Content of the Presentation
• Sight distance at intersection
• Horizontal Alignment
• Super-Elevation
• Radius of curve
• Extra widening
• Transition curve
• Setback Distance
• Vertical Alignment
2
Prepared by: Bhavya Jaiswal
Click to edit Master title style
3
Sight distance at intersection
• Intersection sight distance could be understand as length
of the cross road, that must be clearly visible for the driver
of crossing or turning vehicle to be able to decide or
complete operation without any conflict with other
vehicles, approaching the intersection from the cross road.
• At intersections, where the two or more roads meet it is
essential to provide visibility for drivers, who are
approaching the intersections from the either sides.
• Sight distance should be provided for drivers on each side of the intersection, to make it easy
for them to find and see each other as shown in the below figure.
• IRC recommends that at non-controlled intersections, sufficient visibility should be provided
such that sight distance on each road is at-least equal to SSD corresponding to the design
speed of the road.
3
Prepared by: Bhavya Jaiswal
Click to edit Master title style
4
Sight distance at intersection
• IRC recommends that a minimum visibility distance of 15 m along the minor road and a
distance of 220, 180, 145 and 110 m along the major road corresponding to design
speeds of 100, 80, 65 and 60 kmph. respectively may be provided.
Why it is needed?
1. To enable the change of speed for a vehicle,
2. Enable stopping of the vehicle nearing the approach,
3. Enabling the stopped vehicles on the minor road to safely cross the main road at
intersection.
4
Prepared by: Bhavya Jaiswal
Click to edit Master title style
5
Headlight Distance
• It comes in a consideration during the night time.
• It could be defined as a distance which is visible
to the driver during the night time driving under
the enlightenment of the vehicle head light.
• This sight distance is critical in the case of up-
gradients and at an ascending portion of the
valley curve.
5
Prepared by: Bhavya Jaiswal
Click to edit Master title style
6
Horizontal Alignment
• When a vehicle moves on the horizontal curve, it is subjected to the centrifugal force
which is acting in outward direction of the road. This load can be counteracted upto a
certain level by frictional force between the Tyre and pavement surface.
• This outward centrifugal force causes discomfort to the passenger and increases the
possibility of accidents.
• In such cases, the horizontal alignment comes into picture.
• The components covered in the horizontal alignment are…
Super-Elevation
Radius of curve/ minimum ruling radius
Extra widening
Transition curve
6
Prepared by: Bhavya Jaiswal
Click to edit Master title style
7
Super-Elevation
• The super elevation can be defined as the Rising
of the outer edge of the pavement with respect to
the inner edge throughout the length of curve to
counteract the centrifugal force and reduce the
tendency of a vehicle to overturn is called Super-
Elevation.
• Derivation of the formula of Super-Elevation:
𝑃𝑐𝑜𝑠𝜃 = 𝑊𝑠𝑖𝑛𝜃 + 𝐹𝐴 + 𝐹𝐵
𝑃𝑐𝑜𝑠𝜃 = 𝑊𝑠𝑖𝑛𝜃 + 𝐹𝑅𝐴 + 𝐹𝑅𝐵
𝑃𝑐𝑜𝑠𝜃 = 𝑊𝑠𝑖𝑛𝜃 + 𝐹(𝑊𝑐𝑜𝑠𝜃) + 𝐹(𝑃𝑠𝑖𝑛𝜃)
𝑃𝑐𝑜𝑠𝜃 − 𝐹(𝑃𝑠𝑖𝑛𝜃) = 𝐹(𝑊𝑐𝑜𝑠𝜃) + 𝑊𝑠𝑖𝑛𝜃
𝑃𝑐𝑜𝑠𝜃[1 − 𝐹𝑡𝑎𝑛𝜃] = 𝑊𝑐𝑜𝑠𝜃[𝐹 + 𝑡𝑎𝑛𝜃]
7
Prepared by: Bhavya Jaiswal
Click to edit Master title style
8
Super-Elevation
Hence,
𝑃
𝑊
=
𝐹+𝑡𝑎𝑛𝜃
1−𝐹𝑡𝑎𝑛𝜃
We know that…𝑃 =
𝑚𝑉2
𝑅
=
𝑊𝑉2
𝑔𝑅
𝑃
𝑊
=
𝑉2
𝑔𝑅
If 𝐹𝑒 is neglected than…
𝑉2
𝑔𝑅
=
𝐹+𝑒
1−𝐹𝑒
So, 𝑒 + 𝑓 =
𝑉2
𝑔𝑅
If we put V in kmph and f as 0.15 than the super elevation will be as 𝒆 + 𝒇 =
𝑽𝟐
𝟏𝟐𝟕𝑹
8
Prepared by: Bhavya Jaiswal
Click to edit Master title style
9
Super-Elevation
• Here,
e= Super elevation
V= Speed of the vehicle, kmph
R= Radius of curve, m
f= Lateral Friction, 0.15
𝒆 + 𝒇 =
𝑽𝟐
𝟏𝟐𝟕𝑹
According to IRC:
𝑒𝑚𝑎𝑥 = 4% urban Road
𝑒𝑚𝑎𝑥 = 7% Plain terrain
𝑒𝑚𝑎𝑥 = 10% Hilly terrain
𝑒𝑚𝑖𝑛 = as the camber value
• If the friction factor is neglected than
the e with a formula e =
𝑽𝟐
𝟏𝟐𝟕𝑹
is
known as the Equilibrium Super
elevation.
9
Prepared by: Bhavya Jaiswal
Click to edit Master title style
10
Design of the Super-Elevation
• Design of the super elevation for the mix traffic is a complex problem because various
vehicle moves with various speed.
• Maximum value of the super elevation can be archived by neglecting the lateral friction
that is also for the vehicles which are moving with design speed
• So, to compromise and to catch the practical conditions, for calculation of super
elevation speed is taken as 75% of the design speed.
𝒆 + 𝒇 =
𝑽𝟐
𝟏𝟐𝟕𝑹
After neglecting f, e =
𝑽𝟐
𝟏𝟐𝟕𝑹
Now for the mix traffic, V= 0.75V than e =
𝟎.𝟕𝟓𝑽𝟐
𝟏𝟐𝟕𝑹
so the super elevation will be as e =
𝑽𝟐
𝟐𝟐𝟓𝑹
Step-1
10
Prepared by: Bhavya Jaiswal
Click to edit Master title style
11
