The document discusses planning and managing projects in Microsoft Project 2010. It covers project management terminology and the five process groups of initiating, planning, executing, controlling, and closing a project. It also explains how to use various views and functions in Project 2010, including entering tasks, setting timescales, and printing projects.
Microsoft PPM helps you deliver on business strategies through high-impact outcomes. You can think of the PPM as a lifecycle which comprises of three phases: Ideate, Plan, and Execute.
Ideate: Is the initiation phase in which ideas are collected and projects are proposed. The organization’s business drivers capture the company’s strategy and guide ideation.
Plan: This phase includes preliminary planning of the projects at a high level. Microsoft PPM helps prioritize the projects subject to budget and resourcing constraints. Once projects are approved the solution supports detailed and realistic planning.
Execute: The goal of this phase is to deliver the projects through collaboration of the involved stakeholders.
Built on Microsoft’s cloud Microsoft PPM weaves in cloud services that power the PPM solution with collaboration capabilities, advanced analytics that drive insights and the ability to customize and extend the solution to meet unique needs of your organization.
Microsoft PPM is built on Microsoft’s cloud infrastructure. This means you get enterprise-grade security and compliance, highly secure and geographically diverse data centers, and a 99.9% uptime guarantee.
05. Project And Organizational StructureBhuWan Khadka
Chapter 05 of ICT Project Management of IOE Engineering syllabus. This is an educational purposed slides. This chapter provides knowledge about system view of project management,functional organization, matrix organization ...and more.Provided by Project Management Sir of KU.
The concepts and processes on how to perform project schedule management according to PMBOK Guide 6th edition. You'll find key concepts and terms, plan schedule management, define activities, sequence activities, estimate activity duration, develop schedule, and control schedule.
The concepts and processes on how to perform project resource management according to PMBOK Guide 6th edition. You'll find key concepts and terms, plan resource management, estimate activity resources, acquire team, develop team, manage team, and control resources.
This is the part of the presentation done by a PMP Workgroup which includes the project managers from NashTech, Trobz and Besco to study the Project Management and get the PMP certification. This part describes the process of Sequencing Activities in the Project Schedule Management knowledge area.
The concepts and processes on how to perform project risk management according to PMBOK Guide 6th edition. You'll find key concepts and terms, plan risk management, identify risks, perform qualitative & quantitative risks analysis, plan risk responses, implement risk responses, and monitor risks.
The seventh lesson of the course on Planning and Managing Software projects (http://emanueledellavalle.org/Teaching/PMSP-2011-12.html) that I give at Politecnico di Milano.
The document has been developed keeping in mind the common challenges that a planner may face while
developing a schedule. I have also tried to cover in areas which is required for effective earned value
calculation. The document is been prepared considering that the reader has a basic understanding of Primavera P6.
This material is intended to provide project leaders with a foundational understanding of leading practice project management processes, activities, tools, techniques, and deliverables as prescribed the Project Management Institute (PMI).
Microsoft project provides Project management tools to manage projects. MS Project training allows a Project Manager to follow the different phases, activities and tasks in a project.
On April 18th, C/D/H hosted a webinar with New Horizons on five easy steps to Microsoft Project. Local project management and technology professionals learned project management basics, an overview of Microsoft Project tools, and the benefits of moving to Microsoft Project from Excel.
View C/D/H's Excel to Project in 5 Easy Steps slide deck and see transformational changes you can bring to your daily project management duties with this powerful tool.
And for more information on this or other project management topics, visit our blog at www.cdhtalkstech.com.
Microsoft PPM helps you deliver on business strategies through high-impact outcomes. You can think of the PPM as a lifecycle which comprises of three phases: Ideate, Plan, and Execute.
Ideate: Is the initiation phase in which ideas are collected and projects are proposed. The organization’s business drivers capture the company’s strategy and guide ideation.
Plan: This phase includes preliminary planning of the projects at a high level. Microsoft PPM helps prioritize the projects subject to budget and resourcing constraints. Once projects are approved the solution supports detailed and realistic planning.
Execute: The goal of this phase is to deliver the projects through collaboration of the involved stakeholders.
Built on Microsoft’s cloud Microsoft PPM weaves in cloud services that power the PPM solution with collaboration capabilities, advanced analytics that drive insights and the ability to customize and extend the solution to meet unique needs of your organization.
