SlideShare a Scribd company logo
Control of Ground Water
in exCavation
S.S.A.S.I.T, SURAT GTU
advanCed ConStruCtion & eQuiPMentSadvanCed ConStruCtion & eQuiPMentS
(2160601)(2160601)
PrePared by:-PrePared by:-
MiSS. KhuShbu K. ShahMiSS. KhuShbu K. Shah
aSSt. ProfaSSt. Prof
S.S.a.S.i.t, SuratS.S.a.S.i.t, Surat
Content…
• Introduction
• Dewatering methods
• Suitability of different dewatering methods
Introduction
• Dewatering means removal of excess water from saturated
soil.
• Dewatering is a necessary process when it comes to
many construction projects, particularly when the
construction is for underground projects.
Dewatering Methods
• Factors such as the type of soil and the nature of the construction
site will all influence which dewatering method will be best suited
to the project.
1. Sumps And Ditches 6. Cement Grouting
2. Shallow Well System 7. Chemical Process
3. Deep Well System 8. Freezing Process
4. Well Point System 9. Electro-Osmosis Method
5. Vacuum Method
Sumps and Ditches
• It is the simplest and most commonly used
form of dewatering.
• In this method, shallow pits, called sumps are
dug along the periphery of the area and
connected by drains of semicircular in shape
and 20 cm diameter.
• The water from the slopes flows under
gravity and is collected in sumps from
which it is pumped out.
Shallow Well Dewatering
 A hole of 30 cm diameter or more is bored into the ground to a
depth not more than 10 m below the pump level. A strainer tube of 15 cm
diameter is lowered in the bore hole having a casing tube.
 A gravel filter is formed around the strainer tube by gradually
removing the casing tube and simultaneously pouring the filter well so
formed.
 The suction pipe from a number of such wells may be connected to one
common header connected to the pumping unit.
Shallow Well Dewatering
[A typical layout of a shallow well
system]
Deep Well Dewatering (Bored well system)
 This system is more suitable when the depth of excavation is more than the
16m or where artesian water is present.
 In this, 15 to 16 cm diameter hole is bored and a casing with a large screen is
provided. A row of well points is frequently installed at the toe of the side
slope of the deep excavation.
 A submersible pump is installed at the bottom of the well, of which the
casing generally has a minimum diameter of 150 mm. The discharge pipes
from the submersible pumps of a number of adjacent wells are connected to
a common delivery main. The water is raised from the well by a multi-staged
pump.
Deep Well Dewatering
[A typical layout of a deep well
system]
Well Point System
• The main components of a well-point system are:
1. well points
2. Riser pipe
3. Swinger arm
4. Header pipe
5. pumps
Well Point System
• The well point is perforated pipe 5 to 8 CM in dia & 1m long
covered by cylindrical wire gauge screen known as strainer.
 Pipes are jetted in the ground 1 to 2mt a part.
 Well point → riser pipe → swinger arm → header.
 It is suitable for lowering water table by 5 to 6 m in soil.
13
SINGLE WELLPOINT SYSTEM
14
Multi-Stage Well Point System
Multi-stage well point system is suitable for excavations up to 15
m.
When water table is greater than 6 m this method will use.
 In this method 2 or more rows of well point are installed at different
elevation.
 In this method wells are installed in 2 stages.
 In 1st stage water table lowered by 5 m.
 If required, then 3rd stage of well point can also be installed for further
lower water table.
 This method useful for up to 15 m. For up to 15th m deep well system
will use.
Multi-Stage Well Point System
17
MuLTI WELL POINT SYSTEM
Well Point System
Advantages:
•Installation is very rapid. The equipment is reasonably simple
and cheap.
•As water is filtered while removing from the ground, soil particles are
not washed away. Hence, there is no danger of subsidence of the
surrounding ground.
•As the water is drawn away by well points from the excavation, the
sides of excavation are stabilized and steeper side slopes can be
permitted.
Well Point System
Disadvantages:
•Single stage well point system is suitable for lowering water table by 5 to 6 m
only. For deeper excavations, where water table is to be lowered for a depth
greater than 6 m, multi-stage well point system is required.
•It is essential to continue pumping once it has been started until the
excavation is complete. If it is stopped in between, it may prove to be
disastrous.
•In case of the ground consisting of stiff clay, gravel or boulders, well points
are installed in drilled holes, which increases the installation cost.
Vacuum System
When draining is required for silt or clay which have size less than
0.05mm. That time vacuum pump system will require.
The process is as follows:
 The well-points are driven and 25 CM dia is provided around the well
point.
 Installed in the ground by forcing a jet of water under sufficient
pressure.
 The sand of medium to coarse size is then forced into
this hole as rapidly as possible. This sand forms the filter medium.
Vacuum System
In the upper most 600 mm to 900 mm, an impervious material
such as clay is tamped to form the seal the upper portion.
 The pumping is then carried out by means of equipment capable
of maintaining a vacuum in the well-points and the surrounding
filter.
 In this way, the pressure around the well-points is reduced to a
small fraction of the atmospheric pressure. The ground is acted
upon by the atmospheric pressure. Thus the soil becomes
consolidated under a pressure which is very nearly equal to the
atmospheric.
Vacuum System
In highly permeable cohesionless soil, the safety of the side slopes may be
endangered through the application of severe pumping. In such cases, especially if
control of the groundwater is required permanently, the methods of grouting can
be used.
The main idea is to insert fine materials or chemicals around the excavation in
order to reduce the hydraulic conductivity of the surrounding soil to a minimum.
In other words, the grouting process creates an almost impervious curtain around
the excavation. The grouting is conducted using movable pipes with holes. The
grout material is injected under pressure as it flows outside the pipes through the
