SlideShare a Scribd company logo
Question bank for Energy Managers & Energy Auditors
Chapter 1.7 Project Management
Part – I: Objective type questions and answers
1. Project financing is one of the step of project management- State True or False
2. Proposed new technologies, process modifications, equipment replacements are the
elements of
a) Financing b) contracting c) technical design d) Implementation
3. The term ‘energy services contract’ in a project comes under
a) Financing b) contracting c) monitoring d) evaluation
4. The contractor providing financing and is paid an agreed fraction of actual savings as
they are achieved is called
a) Traditional contract b) Extended financing terms
c) Shared savings performance contract d) energy service contract
5. The contract in which project specifications are provided to a contractor who procures
and installs equipment at cost plus a mark-up or fixed price is called
a) Extended Financing terms b) guaranteed saving performance contract
c) shared saving performance contract d) Traditional contract
6. The technique used for scheduling the tasks and tracking of the progress of energy
management projects is called
a) CPM b) Gantt chart
c) CUSUM d) PERT
7. CPM predicts the time required to complete the project— State True or False
8. The time between its earliest and latest start time, or between its earliest and latest
finish time of an activity is
a) delay time b) slack time c) critical path d) start time
9. The path through the project network in which none of the activities have slack is called
a) start time b) slack time c) critical path d) delay time
10. CPM provides the following benefits
a) graphical view of the project
b) inter-relationship among various tasks
c) Predicts time required to complete the project
d) all the above
1.7 Project management - revised (table format) 50
Question bank for Energy Managers & Energy Auditors
11. Which of the following statements about critical path analysis (CPA) is true?
a) The critical path is the longest path through the network
b) The critical path is the shortest path through the network
c) Tasks with float will never become critical
d) The network should remain constant throughout the project
12. Project management technique which uses three time estimates-optimistic, pessimistic
and most likely, which help in establishing the probability of completing a project within
a specified time and take calculated risk before commencing a project is---------.
(a) PERT (b) CUSUM (c) CPM (d) none of the above
13. The network model that allows for randomness in activity completion times is called
(a) CUSUM (b) CPM (c) PERT (d) Gantt chart
14. The technique which suggests corrective action to be taken in the light of actual
performance is --------
(a) CUSUM (b) PERT (c) Performance monitoring (d) none of the above
15. Performance is done after implementation. State True or false
16. An effective way of communicating a projects benefit usually as a part of a performance
measuring and reporting process is termed as.
(a) Performance indicator (b) CPM (c) PERT (d) Gantt chart
17. In project management system, Critical Path Method CPM) allows for randomness
activity completion time deterministic method while Programme Evaluation Review
Technique (PERT) uses fixed time estimate for each activity. State True or False.
18. In Critical Path of CPM used in project planning techniques indicates _____ .
a) time require for the completion of the project
b) delays in the project
c) early start and late end of the project
d) none of the above
19. Which of the following does not belongs to project planning technique?
a) CPM b) PERT
c) Gantt chart d) IRR (internal rate of return)
20. Formal project Close Out is necessary:
a) On medium to large projects only b) On all projects
c) Only if a project has been terminated early d) As part of Post Project Appraisal
Part – II: Short type questions and answers
1. Define the term ‘project’.
A project is a one-shot, time limited, goal directed, major undertaking requiring the
commitment of varied skills and resources.
1.7 Project management - revised (table format) 51
Question bank for Energy Managers & Energy Auditors
2. List various steps in project management.
The various steps in project management are:
a) Project definition and scope
b) Technical design
c) Financing
d) Contracting
e) Implementation
f) Performance monitoring
3. List the external source of funds during financing stage in project management.
External sources of funds include:
Bank loans
Leasing arrangement
Payment by savings ( a deal arranged with equipment supplier)
Energy services contract
Private finance initiatives
4. List the elements to be considered during technical design of a project management.
a) Proposed new technologies, process modifications, equipment replacement and
other measures included in the project.
b) Product / technology / material supply chain (sourcing of vender from domestic or
international with reliability of supply)
c) Commercial viability of the complete measures (IRR, NPV, etc.)
d) Special technical complexes (installation, maintenance, repair), associated skills
required.
e) Preliminary designs, including schematics along with design requirements,
manufacturer name and contact details and capital cost estimates.
f) Organisational and management plan for implementation including time table,
personal requirements, staff training, project engineering and other logistical issues.
5. While screening the projects, list the criteria used to rank-order project opportunities.
a) Cost effectiveness of energy savings of complete package of measures (IRR, NPC,
Cash flow, payback period)
b) Sustainability of savings over life of the equipment
c) Ease of quantification, monitoring and verifying electricity and fuel savings
d) Availability of technology and ease in adoptability to Indian condition.
e) Other environmental and social benefits (such as reduction in emissions and
