SlideShare a Scribd company logo
SLIP FORM CONSTRUCTION
BY :
14BCL034
14BCL048
14BCL061
14BCL128
1. Introduction
2. Slip form
INDEX
i. Introduction
ii. Procedure
iii.Types of slip form
iv.Advantage
v. Precautions
vi.Application of
slip form
Introduction
• Slip-form Technique is one of the most productive techniques for
construction of High-rise structures like communication towers,
chimneys, bridge piers, silos etc.
• Vertical Slip forming allows concrete to be erected as a monolithic or
a joint-less structure, while reducing overall project duration.
Slipform paving has enabled concrete road pavements, airport
aprons, taxiways, runways, canal lining etc.
• Slip-form Technique has also been successfully applied to various
structures including offshore drilling platforms and nuclear facilities
etc.
• Slip form construction, or
continuously formed construction,
is a construction method in which
concrete is poured into a
continuously moving form.
• Basically, this method involves the
continuous placing of concrete in a
shallow mould having the same
plan as the building to be
constructed. This rigid mould, or
"slip-form" as it is called, forms the
working deck which is jacked
slowly upwards at a controlled rate
until the required elevation is
reached.
Introduction
•Method of vertically extruding a
reinforced concrete section and is
suitable for construction of core walls
in high-rise structures – lift shafts,
stair shafts, towers.
•The formwork rises continuously, at a
rate of about 300 mm per hour,
supporting itself on the core and not
relying on support or access from
other parts of the building or
permanent works.
SLIP FORM
TECHNOLOGY
• Allows for the continuous pouring
of concrete into walls of a
structure and only stops when the
full required height of the
structure has been reached.
• The height of the formwork is
designed in such a way that while
the top of the formwork is being
filled by concrete the lowest layer
of concrete poured earlier has
already gained an initial set. When
the formwork is moved upwards
the concrete that is then exposed
remains firm.
Slip Form
Technology
Procedure
• Assembly can only start once the
foundations are in place and the
wall starter is in correct
alignment.
• Slip form shuttering is aligned
with the help of yokes.
• Horizontal crossbeams connect
these yokes.
• Hydraulic jacks are attached to
these crossbeams for
simultaneous upward movement.
• Height of the slip form ranges
from 1.1 to 1.5 meters.
• Yokes and crossbeams also used to
support the working platform.
• Structure should be rigid and shape
maintained at all times.
• Make sure there is no lag or else it
prevents the structure from free
upward movement
• It is also possible to reduce wall
thicknesses
• as the construction gains height and
arrangements have to be made in the
slip form structure that will enable
such reduction at regular intervals.
Procedure
 It is necessary to use a low slump concrete in slip forming processes where the
formwork is moved horizontally in order for the slab or pavement to retain its
shape as the paving machine advances.
 Presently, slip form pavements use "high early strength" concrete, which
achieves the required strength in approximately 12 hours, as compared to
conventional concrete which requires 5-14 days.
 The water content of this type of concrete is lower than it is for standard
material, resulting in improved strength as well as improved resistance to the
permeation of salt, thereby increasing the finished concrete's resistance to
deterioration from chloride ions.
Structural Concerns
1. VERTICAL SLIP-FORM
In vertical slip forming, the
concrete form may be surrounded
by a platform on which workers
stand, placing steel reinforcing rods
into the concrete and ensuring a
smooth pour. Together, the concrete
form and working platform are
raised by means of hydraulic jacks.
Generally, the slip-form rises at a
rate which permits the concrete to
harden by the time it emerges from
the bottom of the form.
TYPES OF SLIP-FORM
CONSTRUCTION
2. HORIZONTAL SLIP-FORM
In horizontal slip forming for
pavement and traffic separation walls,
concrete is cast, vibrated, worked, and
settled in place while the form itself
slowly moves ahead. This method was
initially devised and utilized in
Interstate Highway construction
initiated during the 1950s.
• Slip form methods of construction can also be adapted to horizontal structures
and are used for paving, canals, and tunneling.
• The technique is more in use for structures that have continuous walls
like silos , chimneys, and piers for very tall bridges.
• It has also been successfully used for construction of buildings, although this
requires the manner of leaving inserts for openings like doors and windows to
be decided well in advance, as well as also any necessary inserts to support
floor slabs after the walls are constructed.
HORIZONTAL SLIP FORM
3. TAPERED SLIP-FORMING
• Slip-forming is also used in the
construction of conical chimneys,
cooling towers, piers and other tall
concrete structures involving constant
or changing thicknesses in walls,
diameters and/or shapes.
• A form is used with sections which
overlap so that one gradually slides over
the other. This is commonly done in
chimney construction but it is not
satisfactory for architectural concrete
because the lap shows.
• While the tapered slip-forming process
is similar to that used on the standard
slip-forming, it requires greater
attention, contractor experience and
expertise ensures the success of such
projects.
ADVANTAGES
•A major cost of concrete structure
construction is the required formwork
to retain the concrete till it can be
safely de-shuttered and be able to
support itself and other imposed
loads.
•The formwork needs to be
continually removed to newer
locations and then re-erected.
•Continuous use of manpower and
lifting equipment like cranes.
• In the case of slip form building, the
formwork is erected only once and
remains intact until the entire
structure is completed.
• Great reduction in the cost of
formwork as well as time saving for
re-erection.
• Cost effective
• The reduction in the movement of
formwork and workers also leads
to far more safe working conditions
that also make it a major advantage.
Advantages
PRECAUTIONS
• Concrete is continuously protected against
loss of moisture and rapid temperature
changes for 7 days
• Unhardened concrete is protected from rain
and flowing water
• Prevent plastic shrinkage
• Plastic cracks are filled by injection of epoxy
resin.
APPLICATIONS
Slip-form construction is used for tall structures, such as towers, buildings,
and dams, as well as horizontal structures, such as roadway barriers. It
enables continuous, non-interrupted, cast-in-place joint-less concrete
structures which have superior performance characteristics over construction
methods using discrete form elements. Slip forming relies on the quick setting
properties of concrete, and requires a balance between quick-setting capacity
and workability.
King Abdul-Aziz Airport, Jeddah, Saudi
Arabia
Capital Gate Tower, Abu Dhabi, UAE
Thank You

