SlideShare a Scribd company logo
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 03 Issue: 02 | Feb-2016 www.irjet.net p-ISSN: 2395-0072
© 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 418
Generator Maintenance Scheduling Of Power System Using Hybrid
Technique
Suraj Kumhar1, Mantosh Kumar2
1M.Tech Scholar, Mewar University, Chittorgarh, Rajasthan, India
2Assistant Professor, Mewar University, Chittorgarh, Rajasthan, India
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - This paper presents generator maintenance
scheduling of a power system based on minimization of the
objective function considering the economical and reliable
operation of a power system while satisfying the network
constraints along with crew/manpower, generation limits,
precedence constraints, demandedload, maintenancewindow,
loss of load probability and reliability constraints.
Optimization was carried out on a practical thermal power
plant consisting of 19 generating units, over a 25 weeks
planning horizon.
Key Words: Maintenance Schedule;ArtificialIntelligence;
Fuzzy Systems; Genetic Algorithm; Evolution Strategy;
Particle Swarm Optimization; Hybrid IntelligentSystems.
1. INTRODUCTION
The scenario of operation and planning in power system
such as economic dispatch, unit commitment, load dispatch,
generation co-ordination are highly influencedbygenerator
maintenance scheduling. The maintenance schedule is a
preventive outage schedule for generating units within a
particular time horizon for decreasing operation cost and
increasing reliability. Maintenance scheduling turns into a
complex problem whenthepowersystemincludesa number
of generating units with different specifications, and when
several constraints have to be taken into consideration to
achieve a practical and feasible solution.
Generator maintenance scheduling is done to minimise
total operation cost satisfying all constraints of units and
power system over time horizons of different durations.
Short-term maintenance scheduling for one hour to one day
ahead is important for day-to-day operations, unit
commitment, and operation planning of power generation
facilities. Medium-term scheduling for a one day up toa year
ahead is essential for resource management. Long-term
scheduling of a year or two years ahead is important for
future planning.
The complexity and larger size of electric system
generation with the more reliability concern and low
operation cost have being causing a great interest in
automatic scheduling techniques for maintenance of
generators and power system, capable of giving feasible or
optimal scheduling.
The reliability of the power system assures that the
demand is met even though an outage occurred in the
system. Generally, the utility provides a spinning reserve, by
supplying more power than demanded. This improves the
system reliability with increased operating cost. A well-
planned schedule for maintenance and repair work should
be prepared for each unit in the system, according to the
period of maintenance activities, which are based on the
operating hours and condition of the engines.
The scheduling starts with all units available for
production; then initial schedulehastobegeneratedinsome
suitable way; then modify this initial schedule subsequently
if the method allows for more than one iteration. Efficient
and practical maintenance schedule increases system
reliability, reduces operation and maintenance costs, and
extends the lifetimes of the generators. Moreover, an easily
revisable maintenance schedule is required to adapt to
increasing load demand and number of generating units ina
larger-scale power system.
Maintenance scheduling is an optimization problem to
obtain the best schedule while meeting a variety of equality,
inequality constraints and thousands of decision variables
which are determined and obeyed simultaneously. The
objective functions in maintenance schedulingare reliability
and cost. The economic objective function includes the
maintenance cost and operation cost [1]. The reliability
objective function can be eitherdeterministic, wheretheaim
is to maximize the system’s net reserve (thesysteminstalled
capacity minus the maximum load and the maintenance
capacity during the period under examination), or random,
where goal is to minimize the risk level.
Several hard and soft constraints should be taken into
account to reflect the actual operating conditions of the
power system in order to make the maintenance plan
feasible. Listed below are some constraints for
maintenance scheduling:
• Crew constraint
• Availability of maintenance resources
• Maintenance period during which each unit should
be maintained
• Load demand
• Total Generation
• Condition of the engine
• Spinning reserve requirement
• Loss of Load Probability
• Transmission network constraints
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 03 Issue: 02 | Feb-2016 www.irjet.net p-ISSN: 2395-0072
© 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 419
The approach needs a trade-off between the quality of the
solution and number of iterations. The methods may not
converge if the stop criterion is inadequately chosen.
2. APPROACHES FOR MAINTENANCE SCHEDULING
PROBLEM
The maintenance-scheduling problem has been solved
using a number of techniques and methodologies. Integer
programming method is the most frequently used
mathematical method for maintenance scheduling.Amixed-
integer programming technique was used for obtaining
optimum schedules in [1] for a planning horizon of one
month. The existing methods indicate that the uncertainties
in the problem, computational time, generating system size,
and long planning horizons are the crucial issues in
developing a feasible, practical maintenance-scheduling
plan. However, the approach could not be applied to large-
scale problems due to excessive processingtimeandstorage
requirements. To reduce the storage and computation time,
successive approximation dynamic programming was
proposed in [2]. Artificial neural networkswereemployedin
[3] to handle the inequality constraints in the maintenance-
scheduling problem. The approach was used for a system
containing 15 generating units and one year planning
horizon. Recently, techniques such as Simulated Annealing
(SA) and Genetic Algorithm (GA) have been proposed for
maintenance scheduling of large systems. Reference [4]
considers a system containing 21 units and one year
planning horizon.
The main motivation of using evolutionary techniques
lies in the strong adaptability and flexibility for solving
difficult multi-objective problem with many constraints. In
this research, actual data from a thermal power system is
used for developing practical maintenance plans.
One of the options available to the utilities in order to
maintain a high level of reliability and economyofthepower
system is economic dispatch (ED). ED allocates the total
power demand among theonlinegeneratingunitsinorder to
minimize the cost of generation while satisfying important
system constraints. Some factors that influence ED of the
system are operating efficiency of generating units, fuel and
operating costs, and transmission losses. The ED problems
are in general non-convex optimizationproblemswithmany
local minima. Numerous classical techniques such as
LaGrange based methods, linear programming (LP), non-
linear programming (NLP)andquadratic programming(QP)
methods have been reported in the literature.
In order to obtain approximate solution of a complex GMS,
new concepts have emerged in recent years [7]-[10]. They
include applications of probabilistic approach[5],simulated
annealing [6], decomposition technique [7] and genetic
algorithm (GA) [8]. The application of GA to GMS presented
in [10] have been compared with, and confirmed to be
superior to other conventional algorithms such as heuristic
approaches and branch-and-bound (B&B) in the quality of
solutions.
GMS using DE for the minimization of reliability cost
function of levelling reserve generationoveran entireperiod
of 52 weeks maintenance window for the Nigerian power
system have been reported in [9],.
2.1 Particle Swarm Optimization (PSO)
Particle Swarm Optimization (PSO) [7] has been
successfully applied in many areas: function optimization,
artificial neural network training, fuzzy system control, and
other areas where GA can be applied. This algorithm was
discovered through simulation of bird flocking and fish
schooling (social behavior).
As sociobiologist E. O. Wilson has written, in referenceto
fish schooling, "In theory at least, individual members of the
school can profit from the discoveries and previous
experience of all other members of the school during the
search for food. This advantage can become decisive,
outweighing the disadvantages of competition for food
items, whenever the resource is unpredictablydistributedin
patches". This statement suggests that social sharing of
information offers an evolutionary advantage: this
hypothesis was fundamental to the development of particle
swarm optimization. Similar toGeneticAlgorithms(GA)[10-
12], PSO is a population based optimization tool. Thesystem
is initialized with a population of random solutions and
searches for optima by updating generations. However,
unlike GA, PSO has no evolution operators such as crossover
and mutation. In PSO,thepotential solutions,calledparticles,
are "flown" through the problem space by following the
current optimum particles.
2.2 Simulated Annealing (SA)
Metaheuristic techniques include Tabu Search, Neural
Networks, Simulated Annealing, Particle Swarm
Optimization and Ant Colony Optimization. Simulated
Annealing and Genetic Algorithms are used to address
combinatorial problems due to the presence of discrete
variables.
Simulated Annealing was developed by Kirkpatrick et al.
[13], followed by Aarts and Korst [14] based on the
Metropolis algorithm dated from 1953. It is a search
procedure in which it is included the possibility of accepting
a solution that is worse than the current one. The simulation
starts at an initial solution, x1, evaluates it using an
Evaluation Function, f(x1), and samples a newsolutioninthe
neighborhood of x1. If this new solution improves f(x1), then
it is accepted. If it is worse than the current one, itcanstill be
accepted depending on a so-called probability of accepting
worse solutions.
2.3 Tabu Search (TS)
In [15-16] the GMS problem is solved using Tabu Search. In
[15] it is used a multi-stage approach to decompose the
problem in several sub-problems. The partial results are
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 03 Issue: 02 | Feb-2016 www.irjet.net p-ISSN: 2395-0072
© 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 420
then combined to pro-ducetheglobal maintenanceschedule.
In [16] the formulation uses the generation cost and the
reserve margin as objectives and the constraints are related
with the availability of crews, predefined sequence of
maintenance actions for several units and continuity of the
maintenance period once a maintenance action starts. The
plans provided by the Tabu Search algorithm for two
generation systems (one with 4 units and another with 22
units) were compared with the results obtained with an
implicit enumeration approach. The results obtained with
Tabu Search were very promising given the more reduced
computation time and their good quality.
The performance of several meta-heuristic approaches,
namely Tabu Search, Simulated Annealing, Genetic
Algorithms, an hybrid Simulated Annealing/Genetic
Algorithm approach and an hybrid Tabu Search/Simulated
Annealing algorithm. The authors report that the combined
use of Simulated Annealing/Genetic Algorithm and of Tabu
Search/Simulated Annealing produces better results than
the isolated use of a single metaheuristic, although the
computational time is sometimes longer.
2.4 Evolution Strategy (ES)
Evolution Strategies [17-21] are part of the field of
evolutionary algorithms. ES has always beencompared with
GA and a concluding statement on whichisbetteriscertainly
not possible. The subtle difference between ES and GA is in
the parameter representation. ES works with real values of
the variables (phenotype) whereas GA works with binary
strings which are subsequently mapped to object variables.
Since ES works completely on a phenotypic level, hence one
can represent moreknowledgeabouttheapplicationdomain
into the coding of the problem. One important difference
between ES and GA is that the main search operator in ES
was based on the mutation operator. But more recently, a
crossover operator was introduced to facilitate the search
process. The traditional ES approach can be represented as
follows:
1. For each parent, generate offspring’s through
mutation process.
2. Select the best individuals from the mutated
and current population asthenextgeneration.
2.5 Genetic Algorithm (GA)
Genetic algorithms (GA) were first described by John
Holland, who presented them as an abstraction of biological
evolution and gave a theoretical mathematical framework
for adaptation. Holland's GA are a method of moving from
one population of "chromosomes" (bit strings representing
candidate solutions to a problem), to a new population of
solutions using selection, together with a set of genetic
operators of cross-over, mutation and inversion. Each
chromosome consists of "genes" (e.g. bits) with each gene
representing an instance of a particular "allele"(e.g.a 0or1).
Genetic algorithms are based on models of genetic change in
a population of individuals.
These models consist of three basic elements;
• A 'fitness' measure which governs an individual's abilityto
influence future generations,
• A selection and reproduction process which produces
offspring for the next generation,
• Genetic operators which determine the geneticmake-up of
the offspring
The distinguishing feature of a GA with respect to
other function optimisation techniques is that the search
towards an optimum solution proceeds not by incremental
changes to a single structure (candidate solution) but by
maintaining a population of solutions from which new
structures are created using the genetic operators.
Fig -1: The overall strategy for maintenance scheduling of
generating unit
3. PROBLEM DISCRIPTION
The objective function consideredina GMSproblemconsists
of the sum of the maintenance costs of the off-line units and
the operational costs of the on-line generators. The
maintenance costs of a generating unit would not change
during the study period and can be regarded as constant in
the GMS problem. The values will not influence the search
for the optimisation operational costs.
Table -1: GENERATOR RATINGS
Unit
Rating
(MW)
a B C
1 6.1 0.0038 5.44 52.6
2 6.1 0.0038 5.44 52.6
3 6.1 0.0038 5.44 52.6
4 6.1 0.0038 5.44 52.6
5 6.1 0.0038 5.44 52.6
6 6.1 0.0038 5.44 52.6
7 6.1 0.0038 5.44 52.6
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 03 Issue: 02 | Feb-2016 www.irjet.net p-ISSN: 2395-0072
© 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 421
8 6.1 0.0046 6.34 53.7
9 6.1 0.0050 5.34 51.5
10 6.4 0.0050 5.34 51.5
11 6.4 0.0057 5.34 52.5
12 6.4 0.0057 5.34 52.5
13 8.0 0.0346 8.06 76.5
14 8.0 0.0346 8.06 76.5
15 2.1 0.0076 6.90 55.4
16 2.1 0.0076 7.10 55.4
17 2.1 0.0076 6.95 55.4
18 2.1 0.0076 7.30 55.4
19 6.1 0.0079 7.10 59.3
The following table shows the data used in the evaluation of
maintenance cost.
Table-2:DOWNTIMEANDMAINTENANCECOSTPERWEEK
OF EACH GENERATOR
Unit
Downtime
(D)
V
($/week)
Unit
Downtime
(D)
V
($/week)
1 1 750 11 3 850
2 4 750 12 3 850
3 1 750 13 4 1500
4 2 750 14 3 1500
5 3 750 15 1 600
6 2 750 16 1 600
7 1 750 17 1 600
8 1 750 18 1 600
9 2 750 19 4 900
10 3 850
The objective function for GMS model
   2
1 1 1
min
Z Y Y
zy y y yz y yz y y
z y y
U A B P C P FV P
  
