SlideShare a Scribd company logo
Case Study-3
Pittsburgh Airport: Midfield Terminal Energy Facility
(Area of discussion- Cost & Quality)
Team
Members:
Case Study – 5
Outline of projectBackground
 The Pittsburgh International Airport is owned and operated by the
Allegheny County Department of Aviation.
 The new Midfield Terminal includes,
Landside/central services bldg - 500,000 sft
Airside building - 1,200,000 sft
Gate capacity - 75 aircraft
Provisions to expand - 100 gate terminal.
 Pittsburg is the second busiest passenger airport in Pennsylvania and
47th-busiest in the United States, serving 8,041,357 passengers in
2012.
Outline of projectBackground
 The airport has the longest runways of a commercial airport in
Pennsylvania at 11,500 feet (3,500 m).
 Until 2004 US Airways largest hub was at PIT.
 PIT occupies more than 12,900 acres (52 km2), making it the fourth-
largest airport by land area owned in the nation.
 The Midfield Terminal Energy Facility was designed to meet the
requirement as:
 Ultimate cooling load of 9,100 tons
 Ultimate heating load of 113 x 106 Btuh
Outline of projectOut Line of Project
 The energy facility also provides electric power to the Midfield
Terminal from the new substation located between the energy facility
and the field-erected concrete cooling tower.
 Completion – 6 weeks ahead of schedule and within budgeted cost.
Outline of project ???
Cost Quality
Outline of projectScope Management
Well defined scope and explicitly
required quality removes building up
of cost contingencies for unknowns
by the executers in turn reduction of
in Cost.
Outline of projectScope Management
Outline of projectTime Management
Realistic
Cost
Scope with
Complete details
Project Completion Time
Outline of projectTime Management
Realistic Project Schedule
All contingencies properly
factored in to the Schedule.
Getting Realistic Input By
allowing more cost on
engineering.
Outline of projectTime Management
Performance Review
Variance Analysis
Resource leveling
What if Analysis
After negotiating the Realistic Engineering and Construction
Budget, The Job was to focus on Schedule regress monitoring of
schedule with following control tools
Outline of projectTime Management
The Start up testing was delayed due to
non controllable issues
Contingencies were taken for preparing
Realistic Schedule
Project was completed Six Weeks of
Ahead of Schedule
Outline of projectCost Management
Key Inputs available General Tools and Techniques Outputs/advantages
Cost Estimation and Budgeting
Very clear project scope
statement
Detailed conceptual engineering
Analysis
Detailed Drawings and
specification with high degree of
accuracy.
Complete project schedule
Project Management software's
Resource (Man, material,
machine) plan
Over Head ratio and Staff
performance analysis
Tax planning
Realistic budget cost without any
contingencies
Cost Management Plan
Cost Control
Cost Base line. Realistic budgeted
cost
Detailed project schedule
Project Management Plan
Periodical Performance review
Productivity Monitoring
Variance analysis
Project completed within the
budget
Due to owners commitment, realistic scheduling , optimum equipment selection, detailed bid
documents and specs, project was completed under budget.
Outline of projectQuality Management
Key Inputs available General Tools and Techniques Outputs/advantages
Quality Planning
Detailed Scope statement
prepared
Detailed Engineering details/specs
Very clear project objective
Budget analysis
Standards of Measurement of
performance
Process Flow charts
Quality Management plan to
implement the quality policy/
Objective.
Quality Assurance /control
Reliable equipment systems are
selected.
Proper technical persons are
deployed
Detailed Activity schedule
Quality Audits
Third Party tests
Training for staffs and workmen
Inspection of material and
products
Audit Findings
Low Maintenance in operation.
Long term availability of energy
Environmentally safe.
Total Job completed with required
quality.
Outline of projectHuman Resource Management
Inputs Tools and Techniques Outputs
1. Develop Human
Resource Plan
Organization Chart and
Position Descriptions
Since project inception stage it was
decided to staffing the project with
well qualified and trained personnel.
2. Acquire Project Team
Pre-assignment,
negotiation, acquisition,
virtual teams
Well trained and skilled persons
were engaged.
3. Develop Project Team
Interpersonal skills, training,
team-building activities,
recognition and rewards
Team work was well-functioned at
every stage.
4. Manage Project Team
Observation and
conversation, performance
appraisals, conflict
management
Every team member was committed
to their performance.
Outline of projectCommunication Management
Inputs Tools and Techniques Outputs
1.Identify Stake Holder
Stake holder analysis,
Expert judgment.
The Owner, Allegheny
County and SE Technology
were well synchronized.
2. Plan Communications