Microsoft PPM is built on Microsoft’s cloud infrastructure. This means you get enterprise-grade security and compliance, highly secure and geographically diverse data centers, and a 99.9% uptime guarantee.
05. Project And Organizational StructureBhuWan Khadka
Chapter 05 of ICT Project Management of IOE Engineering syllabus. This is an educational purposed slides. This chapter provides knowledge about system view of project management,functional organization, matrix organization ...and more.Provided by Project Management Sir of KU.
The concepts and processes on how to perform project schedule management according to PMBOK Guide 6th edition. You'll find key concepts and terms, plan schedule management, define activities, sequence activities, estimate activity duration, develop schedule, and control schedule.
The concepts and processes on how to perform project resource management according to PMBOK Guide 6th edition. You'll find key concepts and terms, plan resource management, estimate activity resources, acquire team, develop team, manage team, and control resources.
This is the part of the presentation done by a PMP Workgroup which includes the project managers from NashTech, Trobz and Besco to study the Project Management and get the PMP certification. This part describes the process of Sequencing Activities in the Project Schedule Management knowledge area.
The concepts and processes on how to perform project risk management according to PMBOK Guide 6th edition. You'll find key concepts and terms, plan risk management, identify risks, perform qualitative & quantitative risks analysis, plan risk responses, implement risk responses, and monitor risks.
The seventh lesson of the course on Planning and Managing Software projects (http://emanueledellavalle.org/Teaching/PMSP-2011-12.html) that I give at Politecnico di Milano.
The document has been developed keeping in mind the common challenges that a planner may face while
developing a schedule. I have also tried to cover in areas which is required for effective earned value
calculation. The document is been prepared considering that the reader has a basic understanding of Primavera P6.
This material is intended to provide project leaders with a foundational understanding of leading practice project management processes, activities, tools, techniques, and deliverables as prescribed the Project Management Institute (PMI).
Microsoft project provides Project management tools to manage projects. MS Project training allows a Project Manager to follow the different phases, activities and tasks in a project.
On April 18th, C/D/H hosted a webinar with New Horizons on five easy steps to Microsoft Project. Local project management and technology professionals learned project management basics, an overview of Microsoft Project tools, and the benefits of moving to Microsoft Project from Excel.
View C/D/H's Excel to Project in 5 Easy Steps slide deck and see transformational changes you can bring to your daily project management duties with this powerful tool.
And for more information on this or other project management topics, visit our blog at www.cdhtalkstech.com.
Project Management: Choosing the Right Tools and ApproachPeter Campbell
Different projects require difgferent approaches. It's not a matter of which is better - traditional Waterfall or the newer agile approach -- it's a matter of what type of project your doing,. This NTEN presentation discusses both approaches and advises on when each one might work, as well as discussing what software will help.
Have you ever used a knife to stir or a shoe to pound a nail? We use these things because they’re convenient. But when we see a chef cooking or carpenter building, they always use the proper tool.
We fall into the same trap managing projects with Microsoft Excel. Why? Because it works for what we need at the time, and, as clients like to tell me, “it’s better than doing it on paper.” But for the best results, we need a tool set that supports collaboration and provides flexible work management solutions.
View the slide deck and find out why Microsoft Project and Project Server is the right tool combination for managing your projects – no matter how big – or how small.
And for more on project management and other topics, visit our blog at www.cdhtalkstech.com.
Project 2010 PPT explains the following
1. Why an organization needs Project 2010
2. How can you help build Organization growth using Project 2010
3. Significant features
4. Benefits of Project 2010
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...UiPathCommunity
💥 Speed, accuracy, and scaling – discover the superpowers of GenAI in action with UiPath Document Understanding and Communications Mining™:
See how to accelerate model training and optimize model performance with active learning
Learn about the latest enhancements to out-of-the-box document processing – with little to no training required
Get an exclusive demo of the new family of UiPath LLMs – GenAI models specialized for processing different types of documents and messages
This is a hands-on session specifically designed for automation developers and AI enthusiasts seeking to enhance their knowledge in leveraging the latest intelligent document processing capabilities offered by UiPath.