pollutants)
1.7 Project management - revised (table format) 52
Question bank for Energy Managers & Energy Auditors
6. What are the different types of contracts involved in project management system.
Traditional contract
Extended technical guarantee/service
Extended financing terms
Guaranteed savings performance contract
Shared savings performance contract
7. Briefly explain guaranteed saving performance contract.
Guaranteed Saving Performance Contract is a contract, where all or part of savings is
guaranteed by the contractor, and all or part of the costs of equipment and/or services is
paid down out of savings as they are achieved.
8. Briefly explain shared saving performance contract.
Shared Savings Performance Contract is the contractor, which provides the financing
and is paid an agreed fraction of actual savings as they are achieved. This payment is
used to pay down the debt costs of equipment and/or services.
9. List guidelines used during implementation stage of projects?
Limit long lead times
Manage out-of-pocket development by focusing efforts
Manage project carefully
10. List the main points that are most important to a successful project
a) A project must meet customer requirements
b) A project must be under budget
c) A project must be on time
11. List the steps involved in CPM project planning?
Steps in CPM Project Planning
1. Specify the individual activities.
2. Determine the sequence/interrelationships of those activities.
3. Draw a network diagram.
4. Estimate the completion time for each activity.
5. Identify the critical path (longest path through the network)
6. Update the CPM diagram as the project progresses.
12. What are the benefits of CPM.
CPM provides the following benefits:
Provides a graphical view of the project.
Depicts the interrelationships among various tasks/activities
Predicts the time required to complete the project.
Shows which activities are critical to maintaining the schedule and which are not.
1.7 Project management - revised (table format) 53
Question bank for Energy Managers & Energy Auditors
13. Define briefly PERT
The Program Evaluation and Review Technique (PERT) is a network model that allows
for randomness in activity completion times. PERT uses three time estimates-optimistic,
pessimistic and most likely, which help in establishing the probability of completing a
project within a specified time and take calculated risk before commencing a project. It
has the potential to reduce both the time and cost required to complete a project.
14. What are the different steps involved in PERT planning?
PERT planning involves the following steps:
1. Identify the specific activities and milestones.
2. Determine the interdependencies and proper sequence of the activities.
3. Construct a network diagram.
4. Estimate the time(three time estimates, if probabilities are to be computed)
required for each activity.
5. Determine the critical path.
6. Update the PERT chart as the project progresses.
15. What are the benefits of PERT.
PERT is useful because it provides the following information:
• Expected project completion time.
• Probability of completion before a specified date.
• The critical path activities that directly impact the completion time.
• The activities that have slack time and that can lend resources to critical path
activities.
• Activity starts and end dates.
16. How performance monitoring in project management is useful? List the benefits.
Once the project is completed performance review should be done periodically to
compare actual performance with projected performance. A feedback device, it is useful
in several ways:
a) It throws light on how realistic were the assumptions underlying the project
b) It provides a documented log of experience that is highly valuable in future decision
making
c) It suggests corrective action to be taken in the light of actual performance
d) It helps in uncovering judgmental biases
e) It includes a desired caution among project sponsors.
17. List the project planning techniques used in project management.
Gantt chart, Critical path method (CPM), Programme evaluation review techniques
(PERT).
1.7 Project management - revised (table format) 54
Question bank for Energy Managers & Energy Auditors
18. What is slack time in critical path in CPM?
The slack time for an activity is the time between its earliest and latest start time, or
between its earliest and latest finish time. Slack is the amount of time that an activity can
be delayed past its earliest start or earliest finish without delaying the project.
19. List the internal source of funds during financing stage in project management.
Internal sources of fund include:
Direct cash provision from company reserves
From the revenue budget (if pay back period is very attractive and less than a year)
New share capital
20. Explain the need for measurement and verification in a project management system
Facility energy savings are determined by comparing the energy use before and after the
installation of energy conservation measures. The “before” case is called the baseline; the
“after” case is referred to as the post-installation or performance period. Proper
determination of savings includes adjusting for changes that affect energy use but that
are not caused by the conservation measures. Such adjustments may account for
differences in capacity utilization, raw material quality, product mix and other
parameters, between the baseline and performance periods.
In general,
Savings = (Baseline Energy use) adjusted –Post-installation Energy use
For example in a paper mill a variety of products depending on thickness (Grams per
Square meter) are made. If energy consumption is evaluated as kCals or kWh per tonne
of paper the figures could be misleading. Under these circumstances the measurement
and verification system is to be designed accounting for these variations
