SlideShare a Scribd company logo
Sampling of cement & Tests
PREPARED BY:
MAYUR .U. RAHANGDALE -202030018
Table of Content
 What is sampling
 Need of sampling
 cement
 Sampling of cement
 Process Inspection
 Lot Inspection
 Test of cement
What is sampling?
 Sampling is the removal from a given lot of material a portion that is representative of
the whole yet of convenient size for further analysis.
 It is done either by hand or by an equipment.
 Hand sampling is usually expensive, slow, and inaccurate, (so that it is generally applied
only where the material is not suitable for equipment sampling (slimy ore, for example)
or where machinery is either not available or too expensive to install.)
 Many different sampling devices are available, including shovels, pipe samplers, and
automatic machine samplers.
 For these sampling machines to provide an accurate representation of the whole lot, the
quantity of a single sample, the total number of samples, and the kind of samples taken
are of decisive importance.
Need of sampling
 Materials used in construction should be of good quality and to check whether a material
is standard or not, sampling and testing is important.
 Sampling can save time and money. A sample study is usually less expensive than a
census study and produces results at a relatively faster speed.
 Sampling remains the only choice when a test involves the destruction of the item under
study.
Sampling of cement
 Process Inspection
 For an in-process quality check for the intermediate and finished product during the
production process.
 Lot Inspection
 Lot Inspection will be generated at the time of production order release.
Process Inspection
 By Purchaser- To ensure its conformity to the specification requirements
 By Manufacturer- To ensure uniformity & reduce quality fluctuations to minimum.
 Methods of Drawing samples
Clinker-
a) Every hour from each kiln, immediately after coming out from cooling chamber.
b) After mixing all these hourly samples, a composite sample shall be made for a day.
c) From this small quantity is taken out for the chemical analysis.
d) Remaining clinker if pulverized after mixing it with gypsum & tested for the other
characteristics.
Process Inspection
Cement Grinding-
a) From grinding mill, Hourly for testing setting time and every alternate hour for fineness
test.
b) Remaining portions form hourly sample shall be mixed to be a composite sample of the
week & tested for the other characteristics, such as heat of hydration of cement.
Cement Packing-
a) From Packing machine, daily for testing fineness, setting time, soundness, compressive
strength and degree of whiteness.
b) Remaining portions form daily sample shall be mixed to be a composite sample of the week
& tested for the other characteristics, such as heat of hydration of cement.
Lot Inspection
 When Process Inspection cannot be made available or when the purchaser so desires, the
procedure of Lot Inspection shall be followed for judging conformity of the lot of
hydraulic cement.
 Recommended- cement should be sampled when it is in motion.
1. Sampling From Conveyors
2. Sampling from bulk storage
3. Sampling from skip’s hold
4. Sampling from wagons
5. Sampling from bags
Lot Inspection
 Sampling from conveyors
1. A lot shall be divided into sub lots at the time of discharging over
a conveyor belt.
2. Then a gross sample is drawn from each of the sub lots & shall be
kept separately.
3. The collecting frequency should be one increment for every 10
tons of discharged cement.
4. Mostly a scoop is used for the sampling from moving belts, which
can sweep across the cross section of the material & along the
belt.
5. After taking the increments out of sub lots, they shall be placed
directly on a moisture proof, air tight containers to avoid moisture
absorption & Aeration of sample.
No’s of sub lots into which a lot is to
be divided
Wt. of Lot (Tons) No’s of sub-lots
<100 2
101-200 3
201-300 4
301-500 5
501-1000 6
1001-2000 7
Lot Inspection
 Sampling from Bulk Storage i.e. silos
1. A lot shall be divided into sub lots depending upon the weight of the Lot
2. Then a gross sample is drawn from each of the sub lots when the cement is being charged into bulk
storage or at the time of discharging from the bulk storage.
3. Increment shall be taken from each opening.
4. The collecting frequency should be one increment for every 10 tons of discharged cement.
Lot Inspection
 Sampling from Ship’s Hold
1. A lot shall be divided into sub lots depending upon the weight of the Lot
2. For collecting samples from ship’s hold, i.e. for depths greater than 2 m, sampling pipe activated by
air jet is used.
3. Then a gross sample is drawn from each of the sub lots.
4. The collecting frequency should be one increment for every 10 tons of cement.
5. The increment shall be weight at least 2 kg.
Lot Inspection
 Sampling from Wagons
1. A lot shall be divided into sub lots depending upon the weight of the Lot
2. For collecting samples from wagons, i.e. for depths smaller than 2 m, Slotted-tube sampler is used.
3. Then a gross sample is drawn from at least six evenly distributed points in each selected wagon.
4. The increment shall be weight at least 2 kg.
5. After taking the increments out of wagons, they shall be placed directly on a moisture proof, air
tight containers to avoid moisture absorption & Aeration of sample.
Lot Inspection
 Sampling from Bags
1. A lot shall be divided into sub lots depending upon the weight of the Lot.
2. at least 2 percent of the bags (minimum of five) shall be sampled.
3. Selection of bags should be random.
4. Tube sampler shall be inserted diagonally into the valve of the bag and the thumb placed over the
air hole and then shall be withdrawn.
5. Equal no’s of increments should be taken out from each bags.
6. The increment shall be weight at least 2 kg.
Sampling Equipments
Tube Sampler For Bags Slotted Tube sampler for bulk storage
Test on Cement
The following tests are conducted on cement in the laboratory are as follows:
1. Fineness Test
2. Consistency Test
3. Setting Time Test
4. Strength Test
5. Soundness Test
6. Heat of Hydration Test
7. Tensile Strength Test
8. Chemical Composition Test
Test on Cement
The following tests are conducted on cement in the field are as follows:
1. Colour Test of Cement
2. Presence of Lumps
3. Cement Adulteration Test
4. Float Test
5. Date of Manufacturing
Consistency Test of cement
 Aim: To determine consistency of standard Cement paste.
 Apparatus:
Consistency Test of cement
Material Used:
Cement material shall be stored in
sealed, airtight containers to avoid
changes in its characteristics due to
absorption or deposition from the
atmosphere.
Consistency Test of cement
 Procedure:
• Keep the vicat apparatus on a level base while using vicat apparatus with dashpot, keep the bearing
movable rod to its highest position and pin it. Unscrew the top of the dashpot. Half fill the dashpot
with any suitable oil of viscosity and screw the top. Work the plunger a number of times.
• Attach the plunger for determining standard consistency to the movable rod. Work the plunger a
number of times.
• Take 400 gm of cement in a pan and a weighed quantity of water in a beaker.