Super-Elevation
If in the above equation Step-1, if e>0.07 than perform Step-2 as…
Put e=0.07 and find f
e + f =
𝑽𝟐
𝟏𝟐𝟕𝑹
f =
𝑽𝟐
𝟏𝟐𝟕𝑹
− 𝟎. 𝟎𝟕
Here, if f<0.15 than OK
But if f>0.15 than go for Step-3 as…
Put e=0.07 and f=0.15 and find new speed Va= allowable speed
e =
𝑽𝒂𝟐
𝟏𝟐𝟕𝑹
Step-2
Step-3
11
Prepared by: Bhavya Jaiswal
Click to edit Master title style
12
Numerical Super-Elevation
Q. Design a super elevation for plain and rolling terrain if R=500m and design
speed=100kmph.
Solution:
Step-1:
e =
𝑽𝟐
𝟐𝟐𝟓𝑹
e= 0.08>0.07
So taking e=0.07
Step-2:
𝒆 + 𝒇 =
𝑽𝟐
𝟏𝟐𝟕𝑹
𝒇 =
𝑽𝟐
𝟏𝟐𝟕𝑹
𝟎. 𝟎𝟕
f=0.07<0.15 OK. Than we can provide e as 0.07
12
Prepared by: Bhavya Jaiswal
Click to edit Master title style
13
Minimum Ruling Radius
The minimum curve radius is a limiting value of curvature for a given design
speed. In the design of horizontal alignment, smaller than the calculated
boundary value of minimum curve radius cannot be used. Thus, the minimum
radius of curvature is a significant value in alignment design.
The minimum ruling radius can be obtained by the following equation.
𝒆 + 𝒇 =
𝑽𝟐
𝟏𝟐𝟕𝑹
𝟎. 𝟎𝟕 + 𝟎. 𝟏𝟓 =
𝑽𝟐
𝟏𝟐𝟕𝑹
R =
𝑽𝟐
𝟐𝟕.𝟗𝟒
and R is in meter.
13
Prepared by: Bhavya Jaiswal
Click to edit Master title style
14
Extra Widening
• Additional width of carriage way which is required
at horizontal curve is known as extra widening.
• The rare wheel follow the inner earth on the curve
as compared to front wheel, this phenomena is
called Off-Tracking.
The following are the reasons for which extra
widening is essential.
1. To avoid off-tracking.
2. To avoid transverse skidding.
3. To increase visibility of curve.
4. To encounter phycological tendency while
overtaking.
14
Prepared by: Bhavya Jaiswal
Click to edit Master title style
15
Extra Widening
We = W mechanical + W phycological
We =
𝑛𝑙2
2𝑅
+
𝑉
9.5√𝑅
Here,
V= speed, kmph
n= number of lane
R= radius of curve, meter
l= wheel base length, meter
𝑙2
2𝑅
= off tracking
As per IRC:
If R<50m, widening only in inner edge.
If 50m<R<300m, widening in both edges.
If R>300m, no widening is required.
15
Prepared by: Bhavya Jaiswal
Click to edit Master title style
16
Grade Composition
• When there is a horizontal curve in addition to gradient than there will be
incremental loss of traction due to both curve and gradient.
• So t is necessary to compensate the grade in such cases of horizontal curve.
It can be found out by the following formula.
• Grade Compensation =
30+𝑅
𝑅
or
75
𝑅
whichever is minimum.
• In no case, Compensated Grade not less than 4%
16
Prepared by: Bhavya Jaiswal
Click to edit Master title style
17
Numerical of Grade Composition
Q. find the grade compensation and compensated grade for a vertical gradient of 7% and
horizontal curve 50m.
• Solution:
𝐺𝐶 =
30 + 𝑅
𝑅
= 1.5
𝐺𝐶 =
75
𝑅
= 1.6
𝑇ℎ𝑒 𝑐𝑜𝑚𝑝𝑒𝑛𝑠𝑎𝑡𝑒𝑑 𝑔𝑟𝑎𝑑𝑒 = 7 − 1.5 = 5.5%
17
Prepared by: Bhavya Jaiswal
Click to edit Master title style
18
Transition Curve
• When a vehicle travelling on straight road and if enters into a
horizontal curve suddenly, it will cause discomfort to the driver.
• To avoid this inconvenience, it is required to provide a
transition curve.
• It a curve having varying radius and provided between two
curves of different radius.
Objectives:
1. To increase centrifugal force between straight and circular
curve gently.
2. To avoid the sudden jerk.
3. To introduce super elevation and extra widening gradually.
4. To improve aesthetic appearance.
18
Prepared by: Bhavya Jaiswal
Click to edit Master title style
19
Length of the Transition Curve
1. On the basis of Rate of change of centrifugal acceleration: L=
𝑉3
𝑅𝐶
Where,
V= m/sec
C = rate of change in acc =
80
75+𝑉
2. Empirical formula by IRC: L=2.7
𝑉2
𝑅
for plain terrain and L=
𝑉2
𝑅
for hilly terrain.
Where, V=kmph
3. On the bases of change in super elevation:
L =
𝑒𝑁
2
(𝑤 + 𝑤𝑒) for rotated about center
L = 𝑒𝑁(𝑤 + 𝑤𝑒) for rotated about inner edge.
Where, 1/N = rate of change in super elevation, We = extra widening
The length of the transition curve is taken as maximum of all of above 3 approaches.
19
Prepared by: Bhavya Jaiswal
Click to edit Master title style
20
Types of the Transition Curve
• According to IRC, ideal shape of transition curve is
Spiral because rate of change of centrifugal
acceleration is constant in case of spiral curve.
• As we can see in the picture, there are three types
of spiral curve:
1) Cubic Parabola
2) Bernoulli's lemniscate
3) Spiral Curve.
20
Prepared by: Bhavya Jaiswal
Click to edit Master title style
21
Numerical on the Transition Curve
Q. Calculate length of the transition curve if the design speed=65kmph, Radius of
curve=220m, number of lane=2, pavement width=7.5m, super elevation=0.07, length of
wheel base=6m.
Solution:
Widening, We=
𝑛𝑙2
2𝑅
+
𝑉
9.5√𝑅
= 0.16 + 0.46 = 0.62𝑚
Length of TC:
