SlideShare a Scribd company logo
STORAGE AND SAFETY PRECAUTIONS [IS: 7969-1975]
In any construction project the material cost constitute about 60 % of the
total project cost. Therefore, materials should be used effectively by reducing
wastage of materials to minimise the project cost. The wastage of material is
mainly due to pilferage, fire, deterioration etc. The store keeper is responsible
for the safety of materials in the store.
The following precautions should be taken for the safety of materials.
1. Timber and plywood should be stacked separately
2. There should be sufficient gap between two stacks of material to avoid
damage during fire.
3. Smoking and open fire should be prohibited.
4. Petroleum products (i.e. petrol, diesel, oil) should be stored separately.
5. Only limited stock of petroleum products should be stored at the site.
6. Fire extinguishing equipments should be made available at the site.
7. Explosives should be stored and handled separately and very carefully.
8. Wastage of cement, sand, aggregate should be prevented.
2
STACKING AND STORAGE OF CONSTRUCTION MATERIALS
Usually large quantities of construction materials have to be stored at
the sites of construction. Thus to prepare a proper job layout at site, it
is neccerry to know the correct method of storing materials at site
Points to be Considered while storing materials at site :
Following points should be kept in mind while storing materials at site.
1. Materials should be stored in such a way that they are not affected
wind or by impurities or by atmospheric agencies such as sun,
moisture etc
2. Cement should be stored in covered sheds.
3.The plinth level of the shed should be at least one metre higher than
the adjoining ground.
4.The cement bags should be stacked on a raised platform of bricks or
on plants about 15 to 20 cms above the shed floor.
5. The space between the walls and cement bags all-round should be
at least 30 cms.
3
6. The inflammable materials must be stored separately from
other combustible materials. This area should be specially
protected from fire hazards. In such area smoking should be
prohibited.
7. Explosives should be stored in a safe place, away from
combustible and inflammable materials under lock and key.
8. Materials of common use must be stored near the place of
their use to minimize the handling.
9. As far as possible materials used for similar purpose must be
stored close together.
10.Heavy items must be kept near the crane or hoist for ease in
handling.
4
5
6
7
Material Purchase procedure
Recognition of the need
Selection of source of supply
Inviting tenders
Analysis of tenders
Placing the order and follow up
Receipt and inspection
Approval of payment
8
Recognition of the need
When on the site, the stock of certain materials is
exhausted, the site engineer or supervisor or inventory
control clerk send a purchase requisition to the purchase
department.
The purchase requisition contains the following details :
•material to be purchased
•quantity of material required
9
10
2. Selection of source of supply
The purchase department, prepares a list of suppliers of
different materials.
For the purchase of new items, the information regarding
suppliers are obtained from:
directories
catalogues
advertisements
exhibitions and fairs
11
3. Inviting quotations / tenders
Quotations/tenders are invited from the selected
suppliers. The following information is included in the tender:
quality of material, specifications, drawings
quantity of material
time limit for delivery of material
EMD
Conditions of purchase
Date, time and place of opening of tenders
12
13
14
4. Analysis of Quotations
The tenders received within stipulated time limit are opened in the
office of the purchase officer on date and time mentioned in the
tender notice.
A comparative statement is prepared. The analysis of comparative
statement is done keeping in mind the following points.
Material cost
Specifications
Delivery place
Delivery period
Taxes
Payment terms and conditions
Guarantee period etc
15
16
17
Placing the order and follow-up
After studying the comparative statement precisely, the best supplier is selected.
When all other conditions are same, the lowest tender is selected.
The lowest tenderer may not be always the best. Therefore, while selecting the
supplier the rates quoted by him, specifications, quality of materials, sales tax,
transportation fares, image of the supplier etc. should also be considered.
As per the purchase policy the total supply order may be split up
among two-three suppliers or local supplier may be given preference.
Number of copies of the purchase order are prepared.
Two copies are given to the supplier and one copy to account section, store and
costing department each. After sending the purchase order, regular follow up is
required to get specified quantity of material on specified date.
18
19
20
Receipt and inspection
After receiving the materials at site its inspection and testing is
done. The receiving clerk prepares the material receive report
indicating the actual types and quantities of material received.
