SlideShare a Scribd company logo
Microsoft
®
Project 2007
Training
Module 1: The Basic
Welcome
This training module was created by: Eng’r Sid Calayag
 Credentials:
• Trained in Planning and Scheduling using Primavera
• Experienced in using Harvard Project Manager and MS Project since version 3
• Trained in Project Management and Quality Management System
• Regular Trainer for Taikisha Philippines Inc.
• Certified Lead auditor for ISO 9001:2000 and ISO 9001:2008
• Practiced Project Management (local and abroad)
• Published major training materials in the internet on the following subjects:
• Guidelines for Project Kick-off Meeting
• Quality in Construction Works
• Improve Project Performance Using 5S Concept
• QA/QC Concept, Roles and Responsibilities in TPI Organization
• Quality Improvement Using Root Cause Analysis
• Practical Auditing
• Upgrade QMS System to ISO 9001:2008
• Introduction to Cleanroom Technology
2
Course Objectives
 This Microsoft Project course gives delegates an
introduction to project management and to the
concepts of planning and scheduling using Microsoft
Project 2007. Delegates on this training will learn
how to identify, organize and manage the tasks and
resources required to complete a project under the
constraints of time and cost to achieve a final project
target.
4
Course contents
• Lesson 1: Project Management
• Concept of Project Management
• Key Metrics and Success Factors
• PERT and CPM
• Lesson 2: Microsoft Project
• Planning the Project
• Task Entry and Linking
• Updating the Project
• Working with your views
• Printing and Reporting
5
 Project Management
• Commonly used terms
• Concept of Project Management
• Key metrics to Project Management
• Key Success Factors
• The Critical Path / PERT Chart
Lesson 1
Commonly used terms
 Activity – a specific project task that requires resources
and time to complete
 Baseline – the original approved plan
 Crash - in CPM, an activity can be conducted at a normal
pace or at an expedited pace at a greater cost
 Critical - an activity or event that if delayed will delay
project completion
 Critical path – the series of activities that determines the
duration of a project. It is the longest path through the
project.
7
Commonly used terms
 Deliverables- any measurable, tangible, verifiable
outcome, result, or item that must be produced to
complete a project
 Fast tracking – a method of shortening the critical path by
carrying out activities in parallel
 Gantt chart – a manner of illustrating multiple time-based
activities on a horizontal time scale
 PERT – Program Evaluation and Review Technique chart
depict task, duration, and dependency information in a
network form.
8
Initiation
Planning
Execution
Closure
Concept of Project Management
Management
• Project termination
• Team Development
• Organization Commitment
• Scope Definition
• Activity Definition
• Schedule Development/Cost
Estimating/Resource Planning
Execution
and Control
Process
• Information Distribution
• Update Project
• Performance Reporting
• Project Close-out
• Administrative close-out
• Project completion
Planning
Process
Closure
Process
Initiation
Process
9
Unique, one-time operations designed to
accomplish a specific set of objectives in a limited
time frame.
Build A
A Done
Build B
B Done
Build C
C Done
Build D
Ship
JAN FEB MAR APR MAY JUN
On time!
Projects
10
Key metrics and success factors
 The Key Metrics
• Time
• Cost
• Performance objectives
 The Key Success Factors
• Top-down commitment
• Having a capable project manager
• Having time to plan
• Careful tracking and control
• Good communications 11
Project Management
 What are the tools?
• Work breakdown structure
• Network diagram
• Gantt charts
12
Project X
Level 1
Level 2
Level 3
Level 4
MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Locate new
facilities
Interview staff
Hire and train staff
Select and order
furniture
Remodel and
install phones
Move in/startup
Gantt Chart
Project Manager
Responsible for: Work Quality
Human Resources Time
Communications Costs
13
Review Lesson 1-a
What are the key metrics?
• ____
• ____
• Performance ___________
What are the Key Success Factors?
• Top-down __________
• Having a _______ project _______
• Having ____ to plan
• Careful tracking and _______
• Good ______________.
What are the key metrics?
• Time
• ____
• Performance ___________
What are the Key Success Factors?
• Top-down __________
• Having a _______ project _______
• Having ____ to plan
• Careful tracking and _______
• Good ______________.
What are the key metrics?
• Time
• Cost
• Performance ___________
What are the Key Success Factors?
• Top-down __________
• Having a _______ project _______
• Having ____ to plan
• Careful tracking and _______
• Good ______________.
What are the key metrics?
• Time
• Cost
• Performance objectives
What are the Key Success Factors?
• Top-down __________
• Having a _______ project _______
• Having ____ to plan
• Careful tracking and _______
• Good ______________.
What are the key metrics?
• Time
• Cost
• Performance objectives
What are the Key Success Factors?
• Top-down commitment
• Having a ______ project _______
• Having ____ to plan
• Careful tracking and _______
• Good ______________.
What are the key metrics?
• Time
• Cost
• Performance objectives
What are the Key Success Factors?
• Top-down commitment
• Having a capable project manager
• Having ____ to plan
• Careful tracking and _______
• Good ______________.
What are the key metrics?
• Time
• Cost
• Performance objectives
What are the Key Success Factors?
• Top-down commitment
• Having a capable project manager
• Having time to plan
• Careful tracking and _______
• Good ______________.
What are the key metrics?
• Time
• Cost
• Performance objectives
What are the Key Success Factors?
• Top-down commitment
• Having a capable project manager
• Having time to plan
• Careful tracking and control
• Good ______________.
What are the key metrics?
• Time
• Cost
• Performance objectives
What are the Key Success Factors?
• Top-down commitment
• Having a capable project manager
• Having time to plan
• Careful tracking and control
• Good communications 14