     
where FVy(Py) is expressed as a linear equation of
production cost.
 
1
0
y y y y
y z
F V P V D
D


 

if unit y start maintenance at week z
For each time period z, z =1,2, 3,……,Z.
The objective function of the problem is subjected to
constraints as given below:
a) Load Balance
1
Z
z y z y y
z
U P D


b) Generator Output Limit
min maxy zy yP P P 
c) Spining Reserve
max
1
(1 %)
Y
zy y y z
y
U P D r

 
d) Maintenance Window
1, ,
0,
0,1,
y y
zy y y y
y y
t ey t l d
U s t s d
e t l
   

   

 
e) Maintenance Area
1
(1 )
Y
zy
y
U 

 
f) Crew Constraint
1 1
(1 )
Z Y
zy
z y
U Cr
 
 
4. PROBLEM SOLUTION
The schedule for GMS is obtained by using mixed genetic
algorithm which is explained below in flowchart as:
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 03 Issue: 02 | Feb-2016 www.irjet.net p-ISSN: 2395-0072
© 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 422
Initialize
Population
Fitness
evaluation
Selection
for the reproduction
(selection)
Crossoverof the
selected
individual
Mutation of
the selected
individual
Fitness
evaluation of
the offspring
Selection for the
replacement
Stopping
criteria?Optimal
Schedule
YES
NO
Fig -2: The flowchart of GMS using GA.
5. RESULTS
Test system consider of 19 generating units for time span of
25 weeks with an objective to minimize the economic cost
function over planning horizon subjected to various
constraints is optimized using genetic algorithm. The result
of optimization compared with other metaheuristic
techniques is shown below in TABLE IV. The total
maintenance cost is obtained using fixed maintenance cost
data. The operational cost Plot obtained is shown below in
figure 3 and the schedule obtained using GA is tabulated
below.
Fig -3:. Operational Cost Plot
Table-3: SCHEDULE OBTAINED USING GENETIC
ALGORITHM
Maintenance
Period
Generating unit’s index of scheduled maintenance
(weeks) 1 2 3 4 5 6 7 8 9
1
0
11 12 13 14 15 16 17 18 19
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 1 1 0
4 1 1 1 0 1 1 1 1 1 1 1 1 1 0 1 1 1 1 1
5 1 0 1 1 1 1 1 1 1 1 0 1 1 1 1 1 1 1 1
6
1 1 1 1 0 1 1 1 1 1 1 1 0 1 1 1 1 1 1
7 1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1
8 1 0 1 1 0 1 1 0 1 1 1 1 1 1 1 1 1 1 1
9 0 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 1 1
10 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0
11 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 0 1
12 1 1 1 1 1 1 0 1 1 1 1 0 1 1 1 1 1 1 1
13 1 1 1 1 1 1 1 1 1 1 0 1 0 1 1 1 1 1 1
14 1 1 0 1 1 1 1 1 1 1 0 1 1 1 1 1 1 1 1
15 1 0 1 1 0 0 1 1 0 0 1 1 1 1 1 1 1 1 0
16 1 1 1 1 1 1 1 1 1 0 1 1 1 1 1 1 1 1 1
17 1 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 1 1
18 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 1 1 1 1
19 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 1 1 1
20 1 1 1 1 1 1 1 1 0 1 1 0 1 1 1 1 1 1 0
21 1 1 1 1 1 0 1 1 1 1 1 1 1 1 1 1 0 1 1
22 1 1 1 1 1 1 1 1 1 0 1 1 1 1 1 1 1 1 1
23 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
24 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
25 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Table-4: RESULTS
S.No. Techniques Optimised Cost
1. Heuristic 73932889.326
2. GA 73928747.045
3. PSO 76930465.182
4. PSO with multiple changes 76930383.249
5. ES 7632895.839
6. ES with multiple mutation 76932699.485
7. ES with multiple mutation and crossover 76932745.216
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 03 Issue: 02 | Feb-2016 www.irjet.net p-ISSN: 2395-0072
© 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 423
6. CONCLUSIONS
The generator maintenance scheduling problemdonefor 19
units test system subjected to various numberofconstraints
using genetic algorithm as optimisation tool to obtain best
schedule to minimize the economic cost function is carried
out. Economic dispatch has been used to find an optimal
combination of power generation that minimizes the total
generation cost whilesatisfyingconstraints.TheGAgives the
most promising results.
The unplanned maintenance allowances and deferred
maintenance can be consider for further work on this area
with the use of hybrid heuristic techniques. One can also
consider a frequency-basedmaintenanceoutageformulation
or multi-objective modeling approach.
REFERENCES
[1] E. L. da Silva, M. Th. Schilling and M. C. Rafael,
“Generation maintenance scheduling considering
transmission constraints”, IEEE Transactions on Power
System, Vol: 15, NO. 2, May 2000.
[2] H. H. Zura, V. H. Qiutaha, “Generation maintenance
scheduling via successive approximation dynamic
programming”, IEEE Trans on PAS vol. PAS-94, 1975.
[3] H. Sasaki, H. Choshi, Y. Takiuchi, J. Kubokawa, “A
solution of maintenance scheduling covering several
consecutive years by artificial neural networks”,
Hiroshima University, IEEE 1993.
[4] K. P. Dahal, C. J. Aldridge, J. R. Mc Donnald, “Generator
maintenance scheduling using a genetic algorithm with
a fuzzy evaluation function”, Eselvier, Fuzzy Sets and
Systems 102: 21-29,1999.
[5] R. Billinton and A. Abdulwhab, “Short-term generating
unit maintenance in a deregulatedpowersystemusinga
probabilistic approach”, IEEE Proceedings -Generation,
TransmissionandDistribution150,(4),pp.463-468,July
2003.
[6] T. Satoh and K. Nara, “Maintenance scheduling by using
simulated annealing method”, IEEE Transactions on
Power Systems, 6, pp. 850-857, 1991.
[7] J. Yellen, T. M. Al-khamis, S. Vermuri and L. Lemonidis,
“A decomposition approach to unit maintenance
scheduling”, IEEE Transactions on Power Systems 7,pp.
726-733, 1992.
[8] H. T. Firma and L. F. L. Legey, “Generation expansion: an
iterative genetic algorithm approach”, IEEE
Transactions on Power Systems, 17, (3), pp. 901-906,
August 2002.
[9] Y. Yare and G. K. Venayagamoorthy, “A differential
evolution approach to optimal generator maintenance
scheduling of the Nigerian power system”, IEEE Power
and Energy Society General Meeting – Conversion and
Delivery of Electrical Energy in the 21st Century,pp.1-8,
20-24 July 2008.
[10]R. C. Eberhart, Y. Shi, “Comparison between genetic
algorithms and particle swarm optimization”,
Evolutionary Programming VII, 1998.
[11]M. Lovbjerg, T. K. Rasmussen, T. Krink, “Hybrid particle
swarm optimiser with breeding and subpopulations”,
Dept. of Computer Science, University of Aarhus, 2001.
[12]T. LogenthiranandD.Srinivasan,“Shorttermgeneration
scheduling of a microgrid”, IEEE TENCON, pp.1-6, 2009.
[13]S. Kirkpatrick, C.D. Gelatt, M.P. Vecchi, “Optimization by
simulated annealing”, Science 220, 671–680, 1983.
[14]E. Aarts, J. Korst, Simulated Annealing and Boltzman
Machines, “Electric Power Systems Research”, New
Scheduling, John Wiley & Sons,67, 67–72, 2003.
[15]E.K. Burke, A.J. Smith, “A multi-stage approach for the
thermal generator maintenanceschedulingproblem”,in
proceedings of the 1999 Congress on Evolutionary
Computation, CEC’99, vol. 2, Washington DC, USA, July,
1999.
[16]I. El-Amin, S. Duffuaa, M. Abbas, “A Tabu Search
algorithm for maintenance scheduling of generating
units”, Electric PowerSystemsResearch54,91–99.York,
2000.
[17]I. Rechenberg, Frommann-Holzboog “Evolutions
strategies”, 1994.
[18]L. Costa, P. Oliveira, “An evolution strategy for
multiobjective optimization”, Dept de Producao e
Sistemas, University do Minho, 2002.
[19]N. Fonseca, V. Miranda, “EPSO - best-of-two-worlds
meta-heuristic applied to power system problems”,
Evolutionary Computation, 2002. CEC '02. Proceedings
of the 2002 Congress on , Volume: 2 , Page(s): 1080 -
1085, 2002.
[20]P. J. Abrao, A. P. A. da Silva, “Applicationsofevolutionary
computation in electric power systems” Evolutionary
Computation, 2002. CEC '02. Proceedings of the 2002
Congress on , Volume: 2 , Page(s): 1057 -1062, 2002.
[21]Y. Yare, and G. K. Venayagamoorthy, “Comparison of DE
and PSO for generator maintenance scheduling”, IEEE
Swarm Intelligence Symposium St. Louis MO USA,
September 21-23, Page(s): 1-8, 2008.
[22]H. C. Sun, Y. C. Huang, and K. Y. Huang, “A new algorithm
for power system scheduling problems”, Eighth
International Conference on Intelligent Systems Design
and Applications, Volume: 1, November, Page(s):36-40,
2008.
[23]R. Eshraghnia, M. H. Modir Shanechi, and H. R.
Mashhadil, “A new approach for maintenance
scheduling of generating units in power market”, 9th
International Conference on Probabilistic Methods
Applied to Power Systems KTH, Stockholm, Sweden,
June 11-15, Page(s): 1-7, 2006.

More Related Content

What's hot

N020698101
N020698101N020698101
Power System Reliability Assessment in a Complex Restructured Power System
Power System Reliability Assessment in a Complex Restructured Power SystemPower System Reliability Assessment in a Complex Restructured Power System
Power System Reliability Assessment in a Complex Restructured Power System
IJECEIAES
 
IRJET- Reducing electricity usage in Internet using transactional data
IRJET-  	  Reducing electricity usage in Internet using transactional dataIRJET-  	  Reducing electricity usage in Internet using transactional data
IRJET- Reducing electricity usage in Internet using transactional data
IRJET Journal
 
Blackout Prevention Plan – The Stability, Reliability and Security Enhancemen...
Blackout Prevention Plan – The Stability, Reliability and Security Enhancemen...Blackout Prevention Plan – The Stability, Reliability and Security Enhancemen...
Blackout Prevention Plan – The Stability, Reliability and Security Enhancemen...
Power System Operation
 
Energy efficient task scheduling algorithms for cloud data centers
Energy efficient task scheduling algorithms for cloud data centersEnergy efficient task scheduling algorithms for cloud data centers
Energy efficient task scheduling algorithms for cloud data centers
eSAT Publishing House
 
Energy efficient task scheduling algorithms for cloud data centers
Energy efficient task scheduling algorithms for cloud data centersEnergy efficient task scheduling algorithms for cloud data centers
Energy efficient task scheduling algorithms for cloud data centers
eSAT Journals
 
IRJET- The Next Generation Green Data Center:Multi-Facetapproach to Reduc...
IRJET-  	  The Next Generation Green Data Center:Multi-Facetapproach to Reduc...IRJET-  	  The Next Generation Green Data Center:Multi-Facetapproach to Reduc...
IRJET- The Next Generation Green Data Center:Multi-Facetapproach to Reduc...
IRJET Journal
 
