SlideShare a Scribd company logo
1 of 15
L&T Case Study
Team Optimus – KJ SIMSR
Amit Divekar, Pravin Bokil, Jitendarkumar Panda
Case – Hydropower Project
Up-gradation of existing system of the plant
• Hydro-electric plant with surface Penstock system
• Capacity : 4*72 MW power station
• Contract to replace current surface penstock system
with combination of surface penstock and steel lined
tunnel
• Contract value- Rs. 44.88 Cr. For a period- 42 months
• Estimated Project Timeline 15-02-02 to 14-08-2005
• Contract Type- Item rate contract
• Carry out the work without interrupting the power
generation
• Activities : Tunneling, Fabrication and Erection
of penstocks
Factors that forced up-gradation
• Increasing age of the existing system resulting in
higher Maintenance Cost & Cleaning Cost
• Reduction in operating efficiency
• Surface penstock vulnerable to damage
• Cost of security and inspection
• Threat of miscreants
• Resultant damage to society
• Damage cost > Project Cost
(refer - Cost calculation for client)
Calculation of Cost for Client
• . Production Capacity 288 MW
Min loss (1 unit shutdown) 72 MW
Max loss (station shutdown) 288 MW
Plant operation
per day(if base load)
24 hrs
Plant operation per day (if peaking load) 6 hrs
Worst case loss of sale per day 6912 MW-hrs
Least loss of sale per day 432 MW-hrs
Unit cost of electricity in year 2002 1.42
Rs per unit
(KW-Hr)
Assumption- 50% revenue for power
producer considering share of discoms
0.71
Total loss of sale per day(worst case) 4907520 Rs
Total loss of sale per day(least loss) 306720 Rs
project cost 448800000 Rs
Risk Evaluation
Risks For Contractor
• Delay due to blasting & drilling
• Extra cost for blasting work – Hard strata
• Delay in removal of muck
• Quality control work resulting in time delay &
cost overrun
• Inventory control- wastage & reconciliation
• Delay due to erection difficulties
• Concreting issues- Quality & cost implications
Delay due to Blasting & Drilling
• 6 months advancement achieved with revised
charge calculation
• Time Risk associated – 1.33 Cr
• % of contract value – 2.97
• Customer taken into confidence while
implementation of new idea
  Tunneling Fabrication Erection
time  in months 15 21 14
total mandays 
Utilised 59805 79125 70650
cost 40981749 54220899 48413352
Risk in Fabrication
• Purchase of material in client’s scope
• Limited material quantity available with contractor
• Improper inventory or material management has
potential risk of material shortage
• Ordering after shortage has risk of high lead time
• Risk of incurring high cost of raw material
• Cost of risk > 1% of contract value
• Probability is moderate as it can only be result of
inefficient management
Force Majeure
• Common clause in contracts that essentially
frees both parties from liability or obligation
• When – In case of an extraordinary event
• Circumstance beyond the control of the parties,
such as a war, strike, riot, crime, act of God
• Does not excuse a party's non-performance
entirely, but only suspends it for the duration of
the force majeure
Risk Evaluation Framework
Catastrophic
S>2
Major
1<S<2
Significant
0.5<S<1
Minor
0.25<S<0.5
Insignificant
S<0.25
Certain
P>0.9
Likely
0.5<P<0.9
Delay due to
Blasting &
Drilling
Moderate
0.1<P<0.5
Cost overrun
in fabrication
Unlikely
0.03<P<0.1
Rare
P<0.03
Force Majeure
Identification
Force
Majeure
Identification
Severity (S) Probability –P
% of total contract value Probability of occurring identified risk event
Best Practices Mitigating Risks
• Menamite instrument to control sound and vibration
limits
• Changes in drilling pattern and charge factor as per
existing ground conditions
• Headgear System to improve efficiency of mucking
operations
• Dedicated fabrication workshops
• Use of rubber closures during testing process
• Turntable for erection of penstocks
• Implementing value stream mapping for waste
reduction
Productivity Rate and
Associated Cost Savings
• Total man days planned- 3.45 Lac
• Total Man days required- 2.09 Lac
• Saved man days- 39.12%
Microsoft Office
Excel Worksheet
Strategy
• De-risking at the Bid Stage – Scope clarification
• During execution – Close follow up
• De-risking via Communicating Contractual Issues
• De-risking Issues at Project Completion Stage
• Knowledge Management- To capture the
innovative practices adopted in project to be
replicated in other projects
• Organizational policies to foster the culture of
innovation
• Preparation of standardized WBS with schedule
Competitive Price Bid
• Total Contract Value: 44.88 Crores
• Total Cost (20% margin): 35.90 Crores
• Total Labor Cost (40% of total Cost): 14.36 Crores
• Total Labor cost saved: 40%
• Assuming that the total cost saved is proportional to the labor cost of the
particular activity
• Work Breakdown Structure
New Bid
•Cost Saving incorporated in the bidding
stage: Muck Removing, Testing and
alignment
•New Labor Cost: 11.76 Crores
•Total Cost: 33.30 Crores
•Total Bid Price: 39.96 Crores
(20% margin)
References:
1.http://www.larsentoubro.com/lntcorporate/pmiv/pdf/conference_paper_
4
2. http://www.larsentoubro.com
3. Dr. Hiren M Maniar /Risk Analysis of Infrastructure Projects
THANK YOU