Critical Path /“Pert” Charts
PERT: Program Evaluation and
Review Technique
CPM: Critical Path Method
• Graphically displays project activities
• Estimates how long the project will take
• Indicates most critical activities
• Show where delays will not affect project
PERT and CPM
The Network Diagram
• Network (precedence) diagram
• Activity-on-arrow (AOA)
• Activity-on-node (AON)
• Activities
• Events
The Network Diagram (cont’d)
 Path
• Sequence of activities that leads from the starting
node to the finishing node
 Critical path
• The longest path; determines expected project
duration
 Critical activities
• Activities on the critical path
 Slack
• Allowable slippage for path; the difference between
the length of path and the length of critical path
Project Network – Activity on Arrow
1
2
3
4
5 6
Locate
facilities
Order
furniture
Furniture
setup
Interview
Hire and
train
Remodel
Move
in
AOA
Project Network – Activity on Node
1
2
3
5
6
Locate
facilities
Order
furniture
Furniture
setup
Interview
Remodel
Move
in
4
Hire and
train
7S
AON
AOA vs. AON
1
2
3
5
6
Locate
facilities
Order
furniture
Furniture
setup
Interview
Remodel
Move
in
4
Hire and
train
7S
AON
1
2
3
4
5 6
Locate
facilities
Order
furniture
Furniture
setup
Interview
Hire and
train
Remodel
Move
in
AOA
Network Conventions
a
b
c a
b
c
a
b
c
d
a
b
c
Dummy
activity
Time Estimates
 Deterministic
• Time estimates that are fairly certain
 Probabilistic
• Estimates of times that allow for variation
Probabilistic Estimates
Activity
start
Optimistic
time
Most likely
time (mode)
Pessimistic
time
to tptm te
Expected Time
te = to + 4tm +tp
6
te = expected time
to = optimistic time
tm = most likely time
tp = pessimistic time
Example 1
3-4-5
d
3-5-7
e
5-7-9
f
2-4-6
b
4-6-8
h
Optimistic
time
Most likely
time
Pessimistic
time
Review Lesson 1 - b
1
2
3
4
5 6
8 weeks
6 weeks
3 weeks
4 weeks
9 weeks
11 weeks
1 week
Move in
Deterministic
time estimates
PATH LENGTH SLACK
1-2-3-4-5-6
1-2-5-6
1-3-5-6
29
PATH LENGTH SLACK
1-2-3-4-5-6
1-2-5-6
1-3-5-6
Solution to Review Lesson 1 - b
PATH LENGTH SLACK
1-2-3-4-5-6 18 2
1-2-5-6
1-3-5-6
PATH LENGTH SLACK
1-2-3-4-5-6 18 2
1-2-5-6 20 0
1-3-5-6
PATH LENGTH SLACK
1-2-3-4-5-6 18 2
1-2-5-6 20 0
1-3-5-6 14 6
PATH LENGTH SLACK
1-2-3-4-5-6 18 2
1-2-5-6 20 0
1-3-5-6 14 6
Critical Path
Solution to Review Lesson 1 - b
PATH LENGTH SLACK
1-2-3-4-5-6 18 2
1-2-5-6 20 0
1-3-5-6 14 6
Critical Path
1
2
3
4
5 6
8 weeks
6 weeks
3 weeks
4 weeks
9 weeks
11 weeks
1 week
Move in
Deterministic
time estimates
Pert Chart
 tasks a and b can start simultaneously
 task c can start after a is complete
 task d can start after b is complete
 c and d must complete before e can begin
0
A
B
C&D E
a
b
c
d
e
The CRITICAL PATH is the longest continuous path of activities through a project that
determines the project end date. 33
Review Lesson 1 - c:
Draw a Pert Chart for this job
Task Title Duration Precedence
a. start 0 -
b. think 1 a
c. plan 2 b
d. procrastinate 5 a
e. assign to someone else 1 c,d
f. hide 3 e
g. finish 1 e
h. grab credit 1 f,g
34
A B C&D E F F&G
D
a b
d
c e f
G
g
0
1 2
5
1 3
1
Critical Path = A D E F H slack in B C, G
H
1
C
Task Title Duration Precedence
a. start 0 -
b. think 1 a
c. plan 2 b
d. procrastinate 5 a
e. assign to someone else 1 c,d
f. hide 3 e
g. finish 1 e
h. grab credit 1 f,g
35
Solution to Review Lesson 1 - c
Lesson 2: Microsoft Project
• Starting Microsoft Project
• The Screen
• The Default View
• Views and Tables
• Menus
• The Tool Bar
Starting Microsoft
Project
1. Run MS Project by opening it in
“All Programs”
• Select MS Project (usually in
the same group where other
MS Office applications are
located.
37
1. Default View
The Screen
3. You may add or delete some
of the Toolbar in the Screen
from this menu.
2. Change the Default
View :
• Choose View,
Toolbar, Project
Guide .
38
Planning the Project
• Where to Begin
• Defining the Project
• Setting the project start date
• Complete the Project Plan
• The base calendar
• Save the New Project File
Planning the project
 Where to Begin
1. Start MS Project
2. Choose the Define
Project in the Task
Wizard
3. Follow succeeding
instructions
40
Planning the Project
 Define the project
1. Choose “Define general
working time” in the
Wizard
2. Choose standard time
for a regular 8 hour
work day
3. Customize it to suit
your needs.
4. Follow succeeding
instruction
41
Task Entry and Linking
• Creating Milestone,
• Task Relationships
• Linking Tasks
• Editing the Task Information
• Formatting the Gantt Chart
• Highlighting the critical path
Create Milestone, Link and Relationship
 When you enter a task or import
a number of tasks, they have a
duration of one day as a default
To create milestone, select the task/s
considered as milestone and then
right click. Select Task Information.
Put a check mark on Milestone.
To create subtask, select the task
considered and then select
Project/Outline/Indent in the Menu
Link the selected tasks by selecting
Edit/Link task in the Menu.
NOTE:
All task are automatically link by
Finish (a task) to Start (another task).
43
Edit the Duration, Start or End Date as
needed.
Editing Task Information
 You can view
information regarding
a task by selecting the
task and then right
click.
44
A Task Information will
appear showing several
tabs where you can add,
delete, or edit
information regarding
Resources, Predecessors,
etc.
Formatting the Gantt Chart
 Select Format/Gantt
Chart Wizard in the
Menu
45
You can format the Gantt
Chart view by using the
Gantt chart Wizard
Follow the instruction in
the Wizard
Highlighting the critical path
 Select Format/Gantt
Chart Wizard in the
Menu
46
You can also highlight
the critical path in the
Gantt Chart view by
using the Wizard
Follow the instruction in
the Wizard
Updating the Project
• Setting the baseline
• Update the project
• Tracking Progress
Setting the Baseline
1. Select Tools/Tracking the
Menu Bar
2. A dialog box appears
where you are given a
choice to “Set a
Baseline” for the whole
project or for the
selected task only.
48
Update the project
1. Select Tools/Tracking the
Menu Bar
2. A dialog box appears where
you are given several
choices to update the
project.
49
Update each task in a project
1. Highlight a column where you
want to insert another
column.
2. Select Insert | Column in the
Menu bar, or
3. Right click and then select
“Insert column”.
4. In the “Column definition”
dialog box , choose
“%Complete”. Then select
“OK”.
5. Update each task in the new
column.
50
Tracking Progress
1. Select Tools | Tracking |
Progress Line in the Menu
bar
2. In the “Progress Line” dialog
box , choose “always display
current progress line” and “At
current date”. Then select
“OK”.
3. A red vertical line will appear
showing the status of the
project.
51
Sample of a project with tracking
52
Network Diagram
• View the Network Diagram
• Elements of the Network Diagram
The Network diagram
1. Select View | Network
diagram in the Menu bar,
2. The Network Diagram
appear immediately as
shown.
3. Close-up view of the
Network diagram
54
55
Elements of the Network diagram
56
Printing and Reporting
• Page Setup
• Reports Setup
Page Set-up
1. Select File| Page Set-up in
the Menu bar,
2. The “Page Set-up” dialog
box will appear showing
paper sizes and other
choices.
3. Customize the printed
output by inserting
additional info in the
“Header “and “Footer”
57
Action Reflection
“Failure to plan is planning to fail”
END OF TRAINING
FOR MODULE 1
60