Network reconfiguration to improve reliability indices and efficiency in dist...
Network reconfiguration to improve reliability indices and efficiency in dist...Network reconfiguration to improve reliability indices and efficiency in dist...
Network reconfiguration to improve reliability indices and efficiency in dist...
INFOGAIN PUBLICATION
 
Power System Restoration Methodologies & Implementation Strategies
Power System Restoration Methodologies & Implementation StrategiesPower System Restoration Methodologies & Implementation Strategies
Power System Restoration Methodologies & Implementation Strategies
Power System Operation
 
A Critical Review on Employed Techniques for Short Term Load Forecasting
A Critical Review on Employed Techniques for Short Term Load ForecastingA Critical Review on Employed Techniques for Short Term Load Forecasting
A Critical Review on Employed Techniques for Short Term Load Forecasting
IRJET Journal
 
Inglett & Stubbs Group Technical Capabilities - 5-1-15
Inglett & Stubbs Group Technical Capabilities - 5-1-15Inglett & Stubbs Group Technical Capabilities - 5-1-15
Inglett & Stubbs Group Technical Capabilities - 5-1-15
Brent Harrison, PMP
 
Optimal tuning of proportional integral controller for fixed-speed wind turb...
Optimal tuning of proportional integral controller for  fixed-speed wind turb...Optimal tuning of proportional integral controller for  fixed-speed wind turb...
Optimal tuning of proportional integral controller for fixed-speed wind turb...
IJECEIAES
 
Elwerfelli2008
Elwerfelli2008Elwerfelli2008
Elwerfelli2008
Gene Rubira
 
IRJET- An Energy-Saving Task Scheduling Strategy based on Vacation Queuing & ...
IRJET- An Energy-Saving Task Scheduling Strategy based on Vacation Queuing & ...IRJET- An Energy-Saving Task Scheduling Strategy based on Vacation Queuing & ...
IRJET- An Energy-Saving Task Scheduling Strategy based on Vacation Queuing & ...
IRJET Journal
 
Sampling-Based Model Predictive Control of PV-Integrated Energy Storage Syste...
Sampling-Based Model Predictive Control of PV-Integrated Energy Storage Syste...Sampling-Based Model Predictive Control of PV-Integrated Energy Storage Syste...
Sampling-Based Model Predictive Control of PV-Integrated Energy Storage Syste...
Power System Operation
 
A cost effective computational design of maximum power point tracking for pho...
A cost effective computational design of maximum power point tracking for pho...A cost effective computational design of maximum power point tracking for pho...
A cost effective computational design of maximum power point tracking for pho...
IJECEIAES
 
Advanced Automated Approach for Interconnected Power System Congestion Forecast
Advanced Automated Approach for Interconnected Power System Congestion ForecastAdvanced Automated Approach for Interconnected Power System Congestion Forecast
Advanced Automated Approach for Interconnected Power System Congestion Forecast
Power System Operation
 
Impact of Dispersed Generation on Optimization of Power Exports
Impact of Dispersed Generation on Optimization of Power ExportsImpact of Dispersed Generation on Optimization of Power Exports
Impact of Dispersed Generation on Optimization of Power Exports
IJERA Editor
 
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
Power System Operation
 

What's hot (19)

N020698101
N020698101N020698101
N020698101
 
Power System Reliability Assessment in a Complex Restructured Power System
Power System Reliability Assessment in a Complex Restructured Power SystemPower System Reliability Assessment in a Complex Restructured Power System
Power System Reliability Assessment in a Complex Restructured Power System
 
IRJET- Reducing electricity usage in Internet using transactional data
IRJET-  	  Reducing electricity usage in Internet using transactional dataIRJET-  	  Reducing electricity usage in Internet using transactional data
IRJET- Reducing electricity usage in Internet using transactional data
 
Blackout Prevention Plan – The Stability, Reliability and Security Enhancemen...
Blackout Prevention Plan – The Stability, Reliability and Security Enhancemen...Blackout Prevention Plan – The Stability, Reliability and Security Enhancemen...
Blackout Prevention Plan – The Stability, Reliability and Security Enhancemen...
 
Energy efficient task scheduling algorithms for cloud data centers
Energy efficient task scheduling algorithms for cloud data centersEnergy efficient task scheduling algorithms for cloud data centers
Energy efficient task scheduling algorithms for cloud data centers
 
Energy efficient task scheduling algorithms for cloud data centers
Energy efficient task scheduling algorithms for cloud data centersEnergy efficient task scheduling algorithms for cloud data centers
Energy efficient task scheduling algorithms for cloud data centers
 
IRJET- The Next Generation Green Data Center:Multi-Facetapproach to Reduc...
IRJET-  	  The Next Generation Green Data Center:Multi-Facetapproach to Reduc...IRJET-  	  The Next Generation Green Data Center:Multi-Facetapproach to Reduc...
IRJET- The Next Generation Green Data Center:Multi-Facetapproach to Reduc...
 
Network reconfiguration to improve reliability indices and efficiency in dist...
Network reconfiguration to improve reliability indices and efficiency in dist...Network reconfiguration to improve reliability indices and efficiency in dist...
Network reconfiguration to improve reliability indices and efficiency in dist...
 
Power System Restoration Methodologies & Implementation Strategies
Power System Restoration Methodologies & Implementation StrategiesPower System Restoration Methodologies & Implementation Strategies
Power System Restoration Methodologies & Implementation Strategies
 
A Critical Review on Employed Techniques for Short Term Load Forecasting
A Critical Review on Employed Techniques for Short Term Load ForecastingA Critical Review on Employed Techniques for Short Term Load Forecasting
A Critical Review on Employed Techniques for Short Term Load Forecasting
 
Inglett & Stubbs Group Technical Capabilities - 5-1-15
Inglett & Stubbs Group Technical Capabilities - 5-1-15Inglett & Stubbs Group Technical Capabilities - 5-1-15
Inglett & Stubbs Group Technical Capabilities - 5-1-15
 
Optimal tuning of proportional integral controller for fixed-speed wind turb...
Optimal tuning of proportional integral controller for  fixed-speed wind turb...Optimal tuning of proportional integral controller for  fixed-speed wind turb...
Optimal tuning of proportional integral controller for fixed-speed wind turb...
 
Elwerfelli2008
Elwerfelli2008Elwerfelli2008
Elwerfelli2008
 
IRJET- An Energy-Saving Task Scheduling Strategy based on Vacation Queuing & ...
IRJET- An Energy-Saving Task Scheduling Strategy based on Vacation Queuing & ...IRJET- An Energy-Saving Task Scheduling Strategy based on Vacation Queuing & ...
IRJET- An Energy-Saving Task Scheduling Strategy based on Vacation Queuing & ...
 
Sampling-Based Model Predictive Control of PV-Integrated Energy Storage Syste...
Sampling-Based Model Predictive Control of PV-Integrated Energy Storage Syste...Sampling-Based Model Predictive Control of PV-Integrated Energy Storage Syste...
Sampling-Based Model Predictive Control of PV-Integrated Energy Storage Syste...
 
A cost effective computational design of maximum power point tracking for pho...
A cost effective computational design of maximum power point tracking for pho...A cost effective computational design of maximum power point tracking for pho...
A cost effective computational design of maximum power point tracking for pho...
 