Communication
requirement analysis,
communication
technology,
communication models.
Project objectives were
established that they will
built a facility of world
class, on schedule and
within the budgeted cost.
Outline of projectCommunication Management
Inputs Tools and Techniques Outputs
3. Distribute Informations Information distribution tools
Project mile stones were
scheduled and monitored
regularly.
4. Manage Stakeholder’s
expectations and
performance reporting
Communication methods,
management skills, variance
analysis, forecasting methods
and reporting systems.
SE Technology came with
idea that HTW system will be
better than the conventional
HPS heating system and it
was accepted considering the
overall impact of this total
project schedule and cost.
17
Management of Engineering
 The facility has been design to serve 365 days per year and 24 hours a
day.
 Though High Pressure Steam System was considered at bidding stage,
during conceptual design it was changed to High Temperature Water
System which provided many advantages.
 HTW System is a less complex system than steam heating.
 Initially there was a perception that HTW System is dangerous. A
practical test was done which proved that HTW is safe comparing with
Steam system.
 HTW System is more energy efficient as it doesn’t have parasitic steam
and heat losses.
18
Management of Engineering
 O&M costs are low as there is no steam trap maintenance, less make
up water, low water treatment chemical requirements.
 System start-up is simple as the system involve only liquid phase of
water.
 Smaller Piping sizes helped to reduce project costs. Pipe installation
was simple as there was no requirement to maintain the slope.
 Heat storage also become possible which helped to handle sudden
increase in loads.
19
Integration Management
 Project integration management - managing the
interdependencies among the various processes involved.
 Key difficulties in the execution of projects have often
been associated with project integration management.
 Despite the fact that many different organizations were
involved, the project must come together as per the
intended purpose.
Outline of projectIntegration Management
Outline of projectIntegration Management
 The processes were planned to ensure that the project is completed
within the approved budget. It consists of resource planning, cost
estimating, cost budgeting, and cost control.
 With proper scheduling and planning, as well as with proper control of
the project, quality in the process is assured.
 By keeping all the stakeholders informed and involving them in the
process whenever appropriate, the owners and the stakeholders grow
to feel for the project and ensured their support and cooperation.
 All stakeholders were focused on the common interests in the process
rather than the opposing positions of the parties.
Cost v/s Quality
• The "cost of quality" isn't the price of creating
a quality product or service. It's the cost of
NOT creating a quality product or service.
Success Factors
 Strategic Project Management
 Conceptual Engineering
 Proper Design
 Construction Management
 Quality in the design and construction was the focus of the
project.
 Emphasis on Start up activities
 Importance of Project Cost
 Realistic Project Schedule
 The right people are put on the job and the job is
managed properly.
23
Key findings
 Owner’s commitment to realistic scheduling, budgeting for
comprehensive engineering.
 Detailed analysis to finalize Energy system
 Better Reliability
 Improved safety
 Greater System efficiency
 Lower O&M Cost
 System Start Up Simplification
 Closed System
 Smaller Piping
 Pipe Installation Simplification
 Close Temperature
 Less Over all Life cycle cost of Energy system
 Detailed bid document helps in competitive bids & minimize
construction cost
 Early completion of project ( 6 weeks ahead schedule)
24
Key Learnings & Conclusion
 Scope management process was properly carried out and
the identified activities were clearly stated.
 Successful projects have owner’s commitment to realistic
scheduling and budgeting.
 If realistic budget & quality is established the project is
properly controlled by controlling the schedule & not the
budget.
 If the schedule is realistic w.r.t quality & budget minimum
contingencies are required.
 Negotiations by the owner for a realistic budget that
ensures required quality & sufficient money.
25
Key Learnings & Conclusion
 Comprehensive preliminary engineering studies by the
owner results in detailed & competitive bidding which
minimizes contingencies & enhances savings on long term
operating costs.
 Owners openness to the adaptability of new technology.
(HTW opted over HPS )
 Success ingredients of project
– Comprehensive and Conceptual Design.
– Focus on quality, Life cycle cost & Schedule.
– Strategic Management to be an integral part of Project
Management.
26
Thank You..!!
27

