SlideShare a Scribd company logo
1 of 6
Download to read offline
1/6
Civilverse Admin 4 April 2021
DCMA 14 Point Schedule Quality Check
civilverse.org/dcma-14-point-schedule-quality-check
Table of Content for DCMA 14 Point Schedule Quality Check
1. Introduction
2. Why check project schedule health?
3. Types of Project Schedule Checks
4. DCMA 14-Point Schedule Quality Check
5. Conclusion
Introduction
The project schedule is an important part of project management. It contains the project
activities aligned in a sequential manner along with their individual time duration and
inter-dependencies. The project schedules can further be incorporated with the resources
and their respective cost.
The project schedule is a powerful tool to control the time taken by a project. The
sequence and inter-dependencies of the activities define the critical path for the project.
The Defence Contract Management Authority (DCMA), USA has set the guidelines for the
quality assessment of project schedule. The DCMA 14-point schedule quality check
guidelines were first published in 2005 for defence and aeronautical projects. The
guidelines are being globally used for the development and maintenance of schedules.
Why check project schedule health?
2/6
A project schedule helps in decision making, cost control, resource planning, monitoring
and tracking the progress. Thus, it is necessary to have a well-constructed and maintained
schedule to accurately achieve the objectives.
The assessment of the project schedule ensures its’ precision and accuracy. The
assessments are of two types qualitative and quantitative.
Types of Project Schedule Checks-
Types of Schedule Check
Qualitative Assessment-
The qualitative check of schedule is the determination of its’ ability to be executed. The
schedule is assessed if it is realistic and executable. The qualitative assessment requires
the team’s experience.
Quantitative Assessment-
The quantitative assessment of the schedule is done on the basis of measurable
parameters. DCMA 14-point schedule quality check guidelines are widely used for
quantitative assessment of project schedule.
DCMA 14-Point Schedule Quality Check
3/6
DCMA 14-Point Schedule Quality Check
1. Logic
The logic check ensures the schedule doesn’t have any incomplete activity that neither has
the predecessor nor the successor. Such activities may affect the critical path and project
duration. DCMA recommends such activities are to be lesser than 5%.
The activities that have no predecessor and no successor can be linked to either the
project start milestone or the project finish milestone.
2. Leads
Lead is the negative lag. Lead signifies that the activity starts before the predecessor
activity ends. DCMA recommends having zero lead. The leads can affect the critical path
thus it is advisable not to have them.
3. Lags
The difference between the finish of activity and the start of its’ successor is called lag.
DCMA recommends activities to not have more than a 5% lag. The activities with lag
should be replaced with intermittent activity. For example, lag between foundation
4/6
casting and machine installation to be replaced with curing period.
4. Relationship Types
There are four relationship types used to interlink activities namely Finish to Start (FS),
Start to Start (SS), Start to Finish (SF) and Finish to Finish (FF). DCMA recommends
more than 90% of activities should be Finish to Start (FS) linked. However, SS and FF are
also acceptable when it is the true link of activity but their use should be minimized. For
example, the casting of beams cannot be completed before the casting of the slab, hence
finish to finish relationship.
5. Hard Constraints
Must Start On, Must Finish On, Start No later Than and Finish no later Than are four
hard constraints used in project schedules. Ideally, there should be no hard constraints
but DCMA recommends limiting their use up to 5%. The hard constraints limit the logic-
driven behaviour of the schedule.
Hard constraints can create negative float.
6. High Float
The time by which an activity can slip without affecting the project completion is called
total float. The total float of 44 days is considered a high float. DCMA recommends
limiting such activities to 5%.
7. Negative Float
Negative Float represents the delay in completion. It is shown when a missed deadline is
being reported. DCMA limit for negative float is zero. As stated earlier, hard constraints
lead to negative float, as hard constraints hold the activities and indicate the upcoming
deadline is likely to be missed.
8. High Duration
The project schedule is a sequential arrangement of activities having discrete-time
duration. The work packages should be such broken that no activity should have a
duration greater than 44 days. DCMA limits such activities to be lesser than 5%.
Activities with high duration are difficult to track, measure and estimate resources. The
project and activity duration can be determined by any of the six methods listed here.
9. Invalid dates
The past dates in the forecast and future dates in completed activities are called invalid
dates. The invalid date check is useful for the project execution stage. The DCMA
threshold for this check is zero.
5/6
The activities not yet started are to be ahead of the status date. The in-progress and
completed activities should be as per the actual dates.
10. Resources
The schedules loaded with resources are helpful in resource estimation. Ideally, all the
activities should be resource loaded but the DCMA has not stated any fixed criteria for the
resource loading. Thus, it is a flexible metric and it depends upon the organisation’s rules.
However, if the resource loading is done in schedule, then every activity should have at
least one resource allocated to it to avoid misbalance.
It is not necessary that every activity requires resource. For example, delivery lead time
and approval from authorities etc.
11. Missed Tasks
The tasks having their baseline completion date before the status date are said to be
missed tasks. The missed tasks should not be more than 5% of the total tasks. However,
the tasks that are likely to be missed but have the baseline completion date after the status
date are not considered in the threshold.
The missed tasks can affect the project completion. They are an indicator of poor
planning, mismanagement and poor resource estimation and allocation.
12. Critical Path Test
The critical path is the longest path in an activity network. To perform the critical path
test, identify any critical activity and increase its’ duration by x days and recalculate the
project dates. If the project completion date also increases by x days then the schedule is
said to have passed the test. The test ensures the fluid network with proper linkage among
the activities.
The failed critical path test indicates the missing inter-dependencies among the activities.
For such a case, the entire schedule needs to be reviewed and corrected.
13. Critical Path Length Index (CPLI)
The Critical Path Length Index (CPLI) is the sum of remaining working days on the
critical path and total float divided by the total remaining days. CPLI indicates the
efficiency required to complete the project on time. The target CPLI should be 1 but
DCMA suggests acceptance up to 0.95.
For CPLI lesser than 1, the delay is likely to happen and efficiency must be increased to
achieve the baseline completion. For CPLI greater than 1, the schedule has margin and
completion is likely to be done before the baseline completion.
14. Baseline Execution Index (BEI)
6/6
The Baseline Execution Index (BEI) is the ratio of total tasks completed to the total tasks
planned as per baseline till status date. The BEI indicates the efficiency of work done. The
target BEI should be 1 but DCMA suggests acceptance up to 0.95.
The BEI lesser than 1 indicates missed tasks. Thus, more effort needs to be put to cover up
the slippage.
The BEI greater than 1 indicates the schedule is ahead of target and likely to be completed
before the baseline completion. This may be due to the availability of unnecessary float or
underestimated resource efficiency.
Conclusion
The DCMA 14-point schedule quality check gives an objective method to evaluate the
schedule. The regular check with these metrics ensures the schedule is in better health.
The routine check also enables the manager to change their strategy as per the
requirement.
The full compliance to all the 14-metrics doesn’t imply that the schedule is feasible and a
non-compliant schedule isn’t necessarily a failure. The metrics are generally available on
the popularly used software like MS Project and Primavera p6 etc.
Liked the article? Let me know in the comments in the comment below.
Happy Engineering!!

