SlideShare a Scribd company logo
Chapter 13




                          Progress and
                          Performance
                         Measurement
                         and Evaluation


McGraw-Hill/Irwin        © 2008 The McGraw-Hill Companies, All Rights Reserved
Project Monitoring System for Control
 Information   System Structure
   What   data are collected?
     o Current status of project (schedule and cost)
     o Remaining cost to compete project
     o Date that project will be complete
     o Potential problems to be addressed now
     o Out-of-control activities requiring intervention
     o Cost and/or schedule overruns and the reasons for
       them
     o Forecast of overruns at time of project completion

                                                            13-2
Project Progress Report Format
 Progress Since Last Report
 Current Status of Project
   Schedule
   Cost
   Scope

 CumulativeTrends
 Problems and Issues Since Last Report
   Actionsand resolution of earlier problems
   New variances and problems identified

 Corrective   Action Planned
                                                13-3
The Project Control Process
Control
      The process of comparing actual performance
       against plan to identify deviations, evaluate
       courses of action, and take appropriate corrective
       action
Project    Control Steps
  1.   Setting a baseline plan
  2.   Measuring progress and performance
  3.   Comparing plan against actual
  4.   Taking actions

                                                            13-4
Monitoring Time Performance
 ToolsUsed to Catch Negative Variances
 from Plan and Communicate Project
 Schedule Status:
   Tracking   and baseline Gantt charts
    o Show expected, actual, and trend data for event
      duration performance
   Control   charts
    o Plot the difference in scheduled time on the critical
      path with the actual point on the critical path


                                                              13-5
Baseline and Tracking Gantt Charts




                                     FIGURE 13.1


                                          13-6
Project Schedule Control Chart




                             FIGURE 13.2


                                     13-7
Disparity Among Monitoring Systems
 Time-Phase   Baseline Plan
   Corrects
           the failure of most monitoring systems to
   connect a project’s actual performance to its
   schedule and forecast budget
 Earned   Value Cost/Schedule System
   Anintegrated project management system based
   on the earned value concept that uses a time-
   phased budget baseline to compare actual and
   planned schedule and costs




                                                       13-8
Glossary of Terms
   EV
       The percent complete times its original budget. The older
        acronym for this value was BCWP—budgeted cost of the
        work performed.
   PV (Planned Value)
       The time-phased baseline of the value of the work
        scheduled. (BCWS—budgeted cost of the work
        scheduled).
   AC
       The actual cost of the work completed. (ACWP—actual
        cost of the work performed).




                                                                    13-9
Glossary of Terms
   CV
       Cost variance is the difference between the earned value and
        the actual costs for the work completed to date where CV=EV-
        AC.
   SV
       Schedule variance (SV) is the difference between the earned
        value and the baseline line to date where SV=EV-PV.
   BAC
       Budgeted cost at completion. The total budgeted cost of the
        baseline or project cost accounts.
   EACre
       Estimated costs at completion. Includes costs to-date plus
        revised estimated costs for the work remaining.
                                                                      13-10
Glossary of Terms
 ETC
     Estimate to complete.
 VAC
     Cost variance at completion (BAC-EACre), where
      EACre is derived by estimators in the field.
   Or, alternatively, cost variance at completion (BAC-
    EACf), where EACf is derived from a formula using
    actual and earned value costs.
   VAC indicates expected actual over-or underrun cost
    at completion.


                                                           13-11
Developing an Integrated
                   Cost/Schedule System
1.   Define the work using a                 3.   Develop a time-phased
     WBS.                                         budget using work packages
     a.   Scope                                   included in an activity.
     b.   Work packages
                                                  Accumulate budgets (PV).
     c.   Deliverables                       4.   At the work package level,
     d.   Organization units                      collect the actual costs for
     e.   Resources
                                                  the work performed (AC).
     f.   Budgets                            5.   Multiply percent complete
                                                  times original budget (EV).
2.   Develop work and resource
     schedules.                              6.   Compute the schedule
     a.   Schedule resources to activities        variance (EV-PV) and the
                                                  cost variance (EV-AC).
     b.   Time-phase work packages into
          a network


