CH- 4 DRAINAGE AND
MAINTENANCE OF ROAD
1
 Highway drainage is a process of removing and
controlling excess surface and sub-soil water
within the right of way.
 It includes interception and diversion of water from
the road surface and sub grade.
2
 Excess moisture in soil subgrade causes considerable lowering
of its stability.
 Increase in moisture cause reduction in strength of many
pavement materials like stabilized soil and water bound
macadam.
 Sustained contact of water with bituminous pavements causes
failure due to stripping of bitumen from aggregates like loosening
or detachment of some of the bituminous pavement layers and
formations of pot holes
 Excess water on shoulders and pavement edges causes
considerable damage.
3
 Adjoining land
 Camber
 Gradient
 Cross drainage works
 Highest flood level
 Side drains
 Intercepting drains
 Water table
 Underground source of water 4
 Removal and diversion of surface water from the road
way and adjoining land is termed as surface drainage.
 Diversion and removal of excess of soil water from the
subgrade is termed as Surface Drainage.
5
1. By Longitudinal side drains.
2. Catch basins and Inlets in urbanareas
3. Providing damp proof course
4. Providing proper camber
5. Providing sufficient slope to the sides
6. Keeping the level of carriage way at least 60 cm above the HFL.
6
A) Side drains for road inembankment
-
7
 It is necessary to provide side drain on one side or both
sides, when road is constructed in embankment.
 Side drains should be at least 2.0 m away from bottom
edge of an embankment.
 Depth of side drains is kept 1.0 to 1.5 m to prevent
the entry of drain water into the embankment.
8
 B) Side drains for road in cutting
9
 A) Catch basins
10
 Catch basin is a structure like chamber constructed on a
sewer line.
 Water from pavement surface is collected in catch basin
and discharged to the sewer line.
 The catch basin (catch pit) is provided with grating to
prevent the entry of rubbish into the drainage system.
11
 Inlets is a concrete box with grating either at the top or in the
side.
12
 Removal or Diversion of excess soil-water from sub-grade is
termed as sub-surface drainage.
13
 When road is in cutting and water seeping from sides.
 When road is near the foot or hill and is likely to be damaged by
water flowing down the hill.
 When road is passing through plain area and water is likely
to accumulated on sides.
 Where water rises up to sub-grade by capillary action.
 Where sub-grade soil is affected by the drain passing near the
road.
Lowering ofWater
Table
ControllingSeepage
Flow
ControllingCapillary
Water
14
 In order to that the sub-grade and pavement are not
subjected to excessive moisture the water table should kept
at least 1.0 to 1.2 m below the sub-grade.
 In places where water table is high to take the road formation
on embankment of height not less than 1.0-1.2m is the best
approach.
 But When the formation level is at or below the general ground
level it is
necessary to lower the water table.
15
(a) If soil is relatively permeable, it may be possible to
lower WT by constructing longitudinal drainage trenches
with drain pipe and filter sand and top of trenches is
covered with clay seal
The depth of trench depend on:
(i) The required lowering of water table
(ii) distance b/w the drainage trenches
(iii)Types of soil
16
17
(b) If the soil is relatively
less permeable, the
lowering of groundWT
may not be adequate.
Hence in addition to the
longitudinal drains
traverse drains have to be
installed at suitable
intervals in effectively
drain off the water.
18
 When the general ground as well as impervious
strata below are sloping, seepage flow is likely to
exist.
 If seepage zone is at depth less than 0.6-0.9 m
from sub-grade level, longitudinal pipe drain in
trench filled with filter material and clay seal may
be constructed to intercept the flow.
19
20
 If the water reaching the sub-grade due to capillary rise is likely to
be detrimental, it is possible to solve the problem by arresting
the capillary rise.
 It can be done by following methods:
(a)A layer of granular materials of suitable thickness is provided
during the construction of embankment, between the sub-grade
and the highest level of sub surface water table.
(b)Alternate method is providing the capillary cut off is by
inserting an impermeable or a bituminous layer in place of
granular blanket.
21
22
23
Maintenance of surface and subsurface
drainage system
1.By cleaning drains
2. Controlling erosion of
drain
24