More Related Content

What's hot

Project Planning | Project Plan In Excel With Gantt Chart | Project Managemen...
Project Planning | Project Plan In Excel With Gantt Chart | Project Managemen...Project Planning | Project Plan In Excel With Gantt Chart | Project Managemen...
Project Planning | Project Plan In Excel With Gantt Chart | Project Managemen...Simplilearn
 
Ms project 2016 overview
Ms project 2016 overviewMs project 2016 overview
Ms project 2016 overviewMaher Almohamad
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact AnalysisChris Carson
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedMichael Pink
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFrancis Ho
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Tim Lloyd
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...John Buchovecky
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery SchedulingChris Carson
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time AnalysisFarhan Moosa
 
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Divyanshu Dayal
 

What's hot (20)

Project Planning | Project Plan In Excel With Gantt Chart | Project Managemen...
Project Planning | Project Plan In Excel With Gantt Chart | Project Managemen...Project Planning | Project Plan In Excel With Gantt Chart | Project Managemen...
Project Planning | Project Plan In Excel With Gantt Chart | Project Managemen...
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Ms project 2016 overview
Ms project 2016 overviewMs project 2016 overview
Ms project 2016 overview
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
Introduction to construction contracts fundamentals
Introduction to construction contracts fundamentalsIntroduction to construction contracts fundamentals
Introduction to construction contracts fundamentals
 