Advanced Automated Approach for Interconnected Power System Congestion Forecast
Advanced Automated Approach for Interconnected Power System Congestion ForecastAdvanced Automated Approach for Interconnected Power System Congestion Forecast
Advanced Automated Approach for Interconnected Power System Congestion Forecast
 
Impact of Dispersed Generation on Optimization of Power Exports
Impact of Dispersed Generation on Optimization of Power ExportsImpact of Dispersed Generation on Optimization of Power Exports
Impact of Dispersed Generation on Optimization of Power Exports
 
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
 

Similar to Generator Maintenance Scheduling Of Power System Using Hybrid Technique

Effective Utilization of CPU
Effective Utilization of CPUEffective Utilization of CPU
Effective Utilization of CPU
IRJET Journal
 
IRJET- Analysis of Micro Inversion to Improve Fault Tolerance in High Spe...
IRJET-  	  Analysis of Micro Inversion to Improve Fault Tolerance in High Spe...IRJET-  	  Analysis of Micro Inversion to Improve Fault Tolerance in High Spe...
IRJET- Analysis of Micro Inversion to Improve Fault Tolerance in High Spe...
IRJET Journal
 
IRJET- Fuzzy predictive control of Variable Speed Wind Turbines using Fuzzy T...
IRJET- Fuzzy predictive control of Variable Speed Wind Turbines using Fuzzy T...IRJET- Fuzzy predictive control of Variable Speed Wind Turbines using Fuzzy T...
IRJET- Fuzzy predictive control of Variable Speed Wind Turbines using Fuzzy T...
IRJET Journal
 
IRJET- Survey of Micro Grid Cost Reduction Techniques
IRJET-  	  Survey of Micro Grid Cost Reduction TechniquesIRJET-  	  Survey of Micro Grid Cost Reduction Techniques
IRJET- Survey of Micro Grid Cost Reduction Techniques
IRJET Journal
 
Forecasting Capacity Issues in Stateful Systems: A Proactive Approach
Forecasting Capacity Issues in Stateful Systems: A Proactive ApproachForecasting Capacity Issues in Stateful Systems: A Proactive Approach
Forecasting Capacity Issues in Stateful Systems: A Proactive Approach
IRJET Journal
 
Techno-economical Unit Commitment Using Harmony Search Optimization Approach
Techno-economical Unit Commitment Using Harmony Search Optimization ApproachTechno-economical Unit Commitment Using Harmony Search Optimization Approach
Techno-economical Unit Commitment Using Harmony Search Optimization Approach
IJAPEJOURNAL
 
IRJET- Generation Planning using WASP Software
IRJET- Generation Planning using WASP SoftwareIRJET- Generation Planning using WASP Software
IRJET- Generation Planning using WASP Software
IRJET Journal
 
Energy Management System in Microgrid with ANFIS Control Scheme using Heurist...
Energy Management System in Microgrid with ANFIS Control Scheme using Heurist...Energy Management System in Microgrid with ANFIS Control Scheme using Heurist...
Energy Management System in Microgrid with ANFIS Control Scheme using Heurist...
IRJET Journal
 
Security Constraint Unit Commitment Considering Line and Unit Contingencies-p...
Security Constraint Unit Commitment Considering Line and Unit Contingencies-p...Security Constraint Unit Commitment Considering Line and Unit Contingencies-p...
Security Constraint Unit Commitment Considering Line and Unit Contingencies-p...
IJAPEJOURNAL
 
Nuclear Power Plant Risk Informed Life Management ver 9
Nuclear Power Plant Risk Informed Life Management ver 9Nuclear Power Plant Risk Informed Life Management ver 9
Nuclear Power Plant Risk Informed Life Management ver 9
Michael Lemiski, P Eng., PMP
 
IRJET- Fitness Function as Trust Value using to Efficient Multipath Routi...
IRJET-  	  Fitness Function as Trust Value using to Efficient Multipath Routi...IRJET-  	  Fitness Function as Trust Value using to Efficient Multipath Routi...
IRJET- Fitness Function as Trust Value using to Efficient Multipath Routi...
IRJET Journal
 
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
Power System Operation
 
Optimal protective relaying scheme of distributed generation connected distri...
Optimal protective relaying scheme of distributed generation connected distri...Optimal protective relaying scheme of distributed generation connected distri...
Optimal protective relaying scheme of distributed generation connected distri...
IJECEIAES
 
IRJET-Effect of Network Reconfiguration on Power Quality of Distribution System
IRJET-Effect of Network Reconfiguration on Power Quality of Distribution SystemIRJET-Effect of Network Reconfiguration on Power Quality of Distribution System
IRJET-Effect of Network Reconfiguration on Power Quality of Distribution System
IRJET Journal
 
IRJET- Comprehensive Analysis on Optimal Allocation and Sizing of Distributed...
IRJET- Comprehensive Analysis on Optimal Allocation and Sizing of Distributed...IRJET- Comprehensive Analysis on Optimal Allocation and Sizing of Distributed...
IRJET- Comprehensive Analysis on Optimal Allocation and Sizing of Distributed...
IRJET Journal
 
Report Information from ProQuestJuly 19 2019 1515 .docx
Report Information from ProQuestJuly 19 2019 1515 .docxReport Information from ProQuestJuly 19 2019 1515 .docx
Report Information from ProQuestJuly 19 2019 1515 .docx
audeleypearl
 
Predicting Machine Learning Pipeline Runtimes in the Context of Automated Mac...
Predicting Machine Learning Pipeline Runtimes in the Context of Automated Mac...Predicting Machine Learning Pipeline Runtimes in the Context of Automated Mac...
Predicting Machine Learning Pipeline Runtimes in the Context of Automated Mac...
IRJET Journal
 
IRJET- An Efficient Dynamic Deputy Cluster Head Selection Method for Wireless...
IRJET- An Efficient Dynamic Deputy Cluster Head Selection Method for Wireless...IRJET- An Efficient Dynamic Deputy Cluster Head Selection Method for Wireless...
IRJET- An Efficient Dynamic Deputy Cluster Head Selection Method for Wireless...
IRJET Journal
 
40220130405017
4022013040501740220130405017
40220130405017
IAEME Publication
 
Predicting the Maintenance of Aircraft Engines using LSTM
Predicting the Maintenance of Aircraft Engines using LSTMPredicting the Maintenance of Aircraft Engines using LSTM
Predicting the Maintenance of Aircraft Engines using LSTM
ijtsrd
 

Similar to Generator Maintenance Scheduling Of Power System Using Hybrid Technique (20)

Effective Utilization of CPU
Effective Utilization of CPUEffective Utilization of CPU
Effective Utilization of CPU
 
IRJET- Analysis of Micro Inversion to Improve Fault Tolerance in High Spe...
IRJET-  	  Analysis of Micro Inversion to Improve Fault Tolerance in High Spe...IRJET-  	  Analysis of Micro Inversion to Improve Fault Tolerance in High Spe...
IRJET- Analysis of Micro Inversion to Improve Fault Tolerance in High Spe...
 
IRJET- Fuzzy predictive control of Variable Speed Wind Turbines using Fuzzy T...
IRJET- Fuzzy predictive control of Variable Speed Wind Turbines using Fuzzy T...IRJET- Fuzzy predictive control of Variable Speed Wind Turbines using Fuzzy T...
IRJET- Fuzzy predictive control of Variable Speed Wind Turbines using Fuzzy T...
 
IRJET- Survey of Micro Grid Cost Reduction Techniques
IRJET-  	  Survey of Micro Grid Cost Reduction TechniquesIRJET-  	  Survey of Micro Grid Cost Reduction Techniques
IRJET- Survey of Micro Grid Cost Reduction Techniques
 
Forecasting Capacity Issues in Stateful Systems: A Proactive Approach
Forecasting Capacity Issues in Stateful Systems: A Proactive ApproachForecasting Capacity Issues in Stateful Systems: A Proactive Approach
Forecasting Capacity Issues in Stateful Systems: A Proactive Approach
 
Techno-economical Unit Commitment Using Harmony Search Optimization Approach
Techno-economical Unit Commitment Using Harmony Search Optimization ApproachTechno-economical Unit Commitment Using Harmony Search Optimization Approach
Techno-economical Unit Commitment Using Harmony Search Optimization Approach
 
IRJET- Generation Planning using WASP Software
IRJET- Generation Planning using WASP SoftwareIRJET- Generation Planning using WASP Software
IRJET- Generation Planning using WASP Software
 
Energy Management System in Microgrid with ANFIS Control Scheme using Heurist...
Energy Management System in Microgrid with ANFIS Control Scheme using Heurist...Energy Management System in Microgrid with ANFIS Control Scheme using Heurist...
Energy Management System in Microgrid with ANFIS Control Scheme using Heurist...
 
Security Constraint Unit Commitment Considering Line and Unit Contingencies-p...
Security Constraint Unit Commitment Considering Line and Unit Contingencies-p...Security Constraint Unit Commitment Considering Line and Unit Contingencies-p...
Security Constraint Unit Commitment Considering Line and Unit Contingencies-p...
 