1. L=
𝑉3
𝑅𝐶
= 46.82𝑚
2. L=2.7
𝑉2
𝑅
= 51.85𝑚
3. L = 𝑒𝑁 𝑤 + 𝑤𝑒 = 85.26𝑚
The maximum among all is 85.26m than the length of TC will be 85.26m.
21
Prepared by: Bhavya Jaiswal
Click to edit Master title style
22
Set-Back Distance
• Set back is clearance between centerline of the curve to
the obstruction on the inner side of curve which is
applied to provide the adequate sight distance.
• Case-1: L > SD
• 𝑀 = 𝑂𝐶 − 𝑂𝐷
• 𝑀 = 𝑅 − 𝑅𝑐𝑜𝑠
∝
2
•
∝
2
=
SD
2R
∗
180
π
If double lane road than 𝑀 = 𝑅 − 𝑅 − 𝑑 𝑐𝑜𝑠
∝
2
• And
∝
2
=
SD
2 R−d
∗
180
π
also 𝑑 =
𝑤+𝑤𝑒
4
22
Prepared by: Bhavya Jaiswal
Click to edit Master title style
23
Set-Back Distance
From the center of inner edge: Ed
𝑀 = 𝑅 − 𝑑 − 𝑅 − 𝑑 𝑐𝑜𝑠
∝
2
From the edge of road: Fd
𝑀 = 𝑅 − 2𝑑 − 𝑅 − 𝑑 𝑐𝑜𝑠
∝
2
So, in general
𝑀 = 𝑅 − 𝑅 − 𝑛 − 1 𝑑 𝑐𝑜𝑠
∝
2
∝
2
=
SD
2 R − n − 1 d
∗
180
π
𝑑 =
𝑤 + 𝑤𝑒
2𝑛
Where n = number of lanes.
23
Prepared by: Bhavya Jaiswal
Click to edit Master title style
24
Set-Back Distance
Case-2: L < SD
𝑀 = 𝑅 − 𝑅𝑐𝑜𝑠
∝
2
+
𝑆𝐷 − 𝐿
2
𝑠𝑖𝑛
∝
2
∝=
𝐿
2𝑅
×
180
𝜋
And change all the formula accordingly.
24
Prepared by: Bhavya Jaiswal
Click to edit Master title style
25
Numerical on Set-Back Distance
Q. A horizontal circular curve with a centerline radius of 160m is provided on two lane two way
straight highway section. Width of two lane is 7m, reaction time 2.4sec, design speed is 80kmph,
f=0.355. calculate the set back distance from center line of inner edge and length of curve is
300m.
Solution:
𝑆 = 𝑉𝑡 +
𝑉2
2𝑔𝑓
= 125𝑚 so L > SD.
From the center of inner edge,
𝑑 =
𝑤 + 𝑤𝑒
4
= 1.97𝑚
∝
2
=
SD
2 R − d
∗
180
π
= 22.66
𝑀 = 𝑅 − 𝑑 − 𝑅 − 𝑑 𝑐𝑜𝑠
∝
2
= 12.19𝑚
25
Prepared by: Bhavya Jaiswal
Click to edit Master title style
26
Vertical curve
• Vertical curves are used in highway and street
vertical alignment to provide a gradual change
between two adjacent grade lines.
• There are two types of vertical curve in the
highway which are as below:
1. Summit Curve
2. Valley Curve
26
Prepared by: Bhavya Jaiswal
Click to edit Master title style
27
1. Summit Curve
• It is a convex upward side and concave downward
side.
• The best shape of the summit curve is square
parabola but the ideal shape of the curve is
circular.
• Square parabola gives the good riding qualities
and uniform rate of change in grade.
• Length of summit curve depends on sight
distances.
• There is no problem of discomfort in summit curve
because gravity forces act downward and
centrifugal force acts upward.
27
Prepared by: Bhavya Jaiswal
Click to edit Master title style
28
Length of the Summit Curve
𝐿 =
𝑁𝑆2
2𝐻 + 2ℎ
2
H = height of driver from pavement surface
H = height of object from pavement surface
H = 1.2m and h = 0.15m for SSD
H = 1.2m and h = 1.2m for OSD
 Case-1, L > Sight Distance
𝐿 =
𝑁𝑆2
4.4
for SSD
𝐿 =
𝑁𝑆2
9.6
for OSD
 Case-2, L < Sight Distance
𝐿 = 25 −
4.4
𝑁
for SSD
𝐿 = 25 −
9.6
𝑁
for OSD
28
Prepared by: Bhavya Jaiswal
Click to edit Master title style
29
Numerical of the Summit Curve
Q. Find the length of the vertical curve when an ascending gradient of 1 in 50 meets a
descending gradient of 1 in 80 and the SSD is 180m.
Solution:
𝑁 = 𝑛1 + 𝑛2
𝑁 =
1
50
+
1
80
𝑁 = 0.0325
Here, SSD = 180m
𝐿 =
𝑁𝑆2
4.4
= 239.3~240𝑚
29
Prepared by: Bhavya Jaiswal
Click to edit Master title style
30
2. Valley Curve
• Valley curve is concave upward and convex
downward.
• Valley curve is generally mid of two transition
curve of equal length without having circular
curve in between.
• Cubic parabola is the best shape for the valley
curves to gradually introduce the centrifugal
force.
• in case of valley curve, centrifugal force and
gravity force both are acting downward that
makes valley curves uncomfortable.
30
Prepared by: Bhavya Jaiswal
Click to edit Master title style
31
2. Valley Curve
The design of the valley curve is done as per the following approaches:
Case-1: Based on comfort, 𝐿𝑉 = 2√
𝑁𝑉3
𝐶
Where,
V = m/sec
C = 0.6m/𝑆2
Case-2: Based on Headlight sight Distance
If L > HSD, 𝐿𝑉 =
𝑁𝑆2
1.5+0.035𝑆
If L < HSD, 𝐿𝑉 = 2𝑆 −
1.5+0.035𝑆
𝑁
Where, S = sight distance
Sight distance is not a problem for valley curve because in night time other vehicle with
headlight can be seen from a considerable distance.
Length of valley curve is taken as the maximum among both 31
Prepared by: Bhavya Jaiswal
Click to edit Master title style
32
Numerical on Valley Curve
Q. A vertical curve is designed when a descending gradient of 1 in 25 meets with
ascending gradient of 1 in 30. Design the length of the Valley curve if the speed is
80kmph.
Solution:
𝑁 = 𝑛1 + 𝑛2
𝑁 = −(
1
25
+
1
30
)
𝑁 = −0.0733
Approach-1:
𝐿𝑉 = 2
𝑁𝑉3
𝐶
= 73.21𝑚
Approach-2:
𝐿𝑉 =
𝑁𝑆2
1.5 + 0.035𝑆
= 198.18𝑚
𝑆 = 𝑉𝑡 +
𝑉2
2𝑔𝑓
= 126.65𝑚
Length of valley curve is taken as the maximum among both so it will be 198.18m 32
Prepared by: Bhavya Jaiswal

