & forecast has been evaluated by Gensol for the modules supplied from South East Asia especially China to India from September 2013 to January 2019. The following points are highlighted:
1) Global & India Solar PV Installations & Forecast (GW)
2) Solar PV System Cost Trend Global & India 2014-2018
3) Module Price Trend (2014- 2018) & Forecast (2019 -2026)
4) Quarterly Variation in Module Price Trend YoY in %
5) Solar PV Demand in India 2017 Vs 2018
WTG has many components & the audit checklist helps to maintain the WTG. Checklist covers the following options -
a) Transformer
b) Isolator
c) VCB Panel & Switch Yard
d) Power Panel
e) Capacitor Panel
f) DFIG Panel
g) Control Panel
h) Junction Box
i) Tubular Tower Shell
j) Climb Arrestor
k) Cables
l) Yaw System
m) Main Bearing
n) Gear Box
o) Generator
p) Rotor Brake
q) Hydraulic Unit
r) Hub Lock
s) Nacelle Control Panel
t) Anemometer & Wind Pane
u) Rotor Blade
v) Battery Bank
w) Nose Cone
The largest tender by Solar Energy Corporation of India for Floating Solar for 150 MW is up for bidding.
The document is a summary of the tender document and covers the commercial & technical guidelines provided in the tender.
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...Gensol Engineering Limited
The presentation is a detailed study on the following:
a) Impact of solar module component on reliability
b) Raw Material - Quality Assurance
c) Manufacturing Process - Quality Assurance
d) Lab Inspection
e) On site module inspection
Gensol has achieved 2 GW of Lender Engineer Credentials at various states of India for both Ground-mounted and Rooftop projects. Gensol has provided Lenders Independent services to major lenders like Power Finance Corporation (PFC), IDBI, IndusInd, SBI, Tata Cleantech etc.
Floating Solar is a 10 GW opportunity in India & the ppt is an introduction to Floating Solar with the following content:
a) Floating Solar Market Outlook
b) Benefits of Floating Solar
c) Working Methodology & Design of Floating Solar
d) Case Studies
The presentation highlights the following :
a) Current status of Renewable Energy in India
b) The issue of duck curve due to high volume of solar energy
c) Demand increase due to Electric Vehicle (EV) will lead to more demand for Renewable Energy
d) Global & Indian Market Scenario for Electric Vehicle (EV)
e) Recommendation of Niti Aayog for development of Electric Vehicle (EV) market in India
Gensol Group Profile - Solar Advisory, Solar Rooftop EPC, Solar O&M (13.12.17)Gensol Engineering Limited
Gensol is the largest Solar Advisory Firm with 7900 MW of solar projects under advisory (including design, lenders engineer, owner engineer) , 49 MW of solar projects under Engineering Procurement and Construction (EPC) & 2200 MW of solar projects under Operation and Maintenance.
Presentation on the status of "Achievement Under National Solar Mission (NSM)" till July'17.
The key highlight being that 13,115 MW of solar projects have been commissioned. The presentation outlays of how "100 GW" of target shall be achieved based on various schemes under progress. Also last few slides focus on Off Grid Targets under NSM.
Multiple Energy Storage Technologies are being developed & are maturing, Gensol did an analysis of 1635 Energy Storage Projects developed globally to come up with which technology has captured market share.
The presentation also has multiple case studies.
Solar Energy Corporation of India (SECI) had, on 15th May (Monday), unveiled the list of bidders who had submitted bids for a total tendered capacity of 500 MW solar rooftop projects (originally 1000 MW). Our representative had witnessed the event and has collated first-hand information, which, we wish to clarify might carry some shades of inaccuracy and the numbers might not be entirely sacrosanct.
Nevertheless, you can peep into the document to know which states are on fire and mostly sought, who are the bidders in the race to pick up allocation and who are the new entrants that have thrown their hats in the ring for the first time.
