PRESENTATION SUBMITTED BY:-
                        ALOK MISHRA
                          0902900015
                        (CE-4th YEAR)
                  KRISHNA INSTITUE OF
ENGINEERING & TECHNOLOGY, GHAZIABAD
Presentation on Summer
                    Training
held at Construction Site of
Police Station Khajuri Khas
                      under
       Central Public Works
                Department
        Project Report
 TOPICS
 Introduction
Project Overview
Site Location
Formwork
Planning
Sequence of Structures
Finishing Works
Project Monitoring
Quality
Conclusion
 INTRODUCTION
About CPWD:

 The Central Public Works Department of India is a Central
  Government owned authority that is in charge of public sector works in the
  country.

 Central Public Works Department (CPWD) under Ministry of Urban
  Development is entrusted with construction and maintenance of buildings
  for most of the Central Government Departments, Public undertakings and
  autonomous bodies.

 CPWD, Delhi is the premier agency of Govt. of India engaged in planning,
  designing, construction and maintenance of Government assets in the field of
  built environment and infrastructure development. Assets in built
  environment include Hospitals, Schools, Colleges, Technical Institutes,
  Police Buildings, Prisons, Courts etc.
OBJECTIVES
1) Sound Planning And Design
2) Engineered Construction
3) Effective Maintenance
4) Benchmarking the Standards
5) Capacity Building
6) Public Private Partnership
7) Manpower Planning
8) Transparency in Management
 PROJECT OVERVIEW
Name Of Work:

 Construction of Police Station Khajuri Khas, Near
 Sonia Vihar, Delhi (SH: C/o Police Station Building,
 Electric sub Station & External Development Work
 i.e. Internal Electrical Installations)
AGREEMENT NO. :       03/EE/CD-III/2011-12


NAME OF CONTRACTOR:   M/S ROSHAN REAL ESTATES PVT LTD.


PLOT SIZE:            5984 Sqm. Area


ESTIMATED COST:       Civil Work-      Rs   6, 01, 47,287/-
                      Elec. Work-      Rs       24, 75,332/-
                                       Rs   6, 26, 22,609/-


TENDERED COST:        Civil Work-      Rs 6, 57, 88,182/-
                      Elec. Work-      Rs    28, 69,490/-
                                       Rs 6, 86, 57,672/-


DATE OF START:        04-08-2011

STIPULATED DATE OF
COMPLETION:           02-08-2012

ACTUAL DATE OF        Work is Under Progress
COMPLETION:           (80% Work is Completed)

TIME ALLOWED :         365 Days
 SITE LOCATION
Advantages Of this Site

 Land
 Store
 Health Unit
 Canteen
 Connectivity Of the Yard
 Ease Of transportation Facilities
 FORMWORK
SIGNIFICANCE OF FORMWORK:-
1) Formwork constitutes 30% of the cost and 60% of the time in concrete construction.
2) Quality of concrete finish and soundness of concrete depends very much on the
formwork        system
3) Desired shape of concrete is not possible if formwork not done properly.
4) Formwork should be properly designed, fabricated and erected to receive concrete.
5) Accidents happen because of the faulty formwork and scaffolding or staging



SAFETY IN USING FORMWORK:-
1) Components are light in weight for manual handling.
2) Loose or hanging components are minimal.
3) Appropriate use of tools.
4) Minimum operations are involved in each reuse.
 PLANNING
Planning of a CPWD Project mainly includes:-

      Pre-requisites for execution of work.
      Deposit works
      Preparation of estimates.
      Execution of original work.
      Expenditure on survey, exhibition.
      Register of buildings.
      Green building norms.
      Preparation and accounting of Standard Measurement book.
      Preparation and passing bills for payment.
      Documentation of accounts.
      General departmental charges.
      Contracts and forms.
      Preparation of tender documents.
      Publicity of tenders
      Sale of documents
      Earnest money.
      Issue of material to contractors.
      Issue of tool and plant.
      Payment to contractors
      Insurance
      Losses or damages.
      Budgeting
      Quality assurance and technical audit wing.
      Inspection and Audit by Chief Controller.
      Public accounts committee.
 SEQUENCE OF STRUCTURE
  WORK
 Site clearance
 Demarcation of site
 Positioning of central coordinate i.e. (0,0,0) as per grid
    plan
   Surveying and layout
   Excavation
   Bar binding and placement of foundation steel
   Shuttering and scaffolding
   Concreting
   Electrical and plumbing
Construction Process And Material Used