The receiving report is verified with the purchase order and any
change in the quantity of material is recorded.
The quality of material is checked. Any change in the specification
or quality of material is brought to the notice of the supplier.
The rates in the bill and tendered rates are also verified.
The material may be sent back if needed.
The receiving clerk prepare three copies of the receiving report.
One copy is given to the concerned department, one copy to the
supplier and one copy is retained by him.
21
Approval of Payment
Before approving the payment to the supplier the
bill is verified with the purchase order. The purpose
of such verification is to check any calculation error,
quality change or quantity change.
22
ECONOMIC ORDER QUANTITY - EOQ OR OPTIMUM LOT
SIZE
Economic order quantity’ is the order quantity of materials which
reduces the inventory cost.
For examples, let a construction company needs 12000 bags of
cement. The following options are there:-
1. All cement bags (12000) may be purchased at once.
2. Total quantity of cement bags may be purchased in two lots
6000 nos. each.
3. Every month 1000 bags are purchased for one year.
Out of the three options, the one which gives minimum material
cost is chosen.
Therefore, the size of order or a size of lot which reduces the
inventory cost is called “Economic order quantity”.
23
24
25
The graph shows relation between unit cost (cost period)
and order quantity (Q). Total cost = Inventory cost +
order cost
OM shows the Economic order quantity (EOQ).
At point ‘M* the total cost per period is minimum.
26
INSPECTION AND TESTING THE QUALITY OF MATERIAL
Inspection :
Inspection means the comparison of the actual sepcificatioris of any
material with its standard specifications. Inspection is an important
tool for measuring the quality of material and quality control.
Inspection is an art in which tests are conducted on material using
measuring equipments and it is decided whether the specifications of
the materials are within prescribed limit or not.
The following steps are involved in the inspection of any
construction :
1. collection of samples
2. taking dimensions and standards of material
3. inspection of layout, foundation etc..
4. inspection of various construction activities
5. laboratory testing
6. inspection of plants and equipments
7. checking records and reports 27
Objectives of Inspection :
1. To find defects in the production of material. The defects found during
inspection are brought to the notice of the concerned officer so that future
quality of product can be improved.
2.To see that the clients does not receive inferior quality materials.
3.To verify the quality of material.
4.To ensure that construction quality is not spoiled due to poor quality
materials.
Types of Inspection :
1. Dimensional inspection
2. Inspection for physical and
mechanical properties
3. Superficial inspection
4. Performance testing
5. Statistical methods 28
a) Inspection and testing of bricks
•Standard size of brick = 19 cm x 9 cm x 9 m
•For 20 bricks, the dimensions shall be as under :
Sr.
No.
Class
Lenth
cm
Width
cm
Height
cm
1. A 368 to 392 174 to 186 174 to 186
2.. B 350 to 410 165 to 195 165 to 195
Weight of one brick is about 2.5 kg.
For first class bricks water absorption should not be more than 20 %.
Compressive strength of bricks should not be less than 7.5 N/mm2.
Sub-Class A bricks :
tolerance limit ± 3%
rectangular faces,shrap edges, shall give clear ringing sound when
strike each other,
29
(b) Inspection and testing of cement
Field testing of cement is done as under :
•The colour of cement should be greenish - grey.
•When hand is inserted in a cement bag, it should give cool feeling.
•When rubbed between fingers, it should give smooth feeling.
•If handful of cement is thrown on the surface of water it should float for
sometime.
•Thick cement paste kept in water should set.
Criteria for Physical Properties of O.P.C. :
Fineness of Cement :
For O.P.C. - Not more than 10%
(Residue on 90 micron IS - Sieve)
For R. H. C. - not more than 5%
Setting time : (For OPC)
initial setting time - not less than 30 min.
final setting time - not more than 600 min.
Soundness :
not more than 10 mm Compressive strength :
30
Time
days
Minimum
Compressive
Strength N/mm2
3 16
7 22
28 33
(c) Inspection and testing of Fine and Coarse
Aggregate
IS : 383 - 1963, IS : 515 - 1959.
If size > 4.75 mm Coarse aggregate
If size < 4.75 mm fine aggregate
Water absorption test :
For C.A. - 0.5 to 1 %
For F.A. - 1 to 10 %
31
Fineness modulus of sand (FM) :
Type of Sand Value of F.M.
Fine Sand 2.2 - 2.6
Medium Sand 2.6 - 2.9
Coarse Sand 2.9 - 3.2
density of aggregates 2000 to 3000 kg/m.
Impact test :
For road aggregate ------ Impact value should be less than
30 %
For building aggregate------ Impact value should be less
than 45 %
32
(d) Reinforcement (IS : 1139, IS : 1786)
Normally in the construction mild steel (Fe 250) is used as distribute steel
and Tor steel Fe-415 is used as main steel in slab, beam, column etc
The steel reinforcement should be free from rust.
It should be free from oil, grease, paints etc.
33
34