holes to fill the voids of the surrounding soil.
The material used for grouting may be clay, cement or special chemical
compounds.
Control of Groundwater by Grouting
Cement Grouting
Cement Grouting
• The material commonly used for grout include:
1) Cement And Water
2) Cement, Rock Flour and Water
3) Cement, Clay and Water
4) Cement, Clay, Sand and Water
5) Asphalt
6) Clay And Water
7) Chemicals
Chemical Grouting
• The desirable properties of chemical grouts:
1)It must be able to modify the properties of soil as desired
2)It may either increase the strength or decrease the permeability of
soil
3)It must be cheap, non-toxic, non-explosive
4)It must be in the form of a liquid with low viscosity so that it can be
readily placed in the soil
5)It must be non-corrosive, so that it can be handled with
common pumps and piping
6)It must be possible to control the gel time by suitable means
Chemical Grouting
Inorganic chemicals
•Sodium silicate
•Calcium chloride
•Ligno-chrome
•Ligno sulphate
•They are called silicate grouts
•They are cheaper
Organic chemicals
•Epoxy resins
•Polyester resins
•They are also called resin grouts
•They possess advantage of low
viscosity, precise control of gel
time and high strength
 Soils that will not drain using conventional methods Typically a ground
freezing system consists of an array of freeze pipes.
 That are installed into the ground around the perimeter of the
excavation, usually in a circular pattern.
 A supermodel brine solution is pump through to freeze the pipes, which
freezes the water bearing soils around the pipes to create a frozen wall.
Extreme care must be taken to make sure that the freeze is complete
because any groundwater seepage though the wall or from below the
excavation depth will have a sliding effect.
FREEZING
PROCESS
GROUND FREEZING
34
GROUND FREEZING
The procedure:
 A refrigeration plant of required installed near the site of work.
 The large pipes of 100 mm to 150 mm diameter.
 The distance between the pipes is about 1 m to 1.50 m.
 The pipes are closed at the bottom.
 The small pipes of 25 mm to 50 mm diameter are inserted into the
large pipes.
 open at the bottom.
 The cold liquid at a temperature of about -23°C to -30°C is then
circulated through the circuit. The liquid comes through the small pipe
and goes up through the large pipe.
 This causes the ground to freeze around the pipes.
Electro-Osmosis Process
• This method is used for fine grained cohesive soils (such as clay), which can
be drained or stabilized using electric current. The method was developed by
L. Casagrande (1952).
• If direct current is passed between two electrodes driven into natural soil
mass, the soil water will travel` from the positive electrode (anode) to the
negative electrode (cathode). The cathode is made in the form of well point
or metal tube for pumping out the seeping form of well point or a metal tube
for pumping out the seeping water.
• A steel rod, a pipe or steel piling of excavation can serve as the cathode. The
arrangement of electrodes is done in such a way that the natural direction of
flow of water is reversed away from the excavation, thereby increasing the
strength of the soil and stability of the slope. The potentials generally used in
the process are from 40 to 180 volts, with electrode spacing of 4 to 5 meters.
Electro-Osmosis Process
The vibroflot is inserted into the ground and typically can be used to improve soil up
to depths of 150 feet. Vibroflotation utilizes water and the mechanical vibrations of
the vibroflot to move the particles into a denser state. Typical radial distances
affected range from 5 to 15 feet (Bauer Maschinen GmbH, 2012).
The vibroflot is suspended from a crane and seats on the surface of the ground that is
to be improved. To penetrate the material, the bottom jet is activated and the
vibration begins. The water saturates the material to create a “quick sand” condition
(i.e. temporarily liquefying the material), which allows the vibroflot to sink to the
desired depth of improvement.
At that point, the bottom jet is stopped and the water is transferred to the upper jet.
This is done to create a saturated environment surrounding the vibroflot, thereby
enhancing the compaction of the material. The vibroflot remains at the desired depth
of improvement until the material reaches adequate density.
Vibro flotation Process
The density of the soil is measured by using the power input (via the
electric current or hydraulic pressure) as an index. As the material
densifies, the vibroflot requires more power to continue vibrating at which
point pressure gauge displays a peak in required power.
Once this point is reached, the vibroflot is raised one lift (generally
ranging from 1 to 3 feet) and compaction ensues until the peak amperage
or hydraulic pressure is reached once again.
The vibroflotation process can offer the following benefits:
•When the process is done properly, it will reduce the possibility of differential settlements that
will improve the foundation condition of the proposed structure.
•It is the fastest and easiest way to improve soil when bottom layers of soil will not provide
good load bearing capacity.
•It is a great technology to improve harbor bottoms.
•On a cost-related standpoint, it helps improve thousands of cubic meters per day. It is faster
than piling.
•It can be done around existing structures without damaging them .
•It does not harm the environment. It improves the soil strata using its own characteristic
•No excavations are needed, reducing the hazards, contamination of soils and hauling material
out from the site.
Advantages
Suitability of Different Methods of Ground
Water Conditions
METHOD CONDITIONS FOR SUITABILITY
1. Sumps and Ditches For shallow excavations in coarse
grained soils.
2. Well point system Suitable for lowering water table by 5-6 m
in soils
3. Bored well system For coarse grained soils and depth of
excavation more than 16 m
4. Vacuum method Draining silty sands and fine sands
5. Cement grouting For coarse materials or rocks with
cracks
6. Freezing process Suitable for excavations in water logged
soils
7. Electro-osmosis process Suitable for fine grained cohesive soils
such as clays
Chapter 4 control of ground water in excavations

