SlideShare a Scribd company logo
1 | P a g e
#MSPROJECTASSIGNMENTHELP
For Help Contact Information:
Harinath Reddy
Phone: +91-9502542081(IND) (Whats App, Viber)
phone: +1-2089086040 (US)
Email: harinath.infotech@gmail.com
ICT Product development Project plan: A
case of CQ Video Company
2 | P a g e
Table of Contents
1. Project background .....................................................................................................................3
2. Assessment Part A.......................................................................................................................4
2.1 Critical path tasks of the project ...........................................................................................4
3. Memo to Director of product development ..................................................................................6
4. Risk Management........................................................................................................................9
5. Approach of project budget reduction........................................................................................10
6. Approach for better project management strategies...................................................................11
7. Better qualityin product development.......................................................................................12
3 | P a g e
1. Project background
Always a proper project management plays a crucial role in deciding the overall success of any
project execution. Prior planning of all the project activities is required across developing a
project plan and in general various assumptions, attributes and constraints are considered.
Assumptions made over the project management plan will be based on the available resources
and infrastructure at the time of project management plan development and in future. Resource
requirements are also estimated against the duration to complete a specific task across
developing a typical project management plan. A case with CQ Video Company is considered
over developing the project plan, where a typical Gantt chart, Tasks and their descriptions,
resource requirements, time duration and budget planning is done based on the inputs provided.
MS Project management Professional 2010 tool is used to plan the desired project and the
corresponding questions raised over the case study are answered in detail and given below
4 | P a g e
2. Assessment Part A
2.1 Critical path tasks of the project
Based on the project plan prepared against the project requirement using the MS project
management software, few critical path tasks are identified and they are as listed below
Critical Path Tasks
CQ Video Company
Milestones
M1 Completion of Concept review
M2 Completion of Design and review
P1 Prototype Building
P2 Prototype Building
M3 Review of Final Design
M4 Review of Product Launch
Workshop planning
Electronics
1.4 Verification tests for all the electronics—P1
1.5 Improvements over Circuit design---P2
Software
Mechanics
5 | P a g e
3.1 Industrial Design
3.2 Modifications to existing PWB outline
3.3 Design of mechanical CAD system---P1
3.4 Analysis of stack tolerance
3.5 Analysis of mechanical tasks---P1
3.6 Modifications to the existing mechanical parts—P2
Verification
4.2 Testing of respective components
4.5 Validation tests for the products
4.6 Compiling technical construction file
4.7 Approval tests and regulatory tests
Prototype 1 Build
5.1 Lead time of all the components is calculated
5.2 Manufacturing and delivery of PWB
5.5 Build of Prototype---P1
Prototype 2 Build
6.1 Lead time of all the components is calculated
6.2 Manufacturing and delivery of PWB
6.4 Lead time calculation of mechanical parts
6.4 Build of prototype---P2
Production of devices for market or customer
8.1 Preparation of production and assembly lines
8.2 Device production
Table 2.1.1: Table showing the critical path tasks of the project
Resource over allocation issues over the current project are created over the file
CQVideoPartA1.mpp and CQVideoPartA2.mpp. All the possible additional milestones are added
6 | P a g e
over the part2 of the MS Project file created and attached and the respective snapshot is as shown
below
Fig 2.1.1 Milestones and project activities of CQ Video project management Gantt chart
CQVideoPartA1.mpp
Fig 2.1.2: Milestones and project activities of CQ Video project management Gantt chart
CQVideoPartA2.mpp
3. Memo to Director of product development
7 | P a g e
Memorandum
CQ Video Company
Subject: Detailed Project Schedule
To: Mr. Product (Product development director)
From: Project Management Team
Based on the previous discussion the first milestone of the project is due on 5th September 2014,l
and from the core analysis of the proposed product development plan, respective project plan
which includes the resources, time constrains, budget and Gantt chart is prepared and is as
attached. It is expected that the entire project will be completed by 1st April 2014 based on the
total milestones set, resources and budget available. Project manager is responsible in this
context, to ensue, all the human capital and budget is completely available through the project
execution plan. A total of 148 to 155 days will be taken to complete the entire proposed project
including all the risks and possible assumptions consideration. Each and every milestone is
divided into number of sub tasks and the critical paths tasks are also identified as a part of the
core project risk analysis and as attached. Based on the time and resources available, it is
estimated that the total budget would be around $293920 in the best possible case. There are few
alternatives to reduce the budget without effecting the resource allocation and would be provided
in the next memo. A brief snapshot of the of the possible labor cost is as provided
Tasks Estimated Cost
Workshop
planning
$ 8,320.00
8 | P a g e
Electronics and
related components
$ 31,920.00
Software module
development
$ 136,480.00
Mechanics
integration
$ 35,200.00
Verification and
testing
$ 28,800.00
Build Proto1 $ 9,600.00
Build Proto2 $ 9,600.00
Documentation of
the milestones and
deliverables
$ 14,000.00
Production
customer
associated devices
(Estimate for 50
units)
$ 20,000.00
Total estimate of
the project
$ 293,920.00
9 | P a g e
We are also attaching the entire project schedule as discussed over the memo, please find the
same and revert in case of further queries or issues.
Regards
Project Management Team
4. Risk Management
In general every project includes both pros and cons and thus estimating the possible risks in