More Related Content

What's hot

highway development in india
highway development in indiahighway development in india
highway development in indiaPrathi Baa
 
Horizontal curve- IRC 38
Horizontal curve- IRC 38Horizontal curve- IRC 38
Horizontal curve- IRC 38Surabhi Suman
 
Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)Civil Zone
 
Overtaking sight distance
Overtaking sight distanceOvertaking sight distance
Overtaking sight distanceAglaia Connect
 
Highway Vertical Alignment
Highway Vertical AlignmentHighway Vertical Alignment
Highway Vertical AlignmentAkshathaBhandary
 
Geometric Design - Horizontal and vertical curves
Geometric Design - Horizontal and vertical curvesGeometric Design - Horizontal and vertical curves
Geometric Design - Horizontal and vertical curvessachin dass
 
L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3 L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3 Sachin PatiL
 
Geometric design of highways
Geometric design of highways Geometric design of highways
Geometric design of highways akshaydesai76
 
Site distance in highway engineering
Site distance in highway engineeringSite distance in highway engineering
Site distance in highway engineeringtirath prajapati
 
Highway engineering PPT
Highway engineering PPTHighway engineering PPT
Highway engineering PPTKavin Raval
 
Highway & road geomatric and its component
Highway & road geomatric and its component Highway & road geomatric and its component
Highway & road geomatric and its component Sumit Kumar
 
Transition curve and Superelevation
Transition curve and SuperelevationTransition curve and Superelevation
Transition curve and SuperelevationMir Zafarullah
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavementpjainrahul
 
Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometricsKHUSHBU SHAH
 
Highway Cross-sectional Elements
Highway Cross-sectional ElementsHighway Cross-sectional Elements
Highway Cross-sectional ElementsAkshathaBhandary
 

What's hot (20)

Sight distance
Sight distanceSight distance
Sight distance
 
highway development in india
highway development in indiahighway development in india
highway development in india
 
Horizontal curve- IRC 38
Horizontal curve- IRC 38Horizontal curve- IRC 38
Horizontal curve- IRC 38
 
Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)
 
Overtaking sight distance
Overtaking sight distanceOvertaking sight distance
Overtaking sight distance
 
Design flexible and rigid pavements
Design flexible and rigid pavementsDesign flexible and rigid pavements
Design flexible and rigid pavements
 
Highway Vertical Alignment
Highway Vertical AlignmentHighway Vertical Alignment
Highway Vertical Alignment
 
Geometric Design - Horizontal and vertical curves
Geometric Design - Horizontal and vertical curvesGeometric Design - Horizontal and vertical curves
Geometric Design - Horizontal and vertical curves
 
Unit 2
Unit 2Unit 2
Unit 2
 
L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3 L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3
 
Geometric design of highways
Geometric design of highways Geometric design of highways
Geometric design of highways
 
Site distance in highway engineering
Site distance in highway engineeringSite distance in highway engineering
Site distance in highway engineering
 
Highway engineering PPT
Highway engineering PPTHighway engineering PPT
Highway engineering PPT
 
Highway & road geomatric and its component
Highway & road geomatric and its component Highway & road geomatric and its component
Highway & road geomatric and its component
 
Superelevation
SuperelevationSuperelevation
Superelevation
 
Transition curve and Superelevation
Transition curve and SuperelevationTransition curve and Superelevation
Transition curve and Superelevation
 
Highway Alignment
Highway AlignmentHighway Alignment
Highway Alignment
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometrics
 
Highway Cross-sectional Elements
Highway Cross-sectional ElementsHighway Cross-sectional Elements
Highway Cross-sectional Elements
 

Similar to Geometric Design of Highways

transitioncurve-210816162648.pdf
transitioncurve-210816162648.pdftransitioncurve-210816162648.pdf
transitioncurve-210816162648.pdfRenjith S Anand
 
hz alignment lec4.pdf
hz alignment lec4.pdfhz alignment lec4.pdf
hz alignment lec4.pdfamira525139
 
Geometric design of the track
Geometric design of the trackGeometric design of the track
Geometric design of the trackT.Naga Anusha
 
Sight Distance for horizontal curves
Sight Distance for horizontal curvesSight Distance for horizontal curves
Sight Distance for horizontal curvesLatif Hyder Wadho
 
3 vertical alignment of road by Malyar Talash
3 vertical alignment of road by Malyar Talash3 vertical alignment of road by Malyar Talash
3 vertical alignment of road by Malyar TalashMalyar Talash
 
transition curve in Highway Geometry Design
transition curve in Highway Geometry Designtransition curve in Highway Geometry Design
transition curve in Highway Geometry DesignNachiketa Mithaiwala
 
Railway engg geometric design
Railway engg geometric designRailway engg geometric design
Railway engg geometric designVijai Krishnan V
 
Chapter 2 track geometrics and its maintainance
Chapter 2 track geometrics and its maintainanceChapter 2 track geometrics and its maintainance
Chapter 2 track geometrics and its maintainancedhara dattani
 
Chapter 2 Track Geometry.pptx
Chapter 2 Track Geometry.pptxChapter 2 Track Geometry.pptx
Chapter 2 Track Geometry.pptxMamushLeta
 
Alighnment & horizontal alignment of highway (transportation engineering)
Alighnment & horizontal alignment of highway (transportation engineering)Alighnment & horizontal alignment of highway (transportation engineering)
Alighnment & horizontal alignment of highway (transportation engineering)Civil Zone
 
Chapter 4 Lecture-11,12,13-Transition-Curves.pptx
Chapter 4 Lecture-11,12,13-Transition-Curves.pptxChapter 4 Lecture-11,12,13-Transition-Curves.pptx
Chapter 4 Lecture-11,12,13-Transition-Curves.pptxakhnd4
 
Dual Axis Steering Mechainism .pdf
Dual Axis Steering Mechainism .pdfDual Axis Steering Mechainism .pdf
Dual Axis Steering Mechainism .pdfKunalSonawane26
 
Vertical Alignment in road design
Vertical Alignment in road designVertical Alignment in road design
Vertical Alignment in road designpresentationsinfo
 
Vertical alignment of highway (transportation engineering)
Vertical alignment of highway (transportation engineering)Vertical alignment of highway (transportation engineering)
Vertical alignment of highway (transportation engineering)Civil Zone
 
CAM Mechanism Reading Material.pdf
CAM Mechanism Reading Material.pdfCAM Mechanism Reading Material.pdf
CAM Mechanism Reading Material.pdfSandip Paudel
 

Similar to Geometric Design of Highways (20)

Transportation engineering highway part
Transportation engineering highway partTransportation engineering highway part
Transportation engineering highway part
 
SUPER_ELEVATION.pdf
SUPER_ELEVATION.pdfSUPER_ELEVATION.pdf
SUPER_ELEVATION.pdf
 
transitioncurve-210816162648.pdf
transitioncurve-210816162648.pdftransitioncurve-210816162648.pdf
transitioncurve-210816162648.pdf
 
hz alignment lec4.pdf
hz alignment lec4.pdfhz alignment lec4.pdf
hz alignment lec4.pdf
 
Geometric design of the track
Geometric design of the trackGeometric design of the track
Geometric design of the track
 
Sight Distance for horizontal curves
Sight Distance for horizontal curvesSight Distance for horizontal curves
Sight Distance for horizontal curves
 
3 vertical alignment of road by Malyar Talash
3 vertical alignment of road by Malyar Talash3 vertical alignment of road by Malyar Talash
3 vertical alignment of road by Malyar Talash
 
transition curve in Highway Geometry Design
transition curve in Highway Geometry Designtransition curve in Highway Geometry Design
transition curve in Highway Geometry Design
 
Geometric design
Geometric designGeometric design
Geometric design
 
Cam mech
Cam mechCam mech
Cam mech
 
Railway engg geometric design
Railway engg geometric designRailway engg geometric design
Railway engg geometric design
 