• Prepare a paste with the water added to cement. Start a stopwatch at the time of adding water to
cement.
• Keep the vicat mould on a non-porous plate and fill the cement paste in it.
Consistency Test of cement
 Procedure:
Consistency Test of cement
 Procedure:
Consistency Test of cement
 Procedure:
• After completely filling the mould, shake it slightly to expel the air. Smooth off the surface of the
paste making it level with the top of the moulder. The cement pastes thus prepared is the test block.
• Place the test block resting on the non-porous plate under the movable rod, bearing the needle.
• Lower the plunger gently to touch the surface of the cement paste and quickly release.
• Remove the pin holding the movable bearing rod to the surface of the cement paste and quickly
release by pushing down the plunger to sink in to the paste. This operation shall be done
immediately after filling the mould.
• Prepare trial test specimens with varying percentages of water until plunger penetrates to a point 5
to 7mm from the bottom of the vicat mould, which is read on the scale. Express the water required
as percentage by weight of the dry cement.
Consistency Test of cement
 Procedure:
Consistency Test of cement
 Observation Table:
SR. NO. DESCRIPTION READING
1. Weight of cement taken (g) (W1)
2. Quantity of water added to cement (W2)
3
Standard Consistency of Cement for 5-7 mm
penetration (W2/W1*100)
Consistency Test of cement
 Significance and importance of the test:
1. It determines the amount of water needed to make a paste. It is necessary to determine consistency
because the amount of water affects the setting time of the cement.
2. Consistency plays a vital role in the determination of compressive strength of concrete or
workability test for concrete.
3. Less water than this quantity would not complete chemical reaction thus resulting in the reduction
of strength and more water would increase water-cement ratio and so would reduce its strength.
Consistency Test of cement
 Why is Consistency Test Done?
We know that the cement we used on our site is mostly affected by
1. Weather Conditions
2. Excessive combination of Silica. One of the cement ingredients which determines the initial and final
setting time of cement paste.
3. The fineness of cement.
4. Manufacturing Defects
By Standardising the consistency of cement, we know that how much of water is required to produce an
effective cement which will eventually produce good quality of concrete.
 Aim :- Determination of the initial and final setting time of cement.
 Reference: - IS 4031 (Part-5):1988
 Appratus :-
Vicat apparatus, vicat mould, needle, gauging trowel, measuring jar, weighing balance,
stop watch, rubber glove, non porous glass plate.
 Material:- Ordinary Portland cement; Water.
Determination of Setting Times of Cement
Determination of Setting Times of Cement
Determination of Setting Times of Cement
 Theory :-
• The time to which cement can be moulded in any desired shape without losing it’s strength is called Initial setting time of
cement
or
• The time at which cement starts hardens and completely loses its plasticity is called Initial setting time of cement
or
• The time available for mixing the cement and placing it in position is an Initial setting time of cement.
or
• Initial set is a stage where the cement paste stiffens to such an extent that the Vicat needle is not permitted to move
down through the paste within 5 ± 0.5 mm measured from the bottom of the mould. The time elapsed between the
moments that the water is added to the cement to the initial set is regarded as initial setting time.
Determination of Setting Times of Cement
• The time at which cement completely loses its plasticity and became hard is a final setting time of
cement.
or
• The time taken by cement to gain its entire strength is a Final setting time of cement.
• For an ordinary Portland cement, the initial setting time should not be less than 30 minutes while the
final setting time should not be more than 600 minutes.
 Procedure :-
1) Preparation of Test Block
• Prepare a neat cement paste by gauging the cement with 0.85 times the water required to give a paste of standard
consistency. Potable or distilled water shall be used in preparing the paste. The paste shall be gauged in the manner and
under the conditions prescribed in IS : 4031 (Part 5)- 1988. Start a stop-watch at the instant when water is added to the
cement. Fill the Vicat mould with a cement paste gauged as above, the mould resting on a nonporous plate. Fill the mould
completely and smooth off the surface of the paste making it level with the top of the mould. The cement block thus
prepared in the mould is the test block.
• Immediately after moulding, place the test block in the moist closet or moist room and allow it to remain there except when
determinations of time of setting are being made.
Determination of Setting Times of Cement
2) Determination of Initial Setting Time
• Place the test block confined in the mould and resting on the non-porous plate, under the rod bearing the needle (with cross section
1 mm2 ).
• lower the needle gently until it comes in contact with the surface of the test block and quickly release, allowing it to penetrate into
the test block.
• In the beginning, the needle will completely pierce the test block. Repeat this procedure until the needle, when brought in contact
with the test block and released as described above, fails to pierce the block beyond 5.0 ± 0.5 mm measured from the bottom of the
mould.
• The period elapsing between the time when water is added to the cement and the time at which the needle fails to pierce the test
block to a point 5.0 ± 0.5 mm measured from the bottom of the mould shall be the initial setting time.
Determination of Setting Times of Cement
3) Determination of Final Setting Time —
• Replace the needle of the Vicat apparatus by the needle with an annular attachment .
• The cement shall be considered as finally set when, upon applying the needle gently to the surface of
the test block, the needle makes an impression thereon, while the attachment fails to do so.
• The period elapsing between the time when water is added to the cement and the time at which
,attachment fails to make an impression on the surface of test block shall be the final setting time.
Initial and Final Setting Time of Cement
 Observations:-
• Weight of given sample of cement is ___________ g.
• The normal consistency of a given sample of cement is ___________ %
• Volume of water taken(0.85 times the water required to give a paste of standard consistency) for
preparation of test block ____________ ml
Initial and Final Setting Time of Cement
Initial and Final Setting Time of Cement
 Precaution for Initial and Final setting time of cement test
• The needle should be cleaned after every use.
• The mould should be slightly moved so that the penetration would not be at the same place.
• The experiment should be carried out at a place where there is no external vibration or
disturbance.
• The mould should not have any type of movement from initial setting time to final setting time.
• The temperature of the room in which the experiment is conducted should be maintained
around 27º-29º C and hydration should be maintained in between 60-70%.
The End..!