prior to milestone or project schedule is equally important in associating with the corresponding
resource allocation strategies. When the current case of CQ Video Company is considered, there
are number of tasks and milestones involved and thus the chances of risks will be also high. In
general these risks can be in the form of resource allocation, deadlines, lack of infrastructure
related components like electronics, software or mechanics and improper allocation of time
against the targets and milestones set. Following are few of the possible risk assumed and they
are discussed as below
 Concept review is the first milestone as per the current case and the main risk associated
in this context, is that previous or existing product development plans and documents
should be in a proper format, such that the respective milestone can be delivered on time
i.e., 5th September 2014. If there is any delay in gathering the required information,
milestone M1 will be effected, which will have potential impact over rest of the
deliverables and milestones of the developed product development project plan
 Another complex risk associated with the current product development project plan is
that, a sequential project management plan is followed against delivery of each milestone
10 | P a g e
and if there is delay with any of the tasks, entire project delivery will be affected. The
best example that can be considered over is that, delay in resource allocation will
complete effect the production of number of units required and this can be handled with a
proper critical path analysis against the respective tasks
 There are some risks associated with the external suppliers in terms of delivering the
required components related to electronics, software and mechanics. Thus the respective
risks can be reduced with proper supply chain management strategies.
5. Approach of project budget reduction
From the analysis of the project plan and Gantt chart prepared against resource allocation, time
constraints and budget allocation against each and every milestone and deliverable, it is noted
that the total estimate of the project is around $293920. The overall estimated budget can be
further reduced or optimized in few interesting ways against applying the sophisticated budget
and project scheduling and few assumptions are considered in this context and they are as listed
below
 Production Engineers and Mechanical Engineers can be increased to two each, so that
even the payout increases, the products can be developed quickly and lot of infrastructure
budget can be optimized in this context and this can be around $1298.
 As per the current project and budget schedule, the total estimate allocated for testing and
documentation is around $42000 and this can be reduced by involving the trainees over
the project deliverables and ensure they document a milestone in parallel to the actual
development.
11 | P a g e
 Testing cost can be reduced by adopting few automation testing techniques, which can be
embedded against the project tasks deliverables and thus total time and cost for
verification, testing and documentation can be reduced up to 28%
 If the mechanical part modification process can be optimized, the overall cost incurred
against the corresponding task can be reduced to 20%. This can be achieved by buying
the respective parts from Quality of Service based supplier or vendor.
 Cost incurred for Software development can also be reduced by outsourcing few of the
modules or purchasing the existing popular web services in the respective fields. This
approach will reduce the budget allocated against Software development to 15-25%.
 Agile and Scrum based project management can be adopted over the current proposal of
product development and thus the overall project budget can be reduced further to 30%
by avoiding rework on the respective deliverables or testing or documentation.
6. Approach for better project management strategies
Based on the project management plan, Gantt chart, resource allocation, budgeting and time
schedules prepared against the proposed project development, it is clear that each and every
project activity is given ample priority and was allocated with required number of resources and
budget. Apart from the current project management strategies applied and stimulated, there is
scope to improve the respective strategies and few of them are as listed below
 The project management plan prepared in the current case is purely based on prototype,
Rapid application development and waterfall methods. With these approaches the risk of
maintenance issues and design mismatch are high irrespective to the quality measures
considered. Thus the respective process can be improved by adopting the Agile project
management framework
12 | P a g e
 From the current project management plan associated with the product development, it is
observed that, lot of attention is given towards the milestone activities and production
activities. In future 4 to 5 Prototype builds can be released using regular scrum patterns of
Agile Project management strategies and thus the quality of the product development and
project management can be further enhanced.
7. Better quality in product development
Utter most care is taken in the current context to deliver the milestones and project activities.
Still there is scope to deliver better quality in terms of project management and product
development and few of the important points are given below after a detailed review of the
current project plan developed
13 | P a g e
 Design, Development and Implementation of the Software modules or activities can be
outsourced or purchased in the form of web services, such that over time will be saved
and better Software quality is ensued
 Production of few electronic and mechanical components can also be improved in terms
of quality by engaging Quality and Test engineers, where the traditional approaches of
testing and bug fixing can be replaced with latest automated testing tools like Selenium.
 Entire project management strategies adopted currently can be replaced by sophisticated
techniques of Agile and SCRUM framework, such that better quality is possible in
product development and milestone deliverables as well.
#SystemDesignAssignmentHelp
#NetworkDesignAssignmentHelp
#CyberSecurityAssignment
#AssignmentHelp
#MSPROJECTASSIGNMENTHELP
#ManagementAssignmentHelp
#AssignmentsHelp
#ProjectsHelp
#HomeworkHelp
#DissertationsHelp
#ThesisHelp
#AcademicAvenue
#AcademicsHelp
#FrustratedWithAssignments
#MarketingAssignmentHelp
14 | P a g e
#ResearchProposalHelp
#CaseStudyHelp
#ResearchReportHelp
#SurveyHelp