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...BBPMedia1
Grote partijen zijn al een tijdje onderweg met retail media. Ondertussen worden in dit domein ook de kansen zichtbaar voor andere spelers in de markt. Maar met die kansen ontstaan ook vragen: Zelf retail media worden of erop adverteren? In welke fase van de funnel past het en hoe integreer je het in een mediaplan? Wat is nu precies het verschil met marketplaces en Programmatic ads? In dit half uur beslechten we de dilemma's en krijg je antwoorden op wanneer het voor jou tijd is om de volgende stap te zetten.
Personal Brand Statement:
As an Army veteran dedicated to lifelong learning, I bring a disciplined, strategic mindset to my pursuits. I am constantly expanding my knowledge to innovate and lead effectively. My journey is driven by a commitment to excellence, and to make a meaningful impact in the world.
The world of search engine optimization (SEO) is buzzing with discussions after Google confirmed that around 2,500 leaked internal documents related to its Search feature are indeed authentic. The revelation has sparked significant concerns within the SEO community. The leaked documents were initially reported by SEO experts Rand Fishkin and Mike King, igniting widespread analysis and discourse. For More Info:- https://news.arihantwebtech.com/search-disrupted-googles-leaked-documents-rock-the-seo-world/
Falcon stands out as a top-tier P2P Invoice Discounting platform in India, bridging esteemed blue-chip companies and eager investors. Our goal is to transform the investment landscape in India by establishing a comprehensive destination for borrowers and investors with diverse profiles and needs, all while minimizing risk. What sets Falcon apart is the elimination of intermediaries such as commercial banks and depository institutions, allowing investors to enjoy higher yields.
Implicitly or explicitly all competing businesses employ a strategy to select a mix
of marketing resources. Formulating such competitive strategies fundamentally
involves recognizing relationships between elements of the marketing mix (e.g.,
price and product quality), as well as assessing competitive and market conditions
(i.e., industry structure in the language of economics).
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s DholeraAvirahi City Dholera
The Tata Group, a titan of Indian industry, is making waves with its advanced talks with Taiwanese chipmakers Powerchip Semiconductor Manufacturing Corporation (PSMC) and UMC Group. The goal? Establishing a cutting-edge semiconductor fabrication unit (fab) in Dholera, Gujarat. This isn’t just any project; it’s a potential game changer for India’s chipmaking aspirations and a boon for investors seeking promising residential projects in dholera sir.
Visit : https://www.avirahi.com/blog/tata-group-dials-taiwan-for-its-chipmaking-ambition-in-gujarats-dholera/
What are the main advantages of using HR recruiter services.pdfHumanResourceDimensi1
HR recruiter services offer top talents to companies according to their specific needs. They handle all recruitment tasks from job posting to onboarding and help companies concentrate on their business growth. With their expertise and years of experience, they streamline the hiring process and save time and resources for the company.
What is the TDS Return Filing Due Date for FY 2024-25.pdfseoforlegalpillers
It is crucial for the taxpayers to understand about the TDS Return Filing Due Date, so that they can fulfill your TDS obligations efficiently. Taxpayers can avoid penalties by sticking to the deadlines and by accurate filing of TDS. Timely filing of TDS will make sure about the availability of tax credits. You can also seek the professional guidance of experts like Legal Pillers for timely filing of the TDS Return.
Digital Transformation and IT Strategy Toolkit and TemplatesAurelien Domont, MBA
This Digital Transformation and IT Strategy Toolkit was created by ex-McKinsey, Deloitte and BCG Management Consultants, after more than 5,000 hours of work. It is considered the world's best & most comprehensive Digital Transformation and IT Strategy Toolkit. It includes all the Frameworks, Best Practices & Templates required to successfully undertake the Digital Transformation of your organization and define a robust IT Strategy.
Editable Toolkit to help you reuse our content: 700 Powerpoint slides | 35 Excel sheets | 84 minutes of Video training
This PowerPoint presentation is only a small preview of our Toolkits. For more details, visit www.domontconsulting.com
3.0 Project 2_ Developing My Brand Identity Kit.pptxtanyjahb
A personal brand exploration presentation summarizes an individual's unique qualities and goals, covering strengths, values, passions, and target audience. It helps individuals understand what makes them stand out, their desired image, and how they aim to achieve it.