Chapter 2 track geometrics and its maintainance
Chapter 2 track geometrics and its maintainanceChapter 2 track geometrics and its maintainance
Chapter 2 track geometrics and its maintainance
 
Chapter 2 Track Geometry.pptx
Chapter 2 Track Geometry.pptxChapter 2 Track Geometry.pptx
Chapter 2 Track Geometry.pptx
 
Chapter 5 cam mechanisms
Chapter 5 cam mechanismsChapter 5 cam mechanisms
Chapter 5 cam mechanisms
 
Alighnment & horizontal alignment of highway (transportation engineering)
Alighnment & horizontal alignment of highway (transportation engineering)Alighnment & horizontal alignment of highway (transportation engineering)
Alighnment & horizontal alignment of highway (transportation engineering)
 
Chapter 4 Lecture-11,12,13-Transition-Curves.pptx
Chapter 4 Lecture-11,12,13-Transition-Curves.pptxChapter 4 Lecture-11,12,13-Transition-Curves.pptx
Chapter 4 Lecture-11,12,13-Transition-Curves.pptx
 
Dual Axis Steering Mechainism .pdf
Dual Axis Steering Mechainism .pdfDual Axis Steering Mechainism .pdf
Dual Axis Steering Mechainism .pdf
 
Vertical Alignment in road design
Vertical Alignment in road designVertical Alignment in road design
Vertical Alignment in road design
 
Vertical alignment of highway (transportation engineering)
Vertical alignment of highway (transportation engineering)Vertical alignment of highway (transportation engineering)
Vertical alignment of highway (transportation engineering)
 
CAM Mechanism Reading Material.pdf
CAM Mechanism Reading Material.pdfCAM Mechanism Reading Material.pdf
CAM Mechanism Reading Material.pdf
 

More from Bhavya Jaiswal

Airport connecting with other mode of transportation and infrastructure devel...
Airport connecting with other mode of transportation and infrastructure devel...Airport connecting with other mode of transportation and infrastructure devel...
Airport connecting with other mode of transportation and infrastructure devel...Bhavya Jaiswal
 
Navigational aids in waterways and infrastructure development with
Navigational aids in waterways and infrastructure development withNavigational aids in waterways and infrastructure development with
Navigational aids in waterways and infrastructure development withBhavya Jaiswal
 
Smartcity ahmedabad_smart_city_proposalsummary-converted
 Smartcity ahmedabad_smart_city_proposalsummary-converted Smartcity ahmedabad_smart_city_proposalsummary-converted
Smartcity ahmedabad_smart_city_proposalsummary-convertedBhavya Jaiswal
 
The its application in railways
The its application in railwaysThe its application in railways
The its application in railwaysBhavya Jaiswal
 
Metro and monorail infrastructure development in india
Metro and monorail infrastructure development in indiaMetro and monorail infrastructure development in india
Metro and monorail infrastructure development in indiaBhavya Jaiswal
 
Desert and swampy road construction
Desert and swampy road constructionDesert and swampy road construction
Desert and swampy road constructionBhavya Jaiswal
 
Seasonal limitations of bituminous pavement construction
Seasonal limitations of bituminous pavement constructionSeasonal limitations of bituminous pavement construction
Seasonal limitations of bituminous pavement constructionBhavya Jaiswal
 
Route optimization for collection of municipal solid waste
Route optimization for collection of municipal solid wasteRoute optimization for collection of municipal solid waste
Route optimization for collection of municipal solid wasteBhavya Jaiswal
 
Design of cc pavement by IRC 58
Design of cc pavement by IRC 58Design of cc pavement by IRC 58
Design of cc pavement by IRC 58Bhavya Jaiswal
 
Dowel bars, tie bars and their design
Dowel bars, tie bars and their designDowel bars, tie bars and their design
Dowel bars, tie bars and their designBhavya Jaiswal
 
Types of joints in rigid pavement
Types of joints in rigid pavementTypes of joints in rigid pavement
Types of joints in rigid pavementBhavya Jaiswal
 
Continuous reinforced rigid pavement
Continuous reinforced rigid pavementContinuous reinforced rigid pavement
Continuous reinforced rigid pavementBhavya Jaiswal
 
Ranking and optimization in pavements
Ranking and optimization in pavementsRanking and optimization in pavements
Ranking and optimization in pavementsBhavya Jaiswal
 
Recycling of the pavements
Recycling of the pavementsRecycling of the pavements
Recycling of the pavementsBhavya Jaiswal
 
Distresses in the pavement
Distresses in the pavementDistresses in the pavement
Distresses in the pavementBhavya Jaiswal
 
Airfield design methods
Airfield design methodsAirfield design methods
Airfield design methodsBhavya Jaiswal
 
Aircraft landing gear configuration and tyre pressure
Aircraft landing gear configuration and tyre pressureAircraft landing gear configuration and tyre pressure
Aircraft landing gear configuration and tyre pressureBhavya Jaiswal
 
Components of Airfield
Components of AirfieldComponents of Airfield
Components of AirfieldBhavya Jaiswal
 

More from Bhavya Jaiswal (20)

Airport connecting with other mode of transportation and infrastructure devel...
Airport connecting with other mode of transportation and infrastructure devel...Airport connecting with other mode of transportation and infrastructure devel...
Airport connecting with other mode of transportation and infrastructure devel...
 
Navigational aids in waterways and infrastructure development with
Navigational aids in waterways and infrastructure development withNavigational aids in waterways and infrastructure development with
Navigational aids in waterways and infrastructure development with
 
Major ports of india
Major ports of indiaMajor ports of india
Major ports of india
 
Smartcity ahmedabad_smart_city_proposalsummary-converted
 Smartcity ahmedabad_smart_city_proposalsummary-converted Smartcity ahmedabad_smart_city_proposalsummary-converted
Smartcity ahmedabad_smart_city_proposalsummary-converted
 
The its application in railways
The its application in railwaysThe its application in railways
The its application in railways
 
Metro and monorail infrastructure development in india
Metro and monorail infrastructure development in indiaMetro and monorail infrastructure development in india
Metro and monorail infrastructure development in india
 
Desert and swampy road construction
Desert and swampy road constructionDesert and swampy road construction
Desert and swampy road construction
 
Seasonal limitations of bituminous pavement construction
Seasonal limitations of bituminous pavement constructionSeasonal limitations of bituminous pavement construction
Seasonal limitations of bituminous pavement construction
 
Route optimization for collection of municipal solid waste
Route optimization for collection of municipal solid wasteRoute optimization for collection of municipal solid waste
Route optimization for collection of municipal solid waste
 
Design of cc pavement by IRC 58
Design of cc pavement by IRC 58Design of cc pavement by IRC 58
Design of cc pavement by IRC 58
 
Dowel bars, tie bars and their design
Dowel bars, tie bars and their designDowel bars, tie bars and their design
Dowel bars, tie bars and their design
 
Types of joints in rigid pavement
Types of joints in rigid pavementTypes of joints in rigid pavement
Types of joints in rigid pavement
 