More Related Content

What's hot

JUMP FORM WORK
JUMP FORM WORKJUMP FORM WORK
JUMP FORM WORK
Pranay Kumar Tode
 
1.1 box jacking
1.1 box jacking1.1 box jacking
1.1 box jacking
Bhalchandra Tankkar
 
Advance Formwork System (PERI FORMWORK SYSTEM)
Advance Formwork System (PERI FORMWORK SYSTEM)Advance Formwork System (PERI FORMWORK SYSTEM)
Advance Formwork System (PERI FORMWORK SYSTEM)
Bhishma Bhatti
 
Joints in concrete
Joints in concreteJoints in concrete
Joints in concrete
Aglaia Connect
 
Slabs and types
Slabs and typesSlabs and types
Slabs and types
Surhan Fatima
 
Pre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concretePre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concrete
Rajat Nainwal
 
Cofferdams
Cofferdams Cofferdams
Cofferdams
GAURAV. H .TANDON
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
Dr K M SONI
 
DEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUESDEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUES
Nirant Patel
 
FOOTING CONSTRUCTION
FOOTING CONSTRUCTIONFOOTING CONSTRUCTION
FOOTING CONSTRUCTION
Md Shadab
 
DEEP FOUNDATION
DEEP FOUNDATIONDEEP FOUNDATION
DEEP FOUNDATION
aframawal
 
Shotcrete
ShotcreteShotcrete
Shotcrete
MTarunkumarreddy
 
rapid walls- modular construction technology
rapid walls- modular construction technologyrapid walls- modular construction technology
rapid walls- modular construction technology
Anjith Augustine
 
Segmental bridge construction
Segmental bridge constructionSegmental bridge construction
Segmental bridge construction
Construction Tech. and Mgmt., VNIT Nagpur
 