[Note: This is a partial preview. To download this presentation, visit:
https://www.oeconsulting.com.sg/training-presentations]
Sustainability has become an increasingly critical topic as the world recognizes the need to protect our planet and its resources for future generations. Sustainability means meeting our current needs without compromising the ability of future generations to meet theirs. It involves long-term planning and consideration of the consequences of our actions. The goal is to create strategies that ensure the long-term viability of People, Planet, and Profit.
Leading companies such as Nike, Toyota, and Siemens are prioritizing sustainable innovation in their business models, setting an example for others to follow. In this Sustainability training presentation, you will learn key concepts, principles, and practices of sustainability applicable across industries. This training aims to create awareness and educate employees, senior executives, consultants, and other key stakeholders, including investors, policymakers, and supply chain partners, on the importance and implementation of sustainability.
LEARNING OBJECTIVES
1. Develop a comprehensive understanding of the fundamental principles and concepts that form the foundation of sustainability within corporate environments.
2. Explore the sustainability implementation model, focusing on effective measures and reporting strategies to track and communicate sustainability efforts.
3. Identify and define best practices and critical success factors essential for achieving sustainability goals within organizations.
CONTENTS
1. Introduction and Key Concepts of Sustainability
2. Principles and Practices of Sustainability
3. Measures and Reporting in Sustainability
4. Sustainability Implementation & Best Practices
To download the complete presentation, visit: https://www.oeconsulting.com.sg/training-presentations
Attending a job Interview for B1 and B2 Englsih learnersErika906060
It is a sample of an interview for a business english class for pre-intermediate and intermediate english students with emphasis on the speking ability.
Cracking the Workplace Discipline Code Main.pptxWorkforce Group
Cultivating and maintaining discipline within teams is a critical differentiator for successful organisations.
Forward-thinking leaders and business managers understand the impact that discipline has on organisational success. A disciplined workforce operates with clarity, focus, and a shared understanding of expectations, ultimately driving better results, optimising productivity, and facilitating seamless collaboration.
Although discipline is not a one-size-fits-all approach, it can help create a work environment that encourages personal growth and accountability rather than solely relying on punitive measures.
In this deck, you will learn the significance of workplace discipline for organisational success. You’ll also learn
• Four (4) workplace discipline methods you should consider
• The best and most practical approach to implementing workplace discipline.
• Three (3) key tips to maintain a disciplined workplace.
Comparison of Solar-Wind Hybrid Policies-07.02.2019
1. S.No Clause National Gujarat Andhra Pradesh (A.P.)
1 Agency National Wind-Solar Hybrid Policy
Gujarat Wind-Solar Hybrid Power
Policy-2017 by Gujarat Energy
Developer Agency (GEDA)
Andhra Pradesh Wind-Solar Hybrid
Power Policy -2018 by New &
Renewable Energy Development
Corporation of
Andhra Pradesh Ltd. (NREDCAP)
2 Region(s) - Saurashtra, Kutch & North Gujarat Rayalaseema Belt
3 Operative Period
Remain in force till withdrawn,
modified or outmoded by the
Government.
Effective from the date of issuance till
period of 5 years
Effective for a period of five (5) years
from the date of issuance and/ or shall
remain in force till such time policy is
withdrawn, modified or superseded by
the Government.
4
Eligibility for Incentives
or Benefits
-
The Project(s) developed during
Operative Period of this Policy for 25
years from the date of
commissioning.
The Project(s) developed during
Operative Period of this Policy for 10
years from the date of
commissioning.
5 Project Sizing
The small size of the solar PVs
capacity can be added as the solar-
hybrid component where the wind
power density is quite good.
The small size of the solar PVs capacity
can be added as the solar-hybrid
component where the wind power
density is quite good.
The small size of the solar PVs capacity
can be added as the solar-hybrid
component where the wind power
density is quite good.
Gensol Engineering Pvt. Ltd
Policy Review: Solar-Wind Hybrid
2. 6
Rated Capacity of Wind
or Solar Projects
The rated capacity of one resource
should be at least 25% of the rated
power capacity of other resource.
