SlideShare a Scribd company logo
SIKKIM MANIPAL INSTITUTE OF
TECHNOLOGY
MAJOR PROJECT REPORT
ON
MASS HOUSING AT SHUKHOBRISHTI SITE,
NEWTOWN KOLKATA
SHUBHAM PRADHAN
REG NO: 20130055
ROLL NO: 07
PILE FOUNDATIONS
• A pile is basically a long cylinder of a strong material such as concrete that is pushed
into the ground to act as a steady support for structures built on top of it.
• Pile foundations are used in the following situations:
When there is a layer of weak soil at the surface. This layer cannot support the weight of
the building, so the loads of the building have to bypass this layer and be transferred to
the layer of stronger soil or rock that is below the weak layer.
• When a building has very heavy, concentrated loads, such as in a high rise structure,
bridge, or water tank.
• Pile foundations are capable of taking higher loads than spread footings.
There are two types of pile foundations, each of which works in its own way.
TYPES OF PILE FOUNDATION
DIFFERENCE IN LOAD TRANSFER
 End bearing piles
 Friction pile
DIFFERENCE
Frictional Piles works on the static friction developed between the surface of the pile and
soil where it is placed. Where as End-Bearing Piles are driven till hard strata of soil is
achieved.
PROCESS OF PILING
HOW PILES ARE CONSTRUCTED
1. Piles are first cast at ground level and then hammered or driven into the ground using a pile
driver.
2. This is a machine that holds the pile perfectly vertical, and then hammers it into the ground
blow by blow.
3. Each blow is struck by lifting a heavy weight and dropping it on the top of the pile - the pile
is temporarily covered with a steel cap to prevent it from disintegrating.
4. The pile driver thus performs two functions - first, it acts as a crane, and lifts the pile from a
horizontal position on the ground and rotates it into the correct vertical position, and second,
it hammers the pile down into the ground.
5. Piles should be hammered into the ground till refusal, at which point they cannot be driven
any further into the soil.
MIVAN Shuttering
• The system of aluminum forms (MIVAN) has been used widely in the construction of
residential units and mass housing projects.
• It is fast, simple, adaptable and cost – effective.
• It produces total quality work which requires minimum maintenance and when durability is
the prime consideration.
• This system is most suitable for Indian condition as a tailor–made aluminum formwork for
cast–in–situ fully concrete structure.
• It does not require much laboures.
• The concrete is produced in RMC batching plants under strict quality control and convey it
to site with transit mixers.
• Aluminum Formwork system is a comparatively a new technology in India.
MIVAN SHUTTERING
• It saves cost, time and improves the quality of construction.
• It was used by L&T for the first time in India in its projects in Mumbai, Delhi & South India
(South city, Bangalore) in 2003 for the construction of both low and high raises apartments
and buildings.
• Aluminum formwork is very cost effective for repetitive Buildings layouts and for above the
plinth work.
It is suitable for:
• Mass housing
• Typical floors
• Fast construction required
• No of repetition are more
• High quality
HISTORY AND BACKGROUND
• Mivan is basically an aluminum formwork system developed by one of the
construction company from Europe. In 1990, the Mivan Company Ltd
from Malaysia started the manufacturing of such formwork systems.
• Now a days more than 30,000 sq. m of formwork used in the world are under their
operation.
• In Mumbai, India there are number of buildings constructed with the help of the
above system which has been proved to be very economical and satisfactory for
Indian Construction Environment.
• The technology has been used extensively in other countries such as Europe, Gulf
Countries, Asia and all other parts of the world.
• All the activities are planned in assembly line manner and hence result into more
accurate, well – controlled and high quality production at optimum cost and in
shortest possible time.
COMPONENTS
MIVAN Formwork Assembly:
MIVAN aims in using modern
construction techniques and equipment