More Related Content

What's hot

Introduction to manufacturing process
Introduction to manufacturing processIntroduction to manufacturing process
Introduction to manufacturing process
Maulana Abul Kalam Azad University of Technology
 
Process Planning & Cost Estimation
Process Planning & Cost EstimationProcess Planning & Cost Estimation
Process Planning & Cost Estimation
Prabhu Bose
 
PPCE Unit 4
PPCE Unit 4PPCE Unit 4
PPCE Unit 4
Aravind Ra
 
INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGINTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNING
SathishkumarM89
 
Unit 3
Unit 3Unit 3
Unit 3
Aravind Ra
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
Aditi Shah
 
Resource Management, Construction labour and labour acts, safety, labour prod...
Resource Management, Construction labour and labour acts, safety, labour prod...Resource Management, Construction labour and labour acts, safety, labour prod...
Resource Management, Construction labour and labour acts, safety, labour prod...
Amit Kumbar
 
Plant layout ppt by me
Plant layout ppt by mePlant layout ppt by me
Plant layout ppt by me
Daisy Gonzales Ruiz
 
INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGINTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNING
SathishkumarM89
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
SathishkumarM89
 
Introduction for PPCE
 Introduction for PPCE Introduction for PPCE
Introduction for PPCE
tamilselvan rathinasamy
 
Team Optimus_IIM K
Team Optimus_IIM KTeam Optimus_IIM K
Team Optimus_IIM K
Pravin Bokil
 
Process Planning & Cost Estimation
Process Planning & Cost Estimation Process Planning & Cost Estimation
Process Planning & Cost Estimation
Prabhu Bose
 
Process planning and cost estimation unit v
Process planning and cost estimation  unit   vProcess planning and cost estimation  unit   v
Process planning and cost estimation unit v
s Kumaravel
 
Plant Location Selection Decision
Plant Location Selection DecisionPlant Location Selection Decision
Plant Location Selection Decision
Yamini Kahaliya
 

What's hot (15)

Introduction to manufacturing process
Introduction to manufacturing processIntroduction to manufacturing process
Introduction to manufacturing process
 
Process Planning & Cost Estimation
Process Planning & Cost EstimationProcess Planning & Cost Estimation
Process Planning & Cost Estimation
 
PPCE Unit 4
PPCE Unit 4PPCE Unit 4
PPCE Unit 4
 
INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGINTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNING
 
Unit 3
Unit 3Unit 3
Unit 3
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
Resource Management, Construction labour and labour acts, safety, labour prod...
Resource Management, Construction labour and labour acts, safety, labour prod...Resource Management, Construction labour and labour acts, safety, labour prod...
Resource Management, Construction labour and labour acts, safety, labour prod...
 
Plant layout ppt by me
Plant layout ppt by mePlant layout ppt by me
Plant layout ppt by me
 
INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGINTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNING
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
 
Introduction for PPCE
 Introduction for PPCE Introduction for PPCE
Introduction for PPCE
 
Team Optimus_IIM K
Team Optimus_IIM KTeam Optimus_IIM K
Team Optimus_IIM K
 
Process Planning & Cost Estimation
Process Planning & Cost Estimation Process Planning & Cost Estimation
Process Planning & Cost Estimation
 
Process planning and cost estimation unit v
Process planning and cost estimation  unit   vProcess planning and cost estimation  unit   v
Process planning and cost estimation unit v
 