More Related Content

What's hot

Soil stabilisation (1)
Soil stabilisation (1)Soil stabilisation (1)
Soil stabilisation (1)
Safiullah Khan
 
Coffer dam and its type
Coffer dam and its typeCoffer dam and its type
Coffer dam and its type
Gaurang Kakadiya
 
Soil exploration part i
Soil exploration part  iSoil exploration part  i
Soil exploration part i
Avinash Kumar Gupta
 
Dewatering process and control in building projects
Dewatering process and control in building projectsDewatering process and control in building projects
Dewatering process and control in building projects
Umar Faruk
 
Grouting in Soils
Grouting in SoilsGrouting in Soils
Grouting in Soils
Shoaib Wani
 
Under reamed piles
Under reamed pilesUnder reamed piles
Under reamed piles
Chaitanya Raval
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
jamali husain
 
Caisson
CaissonCaisson
Caissons
Caissons Caissons
Field compaction methods
Field compaction methodsField compaction methods
Field compaction methods
Shivarajteggi
 
materials of sewer
materials of sewermaterials of sewer
materials of sewer
Manish Goyal
 
compaction equipment
compaction equipmentcompaction equipment
compaction equipment
shailesh chauhan
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
ajinkya gaikwad
 
Ground freezing
Ground freezing Ground freezing
Ground freezing
Mahesh Sharma
 
ELECTRO OSMOSIS METHOD OF DEWATERING
ELECTRO OSMOSIS METHOD OF DEWATERINGELECTRO OSMOSIS METHOD OF DEWATERING
ELECTRO OSMOSIS METHOD OF DEWATERING
TejaswiniNarayane
 
Reinforced soil
Reinforced soilReinforced soil
Reinforced soil
Mohit Goyal
 
Dampness in buildings
Dampness in buildingsDampness in buildings
Dampness in buildings
Ashar Gill
 
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITSDIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
Asaru Champ
 
Construction dewatering
Construction dewateringConstruction dewatering
Construction dewatering
Shubham Parab
 

What's hot (20)

Soil stabilisation (1)
Soil stabilisation (1)Soil stabilisation (1)
Soil stabilisation (1)
 
Coffer dam and its type
Coffer dam and its typeCoffer dam and its type
Coffer dam and its type
 