Construction process''column,beam,slab''
Construction process''column,beam,slab''Construction process''column,beam,slab''
Construction process''column,beam,slab''
Nabeel Rajpoot
 
Shoring
ShoringShoring
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete9833356555
 
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
jay Rathod
 

What's hot (20)

JUMP FORM WORK
JUMP FORM WORKJUMP FORM WORK
JUMP FORM WORK
 
1.1 box jacking
1.1 box jacking1.1 box jacking
1.1 box jacking
 
Advance Formwork System (PERI FORMWORK SYSTEM)
Advance Formwork System (PERI FORMWORK SYSTEM)Advance Formwork System (PERI FORMWORK SYSTEM)
Advance Formwork System (PERI FORMWORK SYSTEM)
 
Joints in concrete
Joints in concreteJoints in concrete
Joints in concrete
 
Slabs and types
Slabs and typesSlabs and types
Slabs and types
 
Pre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concretePre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concrete
 
Cofferdams
Cofferdams Cofferdams
Cofferdams
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
 
DEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUESDEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUES
 
FOOTING CONSTRUCTION
FOOTING CONSTRUCTIONFOOTING CONSTRUCTION
FOOTING CONSTRUCTION
 
DEEP FOUNDATION
DEEP FOUNDATIONDEEP FOUNDATION
DEEP FOUNDATION
 
Shotcrete
ShotcreteShotcrete
Shotcrete
 
rapid walls- modular construction technology
rapid walls- modular construction technologyrapid walls- modular construction technology
rapid walls- modular construction technology
 
Segmental bridge construction
Segmental bridge constructionSegmental bridge construction
Segmental bridge construction
 
Construction process''column,beam,slab''
Construction process''column,beam,slab''Construction process''column,beam,slab''
Construction process''column,beam,slab''
 
Concrete equipment
Concrete equipmentConcrete equipment
Concrete equipment
 
Shoring
ShoringShoring
Shoring
 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete
 
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
 
Design of masonry structures 2004
Design of masonry structures 2004Design of masonry structures 2004
Design of masonry structures 2004
 

Similar to Slip form Construction Technology

Building construction report
Building construction  reportBuilding construction  report
Building construction report
Aprajeeta Singh
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
Axay Sharma
 
Construction Technology
Construction TechnologyConstruction Technology
Construction Technology
SwapnilGorade1
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
ErankajKumar
 
simplex infrastructure
simplex infrastructure simplex infrastructure
simplex infrastructure
Shubham Pradhan
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
KHUSHBU SHAH
 
Construction portfolio (manvi)
Construction portfolio (manvi)Construction portfolio (manvi)
Construction portfolio (manvi)
ManviVarshney2
 
Lift form slab construction
Lift form slab constructionLift form slab construction
Lift form slab construction
tivar rose
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
varun km
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated Column
Anees Khan
 
Form-woks-additional.pptx
Form-woks-additional.pptxForm-woks-additional.pptx
Form-woks-additional.pptx
ssuserc0bf9b
 
Balanced Cantilever Bridge
Balanced Cantilever BridgeBalanced Cantilever Bridge
Balanced Cantilever Bridge
Jeelkumar Patel
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle Slab
Akshay Gawade
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALS
SOUMYA KHANDELWAL
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdf
GourhariBiswas1
 
Super Structure Construction.pptx
Super Structure Construction.pptxSuper Structure Construction.pptx
Super Structure Construction.pptx
Ananthakumar75
 
Ct2 Precast concrete piles
Ct2 Precast concrete pilesCt2 Precast concrete piles
Ct2 Precast concrete piles
Sze Ting Kuek
 
CT2 Group Presentation
CT2 Group PresentationCT2 Group Presentation
CT2 Group Presentation
bee_by
 
Bridges in Hilly areas seminar
Bridges in Hilly areas seminarBridges in Hilly areas seminar
Bridges in Hilly areas seminar
Abhinav Pateriya
 

Similar to Slip form Construction Technology (20)

Building construction report
Building construction  reportBuilding construction  report
Building construction report
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
 