Plant Location Selection Decision
Plant Location Selection DecisionPlant Location Selection Decision
Plant Location Selection Decision
 

Similar to Material management

Sampling of cement & its tests
Sampling of cement & its testsSampling of cement & its tests
Sampling of cement & its tests
Kundan Sanap
 
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Mayur Rahangdale
 
Quality Control- Timber & Structural Steel
Quality Control- Timber & Structural SteelQuality Control- Timber & Structural Steel
Quality Control- Timber & Structural Steel
Pawan Kumar
 
Practical-of-Construction-Material.pptx
Practical-of-Construction-Material.pptxPractical-of-Construction-Material.pptx
Practical-of-Construction-Material.pptx
LaxmiNarayanGurung
 
Top 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteTop 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at Site
SHAZEBALIKHAN1
 
Quality Outlook BDP2031.pptx
Quality Outlook BDP2031.pptxQuality Outlook BDP2031.pptx
Quality Outlook BDP2031.pptx
NajeehAli1
 
Ppt summer presentation on finishing Of Police Station Construction Site
Ppt summer presentation on finishing Of Police Station Construction SitePpt summer presentation on finishing Of Police Station Construction Site
Ppt summer presentation on finishing Of Police Station Construction Site
Alok Mishra
 
HDPE LINING - TANKS (002).pptx
HDPE LINING - TANKS (002).pptxHDPE LINING - TANKS (002).pptx
HDPE LINING - TANKS (002).pptx
Ganesh725683
 
Fineness air permeability final (1)
Fineness air permeability final (1)Fineness air permeability final (1)
Fineness air permeability final (1)
Dave Madhav
 
Trial mixing concrete .pdf
Trial mixing concrete .pdfTrial mixing concrete .pdf
Trial mixing concrete .pdf
en21447648PereraWPDU
 
Nfmt vegas14 how to specify commercial flooring
Nfmt vegas14 how to specify commercial flooringNfmt vegas14 how to specify commercial flooring
Nfmt vegas14 how to specify commercial flooring
Lew Migliore
 
Webinar for manufacturers - HEB packaging - Dec 22.pdf
Webinar for manufacturers - HEB packaging - Dec 22.pdfWebinar for manufacturers - HEB packaging - Dec 22.pdf
Webinar for manufacturers - HEB packaging - Dec 22.pdf
DiamondFoodandBevera
 
Plant Layout- Ajinkya Malpe.pptx
Plant Layout- Ajinkya Malpe.pptxPlant Layout- Ajinkya Malpe.pptx
Plant Layout- Ajinkya Malpe.pptx
AjinkyaMalpe1
 
ioc_2
ioc_2ioc_2
Eqs unit 3 final
Eqs unit 3 finalEqs unit 3 final
Eqs unit 3 final
dhanapal143
 
Steps of final inspection and Report generation.
Steps of final inspection and Report generation. Steps of final inspection and Report generation.
Steps of final inspection and Report generation.
khalid ibn mahbub.
 
OPERATION MANAGEMENT paint project backup.pdf
OPERATION MANAGEMENT paint project backup.pdfOPERATION MANAGEMENT paint project backup.pdf
OPERATION MANAGEMENT paint project backup.pdf
bilal masood
 
Novel Polymer Shelves (See Projects Section on Linkedin)
Novel Polymer Shelves (See Projects Section on Linkedin)Novel Polymer Shelves (See Projects Section on Linkedin)
Novel Polymer Shelves (See Projects Section on Linkedin)
Mick Blackwell
 
Understanding the Vital Role of Bitumen Testing in Construction
Understanding the Vital Role of Bitumen Testing in ConstructionUnderstanding the Vital Role of Bitumen Testing in Construction
Understanding the Vital Role of Bitumen Testing in Construction
HEICO Dynamics Pvt. Ltd
 
PPT on GRP pipes and fittings - manufacturing and testing
PPT on GRP pipes and fittings - manufacturing and testingPPT on GRP pipes and fittings - manufacturing and testing
PPT on GRP pipes and fittings - manufacturing and testing
anoopmanoharan2
 

Similar to Material management (20)

Sampling of cement & its tests
Sampling of cement & its testsSampling of cement & its tests
Sampling of cement & its tests
 