Soil exploration part i
Soil exploration part  iSoil exploration part  i
Soil exploration part i
 
Dewatering process and control in building projects
Dewatering process and control in building projectsDewatering process and control in building projects
Dewatering process and control in building projects
 
Grouting in Soils
Grouting in SoilsGrouting in Soils
Grouting in Soils
 
Under reamed piles
Under reamed pilesUnder reamed piles
Under reamed piles
 
Batching and mixing
Batching and mixingBatching and mixing
Batching and mixing
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
 
Caisson
CaissonCaisson
Caisson
 
Caissons
Caissons Caissons
Caissons
 
Field compaction methods
Field compaction methodsField compaction methods
Field compaction methods
 
materials of sewer
materials of sewermaterials of sewer
materials of sewer
 
compaction equipment
compaction equipmentcompaction equipment
compaction equipment
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
 
Ground freezing
Ground freezing Ground freezing
Ground freezing
 
ELECTRO OSMOSIS METHOD OF DEWATERING
ELECTRO OSMOSIS METHOD OF DEWATERINGELECTRO OSMOSIS METHOD OF DEWATERING
ELECTRO OSMOSIS METHOD OF DEWATERING
 
Reinforced soil
Reinforced soilReinforced soil
Reinforced soil
 
Dampness in buildings
Dampness in buildingsDampness in buildings
Dampness in buildings
 
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITSDIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
 
Construction dewatering
Construction dewateringConstruction dewatering
Construction dewatering
 

Similar to Chapter 4 control of ground water in excavations

5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
VATSAL PATEL
 
Excavation and Ground water control1.pptx
Excavation and Ground water control1.pptxExcavation and Ground water control1.pptx
Excavation and Ground water control1.pptx
ssusercbae26
 
dewateringtechniques 2.pptx
dewateringtechniques 2.pptxdewateringtechniques 2.pptx
dewateringtechniques 2.pptx
CarolTumaneng
 
BCT Module 5 ground water excavation PART 4
BCT Module 5 ground water excavation PART 4BCT Module 5 ground water excavation PART 4
BCT Module 5 ground water excavation PART 4
Shree Swami atmanand saraswati inst. of technology, surat
 
Presentation on well point system
Presentation on well point systemPresentation on well point system
Presentation on well point systemAnshuman Tyagi
 
Subsurface drainage
Subsurface drainageSubsurface drainage
Subsurface drainage
Chethan B J
 
DEWATERING METHODS IN DIFFERENT SOIL CONDITIONS
DEWATERING METHODS IN DIFFERENT SOIL CONDITIONSDEWATERING METHODS IN DIFFERENT SOIL CONDITIONS
DEWATERING METHODS IN DIFFERENT SOIL CONDITIONS
TejaswiniNarayane
 
Dewatering
DewateringDewatering
Dewatering
Madhusudhan Reddy
 
Design, layout and installation of drip and fertigation in precision farming
Design, layout and installation of drip and fertigation in precision farmingDesign, layout and installation of drip and fertigation in precision farming
Design, layout and installation of drip and fertigation in precision farming
Dr. M. Kumaresan Hort.
 
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water ControlWeek 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water Controlnik kin
 
UNIT 1a.pdf
UNIT 1a.pdfUNIT 1a.pdf
UNIT 1a.pdf
LovelyLavakumarLK
 
De watering-ppt
De watering-pptDe watering-ppt
De watering-ppt
Ghulam Mehdi Sahito
 
Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques
GAURAV. H .TANDON
 
5. Dewatering.pdf
5. Dewatering.pdf5. Dewatering.pdf
5. Dewatering.pdf
EmmanuelKiamaMutinda
 
Special Methods of Sub Surface Drainage: Agricultural Draining Engineering
Special Methods of Sub Surface Drainage: Agricultural Draining EngineeringSpecial Methods of Sub Surface Drainage: Agricultural Draining Engineering
Special Methods of Sub Surface Drainage: Agricultural Draining Engineering
Venkata Sai Kari
 
Control of ground water in excavations_Advanced Construction Technology (Seme...
Control of ground water in excavations_Advanced Construction Technology (Seme...Control of ground water in excavations_Advanced Construction Technology (Seme...
Control of ground water in excavations_Advanced Construction Technology (Seme...
A Makwana
 
Pumping Stations
Pumping StationsPumping Stations
Pumping Stations
GAURAV. H .TANDON
 
ppt foundation.pptx
ppt foundation.pptxppt foundation.pptx
ppt foundation.pptx
AnshuBarmase
 