More Related Content

What's hot

Lime
LimeLime
Factor effecting the strength of concrete
Factor effecting the strength of concreteFactor effecting the strength of concrete
Factor effecting the strength of concrete
DHANIK VIKRANT
 
Plain sedimentation tanks ,Types & Design considerations
Plain sedimentation tanks ,Types & Design considerations Plain sedimentation tanks ,Types & Design considerations
Plain sedimentation tanks ,Types & Design considerations
Anshika Saxena
 
Testing of stones
Testing of stonesTesting of stones
Testing of stones
Bahram Nawabi
 
Introduction to water supply engg. by Prof. D S.Shah
Introduction to water supply engg. by Prof. D S.ShahIntroduction to water supply engg. by Prof. D S.Shah
Introduction to water supply engg. by Prof. D S.Shah
dhavalsshah
 
Water demand
Water demandWater demand
Water demand
Riya2001998
 
Cement, Cement manufacturing, Types of cement
Cement, Cement manufacturing, Types of cementCement, Cement manufacturing, Types of cement
Cement, Cement manufacturing, Types of cement
Naresh Kumar
 
Collection of sewage & estimation of its discharge
Collection of sewage & estimation of its dischargeCollection of sewage & estimation of its discharge
Collection of sewage & estimation of its discharge
Rajdip Bhdaraka
 
Workability of Concrete
Workability  of ConcreteWorkability  of Concrete
Workability of Concrete
GulraizArshad1
 
Tests on cement
Tests on cementTests on cement
Tests on cement
FAREED AHMAD
 
02 Types of Intake Structures
02 Types of Intake Structures02 Types of Intake Structures
02 Types of Intake Structures
akashpadole
 
Manufacturing of cement
Manufacturing of cementManufacturing of cement
Manufacturing of cement
Pushpraj Choudhary
 
type of aggregate
type of aggregatetype of aggregate
type of aggregate
Anup Kude
 
Permeability test.pdf
Permeability test.pdfPermeability test.pdf
Permeability test.pdf
Natalie Ulza
 
Chapter 3 -consolidation notes
Chapter 3 -consolidation notesChapter 3 -consolidation notes
Chapter 3 -consolidation notes
DYPCET
 
Light Weight Concrete;High Density Concrete;High Performance Concrete by Dr.V...
Light Weight Concrete;High Density Concrete;High Performance Concrete by Dr.V...Light Weight Concrete;High Density Concrete;High Performance Concrete by Dr.V...
Light Weight Concrete;High Density Concrete;High Performance Concrete by Dr.V...
VIDYA VIKAS INSTITUTE OF ENGINEERING AND TECHNOLOGY
 
Sources of water supply
Sources of water supplySources of water supply
Sources of water supply
Tarun kumar
 
L 3 and l-4 water demand
L 3  and l-4 water demandL 3  and l-4 water demand
L 3 and l-4 water demand
Dr. shrikant jahagirdar
 
AGGREGATES & ITS PROPERTIES
AGGREGATES & ITS PROPERTIESAGGREGATES & ITS PROPERTIES
AGGREGATES & ITS PROPERTIES
Vishal Sharma
 

What's hot (20)

Lime
LimeLime
Lime
 
Factor effecting the strength of concrete
Factor effecting the strength of concreteFactor effecting the strength of concrete
Factor effecting the strength of concrete
 
Plain sedimentation tanks ,Types & Design considerations
Plain sedimentation tanks ,Types & Design considerations Plain sedimentation tanks ,Types & Design considerations
Plain sedimentation tanks ,Types & Design considerations
 
Testing of stones
Testing of stonesTesting of stones
Testing of stones
 
Introduction to water supply engg. by Prof. D S.Shah
Introduction to water supply engg. by Prof. D S.ShahIntroduction to water supply engg. by Prof. D S.Shah
Introduction to water supply engg. by Prof. D S.Shah
 
Water demand
Water demandWater demand
Water demand
 
Cement, Cement manufacturing, Types of cement
Cement, Cement manufacturing, Types of cementCement, Cement manufacturing, Types of cement
Cement, Cement manufacturing, Types of cement
 
Collection of sewage & estimation of its discharge
Collection of sewage & estimation of its dischargeCollection of sewage & estimation of its discharge
Collection of sewage & estimation of its discharge
 
Workability of Concrete
Workability  of ConcreteWorkability  of Concrete
Workability of Concrete
 