in all its projects. On leaving the MIVAN
factory all panels are clearly labeled to
ensure that they are easily identifiable
on site and can be smoothly fitted
together using the formwork modulation
drawings.
PROCEDURE
Pre – Concrete Activities:
I. Receipt of Equipment on Site – The equipment is received in the site as ordered.
II. Level Surveys – Level checking are made to maintain horizontal level check.
III. Setting Out – The setting out of the formwork is done.
IV. Control / Correction of Deviation – Deviation or any correction are carried out.
V. Erect Formwork – The formwork is erected on site.
VI. Erect Deck Formwork – Deck is erected for labours to work.
VII. Setting Kickers – kickers are provided over the beam
PRE – CONCRETE ACTIVITIES
On Concrete Activities:
i. Dislodging of pins/wedges due to vibration.
ii. Beam/deck props adjacent to drop areas slipping due to vibration.
iii. Ensure all bracing at special areas slipping due to vibration.
iv. Overspill of concrete at window opening etc.
Post – Concrete Activities:
i. Cleaning:
• All components should be cleaned with scrapers and wire brushes as soon as they are
struck. Wire brush is to be used on side rails only.
ii. Transporting:
• The heaviest and the longest, which is a full height of wall panel, can be carried up the
nearest stairway. Passes through void areas.
iii. Striking:
• Once cleaned and transported to the next point of erection, panels should be stacked at right
place and in right order.
iv. Erecting Of Formwork:
• After that formwork is erect again on the next floor.
ADVANTAGES
• Mivan formwork requires relatively less labour
• More seismic resistance
• Increased durability
• Lesser number of joints and reduced leakages
• Higher carpet area
• Smooth finishing of wall and slab
• Uniform quality of construction
• Negligible maintenance
• Faster completion
DISADVANTAGES
• Because of few small sizes finishing lines are seen on the concrete surfaces
• Services after completing become slightly difficult due to the small width of components
• It requires uniform planning as well as uniform elevations to be cost effective
• The formwork requires number of spacer, wall ties etc. which are placed @ 2ft c/c; these
produce problems such as seepage, leakages during monsoon
• Due to box-type construction, contraction cracks are likely to appear
• Heat of hydration is high due to shear walls
• It is rigid in design once placed, as any alteration becomes tough later
AAC BLOCKS
What is AAC?
• Autoclaved aerated concrete (AAC), also known as autoclaved cellular concrete (ACC),
autoclaved lightweight concrete (ALC), autoclaved concrete, cellular concrete, porous
concrete, Ytong, Hebel Block, Aircrete, Thermalite.
When was AAC first developed?
• AAC was developed in 1924 by a Swedish architect, who was looking for an alternate
building material with properties similar to that of wood – good thermal insulation, solid
structure and easy to work with – but without the disadvantage of combustibility, decay
and termite damage. It has been refined into a highly thermally insulating concrete-based
material used for both internal and external construction.
• AAC products include blocks, wall panels, floor and roof panels, and lintels.
• AAC has been produced for more than 70 years, and it offers several significant
advantages over other cement construction materials, one of the most important being
its lower environmental impact.
• Improved thermal efficiency reduces the heating and cooling load in buildings.
• Workability allows accurate cutting, which minimizes the generation of solid waste during
use.
• Light weight saves cost & energy in transportation.
• Light weight saves labour expenses.
• Light weight increases chances of survival during seismic activity.
ADVANTAGES
• Termite/Pest Resistant
• Cost Effective
• Easy Workability and Design Flexibility
• Thermally Insulated & Energy Efficient
• Fire Resistant
• Eco-friendly
RAW MATERIALS
SR. NO. RAW MATERIALS RATIO
1 FLY ASH 65 – 70 %
2 LIME 8 – 12 %
3 CEMENT 10 – 15 %
4 GYPSUM 0.5 – 5 %
5 ALUMINIUM POWDER 0.5 %
PROCESS OF LAYING AAC BLOCKS
THANK YOU