More Related Content

What's hot

construction project planing
 construction project planing construction project planing
construction project planing
SANJEEV Wazir
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
NAVNEET KUMAR JHA
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
Essam Lotffy, PMP®, CCP®
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
guy_davis
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
akashpadole
 
Wbs For Building Project
Wbs For Building ProjectWbs For Building Project
Wbs For Building Project
project management
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
hatim ahmed
 
Construction Supervising Site Engineer - Duties & Responsibilities
Construction Supervising Site Engineer - Duties & ResponsibilitiesConstruction Supervising Site Engineer - Duties & Responsibilities
Construction Supervising Site Engineer - Duties & Responsibilities
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Commercial aspects of civil construction
Commercial aspects of civil constructionCommercial aspects of civil construction
Commercial aspects of civil construction
sandesh mundra
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
Twana Ahmad
 
Project cost control
Project cost controlProject cost control
Project cost control
Sourabh Modgil
 
Quality management
Quality managementQuality management
Quality management
charliesleopanadan
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
Vîñõđ Kůmåř
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
Waleed Liaqat
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
Xubitech
 
Terminology used in estimating and costing
Terminology used in estimating and costingTerminology used in estimating and costing
Terminology used in estimating and costing
Janak Mehta
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
srinivas2036
 
Unit-2_Tender
Unit-2_TenderUnit-2_Tender
Unit-2_Tender
Akash Bharti
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...
Shabaz Khan
 
Persons involved in tenders and contract
Persons involved in tenders and contractPersons involved in tenders and contract
Persons involved in tenders and contract
shiva prakash
 

What's hot (20)

construction project planing
 construction project planing construction project planing
construction project planing
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
Wbs For Building Project
Wbs For Building ProjectWbs For Building Project
Wbs For Building Project
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
 
Construction Supervising Site Engineer - Duties & Responsibilities
Construction Supervising Site Engineer - Duties & ResponsibilitiesConstruction Supervising Site Engineer - Duties & Responsibilities
Construction Supervising Site Engineer - Duties & Responsibilities
 
Commercial aspects of civil construction
Commercial aspects of civil constructionCommercial aspects of civil construction
Commercial aspects of civil construction
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
 
Project cost control
Project cost controlProject cost control
Project cost control
 
Quality management
Quality managementQuality management
Quality management
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
Terminology used in estimating and costing
Terminology used in estimating and costingTerminology used in estimating and costing
Terminology used in estimating and costing
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
Unit-2_Tender
Unit-2_TenderUnit-2_Tender
Unit-2_Tender
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...
 
Persons involved in tenders and contract
Persons involved in tenders and contractPersons involved in tenders and contract
Persons involved in tenders and contract
 

Viewers also liked

ICT Support for Business Process Compliance
ICT Support for Business Process ComplianceICT Support for Business Process Compliance
ICT Support for Business Process Compliance
Guido Governatori
 
Software Quality Assurance and Testing: QA in Context
Software Quality Assurance and Testing: QA in ContextSoftware Quality Assurance and Testing: QA in Context
Software Quality Assurance and Testing: QA in Context
University of Dhaka
 
ICT Career Powerpoint (Systems Engineer)
ICT Career Powerpoint (Systems Engineer)ICT Career Powerpoint (Systems Engineer)
ICT Career Powerpoint (Systems Engineer)guest764bb2
 
Position Description - ICT Support Technician PV-CS-1504
Position Description - ICT Support Technician PV-CS-1504Position Description - ICT Support Technician PV-CS-1504
Position Description - ICT Support Technician PV-CS-1504Roman Kales
 
Systems Engineer
Systems EngineerSystems Engineer
Systems Engineerchalikars
 
customer care in ict
customer care in ictcustomer care in ict
customer care in ict
iteclearners
 
Financial officer job description
Financial officer job descriptionFinancial officer job description
Financial officer job description
financemanagement
 
Crude oil extraction ( lec 3a )
Crude oil extraction ( lec 3a )Crude oil extraction ( lec 3a )
Crude oil extraction ( lec 3a )
Asad Malik
 
Systems Engineering in Medical Devices
Systems Engineering in Medical DevicesSystems Engineering in Medical Devices
Systems Engineering in Medical Devices
channylaux
 
Job description 14061 - Software Testing (HIL) Engineer
Job description 14061 - Software Testing (HIL) EngineerJob description 14061 - Software Testing (HIL) Engineer
Job description 14061 - Software Testing (HIL) Engineer
Paolo Bartolini
 
Improving IT Service Delivery
Improving IT Service DeliveryImproving IT Service Delivery
Improving IT Service Delivery
Formicio
 
IT Service Delivery Model Overview
IT Service Delivery Model OverviewIT Service Delivery Model Overview
IT Service Delivery Model Overview
Mark Peacock
 

Viewers also liked (16)