                                                                                 13-12
Baseline Data Relationships




                              13-13
Methods of Variance Analysis
 Cost   Variance (CV)
   Indicates
            if the work accomplished using labor
   and materials costs more or less than was
   planned at any point in the project
 Schedule     Variance (SV)
   Presents an overall assessment in dollar
   terms of the progress of all work packages in
   the project scheduled to date



                                                   13-14
Cost/Schedule Graph




                      FIGURE 13.4


                             13-15
Earned Value Review Exercise




                           FIGURE 13.5


                                  13-16
Digital Camera Prototype Project
      Baseline Gantt Chart




                                   FIGURE 13.7


                                          13-17
Digital Camera Prototype Project
           Baseline




                                   FIGURE 13.8


                                          13-18
Digital Camera Prototype Status
      Reports: Periods 1–3




                           TABLE 13.1
                                        13-19
Digital Camera Prototype Status
      Reports: Periods 4–6




                          TABLE 13.1 (CONT)
                                              13-20
Digital Camera Prototype Status
        Reports: Period 7




                          TABLE 13.1 (CONT)
                                              13-21
Digital Camera Prototype Summary
           Graph (000)




                               FIGURE 13.9


                                      13-22
Digital Camera Project Tracking Gantt Chart

   Showing Status—Through Period 7




                                      FIGURE 13.10


                                              13-23
Digital Camera
 Project Rollup at
End Period 7 (000)




                     FIGURE 13.11
                                    13-24
Indexes to Monitor Progress
 Performance    Indexes
   Cost   Performance Index (CPI)
    o Measures the cost efficiency of work accomplished to date
    o CPI = EV/AC
   Scheduling   Performance Index (SPI)
    o Measures scheduling efficiency
    o SPI = EV/PV
   Percent   Complete Indexes
    o Indicates how much of the work accomplished represents of
      the total budgeted (BAC) and actual (AC) dollars to date
    o PCIB = EV/BAC
    o PCIC = AC/EAC

                                                              13-25
Interpretation of Indexes




                            TABLE 13.3


                                         13-26
Indexes
Periods 1–7




       FIGURE 13.12


                      13-27
Additional Earned Value Rules
 RulesApplied to Short-Duration Activities
 and/or Small-Cost Activities
   0/100   percent rule
    o Assumes 100 % of budget credit is earned at once
      and only when the work is completed
   50/50   rule
    o Allows for 50% of the value of the work package
      budget to be earned when it is started and 50% to
      be earned when the package is completed


                                                          13-28
Forecasting Final Project Cost
 Methods Used to Revise Estimates of
 Future Project Costs:
   EAC
         re
    o Allows experts in the field to change original
      baseline durations and costs because new
      information tells them the original estimates are
      not accurate

   EAC
         f
    o Uses actual costs-to-date plus an efficiency index
      to project final costs in large projects where the
      original budget is unreliable
                                                           13-29
Forecasting Model: EACf
The equation for this forecasting model:




                                           13-30
To Complete Performance Index
           (TCPI)

             BAC - EV
   TCPI=     BAC – AC

   TCPI = the amount of value each
remaining     dollar in the budget must
earn to stay within       budget

                                          13-31

More Related Content

What's hot

Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
Chris Carson
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
Chris Carson
 
Linear programming
Linear programming Linear programming
Linear programming
sadha sivam
 
PMO Frameworks
PMO FrameworksPMO Frameworks
PMO Frameworks
Michael Kaplan
 
PMO 101
PMO 101PMO 101
PMO 101
shailsood
 
Chap011
Chap011Chap011
Chap 6 Developing A Project Plan
Chap 6 Developing A Project PlanChap 6 Developing A Project Plan
Chap 6 Developing A Project Plan
project management
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2
Chris Carson
 
Tools and Techniques for Project Management
Tools and Techniques for Project Management Tools and Techniques for Project Management
Tools and Techniques for Project Management
Teresa Lawrence, Ph.D., PMP
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
Krishna Murthy RVN
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
Chris Carson
 
PROJECT SCHEDULING
PROJECT SCHEDULINGPROJECT SCHEDULING
PROJECT SCHEDULING
Shahrukh Vahora
 
Probabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost AnalysisProbabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost Analysis
Glen Alleman
 