More Related Content

What's hot

1 2 chem plantdesign-intro to plant design economics
1 2 chem plantdesign-intro to plant design  economics1 2 chem plantdesign-intro to plant design  economics
1 2 chem plantdesign-intro to plant design economics
ayimsevenfold
 
KEY ATTRIBUTES FULL TEXT
KEY ATTRIBUTES FULL TEXTKEY ATTRIBUTES FULL TEXT
KEY ATTRIBUTES FULL TEXT
Aled Long
 
Integration of modules on site _ final
Integration of modules on site _ finalIntegration of modules on site _ final
Integration of modules on site _ final
Scott Coombes
 

What's hot (18)

042 iIntegrating Lean Construction
042 iIntegrating Lean Construction042 iIntegrating Lean Construction
042 iIntegrating Lean Construction
 
Process Planning & Cost Estimation
Process Planning & Cost EstimationProcess Planning & Cost Estimation
Process Planning & Cost Estimation
 
Case study electronics industry
Case study   electronics industryCase study   electronics industry
Case study electronics industry
 
Production planing & control
Production planing & controlProduction planing & control
Production planing & control
 
vijay cv
vijay cvvijay cv
vijay cv
 
Updated resume 31 may 15
Updated resume 31 may 15Updated resume 31 may 15
Updated resume 31 may 15
 
COMPONENT OF COST BY G.DINESHPIRAN [DP]
COMPONENT OF COST BY G.DINESHPIRAN [DP]COMPONENT OF COST BY G.DINESHPIRAN [DP]
COMPONENT OF COST BY G.DINESHPIRAN [DP]
 
1 2 chem plantdesign-intro to plant design economics
1 2 chem plantdesign-intro to plant design  economics1 2 chem plantdesign-intro to plant design  economics
1 2 chem plantdesign-intro to plant design economics
 
Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 )
 
160615 Promising Enhancements of the Defence Logistics Footprint Using Additi...
160615 Promising Enhancements of the Defence Logistics Footprint Using Additi...160615 Promising Enhancements of the Defence Logistics Footprint Using Additi...
160615 Promising Enhancements of the Defence Logistics Footprint Using Additi...
 
Introduction to plant design economics
Introduction to plant design economicsIntroduction to plant design economics
Introduction to plant design economics
 
Construction of a General Cargo Vessel
Construction of a General Cargo VesselConstruction of a General Cargo Vessel
Construction of a General Cargo Vessel
 
160615 Progress Update WP1 (Laura Cordova Gonzalez)
160615 Progress Update WP1 (Laura Cordova Gonzalez)160615 Progress Update WP1 (Laura Cordova Gonzalez)
160615 Progress Update WP1 (Laura Cordova Gonzalez)
 
KEY ATTRIBUTES FULL TEXT
KEY ATTRIBUTES FULL TEXTKEY ATTRIBUTES FULL TEXT
KEY ATTRIBUTES FULL TEXT
 
Integration of modules on site _ final
Integration of modules on site _ finalIntegration of modules on site _ final
Integration of modules on site _ final
 
Material management
Material managementMaterial management
Material management
 
Equipment management
Equipment managementEquipment management
Equipment management
 
Asset Management Before and After the Equipment Purchase
Asset Management Before and After the Equipment PurchaseAsset Management Before and After the Equipment Purchase
Asset Management Before and After the Equipment Purchase
 

Viewers also liked

PM Case Study USPS MPI Project-Cardiss Collins P&DC-Chicago
PM Case Study USPS MPI Project-Cardiss Collins P&DC-ChicagoPM Case Study USPS MPI Project-Cardiss Collins P&DC-Chicago
PM Case Study USPS MPI Project-Cardiss Collins P&DC-Chicago
Dennis Usky
 