Tests on cement
Tests on cementTests on cement
Tests on cement
 
02 Types of Intake Structures
02 Types of Intake Structures02 Types of Intake Structures
02 Types of Intake Structures
 
Manufacturing of cement
Manufacturing of cementManufacturing of cement
Manufacturing of cement
 
type of aggregate
type of aggregatetype of aggregate
type of aggregate
 
Testing of cement
Testing of cementTesting of cement
Testing of cement
 
Permeability test.pdf
Permeability test.pdfPermeability test.pdf
Permeability test.pdf
 
Chapter 3 -consolidation notes
Chapter 3 -consolidation notesChapter 3 -consolidation notes
Chapter 3 -consolidation notes
 
Light Weight Concrete;High Density Concrete;High Performance Concrete by Dr.V...
Light Weight Concrete;High Density Concrete;High Performance Concrete by Dr.V...Light Weight Concrete;High Density Concrete;High Performance Concrete by Dr.V...
Light Weight Concrete;High Density Concrete;High Performance Concrete by Dr.V...
 
Sources of water supply
Sources of water supplySources of water supply
Sources of water supply
 
L 3 and l-4 water demand
L 3  and l-4 water demandL 3  and l-4 water demand
L 3 and l-4 water demand
 
AGGREGATES & ITS PROPERTIES
AGGREGATES & ITS PROPERTIESAGGREGATES & ITS PROPERTIES
AGGREGATES & ITS PROPERTIES
 

Similar to Sampling of cement ,Consistency test no cement ,Initial and final setting time of cement (VJTI MUMBAI)

Cement tests
Cement testsCement tests
Cement tests
Elijah Tasani
 
Buildingmaterialslabmanuallab01 161125043012
Buildingmaterialslabmanuallab01 161125043012Buildingmaterialslabmanuallab01 161125043012
Buildingmaterialslabmanuallab01 161125043012
Vijay Patidar
 
Buildingmaterialslabmanuallab01 161125043012 (1)
Buildingmaterialslabmanuallab01 161125043012 (1)Buildingmaterialslabmanuallab01 161125043012 (1)
Buildingmaterialslabmanuallab01 161125043012 (1)
Vijay Patidar
 
Building materials lab_manual lab 01
Building materials lab_manual  lab 01Building materials lab_manual  lab 01
Building materials lab_manual lab 01
Engr. Umair Razzaq
 
Properties of Concrete (cement)
Properties of Concrete (cement)Properties of Concrete (cement)
Properties of Concrete (cement)
Salman H. Sindhoo
 
Normal Consistency and Sitting times of cement paste
Normal Consistency and Sitting times of cement pasteNormal Consistency and Sitting times of cement paste
Normal Consistency and Sitting times of cement paste
Hafizullah Sadat
 
Ppt on test certificate-Amit Payal
Ppt on test certificate-Amit PayalPpt on test certificate-Amit Payal
Ppt on test certificate-Amit Payal
AMIT PAYAL
 
Standard test on fresh concrete
Standard test on fresh concreteStandard test on fresh concrete
Standard test on fresh concrete
Abhishek Shah
 
Cement Test.pdf
Cement Test.pdfCement Test.pdf
Cement Test.pdf
Piyush609360
 
Cement test
Cement testCement test
Cement test
Drawings Point
 
Practical-of-Construction-Material.pptx
Practical-of-Construction-Material.pptxPractical-of-Construction-Material.pptx
Practical-of-Construction-Material.pptx
LaxmiNarayanGurung
 
Tests of cement in concrete technology
Tests of cement in concrete technologyTests of cement in concrete technology
Tests of cement in concrete technology
Sunny Saha
 
Concrete Technology
Concrete TechnologyConcrete Technology
Concrete Technology
Love Sharma
 
Transportation-Engg.-LABORATORY_MANUAL.pdf
Transportation-Engg.-LABORATORY_MANUAL.pdfTransportation-Engg.-LABORATORY_MANUAL.pdf
Transportation-Engg.-LABORATORY_MANUAL.pdf
RESHMAFEGADE
 
Types of road material and its tests
Types of road material and its testsTypes of road material and its tests
Types of road material and its tests
Govt, Polytechnic Tekari, Gaya
 
Laboratory Instruction Manual for Civil Engineers
Laboratory Instruction Manual for Civil EngineersLaboratory Instruction Manual for Civil Engineers
Laboratory Instruction Manual for Civil Engineers
Phurba Tamang
 
Concrete lab manual - Polytechnics
Concrete lab manual - PolytechnicsConcrete lab manual - Polytechnics
Concrete lab manual - Polytechnics
SHAMJITH KM
 
Properties of concrete
Properties of concrete Properties of concrete
Properties of concrete
Salman H. Sindhoo
 
Strengthening of concrete columns made from recycled concrete aggregate
Strengthening of concrete columns made from recycled concrete aggregateStrengthening of concrete columns made from recycled concrete aggregate
Strengthening of concrete columns made from recycled concrete aggregate
nada khaled
 

Similar to Sampling of cement ,Consistency test no cement ,Initial and final setting time of cement (VJTI MUMBAI) (20)

Cement tests
Cement testsCement tests
Cement tests
 
Buildingmaterialslabmanuallab01 161125043012
Buildingmaterialslabmanuallab01 161125043012Buildingmaterialslabmanuallab01 161125043012
Buildingmaterialslabmanuallab01 161125043012
 
Buildingmaterialslabmanuallab01 161125043012 (1)
Buildingmaterialslabmanuallab01 161125043012 (1)Buildingmaterialslabmanuallab01 161125043012 (1)
Buildingmaterialslabmanuallab01 161125043012 (1)
 
Building materials lab_manual lab 01
Building materials lab_manual  lab 01Building materials lab_manual  lab 01
Building materials lab_manual lab 01
 