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptx
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptxSewer joints of pipes, sewer appurtenances, storm water drainage.pptx
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptx
PriyaTalwar8
 
DEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATIONDEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATION
Shivananda Roy
 

Similar to Chapter 4 control of ground water in excavations (20)

5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
 
Excavation and Ground water control1.pptx
Excavation and Ground water control1.pptxExcavation and Ground water control1.pptx
Excavation and Ground water control1.pptx
 
dewateringtechniques 2.pptx
dewateringtechniques 2.pptxdewateringtechniques 2.pptx
dewateringtechniques 2.pptx
 
BCT Module 5 ground water excavation PART 4
BCT Module 5 ground water excavation PART 4BCT Module 5 ground water excavation PART 4
BCT Module 5 ground water excavation PART 4
 
Presentation on well point system
Presentation on well point systemPresentation on well point system
Presentation on well point system
 
Subsurface drainage
Subsurface drainageSubsurface drainage
Subsurface drainage
 
DEWATERING METHODS IN DIFFERENT SOIL CONDITIONS
DEWATERING METHODS IN DIFFERENT SOIL CONDITIONSDEWATERING METHODS IN DIFFERENT SOIL CONDITIONS
DEWATERING METHODS IN DIFFERENT SOIL CONDITIONS
 
Dewatering
DewateringDewatering
Dewatering
 
Design, layout and installation of drip and fertigation in precision farming
Design, layout and installation of drip and fertigation in precision farmingDesign, layout and installation of drip and fertigation in precision farming
Design, layout and installation of drip and fertigation in precision farming
 
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water ControlWeek 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
 
UNIT 1a.pdf
UNIT 1a.pdfUNIT 1a.pdf
UNIT 1a.pdf
 
De watering-ppt
De watering-pptDe watering-ppt
De watering-ppt
 
Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques
 
5. Dewatering.pdf
5. Dewatering.pdf5. Dewatering.pdf
5. Dewatering.pdf
 
Special Methods of Sub Surface Drainage: Agricultural Draining Engineering
Special Methods of Sub Surface Drainage: Agricultural Draining EngineeringSpecial Methods of Sub Surface Drainage: Agricultural Draining Engineering
Special Methods of Sub Surface Drainage: Agricultural Draining Engineering
 
Control of ground water in excavations_Advanced Construction Technology (Seme...
Control of ground water in excavations_Advanced Construction Technology (Seme...Control of ground water in excavations_Advanced Construction Technology (Seme...
Control of ground water in excavations_Advanced Construction Technology (Seme...
 
Pumping Stations
Pumping StationsPumping Stations
Pumping Stations
 
ppt foundation.pptx
ppt foundation.pptxppt foundation.pptx
ppt foundation.pptx
 
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptx
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptxSewer joints of pipes, sewer appurtenances, storm water drainage.pptx
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptx
 
DEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATIONDEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATION
 

More from KHUSHBU SHAH

PLANE TABLE SURVEY
PLANE TABLE SURVEYPLANE TABLE SURVEY
PLANE TABLE SURVEY
KHUSHBU SHAH
 
DEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKDEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORK
KHUSHBU SHAH
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
KHUSHBU SHAH
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge Engineering
KHUSHBU SHAH
 
Chapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackChapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway track
KHUSHBU SHAH
 
Chapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yardsChapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yards
KHUSHBU SHAH
 
Chapter 5 Introduction to railway
Chapter 5 Introduction to railwayChapter 5 Introduction to railway
Chapter 5 Introduction to railway
KHUSHBU SHAH
 
Chapter 4 Drainge and maintenance of road
Chapter 4 Drainge and maintenance of roadChapter 4 Drainge and maintenance of road
Chapter 4 Drainge and maintenance of road
KHUSHBU SHAH
 
Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometrics
KHUSHBU SHAH
 
Chapter 1 Introduction to road
Chapter 1 Introduction to roadChapter 1 Introduction to road
Chapter 1 Introduction to road
KHUSHBU SHAH
 
Equipment management
Equipment managementEquipment management
Equipment management
KHUSHBU SHAH
 
Labour management
Labour managementLabour management
Labour management
KHUSHBU SHAH
 
Material management
Material managementMaterial management
Material management
KHUSHBU SHAH
 
Chapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipmentsChapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipments
KHUSHBU SHAH
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
KHUSHBU SHAH
 