Part – III Long type questions and answers
1. Briefly explain steps in project management.
a) Project definition and scope: The first step in project development cycle is to identify
components of the project. Projects may be identified both internally and externally.
Next screening of the projects is used to rank older project opportunities.
b) Technical design: Once project makes its part the screening process, the hard work of
developing technical specification begins. For a project to be considered a viable
investment, its proponent must present a sound technical feasibility.
c) Financing: The funding for a project is often outside the control of the project
manager. However, it is important that one should understand the principles behind
the provision of scarce funds. Project funds can be obtained from either internal or
external sources.
d) Contracting: Substantial portion of a project is typically executed through contracts,
the proper management of contracts is critical to the successful implementation of a
project. If the project is to be implemented by an outside contractor several types of
contracts may be used to undertake the installation and commissioning.
e) Implementation: Implementation stage involves the execution of project as agreed
whilst carefully monitoring the progress and managing changes. On energy efficiency
projects the main issues are technology selection risk, the overall risk sharing criteria
is the installation contract, structure and relationship with sub-contractors and
enforcing penalties among parties.
f) Project monitoring techniques: there are variety of basic planning and monitoring
1.7 Project management - revised (table format) 55
Question bank for Energy Managers & Energy Auditors
techniques. All monitor progress and costs against resource budgets. Some of them
are Gantt charts, CPM (critical path method), program evaluation and review
techniques.
2. What are the several types of contracts used in project management and explain in brief?
Traditional Contract: All project specifications are provided to a contractor who
procures and installs equipment at cost plus a mark-up or fixed price.
Extended Technical Guarantee/Service: The contract offers extended
guarantees on the performance of selected equipment, and/or offers
service/maintenance agreements.
Extended Financing Terms: The contractor provides the option of an extended
lease or other financing vehicle in which the payment schedule can be based on the
expected savings.
Guaranteed Saving Performance Contract: All or part of savings is guaranteed
by the contractor, and all or part of the costs of equipment and/or services is paid
down out of savings as they are achieved.
Shared Savings Performance Contract: The contractor provides the financing
and is paid an agreed fraction of actual savings as they are achieved. This payment is
used to pay down the debt costs of equipment and/or services.
3. How critical path can be identified in CPM?
The critical path can be identified by determining the following four parameters for each
of the activity:
• ES - earliest start time: the earliest time at which the activity can start given that its
precedent activities must be completed first.
• EF - earliest finish time, equal to the earliest start time for the activity plus the time
required to complete the activity.
• LF - latest finish time: the latest time at which the activity can be completed without
delaying the project.
• LS - latest start time, equal to the latest finish time minus the time required to
complete the activity.
The slack time for an activity is the time between its earliest and latest start time, or
between its earliest and latest finish time. Slack is the amount of time that an activity can
be delayed past its earliest start or earliest finish without delaying the project. The critical
path is the path through the project network in which none of the activities have slack,
that is, the path for which ES=LS and EF=LF for all activities in the path.
4. What is CPM and list the steps in CPM project planning?
CPM models the activities and events of a project as a network. Activities are depicted as
nodes on the network and events that signify the beginning or ending of activities are
depicted as arcs or lines between the nodes. The following is an example of a CPM
network diagram.
1.7 Project management - revised (table format) 56
Question bank for Energy Managers & Energy Auditors
Steps in CPM Project Planning
1. Specify the individual activities.
2. Determine the sequence/interrelationships of those activities.
3. Draw a network diagram.
4. Estimate the completion time for each activity.
5. Identify the critical path (longest path through the network)
6. Update the CPM diagram as the project progresses.
5. Explain and draw a typical Gantt chart
Gantt chart (named after the inventor) or bar charts are used to scheduling the tasks and
tracking of the process of energy management projects. Gantt scheduling tool takes the
form of a horizontal bar graph on a time schedule.
Task Duration 1
week
2
week
3
week
4
week
5
week
6
week
7
week
1. Preliminary audit and report 1 week
2. Identification of external
consultants and obtaining the
proposals
2 weeks
3. Selection of auditor and
awarding contract
1 week
4. Detailed energy audit , field
study & report preparation
4 weeks
The horizontal axis of the Gantt chart is a time scale either in absolute time or in relative
time. Rows of bars in the chart show the beginning and ending dates of individual tasks
in the project. In some cases bars/activities may overlap, where several activities can be
performed in parallel. In such cases Gantt chart is quite useful for communicating the
timings of the various tasks.
For larger projects, the tasks can be broken into sub tasks having their own Gantt charts
to maintain readability and provide easy monitoring.
1.7 Project management - revised (table format) 57