More Related Content

What's hot

IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET Journal
 
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
IRJET Journal
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
Farhan Moosa
 
Integrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performanceIntegrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performance
Glen Alleman
 
Cost management
Cost managementCost management
Cost management
Suranji Kannangara
 
IRJET- Last Planner System
IRJET- Last Planner SystemIRJET- Last Planner System
IRJET- Last Planner System
IRJET Journal
 
Activity schedule and affective control of component based project
Activity schedule and affective control of component based projectActivity schedule and affective control of component based project
Activity schedule and affective control of component based project
eSAT Journals
 
Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management Essentials
Glen Alleman
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
HossamNegidaPMPRMPPS
 
Pittsburgh case study midfield energy system
Pittsburgh case study midfield energy systemPittsburgh case study midfield energy system
Pittsburgh case study midfield energy system
priyang2004
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
PRIYANSHU KUMAR
 
Tracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using PrimaveraTracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using Primavera
IRJET Journal
 
Bindu Sharma
Bindu SharmaBindu Sharma
Bindu Sharma
Bindu Sharma
 
Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOE
Glen Alleman
 
7 Steps Project Execution Process
7 Steps Project Execution Process7 Steps Project Execution Process
7 Steps Project Execution Process
C K Vishwakarma
 
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
Gaurav Verma
 
Agile Project Management Procedures
Agile Project Management ProceduresAgile Project Management Procedures
Agile Project Management Procedures
Glen Alleman
 

What's hot (20)

IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Integrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performanceIntegrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performance
 
Cost management
Cost managementCost management
Cost management
 
IRJET- Last Planner System
IRJET- Last Planner SystemIRJET- Last Planner System
IRJET- Last Planner System
 
Activity schedule and affective control of component based project
Activity schedule and affective control of component based projectActivity schedule and affective control of component based project
Activity schedule and affective control of component based project
 
Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management Essentials
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 
Pittsburgh case study midfield energy system
Pittsburgh case study midfield energy systemPittsburgh case study midfield energy system
Pittsburgh case study midfield energy system
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Tracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using PrimaveraTracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using Primavera
 
Project Control System
Project Control SystemProject Control System
Project Control System
 
Bindu Sharma
Bindu SharmaBindu Sharma
Bindu Sharma
 
Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOE
 
7 Steps Project Execution Process
7 Steps Project Execution Process7 Steps Project Execution Process
7 Steps Project Execution Process
 
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
 
SE chapters 24-25
SE chapters 24-25SE chapters 24-25
SE chapters 24-25
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Agile Project Management Procedures
Agile Project Management ProceduresAgile Project Management Procedures
Agile Project Management Procedures
 

Viewers also liked

Projecting success by Stephanie Atkins
Projecting success by Stephanie AtkinsProjecting success by Stephanie Atkins
Projecting success by Stephanie Atkins
greenwhistle
 