Construction Technology
Construction TechnologyConstruction Technology
Construction Technology
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
simplex infrastructure
simplex infrastructure simplex infrastructure
simplex infrastructure
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
Construction portfolio (manvi)
Construction portfolio (manvi)Construction portfolio (manvi)
Construction portfolio (manvi)
 
Lift form slab construction
Lift form slab constructionLift form slab construction
Lift form slab construction
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated Column
 
Form-woks-additional.pptx
Form-woks-additional.pptxForm-woks-additional.pptx
Form-woks-additional.pptx
 
Balanced Cantilever Bridge
Balanced Cantilever BridgeBalanced Cantilever Bridge
Balanced Cantilever Bridge
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle Slab
 
Jump Formwork
Jump FormworkJump Formwork
Jump Formwork
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALS
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdf
 
Super Structure Construction.pptx
Super Structure Construction.pptxSuper Structure Construction.pptx
Super Structure Construction.pptx
 
Ct2 Precast concrete piles
Ct2 Precast concrete pilesCt2 Precast concrete piles
Ct2 Precast concrete piles
 
CT2 Group Presentation
CT2 Group PresentationCT2 Group Presentation
CT2 Group Presentation
 
Bridges in Hilly areas seminar
Bridges in Hilly areas seminarBridges in Hilly areas seminar
Bridges in Hilly areas seminar
 

Recently uploaded

6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
zwunae
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
dxobcob
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
bhadouriyakaku
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
PauloRodrigues104553
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Ethernet Routing and switching chapter 1.ppt
Ethernet Routing and switching chapter 1.pptEthernet Routing and switching chapter 1.ppt
Ethernet Routing and switching chapter 1.ppt
azkamurat
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
ihlasbinance2003
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
nooriasukmaningtyas
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
Kamal Acharya
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 

Recently uploaded (20)

6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Ethernet Routing and switching chapter 1.ppt
Ethernet Routing and switching chapter 1.pptEthernet Routing and switching chapter 1.ppt
Ethernet Routing and switching chapter 1.ppt
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 