More Related Content

What's hot

Project Management The Managerial Process 5th Edition Larson Solutions Manual
Project Management The Managerial Process 5th Edition Larson Solutions ManualProject Management The Managerial Process 5th Edition Larson Solutions Manual
Project Management The Managerial Process 5th Edition Larson Solutions Manual
Kemppe
 
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET Journal
 
Capm time 150 question final key
Capm time 150 question final keyCapm time 150 question final key
Capm time 150 question final key
University High School - Fresno
 
Outage planning
Outage planningOutage planning
Economics of project evaluation cpm module2
Economics of project evaluation cpm module2Economics of project evaluation cpm module2
Economics of project evaluation cpm module2
ahsanrabbani
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Scope creep - cylfe campain
Scope creep - cylfe campainScope creep - cylfe campain
Scope creep - cylfe campain
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Methodologies of Project Progress Measurement
Methodologies of Project Progress MeasurementMethodologies of Project Progress Measurement
Methodologies of Project Progress Measurement
Amit Kumar Senapati, PMP®
 
Project Management
Project ManagementProject Management
Project Management
Gabriel Barina
 
Day 2 1135 - 1220 - maple - paramita mukerji
Day 2   1135 - 1220  - maple - paramita mukerjiDay 2   1135 - 1220  - maple - paramita mukerji
Day 2 1135 - 1220 - maple - paramita mukerjiPMI2011
 
Delay Disruption & EOT Flyer
Delay Disruption & EOT FlyerDelay Disruption & EOT Flyer
Delay Disruption & EOT FlyerGarry Macdonald
 
Lecture 6
Lecture 6Lecture 6
Lecture 6
Yasir Khan
 
Engineering design process 3rd edition haik solutions manual
Engineering design process 3rd edition haik solutions manualEngineering design process 3rd edition haik solutions manual
Engineering design process 3rd edition haik solutions manual
SummerfieldTBL
 
Project management
Project managementProject management
Project management
Rohit Mishra
 
asdfds
asdfdsasdfds
asdfds
fkdnld1
 
Jerry Beste Resume_04.2015
Jerry Beste Resume_04.2015Jerry Beste Resume_04.2015
Jerry Beste Resume_04.2015Jerry Beste
 
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET Journal
 

What's hot (19)

Project Management The Managerial Process 5th Edition Larson Solutions Manual
Project Management The Managerial Process 5th Edition Larson Solutions ManualProject Management The Managerial Process 5th Edition Larson Solutions Manual
Project Management The Managerial Process 5th Edition Larson Solutions Manual
 
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
 
Capm time 150 question final key
Capm time 150 question final keyCapm time 150 question final key
Capm time 150 question final key
 
SE chapters 24-25
SE chapters 24-25SE chapters 24-25
SE chapters 24-25
 
Outage planning
Outage planningOutage planning
Outage planning
 
Economics of project evaluation cpm module2
Economics of project evaluation cpm module2Economics of project evaluation cpm module2
Economics of project evaluation cpm module2
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
Scope creep - cylfe campain
Scope creep - cylfe campainScope creep - cylfe campain
Scope creep - cylfe campain
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Methodologies of Project Progress Measurement
Methodologies of Project Progress MeasurementMethodologies of Project Progress Measurement
Methodologies of Project Progress Measurement
 
Project Management
Project ManagementProject Management
Project Management
 
Day 2 1135 - 1220 - maple - paramita mukerji
Day 2   1135 - 1220  - maple - paramita mukerjiDay 2   1135 - 1220  - maple - paramita mukerji
Day 2 1135 - 1220 - maple - paramita mukerji
 