Trevor Jones, DHL Supply Chain with Anthony Olomolaiye, Coventry University
Trevor Jones, DHL Supply Chain with Anthony Olomolaiye, Coventry UniversityTrevor Jones, DHL Supply Chain with Anthony Olomolaiye, Coventry University
Trevor Jones, DHL Supply Chain with Anthony Olomolaiye, Coventry University
Association for Project Management
 
It project management assignment ppt
It project management assignment pptIt project management assignment ppt
It project management assignment ppt
OZ Assignment help
 
Project management university
Project management universityProject management university
Project management university
Alejandra Velázquez Aranda
 
Introduce Project Management
Introduce Project ManagementIntroduce Project Management
Introduce Project Management
guest90bddb
 
Atkins' tunnelling projects
Atkins' tunnelling projectsAtkins' tunnelling projects
Atkins' tunnelling projects
Atkins
 
Assignment brief project management
Assignment brief project managementAssignment brief project management
Assignment brief project management
Bhavi Bhatia
 
CSCMP 2011 europe tom kimball - dhl supply chain final
CSCMP 2011 europe   tom kimball - dhl supply chain finalCSCMP 2011 europe   tom kimball - dhl supply chain final
CSCMP 2011 europe tom kimball - dhl supply chain final
DHL Supply Chain
 
Prophets presents "Facebook Timeline for brands essential training"
Prophets presents "Facebook Timeline for brands essential training"Prophets presents "Facebook Timeline for brands essential training"
Prophets presents "Facebook Timeline for brands essential training"
Prophets Agency
 
Vinamilk Supply Chain Management Project - Van M. Vu
Vinamilk Supply Chain Management Project - Van M. VuVinamilk Supply Chain Management Project - Van M. Vu
Vinamilk Supply Chain Management Project - Van M. VuV V?
 
Project Finance management assignment
Project Finance management assignmentProject Finance management assignment
Project Finance management assignment
Manohar Mani Manjula Iyer
 
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
peter747
 
Introduction to project management academic essay assignment - www.topgrade...
Introduction to project management   academic essay assignment - www.topgrade...Introduction to project management   academic essay assignment - www.topgrade...
Introduction to project management academic essay assignment - www.topgrade...Top Grade Papers
 
Project Management Assignment - Bailey
Project Management Assignment - BaileyProject Management Assignment - Bailey
Project Management Assignment - BaileyAllison Bailey
 
Management by exception
Management by exceptionManagement by exception
Management by exception
gaurav_einstien
 
Academic Recruitment Best Practices -Project Report-Final 7.8.15
Academic Recruitment Best Practices -Project Report-Final 7.8.15Academic Recruitment Best Practices -Project Report-Final 7.8.15
Academic Recruitment Best Practices -Project Report-Final 7.8.15Brian Groeschel, MA
 
Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1
Mena M. Eissa
 
3year Project Management Assignment Final
3year Project Management Assignment Final3year Project Management Assignment Final
3year Project Management Assignment FinalMageba25
 
Project Management in Marketing Final Report
Project Management in Marketing Final ReportProject Management in Marketing Final Report
Project Management in Marketing Final Report
Zafar Iqbal
 
Project Management Plan Template
Project Management Plan TemplateProject Management Plan Template
Project Management Plan Template
Simplilearn
 

Viewers also liked (20)

Projecting success by Stephanie Atkins
Projecting success by Stephanie AtkinsProjecting success by Stephanie Atkins
Projecting success by Stephanie Atkins
 
Trevor Jones, DHL Supply Chain with Anthony Olomolaiye, Coventry University
Trevor Jones, DHL Supply Chain with Anthony Olomolaiye, Coventry UniversityTrevor Jones, DHL Supply Chain with Anthony Olomolaiye, Coventry University
Trevor Jones, DHL Supply Chain with Anthony Olomolaiye, Coventry University
 
It project management assignment ppt
It project management assignment pptIt project management assignment ppt
It project management assignment ppt
 
Project management university
Project management universityProject management university
Project management university
 
Introduce Project Management
Introduce Project ManagementIntroduce Project Management
Introduce Project Management
 
Atkins' tunnelling projects
Atkins' tunnelling projectsAtkins' tunnelling projects
Atkins' tunnelling projects
 
