SlideShare a Scribd company logo
GEOMETRIC DESIGN
OF THE TRACK
Necessity of Geometric Design:
 Smooth & safe running of trains.
 Maximum speed.
 Carrying heavy axle loads.
 Avoid accidents & derailments.
 Less maintenance efforts.
 Good aesthetic value.
There, if all the above elements are properly
designed, the possibility of derailments due to defects
in the track can be avoided.
 Gradients
The amount of slope in longitudinal direction of railway track
is called gradient or grade.
 Gradients are provided to negotiate the rise or fall in the level
of the railway track.
 Rising gradient rises the track in the direction of movement,
whereas, falling gradient cause the track to go down in the
direction of movement.
 A gradient is represented by the distance traveled for a rise or
fall of one unit.
It is written as; 1 in ‘X’ or 1 in ‘n’ or as percent
 Gradients are provided on the track due to the
following reasons.
 To provide a uniform rate of rise or fall as far as
possible.
 To reach the various stations located at different
elevation.
 To reduce the cost of earth work.
 Gradients – Types
 Ruling gradient
 Momentum gradient
 Pusher or Helper gradient
 Gradients in Station Yards
A) Ruling gradient: This is the design gradient basically,
because it is determined on the basis of the performance
of the locomotive and at the same time, it tries to look at
the total amount of load which that locomotive can take
up along with it, while negotiating any gradient without
any loss or major loss in the speed of the movement.
 Ruling gradient;
 It is a maximum gradient (steepest gradient), which may
be permitted on the section of the track.
 It is determined by maximum load that a locomotive can
haul with maximum permissible speed.
 Extra pull required by locomotive on gradient with ‘ ’
inclination. P = W Sin = W * gradient
For Ex:-
Weight of train (W)=500 tonnes
Gradient = 1 in 100
Extra power (P) = 5 tonnes
 Ruling gradient with one locomotive.
• In Plane area = 1 in 150 to 1 in 250
• In hilly area = 1 in 100 to 1in 150
 Once a ruling gradient is specified for a section,
then all other gradients provided in that section
should be flatter than the ruling gradients (after
making due to compensation for curvature)
 Gradients – Types ….
b) Momentum gradient:
 Momentum gradient steeper than ruling gradient that is
overcome by momentum gathered while having a run in
plane or on falling gradient in valleys.
 Use additional kinetic energy received during run on a
section.
 No obstruction like signals are provided on section with
these gradients.(means the train should not be stopped
at that territory)
For example, in valleys, a falling gradient is usually
followed by rising gradient acquires sufficient
momentum.
This momentum gives additional kinetic energy to
the moving train which would enable the train to
overcome a steeper rising gradient than the ruling
gradient for a certain length of the track.
This rising gradient is called momentum gradient
and this gradient is steeper than ruling gradient.
C) Pusher or Helper gradient:
 Gradient steeper than ruling gradient requiring extra
locomotive.
• It reduces the length of a railway section.
• It also reduces the overall cost.
Examples : In Darjeeling Railways 1 in 37 Pusher gradient is
used on Western Ghats, B.G tracks & N.G tracks 1 in 25 is
provided.
d) Gradient at Station Yards:
As per as possible the track along the stations & yards
should be level or gradients should be sufficiently low.
• To prevent standing vehicle from rolling & moving
away from the yard due to combined effect of gravity &
strong winds.
• To reduce additional resistive forces required to start a
locomotive to the extent possible.
• Minimum gradient from drainage consideration.
• On Indian railways, maximum gradient permitted is 1 in
400 in station yards & minimum gradient permitted is 1 in
1000
 Grade Compensation ( On Curves):-
 If a curve is provided on a track with ruling
gradient, the resistance of the track will be increased on this
curve. In order to avoid resistance beyond the allowable
limits, the gradients are reduced on curves & this reduction in
gradient is known as grade compensation for curves.
In India, Compensation for curvature is given by.
o BG track: 0.04% per degree of curve
o MG track: 0.03 % per degree of curve
o NG track: 0.02 % per degree of curve
 Grade Compensation ( On Curves);.
Example :If the ruling gradient is 1 in 250 on a particular section
of B.G & at the same time a curve of 4 degree is situated on this
ruling gradient, what should be the allowable ruling gradient?
Solution:
As per Indian railway recommendation, the grade compensation
for of B.G track is 0.04% per degree of curve.
Therefore, Grade compensation for 4 degree curve
= 0.04 * 4 = 0.16%
Ruling gradients is 1 in 250
= 1/250 *100 = 0.4%
Therefore, Required ruling gradient or Actual gradient
= Ruling gradient – grade compensation
= 0.4- 0.16
= 0.24% or 1 in 417
 Radius & Degree of a curve:-
 The main curved portion of a railway track is kept circular
i.e, the radius at every point of the curve is same.
 The radius of a railway curve is sometimes represented by the
degree of the curve.
Degree of a railway curve:-
The angle subtended at the center of the curve by an arc of 30.0m
length is defined as a defined as a degree of the curve.
Relationship between the radius & degree of a curve.
Let, R=radius of the curve in meters, D = degree of the curve
Now, total circumference 2πR makes
360o at the center.
Therefore, for 30.0 m arc makes an angle.
D/30 = 360/2πR
D = 360*30/2πR
D = 1718.87/R
D = 1720/R
 Safe speed on curves...
 Safe speed for all practical purposes means a speed which
is safe from the danger of overturning & derailment with a
certain margin of safety. This speed, to negotiate curves
safely, depends upon the following factors.
• The gauge of track.
• The radius of the curve.
• Amount of super elevation provided.
In India, using safe speed V in kmph, formula.
B.G & M.G : V = 4.35 R- 67
N.G: V = 3.65 R- 6
 Superelevation or Cant….
When a train moves round a curve, it is subjected to a centrifugal
force acting horizontally at the centre of gravity of each vehicle
radially away from the centre of the curve. This increases the
weight on the outer rails.
To counteract the effect of centrifugal forces, the level of
the outer rail is raised above the inner rail by a certain amount to