F test
F testF test
F test
 
Continuous reinforced rigid pavement
Continuous reinforced rigid pavementContinuous reinforced rigid pavement
Continuous reinforced rigid pavement
 
Ranking and optimization in pavements
Ranking and optimization in pavementsRanking and optimization in pavements
Ranking and optimization in pavements
 
Recycling of the pavements
Recycling of the pavementsRecycling of the pavements
Recycling of the pavements
 
Distresses in the pavement
Distresses in the pavementDistresses in the pavement
Distresses in the pavement
 
Airfield design methods
Airfield design methodsAirfield design methods
Airfield design methods
 
Aircraft landing gear configuration and tyre pressure
Aircraft landing gear configuration and tyre pressureAircraft landing gear configuration and tyre pressure
Aircraft landing gear configuration and tyre pressure
 
Components of Airfield
Components of AirfieldComponents of Airfield
Components of Airfield
 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 

Recently uploaded (20)

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 

Geometric Design of Highways

  • 1. Click to edit Master title style 1 Geometric Design of Highway Highway Engineering Prepared by: Bhavya Jaiswal
  • 2. Click to edit Master title style 2 Content of the Presentation • Sight distance at intersection • Horizontal Alignment • Super-Elevation • Radius of curve • Extra widening • Transition curve • Setback Distance • Vertical Alignment 2 Prepared by: Bhavya Jaiswal
  • 3. Click to edit Master title style 3 Sight distance at intersection • Intersection sight distance could be understand as length of the cross road, that must be clearly visible for the driver of crossing or turning vehicle to be able to decide or complete operation without any conflict with other vehicles, approaching the intersection from the cross road. • At intersections, where the two or more roads meet it is essential to provide visibility for drivers, who are approaching the intersections from the either sides. • Sight distance should be provided for drivers on each side of the intersection, to make it easy for them to find and see each other as shown in the below figure. • IRC recommends that at non-controlled intersections, sufficient visibility should be provided such that sight distance on each road is at-least equal to SSD corresponding to the design speed of the road. 3 Prepared by: Bhavya Jaiswal
  • 4. Click to edit Master title style 4 Sight distance at intersection • IRC recommends that a minimum visibility distance of 15 m along the minor road and a distance of 220, 180, 145 and 110 m along the major road corresponding to design speeds of 100, 80, 65 and 60 kmph. respectively may be provided. Why it is needed? 1. To enable the change of speed for a vehicle, 2. Enable stopping of the vehicle nearing the approach, 3. Enabling the stopped vehicles on the minor road to safely cross the main road at intersection. 4 Prepared by: Bhavya Jaiswal
  • 5. Click to edit Master title style 5 Headlight Distance • It comes in a consideration during the night time. • It could be defined as a distance which is visible to the driver during the night time driving under the enlightenment of the vehicle head light. • This sight distance is critical in the case of up- gradients and at an ascending portion of the valley curve. 5 Prepared by: Bhavya Jaiswal
  • 6. Click to edit Master title style 6 Horizontal Alignment • When a vehicle moves on the horizontal curve, it is subjected to the centrifugal force which is acting in outward direction of the road. This load can be counteracted upto a certain level by frictional force between the Tyre and pavement surface. • This outward centrifugal force causes discomfort to the passenger and increases the possibility of accidents. • In such cases, the horizontal alignment comes into picture. • The components covered in the horizontal alignment are… Super-Elevation Radius of curve/ minimum ruling radius Extra widening Transition curve 6 Prepared by: Bhavya Jaiswal
  • 7. Click to edit Master title style 7 Super-Elevation • The super elevation can be defined as the Rising of the outer edge of the pavement with respect to the inner edge throughout the length of curve to counteract the centrifugal force and reduce the tendency of a vehicle to overturn is called Super- Elevation. • Derivation of the formula of Super-Elevation: 𝑃𝑐𝑜𝑠𝜃 = 𝑊𝑠𝑖𝑛𝜃 + 𝐹𝐴 + 𝐹𝐵 𝑃𝑐𝑜𝑠𝜃 = 𝑊𝑠𝑖𝑛𝜃 + 𝐹𝑅𝐴 + 𝐹𝑅𝐵 𝑃𝑐𝑜𝑠𝜃 = 𝑊𝑠𝑖𝑛𝜃 + 𝐹(𝑊𝑐𝑜𝑠𝜃) + 𝐹(𝑃𝑠𝑖𝑛𝜃) 𝑃𝑐𝑜𝑠𝜃 − 𝐹(𝑃𝑠𝑖𝑛𝜃) = 𝐹(𝑊𝑐𝑜𝑠𝜃) + 𝑊𝑠𝑖𝑛𝜃 𝑃𝑐𝑜𝑠𝜃[1 − 𝐹𝑡𝑎𝑛𝜃] = 𝑊𝑐𝑜𝑠𝜃[𝐹 + 𝑡𝑎𝑛𝜃] 7 Prepared by: Bhavya Jaiswal
  • 8. Click to edit Master title style 8 Super-Elevation Hence, 𝑃 𝑊 = 𝐹+𝑡𝑎𝑛𝜃 1−𝐹𝑡𝑎𝑛𝜃 We know that…𝑃 = 𝑚𝑉2 𝑅 = 𝑊𝑉2 𝑔𝑅 𝑃 𝑊 = 𝑉2 𝑔𝑅 If 𝐹𝑒 is neglected than… 𝑉2 𝑔𝑅 = 𝐹+𝑒 1−𝐹𝑒 So, 𝑒 + 𝑓 = 𝑉2 𝑔𝑅 If we put V in kmph and f as 0.15 than the super elevation will be as 𝒆 + 𝒇 = 𝑽𝟐 𝟏𝟐𝟕𝑹 8 Prepared by: Bhavya Jaiswal
  • 9. Click to edit Master title style 9 Super-Elevation • Here, e= Super elevation V= Speed of the vehicle, kmph R= Radius of curve, m f= Lateral Friction, 0.15 𝒆 + 𝒇 = 𝑽𝟐 𝟏𝟐𝟕𝑹 According to IRC: 𝑒𝑚𝑎𝑥 = 4% urban Road 𝑒𝑚𝑎𝑥 = 7% Plain terrain 𝑒𝑚𝑎𝑥 = 10% Hilly terrain 𝑒𝑚𝑖𝑛 = as the camber value • If the friction factor is neglected than the e with a formula e = 𝑽𝟐 𝟏𝟐𝟕𝑹 is known as the Equilibrium Super elevation. 9 Prepared by: Bhavya Jaiswal