Delay Disruption & EOT Flyer
Delay Disruption & EOT FlyerDelay Disruption & EOT Flyer
Delay Disruption & EOT Flyer
 
Lecture 6
Lecture 6Lecture 6
Lecture 6
 
Engineering design process 3rd edition haik solutions manual
Engineering design process 3rd edition haik solutions manualEngineering design process 3rd edition haik solutions manual
Engineering design process 3rd edition haik solutions manual
 
Project management
Project managementProject management
Project management
 
asdfds
asdfdsasdfds
asdfds
 
Jerry Beste Resume_04.2015
Jerry Beste Resume_04.2015Jerry Beste Resume_04.2015
Jerry Beste Resume_04.2015
 
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
 

Similar to 1.2 project management by bee 2

45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
TinotendaChivese
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
pisal3
 
Time Cost Trade Off
Time Cost Trade OffTime Cost Trade Off
Time Cost Trade Off
ssuserfe1b72
 
MGT-Ch07.ppt
MGT-Ch07.pptMGT-Ch07.ppt
MGT-Ch07.ppt
MarkNaguibElAbd
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docx
alfred4lewis58146
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniquesguestc8140fe
 
H1303055462
H1303055462H1303055462
H1303055462
IOSR Journals
 
Chapter 5-Project Management.pptx
Chapter 5-Project Management.pptxChapter 5-Project Management.pptx
Chapter 5-Project Management.pptx
BahredinAbdella1
 
A partial results from a PERT analysis for a project with 50 activit.pdf
A partial results from a PERT analysis for a project with 50 activit.pdfA partial results from a PERT analysis for a project with 50 activit.pdf
A partial results from a PERT analysis for a project with 50 activit.pdf
rozakashif85
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
SydneyJaydeanKhanyil
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
BetshaTizazu2
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
Anupama holla
 
Ijmet 09 11_006
Ijmet 09 11_006Ijmet 09 11_006
Ijmet 09 11_006
IAEME Publication
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptx
MdSabujHossen2
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptx
MdSabujHossen2
 
Planning And Scheduling Construction For Decades
Planning And Scheduling Construction For DecadesPlanning And Scheduling Construction For Decades
Planning And Scheduling Construction For Decades
Beth Hall
 
1.7 project management
1.7 project management1.7 project management
1.7 project management
exemplar2401
 
1-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp011-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp01
Amy Roman
 
Pert, cpm & gert
Pert, cpm & gertPert, cpm & gert
Pert, cpm & gert
Pranav Krishna
 

Similar to 1.2 project management by bee 2 (20)

45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
 
Time Cost Trade Off
Time Cost Trade OffTime Cost Trade Off
Time Cost Trade Off
 
MGT-Ch07.ppt
MGT-Ch07.pptMGT-Ch07.ppt
MGT-Ch07.ppt
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docx
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniques
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
 
H1303055462
H1303055462H1303055462
H1303055462
 
Chapter 5-Project Management.pptx
Chapter 5-Project Management.pptxChapter 5-Project Management.pptx
Chapter 5-Project Management.pptx
 
A partial results from a PERT analysis for a project with 50 activit.pdf
A partial results from a PERT analysis for a project with 50 activit.pdfA partial results from a PERT analysis for a project with 50 activit.pdf
A partial results from a PERT analysis for a project with 50 activit.pdf
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Ijmet 09 11_006
Ijmet 09 11_006Ijmet 09 11_006
Ijmet 09 11_006
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptx
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptx
 
Planning And Scheduling Construction For Decades
Planning And Scheduling Construction For DecadesPlanning And Scheduling Construction For Decades
Planning And Scheduling Construction For Decades
 
1.7 project management
1.7 project management1.7 project management
1.7 project management
 
1-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp011-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp01
 
Pert, cpm & gert
Pert, cpm & gertPert, cpm & gert
Pert, cpm & gert
 

Recently uploaded

DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 

Recently uploaded (20)

DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 

1.2 project management by bee 2

  • 1. Question bank for Energy Managers & Energy Auditors Chapter 1.7 Project Management Part – I: Objective type questions and answers 1. Project financing is one of the step of project management- State True or False 2. Proposed new technologies, process modifications, equipment replacements are the elements of a) Financing b) contracting c) technical design d) Implementation 3. The term ‘energy services contract’ in a project comes under a) Financing b) contracting c) monitoring d) evaluation 4. The contractor providing financing and is paid an agreed fraction of actual savings as they are achieved is called a) Traditional contract b) Extended financing terms c) Shared savings performance contract d) energy service contract 5. The contract in which project specifications are provided to a contractor who procures and installs equipment at cost plus a mark-up or fixed price is called a) Extended Financing terms b) guaranteed saving performance contract c) shared saving performance contract d) Traditional contract 6. The technique used for scheduling the tasks and tracking of the progress of energy management projects is called a) CPM b) Gantt chart c) CUSUM d) PERT 7. CPM predicts the time required to complete the project— State True or False 8. The time between its earliest and latest start time, or between its earliest and latest finish time of an activity is a) delay time b) slack time c) critical path d) start time 9. The path through the project network in which none of the activities have slack is called a) start time b) slack time c) critical path d) delay time 10. CPM provides the following benefits a) graphical view of the project b) inter-relationship among various tasks c) Predicts time required to complete the project d) all the above 1.7 Project management - revised (table format) 50
  • 2. Question bank for Energy Managers & Energy Auditors 11. Which of the following statements about critical path analysis (CPA) is true? a) The critical path is the longest path through the network b) The critical path is the shortest path through the network c) Tasks with float will never become critical d) The network should remain constant throughout the project 12. Project management technique which uses three time estimates-optimistic, pessimistic and most likely, which help in establishing the probability of completing a project within a specified time and take calculated risk before commencing a project is---------. (a) PERT (b) CUSUM (c) CPM (d) none of the above 13. The network model that allows for randomness in activity completion times is called (a) CUSUM (b) CPM (c) PERT (d) Gantt chart 14. The technique which suggests corrective action to be taken in the light of actual performance is -------- (a) CUSUM (b) PERT (c) Performance monitoring (d) none of the above 15. Performance is done after implementation. State True or false 16. An effective way of communicating a projects benefit usually as a part of a performance measuring and reporting process is termed as. (a) Performance indicator (b) CPM (c) PERT (d) Gantt chart 17. In project management system, Critical Path Method CPM) allows for randomness activity completion time deterministic method while Programme Evaluation Review Technique (PERT) uses fixed time estimate for each activity. State True or False. 18. In Critical Path of CPM used in project planning techniques indicates _____ . a) time require for the completion of the project b) delays in the project c) early start and late end of the project d) none of the above 19. Which of the following does not belongs to project planning technique? a) CPM b) PERT c) Gantt chart d) IRR (internal rate of return) 20. Formal project Close Out is necessary: a) On medium to large projects only b) On all projects c) Only if a project has been terminated early d) As part of Post Project Appraisal Part – II: Short type questions and answers 1. Define the term ‘project’. A project is a one-shot, time limited, goal directed, major undertaking requiring the commitment of varied skills and resources. 1.7 Project management - revised (table format) 51
  • 3. Question bank for Energy Managers & Energy Auditors 2. List various steps in project management. The various steps in project management are: a) Project definition and scope b) Technical design c) Financing d) Contracting e) Implementation f) Performance monitoring 3. List the external source of funds during financing stage in project management. External sources of funds include: Bank loans Leasing arrangement Payment by savings ( a deal arranged with equipment supplier) Energy services contract Private finance initiatives 4. List the elements to be considered during technical design of a project management. a) Proposed new technologies, process modifications, equipment replacement and other measures included in the project. b) Product / technology / material supply chain (sourcing of vender from domestic or international with reliability of supply) c) Commercial viability of the complete measures (IRR, NPV, etc.) d) Special technical complexes (installation, maintenance, repair), associated skills required. e) Preliminary designs, including schematics along with design requirements, manufacturer name and contact details and capital cost estimates. f) Organisational and management plan for implementation including time table, personal requirements, staff training, project engineering and other logistical issues. 5. While screening the projects, list the criteria used to rank-order project opportunities. a) Cost effectiveness of energy savings of complete package of measures (IRR, NPC, Cash flow, payback period) b) Sustainability of savings over life of the equipment c) Ease of quantification, monitoring and verifying electricity and fuel savings d) Availability of technology and ease in adoptability to Indian condition. e) Other environmental and social benefits (such as reduction in emissions and pollutants) 1.7 Project management - revised (table format) 52