Speakers:
👨🏫 Andras Palfi, Senior Product Manager, UiPath
👩🏫 Lenka Dulovicova, Product Program Manager, UiPath
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf91mobiles
91mobiles recently conducted a Smart TV Buyer Insights Survey in which we asked over 3,000 respondents about the TV they own, aspects they look at on a new TV, and their TV buying preferences.
In his public lecture, Christian Timmerer provides insights into the fascinating history of video streaming, starting from its humble beginnings before YouTube to the groundbreaking technologies that now dominate platforms like Netflix and ORF ON. Timmerer also presents provocative contributions of his own that have significantly influenced the industry. He concludes by looking at future challenges and invites the audience to join in a discussion.
UiPath Test Automation using UiPath Test Suite series, part 4DianaGray10
Welcome to UiPath Test Automation using UiPath Test Suite series part 4. In this session, we will cover Test Manager overview along with SAP heatmap.
The UiPath Test Manager overview with SAP heatmap webinar offers a concise yet comprehensive exploration of the role of a Test Manager within SAP environments, coupled with the utilization of heatmaps for effective testing strategies.
Participants will gain insights into the responsibilities, challenges, and best practices associated with test management in SAP projects. Additionally, the webinar delves into the significance of heatmaps as a visual aid for identifying testing priorities, areas of risk, and resource allocation within SAP landscapes. Through this session, attendees can expect to enhance their understanding of test management principles while learning practical approaches to optimize testing processes in SAP environments using heatmap visualization techniques
What will you get from this session?
1. Insights into SAP testing best practices
2. Heatmap utilization for testing
3. Optimization of testing processes
4. Demo
Topics covered:
Execution from the test manager
Orchestrator execution result
Defect reporting
SAP heatmap example with demo
Speaker:
Deepak Rai, Automation Practice Lead, Boundaryless Group and UiPath MVP
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...James Anderson
Effective Application Security in Software Delivery lifecycle using Deployment Firewall and DBOM
The modern software delivery process (or the CI/CD process) includes many tools, distributed teams, open-source code, and cloud platforms. Constant focus on speed to release software to market, along with the traditional slow and manual security checks has caused gaps in continuous security as an important piece in the software supply chain. Today organizations feel more susceptible to external and internal cyber threats due to the vast attack surface in their applications supply chain and the lack of end-to-end governance and risk management.
The software team must secure its software delivery process to avoid vulnerability and security breaches. This needs to be achieved with existing tool chains and without extensive rework of the delivery processes. This talk will present strategies and techniques for providing visibility into the true risk of the existing vulnerabilities, preventing the introduction of security issues in the software, resolving vulnerabilities in production environments quickly, and capturing the deployment bill of materials (DBOM).
Speakers:
Bob Boule
Robert Boule is a technology enthusiast with PASSION for technology and making things work along with a knack for helping others understand how things work. He comes with around 20 years of solution engineering experience in application security, software continuous delivery, and SaaS platforms. He is known for his dynamic presentations in CI/CD and application security integrated in software delivery lifecycle.
Gopinath Rebala
Gopinath Rebala is the CTO of OpsMx, where he has overall responsibility for the machine learning and data processing architectures for Secure Software Delivery. Gopi also has a strong connection with our customers, leading design and architecture for strategic implementations. Gopi is a frequent speaker and well-known leader in continuous delivery and integrating security into software delivery.
The Art of the Pitch: WordPress Relationships and SalesLaura Byrne
Clients don’t know what they don’t know. What web solutions are right for them? How does WordPress come into the picture? How do you make sure you understand scope and timeline? What do you do if sometime changes?
All these questions and more will be explored as we talk about matching clients’ needs with what your agency offers without pulling teeth or pulling your hair out. Practical tips, and strategies for successful relationship building that leads to closing the deal.
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Albert Hoitingh
In this session I delve into the encryption technology used in Microsoft 365 and Microsoft Purview. Including the concepts of Customer Key and Double Key Encryption.