Chapter 3 caisson
Chapter 3 caissonChapter 3 caisson
Chapter 3 caisson
KHUSHBU SHAH
 
Chapter 2 coffer-dam
Chapter 2 coffer-damChapter 2 coffer-dam
Chapter 2 coffer-dam
KHUSHBU SHAH
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
KHUSHBU SHAH
 
Chapter 13 green building
Chapter 13 green buildingChapter 13 green building
Chapter 13 green building
KHUSHBU SHAH
 
Chapter 12 special treatments
Chapter 12 special treatmentsChapter 12 special treatments
Chapter 12 special treatments
KHUSHBU SHAH
 

More from KHUSHBU SHAH (20)

PLANE TABLE SURVEY
PLANE TABLE SURVEYPLANE TABLE SURVEY
PLANE TABLE SURVEY
 
DEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKDEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORK
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge Engineering
 
Chapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackChapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway track
 
Chapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yardsChapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yards
 
Chapter 5 Introduction to railway
Chapter 5 Introduction to railwayChapter 5 Introduction to railway
Chapter 5 Introduction to railway
 
Chapter 4 Drainge and maintenance of road
Chapter 4 Drainge and maintenance of roadChapter 4 Drainge and maintenance of road
Chapter 4 Drainge and maintenance of road
 
Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometrics
 
Chapter 1 Introduction to road
Chapter 1 Introduction to roadChapter 1 Introduction to road
Chapter 1 Introduction to road
 
Equipment management
Equipment managementEquipment management
Equipment management
 
Labour management
Labour managementLabour management
Labour management
 
Material management
Material managementMaterial management
Material management
 
Chapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipmentsChapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipments
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
Chapter 3 caisson
Chapter 3 caissonChapter 3 caisson
Chapter 3 caisson
 
Chapter 2 coffer-dam
Chapter 2 coffer-damChapter 2 coffer-dam
Chapter 2 coffer-dam
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
 
Chapter 13 green building
Chapter 13 green buildingChapter 13 green building
Chapter 13 green building
 
Chapter 12 special treatments
Chapter 12 special treatmentsChapter 12 special treatments
Chapter 12 special treatments
 

Recently uploaded

How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
Steve Thomason
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
Nguyen Thanh Tu Collection
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
GeoBlogs
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
EverAndrsGuerraGuerr
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
kaushalkr1407
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
Jheel Barad
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
GeoBlogs
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
PedroFerreira53928
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
bennyroshan06
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumers
PedroFerreira53928
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
Anna Sz.
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 

Recently uploaded (20)

How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumers
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 