Properties of Concrete (cement)
Properties of Concrete (cement)Properties of Concrete (cement)
Properties of Concrete (cement)
 
Normal Consistency and Sitting times of cement paste
Normal Consistency and Sitting times of cement pasteNormal Consistency and Sitting times of cement paste
Normal Consistency and Sitting times of cement paste
 
Ppt on test certificate-Amit Payal
Ppt on test certificate-Amit PayalPpt on test certificate-Amit Payal
Ppt on test certificate-Amit Payal
 
Standard test on fresh concrete
Standard test on fresh concreteStandard test on fresh concrete
Standard test on fresh concrete
 
Cement Test.pdf
Cement Test.pdfCement Test.pdf
Cement Test.pdf
 
Cement test
Cement testCement test
Cement test
 
Practical-of-Construction-Material.pptx
Practical-of-Construction-Material.pptxPractical-of-Construction-Material.pptx
Practical-of-Construction-Material.pptx
 
Tests of cement in concrete technology
Tests of cement in concrete technologyTests of cement in concrete technology
Tests of cement in concrete technology
 
Concrete Technology
Concrete TechnologyConcrete Technology
Concrete Technology
 
Transportation-Engg.-LABORATORY_MANUAL.pdf
Transportation-Engg.-LABORATORY_MANUAL.pdfTransportation-Engg.-LABORATORY_MANUAL.pdf
Transportation-Engg.-LABORATORY_MANUAL.pdf
 
Types of road material and its tests
Types of road material and its testsTypes of road material and its tests
Types of road material and its tests
 
Laboratory Instruction Manual for Civil Engineers
Laboratory Instruction Manual for Civil EngineersLaboratory Instruction Manual for Civil Engineers
Laboratory Instruction Manual for Civil Engineers
 
Concrete lab manual - Polytechnics
Concrete lab manual - PolytechnicsConcrete lab manual - Polytechnics
Concrete lab manual - Polytechnics
 
Properties of concrete
Properties of concrete Properties of concrete
Properties of concrete
 
Strengthening of concrete columns made from recycled concrete aggregate
Strengthening of concrete columns made from recycled concrete aggregateStrengthening of concrete columns made from recycled concrete aggregate
Strengthening of concrete columns made from recycled concrete aggregate
 
Yawer
YawerYawer
Yawer
 

More from Mayur Rahangdale

Update Project Progress (MS PROJECT)
Update Project Progress (MS PROJECT)Update Project Progress (MS PROJECT)
Update Project Progress (MS PROJECT)
Mayur Rahangdale
 
RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)
Mayur Rahangdale
 
Linear Equation in one variable.pptx
Linear Equation in one variable.pptxLinear Equation in one variable.pptx
Linear Equation in one variable.pptx
Mayur Rahangdale
 
Water Absorption of Bricks
Water Absorption of BricksWater Absorption of Bricks
Water Absorption of Bricks
Mayur Rahangdale
 
Tests on Plywood (Tensile Test)
Tests on Plywood (Tensile Test)Tests on Plywood (Tensile Test)
Tests on Plywood (Tensile Test)
Mayur Rahangdale
 
Water quality monitoring in a smart city based on IOT
Water quality monitoring in a smart city based on IOTWater quality monitoring in a smart city based on IOT
Water quality monitoring in a smart city based on IOT
Mayur Rahangdale
 
Gps and its use in vehicle movement study in earthquake disaster management r...
Gps and its use in vehicle movement study in earthquake disaster management r...Gps and its use in vehicle movement study in earthquake disaster management r...
Gps and its use in vehicle movement study in earthquake disaster management r...
Mayur Rahangdale
 
GPS and its use in vehicle movement study in Earthquake Disaster Management
GPS and its use in vehicle movement study in Earthquake Disaster ManagementGPS and its use in vehicle movement study in Earthquake Disaster Management
GPS and its use in vehicle movement study in Earthquake Disaster Management
Mayur Rahangdale
 
Gannt chart of building by MS Project (VJTI MUMBAI)
Gannt chart of building by MS Project (VJTI MUMBAI)Gannt chart of building by MS Project (VJTI MUMBAI)
Gannt chart of building by MS Project (VJTI MUMBAI)
Mayur Rahangdale
 
Planning and scheduling of industrial building (VJTI MUMBAI)
Planning and scheduling of industrial building (VJTI MUMBAI)Planning and scheduling of industrial building (VJTI MUMBAI)
Planning and scheduling of industrial building (VJTI MUMBAI)
Mayur Rahangdale
 
Project Management Information System (VJTI MUMBAI)
Project Management Information System (VJTI MUMBAI)Project Management Information System (VJTI MUMBAI)
Project Management Information System (VJTI MUMBAI)
Mayur Rahangdale
 
Tunnel Engineering Report (VJTI MUMBAI)
Tunnel Engineering Report (VJTI MUMBAI)Tunnel Engineering Report (VJTI MUMBAI)
Tunnel Engineering Report (VJTI MUMBAI)
Mayur Rahangdale
 
Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)
Mayur Rahangdale
 
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
Mayur Rahangdale
 
A Case Study of Existing Institutional Building for Assessment and Repair (VJ...
A Case Study of Existing Institutional Building for Assessment and Repair (VJ...A Case Study of Existing Institutional Building for Assessment and Repair (VJ...
A Case Study of Existing Institutional Building for Assessment and Repair (VJ...
Mayur Rahangdale
 
Organization structure tata Steel (VJTI MUMBAI)
Organization structure tata Steel (VJTI MUMBAI)Organization structure tata Steel (VJTI MUMBAI)
Organization structure tata Steel (VJTI MUMBAI)
Mayur Rahangdale
 