More Related Content

What's hot

Cross section of the canal, balancing depth and canal fsl
Cross section of the canal, balancing depth  and canal fslCross section of the canal, balancing depth  and canal fsl
Cross section of the canal, balancing depth and canal fslAditya Mistry
 
Canal outlets and modules
Canal outlets and modulesCanal outlets and modules
Canal outlets and modulesbhalinder singh
 
Flexible pavement presentation
Flexible pavement presentationFlexible pavement presentation
Flexible pavement presentationPawan Kumar
 
Types of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. ITypes of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. IGauri kadam
 
GROUND IMPROVEMENT-DENSIFICATION METHODS
GROUND IMPROVEMENT-DENSIFICATION METHODSGROUND IMPROVEMENT-DENSIFICATION METHODS
GROUND IMPROVEMENT-DENSIFICATION METHODSramgsvhce
 
Canal falls and its classification
Canal falls and its classificationCanal falls and its classification
Canal falls and its classificationGNANA PRAKASH
 
Canal outlets
Canal outletsCanal outlets
Canal outletssaibabu48
 
Canal regulation works. m4pptx
Canal regulation works. m4pptxCanal regulation works. m4pptx
Canal regulation works. m4pptxBibhabasu Mohanty
 
LOW LEVEL & HIGH LEVEL CAUSEWAY
LOW LEVEL & HIGH LEVEL CAUSEWAYLOW LEVEL & HIGH LEVEL CAUSEWAY
LOW LEVEL & HIGH LEVEL CAUSEWAYGhulam Yasin
 
Highway Cross-sectional Elements
Highway Cross-sectional ElementsHighway Cross-sectional Elements
Highway Cross-sectional ElementsAkshathaBhandary
 
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTUVATSAL PATEL
 
Types of failure in rigid pavements
Types of failure in rigid pavementsTypes of failure in rigid pavements
Types of failure in rigid pavementsAglaia Connect
 
Laying and Testing of sewer
Laying and Testing of sewerLaying and Testing of sewer
Laying and Testing of sewersathyan s
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundationsDar Hilal
 

What's hot (20)

Cross section of the canal, balancing depth and canal fsl
Cross section of the canal, balancing depth  and canal fslCross section of the canal, balancing depth  and canal fsl
Cross section of the canal, balancing depth and canal fsl
 
Highway drainage
Highway drainageHighway drainage
Highway drainage
 
Canal outlets and modules
Canal outlets and modulesCanal outlets and modules
Canal outlets and modules
 
Flexible pavement presentation
Flexible pavement presentationFlexible pavement presentation
Flexible pavement presentation
 
Types of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. ITypes of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. I
 
GROUND IMPROVEMENT-DENSIFICATION METHODS
GROUND IMPROVEMENT-DENSIFICATION METHODSGROUND IMPROVEMENT-DENSIFICATION METHODS
GROUND IMPROVEMENT-DENSIFICATION METHODS
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
 
Canal falls and its classification
Canal falls and its classificationCanal falls and its classification
Canal falls and its classification
 
Spillways
SpillwaysSpillways
Spillways
 
Canal outlets
Canal outletsCanal outlets
Canal outlets
 
Canal regulation works. m4pptx
Canal regulation works. m4pptxCanal regulation works. m4pptx
Canal regulation works. m4pptx
 
LOW LEVEL & HIGH LEVEL CAUSEWAY
LOW LEVEL & HIGH LEVEL CAUSEWAYLOW LEVEL & HIGH LEVEL CAUSEWAY
LOW LEVEL & HIGH LEVEL CAUSEWAY
 
Highway Cross-sectional Elements
Highway Cross-sectional ElementsHighway Cross-sectional Elements
Highway Cross-sectional Elements
 
Road drainage
Road drainageRoad drainage
Road drainage
 
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
 
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
 
Types of failure in rigid pavements
Types of failure in rigid pavementsTypes of failure in rigid pavements
Types of failure in rigid pavements
 