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
 
Quality Control- Timber & Structural Steel
Quality Control- Timber & Structural SteelQuality Control- Timber & Structural Steel
Quality Control- Timber & Structural Steel
 
Practical-of-Construction-Material.pptx
Practical-of-Construction-Material.pptxPractical-of-Construction-Material.pptx
Practical-of-Construction-Material.pptx
 
Top 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteTop 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at Site
 
Quality Outlook BDP2031.pptx
Quality Outlook BDP2031.pptxQuality Outlook BDP2031.pptx
Quality Outlook BDP2031.pptx
 
Ppt summer presentation on finishing Of Police Station Construction Site
Ppt summer presentation on finishing Of Police Station Construction SitePpt summer presentation on finishing Of Police Station Construction Site
Ppt summer presentation on finishing Of Police Station Construction Site
 
HDPE LINING - TANKS (002).pptx
HDPE LINING - TANKS (002).pptxHDPE LINING - TANKS (002).pptx
HDPE LINING - TANKS (002).pptx
 
Fineness air permeability final (1)
Fineness air permeability final (1)Fineness air permeability final (1)
Fineness air permeability final (1)
 
Trial mixing concrete .pdf
Trial mixing concrete .pdfTrial mixing concrete .pdf
Trial mixing concrete .pdf
 
Nfmt vegas14 how to specify commercial flooring
Nfmt vegas14 how to specify commercial flooringNfmt vegas14 how to specify commercial flooring
Nfmt vegas14 how to specify commercial flooring
 
Webinar for manufacturers - HEB packaging - Dec 22.pdf
Webinar for manufacturers - HEB packaging - Dec 22.pdfWebinar for manufacturers - HEB packaging - Dec 22.pdf
Webinar for manufacturers - HEB packaging - Dec 22.pdf
 
Plant Layout- Ajinkya Malpe.pptx
Plant Layout- Ajinkya Malpe.pptxPlant Layout- Ajinkya Malpe.pptx
Plant Layout- Ajinkya Malpe.pptx
 
ioc_2
ioc_2ioc_2
ioc_2
 
Eqs unit 3 final
Eqs unit 3 finalEqs unit 3 final
Eqs unit 3 final
 
Steps of final inspection and Report generation.
Steps of final inspection and Report generation. Steps of final inspection and Report generation.
Steps of final inspection and Report generation.
 
OPERATION MANAGEMENT paint project backup.pdf
OPERATION MANAGEMENT paint project backup.pdfOPERATION MANAGEMENT paint project backup.pdf
OPERATION MANAGEMENT paint project backup.pdf
 
Novel Polymer Shelves (See Projects Section on Linkedin)
Novel Polymer Shelves (See Projects Section on Linkedin)Novel Polymer Shelves (See Projects Section on Linkedin)
Novel Polymer Shelves (See Projects Section on Linkedin)
 
Understanding the Vital Role of Bitumen Testing in Construction
Understanding the Vital Role of Bitumen Testing in ConstructionUnderstanding the Vital Role of Bitumen Testing in Construction
Understanding the Vital Role of Bitumen Testing in Construction
 
PPT on GRP pipes and fittings - manufacturing and testing
PPT on GRP pipes and fittings - manufacturing and testingPPT on GRP pipes and fittings - manufacturing and testing
PPT on GRP pipes and fittings - manufacturing and testing
 

More from KHUSHBU SHAH

PLANE TABLE SURVEY
PLANE TABLE SURVEYPLANE TABLE SURVEY
PLANE TABLE SURVEY
KHUSHBU SHAH
 
DEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKDEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORK
KHUSHBU SHAH
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
KHUSHBU SHAH
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge Engineering
KHUSHBU SHAH
 
Chapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackChapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway track
KHUSHBU SHAH
 
Chapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yardsChapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yards
KHUSHBU SHAH
 
Chapter 5 Introduction to railway
Chapter 5 Introduction to railwayChapter 5 Introduction to railway
Chapter 5 Introduction to railway
KHUSHBU SHAH
 