Linear Regression Analysis method of Forecasting ,:- Management principle and...
Linear Regression Analysis method of Forecasting ,:- Management principle and...Linear Regression Analysis method of Forecasting ,:- Management principle and...
Linear Regression Analysis method of Forecasting ,:- Management principle and...
Mayur Rahangdale
 
G cans project report
G cans project reportG cans project report
G cans project report
Mayur Rahangdale
 
Civil engineering Seminar on G cans project japan.
Civil engineering Seminar on G cans project japan.Civil engineering Seminar on G cans project japan.
Civil engineering Seminar on G cans project japan.
Mayur Rahangdale
 
Steel Structure Design
Steel Structure DesignSteel Structure Design
Steel Structure Design
Mayur Rahangdale
 

More from Mayur Rahangdale (20)

Update Project Progress (MS PROJECT)
Update Project Progress (MS PROJECT)Update Project Progress (MS PROJECT)
Update Project Progress (MS PROJECT)
 
RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)
 
Linear Equation in one variable.pptx
Linear Equation in one variable.pptxLinear Equation in one variable.pptx
Linear Equation in one variable.pptx
 
Water Absorption of Bricks
Water Absorption of BricksWater Absorption of Bricks
Water Absorption of Bricks
 
Tests on Plywood (Tensile Test)
Tests on Plywood (Tensile Test)Tests on Plywood (Tensile Test)
Tests on Plywood (Tensile Test)
 
Water quality monitoring in a smart city based on IOT
Water quality monitoring in a smart city based on IOTWater quality monitoring in a smart city based on IOT
Water quality monitoring in a smart city based on IOT
 
Gps and its use in vehicle movement study in earthquake disaster management r...
Gps and its use in vehicle movement study in earthquake disaster management r...Gps and its use in vehicle movement study in earthquake disaster management r...
Gps and its use in vehicle movement study in earthquake disaster management r...
 
GPS and its use in vehicle movement study in Earthquake Disaster Management
GPS and its use in vehicle movement study in Earthquake Disaster ManagementGPS and its use in vehicle movement study in Earthquake Disaster Management
GPS and its use in vehicle movement study in Earthquake Disaster Management
 
Gannt chart of building by MS Project (VJTI MUMBAI)
Gannt chart of building by MS Project (VJTI MUMBAI)Gannt chart of building by MS Project (VJTI MUMBAI)
Gannt chart of building by MS Project (VJTI MUMBAI)
 
Planning and scheduling of industrial building (VJTI MUMBAI)
Planning and scheduling of industrial building (VJTI MUMBAI)Planning and scheduling of industrial building (VJTI MUMBAI)
Planning and scheduling of industrial building (VJTI MUMBAI)
 
Project Management Information System (VJTI MUMBAI)
Project Management Information System (VJTI MUMBAI)Project Management Information System (VJTI MUMBAI)
Project Management Information System (VJTI MUMBAI)
 
Tunnel Engineering Report (VJTI MUMBAI)
Tunnel Engineering Report (VJTI MUMBAI)Tunnel Engineering Report (VJTI MUMBAI)
Tunnel Engineering Report (VJTI MUMBAI)
 
Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)
 
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
 
A Case Study of Existing Institutional Building for Assessment and Repair (VJ...
A Case Study of Existing Institutional Building for Assessment and Repair (VJ...A Case Study of Existing Institutional Building for Assessment and Repair (VJ...
A Case Study of Existing Institutional Building for Assessment and Repair (VJ...
 
Organization structure tata Steel (VJTI MUMBAI)
Organization structure tata Steel (VJTI MUMBAI)Organization structure tata Steel (VJTI MUMBAI)
Organization structure tata Steel (VJTI MUMBAI)
 
Linear Regression Analysis method of Forecasting ,:- Management principle and...
Linear Regression Analysis method of Forecasting ,:- Management principle and...Linear Regression Analysis method of Forecasting ,:- Management principle and...
Linear Regression Analysis method of Forecasting ,:- Management principle and...
 
G cans project report
G cans project reportG cans project report
G cans project report
 
Civil engineering Seminar on G cans project japan.
Civil engineering Seminar on G cans project japan.Civil engineering Seminar on G cans project japan.
Civil engineering Seminar on G cans project japan.
 
Steel Structure Design
Steel Structure DesignSteel Structure Design
Steel Structure Design
 

Recently uploaded

AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Basic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparelBasic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparel
top1002
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 

Recently uploaded (20)

AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Basic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparelBasic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparel
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 

Sampling of cement ,Consistency test no cement ,Initial and final setting time of cement (VJTI MUMBAI)