introduce the centripetal force. This raised elevation of outer rail
above the inner rail at a horizontal curve is called “Cant”.
 Superelevation or Cant….
 It is the difference in elevation (or height) between the outer
rail and inner rail at a horizontal curve is called “Cant”.
 Inner rail is taken as a reference rail & is maintained at its
original level.
 Inner rail is also known
as ‘gradient rail’.
 It is denoted by “e”.
 Superelevation or Cant….
 Objectives of Superelevation.
 To neutralize the effect of centrifugal force.
 Equal distribution of wheel loads.
 Providing smooth track, improving passenger comfort.
 To reduce wear & tear of the rails & rolling stock.
 Equilibrium Cant….
 The cant or super elevation as given by equation e=(GV2/1.27R)
cm, the load carried by both the wheels will be the same, the
springs will be equally compressed & the passengers will not
tend to lean in either direction, such cant is known as the
“Equilibrium cant”.
 Equilibrium Cant….
 The cant is provided on the basis of average speed of the
trains.
 The majority of Indian Railways provide super elevation for
equilibrium speed or average speed under condition of level
track.
Average speed or Weighted average speed
= n1V1+ n2V2+ n3V3 / n1+ n2+ n3
Where, n1, n2,n3 = Number of trains
V1, V2,V3 = Speed of trains in kmph
 Equilibrium Cant….
 The cant is provided on the basis of average speed of the
trains.
 The majority of Indian Railways provide super elevation for
equilibrium speed or average speed under condition of level
track.
Average speed or Weighted average speed
= n1V1+ n2V2+ n3V3 / n1+ n2+ n3
Where, n1, n2,n3 = Number of trains
V1, V2,V3 = Speed of trains in kmph
 Cant Deficiency (Cd)….
 The equilibrium cant is provided on the basis of equilibrium speed
(or Average speed) of different trains. But this equilibrium cant or
super elevation falls short of that required for the high speed trains.
This shortage of cant is called “ Cant Deficiency”.
 In other words, it is the difference between the equilibrium cant
necessary for the maximum permissible speed on a curve and the
actual cant provided. Higher cant deficiency causes more
unbalanced centrifugal force and discomfort to the passengers.
 Maximum value of cant deficiency prescribed for Indian Railways.
B.G = 7.6cm, M.G = 5.1cm, N.G = 3.8cm
 Negative Superelevation….
 When a branch line diverges from a main line on a curve of
contrary flexure, the super elevation necessary for the average
speed of trains running over the main line, cannot be
provided.
 The speed of the trains over the diverging track and main line
track has to be reduced considerably.
 The reason for the reduction of speed is that, on the branch
line track, the inner rail remains at higher level than the outer
rail.
 Negative Superelevation….
D
Outer rail
Inner rail
Inner rail
 Negative Superelevation….
 Ref fig: AD which is the outer rail of the main line curve must be
higher than inner rail BC or in other words, the point A should be
higher than point B.
 For the branch line, however, BE should be higher than AF or the
point B should be higher than point A.
 These two contradictory conditions cannot be meet at the same
time within one layout . So, outer rail BE on branch line is kept
lower than the inner rail AF. In such case branch line curve has a
negative super elevation & therefore speeds on both tracks must be
restricted, particularly on branch line.
 Negative Superelevation….
 Calculation of restricted speed on the main line & branch line.
 Super elevation for branch line can be calculated
 Calculate equilibrium super elevation for branch line (eb).
 Find super elevation, X = eb – Cd for branch line.
This is to be provided on main line.
 To calculate the maximum permissible speed for main line,
Cant should be, em = X + Cd
 Super elevation for main line can be calculated
 Calculate equilibrium super elevation for main line (em).
 Find super elevation, X = em – Cd for main line.
 Provided cant on branch line as ( -X ).
 To calculate the maximum permissible speed for branch line,
Cant should be, eb = (-X ) + Cd
 Transitional Curves….
 Transition curve is defined as a curve of parabolic nature
which is introduced between a straight and a circular curve or
between two branches of a compound curve.
 It is necessary to provide an easy change from a tangent to the
radius selected for a particular curve.
 It is essential that the curvature and superelevation in the
outer rail and the curvature in the inner rail are attained
gradually, by the use of easement curve or transition curve.
 Transitional Curves….
 Objects:
 Primary objects:
 To decrease the radius of curve gradually from infinite at the
straight to that of circular curve of selected radius.
 To attain gradual rise for the desired superelevation. This is
applicable for outer rail.
 Secondary objects:
 The gradual increase or decrease of the centrifugal force on
the vehicle by use of this curve provides smooth running of
vehicle & comfort to the passengers.
 No sudden application, so the chances of derailment are gently
reduced.
 Transitional Curves….
 Requirements of a Transition Curve;
 It should be perfectly tangential to the straight.
 The length of the transition curve should be such that
curvature may increase at the same rate as the superelevation .
 This curve should join the circular arc tangentially i.e.,
curvature of transition curve should conform with that of
circular curve.
 Superelevation for B.G, M.G & N.G….
 Relationship of superelevation (e), with gauge(G),
speed (V) and radius of the curve ( R ).
W= Weight of moving vehicle in kg.
v = Speed of vehicle in m/sec
V = Speed of vehicle in km.ph
R = Radius of curve in meters
G = Gauge of track in meters
g = Acceleration due to gravity in m/sec2
α = Angle of inclination
S = Length of inclined surface in meters
Centrifugal force is given by the following expression.
F = Wv2/gR -------------(1)
Now resolving the forces along the inclined surface we get
F cosα = W sinα -------- (2)
 Superelevation for B.G, M.G & N.G….
F = Wv2/gR , cosα = G/S & sinα = e/S
Therefore equation (2) becomes Wv2/gR * G/S = W*e/S
Therefore, e = v2/gR * G meters
Where, v in m/sec.
= G ( 0,278V)2/9.81R
= GV2/127 R meter
e = GV2/1.27 R centimeter
For B.G., e = GV2/1.27 R = 1.676 V2/1.27 R centimeter
For M.G., e = GV2/1.27 R = 1.0 V2/1.27 R centimeter
For N.G., e = GV2/1.27 R = 0.762 V2/1.27 R centimeter
Geometric design of the track