More Related Content

What's hot

Bubble deck&hollow core slab
Bubble deck&hollow core slabBubble deck&hollow core slab
Bubble deck&hollow core slab
Penny3688
 
Aluminium formwork(t 4 a)
Aluminium formwork(t 4 a)Aluminium formwork(t 4 a)
Aluminium formwork(t 4 a)
w ss
 
04.chapter ii
04.chapter ii04.chapter ii
04.chapter ii
GTVT
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
ashleyyeap
 

What's hot (20)

Mivan shuttering
Mivan shutteringMivan shuttering
Mivan shuttering
 
Formwork
FormworkFormwork
Formwork
 
Bubble deck&hollow core slab
Bubble deck&hollow core slabBubble deck&hollow core slab
Bubble deck&hollow core slab
 
FORM WORK & SLIPFORM
FORM WORK & SLIPFORMFORM WORK & SLIPFORM
FORM WORK & SLIPFORM
 
Advance Formwork System (PERI FORMWORK SYSTEM)
Advance Formwork System (PERI FORMWORK SYSTEM)Advance Formwork System (PERI FORMWORK SYSTEM)
Advance Formwork System (PERI FORMWORK SYSTEM)
 
Aluminium formwork(t 4 a)
Aluminium formwork(t 4 a)Aluminium formwork(t 4 a)
Aluminium formwork(t 4 a)
 
Technical textiles in Central Public Works Department
Technical textiles in Central Public Works DepartmentTechnical textiles in Central Public Works Department
Technical textiles in Central Public Works Department
 
04.chapter ii
04.chapter ii04.chapter ii
04.chapter ii
 
Slip formwork technique
Slip formwork techniqueSlip formwork technique
Slip formwork technique
 
Aluminium Formwork Vs Conventional Formwork
Aluminium Formwork Vs  Conventional  FormworkAluminium Formwork Vs  Conventional  Formwork
Aluminium Formwork Vs Conventional Formwork
 
Formwork by chakamba john
Formwork by chakamba johnFormwork by chakamba john
Formwork by chakamba john
 
Pre engineered and other buildings
Pre engineered and other buildingsPre engineered and other buildings
Pre engineered and other buildings
 
Formwork
FormworkFormwork
Formwork
 
Table formwork
Table formwork Table formwork
Table formwork
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
New materials and technologies used in NISM Mumbai
New materials and technologies used in NISM MumbaiNew materials and technologies used in NISM Mumbai
New materials and technologies used in NISM Mumbai
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
 
Presentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction techniquePresentation on MIVAN -- A versatile aluminum formwork construction technique
Presentation on MIVAN -- A versatile aluminum formwork construction technique
 
HOLLOW CORE SLABS
HOLLOW CORE SLABSHOLLOW CORE SLABS
HOLLOW CORE SLABS
 
Scaffolding and formwork ppt
Scaffolding and  formwork pptScaffolding and  formwork ppt
Scaffolding and formwork ppt
 

Viewers also liked

Internal and external business environment
Internal and external business environmentInternal and external business environment
Internal and external business environment
Aashish Sahi
 

Viewers also liked (14)

Organizational Structure & Leadership Style in M/s Larsen & Toubro , ...
Organizational Structure & Leadership Style in M/s Larsen & Toubro , ...Organizational Structure & Leadership Style in M/s Larsen & Toubro , ...
Organizational Structure & Leadership Style in M/s Larsen & Toubro , ...
 
Simplex Cyprus Data Center Presentation
Simplex Cyprus Data Center PresentationSimplex Cyprus Data Center Presentation
Simplex Cyprus Data Center Presentation
 
Sec
SecSec
Sec
 
Computer 3
Computer 3Computer 3
Computer 3
 
Earthquake Engineering
Earthquake EngineeringEarthquake Engineering
Earthquake Engineering
 
Shear walls
Shear wallsShear walls
Shear walls
 
Basics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-Agha
Basics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-AghaBasics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-Agha
Basics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-Agha
 
Performance based analysis of rc building consisting shear wall and varying i...
Performance based analysis of rc building consisting shear wall and varying i...Performance based analysis of rc building consisting shear wall and varying i...
Performance based analysis of rc building consisting shear wall and varying i...
 
SHEAR WALL
SHEAR WALLSHEAR WALL
SHEAR WALL
 
Lec01 Design of RC Structures under lateral load (Earthquake Engineering هندس...
Lec01 Design of RC Structures under lateral load (Earthquake Engineering هندس...Lec01 Design of RC Structures under lateral load (Earthquake Engineering هندس...
Lec01 Design of RC Structures under lateral load (Earthquake Engineering هندس...
 