  • 1. Sampling of cement & Tests PREPARED BY: MAYUR .U. RAHANGDALE -202030018
  • 2. Table of Content  What is sampling  Need of sampling  cement  Sampling of cement  Process Inspection  Lot Inspection  Test of cement
  • 3. What is sampling?  Sampling is the removal from a given lot of material a portion that is representative of the whole yet of convenient size for further analysis.  It is done either by hand or by an equipment.  Hand sampling is usually expensive, slow, and inaccurate, (so that it is generally applied only where the material is not suitable for equipment sampling (slimy ore, for example) or where machinery is either not available or too expensive to install.)  Many different sampling devices are available, including shovels, pipe samplers, and automatic machine samplers.  For these sampling machines to provide an accurate representation of the whole lot, the quantity of a single sample, the total number of samples, and the kind of samples taken are of decisive importance.
  • 4. Need of sampling  Materials used in construction should be of good quality and to check whether a material is standard or not, sampling and testing is important.  Sampling can save time and money. A sample study is usually less expensive than a census study and produces results at a relatively faster speed.  Sampling remains the only choice when a test involves the destruction of the item under study.
  • 5. Sampling of cement  Process Inspection  For an in-process quality check for the intermediate and finished product during the production process.  Lot Inspection  Lot Inspection will be generated at the time of production order release.
  • 6. Process Inspection  By Purchaser- To ensure its conformity to the specification requirements  By Manufacturer- To ensure uniformity & reduce quality fluctuations to minimum.  Methods of Drawing samples Clinker- a) Every hour from each kiln, immediately after coming out from cooling chamber. b) After mixing all these hourly samples, a composite sample shall be made for a day. c) From this small quantity is taken out for the chemical analysis. d) Remaining clinker if pulverized after mixing it with gypsum & tested for the other characteristics.
  • 7. Process Inspection Cement Grinding- a) From grinding mill, Hourly for testing setting time and every alternate hour for fineness test. b) Remaining portions form hourly sample shall be mixed to be a composite sample of the week & tested for the other characteristics, such as heat of hydration of cement. Cement Packing- a) From Packing machine, daily for testing fineness, setting time, soundness, compressive strength and degree of whiteness. b) Remaining portions form daily sample shall be mixed to be a composite sample of the week & tested for the other characteristics, such as heat of hydration of cement.
  • 8. Lot Inspection  When Process Inspection cannot be made available or when the purchaser so desires, the procedure of Lot Inspection shall be followed for judging conformity of the lot of hydraulic cement.  Recommended- cement should be sampled when it is in motion. 1. Sampling From Conveyors 2. Sampling from bulk storage 3. Sampling from skip’s hold 4. Sampling from wagons 5. Sampling from bags
  • 9. Lot Inspection  Sampling from conveyors 1. A lot shall be divided into sub lots at the time of discharging over a conveyor belt. 2. Then a gross sample is drawn from each of the sub lots & shall be kept separately. 3. The collecting frequency should be one increment for every 10 tons of discharged cement. 4. Mostly a scoop is used for the sampling from moving belts, which can sweep across the cross section of the material & along the belt. 5. After taking the increments out of sub lots, they shall be placed directly on a moisture proof, air tight containers to avoid moisture absorption & Aeration of sample. No’s of sub lots into which a lot is to be divided Wt. of Lot (Tons) No’s of sub-lots <100 2 101-200 3 201-300 4 301-500 5 501-1000 6 1001-2000 7
  • 10. Lot Inspection  Sampling from Bulk Storage i.e. silos 1. A lot shall be divided into sub lots depending upon the weight of the Lot 2. Then a gross sample is drawn from each of the sub lots when the cement is being charged into bulk storage or at the time of discharging from the bulk storage. 3. Increment shall be taken from each opening. 4. The collecting frequency should be one increment for every 10 tons of discharged cement.
  • 11. Lot Inspection  Sampling from Ship’s Hold 1. A lot shall be divided into sub lots depending upon the weight of the Lot 2. For collecting samples from ship’s hold, i.e. for depths greater than 2 m, sampling pipe activated by air jet is used. 3. Then a gross sample is drawn from each of the sub lots. 4. The collecting frequency should be one increment for every 10 tons of cement. 5. The increment shall be weight at least 2 kg.
  • 12. Lot Inspection  Sampling from Wagons 1. A lot shall be divided into sub lots depending upon the weight of the Lot 2. For collecting samples from wagons, i.e. for depths smaller than 2 m, Slotted-tube sampler is used. 3. Then a gross sample is drawn from at least six evenly distributed points in each selected wagon. 4. The increment shall be weight at least 2 kg. 5. After taking the increments out of wagons, they shall be placed directly on a moisture proof, air tight containers to avoid moisture absorption & Aeration of sample.
  • 13. Lot Inspection  Sampling from Bags 1. A lot shall be divided into sub lots depending upon the weight of the Lot. 2. at least 2 percent of the bags (minimum of five) shall be sampled. 3. Selection of bags should be random. 4. Tube sampler shall be inserted diagonally into the valve of the bag and the thumb placed over the air hole and then shall be withdrawn. 5. Equal no’s of increments should be taken out from each bags. 6. The increment shall be weight at least 2 kg.
  • 14. Sampling Equipments Tube Sampler For Bags Slotted Tube sampler for bulk storage
  • 15. Test on Cement The following tests are conducted on cement in the laboratory are as follows: 1. Fineness Test 2. Consistency Test 3. Setting Time Test 4. Strength Test 5. Soundness Test 6. Heat of Hydration Test 7. Tensile Strength Test 8. Chemical Composition Test
  • 16. Test on Cement The following tests are conducted on cement in the field are as follows: 1. Colour Test of Cement 2. Presence of Lumps 3. Cement Adulteration Test 4. Float Test 5. Date of Manufacturing
  • 17. Consistency Test of cement  Aim: To determine consistency of standard Cement paste.  Apparatus:
  • 18. Consistency Test of cement Material Used: Cement material shall be stored in sealed, airtight containers to avoid changes in its characteristics due to absorption or deposition from the atmosphere.
  • 19. Consistency Test of cement  Procedure: • Keep the vicat apparatus on a level base while using vicat apparatus with dashpot, keep the bearing movable rod to its highest position and pin it. Unscrew the top of the dashpot. Half fill the dashpot with any suitable oil of viscosity and screw the top. Work the plunger a number of times. • Attach the plunger for determining standard consistency to the movable rod. Work the plunger a number of times. • Take 400 gm of cement in a pan and a weighed quantity of water in a beaker. • Prepare a paste with the water added to cement. Start a stopwatch at the time of adding water to cement. • Keep the vicat mould on a non-porous plate and fill the cement paste in it.