More Related Content

What's hot

5.track or permanent way and track stresses
5.track or permanent way and track stresses5.track or permanent way and track stresses
5.track or permanent way and track stresses
Mani Vel
 
Railway station and YARD
Railway station and YARD Railway station and YARD
Railway station and YARD
Dhruv Makadia
 
Railway Engineering: Turnouts
Railway Engineering: TurnoutsRailway Engineering: Turnouts
Railway Engineering: Turnouts
Vijai Krishnan V
 
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of RailsRails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
srinivas2036
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
srinivas2036
 
Sleepers and Ballast
Sleepers and Ballast Sleepers and Ballast
Sleepers and Ballast
T.Naga Anusha
 
Fittings and Fastenings of Rails.pdf
Fittings and Fastenings of Rails.pdfFittings and Fastenings of Rails.pdf
Fittings and Fastenings of Rails.pdf
TVijayaGowri
 
Railway Engineering- Basic Introduction
Railway Engineering- Basic IntroductionRailway Engineering- Basic Introduction
Railway Engineering- Basic Introduction
Bathla Tuition Centre
 
Railway Engineering: Points and crossings
Railway Engineering: Points and crossingsRailway Engineering: Points and crossings
Railway Engineering: Points and crossings
Bathla Tuition Centre
 
Components of railway track
Components of railway trackComponents of railway track
Components of railway track
gayathrysatheesan1
 
1.railway intro and rails
1.railway intro and rails1.railway intro and rails
1.railway intro and rails
Deven Diran
 
Station and Yards in Indian Railway
Station and Yards in Indian RailwayStation and Yards in Indian Railway
Station and Yards in Indian Railway
Arbaz Kazi
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
Shanmugaraj M
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
Chockalingam T
 
Defects in rails. Railway Engineering
Defects in rails. Railway EngineeringDefects in rails. Railway Engineering
Defects in rails. Railway Engineering
Irfan Nasir
 
Design of vertical alignment
Design of vertical alignmentDesign of vertical alignment
Design of vertical alignment
Wyman Words
 
Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)
sharda university
 
Railway track design ppt 2018
Railway track design ppt 2018Railway track design ppt 2018
Railway track design ppt 2018
ishwar dhakad
 

What's hot (20)

5.track or permanent way and track stresses
5.track or permanent way and track stresses5.track or permanent way and track stresses
5.track or permanent way and track stresses
 
Railway station and YARD
Railway station and YARD Railway station and YARD
Railway station and YARD
 