Nuclear Power Plant Risk Informed Life Management ver 9
Nuclear Power Plant Risk Informed Life Management ver 9Nuclear Power Plant Risk Informed Life Management ver 9
Nuclear Power Plant Risk Informed Life Management ver 9
 
IRJET- Fitness Function as Trust Value using to Efficient Multipath Routi...
IRJET-  	  Fitness Function as Trust Value using to Efficient Multipath Routi...IRJET-  	  Fitness Function as Trust Value using to Efficient Multipath Routi...
IRJET- Fitness Function as Trust Value using to Efficient Multipath Routi...
 
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
Energy Storage Systems as a Reliable Alternative to Diesel Generators for Cri...
 
Optimal protective relaying scheme of distributed generation connected distri...
Optimal protective relaying scheme of distributed generation connected distri...Optimal protective relaying scheme of distributed generation connected distri...
Optimal protective relaying scheme of distributed generation connected distri...
 
IRJET-Effect of Network Reconfiguration on Power Quality of Distribution System
IRJET-Effect of Network Reconfiguration on Power Quality of Distribution SystemIRJET-Effect of Network Reconfiguration on Power Quality of Distribution System
IRJET-Effect of Network Reconfiguration on Power Quality of Distribution System
 
IRJET- Comprehensive Analysis on Optimal Allocation and Sizing of Distributed...
IRJET- Comprehensive Analysis on Optimal Allocation and Sizing of Distributed...IRJET- Comprehensive Analysis on Optimal Allocation and Sizing of Distributed...
IRJET- Comprehensive Analysis on Optimal Allocation and Sizing of Distributed...
 
Report Information from ProQuestJuly 19 2019 1515 .docx
Report Information from ProQuestJuly 19 2019 1515 .docxReport Information from ProQuestJuly 19 2019 1515 .docx
Report Information from ProQuestJuly 19 2019 1515 .docx
 
Predicting Machine Learning Pipeline Runtimes in the Context of Automated Mac...
Predicting Machine Learning Pipeline Runtimes in the Context of Automated Mac...Predicting Machine Learning Pipeline Runtimes in the Context of Automated Mac...
Predicting Machine Learning Pipeline Runtimes in the Context of Automated Mac...
 
IRJET- An Efficient Dynamic Deputy Cluster Head Selection Method for Wireless...
IRJET- An Efficient Dynamic Deputy Cluster Head Selection Method for Wireless...IRJET- An Efficient Dynamic Deputy Cluster Head Selection Method for Wireless...
IRJET- An Efficient Dynamic Deputy Cluster Head Selection Method for Wireless...
 
40220130405017
4022013040501740220130405017
40220130405017
 
Predicting the Maintenance of Aircraft Engines using LSTM
Predicting the Maintenance of Aircraft Engines using LSTMPredicting the Maintenance of Aircraft Engines using LSTM
Predicting the Maintenance of Aircraft Engines using LSTM
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
IRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
IRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
IRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
IRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
IRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
IRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
IRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
IRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
171ticu
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
RadiNasr
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
zubairahmad848137
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
mamamaam477
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 

Recently uploaded (20)