CONCRETE

1) Normal Concrete made of Fine Aggregate +
   Regular Aggregate + Water

2) Concrete will set up hard enough in normal
   weather in about 3 hours

3) It takes 28 days for it to reach its fullest strength
Plastering

 Make sure to wet the surface at which you are applying plaster.
    This will ensure better sticking of the plaster.
   Don’t use dry cement over the plastic surface, as there chances of
    it getting distorted.
   Use the appropriate amount of water while mixing chemicals or
    else, there are chances that it won’t set up to the brick wall.
   Wait for 24 hours after plastering the wall and splatter water
    over it for the next 3-4 days. The splattered water will ensure
    better set up of the plaster.
   If you are doing the patch up work in a smaller area, like in a
    room, make sure to keep newspaper pieces on the ground, so
    that if the plaster falls over it, it can be removed. Once dried, it is
    difficult to remove the plaster.
 FINISHING WORKS
Painting

Pre-painting work


Surface preparation


Painting
Pre-Painting Works
Patching


Sanding


Cleaning


Priming
Surface Preparation
 Allow newly plastered surface to mature for a period of at least 6 months
  before painting.

 Rectify existing surface problems such as dampness, cracks etc. before
  actual painting process.

 Check for hand prints, greasy fingerprints, algae as well as dirt and stained
  marks.

 Use a scraper, putty knife or scrub brush to remove any dirt, grease, rust, or
  flaking.

 Fill in the holes, cracks and joints with plaster.

 Clean and dry the surface.

 Make sure the area to be painted is well ventilated as well as free of dust.

 As far as possible, don’t paint under much humid conditions.
Painting
Objects to be Painted

Interior walls


Exterior Walls


Metal Surfaces


Wooden Surfaces
INTERIOR WALLS

 Apply a coat of Wall Primer (water thinnable) on new surfaces.

 Fill and level the minor undulations of wall by applying putty. In case of major
  undulations on the wall surface, POP (Plaster of Paris) work needs to be
  carried out. Ensure that the surface is uniformly smooth by sanding after POP
  or putty work.

 One liberal coat of Wall Primer (solvent thinned or water thinned) is
  recommended on puttied areas before the application of top coat. The primer
  should be allowed to dry for 10 - 12 hours. If the primer coat is not applied over
  the puttied areas, there can be a patchy appearance of the top coat.

 Avoid application of putty or filling compound while painting exterior surfaces.
  Fill up cracks with a 1:3 (by volume) cement and sand mixture.

 All external drainage pipes must be checked for rusting or leakage. Any faulty
  plumbing must be rectified

 Special attention must be given to the roof. Check for cracks near the edges and
  close to the water reservoirs. Proper masonry or waterproofing work on the
  ceiling will enhance the performance of the paint.
 Exterior Walls
Pre-painting
 For exterior surfaces it is very important to undertake
  repairs of any wall imperfections before commencing
  painting.. Avoid applying putty or filling compound
  while painting exterior surfaces. Fill up cracks with a
  1:3 cement and sand mixture.
 All external drainage pipes must be checked for
  rusting or leakage. Any faulty plumbing must be
  rectified.
 Special attention must be given to the roof. Check for
  cracks near the edges and close to the water reservoirs.
  Proper masonry or waterproofing work on the ceiling
  will enhance the performance of the painted surfaces.
Exterior Wall Painting
 Apply a liberal coat of Asian Paints Exterior Wall Primer using
  recommended method.
 Apply two coats of top coat paint at recommended dilution. You can
  use Apex Weather Proof Exterior Emulsion or Apex Textured Exterior
  Emulsion or Ace Exterior Emulsion as top coat.
 A gap of 4 to 6 hours must be given between two coats.
 It is recommended that horizontal surfaces like the tops of awnings
  and Parapets must be given an additional coat for greater protection.
Metal Surfaces

 Surface should be free from dirt, dust, grease, rust, moisture etc. The
  area which is not to be painted must be covered by a masking tape,
  paper and/or cloth.