Slip form Construction Technology

  • 1. SLIP FORM CONSTRUCTION BY : 14BCL034 14BCL048 14BCL061 14BCL128
  • 2. 1. Introduction 2. Slip form INDEX i. Introduction ii. Procedure iii.Types of slip form iv.Advantage v. Precautions vi.Application of slip form
  • 3. Introduction • Slip-form Technique is one of the most productive techniques for construction of High-rise structures like communication towers, chimneys, bridge piers, silos etc. • Vertical Slip forming allows concrete to be erected as a monolithic or a joint-less structure, while reducing overall project duration. Slipform paving has enabled concrete road pavements, airport aprons, taxiways, runways, canal lining etc. • Slip-form Technique has also been successfully applied to various structures including offshore drilling platforms and nuclear facilities etc.
  • 4. • Slip form construction, or continuously formed construction, is a construction method in which concrete is poured into a continuously moving form. • Basically, this method involves the continuous placing of concrete in a shallow mould having the same plan as the building to be constructed. This rigid mould, or "slip-form" as it is called, forms the working deck which is jacked slowly upwards at a controlled rate until the required elevation is reached. Introduction
  • 5. •Method of vertically extruding a reinforced concrete section and is suitable for construction of core walls in high-rise structures – lift shafts, stair shafts, towers. •The formwork rises continuously, at a rate of about 300 mm per hour, supporting itself on the core and not relying on support or access from other parts of the building or permanent works. SLIP FORM TECHNOLOGY
  • 6. • Allows for the continuous pouring of concrete into walls of a structure and only stops when the full required height of the structure has been reached. • The height of the formwork is designed in such a way that while the top of the formwork is being filled by concrete the lowest layer of concrete poured earlier has already gained an initial set. When the formwork is moved upwards the concrete that is then exposed remains firm. Slip Form Technology
  • 7. Procedure • Assembly can only start once the foundations are in place and the wall starter is in correct alignment. • Slip form shuttering is aligned with the help of yokes. • Horizontal crossbeams connect these yokes. • Hydraulic jacks are attached to these crossbeams for simultaneous upward movement. • Height of the slip form ranges from 1.1 to 1.5 meters.
  • 8. • Yokes and crossbeams also used to support the working platform. • Structure should be rigid and shape maintained at all times. • Make sure there is no lag or else it prevents the structure from free upward movement • It is also possible to reduce wall thicknesses • as the construction gains height and arrangements have to be made in the slip form structure that will enable such reduction at regular intervals. Procedure
  • 9.
  • 10.  It is necessary to use a low slump concrete in slip forming processes where the formwork is moved horizontally in order for the slab or pavement to retain its shape as the paving machine advances.  Presently, slip form pavements use "high early strength" concrete, which achieves the required strength in approximately 12 hours, as compared to conventional concrete which requires 5-14 days.  The water content of this type of concrete is lower than it is for standard material, resulting in improved strength as well as improved resistance to the permeation of salt, thereby increasing the finished concrete's resistance to deterioration from chloride ions. Structural Concerns
  • 11. 1. VERTICAL SLIP-FORM In vertical slip forming, the concrete form may be surrounded by a platform on which workers stand, placing steel reinforcing rods into the concrete and ensuring a smooth pour. Together, the concrete form and working platform are raised by means of hydraulic jacks. Generally, the slip-form rises at a rate which permits the concrete to harden by the time it emerges from the bottom of the form. TYPES OF SLIP-FORM CONSTRUCTION
  • 12. 2. HORIZONTAL SLIP-FORM In horizontal slip forming for pavement and traffic separation walls, concrete is cast, vibrated, worked, and settled in place while the form itself slowly moves ahead. This method was initially devised and utilized in Interstate Highway construction initiated during the 1950s.
  • 13. • Slip form methods of construction can also be adapted to horizontal structures and are used for paving, canals, and tunneling. • The technique is more in use for structures that have continuous walls like silos , chimneys, and piers for very tall bridges. • It has also been successfully used for construction of buildings, although this requires the manner of leaving inserts for openings like doors and windows to be decided well in advance, as well as also any necessary inserts to support floor slabs after the walls are constructed. HORIZONTAL SLIP FORM
  • 14. 3. TAPERED SLIP-FORMING • Slip-forming is also used in the construction of conical chimneys, cooling towers, piers and other tall concrete structures involving constant or changing thicknesses in walls, diameters and/or shapes. • A form is used with sections which overlap so that one gradually slides over the other. This is commonly done in chimney construction but it is not satisfactory for architectural concrete because the lap shows. • While the tapered slip-forming process is similar to that used on the standard slip-forming, it requires greater attention, contractor experience and expertise ensures the success of such projects.
  • 15. ADVANTAGES •A major cost of concrete structure construction is the required formwork to retain the concrete till it can be safely de-shuttered and be able to support itself and other imposed loads. •The formwork needs to be continually removed to newer locations and then re-erected. •Continuous use of manpower and lifting equipment like cranes.
  • 16. • In the case of slip form building, the formwork is erected only once and remains intact until the entire structure is completed. • Great reduction in the cost of formwork as well as time saving for re-erection. • Cost effective • The reduction in the movement of formwork and workers also leads to far more safe working conditions that also make it a major advantage. Advantages
  • 17. PRECAUTIONS • Concrete is continuously protected against loss of moisture and rapid temperature changes for 7 days • Unhardened concrete is protected from rain and flowing water • Prevent plastic shrinkage • Plastic cracks are filled by injection of epoxy resin.
  • 18. APPLICATIONS Slip-form construction is used for tall structures, such as towers, buildings, and dams, as well as horizontal structures, such as roadway barriers. It enables continuous, non-interrupted, cast-in-place joint-less concrete structures which have superior performance characteristics over construction methods using discrete form elements. Slip forming relies on the quick setting properties of concrete, and requires a balance between quick-setting capacity and workability. King Abdul-Aziz Airport, Jeddah, Saudi Arabia
  • 19. Capital Gate Tower, Abu Dhabi, UAE