Chapter 4 Drainge and maintenance of road
Chapter 4 Drainge and maintenance of roadChapter 4 Drainge and maintenance of road
Chapter 4 Drainge and maintenance of road
KHUSHBU SHAH
 
Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometrics
KHUSHBU SHAH
 
Chapter 1 Introduction to road
Chapter 1 Introduction to roadChapter 1 Introduction to road
Chapter 1 Introduction to road
KHUSHBU SHAH
 
Labour management
Labour managementLabour management
Labour management
KHUSHBU SHAH
 
Chapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipmentsChapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipments
KHUSHBU SHAH
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
KHUSHBU SHAH
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavations
KHUSHBU SHAH
 
Chapter 3 caisson
Chapter 3 caissonChapter 3 caisson
Chapter 3 caisson
KHUSHBU SHAH
 
Chapter 2 coffer-dam
Chapter 2 coffer-damChapter 2 coffer-dam
Chapter 2 coffer-dam
KHUSHBU SHAH
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
KHUSHBU SHAH
 
Chapter 13 green building
Chapter 13 green buildingChapter 13 green building
Chapter 13 green building
KHUSHBU SHAH
 
Chapter 12 special treatments
Chapter 12 special treatmentsChapter 12 special treatments
Chapter 12 special treatments
KHUSHBU SHAH
 
Chapter 11 temporary works
Chapter 11 temporary worksChapter 11 temporary works
Chapter 11 temporary works
KHUSHBU SHAH
 

More from KHUSHBU SHAH (20)

PLANE TABLE SURVEY
PLANE TABLE SURVEYPLANE TABLE SURVEY
PLANE TABLE SURVEY
 
DEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKDEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORK
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge Engineering
 
Chapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackChapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway track
 
Chapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yardsChapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yards
 
Chapter 5 Introduction to railway
Chapter 5 Introduction to railwayChapter 5 Introduction to railway
Chapter 5 Introduction to railway
 
Chapter 4 Drainge and maintenance of road
Chapter 4 Drainge and maintenance of roadChapter 4 Drainge and maintenance of road
Chapter 4 Drainge and maintenance of road
 
Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometrics
 
Chapter 1 Introduction to road
Chapter 1 Introduction to roadChapter 1 Introduction to road
Chapter 1 Introduction to road
 
Labour management
Labour managementLabour management
Labour management
 
Chapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipmentsChapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipments
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavations
 
Chapter 3 caisson
Chapter 3 caissonChapter 3 caisson
Chapter 3 caisson
 
Chapter 2 coffer-dam
Chapter 2 coffer-damChapter 2 coffer-dam
Chapter 2 coffer-dam
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
 
Chapter 13 green building
Chapter 13 green buildingChapter 13 green building
Chapter 13 green building
 
Chapter 12 special treatments
Chapter 12 special treatmentsChapter 12 special treatments
Chapter 12 special treatments
 
Chapter 11 temporary works
Chapter 11 temporary worksChapter 11 temporary works
Chapter 11 temporary works
 

Recently uploaded

Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
Nada Hikmah
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
shadow0702a
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
gowrishankartb2005
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
Data Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptxData Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptx
ramrag33
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
21UME003TUSHARDEB
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
PKavitha10
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
Prakhyath Rai
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
AjmalKhan50578
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
VANDANAMOHANGOUDA
 
AI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptxAI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptx
architagupta876
 

Recently uploaded (20)

Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
Data Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptxData Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptx
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
 
AI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptxAI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptx
 