 For best results, allow the primer coat to dry for 6 hours and dry
  sand with emery paper no. 320 before application of subsequent coat.

 Allow the surface to dry overnight after application of primer as above.

 Apply top coat using the recommended thinner. For best results, apply
  two coats allowing 8 hours of drying time between two coats.

 The first coat should be wet sanded with waterproof emery paper
  grade 400 before applying the second coat.
Wooden Surfaces
Surface Preparation:

 Previously painted wooden surfaces must be properly sanded to
  remove any dust or grease.

 Apply wood primer by brush, after thinning to given ratio by
  recommended thinner.

 Allow it to dry for 6-8 hrs then apply putty.


 Sand the applied putty with number 180 sand paper and then apply
  second coat of wood primer.

 Now the wooden surface is ready for painting with the top coat
Painting
 For opaque finish you can choose conventional enamels Apply wood
  primer by brush, after thinning to given ratio by recommended thinner.

 Sand the applied putty with 180 no. sand paper & apply 2nd coat of
  wood primer.

 Now the wooden surface is ready for painting with the top coat
 Enamels are normally applied by brushing although they can also be
  sprayed.

 The drying time of enamels is longer; hence care must be taken to
  ensure a dust free environment while the paint film is drying.

 Two coats of paint is sufficient in most cases, however if the earlier
  paint shade was significantly darker than the new shade an additional
  coat of paint is recommended
 PROJECT MONITORING
PROJECT MONITORING SYSTEM
The following three reports are made for the tracking-

 Monthly progress report


 Job cost report


 Project performance report.
 Quality
Quality Control System of CPWD
 Field Level
 Circle Level
 Core Wing at Directorate Level

Quality Assurance Units In The Region
 Contract & Manual
 Standards and Specifications
 Quality Assurance
 Techno-Legal matters
 Technology Application & Standards Unit.
 CONCLUSION
 It was a wonderful learning experience at CPWD office, IP
  Bhawan, New Delhi 110002 for Six Weeks.

 I gained a lot of insight regarding FINISHING aspects of
  Construction site.

 I was given exposure in almost all the departments at the
  site, but I had liked to highlight the areas of safety, quality
  management, material management and execution.

 I hope this experience will surely help me in my future and
  also in shaping my career.

More Related Content

What's hot

A Presentation on Bored Cast-in-Situ Piles
A Presentation on Bored Cast-in-Situ PilesA Presentation on Bored Cast-in-Situ Piles
A Presentation on Bored Cast-in-Situ PilesSubham Kundu
 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete9833356555
 
Repair techniques : Grouting (RR&S)
Repair techniques : Grouting (RR&S)Repair techniques : Grouting (RR&S)
Repair techniques : Grouting (RR&S)RAMPRASAD KUMAWAT
 
Building construction
Building constructionBuilding construction
Building constructionnhmurad
 
Pre stressed concrete construction
Pre stressed concrete constructionPre stressed concrete construction
Pre stressed concrete constructionJenilPatel22
 
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING Ram1239
 
Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavationAl-Amin Ahmed Nabin
 
Site report for Measurement 1
Site report for Measurement 1Site report for Measurement 1
Site report for Measurement 1Yap Xin
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteRajesh Burde
 
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGPROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGAmritpal Singh
 
Chapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingChapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingAnkit Patel
 
Post-tensioning in Prestressed Concrete
Post-tensioning in Prestressed ConcretePost-tensioning in Prestressed Concrete
Post-tensioning in Prestressed ConcreteDavinderpal Singh
 
Crack repair techniques
Crack repair techniquesCrack repair techniques
Crack repair techniquesNayana 54321
 
FOOTING CONSTRUCTION
FOOTING CONSTRUCTIONFOOTING CONSTRUCTION
FOOTING CONSTRUCTIONMd Shadab
 
Goe tech. engg. Ch# 02 strss distribution
Goe tech. engg. Ch# 02 strss distributionGoe tech. engg. Ch# 02 strss distribution
Goe tech. engg. Ch# 02 strss distributionIrfan Malik
 