  • 10. Click to edit Master title style 10 Design of the Super-Elevation • Design of the super elevation for the mix traffic is a complex problem because various vehicle moves with various speed. • Maximum value of the super elevation can be archived by neglecting the lateral friction that is also for the vehicles which are moving with design speed • So, to compromise and to catch the practical conditions, for calculation of super elevation speed is taken as 75% of the design speed. 𝒆 + 𝒇 = 𝑽𝟐 𝟏𝟐𝟕𝑹 After neglecting f, e = 𝑽𝟐 𝟏𝟐𝟕𝑹 Now for the mix traffic, V= 0.75V than e = 𝟎.𝟕𝟓𝑽𝟐 𝟏𝟐𝟕𝑹 so the super elevation will be as e = 𝑽𝟐 𝟐𝟐𝟓𝑹 Step-1 10 Prepared by: Bhavya Jaiswal
  • 11. Click to edit Master title style 11 Super-Elevation If in the above equation Step-1, if e>0.07 than perform Step-2 as… Put e=0.07 and find f e + f = 𝑽𝟐 𝟏𝟐𝟕𝑹 f = 𝑽𝟐 𝟏𝟐𝟕𝑹 − 𝟎. 𝟎𝟕 Here, if f<0.15 than OK But if f>0.15 than go for Step-3 as… Put e=0.07 and f=0.15 and find new speed Va= allowable speed e = 𝑽𝒂𝟐 𝟏𝟐𝟕𝑹 Step-2 Step-3 11 Prepared by: Bhavya Jaiswal
  • 12. Click to edit Master title style 12 Numerical Super-Elevation Q. Design a super elevation for plain and rolling terrain if R=500m and design speed=100kmph. Solution: Step-1: e = 𝑽𝟐 𝟐𝟐𝟓𝑹 e= 0.08>0.07 So taking e=0.07 Step-2: 𝒆 + 𝒇 = 𝑽𝟐 𝟏𝟐𝟕𝑹 𝒇 = 𝑽𝟐 𝟏𝟐𝟕𝑹 𝟎. 𝟎𝟕 f=0.07<0.15 OK. Than we can provide e as 0.07 12 Prepared by: Bhavya Jaiswal
  • 13. Click to edit Master title style 13 Minimum Ruling Radius The minimum curve radius is a limiting value of curvature for a given design speed. In the design of horizontal alignment, smaller than the calculated boundary value of minimum curve radius cannot be used. Thus, the minimum radius of curvature is a significant value in alignment design. The minimum ruling radius can be obtained by the following equation. 𝒆 + 𝒇 = 𝑽𝟐 𝟏𝟐𝟕𝑹 𝟎. 𝟎𝟕 + 𝟎. 𝟏𝟓 = 𝑽𝟐 𝟏𝟐𝟕𝑹 R = 𝑽𝟐 𝟐𝟕.𝟗𝟒 and R is in meter. 13 Prepared by: Bhavya Jaiswal
  • 14. Click to edit Master title style 14 Extra Widening • Additional width of carriage way which is required at horizontal curve is known as extra widening. • The rare wheel follow the inner earth on the curve as compared to front wheel, this phenomena is called Off-Tracking. The following are the reasons for which extra widening is essential. 1. To avoid off-tracking. 2. To avoid transverse skidding. 3. To increase visibility of curve. 4. To encounter phycological tendency while overtaking. 14 Prepared by: Bhavya Jaiswal
  • 15. Click to edit Master title style 15 Extra Widening We = W mechanical + W phycological We = 𝑛𝑙2 2𝑅 + 𝑉 9.5√𝑅 Here, V= speed, kmph n= number of lane R= radius of curve, meter l= wheel base length, meter 𝑙2 2𝑅 = off tracking As per IRC: If R<50m, widening only in inner edge. If 50m<R<300m, widening in both edges. If R>300m, no widening is required. 15 Prepared by: Bhavya Jaiswal
  • 16. Click to edit Master title style 16 Grade Composition • When there is a horizontal curve in addition to gradient than there will be incremental loss of traction due to both curve and gradient. • So t is necessary to compensate the grade in such cases of horizontal curve. It can be found out by the following formula. • Grade Compensation = 30+𝑅 𝑅 or 75 𝑅 whichever is minimum. • In no case, Compensated Grade not less than 4% 16 Prepared by: Bhavya Jaiswal
  • 17. Click to edit Master title style 17 Numerical of Grade Composition Q. find the grade compensation and compensated grade for a vertical gradient of 7% and horizontal curve 50m. • Solution: 𝐺𝐶 = 30 + 𝑅 𝑅 = 1.5 𝐺𝐶 = 75 𝑅 = 1.6 𝑇ℎ𝑒 𝑐𝑜𝑚𝑝𝑒𝑛𝑠𝑎𝑡𝑒𝑑 𝑔𝑟𝑎𝑑𝑒 = 7 − 1.5 = 5.5% 17 Prepared by: Bhavya Jaiswal
  • 18. Click to edit Master title style 18 Transition Curve • When a vehicle travelling on straight road and if enters into a horizontal curve suddenly, it will cause discomfort to the driver. • To avoid this inconvenience, it is required to provide a transition curve. • It a curve having varying radius and provided between two curves of different radius. Objectives: 1. To increase centrifugal force between straight and circular curve gently. 2. To avoid the sudden jerk. 3. To introduce super elevation and extra widening gradually. 4. To improve aesthetic appearance. 18 Prepared by: Bhavya Jaiswal
  • 19. Click to edit Master title style 19 Length of the Transition Curve 1. On the basis of Rate of change of centrifugal acceleration: L= 𝑉3 𝑅𝐶 Where, V= m/sec C = rate of change in acc = 80 75+𝑉 2. Empirical formula by IRC: L=2.7 𝑉2 𝑅 for plain terrain and L= 𝑉2 𝑅 for hilly terrain. Where, V=kmph 3. On the bases of change in super elevation: L = 𝑒𝑁 2 (𝑤 + 𝑤𝑒) for rotated about center L = 𝑒𝑁(𝑤 + 𝑤𝑒) for rotated about inner edge. Where, 1/N = rate of change in super elevation, We = extra widening The length of the transition curve is taken as maximum of all of above 3 approaches. 19 Prepared by: Bhavya Jaiswal
  • 20. Click to edit Master title style 20 Types of the Transition Curve • According to IRC, ideal shape of transition curve is Spiral because rate of change of centrifugal acceleration is constant in case of spiral curve. • As we can see in the picture, there are three types of spiral curve: 1) Cubic Parabola 2) Bernoulli's lemniscate 3) Spiral Curve. 20 Prepared by: Bhavya Jaiswal