More Related Content

What's hot

Pmp quality chapter 8
Pmp quality chapter 8Pmp quality chapter 8
Pmp quality chapter 8
Ahmed Elshaboury,PMP,LEED GA
 
009. project communication management
009. project communication management009. project communication management
009. project communication management
Boobalan G
 
Hoshin Training - Vision
Hoshin Training - VisionHoshin Training - Vision
Hoshin Training - Vision
Harold Philbrick
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6
Agus Suhanto
 
AXELOS - P3O® - Portfolio, Programme and Project Offices - Foundation
AXELOS - P3O® - Portfolio, Programme and Project Offices - FoundationAXELOS - P3O® - Portfolio, Programme and Project Offices - Foundation
AXELOS - P3O® - Portfolio, Programme and Project Offices - Foundation
Mirosław Dąbrowski C-level IT manager, CEO, Agile, ICF Coach, Speaker
 
A3 thinking - background, process and examples
A3 thinking - background, process and examplesA3 thinking - background, process and examples
A3 thinking - background, process and examples
Michael Mahlberg
 
PMP_Project Time Management
PMP_Project Time ManagementPMP_Project Time Management
PMP_Project Time Management
Hisham Haridy MBA, PMP®, RMP®, SP®
 
P3O - The Value Adding PMO - from Strategy to Projects
P3O - The Value Adding PMO - from Strategy to ProjectsP3O - The Value Adding PMO - from Strategy to Projects
P3O - The Value Adding PMO - from Strategy to Projects
Tony Vynckier
 
PMP as per PMBOK 6
PMP as per PMBOK 6PMP as per PMBOK 6
PMP as per PMBOK 6
Amit Gupta
 
PMO (Project Management Office)
PMO (Project Management Office)PMO (Project Management Office)
PMO (Project Management Office)
Dilawar Abbas
 
Project management and Success Criteria
Project management and Success Criteria Project management and Success Criteria
Project management and Success Criteria
ujjwal Mania
 
How to prioritize requirements - better and faster (workshop), Razvan Radulian
How to prioritize requirements -  better and faster (workshop), Razvan RadulianHow to prioritize requirements -  better and faster (workshop), Razvan Radulian
How to prioritize requirements - better and faster (workshop), Razvan Radulian
Why-What-How Consulting, LLC
 
Project Management
Project ManagementProject Management
Project Management
David Edgerton, Jr.
 
Meeting management
Meeting managementMeeting management
Meeting management
Kevin Thomas
 
Key Concepts for Project Mgmt
Key Concepts for Project MgmtKey Concepts for Project Mgmt
Key Concepts for Project Mgmt
Jaiveer Singh
 
Training material on proposal writing & resource mobilization for focus pak...
Training material  on proposal  writing & resource mobilization for focus pak...Training material  on proposal  writing & resource mobilization for focus pak...
Training material on proposal writing & resource mobilization for focus pak...
Fida Karim 🇵🇰
 
Cómo transformar una PMO en una Oficina de Valor
Cómo transformar una PMO en una Oficina de ValorCómo transformar una PMO en una Oficina de Valor
Cómo transformar una PMO en una Oficina de Valor
PMOfficers PMOAcademy
 
Organizational Influences and Project Life Cycle,PMP Chapter 2,PMBOK,PMP Exam...
Organizational Influences and Project Life Cycle,PMP Chapter 2,PMBOK,PMP Exam...Organizational Influences and Project Life Cycle,PMP Chapter 2,PMBOK,PMP Exam...
Organizational Influences and Project Life Cycle,PMP Chapter 2,PMBOK,PMP Exam...
JustAcademy
 
Pmp communication chapter 10
Pmp communication chapter 10Pmp communication chapter 10
Pmp communication chapter 10
Ahmed Elshaboury,PMP,LEED GA
 
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
Anand Bobade
 

What's hot (20)

Pmp quality chapter 8
Pmp quality chapter 8Pmp quality chapter 8
Pmp quality chapter 8
 
009. project communication management
009. project communication management009. project communication management
009. project communication management
 
Hoshin Training - Vision
Hoshin Training - VisionHoshin Training - Vision
Hoshin Training - Vision
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6
 
AXELOS - P3O® - Portfolio, Programme and Project Offices - Foundation
AXELOS - P3O® - Portfolio, Programme and Project Offices - FoundationAXELOS - P3O® - Portfolio, Programme and Project Offices - Foundation
AXELOS - P3O® - Portfolio, Programme and Project Offices - Foundation
 
A3 thinking - background, process and examples
A3 thinking - background, process and examplesA3 thinking - background, process and examples
A3 thinking - background, process and examples
 
PMP_Project Time Management
PMP_Project Time ManagementPMP_Project Time Management
PMP_Project Time Management
 
P3O - The Value Adding PMO - from Strategy to Projects
P3O - The Value Adding PMO - from Strategy to ProjectsP3O - The Value Adding PMO - from Strategy to Projects
P3O - The Value Adding PMO - from Strategy to Projects
 
PMP as per PMBOK 6
PMP as per PMBOK 6PMP as per PMBOK 6
PMP as per PMBOK 6
 
PMO (Project Management Office)
PMO (Project Management Office)PMO (Project Management Office)
PMO (Project Management Office)
 
Project management and Success Criteria
Project management and Success Criteria Project management and Success Criteria
Project management and Success Criteria
 
How to prioritize requirements - better and faster (workshop), Razvan Radulian
How to prioritize requirements -  better and faster (workshop), Razvan RadulianHow to prioritize requirements -  better and faster (workshop), Razvan Radulian
How to prioritize requirements - better and faster (workshop), Razvan Radulian
 
Project Management
Project ManagementProject Management
Project Management
 
Meeting management
Meeting managementMeeting management
Meeting management
 
Key Concepts for Project Mgmt
Key Concepts for Project MgmtKey Concepts for Project Mgmt
Key Concepts for Project Mgmt
 
Training material on proposal writing & resource mobilization for focus pak...
Training material  on proposal  writing & resource mobilization for focus pak...Training material  on proposal  writing & resource mobilization for focus pak...
Training material on proposal writing & resource mobilization for focus pak...
 