Pre stressed concrete Bridge
Pre stressed concrete BridgePre stressed concrete Bridge
Pre stressed concrete BridgeShubham Das
 

What's hot (20)

Retaining Walls
Retaining WallsRetaining Walls
Retaining Walls
 
A Presentation on Bored Cast-in-Situ Piles
A Presentation on Bored Cast-in-Situ PilesA Presentation on Bored Cast-in-Situ Piles
A Presentation on Bored Cast-in-Situ Piles
 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete
 
Repair techniques : Grouting (RR&S)
Repair techniques : Grouting (RR&S)Repair techniques : Grouting (RR&S)
Repair techniques : Grouting (RR&S)
 
Slip formwork technique
Slip formwork techniqueSlip formwork technique
Slip formwork technique
 
Building construction
Building constructionBuilding construction
Building construction
 
Pre stressed concrete construction
Pre stressed concrete constructionPre stressed concrete construction
Pre stressed concrete construction
 
Soil exploration part i
Soil exploration part  iSoil exploration part  i
Soil exploration part i
 
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
 
Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavation
 
Site report for Measurement 1
Site report for Measurement 1Site report for Measurement 1
Site report for Measurement 1
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGPROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
 
Chapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingChapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiiting
 
Post-tensioning in Prestressed Concrete
Post-tensioning in Prestressed ConcretePost-tensioning in Prestressed Concrete
Post-tensioning in Prestressed Concrete
 
Crack repair techniques
Crack repair techniquesCrack repair techniques
Crack repair techniques
 
FOOTING CONSTRUCTION
FOOTING CONSTRUCTIONFOOTING CONSTRUCTION
FOOTING CONSTRUCTION
 
Goe tech. engg. Ch# 02 strss distribution
Goe tech. engg. Ch# 02 strss distributionGoe tech. engg. Ch# 02 strss distribution
Goe tech. engg. Ch# 02 strss distribution
 
Pre stressed concrete Bridge
Pre stressed concrete BridgePre stressed concrete Bridge
Pre stressed concrete Bridge
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 

Similar to Construction Site Project Report

Presentation [AP14015]
Presentation [AP14015]Presentation [AP14015]
Presentation [AP14015]Rahul Dasgupta
 
Fundamentals of Estimating and Costing
 Fundamentals of Estimating and Costing Fundamentals of Estimating and Costing
Fundamentals of Estimating and CostingGanesh Tatikonda
 
chapter1-210122051628.pdf
chapter1-210122051628.pdfchapter1-210122051628.pdf
chapter1-210122051628.pdfDeepak37004
 
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...DougDos
 
Design of automatic wall plastering machine
Design of automatic wall plastering machineDesign of automatic wall plastering machine
Design of automatic wall plastering machineLaukik Raut
 
Cement Plastering procedure
Cement Plastering procedureCement Plastering procedure
Cement Plastering procedureSyed Javed
 
Method statement for expansion joint
Method statement for expansion jointMethod statement for expansion joint
Method statement for expansion jointakash yadav
 
A Descriptive Study on Construction Progress Involved in Apartment Building
A Descriptive Study on Construction Progress Involved in Apartment BuildingA Descriptive Study on Construction Progress Involved in Apartment Building
A Descriptive Study on Construction Progress Involved in Apartment BuildingIRJET Journal
 
Internship report at Indian Oil Corporation Limited
Internship report at Indian Oil Corporation LimitedInternship report at Indian Oil Corporation Limited
Internship report at Indian Oil Corporation LimitedAdityaDiwakar3
 
summer Internship report L&T_ Bihar museum_Patna
summer Internship report L&T_ Bihar museum_Patnasummer Internship report L&T_ Bihar museum_Patna
summer Internship report L&T_ Bihar museum_Patnakishore1192
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.pptSOUMITRAMUDI
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.pptBALAMURUGANR53
 
Method painting works emulsion paint
Method painting works   emulsion paintMethod painting works   emulsion paint
Method painting works emulsion paintMinh Bui Si
 
Method statement honycomb repairing
Method statement  honycomb repairingMethod statement  honycomb repairing
Method statement honycomb repairingBharatha Rathnayke
 

Similar to Construction Site Project Report (20)