  • 21. Click to edit Master title style 21 Numerical on the Transition Curve Q. Calculate length of the transition curve if the design speed=65kmph, Radius of curve=220m, number of lane=2, pavement width=7.5m, super elevation=0.07, length of wheel base=6m. Solution: Widening, We= 𝑛𝑙2 2𝑅 + 𝑉 9.5√𝑅 = 0.16 + 0.46 = 0.62𝑚 Length of TC: 1. L= 𝑉3 𝑅𝐶 = 46.82𝑚 2. L=2.7 𝑉2 𝑅 = 51.85𝑚 3. L = 𝑒𝑁 𝑤 + 𝑤𝑒 = 85.26𝑚 The maximum among all is 85.26m than the length of TC will be 85.26m. 21 Prepared by: Bhavya Jaiswal
  • 22. Click to edit Master title style 22 Set-Back Distance • Set back is clearance between centerline of the curve to the obstruction on the inner side of curve which is applied to provide the adequate sight distance. • Case-1: L > SD • 𝑀 = 𝑂𝐶 − 𝑂𝐷 • 𝑀 = 𝑅 − 𝑅𝑐𝑜𝑠 ∝ 2 • ∝ 2 = SD 2R ∗ 180 π If double lane road than 𝑀 = 𝑅 − 𝑅 − 𝑑 𝑐𝑜𝑠 ∝ 2 • And ∝ 2 = SD 2 R−d ∗ 180 π also 𝑑 = 𝑤+𝑤𝑒 4 22 Prepared by: Bhavya Jaiswal
  • 23. Click to edit Master title style 23 Set-Back Distance From the center of inner edge: Ed 𝑀 = 𝑅 − 𝑑 − 𝑅 − 𝑑 𝑐𝑜𝑠 ∝ 2 From the edge of road: Fd 𝑀 = 𝑅 − 2𝑑 − 𝑅 − 𝑑 𝑐𝑜𝑠 ∝ 2 So, in general 𝑀 = 𝑅 − 𝑅 − 𝑛 − 1 𝑑 𝑐𝑜𝑠 ∝ 2 ∝ 2 = SD 2 R − n − 1 d ∗ 180 π 𝑑 = 𝑤 + 𝑤𝑒 2𝑛 Where n = number of lanes. 23 Prepared by: Bhavya Jaiswal
  • 24. Click to edit Master title style 24 Set-Back Distance Case-2: L < SD 𝑀 = 𝑅 − 𝑅𝑐𝑜𝑠 ∝ 2 + 𝑆𝐷 − 𝐿 2 𝑠𝑖𝑛 ∝ 2 ∝= 𝐿 2𝑅 × 180 𝜋 And change all the formula accordingly. 24 Prepared by: Bhavya Jaiswal
  • 25. Click to edit Master title style 25 Numerical on Set-Back Distance Q. A horizontal circular curve with a centerline radius of 160m is provided on two lane two way straight highway section. Width of two lane is 7m, reaction time 2.4sec, design speed is 80kmph, f=0.355. calculate the set back distance from center line of inner edge and length of curve is 300m. Solution: 𝑆 = 𝑉𝑡 + 𝑉2 2𝑔𝑓 = 125𝑚 so L > SD. From the center of inner edge, 𝑑 = 𝑤 + 𝑤𝑒 4 = 1.97𝑚 ∝ 2 = SD 2 R − d ∗ 180 π = 22.66 𝑀 = 𝑅 − 𝑑 − 𝑅 − 𝑑 𝑐𝑜𝑠 ∝ 2 = 12.19𝑚 25 Prepared by: Bhavya Jaiswal
  • 26. Click to edit Master title style 26 Vertical curve • Vertical curves are used in highway and street vertical alignment to provide a gradual change between two adjacent grade lines. • There are two types of vertical curve in the highway which are as below: 1. Summit Curve 2. Valley Curve 26 Prepared by: Bhavya Jaiswal
  • 27. Click to edit Master title style 27 1. Summit Curve • It is a convex upward side and concave downward side. • The best shape of the summit curve is square parabola but the ideal shape of the curve is circular. • Square parabola gives the good riding qualities and uniform rate of change in grade. • Length of summit curve depends on sight distances. • There is no problem of discomfort in summit curve because gravity forces act downward and centrifugal force acts upward. 27 Prepared by: Bhavya Jaiswal
  • 28. Click to edit Master title style 28 Length of the Summit Curve 𝐿 = 𝑁𝑆2 2𝐻 + 2ℎ 2 H = height of driver from pavement surface H = height of object from pavement surface H = 1.2m and h = 0.15m for SSD H = 1.2m and h = 1.2m for OSD  Case-1, L > Sight Distance 𝐿 = 𝑁𝑆2 4.4 for SSD 𝐿 = 𝑁𝑆2 9.6 for OSD  Case-2, L < Sight Distance 𝐿 = 25 − 4.4 𝑁 for SSD 𝐿 = 25 − 9.6 𝑁 for OSD 28 Prepared by: Bhavya Jaiswal
  • 29. Click to edit Master title style 29 Numerical of the Summit Curve Q. Find the length of the vertical curve when an ascending gradient of 1 in 50 meets a descending gradient of 1 in 80 and the SSD is 180m. Solution: 𝑁 = 𝑛1 + 𝑛2 𝑁 = 1 50 + 1 80 𝑁 = 0.0325 Here, SSD = 180m 𝐿 = 𝑁𝑆2 4.4 = 239.3~240𝑚 29 Prepared by: Bhavya Jaiswal
  • 30. Click to edit Master title style 30 2. Valley Curve • Valley curve is concave upward and convex downward. • Valley curve is generally mid of two transition curve of equal length without having circular curve in between. • Cubic parabola is the best shape for the valley curves to gradually introduce the centrifugal force. • in case of valley curve, centrifugal force and gravity force both are acting downward that makes valley curves uncomfortable. 30 Prepared by: Bhavya Jaiswal
  • 31. Click to edit Master title style 31 2. Valley Curve The design of the valley curve is done as per the following approaches: Case-1: Based on comfort, 𝐿𝑉 = 2√ 𝑁𝑉3 𝐶 Where, V = m/sec C = 0.6m/𝑆2 Case-2: Based on Headlight sight Distance If L > HSD, 𝐿𝑉 = 𝑁𝑆2 1.5+0.035𝑆 If L < HSD, 𝐿𝑉 = 2𝑆 − 1.5+0.035𝑆 𝑁 Where, S = sight distance Sight distance is not a problem for valley curve because in night time other vehicle with headlight can be seen from a considerable distance. Length of valley curve is taken as the maximum among both 31 Prepared by: Bhavya Jaiswal
  • 32. Click to edit Master title style 32 Numerical on Valley Curve Q. A vertical curve is designed when a descending gradient of 1 in 25 meets with ascending gradient of 1 in 30. Design the length of the Valley curve if the speed is 80kmph. Solution: 𝑁 = 𝑛1 + 𝑛2 𝑁 = −( 1 25 + 1 30 ) 𝑁 = −0.0733 Approach-1: 𝐿𝑉 = 2 𝑁𝑉3 𝐶 = 73.21𝑚 Approach-2: 𝐿𝑉 = 𝑁𝑆2 1.5 + 0.035𝑆 = 198.18𝑚 𝑆 = 𝑉𝑡 + 𝑉2 2𝑔𝑓 = 126.65𝑚 Length of valley curve is taken as the maximum among both so it will be 198.18m 32 Prepared by: Bhavya Jaiswal