Laying and Testing of sewer
Laying and Testing of sewerLaying and Testing of sewer
Laying and Testing of sewer
 
3. earthen roads 30 aug
3. earthen roads 30 aug3. earthen roads 30 aug
3. earthen roads 30 aug
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundations
 

Similar to Chapter 4 Drainge and maintenance of road

Chapter Four -4 Highway Drainage slide.pdf
Chapter Four -4 Highway Drainage slide.pdfChapter Four -4 Highway Drainage slide.pdf
Chapter Four -4 Highway Drainage slide.pdfrajundauliya
 
Module 5: Highway Drainage and Highway Economics
Module 5: Highway Drainage and Highway EconomicsModule 5: Highway Drainage and Highway Economics
Module 5: Highway Drainage and Highway EconomicsDhananjayM6
 
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...VATSAL PATEL
 
Water logging.pptx
Water logging.pptxWater logging.pptx
Water logging.pptxEmaan Sharma
 
3. Highway Drainage.pdf
3. Highway Drainage.pdf3. Highway Drainage.pdf
3. Highway Drainage.pdfRoshani Shahi
 
Ground water recharge & water logging
Ground water recharge & water loggingGround water recharge & water logging
Ground water recharge & water loggingNIKHIL PAKWANNE
 
Ground water recharge & water logging by Nikhil Pakwanne
Ground water recharge & water logging by Nikhil PakwanneGround water recharge & water logging by Nikhil Pakwanne
Ground water recharge & water logging by Nikhil PakwanneNIKHIL PAKWANNE
 
Highway drainage system
Highway drainage systemHighway drainage system
Highway drainage systemmadhvitilgam
 
Canal of design
Canal of designCanal of design
Canal of designPREMKUMAR
 
Modes of failure earth dams
Modes of failure   earth damsModes of failure   earth dams
Modes of failure earth damssaibabu48
 
IMPORTANCE OF DRAINAGE IN IRRIGATED AREAS
IMPORTANCE OF DRAINAGE IN IRRIGATED AREASIMPORTANCE OF DRAINAGE IN IRRIGATED AREAS
IMPORTANCE OF DRAINAGE IN IRRIGATED AREASYallanagouda Madagoudra
 

Similar to Chapter 4 Drainge and maintenance of road (20)

Chapter Four -4 Highway Drainage slide.pdf
Chapter Four -4 Highway Drainage slide.pdfChapter Four -4 Highway Drainage slide.pdf
Chapter Four -4 Highway Drainage slide.pdf
 
Highway drainage
Highway drainageHighway drainage
Highway drainage
 
Module 5: Highway Drainage and Highway Economics
Module 5: Highway Drainage and Highway EconomicsModule 5: Highway Drainage and Highway Economics
Module 5: Highway Drainage and Highway Economics
 
To be presented
To be presentedTo be presented
To be presented
 
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
 
Drainage system
Drainage systemDrainage system
Drainage system
 
Water logging.pptx
Water logging.pptxWater logging.pptx
Water logging.pptx
 
chapt 6.pptx
chapt 6.pptxchapt 6.pptx
chapt 6.pptx
 
3. Highway Drainage.pdf
3. Highway Drainage.pdf3. Highway Drainage.pdf
3. Highway Drainage.pdf
 
3. Highway Drainage.pdf
3. Highway Drainage.pdf3. Highway Drainage.pdf
3. Highway Drainage.pdf
 
20160716_WATER SUPPLY.ppt
20160716_WATER SUPPLY.ppt20160716_WATER SUPPLY.ppt
20160716_WATER SUPPLY.ppt
 
Ground water recharge & water logging
Ground water recharge & water loggingGround water recharge & water logging
Ground water recharge & water logging
 
Ground water recharge & water logging by Nikhil Pakwanne
Ground water recharge & water logging by Nikhil PakwanneGround water recharge & water logging by Nikhil Pakwanne
Ground water recharge & water logging by Nikhil Pakwanne
 