Consumers may set up Hybrid Project
to extent of meeting RPO without limit
of Contracted Demand/Sanctioned
Load.
For captive and third party models,
the power contracted from the hybrid
project shall be 50% of the sanctioned
load of consumer for each solar and
wind respectively.
The rated capacity of one resource
should be at least 25% of the rated
power capacity of other resource.
7 Evacuation Voltage - -
Both Wind and Solar project(s) should
connect to grid in the same region at
132 KV and above either through
individual or common pooling station.
8
AC Integration
DC Integration
The AC output of the both the wind
and solar systems is integrated
either at LT side or at HT side.
In case HT integration, both system
uses separate step-up transformer
and HT output of the system is
connected to common AC Bus-bar.
The DC output of the is connected to
a common DC bus and a common
invertors suitable for combined
output AC capacity is used to convert
this DC power in to AC power.
Only AC integration will be permitted.
The AC output of the both the wind and
solar systems will be integrated at the
pooling/ sending-end sub-station.
n the absence of a common RPO :
Only AC integration will be allowed.
Separate electrical lines and meters
need to be laid for both until the
pooling or sending-end substation of
the hybrid project
In the presence of a common RPO :
AC or DC integration will be allowed.
Common electrical lines may be used
up to the pooling substation of the
hybrid project.
The AC output of the both the wind and
solar systems is integrated either at LT
side or at HT side.
In case HT integration, both system
uses separate step-up transformer and
HT output of the system is connected
to common AC Bus-bar.
The DC output of the both the wind
and solar PV plant is connected to a
common DC bus and a common
invertors suitable for combined output
AC capacity is used to convert this DC
power in to AC power.
3. 9
Rated Capacity of
Wind or Solar Projects
The rated capacity of one resource
should be at least 25% of the rated
power capacity of other resource.
Consumers may set to extent of
meeting RPO without limit of
Contracted Demand/Sanctioned Load.
The power contracted from the
project shall be 50% of the sanctioned
load of consumer for each solar and
wind respectively for captive and third
party models.
The rated capacity of one resource
should be at least 25% of the rated
power capacity of other resource.
10
Performance
Obligation
- -
Each 1 MW of contracted project
should achieve a minimum CUF of
40%.
11
Transmission Line
Laying Cost
Developers shall undertake
addition/augmentation in the
system up to the receiving end sub-
station at their own cost.
Developers shall undertake
addition/augmentation in the system
up to the receiving end sub-station at
their own cost.
Developers shall undertake
addition/augmentation in the system
up to the receiving end sub-station at
their own cost.
12
Metering
AC Integration
DC Integration
By apportioning the reading of main
meter installed at the receiving
station on the basis of readings of
ABT meters installed on LT or HT side
of the wind and solar PV plant as the
case may be.
By apportioning the reading of main
meter installed at the receiving
station on the basis of readings of DC
meters installed at the DC output of
the wind and solar PV plant.
At Pooling Sub-Station:
In 15-minute time block by installing
ABT compliant meters separately by
the Project Developers.
At receiving end Sub-Station:
On the basis of meter reading of
common meter installed at receiving
end sub-station appropriately
apportioned as per the respective
meter reading of wind and solar
meters.
By apportioning the reading of main
meter installed at the receiving station
on the basis of readings of ABT meters
installed on LT or HT side of the wind
and solar PV plant as the case may be.
By apportioning the reading of main
meter installed at the receiving station
on the basis of readings of DC meters
installed at the DC output of the wind
and solar PV plant.
13 Wheeling of Power
(a) captive purpose (b) sale to third
party through open access (c) sale to
the distribution company (ies) either
Captive use or third-party sale or sale
of power to the DISCOMs.
(a) captive purpose (b) sale to third
party through open access (c) sale to
the distribution company (ies) either at
4. at tariff determined by the
respective SERC or at tariff
discovered through transparent
bidding process and (d) sale to the
distribution company (ies) at APPC.
project specific tariff determined by
the APERC or at tariff discovered
through transparent bidding process
(d) sale to the distribution company
(ies) at APPC under REC mechanism
and avail RECs.