Chapter 4 control of ground water in excavations

  • 1. Control of Ground Water in exCavation S.S.A.S.I.T, SURAT GTU advanCed ConStruCtion & eQuiPMentSadvanCed ConStruCtion & eQuiPMentS (2160601)(2160601) PrePared by:-PrePared by:- MiSS. KhuShbu K. ShahMiSS. KhuShbu K. Shah aSSt. ProfaSSt. Prof S.S.a.S.i.t, SuratS.S.a.S.i.t, Surat
  • 2. Content… • Introduction • Dewatering methods • Suitability of different dewatering methods
  • 3. Introduction • Dewatering means removal of excess water from saturated soil. • Dewatering is a necessary process when it comes to many construction projects, particularly when the construction is for underground projects.
  • 4. Dewatering Methods • Factors such as the type of soil and the nature of the construction site will all influence which dewatering method will be best suited to the project. 1. Sumps And Ditches 6. Cement Grouting 2. Shallow Well System 7. Chemical Process 3. Deep Well System 8. Freezing Process 4. Well Point System 9. Electro-Osmosis Method 5. Vacuum Method
  • 5. Sumps and Ditches • It is the simplest and most commonly used form of dewatering. • In this method, shallow pits, called sumps are dug along the periphery of the area and connected by drains of semicircular in shape and 20 cm diameter. • The water from the slopes flows under gravity and is collected in sumps from which it is pumped out.
  • 6. Shallow Well Dewatering  A hole of 30 cm diameter or more is bored into the ground to a depth not more than 10 m below the pump level. A strainer tube of 15 cm diameter is lowered in the bore hole having a casing tube.  A gravel filter is formed around the strainer tube by gradually removing the casing tube and simultaneously pouring the filter well so formed.  The suction pipe from a number of such wells may be connected to one common header connected to the pumping unit.
  • 7. Shallow Well Dewatering [A typical layout of a shallow well system]
  • 8. Deep Well Dewatering (Bored well system)  This system is more suitable when the depth of excavation is more than the 16m or where artesian water is present.  In this, 15 to 16 cm diameter hole is bored and a casing with a large screen is provided. A row of well points is frequently installed at the toe of the side slope of the deep excavation.  A submersible pump is installed at the bottom of the well, of which the casing generally has a minimum diameter of 150 mm. The discharge pipes from the submersible pumps of a number of adjacent wells are connected to a common delivery main. The water is raised from the well by a multi-staged pump.
  • 9. Deep Well Dewatering [A typical layout of a deep well system]
  • 10.
  • 11. Well Point System • The main components of a well-point system are: 1. well points 2. Riser pipe 3. Swinger arm 4. Header pipe 5. pumps
  • 12. Well Point System • The well point is perforated pipe 5 to 8 CM in dia & 1m long covered by cylindrical wire gauge screen known as strainer.  Pipes are jetted in the ground 1 to 2mt a part.  Well point → riser pipe → swinger arm → header.  It is suitable for lowering water table by 5 to 6 m in soil.
  • 14. 14
  • 15. Multi-Stage Well Point System Multi-stage well point system is suitable for excavations up to 15 m.
  • 16. When water table is greater than 6 m this method will use.  In this method 2 or more rows of well point are installed at different elevation.  In this method wells are installed in 2 stages.  In 1st stage water table lowered by 5 m.  If required, then 3rd stage of well point can also be installed for further lower water table.  This method useful for up to 15 m. For up to 15th m deep well system will use. Multi-Stage Well Point System
  • 18. Well Point System Advantages: •Installation is very rapid. The equipment is reasonably simple and cheap. •As water is filtered while removing from the ground, soil particles are not washed away. Hence, there is no danger of subsidence of the surrounding ground. •As the water is drawn away by well points from the excavation, the sides of excavation are stabilized and steeper side slopes can be permitted.
  • 19. Well Point System Disadvantages: •Single stage well point system is suitable for lowering water table by 5 to 6 m only. For deeper excavations, where water table is to be lowered for a depth greater than 6 m, multi-stage well point system is required. •It is essential to continue pumping once it has been started until the excavation is complete. If it is stopped in between, it may prove to be disastrous. •In case of the ground consisting of stiff clay, gravel or boulders, well points are installed in drilled holes, which increases the installation cost.
  • 21. When draining is required for silt or clay which have size less than 0.05mm. That time vacuum pump system will require. The process is as follows:  The well-points are driven and 25 CM dia is provided around the well point.  Installed in the ground by forcing a jet of water under sufficient pressure.  The sand of medium to coarse size is then forced into this hole as rapidly as possible. This sand forms the filter medium. Vacuum System
  • 22. In the upper most 600 mm to 900 mm, an impervious material such as clay is tamped to form the seal the upper portion.  The pumping is then carried out by means of equipment capable of maintaining a vacuum in the well-points and the surrounding filter.  In this way, the pressure around the well-points is reduced to a small fraction of the atmospheric pressure. The ground is acted upon by the atmospheric pressure. Thus the soil becomes consolidated under a pressure which is very nearly equal to the atmospheric. Vacuum System
  • 23. In highly permeable cohesionless soil, the safety of the side slopes may be endangered through the application of severe pumping. In such cases, especially if control of the groundwater is required permanently, the methods of grouting can be used. The main idea is to insert fine materials or chemicals around the excavation in order to reduce the hydraulic conductivity of the surrounding soil to a minimum. In other words, the grouting process creates an almost impervious curtain around the excavation. The grouting is conducted using movable pipes with holes. The grout material is injected under pressure as it flows outside the pipes through the holes to fill the voids of the surrounding soil. The material used for grouting may be clay, cement or special chemical compounds. Control of Groundwater by Grouting