Abhishek presentation.pptx
Abhishek presentation.pptxAbhishek presentation.pptx
Abhishek presentation.pptx
 
Presentation [AP14015]
Presentation [AP14015]Presentation [AP14015]
Presentation [AP14015]
 
Training Report
Training ReportTraining Report
Training Report
 
Fundamentals of Estimating and Costing
 Fundamentals of Estimating and Costing Fundamentals of Estimating and Costing
Fundamentals of Estimating and Costing
 
chapter1-210122051628.pdf
chapter1-210122051628.pdfchapter1-210122051628.pdf
chapter1-210122051628.pdf
 
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
 
Contract presentation
Contract presentation  Contract presentation
Contract presentation
 
Design of automatic wall plastering machine
Design of automatic wall plastering machineDesign of automatic wall plastering machine
Design of automatic wall plastering machine
 
Cement Plastering procedure
Cement Plastering procedureCement Plastering procedure
Cement Plastering procedure
 
Method statement for expansion joint
Method statement for expansion jointMethod statement for expansion joint
Method statement for expansion joint
 
A Descriptive Study on Construction Progress Involved in Apartment Building
A Descriptive Study on Construction Progress Involved in Apartment BuildingA Descriptive Study on Construction Progress Involved in Apartment Building
A Descriptive Study on Construction Progress Involved in Apartment Building
 
Internship report at Indian Oil Corporation Limited
Internship report at Indian Oil Corporation LimitedInternship report at Indian Oil Corporation Limited
Internship report at Indian Oil Corporation Limited
 
summer Internship report L&T_ Bihar museum_Patna
summer Internship report L&T_ Bihar museum_Patnasummer Internship report L&T_ Bihar museum_Patna
summer Internship report L&T_ Bihar museum_Patna
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
 
Estimation_and_Costing.ppt
Estimation_and_Costing.pptEstimation_and_Costing.ppt
Estimation_and_Costing.ppt
 
Ici individual
Ici individualIci individual
Ici individual
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
 
Deep-Vac-Work (2)
Deep-Vac-Work (2)Deep-Vac-Work (2)
Deep-Vac-Work (2)
 
Method painting works emulsion paint
Method painting works   emulsion paintMethod painting works   emulsion paint
Method painting works emulsion paint
 
Method statement honycomb repairing
Method statement  honycomb repairingMethod statement  honycomb repairing
Method statement honycomb repairing
 