Shear wall
Shear wallShear wall
Shear wall
 
Earthquake ppt
Earthquake pptEarthquake ppt
Earthquake ppt
 
Internal and external business environment
Internal and external business environmentInternal and external business environment
Internal and external business environment
 
Slideshare Powerpoint presentation
Slideshare Powerpoint presentationSlideshare Powerpoint presentation
Slideshare Powerpoint presentation
 

Similar to simplex infrastructure

Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3
Prasanth Dasu
 

Similar to simplex infrastructure (20)

Modern Formwork: Mivan
Modern Formwork: Mivan Modern Formwork: Mivan
Modern Formwork: Mivan
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptx
 
Mivan form wok - aluminium formwork shuttering tecnology
Mivan form wok - aluminium formwork shuttering tecnologyMivan form wok - aluminium formwork shuttering tecnology
Mivan form wok - aluminium formwork shuttering tecnology
 
Slip form Construction Technology
Slip form Construction TechnologySlip form Construction Technology
Slip form Construction Technology
 
Construction Technology
Construction TechnologyConstruction Technology
Construction Technology
 
Form-woks-additional.pptx
Form-woks-additional.pptxForm-woks-additional.pptx
Form-woks-additional.pptx
 
national building code
national building codenational building code
national building code
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
High rise construction
High rise constructionHigh rise construction
High rise construction
 
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdfSAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
 
rapid walls- modular construction technology
rapid walls- modular construction technologyrapid walls- modular construction technology
rapid walls- modular construction technology
 
highriseconstruction-150505221523-conversion-gate02.pptx
highriseconstruction-150505221523-conversion-gate02.pptxhighriseconstruction-150505221523-conversion-gate02.pptx
highriseconstruction-150505221523-conversion-gate02.pptx
 
Mivan Aluminum formwork ppt presentation
Mivan Aluminum formwork ppt presentationMivan Aluminum formwork ppt presentation
Mivan Aluminum formwork ppt presentation
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examples
 
Construction portfolio (manvi)
Construction portfolio (manvi)Construction portfolio (manvi)
Construction portfolio (manvi)
 
Slipform
SlipformSlipform
Slipform
 
Pre fabricatted and pre engineered building
Pre fabricatted and pre engineered buildingPre fabricatted and pre engineered building
Pre fabricatted and pre engineered building
 
Introduction to construction technology
Introduction to construction technologyIntroduction to construction technology
Introduction to construction technology
 
Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3
 

Recently uploaded

Killer Referans Bahcesehir Catalog Listing Turkey
Killer Referans Bahcesehir Catalog Listing TurkeyKiller Referans Bahcesehir Catalog Listing Turkey
Killer Referans Bahcesehir Catalog Listing Turkey
Listing Turkey
 
Torun Center Residences Istanbul - Listing Turkey
Torun Center Residences Istanbul - Listing TurkeyTorun Center Residences Istanbul - Listing Turkey
Torun Center Residences Istanbul - Listing Turkey
Listing Turkey
 
Listing Turkey - Sinpaş Queen Bomonti Katalog
Listing Turkey - Sinpaş Queen Bomonti KatalogListing Turkey - Sinpaş Queen Bomonti Katalog
Listing Turkey - Sinpaş Queen Bomonti Katalog
Listing Turkey
 
Investing In The US As A Canadian… And How To Do It RIGHT!! (feat. Erwin Szet...
Investing In The US As A Canadian… And How To Do It RIGHT!! (feat. Erwin Szet...Investing In The US As A Canadian… And How To Do It RIGHT!! (feat. Erwin Szet...
Investing In The US As A Canadian… And How To Do It RIGHT!! (feat. Erwin Szet...
Volition Properties
 

Recently uploaded (17)

Sinpas Gokorman Presentation. - Listing Turkey
Sinpas Gokorman Presentation. - Listing TurkeySinpas Gokorman Presentation. - Listing Turkey
Sinpas Gokorman Presentation. - Listing Turkey
 
Oeiras Tech City, Developed by RE Capital and REIG, Will Become Lisbon's Futu...
Oeiras Tech City, Developed by RE Capital and REIG, Will Become Lisbon's Futu...Oeiras Tech City, Developed by RE Capital and REIG, Will Become Lisbon's Futu...
Oeiras Tech City, Developed by RE Capital and REIG, Will Become Lisbon's Futu...
 