Cómo transformar una PMO en una Oficina de Valor
Cómo transformar una PMO en una Oficina de ValorCómo transformar una PMO en una Oficina de Valor
Cómo transformar una PMO en una Oficina de Valor
 
Organizational Influences and Project Life Cycle,PMP Chapter 2,PMBOK,PMP Exam...
Organizational Influences and Project Life Cycle,PMP Chapter 2,PMBOK,PMP Exam...Organizational Influences and Project Life Cycle,PMP Chapter 2,PMBOK,PMP Exam...
Organizational Influences and Project Life Cycle,PMP Chapter 2,PMBOK,PMP Exam...
 
Pmp communication chapter 10
Pmp communication chapter 10Pmp communication chapter 10
Pmp communication chapter 10
 
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
 

Viewers also liked

Microsoft office project 2007
Microsoft office project 2007Microsoft office project 2007
Microsoft office project 2007
Sapperg
 
Microsoft Project 2007 Template project
Microsoft Project 2007 Template projectMicrosoft Project 2007 Template project
Microsoft Project 2007 Template project
epidemicaa
 
microsoft project
microsoft projectmicrosoft project
microsoft project
Annisa Khoerunnisya
 
Microsoft project 2007 tutorial
Microsoft project 2007   tutorialMicrosoft project 2007   tutorial
Microsoft project 2007 tutorial
Muhammad Umari
 
Ms project lectures
Ms project lecturesMs project lectures
Ms project lectures
jillmitchell8778
 
Ms project 2007
Ms project 2007Ms project 2007
Ms project 2007
Elkjaer Braz
 
Enterprise Resource Management Using MS Project Server 2007
Enterprise Resource Management Using MS Project Server 2007Enterprise Resource Management Using MS Project Server 2007
Enterprise Resource Management Using MS Project Server 2007
Productivity Intelligence Institute
 
Project maturity level with ms project server 2007
Project maturity level with ms project server 2007Project maturity level with ms project server 2007
Project maturity level with ms project server 2007
Faisal Masood
 
Lookout @ Microsoft 2007
Lookout @ Microsoft 2007Lookout @ Microsoft 2007
Lookout @ Microsoft 2007
Lim Ming Xuan
 
Microsoft Project 2003 Configuration Training Level 2 Itvamp 2007
Microsoft Project 2003 Configuration Training Level 2 Itvamp 2007Microsoft Project 2003 Configuration Training Level 2 Itvamp 2007
Microsoft Project 2003 Configuration Training Level 2 Itvamp 2007
ITVAMP, LLC
 
Ms word excel power point
Ms word excel power pointMs word excel power point
Ms word excel power point
Manu Kaushik
 
Ms project
Ms projectMs project
Ms project
hendra262
 
Microsoft project 2003
Microsoft project 2003Microsoft project 2003
Microsoft project 2003
pparakh
 
How to schedule_a_project_in_ms_project_2003
How to schedule_a_project_in_ms_project_2003How to schedule_a_project_in_ms_project_2003
How to schedule_a_project_in_ms_project_2003
bebocole
 
Power point 2016 module 1 ppt presentation
Power point 2016 module 1 ppt presentationPower point 2016 module 1 ppt presentation
Power point 2016 module 1 ppt presentation
dgdotson
 
Microsoft® Office 2007 Tutorial
Microsoft® Office 2007 TutorialMicrosoft® Office 2007 Tutorial
Microsoft® Office 2007 Tutorial
Susan Mortensen
 
Using Microsoft Project 2003
Using Microsoft Project 2003Using Microsoft Project 2003
Using Microsoft Project 2003
pparakh
 
Advanced Excel &Basic Excel Training
Advanced Excel &Basic Excel TrainingAdvanced Excel &Basic Excel Training
Advanced Excel &Basic Excel Training
aarkex
 
Microsoft Office Project 2007 Tutorial
Microsoft Office Project 2007 TutorialMicrosoft Office Project 2007 Tutorial
Microsoft Office Project 2007 Tutorial
Anil Purushothaman
 

Viewers also liked (20)

Microsoft office project 2007
Microsoft office project 2007Microsoft office project 2007
Microsoft office project 2007
 
Microsoft Project 2007 Template project
Microsoft Project 2007 Template projectMicrosoft Project 2007 Template project
Microsoft Project 2007 Template project
 
microsoft project
microsoft projectmicrosoft project
microsoft project
 
Training microsoft project
Training microsoft projectTraining microsoft project
Training microsoft project
 
Microsoft project 2007 tutorial
Microsoft project 2007   tutorialMicrosoft project 2007   tutorial
Microsoft project 2007 tutorial
 
Ms project lectures
Ms project lecturesMs project lectures
Ms project lectures
 
Ms project 2007
Ms project 2007Ms project 2007
Ms project 2007
 
Enterprise Resource Management Using MS Project Server 2007
Enterprise Resource Management Using MS Project Server 2007Enterprise Resource Management Using MS Project Server 2007
Enterprise Resource Management Using MS Project Server 2007
 
Project maturity level with ms project server 2007
Project maturity level with ms project server 2007Project maturity level with ms project server 2007
Project maturity level with ms project server 2007
 
Lookout @ Microsoft 2007
Lookout @ Microsoft 2007Lookout @ Microsoft 2007
Lookout @ Microsoft 2007
 
Microsoft Project 2003 Configuration Training Level 2 Itvamp 2007
Microsoft Project 2003 Configuration Training Level 2 Itvamp 2007Microsoft Project 2003 Configuration Training Level 2 Itvamp 2007
Microsoft Project 2003 Configuration Training Level 2 Itvamp 2007
 
Ms word excel power point
Ms word excel power pointMs word excel power point
Ms word excel power point
 
Ms project
Ms projectMs project
Ms project
 
Microsoft project 2003
Microsoft project 2003Microsoft project 2003
Microsoft project 2003
 
How to schedule_a_project_in_ms_project_2003
How to schedule_a_project_in_ms_project_2003How to schedule_a_project_in_ms_project_2003
How to schedule_a_project_in_ms_project_2003
 
Power point 2016 module 1 ppt presentation
Power point 2016 module 1 ppt presentationPower point 2016 module 1 ppt presentation
Power point 2016 module 1 ppt presentation
 
Microsoft® Office 2007 Tutorial
Microsoft® Office 2007 TutorialMicrosoft® Office 2007 Tutorial
Microsoft® Office 2007 Tutorial
 