Daniel O Connell Professional Construction Consultant
Daniel O Connell Professional Construction ConsultantDaniel O Connell Professional Construction Consultant
Daniel O Connell Professional Construction Consultant
danieloconnell
 
3. Project Management A Case Study Of A Successful Erp Implementation
3. Project Management A Case Study Of A Successful Erp Implementation3. Project Management A Case Study Of A Successful Erp Implementation
3. Project Management A Case Study Of A Successful Erp Implementation
Donovan Mulder
 
Case Study - Project Management
Case Study - Project Management Case Study - Project Management
Case Study - Project Management
Jimmy Horn
 

Viewers also liked (13)

A Razzaq Presentation Ff R
A Razzaq Presentation Ff RA Razzaq Presentation Ff R
A Razzaq Presentation Ff R
 
PM Case Study USPS MPI Project-Cardiss Collins P&DC-Chicago
PM Case Study USPS MPI Project-Cardiss Collins P&DC-ChicagoPM Case Study USPS MPI Project-Cardiss Collins P&DC-Chicago
PM Case Study USPS MPI Project-Cardiss Collins P&DC-Chicago
 
Daniel O Connell Professional Construction Consultant
Daniel O Connell Professional Construction ConsultantDaniel O Connell Professional Construction Consultant
Daniel O Connell Professional Construction Consultant
 
3. Project Management A Case Study Of A Successful Erp Implementation
3. Project Management A Case Study Of A Successful Erp Implementation3. Project Management A Case Study Of A Successful Erp Implementation
3. Project Management A Case Study Of A Successful Erp Implementation
 
Case Study - Project Management
Case Study - Project Management Case Study - Project Management
Case Study - Project Management
 
Project Management Case Study .EC Harris International Ltd. (Al Wahda Mast...
Project Management Case Study .EC Harris International Ltd.   (Al Wahda Mast...Project Management Case Study .EC Harris International Ltd.   (Al Wahda Mast...
Project Management Case Study .EC Harris International Ltd. (Al Wahda Mast...
 
Project Management case analysis
Project Management case analysisProject Management case analysis
Project Management case analysis
 
Case study for project management-Triple constraints
Case study for project management-Triple constraintsCase study for project management-Triple constraints
Case study for project management-Triple constraints
 
Project Case Study Sample
Project Case Study SampleProject Case Study Sample
Project Case Study Sample
 
Project Management Case Studies by Terry Hall
Project Management Case Studies by Terry HallProject Management Case Studies by Terry Hall
Project Management Case Studies by Terry Hall
 
Lego Outsourcing
Lego OutsourcingLego Outsourcing
Lego Outsourcing
 
LEGO- Niche MArketing
LEGO- Niche MArketingLEGO- Niche MArketing
LEGO- Niche MArketing
 
Project management
Project managementProject management
Project management
 

Similar to Team Optimus_IIM K

Petrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydPetrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj Lloyd
Nitin Sethi
 
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
irvan septyan mulyana
 
Presentation on project plan for tyre recycling plant
Presentation on project plan for tyre recycling plantPresentation on project plan for tyre recycling plant
Presentation on project plan for tyre recycling plant
abhishekthakur309
 
Shailendra_Kumar_Resume_V01__1_
Shailendra_Kumar_Resume_V01__1_Shailendra_Kumar_Resume_V01__1_
Shailendra_Kumar_Resume_V01__1_
shailendra kumar
 
RESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARRESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIAR
SAQIB MANIAR
 
RESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARRESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIAR
SAQIB MANIAR
 

Similar to Team Optimus_IIM K (20)

Solar Power Plant Procurements
Solar Power Plant ProcurementsSolar Power Plant Procurements
Solar Power Plant Procurements
 
Petrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydPetrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj Lloyd
 
Experienced Sourcing professional with 10years Exp- Material/vendor Management
Experienced Sourcing professional with 10years Exp- Material/vendor ManagementExperienced Sourcing professional with 10years Exp- Material/vendor Management
Experienced Sourcing professional with 10years Exp- Material/vendor Management
 
Why EPC
Why EPCWhy EPC
Why EPC
 
Implementation of Business Process Reengineering in Thermax Ltd.
Implementation of Business Process Reengineering in Thermax Ltd.Implementation of Business Process Reengineering in Thermax Ltd.
Implementation of Business Process Reengineering in Thermax Ltd.
 
MSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdfMSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdf
 
MSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdfMSC Lec 06 - Construction Site Management.pdf
MSC Lec 06 - Construction Site Management.pdf
 
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
Best_Practices_in_CMM_Utilization_-_Achieving_Near-Zero_Methane_Emissions_fro...
 
Presentation on project plan for tyre recycling plant
Presentation on project plan for tyre recycling plantPresentation on project plan for tyre recycling plant
Presentation on project plan for tyre recycling plant
 
Shailendra_Kumar_Resume_V01__1_
Shailendra_Kumar_Resume_V01__1_Shailendra_Kumar_Resume_V01__1_
Shailendra_Kumar_Resume_V01__1_
 
RESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARRESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIAR
 
sounder
soundersounder
sounder
 
CV-Sounder
CV-SounderCV-Sounder
CV-Sounder
 
BlueScape Get the Air Permit for Energy Projects Webinar 9-10-13
BlueScape Get the Air Permit for Energy Projects Webinar 9-10-13BlueScape Get the Air Permit for Energy Projects Webinar 9-10-13
BlueScape Get the Air Permit for Energy Projects Webinar 9-10-13
 
Kalpak Mechanical Engineering Project Portfolio
Kalpak Mechanical Engineering Project PortfolioKalpak Mechanical Engineering Project Portfolio
Kalpak Mechanical Engineering Project Portfolio
 
05 Project Monitoring &amp; Cost Control
05 Project Monitoring &amp; Cost Control05 Project Monitoring &amp; Cost Control
05 Project Monitoring &amp; Cost Control
 
Project Management- Unit III
Project Management- Unit IIIProject Management- Unit III
Project Management- Unit III
 
Pranav.Varshney
Pranav.VarshneyPranav.Varshney
Pranav.Varshney
 
RESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARRESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIAR
 
Supply chain management in project
Supply chain management in projectSupply chain management in project
Supply chain management in project
 

Recently uploaded

The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
daisycvs
 

Recently uploaded (20)

SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Puri CALL GIRL ❤️8084732287❤️ CALL GIRLS IN ESCORT SERVICE WE ARW PROVIDING
Puri CALL GIRL ❤️8084732287❤️ CALL GIRLS IN ESCORT SERVICE WE ARW PROVIDINGPuri CALL GIRL ❤️8084732287❤️ CALL GIRLS IN ESCORT SERVICE WE ARW PROVIDING
Puri CALL GIRL ❤️8084732287❤️ CALL GIRLS IN ESCORT SERVICE WE ARW PROVIDING
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
Chandrapur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Chandrapur Call Girl Just Call 8084732287 Top Class Call Girl Service AvailableChandrapur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Chandrapur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
PITHAMPUR 💋 Call Girl 9827461493 Call Girls in Escort service book now
PITHAMPUR 💋 Call Girl 9827461493 Call Girls in  Escort service book nowPITHAMPUR 💋 Call Girl 9827461493 Call Girls in  Escort service book now
PITHAMPUR 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptxQSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
 
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
 
SRI GANGANAGAR 💋 Call Girl 9827461493 Call Girls in Escort service book now
SRI GANGANAGAR 💋 Call Girl 9827461493 Call Girls in  Escort service book nowSRI GANGANAGAR 💋 Call Girl 9827461493 Call Girls in  Escort service book now
SRI GANGANAGAR 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
Nanded Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Nanded Call Girl Just Call 8084732287 Top Class Call Girl Service AvailableNanded Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Nanded Call Girl Just Call 8084732287 Top Class Call Girl Service Available
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
 
HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Cuttack Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Cuttack Call Girl Just Call 8084732287 Top Class Call Girl Service AvailableCuttack Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Cuttack Call Girl Just Call 8084732287 Top Class Call Girl Service Available
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
Home Furnishings Ecommerce Platform Short Pitch 2024
Home Furnishings Ecommerce Platform Short Pitch 2024Home Furnishings Ecommerce Platform Short Pitch 2024
Home Furnishings Ecommerce Platform Short Pitch 2024
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 