The Disturbing Reality of Today's PMO
The Disturbing Reality of Today's PMOThe Disturbing Reality of Today's PMO
The Disturbing Reality of Today's PMO
Ian Needs
 
Chap 4 Defining A Project
Chap 4 Defining A ProjectChap 4 Defining A Project
Chap 4 Defining A Project
project management
 
Chap 5 Estimating Project Times
Chap 5 Estimating Project TimesChap 5 Estimating Project Times
Chap 5 Estimating Project Times
project management
 
Project portfolio management
Project portfolio managementProject portfolio management
Project portfolio management
Neelangouda Biradar
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
Anand Subramaniam
 
Chap016-Oversight
Chap016-OversightChap016-Oversight
Chap016-Oversight
maisuradi
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
Glen Alleman
 

What's hot (20)

Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Linear programming
Linear programming Linear programming
Linear programming
 
PMO Frameworks
PMO FrameworksPMO Frameworks
PMO Frameworks
 
PMO 101
PMO 101PMO 101
PMO 101
 
Chap011
Chap011Chap011
Chap011
 
Chap 6 Developing A Project Plan
Chap 6 Developing A Project PlanChap 6 Developing A Project Plan
Chap 6 Developing A Project Plan
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2
 
Tools and Techniques for Project Management
Tools and Techniques for Project Management Tools and Techniques for Project Management
Tools and Techniques for Project Management
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
PROJECT SCHEDULING
PROJECT SCHEDULINGPROJECT SCHEDULING
PROJECT SCHEDULING
 
Probabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost AnalysisProbabilistic Schedule and Cost Analysis
Probabilistic Schedule and Cost Analysis
 
The Disturbing Reality of Today's PMO
The Disturbing Reality of Today's PMOThe Disturbing Reality of Today's PMO
The Disturbing Reality of Today's PMO
 
Chap 4 Defining A Project
Chap 4 Defining A ProjectChap 4 Defining A Project
Chap 4 Defining A Project
 
Chap 5 Estimating Project Times
Chap 5 Estimating Project TimesChap 5 Estimating Project Times
Chap 5 Estimating Project Times
 
Project portfolio management
Project portfolio managementProject portfolio management
Project portfolio management
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Chap016-Oversight
Chap016-OversightChap016-Oversight
Chap016-Oversight
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
 

Similar to Chap013 4er1

Group 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdfGroup 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdf
alvieramada23
 
Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015
Dr Ezzat Mansour
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
M Maged Hegazy, LLM, MBA, CCP, P3O
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
eidalin95
 
GL3eChap13-new.pptqpotieuwbsjsjsushshshdhd
GL3eChap13-new.pptqpotieuwbsjsjsushshshdhdGL3eChap13-new.pptqpotieuwbsjsjsushshshdhd
GL3eChap13-new.pptqpotieuwbsjsjsushshshdhd
nithinnick66
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
Craig Brown
 
Sorge.les
Sorge.lesSorge.les
Sorge.les
NASAPMC
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Tipsographic . com
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown Structure
John Carter
 
Chapter ThirteenProgress and Performance Measurement and Evalu
Chapter ThirteenProgress and Performance Measurement and EvaluChapter ThirteenProgress and Performance Measurement and Evalu
Chapter ThirteenProgress and Performance Measurement and Evalu
JinElias52
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeff
NASAPMC
 
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationEarned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
Ricardo Viana Vargas
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Serdar Temiz
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
Russell Taylor BEng CEng FAPM FIET
 
Ch 9 project monitoring & control updated
Ch 9 project monitoring & control updatedCh 9 project monitoring & control updated
Ch 9 project monitoring & control updated
Farhana Rehman
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
reddvise
 
Software Project Management Spm1176
Software Project Management Spm1176Software Project Management Spm1176
Software Project Management Spm1176
Ahmad Hammoud,CPM,IBA,MSE,NLP
 
Schulte
SchulteSchulte
Schulte
NASAPMC
 
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
IJERA Editor
 
CCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost ControlCCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost Control
Hisham Haridy MBA, PMP®, RMP®, SP®
 