A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 

Generator Maintenance Scheduling Of Power System Using Hybrid Technique

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 03 Issue: 02 | Feb-2016 www.irjet.net p-ISSN: 2395-0072 © 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 418 Generator Maintenance Scheduling Of Power System Using Hybrid Technique Suraj Kumhar1, Mantosh Kumar2 1M.Tech Scholar, Mewar University, Chittorgarh, Rajasthan, India 2Assistant Professor, Mewar University, Chittorgarh, Rajasthan, India ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - This paper presents generator maintenance scheduling of a power system based on minimization of the objective function considering the economical and reliable operation of a power system while satisfying the network constraints along with crew/manpower, generation limits, precedence constraints, demandedload, maintenancewindow, loss of load probability and reliability constraints. Optimization was carried out on a practical thermal power plant consisting of 19 generating units, over a 25 weeks planning horizon. Key Words: Maintenance Schedule;ArtificialIntelligence; Fuzzy Systems; Genetic Algorithm; Evolution Strategy; Particle Swarm Optimization; Hybrid IntelligentSystems. 1. INTRODUCTION The scenario of operation and planning in power system such as economic dispatch, unit commitment, load dispatch, generation co-ordination are highly influencedbygenerator maintenance scheduling. The maintenance schedule is a preventive outage schedule for generating units within a particular time horizon for decreasing operation cost and increasing reliability. Maintenance scheduling turns into a complex problem whenthepowersystemincludesa number of generating units with different specifications, and when several constraints have to be taken into consideration to achieve a practical and feasible solution. Generator maintenance scheduling is done to minimise total operation cost satisfying all constraints of units and power system over time horizons of different durations. Short-term maintenance scheduling for one hour to one day ahead is important for day-to-day operations, unit commitment, and operation planning of power generation facilities. Medium-term scheduling for a one day up toa year ahead is essential for resource management. Long-term scheduling of a year or two years ahead is important for future planning. The complexity and larger size of electric system generation with the more reliability concern and low operation cost have being causing a great interest in automatic scheduling techniques for maintenance of generators and power system, capable of giving feasible or optimal scheduling. The reliability of the power system assures that the demand is met even though an outage occurred in the system. Generally, the utility provides a spinning reserve, by supplying more power than demanded. This improves the system reliability with increased operating cost. A well- planned schedule for maintenance and repair work should be prepared for each unit in the system, according to the period of maintenance activities, which are based on the operating hours and condition of the engines. The scheduling starts with all units available for production; then initial schedulehastobegeneratedinsome suitable way; then modify this initial schedule subsequently if the method allows for more than one iteration. Efficient and practical maintenance schedule increases system reliability, reduces operation and maintenance costs, and extends the lifetimes of the generators. Moreover, an easily revisable maintenance schedule is required to adapt to increasing load demand and number of generating units ina larger-scale power system. Maintenance scheduling is an optimization problem to obtain the best schedule while meeting a variety of equality, inequality constraints and thousands of decision variables which are determined and obeyed simultaneously. The objective functions in maintenance schedulingare reliability and cost. The economic objective function includes the maintenance cost and operation cost [1]. The reliability objective function can be eitherdeterministic, wheretheaim is to maximize the system’s net reserve (thesysteminstalled capacity minus the maximum load and the maintenance capacity during the period under examination), or random, where goal is to minimize the risk level. Several hard and soft constraints should be taken into account to reflect the actual operating conditions of the power system in order to make the maintenance plan feasible. Listed below are some constraints for maintenance scheduling: • Crew constraint • Availability of maintenance resources • Maintenance period during which each unit should be maintained • Load demand • Total Generation • Condition of the engine • Spinning reserve requirement • Loss of Load Probability • Transmission network constraints
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 03 Issue: 02 | Feb-2016 www.irjet.net p-ISSN: 2395-0072 © 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 419 The approach needs a trade-off between the quality of the solution and number of iterations. The methods may not converge if the stop criterion is inadequately chosen. 2. APPROACHES FOR MAINTENANCE SCHEDULING PROBLEM The maintenance-scheduling problem has been solved using a number of techniques and methodologies. Integer programming method is the most frequently used mathematical method for maintenance scheduling.Amixed- integer programming technique was used for obtaining optimum schedules in [1] for a planning horizon of one month. The existing methods indicate that the uncertainties in the problem, computational time, generating system size, and long planning horizons are the crucial issues in developing a feasible, practical maintenance-scheduling plan. However, the approach could not be applied to large- scale problems due to excessive processingtimeandstorage requirements. To reduce the storage and computation time, successive approximation dynamic programming was proposed in [2]. Artificial neural networkswereemployedin [3] to handle the inequality constraints in the maintenance- scheduling problem. The approach was used for a system containing 15 generating units and one year planning horizon. Recently, techniques such as Simulated Annealing (SA) and Genetic Algorithm (GA) have been proposed for maintenance scheduling of large systems. Reference [4] considers a system containing 21 units and one year planning horizon. The main motivation of using evolutionary techniques lies in the strong adaptability and flexibility for solving difficult multi-objective problem with many constraints. In this research, actual data from a thermal power system is used for developing practical maintenance plans. One of the options available to the utilities in order to maintain a high level of reliability and economyofthepower system is economic dispatch (ED). ED allocates the total power demand among theonlinegeneratingunitsinorder to minimize the cost of generation while satisfying important system constraints. Some factors that influence ED of the system are operating efficiency of generating units, fuel and operating costs, and transmission losses. The ED problems are in general non-convex optimizationproblemswithmany local minima. Numerous classical techniques such as LaGrange based methods, linear programming (LP), non- linear programming (NLP)andquadratic programming(QP) methods have been reported in the literature. In order to obtain approximate solution of a complex GMS, new concepts have emerged in recent years [7]-[10]. They include applications of probabilistic approach[5],simulated annealing [6], decomposition technique [7] and genetic algorithm (GA) [8]. The application of GA to GMS presented in [10] have been compared with, and confirmed to be superior to other conventional algorithms such as heuristic approaches and branch-and-bound (B&B) in the quality of solutions. GMS using DE for the minimization of reliability cost function of levelling reserve generationoveran entireperiod of 52 weeks maintenance window for the Nigerian power system have been reported in [9],. 