Material management

  • 1.
  • 2. STORAGE AND SAFETY PRECAUTIONS [IS: 7969-1975] In any construction project the material cost constitute about 60 % of the total project cost. Therefore, materials should be used effectively by reducing wastage of materials to minimise the project cost. The wastage of material is mainly due to pilferage, fire, deterioration etc. The store keeper is responsible for the safety of materials in the store. The following precautions should be taken for the safety of materials. 1. Timber and plywood should be stacked separately 2. There should be sufficient gap between two stacks of material to avoid damage during fire. 3. Smoking and open fire should be prohibited. 4. Petroleum products (i.e. petrol, diesel, oil) should be stored separately. 5. Only limited stock of petroleum products should be stored at the site. 6. Fire extinguishing equipments should be made available at the site. 7. Explosives should be stored and handled separately and very carefully. 8. Wastage of cement, sand, aggregate should be prevented. 2
  • 3. STACKING AND STORAGE OF CONSTRUCTION MATERIALS Usually large quantities of construction materials have to be stored at the sites of construction. Thus to prepare a proper job layout at site, it is neccerry to know the correct method of storing materials at site Points to be Considered while storing materials at site : Following points should be kept in mind while storing materials at site. 1. Materials should be stored in such a way that they are not affected wind or by impurities or by atmospheric agencies such as sun, moisture etc 2. Cement should be stored in covered sheds. 3.The plinth level of the shed should be at least one metre higher than the adjoining ground. 4.The cement bags should be stacked on a raised platform of bricks or on plants about 15 to 20 cms above the shed floor. 5. The space between the walls and cement bags all-round should be at least 30 cms. 3
  • 4. 6. The inflammable materials must be stored separately from other combustible materials. This area should be specially protected from fire hazards. In such area smoking should be prohibited. 7. Explosives should be stored in a safe place, away from combustible and inflammable materials under lock and key. 8. Materials of common use must be stored near the place of their use to minimize the handling. 9. As far as possible materials used for similar purpose must be stored close together. 10.Heavy items must be kept near the crane or hoist for ease in handling. 4
  • 5. 5
  • 6. 6
  • 7. 7
  • 8. Material Purchase procedure Recognition of the need Selection of source of supply Inviting tenders Analysis of tenders Placing the order and follow up Receipt and inspection Approval of payment 8
  • 9. Recognition of the need When on the site, the stock of certain materials is exhausted, the site engineer or supervisor or inventory control clerk send a purchase requisition to the purchase department. The purchase requisition contains the following details : •material to be purchased •quantity of material required 9
  • 10. 10
  • 11. 2. Selection of source of supply The purchase department, prepares a list of suppliers of different materials. For the purchase of new items, the information regarding suppliers are obtained from: directories catalogues advertisements exhibitions and fairs 11
  • 12. 3. Inviting quotations / tenders Quotations/tenders are invited from the selected suppliers. The following information is included in the tender: quality of material, specifications, drawings quantity of material time limit for delivery of material EMD Conditions of purchase Date, time and place of opening of tenders 12
  • 13. 13
  • 14. 14
  • 15. 4. Analysis of Quotations The tenders received within stipulated time limit are opened in the office of the purchase officer on date and time mentioned in the tender notice. A comparative statement is prepared. The analysis of comparative statement is done keeping in mind the following points. Material cost Specifications Delivery place Delivery period Taxes Payment terms and conditions Guarantee period etc 15
  • 16. 16
  • 17. 17
  • 18. Placing the order and follow-up After studying the comparative statement precisely, the best supplier is selected. When all other conditions are same, the lowest tender is selected. The lowest tenderer may not be always the best. Therefore, while selecting the supplier the rates quoted by him, specifications, quality of materials, sales tax, transportation fares, image of the supplier etc. should also be considered. As per the purchase policy the total supply order may be split up among two-three suppliers or local supplier may be given preference. Number of copies of the purchase order are prepared. Two copies are given to the supplier and one copy to account section, store and costing department each. After sending the purchase order, regular follow up is required to get specified quantity of material on specified date. 18
  • 19. 19
  • 20. 20