Similar to Chap013 4er1 (20)

Group 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdfGroup 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdf
 
Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015Nasa+evm+reference+card nov+2015
Nasa+evm+reference+card nov+2015
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
GL3eChap13-new.pptqpotieuwbsjsjsushshshdhd
GL3eChap13-new.pptqpotieuwbsjsjsushshshdhdGL3eChap13-new.pptqpotieuwbsjsjsushshshdhd
GL3eChap13-new.pptqpotieuwbsjsjsushshshdhd
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 
Sorge.les
Sorge.lesSorge.les
Sorge.les
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown Structure
 
Chapter ThirteenProgress and Performance Measurement and Evalu
Chapter ThirteenProgress and Performance Measurement and EvaluChapter ThirteenProgress and Performance Measurement and Evalu
Chapter ThirteenProgress and Performance Measurement and Evalu
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeff
 
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationEarned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Ch 9 project monitoring & control updated
Ch 9 project monitoring & control updatedCh 9 project monitoring & control updated
Ch 9 project monitoring & control updated
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
Software Project Management Spm1176
Software Project Management Spm1176Software Project Management Spm1176
Software Project Management Spm1176
 
Schulte
SchulteSchulte
Schulte
 
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
 
CCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost ControlCCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost Control
 

Recently uploaded

AI-Powered Food Delivery Transforming App Development in Saudi Arabia.pdf
AI-Powered Food Delivery Transforming App Development in Saudi Arabia.pdfAI-Powered Food Delivery Transforming App Development in Saudi Arabia.pdf
AI-Powered Food Delivery Transforming App Development in Saudi Arabia.pdf
Techgropse Pvt.Ltd.
 
20240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 202420240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 2024
Matthew Sinclair
 
20240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 202420240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 2024
Matthew Sinclair
 
GenAI Pilot Implementation in the organizations
GenAI Pilot Implementation in the organizationsGenAI Pilot Implementation in the organizations
GenAI Pilot Implementation in the organizations
kumardaparthi1024
 
OpenID AuthZEN Interop Read Out - Authorization
OpenID AuthZEN Interop Read Out - AuthorizationOpenID AuthZEN Interop Read Out - Authorization
OpenID AuthZEN Interop Read Out - Authorization
David Brossard
 
Choosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptxChoosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptx
Brandon Minnick, MBA
 
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAUHCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
panagenda
 
Best 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERPBest 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERP
Pixlogix Infotech
 
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
Edge AI and Vision Alliance
 
Monitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdfMonitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdf
Tosin Akinosho
 
Video Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the FutureVideo Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the Future
Alpen-Adria-Universität
 
Full-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalizationFull-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalization
Zilliz
 
Serial Arm Control in Real Time Presentation
Serial Arm Control in Real Time PresentationSerial Arm Control in Real Time Presentation
Serial Arm Control in Real Time Presentation
tolgahangng
 
June Patch Tuesday
June Patch TuesdayJune Patch Tuesday
June Patch Tuesday
Ivanti
 
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
名前 です男
 
Uni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems Copilot event_05062024_C.Vlachos.pdfUni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems S.M.S.A.
 
Essentials of Automations: The Art of Triggers and Actions in FME
Essentials of Automations: The Art of Triggers and Actions in FMEEssentials of Automations: The Art of Triggers and Actions in FME
Essentials of Automations: The Art of Triggers and Actions in FME
Safe Software
 
“I’m still / I’m still / Chaining from the Block”
“I’m still / I’m still / Chaining from the Block”“I’m still / I’m still / Chaining from the Block”
“I’m still / I’m still / Chaining from the Block”
Claudio Di Ciccio
 
Programming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup SlidesProgramming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup Slides
Zilliz
 
National Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practicesNational Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practices
Quotidiano Piemontese
 

Recently uploaded (20)

AI-Powered Food Delivery Transforming App Development in Saudi Arabia.pdf
AI-Powered Food Delivery Transforming App Development in Saudi Arabia.pdfAI-Powered Food Delivery Transforming App Development in Saudi Arabia.pdf
AI-Powered Food Delivery Transforming App Development in Saudi Arabia.pdf
 