  • 4. Question bank for Energy Managers & Energy Auditors 6. What are the different types of contracts involved in project management system. Traditional contract Extended technical guarantee/service Extended financing terms Guaranteed savings performance contract Shared savings performance contract 7. Briefly explain guaranteed saving performance contract. Guaranteed Saving Performance Contract is a contract, where all or part of savings is guaranteed by the contractor, and all or part of the costs of equipment and/or services is paid down out of savings as they are achieved. 8. Briefly explain shared saving performance contract. Shared Savings Performance Contract is the contractor, which provides the financing and is paid an agreed fraction of actual savings as they are achieved. This payment is used to pay down the debt costs of equipment and/or services. 9. List guidelines used during implementation stage of projects? Limit long lead times Manage out-of-pocket development by focusing efforts Manage project carefully 10. List the main points that are most important to a successful project a) A project must meet customer requirements b) A project must be under budget c) A project must be on time 11. List the steps involved in CPM project planning? Steps in CPM Project Planning 1. Specify the individual activities. 2. Determine the sequence/interrelationships of those activities. 3. Draw a network diagram. 4. Estimate the completion time for each activity. 5. Identify the critical path (longest path through the network) 6. Update the CPM diagram as the project progresses. 12. What are the benefits of CPM. CPM provides the following benefits: Provides a graphical view of the project. Depicts the interrelationships among various tasks/activities Predicts the time required to complete the project. Shows which activities are critical to maintaining the schedule and which are not. 1.7 Project management - revised (table format) 53
  • 5. Question bank for Energy Managers & Energy Auditors 13. Define briefly PERT The Program Evaluation and Review Technique (PERT) is a network model that allows for randomness in activity completion times. PERT uses three time estimates-optimistic, pessimistic and most likely, which help in establishing the probability of completing a project within a specified time and take calculated risk before commencing a project. It has the potential to reduce both the time and cost required to complete a project. 14. What are the different steps involved in PERT planning? PERT planning involves the following steps: 1. Identify the specific activities and milestones. 2. Determine the interdependencies and proper sequence of the activities. 3. Construct a network diagram. 4. Estimate the time(three time estimates, if probabilities are to be computed) required for each activity. 5. Determine the critical path. 6. Update the PERT chart as the project progresses. 15. What are the benefits of PERT. PERT is useful because it provides the following information: • Expected project completion time. • Probability of completion before a specified date. • The critical path activities that directly impact the completion time. • The activities that have slack time and that can lend resources to critical path activities. • Activity starts and end dates. 16. How performance monitoring in project management is useful? List the benefits. Once the project is completed performance review should be done periodically to compare actual performance with projected performance. A feedback device, it is useful in several ways: a) It throws light on how realistic were the assumptions underlying the project b) It provides a documented log of experience that is highly valuable in future decision making c) It suggests corrective action to be taken in the light of actual performance d) It helps in uncovering judgmental biases e) It includes a desired caution among project sponsors. 17. List the project planning techniques used in project management. Gantt chart, Critical path method (CPM), Programme evaluation review techniques (PERT). 1.7 Project management - revised (table format) 54
  • 6. Question bank for Energy Managers & Energy Auditors 18. What is slack time in critical path in CPM? The slack time for an activity is the time between its earliest and latest start time, or between its earliest and latest finish time. Slack is the amount of time that an activity can be delayed past its earliest start or earliest finish without delaying the project. 19. List the internal source of funds during financing stage in project management. Internal sources of fund include: Direct cash provision from company reserves From the revenue budget (if pay back period is very attractive and less than a year) New share capital 20. Explain the need for measurement and verification in a project management system Facility energy savings are determined by comparing the energy use before and after the installation of energy conservation measures. The “before” case is called the baseline; the “after” case is referred to as the post-installation or performance period. Proper determination of savings includes adjusting for changes that affect energy use but that are not caused by the conservation measures. Such adjustments may account for differences in capacity utilization, raw material quality, product mix and other parameters, between the baseline and performance periods. In general, Savings = (Baseline Energy use) adjusted –Post-installation Energy use For example in a paper mill a variety of products depending on thickness (Grams per Square meter) are made. If energy consumption is evaluated as kCals or kWh per tonne of paper the figures could be misleading. Under these circumstances the measurement and verification system is to be designed accounting for these