Assignment brief project management
Assignment brief project managementAssignment brief project management
Assignment brief project management
 
CSCMP 2011 europe tom kimball - dhl supply chain final
CSCMP 2011 europe   tom kimball - dhl supply chain finalCSCMP 2011 europe   tom kimball - dhl supply chain final
CSCMP 2011 europe tom kimball - dhl supply chain final
 
Prophets presents "Facebook Timeline for brands essential training"
Prophets presents "Facebook Timeline for brands essential training"Prophets presents "Facebook Timeline for brands essential training"
Prophets presents "Facebook Timeline for brands essential training"
 
Vinamilk Supply Chain Management Project - Van M. Vu
Vinamilk Supply Chain Management Project - Van M. VuVinamilk Supply Chain Management Project - Van M. Vu
Vinamilk Supply Chain Management Project - Van M. Vu
 
Project Finance management assignment
Project Finance management assignmentProject Finance management assignment
Project Finance management assignment
 
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
 
Introduction to project management academic essay assignment - www.topgrade...
Introduction to project management   academic essay assignment - www.topgrade...Introduction to project management   academic essay assignment - www.topgrade...
Introduction to project management academic essay assignment - www.topgrade...
 
Project Management Assignment - Bailey
Project Management Assignment - BaileyProject Management Assignment - Bailey
Project Management Assignment - Bailey
 
Management by exception
Management by exceptionManagement by exception
Management by exception
 
Academic Recruitment Best Practices -Project Report-Final 7.8.15
Academic Recruitment Best Practices -Project Report-Final 7.8.15Academic Recruitment Best Practices -Project Report-Final 7.8.15
Academic Recruitment Best Practices -Project Report-Final 7.8.15
 
Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1
 
3year Project Management Assignment Final
3year Project Management Assignment Final3year Project Management Assignment Final
3year Project Management Assignment Final
 
Project Management in Marketing Final Report
Project Management in Marketing Final ReportProject Management in Marketing Final Report
Project Management in Marketing Final Report
 
Project Management Plan Template
Project Management Plan TemplateProject Management Plan Template
Project Management Plan Template
 

Similar to edSe275 ms project-assignment

Advanced Product Quality Planning Reference Model
Advanced Product Quality Planning Reference ModelAdvanced Product Quality Planning Reference Model
Advanced Product Quality Planning Reference ModelAurélien Chassagne
 
Ch4 project management process
Ch4 project management processCh4 project management process
Ch4 project management processKittitouch Suteeca
 
Conveyor Belt Project Report
Conveyor Belt Project ReportConveyor Belt Project Report
Conveyor Belt Project Report
RISHABHSIINGH
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
TinotendaChivese
 
Sheet1WBSTask Name1Product development1.1 Electronics1.1.1 .docx
Sheet1WBSTask Name1Product development1.1   Electronics1.1.1      .docxSheet1WBSTask Name1Product development1.1   Electronics1.1.1      .docx
Sheet1WBSTask Name1Product development1.1 Electronics1.1.1 .docx
lesleyryder69361
 
1.2 project management by bee 2
1.2 project management by bee 21.2 project management by bee 2
1.2 project management by bee 2
Narayan Mane
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_a
Forbes Chanakira
 
CCI PM Processes (within PMP Process Groups and Knowledge Areas)
CCI PM Processes (within PMP Process Groups and Knowledge Areas)CCI PM Processes (within PMP Process Groups and Knowledge Areas)
CCI PM Processes (within PMP Process Groups and Knowledge Areas)Pamela Garrett
 
project-closure-software-engineering.ppt
project-closure-software-engineering.pptproject-closure-software-engineering.ppt
project-closure-software-engineering.ppt
JigneshKadia
 
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docxRunning Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
jeanettehully
 
Assessment_4.pptx
Assessment_4.pptxAssessment_4.pptx
Assessment_4.pptx
honeyarguelles
 
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docxRUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
toltonkendal
 
Project management case analysis
Project management case analysisProject management case analysis
Project management case analysis
Service_supportAssignment
 
Project Management Project Assignment - Project Schedule & Resource Allocatio...
Project Management Project Assignment - Project Schedule & Resource Allocatio...Project Management Project Assignment - Project Schedule & Resource Allocatio...
Project Management Project Assignment - Project Schedule & Resource Allocatio...
Shuchi Joshi
 