Top 10 International Schools in Bangalore
Top 10 International Schools in BangaloreTop 10 International Schools in Bangalore
Top 10 International Schools in Bangalore
 
Killer Referans Bahcesehir Catalog Listing Turkey
Killer Referans Bahcesehir Catalog Listing TurkeyKiller Referans Bahcesehir Catalog Listing Turkey
Killer Referans Bahcesehir Catalog Listing Turkey
 
Types and Sources of Mortgage Leads: What You Need to Know
Types and Sources of Mortgage Leads: What You Need to KnowTypes and Sources of Mortgage Leads: What You Need to Know
Types and Sources of Mortgage Leads: What You Need to Know
 
Optimizing Your MCA Lead Capture Process for Better Results
Optimizing Your MCA Lead Capture Process for Better ResultsOptimizing Your MCA Lead Capture Process for Better Results
Optimizing Your MCA Lead Capture Process for Better Results
 
Torun Center Residences Istanbul - Listing Turkey
Torun Center Residences Istanbul - Listing TurkeyTorun Center Residences Istanbul - Listing Turkey
Torun Center Residences Istanbul - Listing Turkey
 
One FNG by Group 108 Sector 142 Noida Construction Update
One FNG by Group 108 Sector 142 Noida Construction UpdateOne FNG by Group 108 Sector 142 Noida Construction Update
One FNG by Group 108 Sector 142 Noida Construction Update
 
Avrupa Konutlari Yenimahalle - Listing Turkey
Avrupa Konutlari Yenimahalle - Listing TurkeyAvrupa Konutlari Yenimahalle - Listing Turkey
Avrupa Konutlari Yenimahalle - Listing Turkey
 
How to Scan Tenants in NYC - You Should Know!
How to Scan Tenants in NYC - You Should Know!How to Scan Tenants in NYC - You Should Know!
How to Scan Tenants in NYC - You Should Know!
 
What is BDA? Understanding the Bangalore Development Authority
What is BDA? Understanding the Bangalore Development AuthorityWhat is BDA? Understanding the Bangalore Development Authority
What is BDA? Understanding the Bangalore Development Authority
 
MC Heights-Best Construction Company in jhang
MC Heights-Best Construction Company in jhangMC Heights-Best Construction Company in jhang
MC Heights-Best Construction Company in jhang
 
Urbanrise Paradise on Earth - Unveiling Unprecedented Luxury in Exquisite Vil...
Urbanrise Paradise on Earth - Unveiling Unprecedented Luxury in Exquisite Vil...Urbanrise Paradise on Earth - Unveiling Unprecedented Luxury in Exquisite Vil...
Urbanrise Paradise on Earth - Unveiling Unprecedented Luxury in Exquisite Vil...
 
2BHK-3BHK NEW FLAT FOR SALE IN TUPUDANA,RANCHI.
2BHK-3BHK NEW FLAT FOR SALE IN TUPUDANA,RANCHI.2BHK-3BHK NEW FLAT FOR SALE IN TUPUDANA,RANCHI.
2BHK-3BHK NEW FLAT FOR SALE IN TUPUDANA,RANCHI.
 