  • 24.
  • 26.
  • 27. Cement Grouting • The material commonly used for grout include: 1) Cement And Water 2) Cement, Rock Flour and Water 3) Cement, Clay and Water 4) Cement, Clay, Sand and Water 5) Asphalt 6) Clay And Water 7) Chemicals
  • 28.
  • 29. Chemical Grouting • The desirable properties of chemical grouts: 1)It must be able to modify the properties of soil as desired 2)It may either increase the strength or decrease the permeability of soil 3)It must be cheap, non-toxic, non-explosive 4)It must be in the form of a liquid with low viscosity so that it can be readily placed in the soil 5)It must be non-corrosive, so that it can be handled with common pumps and piping 6)It must be possible to control the gel time by suitable means
  • 30.
  • 31. Chemical Grouting Inorganic chemicals •Sodium silicate •Calcium chloride •Ligno-chrome •Ligno sulphate •They are called silicate grouts •They are cheaper Organic chemicals •Epoxy resins •Polyester resins •They are also called resin grouts •They possess advantage of low viscosity, precise control of gel time and high strength
  • 32.  Soils that will not drain using conventional methods Typically a ground freezing system consists of an array of freeze pipes.  That are installed into the ground around the perimeter of the excavation, usually in a circular pattern.  A supermodel brine solution is pump through to freeze the pipes, which freezes the water bearing soils around the pipes to create a frozen wall. Extreme care must be taken to make sure that the freeze is complete because any groundwater seepage though the wall or from below the excavation depth will have a sliding effect. FREEZING PROCESS
  • 34. 34
  • 35. GROUND FREEZING The procedure:  A refrigeration plant of required installed near the site of work.  The large pipes of 100 mm to 150 mm diameter.  The distance between the pipes is about 1 m to 1.50 m.  The pipes are closed at the bottom.  The small pipes of 25 mm to 50 mm diameter are inserted into the large pipes.  open at the bottom.  The cold liquid at a temperature of about -23°C to -30°C is then circulated through the circuit. The liquid comes through the small pipe and goes up through the large pipe.  This causes the ground to freeze around the pipes.
  • 37. • This method is used for fine grained cohesive soils (such as clay), which can be drained or stabilized using electric current. The method was developed by L. Casagrande (1952). • If direct current is passed between two electrodes driven into natural soil mass, the soil water will travel` from the positive electrode (anode) to the negative electrode (cathode). The cathode is made in the form of well point or metal tube for pumping out the seeping form of well point or a metal tube for pumping out the seeping water. • A steel rod, a pipe or steel piling of excavation can serve as the cathode. The arrangement of electrodes is done in such a way that the natural direction of flow of water is reversed away from the excavation, thereby increasing the strength of the soil and stability of the slope. The potentials generally used in the process are from 40 to 180 volts, with electrode spacing of 4 to 5 meters. Electro-Osmosis Process
  • 38. The vibroflot is inserted into the ground and typically can be used to improve soil up to depths of 150 feet. Vibroflotation utilizes water and the mechanical vibrations of the vibroflot to move the particles into a denser state. Typical radial distances affected range from 5 to 15 feet (Bauer Maschinen GmbH, 2012). The vibroflot is suspended from a crane and seats on the surface of the ground that is to be improved. To penetrate the material, the bottom jet is activated and the vibration begins. The water saturates the material to create a “quick sand” condition (i.e. temporarily liquefying the material), which allows the vibroflot to sink to the desired depth of improvement. At that point, the bottom jet is stopped and the water is transferred to the upper jet. This is done to create a saturated environment surrounding the vibroflot, thereby enhancing the compaction of the material. The vibroflot remains at the desired depth of improvement until the material reaches adequate density. Vibro flotation Process
  • 39. The density of the soil is measured by using the power input (via the electric current or hydraulic pressure) as an index. As the material densifies, the vibroflot requires more power to continue vibrating at which point pressure gauge displays a peak in required power. Once this point is reached, the vibroflot is raised one lift (generally ranging from 1 to 3 feet) and compaction ensues until the peak amperage or hydraulic pressure is reached once again.
  • 40.
  • 41. The vibroflotation process can offer the following benefits: •When the process is done properly, it will reduce the possibility of differential settlements that will improve the foundation condition of the proposed structure. •It is the fastest and easiest way to improve soil when bottom layers of soil will not provide good load bearing capacity. •It is a great technology to improve harbor bottoms. •On a cost-related standpoint, it helps improve thousands of cubic meters per day. It is faster than piling. •It can be done around existing structures without damaging them . •It does not harm the environment. It improves the soil strata using its own characteristic •No excavations are needed, reducing the hazards, contamination of soils and hauling material out from the site. Advantages
  • 42. Suitability of Different Methods of Ground Water Conditions METHOD CONDITIONS FOR SUITABILITY 1. Sumps and Ditches For shallow excavations in coarse grained soils. 2. Well point system Suitable for lowering water table by 5-6 m in soils 3. Bored well system For coarse grained soils and depth of excavation more than 16 m 4. Vacuum method Draining silty sands and fine sands 5. Cement grouting For coarse materials or rocks with cracks 6. Freezing process Suitable for excavations in water logged soils 7. Electro-osmosis process Suitable for fine grained cohesive soils such as clays