EO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.pptEO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.ppt
yashchotaliyael21
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedWaqar Ahmed
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
carolinef5
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
donaldp2
 
MGT-Ch07.ppt
MGT-Ch07.pptMGT-Ch07.ppt
MGT-Ch07.ppt
MarkNaguibElAbd
 
Student guide for unit 9
Student guide for unit 9Student guide for unit 9
Student guide for unit 9
Peter R Breach
 

Similar to edSe275 ms project-assignment (20)

Advanced Product Quality Planning Reference Model
Advanced Product Quality Planning Reference ModelAdvanced Product Quality Planning Reference Model
Advanced Product Quality Planning Reference Model
 
Ch4 project management process
Ch4 project management processCh4 project management process
Ch4 project management process
 
Conveyor Belt Project Report
Conveyor Belt Project ReportConveyor Belt Project Report
Conveyor Belt Project Report
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
Sheet1WBSTask Name1Product development1.1 Electronics1.1.1 .docx
Sheet1WBSTask Name1Product development1.1   Electronics1.1.1      .docxSheet1WBSTask Name1Product development1.1   Electronics1.1.1      .docx
Sheet1WBSTask Name1Product development1.1 Electronics1.1.1 .docx
 
1.2 project management by bee 2
1.2 project management by bee 21.2 project management by bee 2
1.2 project management by bee 2
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_a
 
CCI PM Processes (within PMP Process Groups and Knowledge Areas)
CCI PM Processes (within PMP Process Groups and Knowledge Areas)CCI PM Processes (within PMP Process Groups and Knowledge Areas)
CCI PM Processes (within PMP Process Groups and Knowledge Areas)
 
project-closure-software-engineering.ppt
project-closure-software-engineering.pptproject-closure-software-engineering.ppt
project-closure-software-engineering.ppt
 
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docxRunning Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
 
Assessment_4.pptx
Assessment_4.pptxAssessment_4.pptx
Assessment_4.pptx
 
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docxRUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
 
Project management case analysis
Project management case analysisProject management case analysis
Project management case analysis
 
Project Management Project Assignment - Project Schedule & Resource Allocatio...
Project Management Project Assignment - Project Schedule & Resource Allocatio...Project Management Project Assignment - Project Schedule & Resource Allocatio...
Project Management Project Assignment - Project Schedule & Resource Allocatio...
 
EO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.pptEO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.ppt
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javed
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
 
MGT-Ch07.ppt
MGT-Ch07.pptMGT-Ch07.ppt
MGT-Ch07.ppt
 
Student guide for unit 9
Student guide for unit 9Student guide for unit 9
Student guide for unit 9
 

Recently uploaded

GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
Nguyen Thanh Tu Collection
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
kaushalkr1407
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
Jisc
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Thiyagu K
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
Vikramjit Singh
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
Jheel Barad
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
EduSkills OECD
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
PedroFerreira53928
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
GeoBlogs
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
Anna Sz.
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
Col Mukteshwar Prasad
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
Celine George
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 

Recently uploaded (20)

GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 

edSe275 ms project-assignment

  • 1. 1 | P a g e #MSPROJECTASSIGNMENTHELP For Help Contact Information: Harinath Reddy Phone: +91-9502542081(IND) (Whats App, Viber) phone: +1-2089086040 (US) Email: harinath.infotech@gmail.com ICT Product development Project plan: A case of CQ Video Company
  • 2. 2 | P a g e Table of Contents 1. Project background .....................................................................................................................3 2. Assessment Part A.......................................................................................................................4 2.1 Critical path tasks of the project ...........................................................................................4 3. Memo to Director of product development ..................................................................................6 4. Risk Management........................................................................................................................9 5. Approach of project budget reduction........................................................................................10 6. Approach for better project management strategies...................................................................11 7. Better qualityin product development.......................................................................................12
  • 3. 3 | P a g e 1. Project background Always a proper project management plays a crucial role in deciding the overall success of any project execution. Prior planning of all the project activities is required across developing a project plan and in general various assumptions, attributes and constraints are considered. Assumptions made over the project management plan will be based on the available resources and infrastructure at the time of project management plan development and in future. Resource requirements are also estimated against the duration to complete a specific task across developing a typical project management plan. A case with CQ Video Company is considered over developing the project plan, where a typical Gantt chart, Tasks and their descriptions, resource requirements, time duration and budget planning is done based on the inputs provided. MS Project management Professional 2010 tool is used to plan the desired project and the corresponding questions raised over the case study are answered in detail and given below
  • 4. 4 | P a g e 2. Assessment Part A 2.1 Critical path tasks of the project Based on the project plan prepared against the project requirement using the MS project management software, few critical path tasks are identified and they are as listed below Critical Path Tasks CQ Video Company Milestones M1 Completion of Concept review M2 Completion of Design and review P1 Prototype Building P2 Prototype Building M3 Review of Final Design M4 Review of Product Launch Workshop planning Electronics 1.4 Verification tests for all the electronics—P1 1.5 Improvements over Circuit design---P2 Software Mechanics
  • 5. 5 | P a g e 3.1 Industrial Design 3.2 Modifications to existing PWB outline 3.3 Design of mechanical CAD system---P1 3.4 Analysis of stack tolerance 3.5 Analysis of mechanical tasks---P1 3.6 Modifications to the existing mechanical parts—P2 Verification 4.2 Testing of respective components 4.5 Validation tests for the products 4.6 Compiling technical construction file 4.7 Approval tests and regulatory tests Prototype 1 Build 5.1 Lead time of all the components is calculated 5.2 Manufacturing and delivery of PWB 5.5 Build of Prototype---P1 Prototype 2 Build 6.1 Lead time of all the components is calculated 6.2 Manufacturing and delivery of PWB 6.4 Lead time calculation of mechanical parts 6.4 Build of prototype---P2 Production of devices for market or customer 8.1 Preparation of production and assembly lines 8.2 Device production Table 2.1.1: Table showing the critical path tasks of the project Resource over allocation issues over the current project are created over the file CQVideoPartA1.mpp and CQVideoPartA2.mpp. All the possible additional milestones are added
  • 6. 6 | P a g e over the part2 of the MS Project file created and attached and the respective snapshot is as shown below Fig 2.1.1 Milestones and project activities of CQ Video project management Gantt chart CQVideoPartA1.mpp Fig 2.1.2: Milestones and project activities of CQ Video project management Gantt chart CQVideoPartA2.mpp 3. Memo to Director of product development
  • 7. 7 | P a g e Memorandum CQ Video Company Subject: Detailed Project Schedule To: Mr. Product (Product development director) From: Project Management Team Based on the previous discussion the first milestone of the project is due on 5th September 2014,l and from the core analysis of the proposed product development plan, respective project plan which includes the resources, time constrains, budget and Gantt chart is prepared and is as attached. It is expected that the entire project will be completed by 1st April 2014 based on the total milestones set, resources and budget available. Project manager is responsible in this context, to ensue, all the human capital and budget is completely available through the project execution plan. A total of 148 to 155 days will be taken to complete the entire proposed project including all the risks and possible assumptions consideration. Each and every milestone is divided into number of sub tasks and the critical paths tasks are also identified as a part of the core project risk analysis and as attached. Based on the time and resources available, it is estimated that the total budget would be around $293920 in the best possible case. There are few alternatives to reduce the budget without effecting the resource allocation and would be provided in the next memo. A brief snapshot of the of the possible labor cost is as provided Tasks Estimated Cost Workshop planning $ 8,320.00
  • 8. 8 | P a g e Electronics and related components $ 31,920.00 Software module development $ 136,480.00 Mechanics integration $ 35,200.00 Verification and testing $ 28,800.00 Build Proto1 $ 9,600.00 Build Proto2 $ 9,600.00 Documentation of the milestones and deliverables $ 14,000.00 Production customer associated devices (Estimate for 50 units) $ 20,000.00 Total estimate of the project $ 293,920.00