Standard Forms of Construction Contracts
Standard Forms of Construction ContractsStandard Forms of Construction Contracts
Standard Forms of Construction Contracts
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
CCP Technical Paper and Application
CCP Technical Paper and ApplicationCCP Technical Paper and Application
CCP Technical Paper and Application
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Analisis del valor ganado
Analisis del valor ganadoAnalisis del valor ganado
Analisis del valor ganado
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery Scheduling
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
 

Similar to DCMA 14-Point Schedule Quality Check

Project Life Cycle final.pptx
Project Life Cycle final.pptxProject Life Cycle final.pptx
Project Life Cycle final.pptxPranshiGoyal2
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-seminiMaya
 
The Value of a Standard Schedule Quality Index
The Value of a Standard Schedule Quality IndexThe Value of a Standard Schedule Quality Index
The Value of a Standard Schedule Quality IndexAcumen
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdfSurashmie Kaalmegh
 
Taming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule AssessmentTaming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule AssessmentAcumen
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsAcumen
 
IRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project ScheduleIRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project ScheduleIRJET Journal
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Acumen
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsSHAZEBALIKHAN1
 
Chapter 13Project Management and SDLCPrepared by Dr. D.docx
Chapter 13Project Management and SDLCPrepared by Dr. D.docxChapter 13Project Management and SDLCPrepared by Dr. D.docx
Chapter 13Project Management and SDLCPrepared by Dr. D.docxzebadiahsummers
 
Chapter 13Project Management and SDLCPrepared by Dr. D.docx
Chapter 13Project Management and SDLCPrepared by Dr. D.docxChapter 13Project Management and SDLCPrepared by Dr. D.docx
Chapter 13Project Management and SDLCPrepared by Dr. D.docxbartholomeocoombs
 
Chapter 13Project Management and SDLCPrepared by Dr. D.docx
Chapter 13Project Management and SDLCPrepared by Dr. D.docxChapter 13Project Management and SDLCPrepared by Dr. D.docx
Chapter 13Project Management and SDLCPrepared by Dr. D.docxcravennichole326
 
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET Journal
 
Presentation4 5.1.pptx
Presentation4 5.1.pptxPresentation4 5.1.pptx
Presentation4 5.1.pptxDrRRajalakshmi
 
Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOEGlen Alleman
 

Similar to DCMA 14-Point Schedule Quality Check (20)

Stopping the insanity
Stopping the insanityStopping the insanity
Stopping the insanity
 
Project Life Cycle final.pptx
Project Life Cycle final.pptxProject Life Cycle final.pptx
Project Life Cycle final.pptx
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
The Value of a Standard Schedule Quality Index
The Value of a Standard Schedule Quality IndexThe Value of a Standard Schedule Quality Index
The Value of a Standard Schedule Quality Index
 
Pmp in summary
Pmp in summaryPmp in summary
Pmp in summary
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdf
 
Taming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule AssessmentTaming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule Assessment
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
IRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project ScheduleIRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project Schedule
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 
Chapter 13Project Management and SDLCPrepared by Dr. D.docx
Chapter 13Project Management and SDLCPrepared by Dr. D.docxChapter 13Project Management and SDLCPrepared by Dr. D.docx
Chapter 13Project Management and SDLCPrepared by Dr. D.docx
 
Chapter 13Project Management and SDLCPrepared by Dr. D.docx
Chapter 13Project Management and SDLCPrepared by Dr. D.docxChapter 13Project Management and SDLCPrepared by Dr. D.docx
Chapter 13Project Management and SDLCPrepared by Dr. D.docx
 
Chapter 13Project Management and SDLCPrepared by Dr. D.docx
Chapter 13Project Management and SDLCPrepared by Dr. D.docxChapter 13Project Management and SDLCPrepared by Dr. D.docx
Chapter 13Project Management and SDLCPrepared by Dr. D.docx
 
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
 
Presentation4 5.1.pptx
Presentation4 5.1.pptxPresentation4 5.1.pptx
Presentation4 5.1.pptx
 
Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOE
 

More from SHAZEBALIKHAN1

Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateSHAZEBALIKHAN1
 
5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them TooSHAZEBALIKHAN1
 
Top 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowTop 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowSHAZEBALIKHAN1
 
Residential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateResidential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateSHAZEBALIKHAN1
 