  • 21. Receipt and inspection After receiving the materials at site its inspection and testing is done. The receiving clerk prepares the material receive report indicating the actual types and quantities of material received. The receiving report is verified with the purchase order and any change in the quantity of material is recorded. The quality of material is checked. Any change in the specification or quality of material is brought to the notice of the supplier. The rates in the bill and tendered rates are also verified. The material may be sent back if needed. The receiving clerk prepare three copies of the receiving report. One copy is given to the concerned department, one copy to the supplier and one copy is retained by him. 21
  • 22. Approval of Payment Before approving the payment to the supplier the bill is verified with the purchase order. The purpose of such verification is to check any calculation error, quality change or quantity change. 22
  • 23. ECONOMIC ORDER QUANTITY - EOQ OR OPTIMUM LOT SIZE Economic order quantity’ is the order quantity of materials which reduces the inventory cost. For examples, let a construction company needs 12000 bags of cement. The following options are there:- 1. All cement bags (12000) may be purchased at once. 2. Total quantity of cement bags may be purchased in two lots 6000 nos. each. 3. Every month 1000 bags are purchased for one year. Out of the three options, the one which gives minimum material cost is chosen. Therefore, the size of order or a size of lot which reduces the inventory cost is called “Economic order quantity”. 23
  • 24. 24
  • 25. 25
  • 26. The graph shows relation between unit cost (cost period) and order quantity (Q). Total cost = Inventory cost + order cost OM shows the Economic order quantity (EOQ). At point ‘M* the total cost per period is minimum. 26
  • 27. INSPECTION AND TESTING THE QUALITY OF MATERIAL Inspection : Inspection means the comparison of the actual sepcificatioris of any material with its standard specifications. Inspection is an important tool for measuring the quality of material and quality control. Inspection is an art in which tests are conducted on material using measuring equipments and it is decided whether the specifications of the materials are within prescribed limit or not. The following steps are involved in the inspection of any construction : 1. collection of samples 2. taking dimensions and standards of material 3. inspection of layout, foundation etc.. 4. inspection of various construction activities 5. laboratory testing 6. inspection of plants and equipments 7. checking records and reports 27
  • 28. Objectives of Inspection : 1. To find defects in the production of material. The defects found during inspection are brought to the notice of the concerned officer so that future quality of product can be improved. 2.To see that the clients does not receive inferior quality materials. 3.To verify the quality of material. 4.To ensure that construction quality is not spoiled due to poor quality materials. Types of Inspection : 1. Dimensional inspection 2. Inspection for physical and mechanical properties 3. Superficial inspection 4. Performance testing 5. Statistical methods 28
  • 29. a) Inspection and testing of bricks •Standard size of brick = 19 cm x 9 cm x 9 m •For 20 bricks, the dimensions shall be as under : Sr. No. Class Lenth cm Width cm Height cm 1. A 368 to 392 174 to 186 174 to 186 2.. B 350 to 410 165 to 195 165 to 195 Weight of one brick is about 2.5 kg. For first class bricks water absorption should not be more than 20 %. Compressive strength of bricks should not be less than 7.5 N/mm2. Sub-Class A bricks : tolerance limit ± 3% rectangular faces,shrap edges, shall give clear ringing sound when strike each other, 29
  • 30. (b) Inspection and testing of cement Field testing of cement is done as under : •The colour of cement should be greenish - grey. •When hand is inserted in a cement bag, it should give cool feeling. •When rubbed between fingers, it should give smooth feeling. •If handful of cement is thrown on the surface of water it should float for sometime. •Thick cement paste kept in water should set. Criteria for Physical Properties of O.P.C. : Fineness of Cement : For O.P.C. - Not more than 10% (Residue on 90 micron IS - Sieve) For R. H. C. - not more than 5% Setting time : (For OPC) initial setting time - not less than 30 min. final setting time - not more than 600 min. Soundness : not more than 10 mm Compressive strength : 30
  • 31. Time days Minimum Compressive Strength N/mm2 3 16 7 22 28 33 (c) Inspection and testing of Fine and Coarse Aggregate IS : 383 - 1963, IS : 515 - 1959. If size > 4.75 mm Coarse aggregate If size < 4.75 mm fine aggregate Water absorption test : For C.A. - 0.5 to 1 % For F.A. - 1 to 10 % 31
  • 32. Fineness modulus of sand (FM) : Type of Sand Value of F.M. Fine Sand 2.2 - 2.6 Medium Sand 2.6 - 2.9 Coarse Sand 2.9 - 3.2 density of aggregates 2000 to 3000 kg/m. Impact test : For road aggregate ------ Impact value should be less than 30 % For building aggregate------ Impact value should be less than 45 % 32
  • 33. (d) Reinforcement (IS : 1139, IS : 1786) Normally in the construction mild steel (Fe 250) is used as distribute steel and Tor steel Fe-415 is used as main steel in slab, beam, column etc The steel reinforcement should be free from rust. It should be free from oil, grease, paints etc. 33
  • 34. 34