ICT_OPERATIONS_MANAGER
ICT_OPERATIONS_MANAGERICT_OPERATIONS_MANAGER
ICT_OPERATIONS_MANAGER
 
ICT Support for Business Process Compliance
ICT Support for Business Process ComplianceICT Support for Business Process Compliance
ICT Support for Business Process Compliance
 
Software Quality Assurance and Testing: QA in Context
Software Quality Assurance and Testing: QA in ContextSoftware Quality Assurance and Testing: QA in Context
Software Quality Assurance and Testing: QA in Context
 
ICT Career Powerpoint (Systems Engineer)
ICT Career Powerpoint (Systems Engineer)ICT Career Powerpoint (Systems Engineer)
ICT Career Powerpoint (Systems Engineer)
 
Position Description - ICT Support Technician PV-CS-1504
Position Description - ICT Support Technician PV-CS-1504Position Description - ICT Support Technician PV-CS-1504
Position Description - ICT Support Technician PV-CS-1504
 
Systems Engineer
Systems EngineerSystems Engineer
Systems Engineer
 
Kuwait oil field
Kuwait oil fieldKuwait oil field
Kuwait oil field
 
customer care in ict
customer care in ictcustomer care in ict
customer care in ict
 
Financial officer job description
Financial officer job descriptionFinancial officer job description
Financial officer job description
 
Crude oil extraction ( lec 3a )
Crude oil extraction ( lec 3a )Crude oil extraction ( lec 3a )
Crude oil extraction ( lec 3a )
 
Challenges airport planning
Challenges airport planningChallenges airport planning
Challenges airport planning
 
Crude oil
Crude oilCrude oil
Crude oil
 
Systems Engineering in Medical Devices
Systems Engineering in Medical DevicesSystems Engineering in Medical Devices
Systems Engineering in Medical Devices
 
Job description 14061 - Software Testing (HIL) Engineer
Job description 14061 - Software Testing (HIL) EngineerJob description 14061 - Software Testing (HIL) Engineer
Job description 14061 - Software Testing (HIL) Engineer
 
Improving IT Service Delivery
Improving IT Service DeliveryImproving IT Service Delivery
Improving IT Service Delivery
 
IT Service Delivery Model Overview
IT Service Delivery Model OverviewIT Service Delivery Model Overview
IT Service Delivery Model Overview
 

Similar to Pittsburgh case study midfield energy system

Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Aconex
 
Construction project management
Construction project managementConstruction project management
Construction project management
saif hasan
 
Esound Brochure
Esound BrochureEsound Brochure
Esound Brochurekkdeacon
 
Esound Brochure
Esound BrochureEsound Brochure
Esound Brochure
Devan2012
 
Esound Quick Brochure
Esound Quick BrochureEsound Quick Brochure
Esound Quick Brochurediegobelmonte
 
10 me667 chap2 project management
10 me667 chap2 project management10 me667 chap2 project management
10 me667 chap2 project managementPavan Kumar
 
Esound Ireland Brochure
Esound Ireland BrochureEsound Ireland Brochure
Esound Ireland Brochuregarretflower
 
Ch 2 project planning and control
Ch 2 project planning and controlCh 2 project planning and control
Ch 2 project planning and controlJanak Singh Chauhan
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business planfarouq umar
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
Gregoire Lesecq
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET Journal
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
pisal3
 
Supply chain management in project
Supply chain management in projectSupply chain management in project
Supply chain management in project
Mukesh Doshi
 
Virtual design and construction
Virtual design and constructionVirtual design and construction
Virtual design and construction
Ankit Singhai
 
1.7 project management
1.7 project management1.7 project management
1.7 project management
exemplar2401
 
1-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp011-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp01
Amy Roman
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
Ala Ibrahim
 

Similar to Pittsburgh case study midfield energy system (20)

Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Esound Brochure
Esound BrochureEsound Brochure
Esound Brochure
 
Esound Brochure
Esound BrochureEsound Brochure
Esound Brochure
 
Esound Quick Brochure
Esound Quick BrochureEsound Quick Brochure
Esound Quick Brochure
 
Project planning: A career path
Project planning: A career pathProject planning: A career path
Project planning: A career path
 
Prashant Wani1
Prashant Wani1Prashant Wani1
Prashant Wani1
 
10 me667 chap2 project management
10 me667 chap2 project management10 me667 chap2 project management
10 me667 chap2 project management
 
Esound Ireland Brochure
Esound Ireland BrochureEsound Ireland Brochure
Esound Ireland Brochure
 