3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction WorksSHAZEBALIKHAN1
 
5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil EngineersSHAZEBALIKHAN1
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingSHAZEBALIKHAN1
 
All About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateAll About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateSHAZEBALIKHAN1
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation StepsSHAZEBALIKHAN1
 
Construction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileConstruction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileSHAZEBALIKHAN1
 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims EffectivelySHAZEBALIKHAN1
 
How Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsHow Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsSHAZEBALIKHAN1
 
Top 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteTop 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteSHAZEBALIKHAN1
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementSHAZEBALIKHAN1
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingSHAZEBALIKHAN1
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction ContractsSHAZEBALIKHAN1
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksSHAZEBALIKHAN1
 
Types of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepTypes of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepSHAZEBALIKHAN1
 
Basics of Contract Management
Basics of Contract ManagementBasics of Contract Management
Basics of Contract ManagementSHAZEBALIKHAN1
 
Bamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & PerformanceBamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & PerformanceSHAZEBALIKHAN1
 

More from SHAZEBALIKHAN1 (20)

Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
 
5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too
 
Top 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowTop 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should Know
 
Residential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateResidential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel Template
 
3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works
 
5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential Building
 
All About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateAll About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel Template
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
 
Construction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileConstruction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel file
 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims Effectively
 
How Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsHow Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling Factors
 
Top 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteTop 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at Site
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project Management
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & Tricks
 
Types of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepTypes of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and Deep
 
Basics of Contract Management
Basics of Contract ManagementBasics of Contract Management
Basics of Contract Management
 
Bamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & PerformanceBamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & Performance
 