Using Microsoft Project 2003
Using Microsoft Project 2003Using Microsoft Project 2003
Using Microsoft Project 2003
 
Advanced Excel &Basic Excel Training
Advanced Excel &Basic Excel TrainingAdvanced Excel &Basic Excel Training
Advanced Excel &Basic Excel Training
 
Microsoft Office Project 2007 Tutorial
Microsoft Office Project 2007 TutorialMicrosoft Office Project 2007 Tutorial
Microsoft Office Project 2007 Tutorial
 

Similar to Ms project training ver 01

AASP_SUMMIT2015_Project_Mgt.pptx
AASP_SUMMIT2015_Project_Mgt.pptxAASP_SUMMIT2015_Project_Mgt.pptx
AASP_SUMMIT2015_Project_Mgt.pptx
aravind Guru
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
PRIYANSHU KUMAR
 
pm--basic.pptx
pm--basic.pptxpm--basic.pptx
pm--basic.pptx
ssuserbc5970
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
Rasan Samarasinghe
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management a
Rai University
 
06 project time management
06  project time management06  project time management
06 project time management
Ala Ibrahim
 
Software project management tools
Software project management toolsSoftware project management tools
Software project management tools
Darshak Mehta
 
pmppgoav14.ppt
pmppgoav14.pptpmppgoav14.ppt
pmppgoav14.ppt
AmrikSingh922379
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheeder
Karin Rheeder
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
Carla Fair-Wright
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapter
preetidamakale
 
system analysis and design Class 3
system analysis and design Class 3system analysis and design Class 3
system analysis and design Class 3
Dr. Mazin Mohamed alkathiri
 
Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptx
MohanadRabea1
 
A Short Workshop on Project Management
A Short Workshop on Project ManagementA Short Workshop on Project Management
A Short Workshop on Project Management
Nicole Fronda
 
PME UNIT-3.pptx
PME UNIT-3.pptxPME UNIT-3.pptx
PME UNIT-3.pptx
MayankVasisthGandhi
 
Presintation on Project constraint
Presintation on Project constraint Presintation on Project constraint
Presintation on Project constraint
university(kust)
 
2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx
ProfDrAnbalaganChinn
 
programmed evaluation and review technique,
programmed evaluation and review technique,programmed evaluation and review technique,
programmed evaluation and review technique,
siddhagiri nursing institute kaneri kolhapur
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptx
HarsimratDeo1
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptx
HarsimratDeo1
 

Similar to Ms project training ver 01 (20)

AASP_SUMMIT2015_Project_Mgt.pptx
AASP_SUMMIT2015_Project_Mgt.pptxAASP_SUMMIT2015_Project_Mgt.pptx
AASP_SUMMIT2015_Project_Mgt.pptx
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
pm--basic.pptx
pm--basic.pptxpm--basic.pptx
pm--basic.pptx
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management a
 
06 project time management
06  project time management06  project time management
06 project time management
 
Software project management tools
Software project management toolsSoftware project management tools
Software project management tools
 
pmppgoav14.ppt
pmppgoav14.pptpmppgoav14.ppt
pmppgoav14.ppt
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheeder
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapter
 
system analysis and design Class 3
system analysis and design Class 3system analysis and design Class 3
system analysis and design Class 3
 
Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptx
 
A Short Workshop on Project Management
A Short Workshop on Project ManagementA Short Workshop on Project Management
A Short Workshop on Project Management
 
PME UNIT-3.pptx
PME UNIT-3.pptxPME UNIT-3.pptx
PME UNIT-3.pptx
 
Presintation on Project constraint
Presintation on Project constraint Presintation on Project constraint
Presintation on Project constraint
 
2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx
 
programmed evaluation and review technique,
programmed evaluation and review technique,programmed evaluation and review technique,
programmed evaluation and review technique,
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptx
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptx
 

More from Isidro Sid Calayag

Upgrade iso 9001 2000 to 2008 version
Upgrade  iso 9001 2000 to 2008 versionUpgrade  iso 9001 2000 to 2008 version
Upgrade iso 9001 2000 to 2008 version
Isidro Sid Calayag
 
Quality management in construction
Quality management in constructionQuality management in construction
Quality management in construction
Isidro Sid Calayag
 
Practical auditing
Practical auditingPractical auditing
Practical auditing
Isidro Sid Calayag
 
Kick off meeting presentation
Kick off meeting presentationKick off meeting presentation
Kick off meeting presentation
Isidro Sid Calayag
 
Crash course rca training rev 01
Crash course rca training rev 01Crash course rca training rev 01
Crash course rca training rev 01
Isidro Sid Calayag
 
5 s – a program to improve project.ppt [compatibility mode]
5 s – a program to improve project.ppt [compatibility mode]5 s – a program to improve project.ppt [compatibility mode]
5 s – a program to improve project.ppt [compatibility mode]
Isidro Sid Calayag
 
Upgrade iso 9001 2000 to 2008 version
Upgrade  iso 9001 2000 to 2008 versionUpgrade  iso 9001 2000 to 2008 version
Upgrade iso 9001 2000 to 2008 version
Isidro Sid Calayag
 
Ms project training ver 01
Ms project training ver 01Ms project training ver 01
Ms project training ver 01
Isidro Sid Calayag
 
5 S – A Program To Improve Project
5 S – A Program To Improve Project5 S – A Program To Improve Project
5 S – A Program To Improve Project
Isidro Sid Calayag
 
Basic Cleanroom Protocol
Basic Cleanroom ProtocolBasic Cleanroom Protocol
Basic Cleanroom Protocol
Isidro Sid Calayag
 
Practical Auditing
Practical AuditingPractical Auditing
Practical Auditing
Isidro Sid Calayag
 
Typical Quality Management System Based On Iso 9001 2008
Typical Quality Management System Based On Iso 9001 2008Typical Quality Management System Based On Iso 9001 2008
Typical Quality Management System Based On Iso 9001 2008
Isidro Sid Calayag
 
Quality Management In Construction
Quality Management In ConstructionQuality Management In Construction
Quality Management In Construction
Isidro Sid Calayag
 
Kick Off Meeting Presentation
Kick Off Meeting PresentationKick Off Meeting Presentation
Kick Off Meeting Presentation
Isidro Sid Calayag
 
Crash Course Rca Training Rev 01
Crash Course Rca Training Rev 01Crash Course Rca Training Rev 01
Crash Course Rca Training Rev 01
Isidro Sid Calayag
 
Rca Training Rev 0
Rca Training Rev 0Rca Training Rev 0
Rca Training Rev 0
Isidro Sid Calayag
 

More from Isidro Sid Calayag (16)