Ch 2 project planning and control
Ch 2 project planning and controlCh 2 project planning and control
Ch 2 project planning and control
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business plan
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
Samrat Khanorkar_Resume
Samrat Khanorkar_ResumeSamrat Khanorkar_Resume
Samrat Khanorkar_Resume
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
 
Supply chain management in project
Supply chain management in projectSupply chain management in project
Supply chain management in project
 
Virtual design and construction
Virtual design and constructionVirtual design and construction
Virtual design and construction
 
1.7 project management
1.7 project management1.7 project management
1.7 project management
 
1-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp011-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp01
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
 

Recently uploaded

Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 

Recently uploaded (20)

Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 

Pittsburgh case study midfield energy system

  • 1. Case Study-3 Pittsburgh Airport: Midfield Terminal Energy Facility (Area of discussion- Cost & Quality) Team Members: Case Study – 5
  • 2. Outline of projectBackground  The Pittsburgh International Airport is owned and operated by the Allegheny County Department of Aviation.  The new Midfield Terminal includes, Landside/central services bldg - 500,000 sft Airside building - 1,200,000 sft Gate capacity - 75 aircraft Provisions to expand - 100 gate terminal.  Pittsburg is the second busiest passenger airport in Pennsylvania and 47th-busiest in the United States, serving 8,041,357 passengers in 2012.
  • 3. Outline of projectBackground  The airport has the longest runways of a commercial airport in Pennsylvania at 11,500 feet (3,500 m).  Until 2004 US Airways largest hub was at PIT.  PIT occupies more than 12,900 acres (52 km2), making it the fourth- largest airport by land area owned in the nation.  The Midfield Terminal Energy Facility was designed to meet the requirement as:  Ultimate cooling load of 9,100 tons  Ultimate heating load of 113 x 106 Btuh
  • 4. Outline of projectOut Line of Project  The energy facility also provides electric power to the Midfield Terminal from the new substation located between the energy facility and the field-erected concrete cooling tower.  Completion – 6 weeks ahead of schedule and within budgeted cost.
  • 5. Outline of project ??? Cost Quality
  • 6. Outline of projectScope Management Well defined scope and explicitly required quality removes building up of cost contingencies for unknowns by the executers in turn reduction of in Cost.
  • 8. Outline of projectTime Management Realistic Cost Scope with Complete details Project Completion Time
  • 9. Outline of projectTime Management Realistic Project Schedule All contingencies properly factored in to the Schedule. Getting Realistic Input By allowing more cost on engineering.
  • 10. Outline of projectTime Management Performance Review Variance Analysis Resource leveling What if Analysis After negotiating the Realistic Engineering and Construction Budget, The Job was to focus on Schedule regress monitoring of schedule with following control tools
  • 11. Outline of projectTime Management The Start up testing was delayed due to non controllable issues Contingencies were taken for preparing Realistic Schedule Project was completed Six Weeks of Ahead of Schedule
  • 12. Outline of projectCost Management Key Inputs available General Tools and Techniques Outputs/advantages Cost Estimation and Budgeting Very clear project scope statement Detailed conceptual engineering Analysis Detailed Drawings and specification with high degree of accuracy. Complete project schedule Project Management software's Resource (Man, material, machine) plan Over Head ratio and Staff performance analysis Tax planning Realistic budget cost without any contingencies Cost Management Plan Cost Control Cost Base line. Realistic budgeted cost Detailed project schedule Project Management Plan Periodical Performance review Productivity Monitoring Variance analysis Project completed within the budget Due to owners commitment, realistic scheduling , optimum equipment selection, detailed bid documents and specs, project was completed under budget.
  • 13. Outline of projectQuality Management Key Inputs available General Tools and Techniques Outputs/advantages Quality Planning Detailed Scope statement prepared Detailed Engineering details/specs Very clear project objective Budget analysis Standards of Measurement of performance Process Flow charts Quality Management plan to implement the quality policy/ Objective. Quality Assurance /control Reliable equipment systems are selected. Proper technical persons are deployed Detailed Activity schedule Quality Audits Third Party tests Training for staffs and workmen Inspection of material and products Audit Findings Low Maintenance in operation. Long term availability of energy Environmentally safe. Total Job completed with required quality.
  • 14. Outline of projectHuman Resource Management Inputs Tools and Techniques Outputs 1. Develop Human Resource Plan Organization Chart and Position Descriptions Since project inception stage it was decided to staffing the project with well qualified and trained personnel. 2. Acquire Project Team Pre-assignment, negotiation, acquisition, virtual teams Well trained and skilled persons were engaged. 3. Develop Project Team Interpersonal skills, training, team-building activities, recognition and rewards Team work was well-functioned at every stage. 4. Manage Project Team Observation and conversation, performance appraisals, conflict management Every team member was committed to their performance.