Construction Site Project Report

  • 1. PRESENTATION SUBMITTED BY:- ALOK MISHRA 0902900015 (CE-4th YEAR) KRISHNA INSTITUE OF ENGINEERING & TECHNOLOGY, GHAZIABAD
  • 2. Presentation on Summer Training held at Construction Site of Police Station Khajuri Khas under Central Public Works Department Project Report
  • 3.  TOPICS  Introduction Project Overview Site Location Formwork Planning Sequence of Structures Finishing Works Project Monitoring Quality Conclusion
  • 4.  INTRODUCTION About CPWD:  The Central Public Works Department of India is a Central Government owned authority that is in charge of public sector works in the country.  Central Public Works Department (CPWD) under Ministry of Urban Development is entrusted with construction and maintenance of buildings for most of the Central Government Departments, Public undertakings and autonomous bodies.  CPWD, Delhi is the premier agency of Govt. of India engaged in planning, designing, construction and maintenance of Government assets in the field of built environment and infrastructure development. Assets in built environment include Hospitals, Schools, Colleges, Technical Institutes, Police Buildings, Prisons, Courts etc.
  • 5. OBJECTIVES 1) Sound Planning And Design 2) Engineered Construction 3) Effective Maintenance 4) Benchmarking the Standards 5) Capacity Building 6) Public Private Partnership 7) Manpower Planning 8) Transparency in Management
  • 6.  PROJECT OVERVIEW Name Of Work:  Construction of Police Station Khajuri Khas, Near Sonia Vihar, Delhi (SH: C/o Police Station Building, Electric sub Station & External Development Work i.e. Internal Electrical Installations)
  • 7. AGREEMENT NO. : 03/EE/CD-III/2011-12 NAME OF CONTRACTOR: M/S ROSHAN REAL ESTATES PVT LTD. PLOT SIZE: 5984 Sqm. Area ESTIMATED COST: Civil Work- Rs 6, 01, 47,287/- Elec. Work- Rs 24, 75,332/- Rs 6, 26, 22,609/- TENDERED COST: Civil Work- Rs 6, 57, 88,182/- Elec. Work- Rs 28, 69,490/- Rs 6, 86, 57,672/- DATE OF START: 04-08-2011 STIPULATED DATE OF COMPLETION: 02-08-2012 ACTUAL DATE OF Work is Under Progress COMPLETION: (80% Work is Completed) TIME ALLOWED : 365 Days
  • 8.  SITE LOCATION Advantages Of this Site  Land  Store  Health Unit  Canteen  Connectivity Of the Yard  Ease Of transportation Facilities
  • 9.  FORMWORK SIGNIFICANCE OF FORMWORK:- 1) Formwork constitutes 30% of the cost and 60% of the time in concrete construction. 2) Quality of concrete finish and soundness of concrete depends very much on the formwork system 3) Desired shape of concrete is not possible if formwork not done properly. 4) Formwork should be properly designed, fabricated and erected to receive concrete. 5) Accidents happen because of the faulty formwork and scaffolding or staging SAFETY IN USING FORMWORK:- 1) Components are light in weight for manual handling. 2) Loose or hanging components are minimal. 3) Appropriate use of tools. 4) Minimum operations are involved in each reuse.
  • 10.
  • 12. Planning of a CPWD Project mainly includes:-  Pre-requisites for execution of work.  Deposit works  Preparation of estimates.  Execution of original work.  Expenditure on survey, exhibition.  Register of buildings.  Green building norms.  Preparation and accounting of Standard Measurement book.  Preparation and passing bills for payment.  Documentation of accounts.  General departmental charges.  Contracts and forms.  Preparation of tender documents.  Publicity of tenders  Sale of documents  Earnest money.  Issue of material to contractors.  Issue of tool and plant.  Payment to contractors  Insurance  Losses or damages.  Budgeting  Quality assurance and technical audit wing.  Inspection and Audit by Chief Controller.  Public accounts committee.
  • 13.  SEQUENCE OF STRUCTURE WORK  Site clearance  Demarcation of site  Positioning of central coordinate i.e. (0,0,0) as per grid plan  Surveying and layout  Excavation  Bar binding and placement of foundation steel  Shuttering and scaffolding  Concreting  Electrical and plumbing
  • 14. Construction Process And Material Used CONCRETE 1) Normal Concrete made of Fine Aggregate + Regular Aggregate + Water 2) Concrete will set up hard enough in normal weather in about 3 hours 3) It takes 28 days for it to reach its fullest strength
  • 15. Plastering  Make sure to wet the surface at which you are applying plaster. This will ensure better sticking of the plaster.  Don’t use dry cement over the plastic surface, as there chances of it getting distorted.  Use the appropriate amount of water while mixing chemicals or else, there are chances that it won’t set up to the brick wall.  Wait for 24 hours after plastering the wall and splatter water over it for the next 3-4 days. The splattered water will ensure better set up of the plaster.  If you are doing the patch up work in a smaller area, like in a room, make sure to keep newspaper pieces on the ground, so that if the plaster falls over it, it can be removed. Once dried, it is difficult to remove the plaster.
  • 16.  FINISHING WORKS Painting Pre-painting work Surface preparation Painting