Elevating Tactical DDD Patterns Through Object CalisthenicsDorra BARTAGUIZ
After immersing yourself in the blue book and its red counterpart, attending DDD-focused conferences, and applying tactical patterns, you're left with a crucial question: How do I ensure my design is effective? Tactical patterns within Domain-Driven Design (DDD) serve as guiding principles for creating clear and manageable domain models. However, achieving success with these patterns requires additional guidance. Interestingly, we've observed that a set of constraints initially designed for training purposes remarkably aligns with effective pattern implementation, offering a more ‘mechanical’ approach. Let's explore together how Object Calisthenics can elevate the design of your tactical DDD patterns, offering concrete help for those venturing into DDD for the first time!
Epistemic Interaction - tuning interfaces to provide information for AI supportAlan Dix
Paper presented at SYNERGY workshop at AVI 2024, Genoa, Italy. 3rd June 2024
https://alandix.com/academic/papers/synergy2024-epistemic/
As machine learning integrates deeper into human-computer interactions, the concept of epistemic interaction emerges, aiming to refine these interactions to enhance system adaptability. This approach encourages minor, intentional adjustments in user behaviour to enrich the data available for system learning. This paper introduces epistemic interaction within the context of human-system communication, illustrating how deliberate interaction design can improve system understanding and adaptation. Through concrete examples, we demonstrate the potential of epistemic interaction to significantly advance human-computer interaction by leveraging intuitive human communication strategies to inform system design and functionality, offering a novel pathway for enriching user-system engagements.
Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™UiPathCommunity
In questo evento online gratuito, organizzato dalla Community Italiana di UiPath, potrai esplorare le nuove funzionalità di Autopilot, il tool che integra l'Intelligenza Artificiale nei processi di sviluppo e utilizzo delle Automazioni.
📕 Vedremo insieme alcuni esempi dell'utilizzo di Autopilot in diversi tool della Suite UiPath:
Autopilot per Studio Web
Autopilot per Studio
Autopilot per Apps
Clipboard AI
GenAI applicata alla Document Understanding
👨🏫👨💻 Speakers:
Stefano Negro, UiPath MVPx3, RPA Tech Lead @ BSP Consultant
Flavio Martinelli, UiPath MVP 2023, Technical Account Manager @UiPath
Andrei Tasca, RPA Solutions Team Lead @NTT Data
Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™
Ms project 2010 tutorial 1
1. Tutorial 1:
Planning a Project
Planning a Project
Microsoft Project 2010
®
http://www.learningquotient.in
2. In Tutorial Section 1.1 XP
you will:
you will:
• Learn project management terminology
• Understand the benefits of project
d d h b f f
management
• Explore the Project 2010 window
• Check and change default settings
g g
• Enter tasks and save a project
http://www.learningquotient.in
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 2
3. In Tutorial Section 1.2 XP
you will:
you will:
• Open and explore an existing project
• Examine different project views
d ff
• Compare the Gantt Chart and Network
Diagram views
• Use project time scale and calendar
p j
• Use Backstage view and Page Setup dialog box
http://www.learningquotient.in
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 3
4. Introduction to Project XP
Management
• Project Management: process of initiating,
planning, executing, controlling, and closing a
planning executing controlling and closing a
project
• Project Goal is the desired outcome
j l h d d
– Should be short and simple, yet clearly
communicate scope, time frame, and budget.
f b
http://www.learningquotient.in
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 4
5. Introduction to Project XP
Management, Cont.
Management Cont
• A Process Group is a series of steps to
complete in order move on to the next phase
complete in order move on to the next phase
of a project.
• There are 5 Process Groups in Project
h
Management
http://www.learningquotient.in
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 5
6. Project Management Process XP
Groups
http://www.learningquotient.in
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 6
7. Initiating XP
• Setting the project goal
• Identifying start or finish dates
d f f hd
• Identifying the project manager
• Identifying project budget and quality
considerations
http://www.learningquotient.in
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 7
8. Planning XP
• Entering project information
• Identifying project subdivisions and milestones
d f bd d l
• Documenting resources
• Entering restrictions
• Assigning Resources to tasks
Assigning Resources to tasks
http://www.learningquotient.in
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 8
9. Executing XP
• Producing work results
• Requesting changes
h
• Recommending improvements
• Creating project records, reports, and
p
presentations
http://www.learningquotient.in
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 9
10. Controlling XP
• Updating project
• Managing resources and tasks
d k
• Meet management timing, resource, and cost
objectives
• Changing project
g gp j
http://www.learningquotient.in
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 10
11. Closing XP
• Entering final status of finished project
• Printing final reports
f l
• Review and analyze performance of the
project
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 11
12. Project Management Terminology
XP
• Understanding key project terminology is
fundamental to your success as a project
fundamental to your success as a project
manager:
–T k
Task –P j M
Project Manager
– Duration – Scope
– Start and Finish Dates – Quality
– Predecessor and – Risk
Successor
S
– Resources
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 12
13. Benefits of Project Management XP
• Better understanding of overall project goals
• Better understanding of alignment with
d d f l h
business objectives
• More organized and streamlined way to
manage a project
• More accurate and reliable project status
information
• More efficient use of project resources
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 13
14. Benefits of Project Management, XP
Cont.