Railway Engineering: Turnouts
Railway Engineering: TurnoutsRailway Engineering: Turnouts
Railway Engineering: Turnouts
 
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of RailsRails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
 
Sleepers and Ballast
Sleepers and Ballast Sleepers and Ballast
Sleepers and Ballast
 
Fittings and Fastenings of Rails.pdf
Fittings and Fastenings of Rails.pdfFittings and Fastenings of Rails.pdf
Fittings and Fastenings of Rails.pdf
 
Railway Engineering- Basic Introduction
Railway Engineering- Basic IntroductionRailway Engineering- Basic Introduction
Railway Engineering- Basic Introduction
 
Left hand turnout
Left hand turnoutLeft hand turnout
Left hand turnout
 
Railway Engineering: Points and crossings
Railway Engineering: Points and crossingsRailway Engineering: Points and crossings
Railway Engineering: Points and crossings
 
Components of railway track
Components of railway trackComponents of railway track
Components of railway track
 
1.railway intro and rails
1.railway intro and rails1.railway intro and rails
1.railway intro and rails
 
Station and Yards in Indian Railway
Station and Yards in Indian RailwayStation and Yards in Indian Railway
Station and Yards in Indian Railway
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Railway Gauge
Railway GaugeRailway Gauge
Railway Gauge
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
 
Defects in rails. Railway Engineering
Defects in rails. Railway EngineeringDefects in rails. Railway Engineering
Defects in rails. Railway Engineering
 
Design of vertical alignment
Design of vertical alignmentDesign of vertical alignment
Design of vertical alignment
 
Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)
 
Railway track design ppt 2018
Railway track design ppt 2018Railway track design ppt 2018
Railway track design ppt 2018
 

Viewers also liked

Floods
FloodsFloods
Geometric desing of railway track
Geometric desing of railway trackGeometric desing of railway track
Geometric desing of railway track
mohitjain123
 
Surface runoff
Surface runoffSurface runoff
Surface runoff
Mohsin Siddique
 
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
Hossam Shafiq II
 
Introduction to ground water hydrology
Introduction to ground water hydrologyIntroduction to ground water hydrology
Introduction to ground water hydrology
Mohsin Siddique
 
Stations and Yards of Railway
Stations and Yards of RailwayStations and Yards of Railway
Stations and Yards of Railway
Souvik Mondal
 
Station yards
Station yardsStation yards
Station yards
jagadish108
 
Stream flow measurement
Stream flow measurementStream flow measurement
Stream flow measurement
MOHIT MAYOOR
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
Shanmugaraj M
 
Water cycle and water budget
Water cycle and water budgetWater cycle and water budget
Water cycle and water budget
Mohsin Siddique
 
2 handouts-lecture-7
2  handouts-lecture-72  handouts-lecture-7
2 handouts-lecture-7
Saleem Malik
 
Points and crossings ( special assigments )
Points and crossings ( special assigments )Points and crossings ( special assigments )
Points and crossings ( special assigments )
hiranrathva
 
Precipitation and its estimation
Precipitation and its estimationPrecipitation and its estimation
Precipitation and its estimation
Mohsin Siddique
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
hiranrathva
 
Railway track:An Introduction
Railway track:An IntroductionRailway track:An Introduction
Railway track:An Introduction
Prem Prakash Kumar
 
Railway transportation 2.1
Railway transportation 2.1Railway transportation 2.1
Railway transportation 2.1Hasan Gunes
 
Topic%20 compression
Topic%20 compressionTopic%20 compression
Topic%20 compressionSaleem Malik
 
Chapter 6 concrete dam engineering with examples
Chapter 6 concrete dam engineering with examplesChapter 6 concrete dam engineering with examples
Chapter 6 concrete dam engineering with examples
Mohsin Siddique
 
Bolted connections
Bolted connectionsBolted connections
Bolted connections
Dr.Subramanian Narayanan
 
steel structural basics
steel structural basicssteel structural basics
steel structural basics
Asan Ibrahim
 

Viewers also liked (20)

Floods
FloodsFloods
Floods
 
Geometric desing of railway track
Geometric desing of railway trackGeometric desing of railway track
Geometric desing of railway track
 
Surface runoff
Surface runoffSurface runoff
Surface runoff
 
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
 
Introduction to ground water hydrology
Introduction to ground water hydrologyIntroduction to ground water hydrology
Introduction to ground water hydrology
 
Stations and Yards of Railway
Stations and Yards of RailwayStations and Yards of Railway
Stations and Yards of Railway
 
Station yards
Station yardsStation yards
Station yards
 
Stream flow measurement
Stream flow measurementStream flow measurement
Stream flow measurement
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Water cycle and water budget
Water cycle and water budgetWater cycle and water budget
Water cycle and water budget
 
2 handouts-lecture-7
2  handouts-lecture-72  handouts-lecture-7
2 handouts-lecture-7
 