  • 15. Outline of projectCommunication Management Inputs Tools and Techniques Outputs 1.Identify Stake Holder Stake holder analysis, Expert judgment. The Owner, Allegheny County and SE Technology were well synchronized. 2. Plan Communications Communication requirement analysis, communication technology, communication models. Project objectives were established that they will built a facility of world class, on schedule and within the budgeted cost.
  • 16. Outline of projectCommunication Management Inputs Tools and Techniques Outputs 3. Distribute Informations Information distribution tools Project mile stones were scheduled and monitored regularly. 4. Manage Stakeholder’s expectations and performance reporting Communication methods, management skills, variance analysis, forecasting methods and reporting systems. SE Technology came with idea that HTW system will be better than the conventional HPS heating system and it was accepted considering the overall impact of this total project schedule and cost.
  • 17. 17 Management of Engineering  The facility has been design to serve 365 days per year and 24 hours a day.  Though High Pressure Steam System was considered at bidding stage, during conceptual design it was changed to High Temperature Water System which provided many advantages.  HTW System is a less complex system than steam heating.  Initially there was a perception that HTW System is dangerous. A practical test was done which proved that HTW is safe comparing with Steam system.  HTW System is more energy efficient as it doesn’t have parasitic steam and heat losses.
  • 18. 18 Management of Engineering  O&M costs are low as there is no steam trap maintenance, less make up water, low water treatment chemical requirements.  System start-up is simple as the system involve only liquid phase of water.  Smaller Piping sizes helped to reduce project costs. Pipe installation was simple as there was no requirement to maintain the slope.  Heat storage also become possible which helped to handle sudden increase in loads.
  • 19. 19 Integration Management  Project integration management - managing the interdependencies among the various processes involved.  Key difficulties in the execution of projects have often been associated with project integration management.  Despite the fact that many different organizations were involved, the project must come together as per the intended purpose.
  • 21. Outline of projectIntegration Management  The processes were planned to ensure that the project is completed within the approved budget. It consists of resource planning, cost estimating, cost budgeting, and cost control.  With proper scheduling and planning, as well as with proper control of the project, quality in the process is assured.  By keeping all the stakeholders informed and involving them in the process whenever appropriate, the owners and the stakeholders grow to feel for the project and ensured their support and cooperation.  All stakeholders were focused on the common interests in the process rather than the opposing positions of the parties.
  • 22. Cost v/s Quality • The "cost of quality" isn't the price of creating a quality product or service. It's the cost of NOT creating a quality product or service.
  • 23. Success Factors  Strategic Project Management  Conceptual Engineering  Proper Design  Construction Management  Quality in the design and construction was the focus of the project.  Emphasis on Start up activities  Importance of Project Cost  Realistic Project Schedule  The right people are put on the job and the job is managed properly. 23
  • 24. Key findings  Owner’s commitment to realistic scheduling, budgeting for comprehensive engineering.  Detailed analysis to finalize Energy system  Better Reliability  Improved safety  Greater System efficiency  Lower O&M Cost  System Start Up Simplification  Closed System  Smaller Piping  Pipe Installation Simplification  Close Temperature  Less Over all Life cycle cost of Energy system  Detailed bid document helps in competitive bids & minimize construction cost  Early completion of project ( 6 weeks ahead schedule) 24
  • 25. Key Learnings & Conclusion  Scope management process was properly carried out and the identified activities were clearly stated.  Successful projects have owner’s commitment to realistic scheduling and budgeting.  If realistic budget & quality is established the project is properly controlled by controlling the schedule & not the budget.  If the schedule is realistic w.r.t quality & budget minimum contingencies are required.  Negotiations by the owner for a realistic budget that ensures required quality & sufficient money. 25
  • 26. Key Learnings & Conclusion  Comprehensive preliminary engineering studies by the owner results in detailed & competitive bidding which minimizes contingencies & enhances savings on long term operating costs.  Owners openness to the adaptability of new technology. (HTW opted over HPS )  Success ingredients of project – Comprehensive and Conceptual Design. – Focus on quality, Life cycle cost & Schedule. – Strategic Management to be an integral part of Project Management. 26

Editor's Notes

  1. of foreasted and installed
  2. of foreasted and installed