Team Optimus_IIM K

  • 1. L&T Case Study Team Optimus – KJ SIMSR Amit Divekar, Pravin Bokil, Jitendarkumar Panda
  • 2. Case – Hydropower Project Up-gradation of existing system of the plant • Hydro-electric plant with surface Penstock system • Capacity : 4*72 MW power station • Contract to replace current surface penstock system with combination of surface penstock and steel lined tunnel • Contract value- Rs. 44.88 Cr. For a period- 42 months • Estimated Project Timeline 15-02-02 to 14-08-2005 • Contract Type- Item rate contract • Carry out the work without interrupting the power generation • Activities : Tunneling, Fabrication and Erection of penstocks
  • 3. Factors that forced up-gradation • Increasing age of the existing system resulting in higher Maintenance Cost & Cleaning Cost • Reduction in operating efficiency • Surface penstock vulnerable to damage • Cost of security and inspection • Threat of miscreants • Resultant damage to society • Damage cost > Project Cost (refer - Cost calculation for client)
  • 4. Calculation of Cost for Client • . Production Capacity 288 MW Min loss (1 unit shutdown) 72 MW Max loss (station shutdown) 288 MW Plant operation per day(if base load) 24 hrs Plant operation per day (if peaking load) 6 hrs Worst case loss of sale per day 6912 MW-hrs Least loss of sale per day 432 MW-hrs Unit cost of electricity in year 2002 1.42 Rs per unit (KW-Hr) Assumption- 50% revenue for power producer considering share of discoms 0.71 Total loss of sale per day(worst case) 4907520 Rs Total loss of sale per day(least loss) 306720 Rs project cost 448800000 Rs
  • 6. Risks For Contractor • Delay due to blasting & drilling • Extra cost for blasting work – Hard strata • Delay in removal of muck • Quality control work resulting in time delay & cost overrun • Inventory control- wastage & reconciliation • Delay due to erection difficulties • Concreting issues- Quality & cost implications
  • 7. Delay due to Blasting & Drilling • 6 months advancement achieved with revised charge calculation • Time Risk associated – 1.33 Cr • % of contract value – 2.97 • Customer taken into confidence while implementation of new idea   Tunneling Fabrication Erection time  in months 15 21 14 total mandays  Utilised 59805 79125 70650 cost 40981749 54220899 48413352
  • 8. Risk in Fabrication • Purchase of material in client’s scope • Limited material quantity available with contractor • Improper inventory or material management has potential risk of material shortage • Ordering after shortage has risk of high lead time • Risk of incurring high cost of raw material • Cost of risk > 1% of contract value • Probability is moderate as it can only be result of inefficient management
  • 9. Force Majeure • Common clause in contracts that essentially frees both parties from liability or obligation • When – In case of an extraordinary event • Circumstance beyond the control of the parties, such as a war, strike, riot, crime, act of God • Does not excuse a party's non-performance entirely, but only suspends it for the duration of the force majeure
  • 10. Risk Evaluation Framework Catastrophic S>2 Major 1<S<2 Significant 0.5<S<1 Minor 0.25<S<0.5 Insignificant S<0.25 Certain P>0.9 Likely 0.5<P<0.9 Delay due to Blasting & Drilling Moderate 0.1<P<0.5 Cost overrun in fabrication Unlikely 0.03<P<0.1 Rare P<0.03 Force Majeure Identification Force Majeure Identification Severity (S) Probability –P % of total contract value Probability of occurring identified risk event
  • 11. Best Practices Mitigating Risks • Menamite instrument to control sound and vibration limits • Changes in drilling pattern and charge factor as per existing ground conditions • Headgear System to improve efficiency of mucking operations • Dedicated fabrication workshops • Use of rubber closures during testing process • Turntable for erection of penstocks • Implementing value stream mapping for waste reduction
  • 12. Productivity Rate and Associated Cost Savings • Total man days planned- 3.45 Lac • Total Man days required- 2.09 Lac • Saved man days- 39.12% Microsoft Office Excel Worksheet
  • 13. Strategy • De-risking at the Bid Stage – Scope clarification • During execution – Close follow up • De-risking via Communicating Contractual Issues • De-risking Issues at Project Completion Stage • Knowledge Management- To capture the innovative practices adopted in project to be replicated in other projects • Organizational policies to foster the culture of innovation • Preparation of standardized WBS with schedule
  • 14. Competitive Price Bid • Total Contract Value: 44.88 Crores • Total Cost (20% margin): 35.90 Crores • Total Labor Cost (40% of total Cost): 14.36 Crores • Total Labor cost saved: 40% • Assuming that the total cost saved is proportional to the labor cost of the particular activity • Work Breakdown Structure New Bid •Cost Saving incorporated in the bidding stage: Muck Removing, Testing and alignment •New Labor Cost: 11.76 Crores •Total Cost: 33.30 Crores •Total Bid Price: 39.96 Crores (20% margin)