Points and crossings ( special assigments )
Points and crossings ( special assigments )Points and crossings ( special assigments )
Points and crossings ( special assigments )
 
Precipitation and its estimation
Precipitation and its estimationPrecipitation and its estimation
Precipitation and its estimation
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Railway track:An Introduction
Railway track:An IntroductionRailway track:An Introduction
Railway track:An Introduction
 
Railway transportation 2.1
Railway transportation 2.1Railway transportation 2.1
Railway transportation 2.1
 
Topic%20 compression
Topic%20 compressionTopic%20 compression
Topic%20 compression
 
Chapter 6 concrete dam engineering with examples
Chapter 6 concrete dam engineering with examplesChapter 6 concrete dam engineering with examples
Chapter 6 concrete dam engineering with examples
 
Bolted connections
Bolted connectionsBolted connections
Bolted connections
 
steel structural basics
steel structural basicssteel structural basics
steel structural basics
 

Similar to Geometric design of the track

Chapter 2 track geometrics and its maintainance
Chapter 2 track geometrics and its maintainanceChapter 2 track geometrics and its maintainance
Chapter 2 track geometrics and its maintainance
dhara dattani
 
Presentation on railway construction and maintenance
Presentation on railway construction and maintenancePresentation on railway construction and maintenance
Presentation on railway construction and maintenance
Mohd Bakhsh
 
Geometric design of railway track
Geometric design of railway  trackGeometric design of railway  track
Geometric design of railway track
MOHIT DUREJA
 
Geometric Design - Horizontal and vertical curves
Geometric Design - Horizontal and vertical curvesGeometric Design - Horizontal and vertical curves
Geometric Design - Horizontal and vertical curves
sachin dass
 
Geometric design of track
Geometric design of trackGeometric design of track
Geometric design of track
JOYCHENKENGLANG
 
1. curvature of track
1. curvature of track1. curvature of track
1. curvature of track
Khaza Ahmed Palash
 
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
Hossam Shafiq I
 
SUPER_ELEVATION.pdf
SUPER_ELEVATION.pdfSUPER_ELEVATION.pdf
SUPER_ELEVATION.pdf
William808440
 
Chapter 2 Track Geometry.pptx
Chapter 2 Track Geometry.pptxChapter 2 Track Geometry.pptx
Chapter 2 Track Geometry.pptx
MamushLeta
 
transitioncurve-210816162648.pdf
transitioncurve-210816162648.pdftransitioncurve-210816162648.pdf
transitioncurve-210816162648.pdf
Renjith S Anand
 
Transition curve and Superelevation
Transition curve and SuperelevationTransition curve and Superelevation
Transition curve and Superelevation
Mir Zafarullah
 
Curves and elevation
Curves and elevationCurves and elevation
Curves and elevation
Rohit894
 
Highway Horizontal Alignment
Highway Horizontal AlignmentHighway Horizontal Alignment
Highway Horizontal Alignment
AkshathaBhandary
 
Chapter 4 Lecture-11,12,13-Transition-Curves.pptx
Chapter 4 Lecture-11,12,13-Transition-Curves.pptxChapter 4 Lecture-11,12,13-Transition-Curves.pptx
Chapter 4 Lecture-11,12,13-Transition-Curves.pptx
akhnd4
 
Transportation engineering highway part
Transportation engineering highway partTransportation engineering highway part
Transportation engineering highway part
Dhaka University of Engineering and Technology
 
15946154310513679877-engg ppt curves.pdf
15946154310513679877-engg ppt curves.pdf15946154310513679877-engg ppt curves.pdf
15946154310513679877-engg ppt curves.pdf
johnpeter157791
 
3 vertical alignment of road by Malyar Talash
3 vertical alignment of road by Malyar Talash3 vertical alignment of road by Malyar Talash
3 vertical alignment of road by Malyar Talash
Malyar Talash
 
Curve setting (Basic Mine Surveying)_MI10412MI.pptx
Curve setting (Basic Mine Surveying)_MI10412MI.pptxCurve setting (Basic Mine Surveying)_MI10412MI.pptx
Curve setting (Basic Mine Surveying)_MI10412MI.pptx
Dr Romil Mishra
 
transition curve in Highway Geometry Design
transition curve in Highway Geometry Designtransition curve in Highway Geometry Design
transition curve in Highway Geometry Design
Nachiketa Mithaiwala
 
Geometric design of highway
Geometric design of highwayGeometric design of highway
Geometric design of highway
Bhavya Jaiswal
 

Similar to Geometric design of the track (20)

Chapter 2 track geometrics and its maintainance
Chapter 2 track geometrics and its maintainanceChapter 2 track geometrics and its maintainance
Chapter 2 track geometrics and its maintainance
 
Presentation on railway construction and maintenance
Presentation on railway construction and maintenancePresentation on railway construction and maintenance
Presentation on railway construction and maintenance
 
Geometric design of railway track
Geometric design of railway  trackGeometric design of railway  track
Geometric design of railway track
 