variations Part – III Long type questions and answers 1. Briefly explain steps in project management. a) Project definition and scope: The first step in project development cycle is to identify components of the project. Projects may be identified both internally and externally. Next screening of the projects is used to rank older project opportunities. b) Technical design: Once project makes its part the screening process, the hard work of developing technical specification begins. For a project to be considered a viable investment, its proponent must present a sound technical feasibility. c) Financing: The funding for a project is often outside the control of the project manager. However, it is important that one should understand the principles behind the provision of scarce funds. Project funds can be obtained from either internal or external sources. d) Contracting: Substantial portion of a project is typically executed through contracts, the proper management of contracts is critical to the successful implementation of a project. If the project is to be implemented by an outside contractor several types of contracts may be used to undertake the installation and commissioning. e) Implementation: Implementation stage involves the execution of project as agreed whilst carefully monitoring the progress and managing changes. On energy efficiency projects the main issues are technology selection risk, the overall risk sharing criteria is the installation contract, structure and relationship with sub-contractors and enforcing penalties among parties. f) Project monitoring techniques: there are variety of basic planning and monitoring 1.7 Project management - revised (table format) 55
  • 7. Question bank for Energy Managers & Energy Auditors techniques. All monitor progress and costs against resource budgets. Some of them are Gantt charts, CPM (critical path method), program evaluation and review techniques. 2. What are the several types of contracts used in project management and explain in brief? Traditional Contract: All project specifications are provided to a contractor who procures and installs equipment at cost plus a mark-up or fixed price. Extended Technical Guarantee/Service: The contract offers extended guarantees on the performance of selected equipment, and/or offers service/maintenance agreements. Extended Financing Terms: The contractor provides the option of an extended lease or other financing vehicle in which the payment schedule can be based on the expected savings. Guaranteed Saving Performance Contract: All or part of savings is guaranteed by the contractor, and all or part of the costs of equipment and/or services is paid down out of savings as they are achieved. Shared Savings Performance Contract: The contractor provides the financing and is paid an agreed fraction of actual savings as they are achieved. This payment is used to pay down the debt costs of equipment and/or services. 3. How critical path can be identified in CPM? The critical path can be identified by determining the following four parameters for each of the activity: • ES - earliest start time: the earliest time at which the activity can start given that its precedent activities must be completed first. • EF - earliest finish time, equal to the earliest start time for the activity plus the time required to complete the activity. • LF - latest finish time: the latest time at which the activity can be completed without delaying the project. • LS - latest start time, equal to the latest finish time minus the time required to complete the activity. The slack time for an activity is the time between its earliest and latest start time, or between its earliest and latest finish time. Slack is the amount of time that an activity can be delayed past its earliest start or earliest finish without delaying the project. The critical path is the path through the project network in which none of the activities have slack, that is, the path for which ES=LS and EF=LF for all activities in the path. 4. What is CPM and list the steps in CPM project planning? CPM models the activities and events of a project as a network. Activities are depicted as nodes on the network and events that signify the beginning or ending of activities are depicted as arcs or lines between the nodes. The following is an example of a CPM network diagram. 1.7 Project management - revised (table format) 56
  • 8. Question bank for Energy Managers & Energy Auditors Steps in CPM Project Planning 1. Specify the individual activities. 2. Determine the sequence/interrelationships of those activities. 3. Draw a network diagram. 4. Estimate the completion time for each activity. 5. Identify the critical path (longest path through the network) 6. Update the CPM diagram as the project progresses. 5. Explain and draw a typical Gantt chart Gantt chart (named after the inventor) or bar charts are used to scheduling the tasks and tracking of the process of energy management projects. Gantt scheduling tool takes the form of a horizontal bar graph on a time schedule. Task Duration 1 week 2 week 3 week 4 week 5 week 6 week 7 week 1. Preliminary audit and report 1 week 2. Identification of external consultants and obtaining the proposals 2 weeks 3. Selection of auditor and awarding contract 1 week 4. Detailed energy audit , field study & report preparation 4 weeks The horizontal axis of the Gantt chart is a time scale either in absolute time or in relative time. Rows of bars in the chart show the beginning and ending dates of individual tasks in the project. In some cases bars/activities may overlap, where several activities can be performed in parallel. In such cases Gantt chart is quite useful for communicating the timings of the various tasks. For larger projects, the tasks can be broken into sub tasks having their own Gantt charts to maintain readability and provide easy monitoring. 1.7 Project management - revised (table format) 57