14 Reactive power -
The drawl of reactive power will be
charged as per the GERC Orders
-
15 Transmission Charges
No additional connectivity capacity
charges will be levied for
hybridisation at existing wind/solar
PV plants if already granted
transmission connectivity/ access is
being used.
Transmission charges may be
applicable for the additional
transmission capacity/ access
granted as per prevailing regulation.
Existing Projects :
Where open access is already granted
to the extent of rated capacity of
transmission line/ sub-station of
GETCO and injection of power from
additional wind/ solar capacity to be
set up is restricted up to rated capacity,
transmission charges are not
applicable on such additional capacity.
In the cases where there is capacity
margin in the existing transmission
system/ sub-station of GETCO after
taking into account open access already
granted to the existing wind/solar
project of transmission capacity for
allowing additional capacity, the
transmission charges shall be
applicable on such additional
sanctioned/allocated
New Projects :
Transmission charges shall be
applicable on the basis of sanctioned/
allocated transmission capacity.
Transmission and Distribution charges
shall be exempted upto 50% of the
applicable charges for wheeling of
power generated from new Wind –
Solar Hybrid Power Projects within the
State.
No additional connectivity capacity
charges will be levied for hybridisation
at existing wind/solar PV plants if
already granted transmission
connectivity/ access is being used.
Transmission charges may be
applicable for the additional
transmission capacity/ access granted
as per prevailing regulation.
5. 16 Tariff -
Existing Projects:
The purchase of power from existing
wind/solar capacity shall be in
accordance with the respective PPAs
with GUVNL.
The sale and purchase of power
from additional/ new wind/solar
capacity shall be at the tariff
discovered through competitive
bidding (reverse bidding whenever
required) undertaken by DISCOMs
separately for wind and solar power
purchase.
New Projects:
The purchase of wind/solar power
shall be at the tariff discovered
through competitive bidding (reverse
bidding whenever required)
undertaken by DISCOMs separately
for wind and solar power purchase
until a common tariff mechanism
and RPO for the hybrid project is
evolved.
-
6. 17 Wheeling Charges -
For Captive Use:
In case of injection at 66 KV and drawl
at 11 KV voltage level, 50% of
wheeling charges and 50% of
distribution losses of the energy fed to
the grid at the receiving end sub-
station of GETCO, as applicable to
normal Open Access Consumers.
For Third-Party Sale:
Wheeling charges and losses of energy
fed to the grid as measured at
receiving-end sub-station of GETCO will
be applicable
Hybrid Projects availing open access
for captive use/ third-party sale under
REC mechanism
Such projects will be allowed to wheel
the electricity on payment of
applicable transmission charges/
losses, wheeling charges/ losses and
other charges as applicable to other
normal Open Access Consumers.
-
18
Cross Subsidy
Surcharge
-
For third party sale:
Concession of 50% of cross subsidy
and additional Surcharge will be given.
For projects under REC mechanism:
Cross Subsidy and Additional
Surcharge will be applicable.
50% of the Cross subsidy surcharge will
be paid for third party sale provided
the source of power is from projects
setup within the State.
19 Electricity Duty -
Electricity generated and consumed
for self-consumption/ sale to third-
party within the State shall be
exempted from payment of electricity
duty in accordance with the provisions
50% of applicable Electricity duty shall
be exempted for captive consumption,
sale to DISCOMs and third party sale
provided the source of power is from
projects set up within the State.
7. of the Gujarat Electricity Duty Act,
1958
20 Demand Cut -
Exemption from demand cut to the
extent of 50% of installed capacity of in
case of captive consumption and third-
party sale within the State.
-
21 Supervision Charges - -
Exempted from paying the Supervision
charges to APTransco/Discom(s) only
in case of transmission of power from
State Transmission Utility (STU) to
Central transmission utility (CTU)
22
Deemed Public Private
Partnership (PPP)
- -
Deemed PPP status will be provided for
solar-wind hybrid project.