2.1 Particle Swarm Optimization (PSO) Particle Swarm Optimization (PSO) [7] has been successfully applied in many areas: function optimization, artificial neural network training, fuzzy system control, and other areas where GA can be applied. This algorithm was discovered through simulation of bird flocking and fish schooling (social behavior). As sociobiologist E. O. Wilson has written, in referenceto fish schooling, "In theory at least, individual members of the school can profit from the discoveries and previous experience of all other members of the school during the search for food. This advantage can become decisive, outweighing the disadvantages of competition for food items, whenever the resource is unpredictablydistributedin patches". This statement suggests that social sharing of information offers an evolutionary advantage: this hypothesis was fundamental to the development of particle swarm optimization. Similar toGeneticAlgorithms(GA)[10- 12], PSO is a population based optimization tool. Thesystem is initialized with a population of random solutions and searches for optima by updating generations. However, unlike GA, PSO has no evolution operators such as crossover and mutation. In PSO,thepotential solutions,calledparticles, are "flown" through the problem space by following the current optimum particles. 2.2 Simulated Annealing (SA) Metaheuristic techniques include Tabu Search, Neural Networks, Simulated Annealing, Particle Swarm Optimization and Ant Colony Optimization. Simulated Annealing and Genetic Algorithms are used to address combinatorial problems due to the presence of discrete variables. Simulated Annealing was developed by Kirkpatrick et al. [13], followed by Aarts and Korst [14] based on the Metropolis algorithm dated from 1953. It is a search procedure in which it is included the possibility of accepting a solution that is worse than the current one. The simulation starts at an initial solution, x1, evaluates it using an Evaluation Function, f(x1), and samples a newsolutioninthe neighborhood of x1. If this new solution improves f(x1), then it is accepted. If it is worse than the current one, itcanstill be accepted depending on a so-called probability of accepting worse solutions. 2.3 Tabu Search (TS) In [15-16] the GMS problem is solved using Tabu Search. In [15] it is used a multi-stage approach to decompose the problem in several sub-problems. The partial results are
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 03 Issue: 02 | Feb-2016 www.irjet.net p-ISSN: 2395-0072 © 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 420 then combined to pro-ducetheglobal maintenanceschedule. In [16] the formulation uses the generation cost and the reserve margin as objectives and the constraints are related with the availability of crews, predefined sequence of maintenance actions for several units and continuity of the maintenance period once a maintenance action starts. The plans provided by the Tabu Search algorithm for two generation systems (one with 4 units and another with 22 units) were compared with the results obtained with an implicit enumeration approach. The results obtained with Tabu Search were very promising given the more reduced computation time and their good quality. The performance of several meta-heuristic approaches, namely Tabu Search, Simulated Annealing, Genetic Algorithms, an hybrid Simulated Annealing/Genetic Algorithm approach and an hybrid Tabu Search/Simulated Annealing algorithm. The authors report that the combined use of Simulated Annealing/Genetic Algorithm and of Tabu Search/Simulated Annealing produces better results than the isolated use of a single metaheuristic, although the computational time is sometimes longer. 2.4 Evolution Strategy (ES) Evolution Strategies [17-21] are part of the field of evolutionary algorithms. ES has always beencompared with GA and a concluding statement on whichisbetteriscertainly not possible. The subtle difference between ES and GA is in the parameter representation. ES works with real values of the variables (phenotype) whereas GA works with binary strings which are subsequently mapped to object variables. Since ES works completely on a phenotypic level, hence one can represent moreknowledgeabouttheapplicationdomain into the coding of the problem. One important difference between ES and GA is that the main search operator in ES was based on the mutation operator. But more recently, a crossover operator was introduced to facilitate the search process. The traditional ES approach can be represented as follows: 1. For each parent, generate offspring’s through mutation process. 2. Select the best individuals from the mutated and current population asthenextgeneration. 2.5 Genetic Algorithm (GA) Genetic algorithms (GA) were first described by John Holland, who presented them as an abstraction of biological evolution and gave a theoretical mathematical framework for adaptation. Holland's GA are a method of moving from one population of "chromosomes" (bit strings representing candidate solutions to a problem), to a new population of solutions using selection, together with a set of genetic operators of cross-over, mutation and inversion. Each chromosome consists of "genes" (e.g. bits) with each gene representing an instance of a particular "allele"(e.g.a 0or1). Genetic algorithms are based on models of genetic change in a population of individuals. These models consist of three basic elements; • A 'fitness' measure which governs an individual's abilityto influence future generations, • A selection and reproduction process which produces offspring for the next generation, • Genetic operators which determine the geneticmake-up of the offspring The distinguishing feature of a GA with respect to other function optimisation techniques is that the search towards an optimum solution proceeds not by incremental changes to a single structure (candidate solution) but by maintaining a population of solutions from which new structures are created using the genetic operators. Fig -1: The overall strategy for maintenance scheduling of generating unit 3. PROBLEM DISCRIPTION The objective function consideredina GMSproblemconsists of the sum of the maintenance costs of the off-line units and the operational costs of the on-line generators. The maintenance costs of a generating unit would not change during the study period and can be regarded as constant in the GMS problem. The values will not influence the search for the optimisation operational costs. Table -1: GENERATOR RATINGS Unit Rating (MW) a B C 1 6.1 0.0038 5.44 52.6 2 6.1 0.0038 5.44 52.6 3 6.1 0.0038 5.44 52.6 4 6.1 0.0038 5.44 52.6 5 6.1 0.0038 5.44 52.6 6 6.1 0.0038 5.44 52.6 7 6.1 0.0038 5.44 52.6
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 03 Issue: 02 | Feb-2016 www.irjet.net p-ISSN: 2395-0072 © 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 421 8 6.1 0.0046 6.34 53.7 9 6.1 0.0050 5.34 51.5 10 6.4 0.0050 5.34 51.5 11 6.4 0.0057 5.34 52.5 12 6.4 0.0057 5.34 52.5 13 8.0 0.0346 8.06 76.5 14 8.0 0.0346 8.06 76.5 15 2.1 0.0076 6.90 55.4 16 2.1 0.0076 7.10 55.4 17 2.1 0.0076 6.95 55.4 18 2.1 0.0076 7.30 55.4 19 6.1 0.0079 7.10 59.3 The following table shows the data used in the evaluation of maintenance cost. Table-2:DOWNTIMEANDMAINTENANCECOSTPERWEEK OF EACH GENERATOR Unit Downtime (D) V ($/week) Unit Downtime (D) V ($/week) 1 1 750 11 3 850 2 4 750 12 3 850 3 1 750 13 4 1500 4 2 750 14 3 1500 5 3 750 15 1 600 6 2 750 16 1 600 7 1 750 17 1 600 8 1 750 18 1 600 9 2 750 19 4 900 10 3 850 The objective function for GMS model    2 1 1 1 min Z Y Y zy y y yz y yz y y z y y U A B P C P FV P          where FVy(Py) is expressed as a linear equation of production cost.   1 0 y y y y y z F V P V D D      if unit y start maintenance at week z For each time period z, z =1,2, 3,……,Z. The objective function of the problem is subjected to constraints as given below: a) Load Balance 1 Z z y z y y z U P D   b) Generator Output Limit min maxy zy yP P P  c) Spining Reserve max 1 (1 %) Y zy y y z y U P D r    d) Maintenance Window 1, , 0, 0,1, y y zy y y y y y t ey t l d U s t s d e t l             e) Maintenance Area 1 (1 ) Y zy y U     f) Crew Constraint 1 1 (1 ) Z Y zy z y U Cr     4. PROBLEM SOLUTION The schedule for GMS is obtained by using mixed genetic algorithm which is explained below in flowchart as:
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 03 Issue: 02 | Feb-2016 www.irjet.net p-ISSN: 2395-0072 © 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 422 Initialize Population Fitness evaluation Selection for the reproduction (selection) Crossoverof the selected individual Mutation of the selected individual Fitness evaluation of the offspring Selection for the replacement Stopping criteria?Optimal Schedule YES NO Fig -2: The flowchart of GMS using GA. 5. RESULTS Test system consider of 19 generating units for time span of 25 weeks with an objective to minimize the economic cost function over planning horizon subjected to various constraints is optimized using genetic algorithm. The result of optimization compared with other metaheuristic techniques is shown below in TABLE IV. The total maintenance cost is obtained using fixed maintenance cost data. The operational cost Plot obtained is shown below in figure 3 and the schedule obtained using GA is tabulated below. Fig -3:. Operational Cost Plot Table-3: SCHEDULE OBTAINED USING GENETIC ALGORITHM Maintenance Period Generating unit’s index of scheduled maintenance (weeks) 1 2 3 4 5 6 7 8 9 1 0 11 12 13 14 15 16 17 18 19 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 3 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 1 1 0 4 1 1 1 0 1 1 1 1 1 1 1 1 1 0 1 1 1 1 1 5 1 0 1 1 1 1 1 1 1 1 0 1 1 1 1 1 1 1 1 6 1 1 1 1 0 1 1 1 1 1 1 1 0 1 1 1 1 1 1 7 1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 8 1 0 1 1 0 1 1 0 1 1 1 1 1 1 1 1 1 1 1 9 0 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 1 1 10 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 11 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 0 1 12 1 1 1 1 1 1 0 1 1 1 1 0 1 1 1 1 1 1 1 13 1 1 1 1 1 1 1 1 1 1 0 1 0 1 1 1 1 1 1 14 1 1 0 1 1 1 1 1 1 1 0 1 1 1 1 1 1 1 1 15 1 0 1 1 0 0 1 1 0 0 1 1 1 1 1 1 1 1 0 16 1 1 1 1 1 1 1 1 1 0 1 1 1 1 1 1 1 1 1 17 1 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 1 1 18 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 1 1 1 1 19 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 1 1 1 20 1 1 1 1 1 1 1 1 0 1 1 0 1 1 1 1 1 1 0 21 1 1 1 1 1 0 1 1 1 1 1 1 1 1 1 1 0 1 1 22 1 1 1 1 1 1 1 1 1 0 1 1 1 1 1 1 1 1 1 23 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 25 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Table-4: RESULTS S.No. Techniques Optimised Cost 1. Heuristic 73932889.326 2. GA 73928747.045 3. PSO 76930465.182 4. PSO with multiple changes 76930383.249 5. ES 7632895.839 6. ES with multiple mutation 76932699.485 7. ES with multiple mutation and crossover 76932745.216
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 03 Issue: 02 | Feb-2016 www.irjet.net p-ISSN: 2395-0072 © 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 423 6. CONCLUSIONS The generator maintenance scheduling problemdonefor 19 units test system subjected to various numberofconstraints using genetic algorithm as optimisation tool to obtain best schedule to minimize the economic cost function is carried out. Economic dispatch has been used to find an optimal combination of power generation that minimizes the total generation cost whilesatisfyingconstraints.TheGAgives the most promising results. The unplanned maintenance allowances and deferred maintenance can be consider for further work on this area with the use of hybrid heuristic techniques. One can also consider a frequency-basedmaintenanceoutageformulation or multi-objective modeling approach. REFERENCES [1] E. L. da Silva, M. Th. Schilling and M. C. Rafael, “Generation maintenance scheduling considering transmission constraints”, IEEE Transactions on Power System, Vol: 15, NO. 2, May 2000. [2] H. H. Zura, V. H. Qiutaha, “Generation maintenance scheduling via successive approximation dynamic programming”, IEEE Trans on PAS vol. PAS-94, 1975. [3] H. Sasaki, H. Choshi, Y. Takiuchi, J. Kubokawa, “A solution of maintenance scheduling covering several consecutive years by artificial neural networks”, Hiroshima University, IEEE 1993. [4] K. P. Dahal, C. J. Aldridge, J. R. Mc Donnald, “Generator maintenance scheduling using a genetic algorithm with a fuzzy evaluation function”, Eselvier, Fuzzy Sets and Systems 102: 21-29,1999. [5] R. Billinton and A. Abdulwhab, “Short-term generating unit maintenance in a deregulatedpowersystemusinga probabilistic approach”, IEEE Proceedings -Generation, TransmissionandDistribution150,(4),pp.463-468,July 2003. [6] T. Satoh and K. Nara, “Maintenance scheduling by using simulated annealing method”, IEEE Transactions on Power Systems, 6, pp. 850-857, 1991. [7] J. Yellen, T. M. Al-khamis, S. Vermuri and L. Lemonidis, “A decomposition approach to unit maintenance scheduling”, IEEE Transactions on Power Systems 7,pp. 726-733, 1992. [8] H. T. Firma and L. F. L. Legey, “Generation expansion: an iterative genetic algorithm approach”, IEEE Transactions on Power Systems, 17, (3), pp. 901-906, August 2002. [9] Y. Yare and G. K. Venayagamoorthy, “A differential evolution approach to optimal generator maintenance scheduling of the Nigerian power system”, IEEE Power and Energy Society General Meeting – Conversion and Delivery of Electrical Energy in the 21st Century,pp.1-8, 20-24 July 2008. [10]R. C. Eberhart, Y. Shi, “Comparison between genetic algorithms and particle swarm optimization”, Evolutionary Programming VII, 1998. [11]M. Lovbjerg, T. K. Rasmussen, T. Krink, “Hybrid particle swarm optimiser with breeding and subpopulations”, Dept. of Computer Science, University of Aarhus, 2001. [12]T. LogenthiranandD.Srinivasan,“Shorttermgeneration scheduling of a microgrid”, IEEE TENCON, pp.1-6, 2009. [13]S. Kirkpatrick, C.D. Gelatt, M.P. Vecchi, “Optimization by simulated annealing”, Science 220, 671–680, 1983. [14]E. Aarts, J. Korst, Simulated Annealing and Boltzman Machines, “Electric Power Systems Research”, New Scheduling, John Wiley & Sons,67, 67–72, 2003. [15]E.K. Burke, A.J. Smith, “A multi-stage approach for the thermal generator maintenanceschedulingproblem”,in proceedings of the 1999 Congress on Evolutionary Computation, CEC’99, vol. 2, Washington DC, USA, July, 1999. [16]I. El-Amin, S. Duffuaa, M. Abbas, “A Tabu Search algorithm for maintenance scheduling of generating units”, Electric PowerSystemsResearch54,91–99.York, 2000. [17]I. Rechenberg, Frommann-Holzboog “Evolutions strategies”, 1994. [18]L. Costa, P. Oliveira, “An evolution strategy for multiobjective optimization”, Dept de Producao e Sistemas, University do Minho, 2002. [19]N. Fonseca, V. Miranda, “EPSO - best-of-two-worlds meta-heuristic applied to power system problems”, Evolutionary Computation, 2002. CEC '02. Proceedings of the 2002 Congress on , Volume: 2 , Page(s): 1080 - 1085, 2002. [20]P. J. Abrao, A. P. A. da Silva, “Applicationsofevolutionary computation in electric power systems” Evolutionary Computation, 2002. CEC '02. Proceedings of the 2002 Congress on , Volume: 2 , Page(s): 1057 -1062, 2002. [21]Y. Yare, and G. K. Venayagamoorthy, “Comparison of DE and PSO for generator maintenance scheduling”, IEEE Swarm Intelligence Symposium St. Louis MO USA, September 21-23, Page(s): 1-8, 2008. [22]H. C. Sun, Y. C. Huang, and K. Y. Huang, “A new algorithm for power system scheduling problems”, Eighth International Conference on Intelligent Systems Design and Applications, Volume: 1, November, Page(s):36-40, 2008. [23]R. Eshraghnia, M. H. Modir Shanechi, and H. R. Mashhadil, “A new approach for maintenance scheduling of generating units in power market”, 9th International Conference on Probabilistic Methods Applied to Power Systems KTH, Stockholm, Sweden, June 11-15, Page(s): 1-7, 2006.