  • 20. Consistency Test of cement  Procedure:
  • 21. Consistency Test of cement  Procedure:
  • 22. Consistency Test of cement  Procedure: • After completely filling the mould, shake it slightly to expel the air. Smooth off the surface of the paste making it level with the top of the moulder. The cement pastes thus prepared is the test block. • Place the test block resting on the non-porous plate under the movable rod, bearing the needle. • Lower the plunger gently to touch the surface of the cement paste and quickly release. • Remove the pin holding the movable bearing rod to the surface of the cement paste and quickly release by pushing down the plunger to sink in to the paste. This operation shall be done immediately after filling the mould. • Prepare trial test specimens with varying percentages of water until plunger penetrates to a point 5 to 7mm from the bottom of the vicat mould, which is read on the scale. Express the water required as percentage by weight of the dry cement.
  • 23. Consistency Test of cement  Procedure:
  • 24. Consistency Test of cement  Observation Table: SR. NO. DESCRIPTION READING 1. Weight of cement taken (g) (W1) 2. Quantity of water added to cement (W2) 3 Standard Consistency of Cement for 5-7 mm penetration (W2/W1*100)
  • 25. Consistency Test of cement  Significance and importance of the test: 1. It determines the amount of water needed to make a paste. It is necessary to determine consistency because the amount of water affects the setting time of the cement. 2. Consistency plays a vital role in the determination of compressive strength of concrete or workability test for concrete. 3. Less water than this quantity would not complete chemical reaction thus resulting in the reduction of strength and more water would increase water-cement ratio and so would reduce its strength.
  • 26. Consistency Test of cement  Why is Consistency Test Done? We know that the cement we used on our site is mostly affected by 1. Weather Conditions 2. Excessive combination of Silica. One of the cement ingredients which determines the initial and final setting time of cement paste. 3. The fineness of cement. 4. Manufacturing Defects By Standardising the consistency of cement, we know that how much of water is required to produce an effective cement which will eventually produce good quality of concrete.
  • 27.  Aim :- Determination of the initial and final setting time of cement.  Reference: - IS 4031 (Part-5):1988  Appratus :- Vicat apparatus, vicat mould, needle, gauging trowel, measuring jar, weighing balance, stop watch, rubber glove, non porous glass plate.  Material:- Ordinary Portland cement; Water. Determination of Setting Times of Cement
  • 28. Determination of Setting Times of Cement
  • 29. Determination of Setting Times of Cement  Theory :- • The time to which cement can be moulded in any desired shape without losing it’s strength is called Initial setting time of cement or • The time at which cement starts hardens and completely loses its plasticity is called Initial setting time of cement or • The time available for mixing the cement and placing it in position is an Initial setting time of cement. or • Initial set is a stage where the cement paste stiffens to such an extent that the Vicat needle is not permitted to move down through the paste within 5 ± 0.5 mm measured from the bottom of the mould. The time elapsed between the moments that the water is added to the cement to the initial set is regarded as initial setting time.
  • 30. Determination of Setting Times of Cement • The time at which cement completely loses its plasticity and became hard is a final setting time of cement. or • The time taken by cement to gain its entire strength is a Final setting time of cement. • For an ordinary Portland cement, the initial setting time should not be less than 30 minutes while the final setting time should not be more than 600 minutes.
  • 31.  Procedure :- 1) Preparation of Test Block • Prepare a neat cement paste by gauging the cement with 0.85 times the water required to give a paste of standard consistency. Potable or distilled water shall be used in preparing the paste. The paste shall be gauged in the manner and under the conditions prescribed in IS : 4031 (Part 5)- 1988. Start a stop-watch at the instant when water is added to the cement. Fill the Vicat mould with a cement paste gauged as above, the mould resting on a nonporous plate. Fill the mould completely and smooth off the surface of the paste making it level with the top of the mould. The cement block thus prepared in the mould is the test block. • Immediately after moulding, place the test block in the moist closet or moist room and allow it to remain there except when determinations of time of setting are being made. Determination of Setting Times of Cement
  • 32. 2) Determination of Initial Setting Time • Place the test block confined in the mould and resting on the non-porous plate, under the rod bearing the needle (with cross section 1 mm2 ). • lower the needle gently until it comes in contact with the surface of the test block and quickly release, allowing it to penetrate into the test block. • In the beginning, the needle will completely pierce the test block. Repeat this procedure until the needle, when brought in contact with the test block and released as described above, fails to pierce the block beyond 5.0 ± 0.5 mm measured from the bottom of the mould. • The period elapsing between the time when water is added to the cement and the time at which the needle fails to pierce the test block to a point 5.0 ± 0.5 mm measured from the bottom of the mould shall be the initial setting time. Determination of Setting Times of Cement
  • 33.
  • 34. 3) Determination of Final Setting Time — • Replace the needle of the Vicat apparatus by the needle with an annular attachment . • The cement shall be considered as finally set when, upon applying the needle gently to the surface of the test block, the needle makes an impression thereon, while the attachment fails to do so. • The period elapsing between the time when water is added to the cement and the time at which ,attachment fails to make an impression on the surface of test block shall be the final setting time. Initial and Final Setting Time of Cement
  • 35.
  • 36.  Observations:- • Weight of given sample of cement is ___________ g. • The normal consistency of a given sample of cement is ___________ % • Volume of water taken(0.85 times the water required to give a paste of standard consistency) for preparation of test block ____________ ml Initial and Final Setting Time of Cement
  • 37. Initial and Final Setting Time of Cement  Precaution for Initial and Final setting time of cement test • The needle should be cleaned after every use. • The mould should be slightly moved so that the penetration would not be at the same place. • The experiment should be carried out at a place where there is no external vibration or disturbance. • The mould should not have any type of movement from initial setting time to final setting time. • The temperature of the room in which the experiment is conducted should be maintained around 27º-29º C and hydration should be maintained in between 60-70%.