Upgrade iso 9001 2000 to 2008 version
Upgrade  iso 9001 2000 to 2008 versionUpgrade  iso 9001 2000 to 2008 version
Upgrade iso 9001 2000 to 2008 version
 
Quality management in construction
Quality management in constructionQuality management in construction
Quality management in construction
 
Practical auditing
Practical auditingPractical auditing
Practical auditing
 
Kick off meeting presentation
Kick off meeting presentationKick off meeting presentation
Kick off meeting presentation
 
Crash course rca training rev 01
Crash course rca training rev 01Crash course rca training rev 01
Crash course rca training rev 01
 
5 s – a program to improve project.ppt [compatibility mode]
5 s – a program to improve project.ppt [compatibility mode]5 s – a program to improve project.ppt [compatibility mode]
5 s – a program to improve project.ppt [compatibility mode]
 
Upgrade iso 9001 2000 to 2008 version
Upgrade  iso 9001 2000 to 2008 versionUpgrade  iso 9001 2000 to 2008 version
Upgrade iso 9001 2000 to 2008 version
 
Ms project training ver 01
Ms project training ver 01Ms project training ver 01
Ms project training ver 01
 
5 S – A Program To Improve Project
5 S – A Program To Improve Project5 S – A Program To Improve Project
5 S – A Program To Improve Project
 
Basic Cleanroom Protocol
Basic Cleanroom ProtocolBasic Cleanroom Protocol
Basic Cleanroom Protocol
 
Practical Auditing
Practical AuditingPractical Auditing
Practical Auditing
 
Typical Quality Management System Based On Iso 9001 2008
Typical Quality Management System Based On Iso 9001 2008Typical Quality Management System Based On Iso 9001 2008
Typical Quality Management System Based On Iso 9001 2008
 
Quality Management In Construction
Quality Management In ConstructionQuality Management In Construction
Quality Management In Construction
 
Kick Off Meeting Presentation
Kick Off Meeting PresentationKick Off Meeting Presentation
Kick Off Meeting Presentation
 
Crash Course Rca Training Rev 01
Crash Course Rca Training Rev 01Crash Course Rca Training Rev 01
Crash Course Rca Training Rev 01
 
Rca Training Rev 0
Rca Training Rev 0Rca Training Rev 0
Rca Training Rev 0
 

Recently uploaded

The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...
The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...
The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...
Stephen Cashman
 
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
my Pandit
 
The latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from NewentideThe latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from Newentide
JoeYangGreatMachiner
 
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
APCO
 
Authentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto RicoAuthentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto Rico
Corey Perlman, Social Media Speaker and Consultant
 
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
Aleksey Savkin
 
Call8328958814 satta matka Kalyan result satta guessing
Call8328958814 satta matka Kalyan result satta guessingCall8328958814 satta matka Kalyan result satta guessing
Call8328958814 satta matka Kalyan result satta guessing
➑➌➋➑➒➎➑➑➊➍
 
GKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt PresentationGKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt Presentation
GraceKohler1
 
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Neil Horowitz
 
Organizational Change Leadership Agile Tour Geneve 2024
Organizational Change Leadership Agile Tour Geneve 2024Organizational Change Leadership Agile Tour Geneve 2024
Organizational Change Leadership Agile Tour Geneve 2024
Kirill Klimov
 
Business storytelling: key ingredients to a story
Business storytelling: key ingredients to a storyBusiness storytelling: key ingredients to a story
Business storytelling: key ingredients to a story
Alexandra Fulford
 
Easily Verify Compliance and Security with Binance KYC
Easily Verify Compliance and Security with Binance KYCEasily Verify Compliance and Security with Binance KYC
Easily Verify Compliance and Security with Binance KYC
Any kyc Account
 
Best Competitive Marble Pricing in Dubai - ☎ 9928909666
Best Competitive Marble Pricing in Dubai - ☎ 9928909666Best Competitive Marble Pricing in Dubai - ☎ 9928909666
Best Competitive Marble Pricing in Dubai - ☎ 9928909666
Stone Art Hub
 
Income Tax exemption for Start up : Section 80 IAC
Income Tax  exemption for Start up : Section 80 IACIncome Tax  exemption for Start up : Section 80 IAC
Income Tax exemption for Start up : Section 80 IAC
CA Dr. Prithvi Ranjan Parhi
 
3 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 20243 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 2024
SEOSMMEARTH
 
The Genesis of BriansClub.cm Famous Dark WEb Platform
The Genesis of BriansClub.cm Famous Dark WEb PlatformThe Genesis of BriansClub.cm Famous Dark WEb Platform
The Genesis of BriansClub.cm Famous Dark WEb Platform
SabaaSudozai
 
Part 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 SlowdownPart 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 Slowdown
jeffkluth1
 
Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
Top Forex Brokers Review
 
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
taqyea
 
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
Lacey Max
 

Recently uploaded (20)

The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...
The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...
The Heart of Leadership_ How Emotional Intelligence Drives Business Success B...
 
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
 
The latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from NewentideThe latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from Newentide
 
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
 
Authentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto RicoAuthentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto Rico
 
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
 
Call8328958814 satta matka Kalyan result satta guessing
Call8328958814 satta matka Kalyan result satta guessingCall8328958814 satta matka Kalyan result satta guessing
Call8328958814 satta matka Kalyan result satta guessing
 
GKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt PresentationGKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt Presentation
 
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
 
Organizational Change Leadership Agile Tour Geneve 2024
Organizational Change Leadership Agile Tour Geneve 2024Organizational Change Leadership Agile Tour Geneve 2024
Organizational Change Leadership Agile Tour Geneve 2024
 
Business storytelling: key ingredients to a story
Business storytelling: key ingredients to a storyBusiness storytelling: key ingredients to a story
Business storytelling: key ingredients to a story
 
Easily Verify Compliance and Security with Binance KYC
Easily Verify Compliance and Security with Binance KYCEasily Verify Compliance and Security with Binance KYC
Easily Verify Compliance and Security with Binance KYC
 
Best Competitive Marble Pricing in Dubai - ☎ 9928909666
Best Competitive Marble Pricing in Dubai - ☎ 9928909666Best Competitive Marble Pricing in Dubai - ☎ 9928909666
Best Competitive Marble Pricing in Dubai - ☎ 9928909666
 
Income Tax exemption for Start up : Section 80 IAC
Income Tax  exemption for Start up : Section 80 IACIncome Tax  exemption for Start up : Section 80 IAC
Income Tax exemption for Start up : Section 80 IAC
 
3 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 20243 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 2024
 