Geometric Design - Horizontal and vertical curves
Geometric Design - Horizontal and vertical curvesGeometric Design - Horizontal and vertical curves
Geometric Design - Horizontal and vertical curves
 
Geometric design of track
Geometric design of trackGeometric design of track
Geometric design of track
 
1. curvature of track
1. curvature of track1. curvature of track
1. curvature of track
 
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
 
SUPER_ELEVATION.pdf
SUPER_ELEVATION.pdfSUPER_ELEVATION.pdf
SUPER_ELEVATION.pdf
 
Chapter 2 Track Geometry.pptx
Chapter 2 Track Geometry.pptxChapter 2 Track Geometry.pptx
Chapter 2 Track Geometry.pptx
 
transitioncurve-210816162648.pdf
transitioncurve-210816162648.pdftransitioncurve-210816162648.pdf
transitioncurve-210816162648.pdf
 
Transition curve and Superelevation
Transition curve and SuperelevationTransition curve and Superelevation
Transition curve and Superelevation
 
Curves and elevation
Curves and elevationCurves and elevation
Curves and elevation
 
Highway Horizontal Alignment
Highway Horizontal AlignmentHighway Horizontal Alignment
Highway Horizontal Alignment
 
Chapter 4 Lecture-11,12,13-Transition-Curves.pptx
Chapter 4 Lecture-11,12,13-Transition-Curves.pptxChapter 4 Lecture-11,12,13-Transition-Curves.pptx
Chapter 4 Lecture-11,12,13-Transition-Curves.pptx
 
Transportation engineering highway part
Transportation engineering highway partTransportation engineering highway part
Transportation engineering highway part
 
15946154310513679877-engg ppt curves.pdf
15946154310513679877-engg ppt curves.pdf15946154310513679877-engg ppt curves.pdf
15946154310513679877-engg ppt curves.pdf
 
3 vertical alignment of road by Malyar Talash
3 vertical alignment of road by Malyar Talash3 vertical alignment of road by Malyar Talash
3 vertical alignment of road by Malyar Talash
 
Curve setting (Basic Mine Surveying)_MI10412MI.pptx
Curve setting (Basic Mine Surveying)_MI10412MI.pptxCurve setting (Basic Mine Surveying)_MI10412MI.pptx
Curve setting (Basic Mine Surveying)_MI10412MI.pptx
 
transition curve in Highway Geometry Design
transition curve in Highway Geometry Designtransition curve in Highway Geometry Design
transition curve in Highway Geometry Design
 
Geometric design of highway
Geometric design of highwayGeometric design of highway
Geometric design of highway
 

Recently uploaded

ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 

Recently uploaded (20)

ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 

Geometric design of the track

  • 2.
  • 3. Necessity of Geometric Design:  Smooth & safe running of trains.  Maximum speed.  Carrying heavy axle loads.  Avoid accidents & derailments.  Less maintenance efforts.  Good aesthetic value. There, if all the above elements are properly designed, the possibility of derailments due to defects in the track can be avoided.
  • 4.  Gradients The amount of slope in longitudinal direction of railway track is called gradient or grade.  Gradients are provided to negotiate the rise or fall in the level of the railway track.  Rising gradient rises the track in the direction of movement, whereas, falling gradient cause the track to go down in the direction of movement.  A gradient is represented by the distance traveled for a rise or fall of one unit. It is written as; 1 in ‘X’ or 1 in ‘n’ or as percent
  • 5.
  • 6.  Gradients are provided on the track due to the following reasons.  To provide a uniform rate of rise or fall as far as possible.  To reach the various stations located at different elevation.  To reduce the cost of earth work.
  • 7.  Gradients – Types  Ruling gradient  Momentum gradient  Pusher or Helper gradient  Gradients in Station Yards
  • 8. A) Ruling gradient: This is the design gradient basically, because it is determined on the basis of the performance of the locomotive and at the same time, it tries to look at the total amount of load which that locomotive can take up along with it, while negotiating any gradient without any loss or major loss in the speed of the movement.
  • 9.  Ruling gradient;  It is a maximum gradient (steepest gradient), which may be permitted on the section of the track.  It is determined by maximum load that a locomotive can haul with maximum permissible speed.  Extra pull required by locomotive on gradient with ‘ ’ inclination. P = W Sin = W * gradient For Ex:- Weight of train (W)=500 tonnes Gradient = 1 in 100 Extra power (P) = 5 tonnes
  • 10.  Ruling gradient with one locomotive. • In Plane area = 1 in 150 to 1 in 250 • In hilly area = 1 in 100 to 1in 150  Once a ruling gradient is specified for a section, then all other gradients provided in that section should be flatter than the ruling gradients (after making due to compensation for curvature)
  • 11.  Gradients – Types …. b) Momentum gradient:  Momentum gradient steeper than ruling gradient that is overcome by momentum gathered while having a run in plane or on falling gradient in valleys.  Use additional kinetic energy received during run on a section.  No obstruction like signals are provided on section with these gradients.(means the train should not be stopped at that territory)
  • 12.
  • 13. For example, in valleys, a falling gradient is usually followed by rising gradient acquires sufficient momentum. This momentum gives additional kinetic energy to the moving train which would enable the train to overcome a steeper rising gradient than the ruling gradient for a certain length of the track. This rising gradient is called momentum gradient and this gradient is steeper than ruling gradient.
  • 14.
  • 15. C) Pusher or Helper gradient:  Gradient steeper than ruling gradient requiring extra locomotive. • It reduces the length of a railway section. • It also reduces the overall cost. Examples : In Darjeeling Railways 1 in 37 Pusher gradient is used on Western Ghats, B.G tracks & N.G tracks 1 in 25 is provided.
  • 16.
  • 17. d) Gradient at Station Yards: As per as possible the track along the stations & yards should be level or gradients should be sufficiently low. • To prevent standing vehicle from rolling & moving away from the yard due to combined effect of gravity & strong winds. • To reduce additional resistive forces required to start a locomotive to the extent possible. • Minimum gradient from drainage consideration. • On Indian railways, maximum gradient permitted is 1 in 400 in station yards & minimum gradient permitted is 1 in 1000
  • 18.
  • 19.  Grade Compensation ( On Curves):-  If a curve is provided on a track with ruling gradient, the resistance of the track will be increased on this curve. In order to avoid resistance beyond the allowable limits, the gradients are reduced on curves & this reduction in gradient is known as grade compensation for curves. In India, Compensation for curvature is given by. o BG track: 0.04% per degree of curve o MG track: 0.03 % per degree of curve o NG track: 0.02 % per degree of curve
  • 20.  Grade Compensation ( On Curves);. Example :If the ruling gradient is 1 in 250 on a particular section of B.G & at the same time a curve of 4 degree is situated on this ruling gradient, what should be the allowable ruling gradient? Solution: As per Indian railway recommendation, the grade compensation for of B.G track is 0.04% per degree of curve. Therefore, Grade compensation for 4 degree curve = 0.04 * 4 = 0.16% Ruling gradients is 1 in 250 = 1/250 *100 = 0.4% Therefore, Required ruling gradient or Actual gradient = Ruling gradient – grade compensation = 0.4- 0.16 = 0.24% or 1 in 417
  • 21.  Radius & Degree of a curve:-  The main curved portion of a railway track is kept circular i.e, the radius at every point of the curve is same.  The radius of a railway curve is sometimes represented by the degree of the curve. Degree of a railway curve:- The angle subtended at the center of the curve by an arc of 30.0m length is defined as a defined as a degree of the curve. Relationship between the radius & degree of a curve. Let, R=radius of the curve in meters, D = degree of the curve Now, total circumference 2πR makes 360o at the center. Therefore, for 30.0 m arc makes an angle. D/30 = 360/2πR D = 360*30/2πR D = 1718.87/R D = 1720/R
  • 22.  Safe speed on curves...  Safe speed for all practical purposes means a speed which is safe from the danger of overturning & derailment with a certain margin of safety. This speed, to negotiate curves safely, depends upon the following factors. • The gauge of track. • The radius of the curve. • Amount of super elevation provided. In India, using safe speed V in kmph, formula. B.G & M.G : V = 4.35 R- 67 N.G: V = 3.65 R- 6
  • 23.  Superelevation or Cant…. When a train moves round a curve, it is subjected to a centrifugal force acting horizontally at the centre of gravity of each vehicle radially away from the centre of the curve. This increases the weight on the outer rails. To counteract the effect of centrifugal forces, the level of the outer rail is raised above the inner rail by a certain amount to introduce the centripetal force. This raised elevation of outer rail above the inner rail at a horizontal curve is called “Cant”.