  • 20.  Allow newly plastered surface to mature for a period of at least 6 months before painting.  Rectify existing surface problems such as dampness, cracks etc. before actual painting process.  Check for hand prints, greasy fingerprints, algae as well as dirt and stained marks.  Use a scraper, putty knife or scrub brush to remove any dirt, grease, rust, or flaking.  Fill in the holes, cracks and joints with plaster.  Clean and dry the surface.  Make sure the area to be painted is well ventilated as well as free of dust.  As far as possible, don’t paint under much humid conditions.
  • 22. Objects to be Painted Interior walls Exterior Walls Metal Surfaces Wooden Surfaces
  • 23. INTERIOR WALLS  Apply a coat of Wall Primer (water thinnable) on new surfaces.  Fill and level the minor undulations of wall by applying putty. In case of major undulations on the wall surface, POP (Plaster of Paris) work needs to be carried out. Ensure that the surface is uniformly smooth by sanding after POP or putty work.  One liberal coat of Wall Primer (solvent thinned or water thinned) is recommended on puttied areas before the application of top coat. The primer should be allowed to dry for 10 - 12 hours. If the primer coat is not applied over the puttied areas, there can be a patchy appearance of the top coat.  Avoid application of putty or filling compound while painting exterior surfaces. Fill up cracks with a 1:3 (by volume) cement and sand mixture.  All external drainage pipes must be checked for rusting or leakage. Any faulty plumbing must be rectified  Special attention must be given to the roof. Check for cracks near the edges and close to the water reservoirs. Proper masonry or waterproofing work on the ceiling will enhance the performance of the paint.
  • 24.  Exterior Walls Pre-painting  For exterior surfaces it is very important to undertake repairs of any wall imperfections before commencing painting.. Avoid applying putty or filling compound while painting exterior surfaces. Fill up cracks with a 1:3 cement and sand mixture.  All external drainage pipes must be checked for rusting or leakage. Any faulty plumbing must be rectified.  Special attention must be given to the roof. Check for cracks near the edges and close to the water reservoirs. Proper masonry or waterproofing work on the ceiling will enhance the performance of the painted surfaces.
  • 25. Exterior Wall Painting  Apply a liberal coat of Asian Paints Exterior Wall Primer using recommended method.  Apply two coats of top coat paint at recommended dilution. You can use Apex Weather Proof Exterior Emulsion or Apex Textured Exterior Emulsion or Ace Exterior Emulsion as top coat.  A gap of 4 to 6 hours must be given between two coats.  It is recommended that horizontal surfaces like the tops of awnings and Parapets must be given an additional coat for greater protection.
  • 26. Metal Surfaces  Surface should be free from dirt, dust, grease, rust, moisture etc. The area which is not to be painted must be covered by a masking tape, paper and/or cloth.  For best results, allow the primer coat to dry for 6 hours and dry sand with emery paper no. 320 before application of subsequent coat.  Allow the surface to dry overnight after application of primer as above.  Apply top coat using the recommended thinner. For best results, apply two coats allowing 8 hours of drying time between two coats.  The first coat should be wet sanded with waterproof emery paper grade 400 before applying the second coat.
  • 27. Wooden Surfaces Surface Preparation:  Previously painted wooden surfaces must be properly sanded to remove any dust or grease.  Apply wood primer by brush, after thinning to given ratio by recommended thinner.  Allow it to dry for 6-8 hrs then apply putty.  Sand the applied putty with number 180 sand paper and then apply second coat of wood primer.  Now the wooden surface is ready for painting with the top coat
  • 28.
  • 29. Painting  For opaque finish you can choose conventional enamels Apply wood primer by brush, after thinning to given ratio by recommended thinner.  Sand the applied putty with 180 no. sand paper & apply 2nd coat of wood primer.  Now the wooden surface is ready for painting with the top coat  Enamels are normally applied by brushing although they can also be sprayed.  The drying time of enamels is longer; hence care must be taken to ensure a dust free environment while the paint film is drying.  Two coats of paint is sufficient in most cases, however if the earlier paint shade was significantly darker than the new shade an additional coat of paint is recommended
  • 30.  PROJECT MONITORING PROJECT MONITORING SYSTEM The following three reports are made for the tracking-  Monthly progress report  Job cost report  Project performance report.
  • 31.  Quality Quality Control System of CPWD  Field Level  Circle Level  Core Wing at Directorate Level Quality Assurance Units In The Region  Contract & Manual  Standards and Specifications  Quality Assurance  Techno-Legal matters  Technology Application & Standards Unit.
  • 32.  CONCLUSION  It was a wonderful learning experience at CPWD office, IP Bhawan, New Delhi 110002 for Six Weeks.  I gained a lot of insight regarding FINISHING aspects of Construction site.  I was given exposure in almost all the departments at the site, but I had liked to highlight the areas of safety, quality management, material management and execution.  I hope this experience will surely help me in my future and also in shaping my career.