Recently uploaded

Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 

DCMA 14-Point Schedule Quality Check

  • 1. 1/6 Civilverse Admin 4 April 2021 DCMA 14 Point Schedule Quality Check civilverse.org/dcma-14-point-schedule-quality-check Table of Content for DCMA 14 Point Schedule Quality Check 1. Introduction 2. Why check project schedule health? 3. Types of Project Schedule Checks 4. DCMA 14-Point Schedule Quality Check 5. Conclusion Introduction The project schedule is an important part of project management. It contains the project activities aligned in a sequential manner along with their individual time duration and inter-dependencies. The project schedules can further be incorporated with the resources and their respective cost. The project schedule is a powerful tool to control the time taken by a project. The sequence and inter-dependencies of the activities define the critical path for the project. The Defence Contract Management Authority (DCMA), USA has set the guidelines for the quality assessment of project schedule. The DCMA 14-point schedule quality check guidelines were first published in 2005 for defence and aeronautical projects. The guidelines are being globally used for the development and maintenance of schedules. Why check project schedule health?
  • 2. 2/6 A project schedule helps in decision making, cost control, resource planning, monitoring and tracking the progress. Thus, it is necessary to have a well-constructed and maintained schedule to accurately achieve the objectives. The assessment of the project schedule ensures its’ precision and accuracy. The assessments are of two types qualitative and quantitative. Types of Project Schedule Checks- Types of Schedule Check Qualitative Assessment- The qualitative check of schedule is the determination of its’ ability to be executed. The schedule is assessed if it is realistic and executable. The qualitative assessment requires the team’s experience. Quantitative Assessment- The quantitative assessment of the schedule is done on the basis of measurable parameters. DCMA 14-point schedule quality check guidelines are widely used for quantitative assessment of project schedule. DCMA 14-Point Schedule Quality Check
  • 3. 3/6 DCMA 14-Point Schedule Quality Check 1. Logic The logic check ensures the schedule doesn’t have any incomplete activity that neither has the predecessor nor the successor. Such activities may affect the critical path and project duration. DCMA recommends such activities are to be lesser than 5%. The activities that have no predecessor and no successor can be linked to either the project start milestone or the project finish milestone. 2. Leads Lead is the negative lag. Lead signifies that the activity starts before the predecessor activity ends. DCMA recommends having zero lead. The leads can affect the critical path thus it is advisable not to have them. 3. Lags The difference between the finish of activity and the start of its’ successor is called lag. DCMA recommends activities to not have more than a 5% lag. The activities with lag should be replaced with intermittent activity. For example, lag between foundation
  • 4. 4/6 casting and machine installation to be replaced with curing period. 4. Relationship Types There are four relationship types used to interlink activities namely Finish to Start (FS), Start to Start (SS), Start to Finish (SF) and Finish to Finish (FF). DCMA recommends more than 90% of activities should be Finish to Start (FS) linked. However, SS and FF are also acceptable when it is the true link of activity but their use should be minimized. For example, the casting of beams cannot be completed before the casting of the slab, hence finish to finish relationship. 5. Hard Constraints Must Start On, Must Finish On, Start No later Than and Finish no later Than are four hard constraints used in project schedules. Ideally, there should be no hard constraints but DCMA recommends limiting their use up to 5%. The hard constraints limit the logic- driven behaviour of the schedule. Hard constraints can create negative float. 6. High Float The time by which an activity can slip without affecting the project completion is called total float. The total float of 44 days is considered a high float. DCMA recommends limiting such activities to 5%. 7. Negative Float Negative Float represents the delay in completion. It is shown when a missed deadline is being reported. DCMA limit for negative float is zero. As stated earlier, hard constraints lead to negative float, as hard constraints hold the activities and indicate the upcoming deadline is likely to be missed. 8. High Duration The project schedule is a sequential arrangement of activities having discrete-time duration. The work packages should be such broken that no activity should have a duration greater than 44 days. DCMA limits such activities to be lesser than 5%. Activities with high duration are difficult to track, measure and estimate resources. The project and activity duration can be determined by any of the six methods listed here. 9. Invalid dates The past dates in the forecast and future dates in completed activities are called invalid dates. The invalid date check is useful for the project execution stage. The DCMA threshold for this check is zero.
  • 5. 5/6 The activities not yet started are to be ahead of the status date. The in-progress and completed activities should be as per the actual dates. 10. Resources The schedules loaded with resources are helpful in resource estimation. Ideally, all the activities should be resource loaded but the DCMA has not stated any fixed criteria for the resource loading. Thus, it is a flexible metric and it depends upon the organisation’s rules. However, if the resource loading is done in schedule, then every activity should have at least one resource allocated to it to avoid misbalance. It is not necessary that every activity requires resource. For example, delivery lead time and approval from authorities etc. 11. Missed Tasks The tasks having their baseline completion date before the status date are said to be missed tasks. The missed tasks should not be more than 5% of the total tasks. However, the tasks that are likely to be missed but have the baseline completion date after the status date are not considered in the threshold. The missed tasks can affect the project completion. They are an indicator of poor planning, mismanagement and poor resource estimation and allocation. 12. Critical Path Test The critical path is the longest path in an activity network. To perform the critical path test, identify any critical activity and increase its’ duration by x days and recalculate the project dates. If the project completion date also increases by x days then the schedule is said to have passed the test. The test ensures the fluid network with proper linkage among the activities. The failed critical path test indicates the missing inter-dependencies among the activities. For such a case, the entire schedule needs to be reviewed and corrected. 13. Critical Path Length Index (CPLI) The Critical Path Length Index (CPLI) is the sum of remaining working days on the critical path and total float divided by the total remaining days. CPLI indicates the efficiency required to complete the project on time. The target CPLI should be 1 but DCMA suggests acceptance up to 0.95. For CPLI lesser than 1, the delay is likely to happen and efficiency must be increased to achieve the baseline completion. For CPLI greater than 1, the schedule has margin and completion is likely to be done before the baseline completion. 14. Baseline Execution Index (BEI)
  • 6. 6/6 The Baseline Execution Index (BEI) is the ratio of total tasks completed to the total tasks planned as per baseline till status date. The BEI indicates the efficiency of work done. The target BEI should be 1 but DCMA suggests acceptance up to 0.95. The BEI lesser than 1 indicates missed tasks. Thus, more effort needs to be put to cover up the slippage. The BEI greater than 1 indicates the schedule is ahead of target and likely to be completed before the baseline completion. This may be due to the availability of unnecessary float or underestimated resource efficiency. Conclusion The DCMA 14-point schedule quality check gives an objective method to evaluate the schedule. The regular check with these metrics ensures the schedule is in better health. The routine check also enables the manager to change their strategy as per the requirement. The full compliance to all the 14-metrics doesn’t imply that the schedule is feasible and a non-compliant schedule isn’t necessarily a failure. The metrics are generally available on the popularly used software like MS Project and Primavera p6 etc. Liked the article? Let me know in the comments in the comment below. Happy Engineering!!