23
Deemed Non-
Agricultural (NA) status
-
Hybrid parks will be developed on the
same lines as solar parks
Deemed Non-Agricultural (NA) status
for the land where wind-solar hybrid
power projects will be accorded, on
payment of applicable statutory fees.
24 Pollution Clearance - -
Hybrid power projects will be
exempted from obtaining any
NOC/Consent for establishment under
pollution control laws from AP
Pollution Control Board.
25 MUST RUN STATUS - -
All Wind- Solar hybrid power projects
will be treated as “MUST RUN” power
plants and will not be subjected to
‘Merit Order Despatch (MOD)
principles’
26
Round The Clock
Power
- -
For Round The Clock (RTC) power by
Wind-Solar Hybrid projects, at least
51% of the energy requirement should
be from the Renewable Energy
projects (Solar/Wind).
8. 27
Energy Banking
/Energy Accounting
-
If the Consumer does not claim the
renewable attribute of wind/solar for
meeting its Solar/Non-Solar RPO,
energy injection worked out at the
receiving end sub-station of GETCO will
be set-off against the consumption
during the Consumer's billing cycle.
If the consumer claims the renewable
attributes of solar/wind for meeting its
solar/non-solar RPO, then energy
accounting will be based on 15-
minute time block-basis.
In both the cases, surplus power, after
giving set off, will be purchased by
DISCOM at Average Pooled Power
Purchase Cost (APPC) of the year of
commissioning of the project.
Surplus power, after giving set off, will
be purchased by the DISCOM at 85%
of Average Pooled Power Purchase
Cost (APPC) of the year of
commissioning of the project.
Banking of 100% of energy will be
permitted during all 12 months of the
year, based on the feasibility and prior
approval of APTRANSCO/APDISCOMs.
Banking charges will be adjusted in
kind at 5% of the energy delivered at
the point of drawl.
The unutilized banked energy shall be
considered as deemed purchase by
Discoms at 75% of the Average Pooled
Power Purchase Cost as determined by
the APERC for the applicable year.
28
Renewable Power
Purchase Obligation
(RPO)
Fulfilment of solar RPO and non-
solar RPO in the proportion of rated
capacity of solar and wind power in
the hybrid plant respectively.
Fulfilment of RPO by purchasing
wind/solar power at the tariff
determined by GERC or tariff
discovered through competitive
bidding process.
Fulfilment of solar RPO and non-solar
RPO in the proportion of rated capacity
of solar and wind power in the hybrid
plant respectively.
9. 29 Forecasting Schedule -
Forecast will be scheduled for day-to-
day operations, which will be
governed by regulations as passed and
amended by GERC.
Project(s) must give the common
scheduling and forecasting for the
Wind and Solar Project(s) and further
at any point of time should not exceed
the project capacity.
30 Restrictions -
Second hand WTGs/ solar modules or
other equipment shall not be eligible
for installation
-
31
Clean Development
Mechanism
(CDM)Benefit
-
The Clean Development Mechanism
(CDM) benefits will be shared on net
proceeds, starting from 100% to
Developer in the first year after
commissioning, and thereafter
reducing by 10% every year till the
sharing becomes equal (50:50)
between the Developer and the Power
Procurer, in the sixth year.
-
32 Security Deposit
Bank guarantee equivalent to
Rs.2.00 lakhs/ MW in favour of
NREDCAP.
Developer shall be required to provide
Bank Guarantee @ Rs. 3 lacs per MW
to GETCO based on allotment of
transmission capacity
-
33 Liability Charges -
Developer shall commission new
Hybrid capacity at least 10% of the
allotted capacity within 1 month of
charging of evacuation line, failing
which, the Developer shall be liable to
pay long term transmission charges for
10% of allotted capacity till such 10% of
allotted capacity is commissioned.
-
34 Proposal Fees - - Rs. 25,000/MW
10. 35 Allotment Fees - -
Rs.1,50,000/MW shall be paid at the
time of entering into agreement.
36
Project Completion
Timeline
- - 24 months from the date of allotment.