The Genesis of BriansClub.cm Famous Dark WEb Platform
The Genesis of BriansClub.cm Famous Dark WEb PlatformThe Genesis of BriansClub.cm Famous Dark WEb Platform
The Genesis of BriansClub.cm Famous Dark WEb Platform
 
Part 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 SlowdownPart 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 Slowdown
 
Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
 
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
 
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
 

Ms project training ver 01

  • 2. Welcome This training module was created by: Eng’r Sid Calayag  Credentials: • Trained in Planning and Scheduling using Primavera • Experienced in using Harvard Project Manager and MS Project since version 3 • Trained in Project Management and Quality Management System • Regular Trainer for Taikisha Philippines Inc. • Certified Lead auditor for ISO 9001:2000 and ISO 9001:2008 • Practiced Project Management (local and abroad) • Published major training materials in the internet on the following subjects: • Guidelines for Project Kick-off Meeting • Quality in Construction Works • Improve Project Performance Using 5S Concept • QA/QC Concept, Roles and Responsibilities in TPI Organization • Quality Improvement Using Root Cause Analysis • Practical Auditing • Upgrade QMS System to ISO 9001:2008 • Introduction to Cleanroom Technology 2
  • 3. Course Objectives  This Microsoft Project course gives delegates an introduction to project management and to the concepts of planning and scheduling using Microsoft Project 2007. Delegates on this training will learn how to identify, organize and manage the tasks and resources required to complete a project under the constraints of time and cost to achieve a final project target. 4
  • 4. Course contents • Lesson 1: Project Management • Concept of Project Management • Key Metrics and Success Factors • PERT and CPM • Lesson 2: Microsoft Project • Planning the Project • Task Entry and Linking • Updating the Project • Working with your views • Printing and Reporting 5
  • 5.  Project Management • Commonly used terms • Concept of Project Management • Key metrics to Project Management • Key Success Factors • The Critical Path / PERT Chart Lesson 1
  • 6. Commonly used terms  Activity – a specific project task that requires resources and time to complete  Baseline – the original approved plan  Crash - in CPM, an activity can be conducted at a normal pace or at an expedited pace at a greater cost  Critical - an activity or event that if delayed will delay project completion  Critical path – the series of activities that determines the duration of a project. It is the longest path through the project. 7
  • 7. Commonly used terms  Deliverables- any measurable, tangible, verifiable outcome, result, or item that must be produced to complete a project  Fast tracking – a method of shortening the critical path by carrying out activities in parallel  Gantt chart – a manner of illustrating multiple time-based activities on a horizontal time scale  PERT – Program Evaluation and Review Technique chart depict task, duration, and dependency information in a network form. 8
  • 8. Initiation Planning Execution Closure Concept of Project Management Management • Project termination • Team Development • Organization Commitment • Scope Definition • Activity Definition • Schedule Development/Cost Estimating/Resource Planning Execution and Control Process • Information Distribution • Update Project • Performance Reporting • Project Close-out • Administrative close-out • Project completion Planning Process Closure Process Initiation Process 9
  • 9. Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame. Build A A Done Build B B Done Build C C Done Build D Ship JAN FEB MAR APR MAY JUN On time! Projects 10
  • 10. Key metrics and success factors  The Key Metrics • Time • Cost • Performance objectives  The Key Success Factors • Top-down commitment • Having a capable project manager • Having time to plan • Careful tracking and control • Good communications 11
  • 11. Project Management  What are the tools? • Work breakdown structure • Network diagram • Gantt charts 12 Project X Level 1 Level 2 Level 3 Level 4 MAR APR MAY JUN JUL AUG SEP OCT NOV DEC Locate new facilities Interview staff Hire and train staff Select and order furniture Remodel and install phones Move in/startup Gantt Chart
  • 12. Project Manager Responsible for: Work Quality Human Resources Time Communications Costs 13
  • 13. Review Lesson 1-a What are the key metrics? • ____ • ____ • Performance ___________ What are the Key Success Factors? • Top-down __________ • Having a _______ project _______ • Having ____ to plan • Careful tracking and _______ • Good ______________. What are the key metrics? • Time • ____ • Performance ___________ What are the Key Success Factors? • Top-down __________ • Having a _______ project _______ • Having ____ to plan • Careful tracking and _______ • Good ______________. What are the key metrics? • Time • Cost • Performance ___________ What are the Key Success Factors? • Top-down __________ • Having a _______ project _______ • Having ____ to plan • Careful tracking and _______ • Good ______________. What are the key metrics? • Time • Cost • Performance objectives What are the Key Success Factors? • Top-down __________ • Having a _______ project _______ • Having ____ to plan • Careful tracking and _______ • Good ______________. What are the key metrics? • Time • Cost • Performance objectives What are the Key Success Factors? • Top-down commitment • Having a ______ project _______ • Having ____ to plan • Careful tracking and _______ • Good ______________. What are the key metrics? • Time • Cost • Performance objectives What are the Key Success Factors? • Top-down commitment • Having a capable project manager • Having ____ to plan • Careful tracking and _______ • Good ______________. What are the key metrics? • Time • Cost • Performance objectives What are the Key Success Factors? • Top-down commitment • Having a capable project manager • Having time to plan • Careful tracking and _______ • Good ______________. What are the key metrics? • Time • Cost • Performance objectives What are the Key Success Factors? • Top-down commitment • Having a capable project manager • Having time to plan • Careful tracking and control • Good ______________. What are the key metrics? • Time • Cost • Performance objectives What are the Key Success Factors? • Top-down commitment • Having a capable project manager • Having time to plan • Careful tracking and control • Good communications 14
  • 15. PERT: Program Evaluation and Review Technique CPM: Critical Path Method • Graphically displays project activities • Estimates how long the project will take • Indicates most critical activities • Show where delays will not affect project PERT and CPM
  • 16. The Network Diagram • Network (precedence) diagram • Activity-on-arrow (AOA) • Activity-on-node (AON) • Activities • Events