Lecture 8
Lecture 8Lecture 8
Lecture 8
 
Water logging
Water loggingWater logging
Water logging
 
Highway drainage system
Highway drainage systemHighway drainage system
Highway drainage system
 
Drainage
DrainageDrainage
Drainage
 
Canal of design
Canal of designCanal of design
Canal of design
 
Modes of failure earth dams
Modes of failure   earth damsModes of failure   earth dams
Modes of failure earth dams
 
IMPORTANCE OF DRAINAGE IN IRRIGATED AREAS
IMPORTANCE OF DRAINAGE IN IRRIGATED AREASIMPORTANCE OF DRAINAGE IN IRRIGATED AREAS
IMPORTANCE OF DRAINAGE IN IRRIGATED AREAS
 

More from KHUSHBU SHAH

PLANE TABLE SURVEY
PLANE TABLE SURVEYPLANE TABLE SURVEY
PLANE TABLE SURVEYKHUSHBU SHAH
 
DEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKDEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKKHUSHBU SHAH
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge EngineeringKHUSHBU SHAH
 
Chapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackChapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackKHUSHBU SHAH
 
Chapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yardsChapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yardsKHUSHBU SHAH
 
Chapter 5 Introduction to railway
Chapter 5 Introduction to railwayChapter 5 Introduction to railway
Chapter 5 Introduction to railwayKHUSHBU SHAH
 
Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometricsKHUSHBU SHAH
 
Chapter 1 Introduction to road
Chapter 1 Introduction to roadChapter 1 Introduction to road
Chapter 1 Introduction to roadKHUSHBU SHAH
 
Equipment management
Equipment managementEquipment management
Equipment managementKHUSHBU SHAH
 
Material management
Material managementMaterial management
Material managementKHUSHBU SHAH
 
Chapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipmentsChapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipmentsKHUSHBU SHAH
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formworkKHUSHBU SHAH
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsKHUSHBU SHAH
 
Chapter 2 coffer-dam
Chapter 2 coffer-damChapter 2 coffer-dam
Chapter 2 coffer-damKHUSHBU SHAH
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSKHUSHBU SHAH
 
Chapter 13 green building
Chapter 13 green buildingChapter 13 green building
Chapter 13 green buildingKHUSHBU SHAH
 
Chapter 12 special treatments
Chapter 12 special treatmentsChapter 12 special treatments
Chapter 12 special treatmentsKHUSHBU SHAH
 

More from KHUSHBU SHAH (20)

PLANE TABLE SURVEY
PLANE TABLE SURVEYPLANE TABLE SURVEY
PLANE TABLE SURVEY
 
DEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKDEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORK
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge Engineering
 
Chapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackChapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway track
 
Chapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yardsChapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yards
 
Chapter 5 Introduction to railway
Chapter 5 Introduction to railwayChapter 5 Introduction to railway
Chapter 5 Introduction to railway
 
Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometrics
 
Chapter 1 Introduction to road
Chapter 1 Introduction to roadChapter 1 Introduction to road
Chapter 1 Introduction to road
 
Equipment management
Equipment managementEquipment management
Equipment management
 
Labour management
Labour managementLabour management
Labour management
 
Material management
Material managementMaterial management
Material management
 
Chapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipmentsChapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipments
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavations
 
Chapter 3 caisson
Chapter 3 caissonChapter 3 caisson
Chapter 3 caisson
 
Chapter 2 coffer-dam
Chapter 2 coffer-damChapter 2 coffer-dam
Chapter 2 coffer-dam
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
 
Chapter 13 green building
Chapter 13 green buildingChapter 13 green building
Chapter 13 green building
 
Chapter 12 special treatments
Chapter 12 special treatmentsChapter 12 special treatments
Chapter 12 special treatments
 

Recently uploaded

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 

Recently uploaded (20)