  • 9. 9 | P a g e We are also attaching the entire project schedule as discussed over the memo, please find the same and revert in case of further queries or issues. Regards Project Management Team 4. Risk Management In general every project includes both pros and cons and thus estimating the possible risks in prior to milestone or project schedule is equally important in associating with the corresponding resource allocation strategies. When the current case of CQ Video Company is considered, there are number of tasks and milestones involved and thus the chances of risks will be also high. In general these risks can be in the form of resource allocation, deadlines, lack of infrastructure related components like electronics, software or mechanics and improper allocation of time against the targets and milestones set. Following are few of the possible risk assumed and they are discussed as below  Concept review is the first milestone as per the current case and the main risk associated in this context, is that previous or existing product development plans and documents should be in a proper format, such that the respective milestone can be delivered on time i.e., 5th September 2014. If there is any delay in gathering the required information, milestone M1 will be effected, which will have potential impact over rest of the deliverables and milestones of the developed product development project plan  Another complex risk associated with the current product development project plan is that, a sequential project management plan is followed against delivery of each milestone
  • 10. 10 | P a g e and if there is delay with any of the tasks, entire project delivery will be affected. The best example that can be considered over is that, delay in resource allocation will complete effect the production of number of units required and this can be handled with a proper critical path analysis against the respective tasks  There are some risks associated with the external suppliers in terms of delivering the required components related to electronics, software and mechanics. Thus the respective risks can be reduced with proper supply chain management strategies. 5. Approach of project budget reduction From the analysis of the project plan and Gantt chart prepared against resource allocation, time constraints and budget allocation against each and every milestone and deliverable, it is noted that the total estimate of the project is around $293920. The overall estimated budget can be further reduced or optimized in few interesting ways against applying the sophisticated budget and project scheduling and few assumptions are considered in this context and they are as listed below  Production Engineers and Mechanical Engineers can be increased to two each, so that even the payout increases, the products can be developed quickly and lot of infrastructure budget can be optimized in this context and this can be around $1298.  As per the current project and budget schedule, the total estimate allocated for testing and documentation is around $42000 and this can be reduced by involving the trainees over the project deliverables and ensure they document a milestone in parallel to the actual development.
  • 11. 11 | P a g e  Testing cost can be reduced by adopting few automation testing techniques, which can be embedded against the project tasks deliverables and thus total time and cost for verification, testing and documentation can be reduced up to 28%  If the mechanical part modification process can be optimized, the overall cost incurred against the corresponding task can be reduced to 20%. This can be achieved by buying the respective parts from Quality of Service based supplier or vendor.  Cost incurred for Software development can also be reduced by outsourcing few of the modules or purchasing the existing popular web services in the respective fields. This approach will reduce the budget allocated against Software development to 15-25%.  Agile and Scrum based project management can be adopted over the current proposal of product development and thus the overall project budget can be reduced further to 30% by avoiding rework on the respective deliverables or testing or documentation. 6. Approach for better project management strategies Based on the project management plan, Gantt chart, resource allocation, budgeting and time schedules prepared against the proposed project development, it is clear that each and every project activity is given ample priority and was allocated with required number of resources and budget. Apart from the current project management strategies applied and stimulated, there is scope to improve the respective strategies and few of them are as listed below  The project management plan prepared in the current case is purely based on prototype, Rapid application development and waterfall methods. With these approaches the risk of maintenance issues and design mismatch are high irrespective to the quality measures considered. Thus the respective process can be improved by adopting the Agile project management framework
  • 12. 12 | P a g e  From the current project management plan associated with the product development, it is observed that, lot of attention is given towards the milestone activities and production activities. In future 4 to 5 Prototype builds can be released using regular scrum patterns of Agile Project management strategies and thus the quality of the product development and project management can be further enhanced. 7. Better quality in product development Utter most care is taken in the current context to deliver the milestones and project activities. Still there is scope to deliver better quality in terms of project management and product development and few of the important points are given below after a detailed review of the current project plan developed
  • 13. 13 | P a g e  Design, Development and Implementation of the Software modules or activities can be outsourced or purchased in the form of web services, such that over time will be saved and better Software quality is ensued  Production of few electronic and mechanical components can also be improved in terms of quality by engaging Quality and Test engineers, where the traditional approaches of testing and bug fixing can be replaced with latest automated testing tools like Selenium.  Entire project management strategies adopted currently can be replaced by sophisticated techniques of Agile and SCRUM framework, such that better quality is possible in product development and milestone deliverables as well. #SystemDesignAssignmentHelp #NetworkDesignAssignmentHelp #CyberSecurityAssignment #AssignmentHelp #MSPROJECTASSIGNMENTHELP #ManagementAssignmentHelp #AssignmentsHelp #ProjectsHelp #HomeworkHelp #DissertationsHelp #ThesisHelp #AcademicAvenue #AcademicsHelp #FrustratedWithAssignments #MarketingAssignmentHelp
  • 14. 14 | P a g e #ResearchProposalHelp #CaseStudyHelp #ResearchReportHelp #SurveyHelp