  • 17. The Network Diagram (cont’d)  Path • Sequence of activities that leads from the starting node to the finishing node  Critical path • The longest path; determines expected project duration  Critical activities • Activities on the critical path  Slack • Allowable slippage for path; the difference between the length of path and the length of critical path
  • 18. Project Network – Activity on Arrow 1 2 3 4 5 6 Locate facilities Order furniture Furniture setup Interview Hire and train Remodel Move in AOA
  • 19. Project Network – Activity on Node 1 2 3 5 6 Locate facilities Order furniture Furniture setup Interview Remodel Move in 4 Hire and train 7S AON
  • 20. AOA vs. AON 1 2 3 5 6 Locate facilities Order furniture Furniture setup Interview Remodel Move in 4 Hire and train 7S AON 1 2 3 4 5 6 Locate facilities Order furniture Furniture setup Interview Hire and train Remodel Move in AOA
  • 22. Time Estimates  Deterministic • Time estimates that are fairly certain  Probabilistic • Estimates of times that allow for variation
  • 24. Expected Time te = to + 4tm +tp 6 te = expected time to = optimistic time tm = most likely time tp = pessimistic time
  • 26. Review Lesson 1 - b 1 2 3 4 5 6 8 weeks 6 weeks 3 weeks 4 weeks 9 weeks 11 weeks 1 week Move in Deterministic time estimates PATH LENGTH SLACK 1-2-3-4-5-6 1-2-5-6 1-3-5-6
  • 27. 29 PATH LENGTH SLACK 1-2-3-4-5-6 1-2-5-6 1-3-5-6 Solution to Review Lesson 1 - b PATH LENGTH SLACK 1-2-3-4-5-6 18 2 1-2-5-6 1-3-5-6 PATH LENGTH SLACK 1-2-3-4-5-6 18 2 1-2-5-6 20 0 1-3-5-6 PATH LENGTH SLACK 1-2-3-4-5-6 18 2 1-2-5-6 20 0 1-3-5-6 14 6 PATH LENGTH SLACK 1-2-3-4-5-6 18 2 1-2-5-6 20 0 1-3-5-6 14 6 Critical Path
  • 28. Solution to Review Lesson 1 - b PATH LENGTH SLACK 1-2-3-4-5-6 18 2 1-2-5-6 20 0 1-3-5-6 14 6 Critical Path 1 2 3 4 5 6 8 weeks 6 weeks 3 weeks 4 weeks 9 weeks 11 weeks 1 week Move in Deterministic time estimates
  • 29. Pert Chart  tasks a and b can start simultaneously  task c can start after a is complete  task d can start after b is complete  c and d must complete before e can begin 0 A B C&D E a b c d e The CRITICAL PATH is the longest continuous path of activities through a project that determines the project end date. 33
  • 30. Review Lesson 1 - c: Draw a Pert Chart for this job Task Title Duration Precedence a. start 0 - b. think 1 a c. plan 2 b d. procrastinate 5 a e. assign to someone else 1 c,d f. hide 3 e g. finish 1 e h. grab credit 1 f,g 34
  • 31. A B C&D E F F&G D a b d c e f G g 0 1 2 5 1 3 1 Critical Path = A D E F H slack in B C, G H 1 C Task Title Duration Precedence a. start 0 - b. think 1 a c. plan 2 b d. procrastinate 5 a e. assign to someone else 1 c,d f. hide 3 e g. finish 1 e h. grab credit 1 f,g 35 Solution to Review Lesson 1 - c
  • 32. Lesson 2: Microsoft Project • Starting Microsoft Project • The Screen • The Default View • Views and Tables • Menus • The Tool Bar
  • 33. Starting Microsoft Project 1. Run MS Project by opening it in “All Programs” • Select MS Project (usually in the same group where other MS Office applications are located. 37
  • 34. 1. Default View The Screen 3. You may add or delete some of the Toolbar in the Screen from this menu. 2. Change the Default View : • Choose View, Toolbar, Project Guide . 38
  • 35. Planning the Project • Where to Begin • Defining the Project • Setting the project start date • Complete the Project Plan • The base calendar • Save the New Project File
  • 36. Planning the project  Where to Begin 1. Start MS Project 2. Choose the Define Project in the Task Wizard 3. Follow succeeding instructions 40
  • 37. Planning the Project  Define the project 1. Choose “Define general working time” in the Wizard 2. Choose standard time for a regular 8 hour work day 3. Customize it to suit your needs. 4. Follow succeeding instruction 41
  • 38. Task Entry and Linking • Creating Milestone, • Task Relationships • Linking Tasks • Editing the Task Information • Formatting the Gantt Chart • Highlighting the critical path
  • 39. Create Milestone, Link and Relationship  When you enter a task or import a number of tasks, they have a duration of one day as a default To create milestone, select the task/s considered as milestone and then right click. Select Task Information. Put a check mark on Milestone. To create subtask, select the task considered and then select Project/Outline/Indent in the Menu Link the selected tasks by selecting Edit/Link task in the Menu. NOTE: All task are automatically link by Finish (a task) to Start (another task). 43 Edit the Duration, Start or End Date as needed.
  • 40. Editing Task Information  You can view information regarding a task by selecting the task and then right click. 44 A Task Information will appear showing several tabs where you can add, delete, or edit information regarding Resources, Predecessors, etc.
  • 41. Formatting the Gantt Chart  Select Format/Gantt Chart Wizard in the Menu 45 You can format the Gantt Chart view by using the Gantt chart Wizard Follow the instruction in the Wizard
  • 42. Highlighting the critical path  Select Format/Gantt Chart Wizard in the Menu 46 You can also highlight the critical path in the Gantt Chart view by using the Wizard Follow the instruction in the Wizard
  • 43. Updating the Project • Setting the baseline • Update the project • Tracking Progress
  • 44. Setting the Baseline 1. Select Tools/Tracking the Menu Bar 2. A dialog box appears where you are given a choice to “Set a Baseline” for the whole project or for the selected task only. 48
  • 45. Update the project 1. Select Tools/Tracking the Menu Bar 2. A dialog box appears where you are given several choices to update the project. 49
  • 46. Update each task in a project 1. Highlight a column where you want to insert another column. 2. Select Insert | Column in the Menu bar, or 3. Right click and then select “Insert column”. 4. In the “Column definition” dialog box , choose “%Complete”. Then select “OK”. 5. Update each task in the new column. 50
  • 47. Tracking Progress 1. Select Tools | Tracking | Progress Line in the Menu bar 2. In the “Progress Line” dialog box , choose “always display current progress line” and “At current date”. Then select “OK”. 3. A red vertical line will appear showing the status of the project. 51
  • 48. Sample of a project with tracking 52
  • 49. Network Diagram • View the Network Diagram • Elements of the Network Diagram
  • 50. The Network diagram 1. Select View | Network diagram in the Menu bar, 2. The Network Diagram appear immediately as shown. 3. Close-up view of the Network diagram 54
  • 51. 55 Elements of the Network diagram
  • 52. 56 Printing and Reporting • Page Setup • Reports Setup
  • 53. Page Set-up 1. Select File| Page Set-up in the Menu bar, 2. The “Page Set-up” dialog box will appear showing paper sizes and other choices. 3. Customize the printed output by inserting additional info in the “Header “and “Footer” 57
  • 54. Action Reflection “Failure to plan is planning to fail”
  • 55. END OF TRAINING FOR MODULE 1 60