Sefakoy Sinpas Boulevard Istanbul - Presentation
Sefakoy Sinpas Boulevard Istanbul - PresentationSefakoy Sinpas Boulevard Istanbul - Presentation
Sefakoy Sinpas Boulevard Istanbul - Presentation
 
Listing Turkey - Sinpaş Queen Bomonti Katalog
Listing Turkey - Sinpaş Queen Bomonti KatalogListing Turkey - Sinpaş Queen Bomonti Katalog
Listing Turkey - Sinpaş Queen Bomonti Katalog
 
Investing In The US As A Canadian… And How To Do It RIGHT!! (feat. Erwin Szet...
Investing In The US As A Canadian… And How To Do It RIGHT!! (feat. Erwin Szet...Investing In The US As A Canadian… And How To Do It RIGHT!! (feat. Erwin Szet...
Investing In The US As A Canadian… And How To Do It RIGHT!! (feat. Erwin Szet...
 

simplex infrastructure

  • 1. SIKKIM MANIPAL INSTITUTE OF TECHNOLOGY MAJOR PROJECT REPORT ON MASS HOUSING AT SHUKHOBRISHTI SITE, NEWTOWN KOLKATA SHUBHAM PRADHAN REG NO: 20130055 ROLL NO: 07
  • 2. PILE FOUNDATIONS • A pile is basically a long cylinder of a strong material such as concrete that is pushed into the ground to act as a steady support for structures built on top of it. • Pile foundations are used in the following situations: When there is a layer of weak soil at the surface. This layer cannot support the weight of the building, so the loads of the building have to bypass this layer and be transferred to the layer of stronger soil or rock that is below the weak layer. • When a building has very heavy, concentrated loads, such as in a high rise structure, bridge, or water tank. • Pile foundations are capable of taking higher loads than spread footings. There are two types of pile foundations, each of which works in its own way.
  • 3. TYPES OF PILE FOUNDATION
  • 4. DIFFERENCE IN LOAD TRANSFER  End bearing piles  Friction pile DIFFERENCE Frictional Piles works on the static friction developed between the surface of the pile and soil where it is placed. Where as End-Bearing Piles are driven till hard strata of soil is achieved.
  • 6. HOW PILES ARE CONSTRUCTED 1. Piles are first cast at ground level and then hammered or driven into the ground using a pile driver. 2. This is a machine that holds the pile perfectly vertical, and then hammers it into the ground blow by blow. 3. Each blow is struck by lifting a heavy weight and dropping it on the top of the pile - the pile is temporarily covered with a steel cap to prevent it from disintegrating. 4. The pile driver thus performs two functions - first, it acts as a crane, and lifts the pile from a horizontal position on the ground and rotates it into the correct vertical position, and second, it hammers the pile down into the ground. 5. Piles should be hammered into the ground till refusal, at which point they cannot be driven any further into the soil.
  • 7. MIVAN Shuttering • The system of aluminum forms (MIVAN) has been used widely in the construction of residential units and mass housing projects. • It is fast, simple, adaptable and cost – effective. • It produces total quality work which requires minimum maintenance and when durability is the prime consideration. • This system is most suitable for Indian condition as a tailor–made aluminum formwork for cast–in–situ fully concrete structure. • It does not require much laboures. • The concrete is produced in RMC batching plants under strict quality control and convey it to site with transit mixers. • Aluminum Formwork system is a comparatively a new technology in India. MIVAN SHUTTERING
  • 8. • It saves cost, time and improves the quality of construction. • It was used by L&T for the first time in India in its projects in Mumbai, Delhi & South India (South city, Bangalore) in 2003 for the construction of both low and high raises apartments and buildings. • Aluminum formwork is very cost effective for repetitive Buildings layouts and for above the plinth work.
  • 9. It is suitable for: • Mass housing • Typical floors • Fast construction required • No of repetition are more • High quality
  • 10. HISTORY AND BACKGROUND • Mivan is basically an aluminum formwork system developed by one of the construction company from Europe. In 1990, the Mivan Company Ltd from Malaysia started the manufacturing of such formwork systems. • Now a days more than 30,000 sq. m of formwork used in the world are under their operation. • In Mumbai, India there are number of buildings constructed with the help of the above system which has been proved to be very economical and satisfactory for Indian Construction Environment. • The technology has been used extensively in other countries such as Europe, Gulf Countries, Asia and all other parts of the world. • All the activities are planned in assembly line manner and hence result into more accurate, well – controlled and high quality production at optimum cost and in shortest possible time.