  • 24.  Superelevation or Cant….  It is the difference in elevation (or height) between the outer rail and inner rail at a horizontal curve is called “Cant”.  Inner rail is taken as a reference rail & is maintained at its original level.  Inner rail is also known as ‘gradient rail’.  It is denoted by “e”.
  • 25.  Superelevation or Cant….  Objectives of Superelevation.  To neutralize the effect of centrifugal force.  Equal distribution of wheel loads.  Providing smooth track, improving passenger comfort.  To reduce wear & tear of the rails & rolling stock.
  • 26.
  • 27.
  • 28.  Equilibrium Cant….  The cant or super elevation as given by equation e=(GV2/1.27R) cm, the load carried by both the wheels will be the same, the springs will be equally compressed & the passengers will not tend to lean in either direction, such cant is known as the “Equilibrium cant”.
  • 29.  Equilibrium Cant….  The cant is provided on the basis of average speed of the trains.  The majority of Indian Railways provide super elevation for equilibrium speed or average speed under condition of level track. Average speed or Weighted average speed = n1V1+ n2V2+ n3V3 / n1+ n2+ n3 Where, n1, n2,n3 = Number of trains V1, V2,V3 = Speed of trains in kmph
  • 30.  Equilibrium Cant….  The cant is provided on the basis of average speed of the trains.  The majority of Indian Railways provide super elevation for equilibrium speed or average speed under condition of level track. Average speed or Weighted average speed = n1V1+ n2V2+ n3V3 / n1+ n2+ n3 Where, n1, n2,n3 = Number of trains V1, V2,V3 = Speed of trains in kmph
  • 31.  Cant Deficiency (Cd)….  The equilibrium cant is provided on the basis of equilibrium speed (or Average speed) of different trains. But this equilibrium cant or super elevation falls short of that required for the high speed trains. This shortage of cant is called “ Cant Deficiency”.  In other words, it is the difference between the equilibrium cant necessary for the maximum permissible speed on a curve and the actual cant provided. Higher cant deficiency causes more unbalanced centrifugal force and discomfort to the passengers.  Maximum value of cant deficiency prescribed for Indian Railways. B.G = 7.6cm, M.G = 5.1cm, N.G = 3.8cm
  • 32.  Negative Superelevation….  When a branch line diverges from a main line on a curve of contrary flexure, the super elevation necessary for the average speed of trains running over the main line, cannot be provided.  The speed of the trains over the diverging track and main line track has to be reduced considerably.  The reason for the reduction of speed is that, on the branch line track, the inner rail remains at higher level than the outer rail.
  • 33.  Negative Superelevation…. D Outer rail Inner rail Inner rail
  • 34.  Negative Superelevation….  Ref fig: AD which is the outer rail of the main line curve must be higher than inner rail BC or in other words, the point A should be higher than point B.  For the branch line, however, BE should be higher than AF or the point B should be higher than point A.  These two contradictory conditions cannot be meet at the same time within one layout . So, outer rail BE on branch line is kept lower than the inner rail AF. In such case branch line curve has a negative super elevation & therefore speeds on both tracks must be restricted, particularly on branch line.
  • 35.  Negative Superelevation….  Calculation of restricted speed on the main line & branch line.  Super elevation for branch line can be calculated  Calculate equilibrium super elevation for branch line (eb).  Find super elevation, X = eb – Cd for branch line. This is to be provided on main line.  To calculate the maximum permissible speed for main line, Cant should be, em = X + Cd  Super elevation for main line can be calculated  Calculate equilibrium super elevation for main line (em).  Find super elevation, X = em – Cd for main line.  Provided cant on branch line as ( -X ).  To calculate the maximum permissible speed for branch line, Cant should be, eb = (-X ) + Cd
  • 36.  Transitional Curves….  Transition curve is defined as a curve of parabolic nature which is introduced between a straight and a circular curve or between two branches of a compound curve.  It is necessary to provide an easy change from a tangent to the radius selected for a particular curve.  It is essential that the curvature and superelevation in the outer rail and the curvature in the inner rail are attained gradually, by the use of easement curve or transition curve.
  • 37.  Transitional Curves….  Objects:  Primary objects:  To decrease the radius of curve gradually from infinite at the straight to that of circular curve of selected radius.  To attain gradual rise for the desired superelevation. This is applicable for outer rail.  Secondary objects:  The gradual increase or decrease of the centrifugal force on the vehicle by use of this curve provides smooth running of vehicle & comfort to the passengers.  No sudden application, so the chances of derailment are gently reduced.
  • 38.  Transitional Curves….  Requirements of a Transition Curve;  It should be perfectly tangential to the straight.  The length of the transition curve should be such that curvature may increase at the same rate as the superelevation .  This curve should join the circular arc tangentially i.e., curvature of transition curve should conform with that of circular curve.
  • 39.  Superelevation for B.G, M.G & N.G….  Relationship of superelevation (e), with gauge(G), speed (V) and radius of the curve ( R ). W= Weight of moving vehicle in kg. v = Speed of vehicle in m/sec V = Speed of vehicle in km.ph R = Radius of curve in meters G = Gauge of track in meters g = Acceleration due to gravity in m/sec2 α = Angle of inclination S = Length of inclined surface in meters Centrifugal force is given by the following expression. F = Wv2/gR -------------(1) Now resolving the forces along the inclined surface we get F cosα = W sinα -------- (2)
  • 40.  Superelevation for B.G, M.G & N.G…. F = Wv2/gR , cosα = G/S & sinα = e/S Therefore equation (2) becomes Wv2/gR * G/S = W*e/S Therefore, e = v2/gR * G meters Where, v in m/sec. = G ( 0,278V)2/9.81R = GV2/127 R meter e = GV2/1.27 R centimeter For B.G., e = GV2/1.27 R = 1.676 V2/1.27 R centimeter For M.G., e = GV2/1.27 R = 1.0 V2/1.27 R centimeter For N.G., e = GV2/1.27 R = 0.762 V2/1.27 R centimeter