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 

Chapter 4 Drainge and maintenance of road

  • 1. CH- 4 DRAINAGE AND MAINTENANCE OF ROAD 1
  • 2.  Highway drainage is a process of removing and controlling excess surface and sub-soil water within the right of way.  It includes interception and diversion of water from the road surface and sub grade. 2
  • 3.  Excess moisture in soil subgrade causes considerable lowering of its stability.  Increase in moisture cause reduction in strength of many pavement materials like stabilized soil and water bound macadam.  Sustained contact of water with bituminous pavements causes failure due to stripping of bitumen from aggregates like loosening or detachment of some of the bituminous pavement layers and formations of pot holes  Excess water on shoulders and pavement edges causes considerable damage. 3
  • 4.  Adjoining land  Camber  Gradient  Cross drainage works  Highest flood level  Side drains  Intercepting drains  Water table  Underground source of water 4
  • 5.  Removal and diversion of surface water from the road way and adjoining land is termed as surface drainage.  Diversion and removal of excess of soil water from the subgrade is termed as Surface Drainage. 5
  • 6. 1. By Longitudinal side drains. 2. Catch basins and Inlets in urbanareas 3. Providing damp proof course 4. Providing proper camber 5. Providing sufficient slope to the sides 6. Keeping the level of carriage way at least 60 cm above the HFL. 6
  • 7. A) Side drains for road inembankment - 7
  • 8.  It is necessary to provide side drain on one side or both sides, when road is constructed in embankment.  Side drains should be at least 2.0 m away from bottom edge of an embankment.  Depth of side drains is kept 1.0 to 1.5 m to prevent the entry of drain water into the embankment. 8
  • 9.  B) Side drains for road in cutting 9
  • 10.  A) Catch basins 10
  • 11.  Catch basin is a structure like chamber constructed on a sewer line.  Water from pavement surface is collected in catch basin and discharged to the sewer line.  The catch basin (catch pit) is provided with grating to prevent the entry of rubbish into the drainage system. 11
  • 12.  Inlets is a concrete box with grating either at the top or in the side. 12
  • 13.  Removal or Diversion of excess soil-water from sub-grade is termed as sub-surface drainage. 13  When road is in cutting and water seeping from sides.  When road is near the foot or hill and is likely to be damaged by water flowing down the hill.  When road is passing through plain area and water is likely to accumulated on sides.  Where water rises up to sub-grade by capillary action.  Where sub-grade soil is affected by the drain passing near the road.
  • 15.  In order to that the sub-grade and pavement are not subjected to excessive moisture the water table should kept at least 1.0 to 1.2 m below the sub-grade.  In places where water table is high to take the road formation on embankment of height not less than 1.0-1.2m is the best approach.  But When the formation level is at or below the general ground level it is necessary to lower the water table. 15
  • 16. (a) If soil is relatively permeable, it may be possible to lower WT by constructing longitudinal drainage trenches with drain pipe and filter sand and top of trenches is covered with clay seal The depth of trench depend on: (i) The required lowering of water table (ii) distance b/w the drainage trenches (iii)Types of soil 16
  • 17. 17
  • 18. (b) If the soil is relatively less permeable, the lowering of groundWT may not be adequate. Hence in addition to the longitudinal drains traverse drains have to be installed at suitable intervals in effectively drain off the water. 18
  • 19.  When the general ground as well as impervious strata below are sloping, seepage flow is likely to exist.  If seepage zone is at depth less than 0.6-0.9 m from sub-grade level, longitudinal pipe drain in trench filled with filter material and clay seal may be constructed to intercept the flow. 19
  • 20. 20
  • 21.  If the water reaching the sub-grade due to capillary rise is likely to be detrimental, it is possible to solve the problem by arresting the capillary rise.  It can be done by following methods: (a)A layer of granular materials of suitable thickness is provided during the construction of embankment, between the sub-grade and the highest level of sub surface water table. (b)Alternate method is providing the capillary cut off is by inserting an impermeable or a bituminous layer in place of granular blanket. 21
  • 22. 22
  • 23. 23 Maintenance of surface and subsurface drainage system 1.By cleaning drains 2. Controlling erosion of drain
  • 24. 24