20240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 202420240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 2024
 
20240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 202420240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 2024
 
GenAI Pilot Implementation in the organizations
GenAI Pilot Implementation in the organizationsGenAI Pilot Implementation in the organizations
GenAI Pilot Implementation in the organizations
 
OpenID AuthZEN Interop Read Out - Authorization
OpenID AuthZEN Interop Read Out - AuthorizationOpenID AuthZEN Interop Read Out - Authorization
OpenID AuthZEN Interop Read Out - Authorization
 
Choosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptxChoosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptx
 
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAUHCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
 
Best 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERPBest 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERP
 
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
 
Monitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdfMonitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdf
 
Video Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the FutureVideo Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the Future
 
Full-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalizationFull-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalization
 
Serial Arm Control in Real Time Presentation
Serial Arm Control in Real Time PresentationSerial Arm Control in Real Time Presentation
Serial Arm Control in Real Time Presentation
 
June Patch Tuesday
June Patch TuesdayJune Patch Tuesday
June Patch Tuesday
 
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
 
Uni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems Copilot event_05062024_C.Vlachos.pdfUni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems Copilot event_05062024_C.Vlachos.pdf
 
Essentials of Automations: The Art of Triggers and Actions in FME
Essentials of Automations: The Art of Triggers and Actions in FMEEssentials of Automations: The Art of Triggers and Actions in FME
Essentials of Automations: The Art of Triggers and Actions in FME
 
“I’m still / I’m still / Chaining from the Block”
“I’m still / I’m still / Chaining from the Block”“I’m still / I’m still / Chaining from the Block”
“I’m still / I’m still / Chaining from the Block”
 
Programming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup SlidesProgramming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup Slides
 
National Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practicesNational Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practices
 