Cont
• Better communication
• Faster response to conflicting project goals
fl l
• Greater awareness of project progress
• Faster project completion
• Lower project costs
Lower project costs
• Fewer project failures
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 14
15. How Project 2010 Supports XP
Successful Project Management
Successful Project Management
• MS Project 2010
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 15
16. Chart and Diagram Tools XP
• The Gantt Chart and Network Diagram are two
important project management tools within
important project management tools within
Project 2010.
• The Gantt Chart provides a graphical
h h d h l
visualization of the project.
– Tasks are shown as horizontal bars
– Illustrates task dependencies
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 16
17. Basic Gantt Chart XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 17
18. Chart and Diagram Tools, Cont. XP
• The Network Diagram’s primary purpose is to
show the critical path of the project.
show the critical path of the project
– Tasks are displayed as boxes, called nodes.
– Dependent tasks are linked together via link lines.
d k l k d h l kl
– The critical path is the series of tasks that dictates
the earliest calculated project finish date.
th li t l l t d j t fi i h d t
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 18
19. Basic Network Diagram XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 19
20. Getting Started with Project 2010 XP
• Starting Project 2010
• View Bar
• Entry Table
• Gantt Chart
• Timeline
• Timescale
–AA major scale (the upper scale)
j l (th l )
– A minor scale (the lower scale)
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 20
21. Microsoft Project Window XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 21
22. View Bar and View Tab XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 22
23. Entry Table XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 23
24. Gantt Chart and Split Bar XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 24
25. The Timeline XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 25
26. The Timescale XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 26
27. Getting Started with Project 2010,
XP
Cont.
Cont
• Current Date
• Working Days and Nonworking Days
k d k
• Setting Automatic Scheduling
• Setting Project Start and Finish Dates
• Entering Tasks
Entering Tasks
• Saving a Project
• Closing a Project
l i j
• Opening an Existing Project
• Saving a Project with a new name
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 27
30. Changing the Current Date XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 30
31. Entering Tasks XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 31
32. Two Tasks Entered XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 32
33. Saving a Project XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 33
34. Working in Different Views XP
• Chart or Graphic: representation of data using
bars, boxes, lines, and images
bars boxes lines and images
• Sheet: A spreadsheet‐like representation of
data in rows and columns
d d l
• Form: view of many pieces of information to
focus on the details of one task
• Combination: view of many tasks at the top of
y p
the screen, view of task details below.
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 34
35. Common Project Views (Task XP
Views)
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 35
36. Common Views XP
• Gantt Chart View
• Network Diagram View
k
• Calendar View
• Task Information Dialog Box
• Notes Tab, Notes Indicator
Notes Tab Notes Indicator
• Relationship View
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 36
37. Network Diagram View XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 37
38. Calendar view XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 38
40. Notes Tab XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 40
41. Notes Indicators XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 41
42. Relationship Diagram View XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 42
43. Common Views, Cont. XP
• Entry Table
• Schedule Table
h d l bl
• Split View
• Zooming in and Out
• Timescale Dialog Box
Timescale Dialog Box
• Changing the timescale
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 43
44. Entry Table XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 44
45. Schedule Table XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 45
46. Split View XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 46
47. Zooming In and Out XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 47
48. Timescale Dialog Box XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 48
49. Changing the Timescale XP
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 49
50. Successful Printing XP
• The key aspects of successful printing:
–ZZooming to an acceptable magnification level
i bl ifi i l l
– Print previewing your work
– Using the page setup dialog box to make changes
http://www.learningquotient.in
New Perspectives on Microsoft Project 2010 50