  • 11. COMPONENTS MIVAN Formwork Assembly: MIVAN aims in using modern construction techniques and equipment in all its projects. On leaving the MIVAN factory all panels are clearly labeled to ensure that they are easily identifiable on site and can be smoothly fitted together using the formwork modulation drawings.
  • 12. PROCEDURE Pre – Concrete Activities: I. Receipt of Equipment on Site – The equipment is received in the site as ordered. II. Level Surveys – Level checking are made to maintain horizontal level check. III. Setting Out – The setting out of the formwork is done. IV. Control / Correction of Deviation – Deviation or any correction are carried out. V. Erect Formwork – The formwork is erected on site. VI. Erect Deck Formwork – Deck is erected for labours to work. VII. Setting Kickers – kickers are provided over the beam
  • 13. PRE – CONCRETE ACTIVITIES
  • 14. On Concrete Activities: i. Dislodging of pins/wedges due to vibration. ii. Beam/deck props adjacent to drop areas slipping due to vibration. iii. Ensure all bracing at special areas slipping due to vibration. iv. Overspill of concrete at window opening etc.
  • 15. Post – Concrete Activities: i. Cleaning: • All components should be cleaned with scrapers and wire brushes as soon as they are struck. Wire brush is to be used on side rails only. ii. Transporting: • The heaviest and the longest, which is a full height of wall panel, can be carried up the nearest stairway. Passes through void areas. iii. Striking: • Once cleaned and transported to the next point of erection, panels should be stacked at right place and in right order. iv. Erecting Of Formwork: • After that formwork is erect again on the next floor.
  • 16. ADVANTAGES • Mivan formwork requires relatively less labour • More seismic resistance • Increased durability • Lesser number of joints and reduced leakages • Higher carpet area • Smooth finishing of wall and slab • Uniform quality of construction • Negligible maintenance • Faster completion
  • 17. DISADVANTAGES • Because of few small sizes finishing lines are seen on the concrete surfaces • Services after completing become slightly difficult due to the small width of components • It requires uniform planning as well as uniform elevations to be cost effective • The formwork requires number of spacer, wall ties etc. which are placed @ 2ft c/c; these produce problems such as seepage, leakages during monsoon • Due to box-type construction, contraction cracks are likely to appear • Heat of hydration is high due to shear walls • It is rigid in design once placed, as any alteration becomes tough later
  • 18. AAC BLOCKS What is AAC? • Autoclaved aerated concrete (AAC), also known as autoclaved cellular concrete (ACC), autoclaved lightweight concrete (ALC), autoclaved concrete, cellular concrete, porous concrete, Ytong, Hebel Block, Aircrete, Thermalite. When was AAC first developed? • AAC was developed in 1924 by a Swedish architect, who was looking for an alternate building material with properties similar to that of wood – good thermal insulation, solid structure and easy to work with – but without the disadvantage of combustibility, decay and termite damage. It has been refined into a highly thermally insulating concrete-based material used for both internal and external construction. • AAC products include blocks, wall panels, floor and roof panels, and lintels.
  • 19. • AAC has been produced for more than 70 years, and it offers several significant advantages over other cement construction materials, one of the most important being its lower environmental impact. • Improved thermal efficiency reduces the heating and cooling load in buildings. • Workability allows accurate cutting, which minimizes the generation of solid waste during use. • Light weight saves cost & energy in transportation. • Light weight saves labour expenses. • Light weight increases chances of survival during seismic activity.
  • 20. ADVANTAGES • Termite/Pest Resistant • Cost Effective • Easy Workability and Design Flexibility • Thermally Insulated & Energy Efficient • Fire Resistant • Eco-friendly
  • 21. RAW MATERIALS SR. NO. RAW MATERIALS RATIO 1 FLY ASH 65 – 70 % 2 LIME 8 – 12 % 3 CEMENT 10 – 15 % 4 GYPSUM 0.5 – 5 % 5 ALUMINIUM POWDER 0.5 %
  • 22. PROCESS OF LAYING AAC BLOCKS
  • 23.