Chap013 4er1

  • 1. Chapter 13 Progress and Performance Measurement and Evaluation McGraw-Hill/Irwin © 2008 The McGraw-Hill Companies, All Rights Reserved
  • 2. Project Monitoring System for Control  Information System Structure  What data are collected? o Current status of project (schedule and cost) o Remaining cost to compete project o Date that project will be complete o Potential problems to be addressed now o Out-of-control activities requiring intervention o Cost and/or schedule overruns and the reasons for them o Forecast of overruns at time of project completion 13-2
  • 3. Project Progress Report Format  Progress Since Last Report  Current Status of Project  Schedule  Cost  Scope  CumulativeTrends  Problems and Issues Since Last Report  Actionsand resolution of earlier problems  New variances and problems identified  Corrective Action Planned 13-3
  • 4. The Project Control Process Control  The process of comparing actual performance against plan to identify deviations, evaluate courses of action, and take appropriate corrective action Project Control Steps 1. Setting a baseline plan 2. Measuring progress and performance 3. Comparing plan against actual 4. Taking actions 13-4
  • 5. Monitoring Time Performance  ToolsUsed to Catch Negative Variances from Plan and Communicate Project Schedule Status:  Tracking and baseline Gantt charts o Show expected, actual, and trend data for event duration performance  Control charts o Plot the difference in scheduled time on the critical path with the actual point on the critical path 13-5
  • 6. Baseline and Tracking Gantt Charts FIGURE 13.1 13-6
  • 7. Project Schedule Control Chart FIGURE 13.2 13-7
  • 8. Disparity Among Monitoring Systems  Time-Phase Baseline Plan  Corrects the failure of most monitoring systems to connect a project’s actual performance to its schedule and forecast budget  Earned Value Cost/Schedule System  Anintegrated project management system based on the earned value concept that uses a time- phased budget baseline to compare actual and planned schedule and costs 13-8
  • 9. Glossary of Terms  EV  The percent complete times its original budget. The older acronym for this value was BCWP—budgeted cost of the work performed.  PV (Planned Value)  The time-phased baseline of the value of the work scheduled. (BCWS—budgeted cost of the work scheduled).  AC  The actual cost of the work completed. (ACWP—actual cost of the work performed). 13-9
  • 10. Glossary of Terms  CV  Cost variance is the difference between the earned value and the actual costs for the work completed to date where CV=EV- AC.  SV  Schedule variance (SV) is the difference between the earned value and the baseline line to date where SV=EV-PV.  BAC  Budgeted cost at completion. The total budgeted cost of the baseline or project cost accounts.  EACre  Estimated costs at completion. Includes costs to-date plus revised estimated costs for the work remaining. 13-10
  • 11. Glossary of Terms  ETC  Estimate to complete.  VAC  Cost variance at completion (BAC-EACre), where EACre is derived by estimators in the field.  Or, alternatively, cost variance at completion (BAC- EACf), where EACf is derived from a formula using actual and earned value costs.  VAC indicates expected actual over-or underrun cost at completion. 13-11
  • 12. Developing an Integrated Cost/Schedule System 1. Define the work using a 3. Develop a time-phased WBS. budget using work packages a. Scope included in an activity. b. Work packages Accumulate budgets (PV). c. Deliverables 4. At the work package level, d. Organization units collect the actual costs for e. Resources the work performed (AC). f. Budgets 5. Multiply percent complete times original budget (EV). 2. Develop work and resource schedules. 6. Compute the schedule a. Schedule resources to activities variance (EV-PV) and the cost variance (EV-AC). b. Time-phase work packages into a network 13-12
  • 14. Methods of Variance Analysis  Cost Variance (CV)  Indicates if the work accomplished using labor and materials costs more or less than was planned at any point in the project  Schedule Variance (SV)  Presents an overall assessment in dollar terms of the progress of all work packages in the project scheduled to date 13-14
  • 15. Cost/Schedule Graph FIGURE 13.4 13-15
  • 16. Earned Value Review Exercise FIGURE 13.5 13-16
  • 17. Digital Camera Prototype Project Baseline Gantt Chart FIGURE 13.7 13-17
  • 18. Digital Camera Prototype Project Baseline FIGURE 13.8 13-18
  • 19. Digital Camera Prototype Status Reports: Periods 1–3 TABLE 13.1 13-19
  • 20. Digital Camera Prototype Status Reports: Periods 4–6 TABLE 13.1 (CONT) 13-20
  • 21. Digital Camera Prototype Status Reports: Period 7 TABLE 13.1 (CONT) 13-21
  • 22. Digital Camera Prototype Summary Graph (000) FIGURE 13.9 13-22
  • 23. Digital Camera Project Tracking Gantt Chart Showing Status—Through Period 7 FIGURE 13.10 13-23
  • 24. Digital Camera Project Rollup at End Period 7 (000) FIGURE 13.11 13-24
  • 25. Indexes to Monitor Progress  Performance Indexes  Cost Performance Index (CPI) o Measures the cost efficiency of work accomplished to date o CPI = EV/AC  Scheduling Performance Index (SPI) o Measures scheduling efficiency o SPI = EV/PV  Percent Complete Indexes o Indicates how much of the work accomplished represents of the total budgeted (BAC) and actual (AC) dollars to date o PCIB = EV/BAC o PCIC = AC/EAC 13-25
  • 26. Interpretation of Indexes TABLE 13.3 13-26
  • 27. Indexes Periods 1–7 FIGURE 13.12 13-27
  • 28. Additional Earned Value Rules  RulesApplied to Short-Duration Activities and/or Small-Cost Activities  0/100 percent rule o Assumes 100 % of budget credit is earned at once and only when the work is completed  50/50 rule o Allows for 50% of the value of the work package budget to be earned when it is started and 50% to be earned when the package is completed 13-28
  • 29. Forecasting Final Project Cost  Methods Used to Revise Estimates of Future Project Costs:  EAC re o Allows experts in the field to change original baseline durations and costs because new information tells them the original estimates are not accurate  EAC f o Uses actual costs-to-date plus an efficiency index to project final costs in large projects where the original budget is unreliable 13-29
  • 30. Forecasting Model: EACf The equation for this forecasting model: 13-30
  • 31. To Complete Performance Index (TCPI) BAC - EV TCPI= BAC – AC TCPI = the amount of value each remaining dollar in the budget must earn to stay within budget 13-31